Anúncio
Anúncio

Mais conteúdo relacionado

Anúncio

J Ray Firsts

  1. J. Ray McDermott “Firsts” Subsea Tieback Forum 2004 R
  2. What Contractor was the “First to Incorporate “SCRAMS” Technology into a Subsea System Design?”
  3. R
  4. Allegheny Field Development Production Facility Client: British-Borneo Exploration, Inc. SeaStar® TLP Supplier: Atlantia Corporation Location: Green Canyon Blocks 254, 297 & 298 Water Depth: 3,310 feet Scope:  EPCI Contract: Installation of the SeaStar® tension leg platform (TLP), including piled foundations, tendons, hull and deck, 5 subsea trees, 2 REM’s 5 x 4” and 2 x 12” SCR with titanium stress joints. Description:  Five wells, planned among two well centers. Production flows to the SeaStar® mini TLP via individual 4 inch diameter insulated steel catenary risers (SCRs). One well center is situated north- northwest of the platform and the other is to the south-southwest. The well centers are 3,000 feet from the TLP. The TLP contains process equipment and serves as the control center. Two 12 inch SCRs exit the TLP to the north-northwest to export the processed oil and gas. • Innovation:  Titanium Tapered Stress Joint used for suspending the SCRs at the TLP  High Collapse Resistance (HCR) hoses in a direct hydraulic /electric control umbilical  Two years from design concept to first oil  Insulated high pressure 4” flowline SCRs
  5. What Contractor “Developed the Sand-Jack System for Deck-to- Jacket Mating Offshore?”
  6. R
  7. The Sand-Jack System design was used to install Ras Laffan and QGas in 1998. Development was started in 1996 in a FEED Study for Ras Laffan and began serious development in 1997. In the eighties, JRM used a Crude Sand-Jack System to install three decks for Exxon in Mobile Bay.
  8. What Contractor “Entered into an Exclusive Yard Contract for the Sole Fabrication of 70,000 Tons of Topsides?”
  9. R
  10. Atlantis Field Development Production Facility Scope/Description:  The Atlantis topsides consist of three modules, the Production and Compression Modules, each weighing about 5,000 tons, and a Generation Module weighing 4,000 tons. Equipment consists of electrical generating equipment and oil and gas processing equipment. The three modules will be installed on a moored semi-submersible hull. Client: BP Location: Along the Sigsbee Escarpment in Green Canyon Blocks 699, 700, 742, and 744 Water Depth: 4,400 to 7,100 feet Innovation:  Atlantis is one of four major BP deepwater projects for the Gulf of Mexico under construction at the company’s Morgan City facility which is under exclusive use for BP.
  11. Holstein Field Development Client: BP Location: Green Canyon Blocks 645 Water Depth: 4,300 feet Production Facility Scope/Description:  Holstein will be a 149.25’ diameter SPAR moored by 16 chain, wire and suction pile anchors, supporting a topsides with a total operating weight of approximately 26,445 ST. The topsides will consist of 4 levels with all the production vessels, compressors, generators, and quarters needed for self-sufficient operations. It will have wells for production and water injection and a drilling rig capable of drilling to 25,000 feet. Holstein will also have two steel catenary risers for oil and gas export.  Topside facilities are being fabricated in three major components. The North Module will house the drilling and processing facilities; the South Module will house the quarters and utilities; and the Module Support Frame will house the support structure that will mate the topsides to the spar hull. Innovation:  Holstein is one of four major BP deepwater projects for the Gulf of Mexico under construction at the company’s Morgan City facility which is under exclusive use for BP. Topsides under construction
  12. Mad Dog Field Development Production Facility Client: BP Location: Green Canyon 782 Water Depth: 4,500 feet Scope/Description:  Mad Dog will be 16-slot truss spar providing a dry-tree environment for production of oil and gas, as well as provide a host facility for future subsea developments. Production equipment, a drilling rig, and permanent quarters for both drilling and production personnel will be located on the spar.  The Spar will be a single piece structure with a total payload of approximately 18,000 short tons excluding hull storage.  The topsides are designed around a single-lift integrated deck concept with a lift weight of approximately 8,400 short tons. Innovation:  Mad Dog is one of four major BP deepwater projects for the Gulf of Mexico under construction at the company’s Morgan City facility which is under exclusive use for BP. Topsides under construction
  13. Thunder Horse Field Development Production Facility Client: BP Location: Mississippi Canyon Block 778/822 Water Depth: 6,050 feet Scope/Description:  Thunder Horse facilities for drilling, processing and exporting hydrocarbons will be floating, large and complex, including a PDQ (Production-Drilling- Quarters) semi-submersible. The semi-submersible is currently expected to be moored by 16 chain, wire and suction pile anchors with a weight of approximately 82,543 metric tons. The 185 man quarters will be built into the hull of the semi- submersible.  The topsides consist of three modules – Production, Generator and Compression. The Production and Compression Modules, which are three main deck levels high, each measure approximately 115’ wide x 170’ long x 90’ high and weigh 5,669 tons and 6,130 tons, respectively. The Generator Module, which has two main continuous deck levels, measures approximately 104’ wide x 292’ long x 35’ high and will weigh 7,658 tons. Topsides under construction Innovation:  Thunder Horse is one of four major BP deepwater projects for the Gulf of Mexico under construction at the company’s Morgan City facility which is under exclusive use for BP.
  14. What Contractor installed the “First Pipeline Utilizing the J-Lay Method?”
  15. R
  16. Auger Client: Shell Offshore, Inc. Location: Garden Banks 426A Gulf of Mexico Water Depth: 2,860 Feet Scope: Multi-services contract with J. Ray McDermott being responsible for:  Fabrication of deck  Offshore mating of Auger hull and deck  Installation of lateral mooring system  Connection of Auger TLP to lateral mooring system  Tendon assembly, installation and TLP tendon tensioning  Installation of 12” Oil & Gas Sales Pipelines Innovation:  Box girder and node fabrication techniques  Float-over mating in open water  Tendon assembly and installation  Lateral mooring system installation  Pipelay utilizing S-Lay and J-Lay techniques Technology:  World’s first application of J-Lay pipelay technology  Set Gulf of Mexico pipelay water depth records at time of construction  Largest single piece deck fabricated by J. Ray McDermott •
  17. Who became the “First Offshore Platform Fabrication Company to receive ISO 14001 Certification by ABS Quality Evaluations?”
  18. R
  19. J. Ray McDermott Morgan City Fab. Yard December 26, 2001
  20. What Contractor designed and installed the First “In-Line Diverless Pipeline Tie-In Sled?”
  21. R
  22. Client: British-Borneo Exploration, Inc. SeaStar® Supplier: Atlantia Corporation Location: Ewing Banks 921, 964, 965 Water Depth: 1,690 feet Scope:  Lump Sum contract, plus reimbursable on certain procured items, with McDermott being responsible for designing, procuring & installing export pipelines, 3 subsea production and 1 water injection well with associated controls, umbilicals and risers. This also includes installation of the SeaStar® TLP in 1,690’ of water. Innovation:  First deepwater project for British-Borneo  Two years from concept design to first oil  First use of Atlantia SeaStar® mini TLP technology  First JRM designed and installed steel catenary risers  First JRM designed, procured and installed subsea system in the Gulf of Mexico  First deepwater diverless pipeline sidetaps in the Gulf of Mexico  First insulated flexible flowlines in the Gulf of Mexico  First coiled tubing access of subsea production system from surface TLP Morpeth Field Development
  23. What Contractor designed, fabricated, and installed the “Only Compliant Tower Facilities in the World?”
  24. R
  25. Baldpate Field Development Description:  The Baldpate site development includes a compliant tower designed for drilling, production and workover operations. Seven wells will be predrilled with a semi- submersible drilling rig and tied-back to the production facility. Eleven additional well slots are provided for future drilling and provisions for future subsea tie-ins were included in the design. Scope:  JRM Engineering was awarded the design of the compliant tower including foundation piling, drilling & production conductors and tie- back strings  JRM fabrication was awarded the fabrication of the tower base section and foundation piling. Client: Amerada Hess Corporation Location: Garden Banks 260 Gulf of Mexico Water Depth: 1,650 Feet Innovation:  Deepest bottom founded structure designed and erected offshore anywhere  First compliant tower without guylines  First articulated compliant tower  First compliant tower installed in two sections offshore • Drilling and Production Compliant Tower
  26. What Contractor’s Barge “Worked a Total of 1,284 days without a Lost Time Accident?”
  27. R
  28. J. Ray McDermott DB-16
  29. What Contractor designed, fabricated, and installed the “Deepest Tripod Jacket in the World?”
  30. R
  31. Cinnamon Tripod Deepest Tripod Jacket in the World Client: Shell Offshore, Inc. Location: Green Canyon 89A, Gulf of Mexico Water Depth: 671 Feet Scope / Description:  Risk sharing contract to purchase materials, fabricate and loadout a tripod jacket with appurtenances, piles and conductors.  Transport & Install tripod jacket (approx. 6,000 s. tons) in 670’ water depth.  Dual Derrick Barge Lift - DB50 & Shearleg 5000  Secure jacket to seafloor with 4 x 84”ø piles (2 @ C1, 1 @ A2 and 1 @ B2);  T.O.J. “Dummy Leg” framing to accept a 4-leg deck (approx. 1,600 s. tons)  Designed for Full API Rig (H&P 107)  Jacket footprint: 260’ x 260’ x 213’  Skirt piles: 2 @ C1 = 320 s. tons /330’ & 1@ A2 & B2 - 420 s. tons/425’ Innovation:  The Cinnamon jacket is the deepest tripod jacket fabricated and installed to date.  Due to the uncertainties associated with fabrication of a tripod of this size and considering engineering was still in progress, it was decided to handle this project under a risk sharing type of contract. The project was completed on schedule and under budget.
  32. What Contractor designed and installed the “First ever 15,000 psi Pipeline in the World?”
  33. R
  34. Scope:  Design, procure, fabricate and install four subsea pipeline end manifolds  Install two 8” rigid flowlines (5 miles ea.) utilizing S-Lay method  Install one - 6” pipeline (1 mile)  Pigging and Hydrotesting of installed system  First 15K subsea pipeline in the world Description:  DB16 installed two 8” dia. Flowlines from J-tubes at the “Salsa” platform to subsea pipeline end manifolds using deepwater S-lay method  6” flowline was laid from a wellhead to the pipeline end manifold  Manifold and pipeline end sleds were also installed Conger Subsea DevelopmentConger Subsea Development Client: Shell Location: Garden Banks 172 - 215 Gulf of Mexico Water Depth: 700 to 1,450 Feet
  35. What Contractor designed and installed the “Deepest and Largest Diameter PIP project to date (also the deepest JRM J-Lay to date)?”
  36. R
  37. Crosby Client: Shell International Exploration and Production Inc. (SIEP) Location: Mississippi Canyon 809 to 899 Gulf of Mexico Water Depth: 3,800 - 4,400 Feet Scope:  Installed dual 8”x12” steel pipe-in-pipe flowlines and Steel Catenary Risers (SCR’s) Approximately 10 miles each from subsea well cluster to Ursa TLP  Installed subsea manifold (200 short tons) in 4,400’ water depth  Installed topside package at Ursa TLP  Hand-off SCR’s to Ursa TLP World’s Deepest Steel Pipe-in-Pipe Flowlines Technology & Innovation:  World’s deepest steel pipe-in-pipe to date  JRM’s deepest pipeline to date  JRM’s deepest subsea manifold installation to date Description:  Dynamic positioned DB-50 and J-lay system used for installation  Flowlines were initiated at subsea well cluster while drill rig was on station •
  38. What Contractor installed the First “Man-Made Reef” in Mobil Bay?
  39. R
  40. J. Ray McDermott Utilizing Surplus Army Tanks
  41. What Contractor fabricated and installed a platform that received the Award for “Outstanding Civil Engineering Achievement” and was the “World’s Tallest Man-Made Structure?”
  42. R
  43. Auger Client: Shell Offshore, Inc. Location: Garden Banks 426A Gulf of Mexico Water Depth: 2,860 Feet Scope: Multi-services contract with J. Ray McDermott being responsible for:  Fabrication of deck  Offshore mating of Auger hull and deck  Installation of lateral mooring system  Connection of Auger TLP to lateral mooring system  Tendon assembly, installation and TLP tendon tensioning  Installation of 12” Oil & Gas Sales Pipelines Innovation:  Box girder and node fabrication techniques  Float-over mating in open water  Tendon assembly and installation  Lateral mooring system installation  Pipelay utilizing S-Lay and J-Lay techniques Technology:  World’s first application of J-Lay pipelay technology  Set Gulf of Mexico pipelay water depth records at time of construction  Largest single piece deck fabricated by J. Ray McDermott •
  44. What Contractor designed, fabricated, installed and commissioned the “Deepest SPAR?”
  45. R
  46. Location Mississippi Canyon 773, Gulf of Mexico Water depth 5,610 feet Gas rate 110 MMscfd of feed gas Oil rate 60 Mbpd Water rate 40 Mbpd Fabricated weight ~6,400 tons Project drivers Total McDermott supply of EPCI contract services Fast-track project schedule & delivery Engineering Scope:  Engineering & procurement management  Topsides & mooring system FEED design & detailed engineering design & hull detailed engineering design  Procurement of all topsides & hull marine systems equipment & mooring system equipment & components  Hull & topsides fabrication support engineering & installation engineering Dominion Devils Tower Spar
  47. What Contractor designed, fabricated, and installed the “Largest Sulfur Mining Facility Platforms and Bridges in the GOM?”
  48. R
  49. Freeport McMoRan Client: Freeport-McMoRan Resource Location: Main Pass 299, Gulf of Mexico Water Depth: 212 Feet Sulphur Mine Project Description:  Fifteen platforms make up the Freeport-McMoRan Resource Partner’s Main Pass Mine, the largest offshore complex in the Gulf of Mexico. Five of the 6 major platforms are connected via 13 bridges (which span is approximately 1 mile) supported by 9 bridge support platforms.  Six (6) Major Platforms:  - 2 Production and Drilling  - Pressure Control  - Power Plant  - Sulphur Storage  - Living Quarters/Warehouse Innovations:  Longest and heaviest offshore bridge: 600 ft. and 2000 s.t.  Thickest and highest strength pile: 60” dia. X 5.0” thick, 100 ksi yield steel  Platforms designed for maximum of 60 ft. vertical subsidence and 30 ft. lateral movement
  50. What Contractor installed the “First Drilling and Production SPAR?”
  51. R
  52. Genesis Spar Client: Chevron U.S.A. Inc. Location: Green Canyon 205A, Gulf of Mexico Water Depth: 2,590 Feet • Scope / Description:  Cost reimbursable contract for topsides design, fabrication, topsides equipment, procurement, conceptual riser design services and detailed review, and installation of the spar mooring system, hull, topsides facility and hookup & commissioning services. Production is through buoyancy tensioned risers connected to subsea wellheads with surface intervention and control.  JRM Engineering provided topsides design and equipment procurement.  Mentor provided conceptual riser design services and detailed riser review.  JRM Fabrication provided topsides fabrication.  JRM Marine provided installation of the spar mooring system, hull, topsides facility and hookup & commissioning services Innovation:  Box girder and node fabrication techniques  Float-over mating in open water  Tendon assembly and installation  Lateral mooring system installation  Pipelay utilizing S-Lay and J-Lay techniques First Drilling and Production Spar in the Gulf of Mexico
  53. What Contractor installed the “First Mid-Line Electrical Connector” for Electric Heated PIP Project?
  54. R
  55. Habanero Client: Shell Exploration & Production Company Location: Garden Banks Blocks 341, 384, 427 & 426 - Gulf of Mexico Water Depth: 2,000 to 2,860 Feet Flowline & Steel Catenary Riser Installation Scope:  Installation contract for the construction of two (2) electrically- heated pipe-in-pipe (PIP) flowlines comprised of 6.625” x 0.719” API 5L X70 SMLS carrier pipe and 10.750” x 0.438” API 5L X70 ERW casing pipe. The 6.625” carrier pipe was insulated with 1.3-inch thick jacketed polyurethane foam.  Flowline construction activities included the installation of two (2) PIP flowline initiation sleds located in 2,000 feet of water using pre- installed suction piles located adjacent to the two (2) subsea wells, and the installation of two (2) 6.625” x 0.844” API 5L X70 SMLS steel catenary risers (SCR’s) located in 2,860 feet of water and insulated with 3.0” of multi-layered Thermotite insulation.  Installation engineering work was performed by JRM Engineering in Houston, TX. All flowline installation activities were performed by the Derrick Barge No. 50 (DB50) utilizing J-Lay installation methods. All welding work was performed by the JRM Vermatt Bug-N-Band Automatic Welding System (JBBS). Innovation:  Subsea Mid-Line Electrical Connector Assembly For Hydrate Mitigation  Purpose-Built SCR Installation Mast Eliminating Need For Drill Rig Assistance During SCR Pull-In Operations •
  56. What Contractor designed, fabricated, and installed the “First Offshore Platform in the GOM?”
  57. R
  58. Kerr-McGee Client: Kerr-McGee Location: Gulf of Mexico Water Depth: 20 Feet First Installed Steel Structure in the GOM Innovations: In 1947 – our first – McDermott installed in the Gulf of Mexico the first steel structure employing the jacket concept for drilling over water.
  59. What Contractor fabricated the largest “Single-Piece TLP Deck” in the GOM History?
  60. R
  61. Auger Client: Shell Offshore, Inc. Location: Garden Banks 426A Gulf of Mexico Water Depth: 2,860 Feet Scope: Multi-services contract with J. Ray McDermott being responsible for:  Fabrication of deck  Offshore mating of Auger hull and deck  Installation of lateral mooring system  Connection of Auger TLP to lateral mooring system  Tendon assembly, installation and TLP tendon tensioning  Installation of 12” Oil & Gas Sales Pipelines Innovation:  Box girder and node fabrication techniques  Float-over mating in open water  Tendon assembly and installation  Lateral mooring system installation  Pipelay utilizing S-Lay and J-Lay techniques Technology:  World’s first application of J-Lay pipelay technology  Set Gulf of Mexico pipelay water depth records at time of construction  Largest single piece deck fabricated by J. Ray McDermott of 26,000 Short Tons in 1994 •
  62. What Contractor designed the First Buoyed “Lazy-Wave” SCR?
  63. R
  64. King Kong / Yosemite Field Development Client: Mariner Energy, Inc. Host Facility: AGIP Petroleum, Inc. Location: Green Canyon Blocks 254, 472, 473 & 572 Water Depth: 3,400 feet Scope:  Engineering & PMT: Performed the detailed design of 2 x 5” flowlines 2-miles each, 2 x 7” flowlines 15- miles each and 2 x 6” buoyed steel catenary risers. Prepared all specifications and request for proposal documents for procurement and installation of the flowline & riser system. Technology:  API RP 1111 Limit State Design of flowlines and pipelines  First Buoyed Steel Catenary Risers  First use of CRP, Inc. Uraduct® on an Umbilical Crossing in the Gulf of Mexico  Insulated VIV Strakes on SCRs  Titanium Stress Joints on the SCRs  Titanium SCR Stress Joints Figure A-8: SCR With Buoyancy Modules Departing Lay Vessel Mariner KKY SCR (with 900' Buoyancy modules 1500' from Strakes) Total Static Stress Distribution (with 7500 psi Internal Pressure) 0.00 5000.00 10000.00 15000.00 20000.00 25000.00 30000.00 35000.00 40000.00 0 500 1000 1500 2000 2500 3000 3500 4000 Arc Distance From The Top of The SCR (ft) StaticStress(psi) Stress Joint Strake Bare pipe Buoyant Sagbend Buoyed Region Straked Region
  65. What Contractor designed and installed the First “Pipe-in-Pipe Pipeline Utilizing the J-Lay Method?”
  66. R
  67. Macaroni Flowlines/Steel Catenary Risers Client: Shell Deepwater Development Location: Garden Banks 602 to 426 Gulf of Mexico Water Depth: 2,970 to 3,670 Feet Scope:  Installation of two pipe-in-pipe (PIP) flowlines (6 x .719” X-65 Carrier pipe w/10 x . 469” X-52 Jacket pipe) from GB602 (subsea Sled) to GB426 (SCR). Description:  Each line (approx. 11.8 miles ea.) was initiated with a Sled pull-in assisted by a drill rig mounted winch. Both lines terminated at Shell’s Auger TLP with a SCR. The SCRs were pulled into their final position utilizing the TLP’s Drill Derrick. Technology:  JRM’s DB50 and (enhanced) J-Lay was utilized. The JRM J-Lay system and pipeline abandonment and recovery (A&R) system were upgraded to perform the work. Innovations:  JRM developed an internal weld cooling device, which significantly reduced the weld cycle times (~20%) - (JRM applied Floatec between the Carrier and Jacket.) The application worked very well and there was controllable shrinkage. •
  68. What Contractor installed the “First Water Injection Riser” in the GOM?
  69. R
  70. Client: AGIP Petroleum Host: Morpeth TLP Location: Ewing Banks 921, 964, 965 Water Depth: 1,690 feet Scope:  To manage project on behalf of AGIP, carrying out detail design and overseeing equipment refurbishment.  To provide offshore installation support Innovation:  Fast track well conversion from water injector (WI) to producer  Reuse of original WI, stab and hinge over (SHO) connector  Reuse of modified existing pigging loop  Reuse of WI tree, modified for production Morpeth Producing Well Conversion of Water Injection Well to a Producing Well
  71. What Contractor installed the “Dual Infield Flowlines in a Single Lay Pass?”
  72. R
  73. Tahoe Client: Shell Oil Company Location: Viosca Knoll 783, Main Pass 252 Gulf of Mexico Water Depth: 275 feet to 1500 feet Scope/Description:  Pipe Length was 12 miles each  Project consisted of dual 4” flowlines from an existing well to an existing platform  Recover previously laid flexible pipe tails  Rigid pipe welded to the two flexible pipe sections  Two lines laid from separate reels simultaneously Innovations:  Use of project stinger designed and built by JRM
  74. What Contractor installed the First “Atlantia SeaStar® Mini-TLP?”
  75. R
  76. Client: British-Borneo Exploration, Inc. SeaStar® Supplier: Atlantia Corporation Location: Ewing Banks 921, 964, 965 Water Depth: 1,690 feet Scope:  Lump Sum contract, plus reimbursable on certain procured items, with McDermott being responsible for designing, procuring & installing export pipelines, 3 subsea production and 1 water injection well with associated controls, umbilicals and risers. This also includes installation of the SeaStar® TLP in 1,690’ of water. Innovation:  First deepwater project for British-Borneo  Two years from concept design to first oil  First use of Atlantia SeaStar® mini TLP technology  First JRM designed and installed steel catenary risers  First JRM designed, procured and installed subsea system in the Gulf of Mexico  First deepwater diverless pipeline sidetaps in the Gulf of Mexico  First insulated flexible flowlines in the Gulf of Mexico  First coiled tubing access of subsea production system from surface TLP Morpeth Field Development
  77. What Contractor installed the “First Truss - SPAR?”
  78. R
  79. Client: Kerr-McGee (op.), Ocean Energy & Enterprise Oil Location: Nansen - E. Breaks 602 Boomvang - E. Breaks 643 Gulf of Mexico Water Depth: Nansen - 3,678 feet Boomvang - 3,453 feet Scope/Description:  Contract type: Lump sum  Mentor is providing engineering, procurement and project management  Each facility utilizes production from wells completed beneath the spar and tied back through Top Tensioned Risers (TTR) and “dry” wellheads and trees. Additionally, tie-ins will be incorporated from subsea satellite wells  Mentor’s scope includes nine (9) top tensioned production risers and associated equipment for Nansen and five (5) top tensioned production risers and associated equipment for Boomvang.  Design work for SCR’s was performed to assess the impact on hull/truss design with regard to loads. Innovation/Technology:  9 5/8” single casing riser design  Single pieces, multi-chamber buoyancy cans  Space saving surface wellhead  Ten (10) foot space-out adjustment in addition to riser pups  Internal tieback adapter to subsea wellhead & stress joint designed for 350 ft. nominal drilling offset  Tensioning monitoring for each top tensioned riser  Provision for “through the keel” tie-in of future import or export flowlines or pipelines up to 12” Nansen and Boomvang Double Spar Development
  80. What Contractor designed and installed the First “HIPPS (High Integrity Pipeline Protection System?”
  81. R
  82. Shell Expro - Kingfisher Field Development Clients: Shell Expro formerly Enterprise Oil Location: Central North Sea, Blocks 16/8a & 16/8c Water Depth: 360 feet Description:  The Kingfisher prospect, located to the east of the Miller and Brae fields, comprises two reservoirs, Heather and Brae. The host platform for the tie-back is Marathon’s Brae “B”, approximately 5 miles away. Well fluids co-mingle in a subsea manifold before entering two ten inch pipelines which operate in multi- phase flow back to the platform. Scope:  J. Ray McDermott’s success in Shell’s design competition led to the award of this EPCI contract to develop the Kingfisher prospect as a subsea tie-back. JRM was responsible for design through to commissioning of all components, from the downstream flange of the subsea well guide bases to the top of the test and production risers on the host platform.  The project was managed by an integrated Project Management Team composed of Shell and JRM personnel. It was executed under an alliance agreement with risk and performance targets for schedule, capital and operating costs and system availability.
  83. What Contractor designed the first “Insulated Flexible Catenary Riser” in the GOM?
  84. R
  85. Client: British-Borneo Exploration, Inc. SeaStar® Supplier: Atlantia Corporation Location: Ewing Banks 921, 964, 965 Water Depth: 1,690 feet Scope:  Lump Sum contract, plus reimbursable on certain procured items, with McDermott being responsible for designing, procuring & installing export pipelines, 3 subsea production and 1 water injection well with associated controls, umbilicals and risers. This also includes installation of the SeaStar® TLP in 1,690’ of water. Innovation:  First deepwater project for British-Borneo  Two years from concept design to first oil  First use of Atlantia SeaStar® mini TLP technology  First JRM designed and installed steel catenary risers  First JRM designed, procured and installed subsea system in the Gulf of Mexico  First deepwater diverless pipeline sidetaps in the Gulf of Mexico  First insulated flexible flowlines in the Gulf of Mexico  First coiled tubing access of subsea production system from surface TLP Morpeth Field Development
  86. What Contractor Designed, Built, and Patented the First “Laser Tracking System” for Pulse Gas Metal Arc Welding (GMAW-P) Process?
  87. R
  88. AWS Welding System (JAWS)  Pulsed Arc (PGMAW) process offers improved penetration and reduces the potential for incomplete sidewall fusion  Less weld spatter reduces porosity and increases deposition efficiency  Six welding torches at each station provide exceptional production  Programmed welding parameters eliminate operator adjustments  Easily maintained, reliable, with very little equipment downtime  For use with 20” - 48” pipe in S- Lay mode Track record in excess of 2.500 KM  Lay rates 30”∅ up to 4.0 KM/day (329 joints)  Lay rates 24”∅ up to 5.2 KM/day (424 joints)
  89. What Contractor developed the “First Commercial Subsea Development West of Shetland?”
  90. R
  91. BP – Foinaven Development Client: BP Location: 190km West of Shetland UK Sector Water Depth: 400 to 600m Scope / Description:  Alliance contract, with McDermott responsible for project management, design, engineering, procurement and installation of total subsea system (trees, flowlines, risers, etc.) as well as design, procurement and supervision of hook-up & commissioning of the 95,000 bopd topsides and turret. Innovation:  1st Commercial Development in the hostile Atlantic Frontier  Open management and mutual business goals, e.g. subsea alliance involving all major suppliers, shared risks and rewards  Fast track schedule, 3.5 years from discovery to first oil  Parallel engineering, field appraisal and design work carried out simultaneously Petrojarl IV FPSO & Subsea System
  92. What Contractor has “Worldwide In-House Capabilities for the Design, Fabrication, Installation, and Commissioning of Platforms, Topsides, SPARS, and Subsea Field Developments going back over 58 years?”
  93. R
  94. J. Ray McDermott 1946 - 2004
Anúncio