SlideShare uma empresa Scribd logo
1 de 17
Baixar para ler offline
National Aeronautics and Space Administration
National Aeronautics and Space Administration




                 The Ares Project Office
                PPBE and EVM Integration




www.nasa.gov
www.nasa.gov
Objective




•   Understand the Planning, Programming,
    Budget and Execution (PPBE) process
       and how it is integrated into the
     Performance Measurement Baseline
                    (PMB)



                                            2
Outline

Budget vs. Funding.

The PPBE Process.

The PMB process.

PPBE and PMB Integration.

Implementation Challenges.

NOA and the PMB.

Conclusion and Discussion.

                             3
Funding & The Federal Budget Process


Funding is the end result of the Federal Budget
Process.
   NASA submits proposed budget by FY to the Office of
   Management and Budget (OMB).
   OMB reviews the budget submittal, makes recommendations
   and forwards to the President.
   The President approves the proposed budget and forwards it to
   Congress.
   Congress approves and issues Authorization Acts and
   Appropriation Acts.
   OMB disburses appropriated funds (this is where the word
   “funding” originates) to the Agency.

Each Agency authorizes and distributes funding to Programs,
Projects, and Organizations.
                                                                   4
NASA Funding

NASA Headquarters receives appropriated funds from
OMB.

NASA Headquarters distributes the appropriated
funds to each Mission Directorate (MD).

MD’s authorize funds disbursement to individual
Programs and Projects.

MD’s retains reserves that are disbursed during the
FY.

The Chief Financial Officer (CFO), The Program
Office and the Project Office are responsible for funds
control.
                                                          5
Budget vs. Funding Summary

Funding and Budget (Performance Measurement
Baseline – PMB) are separate but interrelated.

Changes to the Budget can impact the Funding and
vice versa.

Funding is authorized, monitored and controlled by FY.

Budget is developed, monitored and controlled for the
life-cycle of a project.

The project life-cycle budget can be used to forecast
out-year Funding profiles. Out-year funding profiles do
not necessarily constitute a change to the PMB.
                                                          6
Budget vs. Funding



                                         FY 09
                                 Funding (Projected)



                                FY 08
                               Funding
                  Funding



                   FY 07
$                 Funding                                   Budget



         FY 06
                                Points Where
        Funding                Budget Exceeds
                                  Funding




Start                                                                Completion
                                                 Time Now
Date                                                                   Date

                                                                                  7
The PPBE Process

A planning and budgeting process used by the Agency to
convert strategies and priorities into programs and
budgets.
A focus on “Programming”, high-level, multi-year,
structured analyses of alternative uses of capabilities and
capacities
Key Elements
   Alternative uses of capabilities and capacities, including gap and
   excess analyses
   Multi-year resource implications
   Explicit, balanced, and feasible alternative methods of
   accomplishment
   Trade-off options: needs and costs considered simultaneously
   Risk Analysis
   Prioritization

                                                                    8
High-level Agency PPBE Process


  Planning       Programming         Budgeting          Execution
                                     Programmatic and   Operating Plan
Strategic Plan     Resources            Institutional        and
                   Guidance              Guidance       Reprogramming
Implementation
     Plan
                                     OMB Budget
                  Program Analyses
  Priorities        and Alignment
                                     Development          Monthly
                                                        Phasing Plans
Assessments
                     Institutional
 Performance        Infrastructure    President’s         Analyses of
  Measures             Analyses                          Performance/
                                        Budget
                                                         Expenditures
                                        (IBPD)
                  Program Review/
                    Issues Book

 Strategic        Program Decision                       Close-out &
 Program            Memorandum       Appropriation       Report (PAR)
 Guidance              (PDM)



                                                                         9
The PPBE Process (continued)

Purpose
  The conversion of information from the Strategic Plan, the
  Mission Directorate and Institutional Implementation Plans,
  priorities, studies and assessments, and performance measures
  into strategic guidance for Mission Directorates, Mission Support
  Offices, the Program Offices and the Projects.
Inputs
  The inputs for this step are the Strategic Plan or updates, the
  Mission Directorate and Institutional Implementation Plans, the
  most recent OMB pass-back, and various studies, reports, and
  assessments – e.g. program schedules, staffing levels, critical
  facilities, etc.
Outputs
  Guidance is issued to the Mission Directorates, the Program and
  Project Offices to accomplish the specific strategic objectives.
  Examples include Initial Operational Capability (IOC) and Full
  Operational Capability (FOC) by specific dates. Additionally,
  specific budget guidance by FY is given.


                                                                    10
The Performance Measurement Baseline (PMB)

 The PMB is a time-phased budget against which EVM
 performance is measured. The PMB includes both prime
 contractor and NASA “in-house” efforts.

 The PMB is the summation of Work Packages (WP) and Planning
 Packages (PP) and includes Undistributed Budget (UB) held at the
 Project level.

 The PMB is developed early in the project life-cycle (typically 6
 months post ATP for prime contractors) based on anticipated work
 flow, technical requirements and major schedule milestones (CDR,
 PDR, Orion 1 flight, etc.).

 The PMB is authorized by the Program Office to the Project Office
 via a Project Authorization Document (PAD).

 The PMB is maintained via formal change control. If the PPBE
 changes constitute a revised PAD the PMB must be revised.

                                                                     11
PPBE and PMB Integration

The PPBE provides Agency-level strategic guidance to the Mission
Directorates. The Mission Directorates flow this guidance down to
the Program Office, and then to each Project Office. This guidance
includes specific funding (marks) and schedule direction.
   Specific schedule milestones, Ares I-Y, Orion I, IOC, FOC dates.
   Specific funding by FY to develop the PMB.
   Specific assumptions for future FY planning.

Each Project Office uses this guidance to perform detailed
planning. The Project Office rolls-up the detailed plan (by WBS,
Element, system and/or sub-system) and ensures compliance with
the PPBE guidance.

Once Project Office planning is complete, formal reviews are
conducted between the Program Office and the Project Offices.

When agreement is reached, the Program Office issues revised
PADs to each Project Office.

                                                                      12
Challenges to Developing the Revised PMB


Detailed planning by the Project Offices to meet strategic goals
from the PPBE exceed the funding profile by FY.

Revised direction (contractual via the CO) to prime contractors
and their formal submittal of a new PMB can take months to
complete.
   EVM reporting by the prime contractors become antiquated during this
   long re-planning period.

Known risk items (sometimes referred to as cost threats) can not
be included in the PMB due to funding limitations.
   Work is performed to mitigate risk without approved budget or
   schedule.
   Poor performance on “in-scope” work can be masked by work
   performed that is “out-of-scope”.

Direction has been given to the Project Office to include specific
scope without budget, schedule or written direction.
                                                                          13
New Obligation Authority (NOA) and the
             Revised PMB

When the PPBE changes the funding (NOA profile) but a revised
PAD is not issued.
   The Project using Inception-To-Date (ITD) actual cost, may create a
   new Estimate to Complete (ETC) for remaining effort to match NOA
   Profile.
   Cost and/or schedule risk can be entered or tracked as one of the
   reconciliations from EAC to new NOA profile.
   The Project can submit to the Program Office a Budget Change
   Request (BCR) requesting new budget using EAC as backup for
   request. No changes to PMB will be implemented until the PAD
   revision is issued.

Changes to the PMB as a result of the PPBE can include;
   Depending on what changes.
       Project may replan specific efforts (close open WPs and open new WPs
       and covert PPs to WPs)
       Project Office may replan the total Project
       Rebaseline the entire project which implies setting cum
       BCWS/BCWP to ACWP
                                                                              14
NOA Options and Assumptions

Seven Data points used in EVM and NOA (Plan vs Actuals) analysis.
1.   BCWS – Budgeted Cost Of Work Scheduled (PMB Budget).
2.   BCWP – Budgeted Cost Of Work Performed (Schedule Status).
3.   ACWP – Actual Cost Of Work Performed.
4.   BAC – Budget At Complete (Sum of PMB).
5.   EAC – Estimate At Complete (Latest forecast of total expected cost).
6.   NOA – Planned time phased funding profiles.
7.   Actuals – Total spent against NOA.

BCWS will equal NOA upon initial implementation of PPBE guidance.

ACWP will equal or be reconcilable to Actuals.

Future PPBE exercises may modify NOA’s.

EAC (1 of the 3 point EAC of Best, Worst, or Most Likely) will be equal to
or reconcilable to future PPBE exercises.


                                                                             15
Conclusion and Best Practices


Revised PPBE guidance will be issued yearly. Projects
must accept this fact and have dynamic tools and
processes to respond.

Disciplined Configuration Management (CM) processes
are essential to documenting and tracking changes that
result from PPBE guidance.

Programs and Projects must resist the urge to
rebaseline each year.

The Program Office should not provide verbal direction
but should provide timely written direction.

                                                         16
Question and Discussion




                          17

Mais conteúdo relacionado

Mais procurados

Coonce.tom
Coonce.tomCoonce.tom
Coonce.tomNASAPMC
 
Budget integration, program budgeting and reengineering of business processes
Budget integration, program budgeting and reengineering of business processesBudget integration, program budgeting and reengineering of business processes
Budget integration, program budgeting and reengineering of business processesJean-Marc Lepain
 
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1Yarille Velazquez
 
Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...Oswar Mungkasa
 
Blythe.mike
Blythe.mikeBlythe.mike
Blythe.mikeNASAPMC
 
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...Fosu Anthony
 
Priority Based Budgeting - How to respond to Downturn and Austerity
Priority Based Budgeting - How to respond to Downturn and AusterityPriority Based Budgeting - How to respond to Downturn and Austerity
Priority Based Budgeting - How to respond to Downturn and AusterityMalcolm Anthony
 
Budget entities regulatory framework
Budget entities regulatory frameworkBudget entities regulatory framework
Budget entities regulatory frameworkJean-Marc Lepain
 
Committed to the path of sustainability Excellence with EFQM
Committed to the path of sustainability Excellence with EFQMCommitted to the path of sustainability Excellence with EFQM
Committed to the path of sustainability Excellence with EFQMJean-marc SOULIER
 
Public Investment Management in Brief.
Public Investment Management in Brief.Public Investment Management in Brief.
Public Investment Management in Brief.mohmad Alawneh
 

Mais procurados (19)

Coonce.tom
Coonce.tomCoonce.tom
Coonce.tom
 
P715
P715P715
P715
 
Op format word_fy01mwlayout
Op format word_fy01mwlayoutOp format word_fy01mwlayout
Op format word_fy01mwlayout
 
P746
P746P746
P746
 
Agricultural Public Expenditure Reviews: A Synthesis_2009
Agricultural Public Expenditure Reviews: A Synthesis_2009Agricultural Public Expenditure Reviews: A Synthesis_2009
Agricultural Public Expenditure Reviews: A Synthesis_2009
 
P746
P746P746
P746
 
Budget integration, program budgeting and reengineering of business processes
Budget integration, program budgeting and reengineering of business processesBudget integration, program budgeting and reengineering of business processes
Budget integration, program budgeting and reengineering of business processes
 
P775
P775P775
P775
 
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1
Standard do d_fm_briefing_practicalexercise_27mar_mtvernon1
 
Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...Getting started on the PBB reform agenda in Indonesia – a practical outline o...
Getting started on the PBB reform agenda in Indonesia – a practical outline o...
 
Investment Programming
Investment ProgrammingInvestment Programming
Investment Programming
 
Geoff dixon presentation for workshop sunday evening
Geoff dixon presentation for workshop sunday eveningGeoff dixon presentation for workshop sunday evening
Geoff dixon presentation for workshop sunday evening
 
Blythe.mike
Blythe.mikeBlythe.mike
Blythe.mike
 
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...
ANALYSIS OF PLAN IMPLEMENTATION AND MANAGEMENT EXPERIENCES OF ASANTE AKIM NOR...
 
Priority Based Budgeting - How to respond to Downturn and Austerity
Priority Based Budgeting - How to respond to Downturn and AusterityPriority Based Budgeting - How to respond to Downturn and Austerity
Priority Based Budgeting - How to respond to Downturn and Austerity
 
Budget entities regulatory framework
Budget entities regulatory frameworkBudget entities regulatory framework
Budget entities regulatory framework
 
Committed to the path of sustainability Excellence with EFQM
Committed to the path of sustainability Excellence with EFQMCommitted to the path of sustainability Excellence with EFQM
Committed to the path of sustainability Excellence with EFQM
 
M&E of the Malaysian 10th Development plan at the Economic Planning Unit
M&E of the Malaysian 10th Development plan at the Economic Planning UnitM&E of the Malaysian 10th Development plan at the Economic Planning Unit
M&E of the Malaysian 10th Development plan at the Economic Planning Unit
 
Public Investment Management in Brief.
Public Investment Management in Brief.Public Investment Management in Brief.
Public Investment Management in Brief.
 

Destaque

Les.sorge
Les.sorgeLes.sorge
Les.sorgeNASAPMC
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
Moser.bryan
Moser.bryanMoser.bryan
Moser.bryanNASAPMC
 
Bill.bastedo
Bill.bastedoBill.bastedo
Bill.bastedoNASAPMC
 
Sammy.kayali
Sammy.kayaliSammy.kayali
Sammy.kayaliNASAPMC
 
Barley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalBarley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalNASAPMC
 
Keer.beth
Keer.bethKeer.beth
Keer.bethNASAPMC
 
Bush.stewart
Bush.stewartBush.stewart
Bush.stewartNASAPMC
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoinNASAPMC
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011NASAPMC
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoinNASAPMC
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.updateNASAPMC
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smithNASAPMC
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jonNASAPMC
 
Steven noneman
Steven nonemanSteven noneman
Steven nonemanNASAPMC
 
Pamela.west
Pamela.westPamela.west
Pamela.westNASAPMC
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayneNASAPMC
 

Destaque (20)

Les.sorge
Les.sorgeLes.sorge
Les.sorge
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
Moser.bryan
Moser.bryanMoser.bryan
Moser.bryan
 
Bill.bastedo
Bill.bastedoBill.bastedo
Bill.bastedo
 
Sammy.kayali
Sammy.kayaliSammy.kayali
Sammy.kayali
 
Barley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinalBarley2 ce hierarchica valuepmcfinal
Barley2 ce hierarchica valuepmcfinal
 
Trahan
TrahanTrahan
Trahan
 
Keer.beth
Keer.bethKeer.beth
Keer.beth
 
Bush.stewart
Bush.stewartBush.stewart
Bush.stewart
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoin
 
Heard
HeardHeard
Heard
 
C null 01-17-2011
C null 01-17-2011C null 01-17-2011
C null 01-17-2011
 
Michael.aucoin
Michael.aucoinMichael.aucoin
Michael.aucoin
 
Patrick.guske.update
Patrick.guske.updatePatrick.guske.update
Patrick.guske.update
 
Hulett
HulettHulett
Hulett
 
Backup norm.smith
Backup norm.smithBackup norm.smith
Backup norm.smith
 
Fleming.jon
Fleming.jonFleming.jon
Fleming.jon
 
Steven noneman
Steven nonemanSteven noneman
Steven noneman
 
Pamela.west
Pamela.westPamela.west
Pamela.west
 
Brantley.wayne
Brantley.wayneBrantley.wayne
Brantley.wayne
 

Semelhante a Smith.donnie

A five-step-guide-to-budget-development
A five-step-guide-to-budget-developmentA five-step-guide-to-budget-development
A five-step-guide-to-budget-developmentCatalin Ilie
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.pptDejeneTsegaye6
 
Program Management Dashboards
Program Management DashboardsProgram Management Dashboards
Program Management DashboardsBob Prieto
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology OverviewDaniel Brody
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfDejeneTsegaye6
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
Project Management
Project ManagementProject Management
Project Managementamit soni
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeffNASAPMC
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneWaleed Hamdy Albana
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 waleed hamdy
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysGlen Alleman
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxYogesh Singh
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: BudgetMinhas Kamal
 

Semelhante a Smith.donnie (20)

A five-step-guide-to-budget-development
A five-step-guide-to-budget-developmentA five-step-guide-to-budget-development
A five-step-guide-to-budget-development
 
Project Budget.pptx.ppt
Project Budget.pptx.pptProject Budget.pptx.ppt
Project Budget.pptx.ppt
 
Program Management Dashboards
Program Management DashboardsProgram Management Dashboards
Program Management Dashboards
 
Budgeting
BudgetingBudgeting
Budgeting
 
@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview@CIOBRODY PMO Methodology Overview
@CIOBRODY PMO Methodology Overview
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
CPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdfCPM lecture note 4,5,6&7.pdf
CPM lecture note 4,5,6&7.pdf
 
Trn 06
Trn 06Trn 06
Trn 06
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
Pmo
PmoPmo
Pmo
 
AWPB
AWPBAWPB
AWPB
 
Project Management
Project ManagementProject Management
Project Management
 
Vanessa.jeff
Vanessa.jeffVanessa.jeff
Vanessa.jeff
 
Projects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part OneProjects Control Using Earned Value Techniques - Part One
Projects Control Using Earned Value Techniques - Part One
 
project control using earned value analysis - Part 01
project control using earned value analysis - Part 01 project control using earned value analysis - Part 01
project control using earned value analysis - Part 01
 
Building a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two DaysBuilding a Credible Performance Measurement Baseline in Two Days
Building a Credible Performance Measurement Baseline in Two Days
 
Budgetary control
Budgetary controlBudgetary control
Budgetary control
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 
ppt for primevera
ppt for primeverappt for primevera
ppt for primevera
 
Software Project Management: Budget
Software Project Management: BudgetSoftware Project Management: Budget
Software Project Management: Budget
 

Mais de NASAPMC

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk boNASAPMC
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski johnNASAPMC
 
Yew manson
Yew mansonYew manson
Yew mansonNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wood frank
Wood frankWood frank
Wood frankNASAPMC
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)NASAPMC
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joeNASAPMC
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuartNASAPMC
 
Stock gahm
Stock gahmStock gahm
Stock gahmNASAPMC
 
Snow lee
Snow leeSnow lee
Snow leeNASAPMC
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandraNASAPMC
 
Seftas krage
Seftas krageSeftas krage
Seftas krageNASAPMC
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marcoNASAPMC
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mikeNASAPMC
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karleneNASAPMC
 
Rackley mike
Rackley mikeRackley mike
Rackley mikeNASAPMC
 
Paradis william
Paradis williamParadis william
Paradis williamNASAPMC
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeffNASAPMC
 
O'keefe william
O'keefe williamO'keefe william
O'keefe williamNASAPMC
 
Muller ralf
Muller ralfMuller ralf
Muller ralfNASAPMC
 

Mais de NASAPMC (20)

Bejmuk bo
Bejmuk boBejmuk bo
Bejmuk bo
 
Baniszewski john
Baniszewski johnBaniszewski john
Baniszewski john
 
Yew manson
Yew mansonYew manson
Yew manson
 
Wood frank
Wood frankWood frank
Wood frank
 
Wood frank
Wood frankWood frank
Wood frank
 
Wessen randi (cd)
Wessen randi (cd)Wessen randi (cd)
Wessen randi (cd)
 
Vellinga joe
Vellinga joeVellinga joe
Vellinga joe
 
Trahan stuart
Trahan stuartTrahan stuart
Trahan stuart
 
Stock gahm
Stock gahmStock gahm
Stock gahm
 
Snow lee
Snow leeSnow lee
Snow lee
 
Smalley sandra
Smalley sandraSmalley sandra
Smalley sandra
 
Seftas krage
Seftas krageSeftas krage
Seftas krage
 
Sampietro marco
Sampietro marcoSampietro marco
Sampietro marco
 
Rudolphi mike
Rudolphi mikeRudolphi mike
Rudolphi mike
 
Roberts karlene
Roberts karleneRoberts karlene
Roberts karlene
 
Rackley mike
Rackley mikeRackley mike
Rackley mike
 
Paradis william
Paradis williamParadis william
Paradis william
 
Osterkamp jeff
Osterkamp jeffOsterkamp jeff
Osterkamp jeff
 
O'keefe william
O'keefe williamO'keefe william
O'keefe william
 
Muller ralf
Muller ralfMuller ralf
Muller ralf
 

Último

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024TopCSSGallery
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesManik S Magar
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsRavi Sanghani
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality AssuranceInflectra
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesKari Kakkonen
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Nikki Chapple
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...itnewsafrica
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentPim van der Noll
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfNeo4j
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkPixlogix Infotech
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024Lonnie McRorey
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxfnnc6jmgwh
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 

Último (20)

Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024Top 10 Hubspot Development Companies in 2024
Top 10 Hubspot Development Companies in 2024
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
 
Potential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and InsightsPotential of AI (Generative AI) in Business: Learnings and Insights
Potential of AI (Generative AI) in Business: Learnings and Insights
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance[Webinar] SpiraTest - Setting New Standards in Quality Assurance
[Webinar] SpiraTest - Setting New Standards in Quality Assurance
 
Testing tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examplesTesting tools and AI - ideas what to try with some tool examples
Testing tools and AI - ideas what to try with some tool examples
 
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
Microsoft 365 Copilot: How to boost your productivity with AI – Part one: Ado...
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
 
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native developmentEmixa Mendix Meetup 11 April 2024 about Mendix Native development
Emixa Mendix Meetup 11 April 2024 about Mendix Native development
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Connecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdfConnecting the Dots for Information Discovery.pdf
Connecting the Dots for Information Discovery.pdf
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App Framework
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 
TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024TeamStation AI System Report LATAM IT Salaries 2024
TeamStation AI System Report LATAM IT Salaries 2024
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptxGenerative AI - Gitex v1Generative AI - Gitex v1.pptx
Generative AI - Gitex v1Generative AI - Gitex v1.pptx
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 

Smith.donnie

  • 1. National Aeronautics and Space Administration National Aeronautics and Space Administration The Ares Project Office PPBE and EVM Integration www.nasa.gov www.nasa.gov
  • 2. Objective • Understand the Planning, Programming, Budget and Execution (PPBE) process and how it is integrated into the Performance Measurement Baseline (PMB) 2
  • 3. Outline Budget vs. Funding. The PPBE Process. The PMB process. PPBE and PMB Integration. Implementation Challenges. NOA and the PMB. Conclusion and Discussion. 3
  • 4. Funding & The Federal Budget Process Funding is the end result of the Federal Budget Process. NASA submits proposed budget by FY to the Office of Management and Budget (OMB). OMB reviews the budget submittal, makes recommendations and forwards to the President. The President approves the proposed budget and forwards it to Congress. Congress approves and issues Authorization Acts and Appropriation Acts. OMB disburses appropriated funds (this is where the word “funding” originates) to the Agency. Each Agency authorizes and distributes funding to Programs, Projects, and Organizations. 4
  • 5. NASA Funding NASA Headquarters receives appropriated funds from OMB. NASA Headquarters distributes the appropriated funds to each Mission Directorate (MD). MD’s authorize funds disbursement to individual Programs and Projects. MD’s retains reserves that are disbursed during the FY. The Chief Financial Officer (CFO), The Program Office and the Project Office are responsible for funds control. 5
  • 6. Budget vs. Funding Summary Funding and Budget (Performance Measurement Baseline – PMB) are separate but interrelated. Changes to the Budget can impact the Funding and vice versa. Funding is authorized, monitored and controlled by FY. Budget is developed, monitored and controlled for the life-cycle of a project. The project life-cycle budget can be used to forecast out-year Funding profiles. Out-year funding profiles do not necessarily constitute a change to the PMB. 6
  • 7. Budget vs. Funding FY 09 Funding (Projected) FY 08 Funding Funding FY 07 $ Funding Budget FY 06 Points Where Funding Budget Exceeds Funding Start Completion Time Now Date Date 7
  • 8. The PPBE Process A planning and budgeting process used by the Agency to convert strategies and priorities into programs and budgets. A focus on “Programming”, high-level, multi-year, structured analyses of alternative uses of capabilities and capacities Key Elements Alternative uses of capabilities and capacities, including gap and excess analyses Multi-year resource implications Explicit, balanced, and feasible alternative methods of accomplishment Trade-off options: needs and costs considered simultaneously Risk Analysis Prioritization 8
  • 9. High-level Agency PPBE Process Planning Programming Budgeting Execution Programmatic and Operating Plan Strategic Plan Resources Institutional and Guidance Guidance Reprogramming Implementation Plan OMB Budget Program Analyses Priorities and Alignment Development Monthly Phasing Plans Assessments Institutional Performance Infrastructure President’s Analyses of Measures Analyses Performance/ Budget Expenditures (IBPD) Program Review/ Issues Book Strategic Program Decision Close-out & Program Memorandum Appropriation Report (PAR) Guidance (PDM) 9
  • 10. The PPBE Process (continued) Purpose The conversion of information from the Strategic Plan, the Mission Directorate and Institutional Implementation Plans, priorities, studies and assessments, and performance measures into strategic guidance for Mission Directorates, Mission Support Offices, the Program Offices and the Projects. Inputs The inputs for this step are the Strategic Plan or updates, the Mission Directorate and Institutional Implementation Plans, the most recent OMB pass-back, and various studies, reports, and assessments – e.g. program schedules, staffing levels, critical facilities, etc. Outputs Guidance is issued to the Mission Directorates, the Program and Project Offices to accomplish the specific strategic objectives. Examples include Initial Operational Capability (IOC) and Full Operational Capability (FOC) by specific dates. Additionally, specific budget guidance by FY is given. 10
  • 11. The Performance Measurement Baseline (PMB) The PMB is a time-phased budget against which EVM performance is measured. The PMB includes both prime contractor and NASA “in-house” efforts. The PMB is the summation of Work Packages (WP) and Planning Packages (PP) and includes Undistributed Budget (UB) held at the Project level. The PMB is developed early in the project life-cycle (typically 6 months post ATP for prime contractors) based on anticipated work flow, technical requirements and major schedule milestones (CDR, PDR, Orion 1 flight, etc.). The PMB is authorized by the Program Office to the Project Office via a Project Authorization Document (PAD). The PMB is maintained via formal change control. If the PPBE changes constitute a revised PAD the PMB must be revised. 11
  • 12. PPBE and PMB Integration The PPBE provides Agency-level strategic guidance to the Mission Directorates. The Mission Directorates flow this guidance down to the Program Office, and then to each Project Office. This guidance includes specific funding (marks) and schedule direction. Specific schedule milestones, Ares I-Y, Orion I, IOC, FOC dates. Specific funding by FY to develop the PMB. Specific assumptions for future FY planning. Each Project Office uses this guidance to perform detailed planning. The Project Office rolls-up the detailed plan (by WBS, Element, system and/or sub-system) and ensures compliance with the PPBE guidance. Once Project Office planning is complete, formal reviews are conducted between the Program Office and the Project Offices. When agreement is reached, the Program Office issues revised PADs to each Project Office. 12
  • 13. Challenges to Developing the Revised PMB Detailed planning by the Project Offices to meet strategic goals from the PPBE exceed the funding profile by FY. Revised direction (contractual via the CO) to prime contractors and their formal submittal of a new PMB can take months to complete. EVM reporting by the prime contractors become antiquated during this long re-planning period. Known risk items (sometimes referred to as cost threats) can not be included in the PMB due to funding limitations. Work is performed to mitigate risk without approved budget or schedule. Poor performance on “in-scope” work can be masked by work performed that is “out-of-scope”. Direction has been given to the Project Office to include specific scope without budget, schedule or written direction. 13
  • 14. New Obligation Authority (NOA) and the Revised PMB When the PPBE changes the funding (NOA profile) but a revised PAD is not issued. The Project using Inception-To-Date (ITD) actual cost, may create a new Estimate to Complete (ETC) for remaining effort to match NOA Profile. Cost and/or schedule risk can be entered or tracked as one of the reconciliations from EAC to new NOA profile. The Project can submit to the Program Office a Budget Change Request (BCR) requesting new budget using EAC as backup for request. No changes to PMB will be implemented until the PAD revision is issued. Changes to the PMB as a result of the PPBE can include; Depending on what changes. Project may replan specific efforts (close open WPs and open new WPs and covert PPs to WPs) Project Office may replan the total Project Rebaseline the entire project which implies setting cum BCWS/BCWP to ACWP 14
  • 15. NOA Options and Assumptions Seven Data points used in EVM and NOA (Plan vs Actuals) analysis. 1. BCWS – Budgeted Cost Of Work Scheduled (PMB Budget). 2. BCWP – Budgeted Cost Of Work Performed (Schedule Status). 3. ACWP – Actual Cost Of Work Performed. 4. BAC – Budget At Complete (Sum of PMB). 5. EAC – Estimate At Complete (Latest forecast of total expected cost). 6. NOA – Planned time phased funding profiles. 7. Actuals – Total spent against NOA. BCWS will equal NOA upon initial implementation of PPBE guidance. ACWP will equal or be reconcilable to Actuals. Future PPBE exercises may modify NOA’s. EAC (1 of the 3 point EAC of Best, Worst, or Most Likely) will be equal to or reconcilable to future PPBE exercises. 15
  • 16. Conclusion and Best Practices Revised PPBE guidance will be issued yearly. Projects must accept this fact and have dynamic tools and processes to respond. Disciplined Configuration Management (CM) processes are essential to documenting and tracking changes that result from PPBE guidance. Programs and Projects must resist the urge to rebaseline each year. The Program Office should not provide verbal direction but should provide timely written direction. 16