SlideShare a Scribd company logo
1 of 7
Download to read offline
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
1 | P a g e
CIVIL ENGINEERING DEPARTMENT
DCC10022 – BRICKWORKS AND CONCRETE
LABORATORY
BRICKWORK LABORATORY 4 : WALL
PLASTERING
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
2 | P a g e
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
3 | P a g e
INTRODUCTION
Brickwork is masonry produced by a bricklayer, using bricks and mortar to build up brick structures such
as walls. Brickwork is also used to finish corners, door, and window openings, etc. in buildings made of
other materials. There are two main types of clay bricks: pressed and wire-cut. Pressed bricks usually
have a deep frog in one bedding surface and a shallow frog in the other. Wire-cut bricks usually have 3
or 4 holes through them constituting up to 25% of the total volume of the brick. Some ‘perforated’
bricks have many smaller holes.
There are three main categories of use, and both pressed bricks or wire-cut brick types
are used in all three categories:
❖ Facing brickwork is the visible decorative work.
❖ Engineering brickwork, (using engineering bricks) often seen in bridges and
large industrial construction but may also be hidden in ground works where
maximum durability is required, e.g., in manhole construction.
❖ Common brickwork is not usually seen and is used where engineering qualities
are not required; below ground in domestic buildings and internal walls, for
instance.
OBJECTIVE OF THE EXPERIMENT
➢ In the bricklaying field, the term stretcher bond is a reference to the format and standard to
which certain types of brick walls are built in order to be stable. Stretcher bond is the term given
to the repeating pattern the bricks are laid in. This pattern includes vertical supports tied in to
the foundation of the structure the wall is being built on.
➢ This type of brick format is used mostly in interior settings because it is only applicable in thin-
walled settings. As a matter of fact, the stretcher bond wall is only usable in the thinnest of brick
wall settings. This is because it is only as thick as one half of a brick.
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
4 | P a g e
THEORY
BONDS
A wall relies on the way the bricks are bonded for its strength. The vertical joints between bricks in
adjacent courses must not coincide either on the face of the wall or across its thickness. There is a
variety of possible bonds. A half-brick wall up to 1m high can be built in stretcher or open bond. You
should bond in piers (328 x 215mm) at the ends of the wall and at a maximum of 1.8m centres. A
215mm wall can be built using either English or Flemish bond. Careful cutting is needed at junctions and
corners to avoid continuous vertical joints through two or more courses of brick.
WALLS PLASTERING
After you have cement rendered the brick walls of your room, you have to prepare them
for the paint coats by applying the plaster.
✓ Plastering a brick wall is not a complex task, being similar to plastering a drywall, but you have
to follow a couple of guidelines, as to get the job done in a professional manner. Consequently,
you must apply two coats of plaster, the first one a little more coarse, while the second one
should be very fine. After the two coats have dried out, you have to sand thoroughly the
surface, as to make it even and neat.
✓ Make sure the surface is ready to apply plaster. If we speak of a new construction, then you
should make sure you have cement rendered the walls and let them dry for a couple of days.
✓ If you want to plaster an old room, then you have to remove the coats of paint and sand the
surface thoroughly. In addition, cover the walls with PVA bonding, according to the
manufacturer’s instructions, as to make sure the plaster will adhere to the walls.
In order to mix the plaster, you need several tools: a clean construction bucket and a drill mixer /
margin trowel. Pour water in the bucket (1/3 of the volume) and then add gradually the plaster. After a
couple of minutes you have to mix thoroughly the compounds, until you get a material with the
consistency of cream. If the plaster doesn’t fall off the trowel, it means that it has the right consistency
SAFETY AND HEALTH
WHAT IS A SAFE SITE?
Many definition of safety have been offered over the years but we prefer that which suggests that a
construction site is safe when person can go about their normal daily work without undue risk. This, we
feel, is a realistic definition, for it accepts that there is risk situation in all everyday activities and does
not pretend that a workplace can be entirely accident proof.
SAFETY REGULATION
There are several safety regulations in construction such as wear a suitable clothes like wear a helmet,
safety boot etc.
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
5 | P a g e
HELMET HAND GLOVE SAFETY BOOTS
MATERIALS / APPARATUS / TOOLS
The basic tools used in masonry are:
CEMENT SAND WATER STEEL SQUARE
CHALK BOX PAIL BRICK CHISELS BRICK JOINTER
TROWEL BRICK MEASURING TAPE LEVEL
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
6 | P a g e
PROCEDURES
1. Put mortar for plaster on a dust mask.
2. Add water to a bucket. It should be between cool and room temperature. You will learn through trial
and error how much water to use, but most people tend to underestimate the amount of water needed.
If you want to avoid clean-up, line your bucket with a plastic bag, then discard the whole thing at the
end.
3. Using a cup or scoop, start adding plaster to the water. Sprinkle the plaster out evenly over the whole
surface of the water. You don't have to be in a big hurry, but don't work too slowly or the plaster will
start to set. Some people prefer to sift the plaster into the water. At first the plaster will sit on the
surface of the water very briefly before it disappears beneath the surface of the water. (This is called
"slaking".)
4. Keep adding plaster, sprinkling it in the same manner. After a while the plaster will be visible for a few
seconds before it disappears into the water. You are getting close... Keep adding plaster. When you add
plaster and can count to 5 before it disappears, you have enough. Let it sit for 1-2 minutes to wet the
plaster particles (this helps reduce air bubbles).
5. Mix. You want to make sure that you aren't adding air to your plaster, or you will get bubbles which
will cause problems later. So if you use an electric mixer make sure to keep the blade deep in the
plaster. Or, just take your hand (a glove is useful) and place it at the bottom of the bucket, and slowly
move your hand back and forth across the bottom of the bucket. This slowly wets all the particles.
6. When you can draw a line in the plaster and it doesn't immediately flatten back out, the plaster is
ready to pour.
BRICK HAMMER SHOVEL HAWK FLOAT CONSTRUCTION
DCC10022 – BRICKWORKS AND CONCRETE LABORATORY
7 | P a g e
7. POURING
➢ The goal in pouring the plaster is to avoid introducing air pockets, particularly at the surface that
you are going to be using.
➢ Pour slowly.
➢ Some people allow the stream of plaster to run off the palm of their hand, thus slowing it down.
➢ It is helpful to apply a thin coating all over the surface and allow it to set a little before pouring
the final amount necessary for the mold. If the air bubbles come to the top of the thin surface,
they will be away from the actual surface you will be using. (This is especially useful if you are
pouring upside down, i.e. will use the bottom surface of the mold you are pouring.)
8. After pouring, pick up your container and softly tap it on the table or the floor. Or if it is too big, tap
the edges and shake from side to side. You are trying to get air bubbles to the surface.
9. And perhaps the ultimate trick. Use rubbing or denatured alcohol in a spray bottle (some people
dilute, some don't). When the plaster mixing is almost complete, spray a couple bursts into the plaster.
This breaks down the surface tension of bubbles on top and they disappear. After pouring you can
repeat this when there are bubbles that have risen to the top of the mould. (This is especially useful if
you will be using the top surface of the mould you are pouring.)
10.Smooth the top of your plaster item with a rib or something like that, and let it set. Clean your bucket
and tools at this time.
11.If you are pouring a very large mould, or for some reason didn't mix enough plaster in the first batch,
immediately start mixing the second batch. When it is ready you can pour it over the existing plaster.
Scratch crisscross lines into the top of the first layer before pouring the second layer to help them
adhere together.
12.There will be a point where the plaster is hard, but still wet enough to easily carve. This is a good
time to put the item on your wheel and trim it, or trim off the rough edges by hand, or start carving your
designs.
13. It can take many months for a large plaster mould to completely dry out, so it will continue to get
lighter as that happens. But it is usable immediately. If using the same piece of plaster over and over, it
will eventually become too wet to release the clay. Let it dry and it will again work fine. If you can't wait
for the plaster to dry, you can sprinkle with talc. Here is a beautiful thing about plaster. If you ever want
to carve into it later, you can soak it in water, re-wet it, and it will become.

More Related Content

Similar to REPORT BRICKWORK WALL PLASTERING.pdf

educational sheet clay plaster
educational sheet clay plastereducational sheet clay plaster
educational sheet clay plasterlibnam
 
Drywall Finishing Tips
Drywall Finishing TipsDrywall Finishing Tips
Drywall Finishing TipsDaniel Henny
 
Research into steps in making different kinds of sculptures
Research into steps in making different kinds of sculpturesResearch into steps in making different kinds of sculptures
Research into steps in making different kinds of sculpturesChelsea-Ann Cook
 
Jointing & Pointing
Jointing & PointingJointing & Pointing
Jointing & PointingSteve Jarvis
 
Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Chan Yifung
 
How to stamp concrete patios, pool deck, driveways etc.
How to stamp concrete patios, pool deck, driveways etc.How to stamp concrete patios, pool deck, driveways etc.
How to stamp concrete patios, pool deck, driveways etc.Elite Crete Australia
 
How To Repair And Replace Broken Bathroom Ceramic Tiles
How To Repair And Replace Broken Bathroom Ceramic TilesHow To Repair And Replace Broken Bathroom Ceramic Tiles
How To Repair And Replace Broken Bathroom Ceramic TilesOttawa Tile
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxswethaasukumar
 
Timber Panels Installation
Timber Panels InstallationTimber Panels Installation
Timber Panels InstallationDeziner Panels
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkSteve Jarvis
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialConstrofacilitator
 
pointing, plastering, bonding
pointing, plastering, bondingpointing, plastering, bonding
pointing, plastering, bondingRAHUL SINHA
 

Similar to REPORT BRICKWORK WALL PLASTERING.pdf (20)

educational sheet clay plaster
educational sheet clay plastereducational sheet clay plaster
educational sheet clay plaster
 
Drywall Finishing Tips
Drywall Finishing TipsDrywall Finishing Tips
Drywall Finishing Tips
 
Research into steps in making different kinds of sculptures
Research into steps in making different kinds of sculpturesResearch into steps in making different kinds of sculptures
Research into steps in making different kinds of sculptures
 
Jointing & Pointing
Jointing & PointingJointing & Pointing
Jointing & Pointing
 
Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)Introduction brickwall-report-yf (1)
Introduction brickwall-report-yf (1)
 
How to stamp concrete patios, pool deck, driveways etc.
How to stamp concrete patios, pool deck, driveways etc.How to stamp concrete patios, pool deck, driveways etc.
How to stamp concrete patios, pool deck, driveways etc.
 
cereamic
cereamiccereamic
cereamic
 
Replace broken tiles
Replace broken tilesReplace broken tiles
Replace broken tiles
 
How To Repair And Replace Broken Bathroom Ceramic Tiles
How To Repair And Replace Broken Bathroom Ceramic TilesHow To Repair And Replace Broken Bathroom Ceramic Tiles
How To Repair And Replace Broken Bathroom Ceramic Tiles
 
Deep-Vac-Work (2)
Deep-Vac-Work (2)Deep-Vac-Work (2)
Deep-Vac-Work (2)
 
HALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptxHALF BRICK PARTITION WALL.pptx
HALF BRICK PARTITION WALL.pptx
 
Artex and plaster
Artex and plasterArtex and plaster
Artex and plaster
 
Deck post holes
Deck post holesDeck post holes
Deck post holes
 
Timber Panels Installation
Timber Panels InstallationTimber Panels Installation
Timber Panels Installation
 
Deck post holes
Deck post holesDeck post holes
Deck post holes
 
Basement Waterproofing
Basement WaterproofingBasement Waterproofing
Basement Waterproofing
 
Jointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & BlockworkJointing & Pointing Brick & Blockwork
Jointing & Pointing Brick & Blockwork
 
Waterproof your roof
Waterproof your roofWaterproof your roof
Waterproof your roof
 
Plastering mortar insulation and bonding material
Plastering mortar insulation and bonding materialPlastering mortar insulation and bonding material
Plastering mortar insulation and bonding material
 
pointing, plastering, bonding
pointing, plastering, bondingpointing, plastering, bonding
pointing, plastering, bonding
 

More from MuhammadMuazzam16

MPU23052 STKI SESI 1 2022/2023 KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...
MPU23052 STKI SESI 1 2022/2023KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...MPU23052 STKI SESI 1 2022/2023KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...
MPU23052 STKI SESI 1 2022/2023 KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...MuhammadMuazzam16
 
DCC10032 CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAAN
DCC10032	CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAANDCC10032	CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAAN
DCC10032 CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAANMuhammadMuazzam16
 
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdf
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdfDCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdf
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdfMuhammadMuazzam16
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfMuhammadMuazzam16
 
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdf
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdfREPORT SURVEY LEVELLING CIVIL ENGINEERING.pdf
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdfMuhammadMuazzam16
 
PENGHAYATAN ETIKA DAN PERADABAN .pdf
PENGHAYATAN ETIKA DAN PERADABAN .pdfPENGHAYATAN ETIKA DAN PERADABAN .pdf
PENGHAYATAN ETIKA DAN PERADABAN .pdfMuhammadMuazzam16
 
PENGHAYATAN ETIKA PERADABAN .pdf
PENGHAYATAN ETIKA PERADABAN .pdfPENGHAYATAN ETIKA PERADABAN .pdf
PENGHAYATAN ETIKA PERADABAN .pdfMuhammadMuazzam16
 
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdf
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdfSAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdf
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdfMuhammadMuazzam16
 

More from MuhammadMuazzam16 (9)

MPU23052 STKI SESI 1 2022/2023 KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...
MPU23052 STKI SESI 1 2022/2023KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...MPU23052 STKI SESI 1 2022/2023KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...
MPU23052 STKI SESI 1 2022/2023 KEPERLUAN SAINS TEKNOLOGI DAN KEJURUTERAAN DAL...
 
DCC10032 CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAAN
DCC10032	CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAANDCC10032	CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAAN
DCC10032 CIVIL ENGINEERING MATERIALS JENTERA & MESIN DALAM PEMBINAAN
 
Presentation contract.pptx
Presentation contract.pptxPresentation contract.pptx
Presentation contract.pptx
 
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdf
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdfDCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdf
DCC20042P CARPENTRY TANGGAM KAYU (WOOD JOINT).pdf
 
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdfREPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
REPORT SURVEY RANGING CURVE CIVIL ENGINEERING.pdf
 
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdf
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdfREPORT SURVEY LEVELLING CIVIL ENGINEERING.pdf
REPORT SURVEY LEVELLING CIVIL ENGINEERING.pdf
 
PENGHAYATAN ETIKA DAN PERADABAN .pdf
PENGHAYATAN ETIKA DAN PERADABAN .pdfPENGHAYATAN ETIKA DAN PERADABAN .pdf
PENGHAYATAN ETIKA DAN PERADABAN .pdf
 
PENGHAYATAN ETIKA PERADABAN .pdf
PENGHAYATAN ETIKA PERADABAN .pdfPENGHAYATAN ETIKA PERADABAN .pdf
PENGHAYATAN ETIKA PERADABAN .pdf
 
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdf
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdfSAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdf
SAINS TEKNOLOGI KEJURUTERAAN ISLAM E-FOLIO.pdf
 

Recently uploaded

Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHC Sai Kiran
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxRomil Mishra
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm Systemirfanmechengr
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESNarmatha D
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...Amil Baba Dawood bangali
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadaditya806802
 

Recently uploaded (20)

Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Introduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECHIntroduction to Machine Learning Unit-3 for II MECH
Introduction to Machine Learning Unit-3 for II MECH
 
Mine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptxMine Environment II Lab_MI10448MI__________.pptx
Mine Environment II Lab_MI10448MI__________.pptx
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Class 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm SystemClass 1 | NFPA 72 | Overview Fire Alarm System
Class 1 | NFPA 72 | Overview Fire Alarm System
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
Industrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIESIndustrial Safety Unit-I SAFETY TERMINOLOGIES
Industrial Safety Unit-I SAFETY TERMINOLOGIES
 
Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
NO1 Certified Black Magic Specialist Expert Amil baba in Uae Dubai Abu Dhabi ...
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
home automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasadhome automation using Arduino by Aditya Prasad
home automation using Arduino by Aditya Prasad
 

REPORT BRICKWORK WALL PLASTERING.pdf

  • 1. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 1 | P a g e CIVIL ENGINEERING DEPARTMENT DCC10022 – BRICKWORKS AND CONCRETE LABORATORY BRICKWORK LABORATORY 4 : WALL PLASTERING
  • 2. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 2 | P a g e
  • 3. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 3 | P a g e INTRODUCTION Brickwork is masonry produced by a bricklayer, using bricks and mortar to build up brick structures such as walls. Brickwork is also used to finish corners, door, and window openings, etc. in buildings made of other materials. There are two main types of clay bricks: pressed and wire-cut. Pressed bricks usually have a deep frog in one bedding surface and a shallow frog in the other. Wire-cut bricks usually have 3 or 4 holes through them constituting up to 25% of the total volume of the brick. Some ‘perforated’ bricks have many smaller holes. There are three main categories of use, and both pressed bricks or wire-cut brick types are used in all three categories: ❖ Facing brickwork is the visible decorative work. ❖ Engineering brickwork, (using engineering bricks) often seen in bridges and large industrial construction but may also be hidden in ground works where maximum durability is required, e.g., in manhole construction. ❖ Common brickwork is not usually seen and is used where engineering qualities are not required; below ground in domestic buildings and internal walls, for instance. OBJECTIVE OF THE EXPERIMENT ➢ In the bricklaying field, the term stretcher bond is a reference to the format and standard to which certain types of brick walls are built in order to be stable. Stretcher bond is the term given to the repeating pattern the bricks are laid in. This pattern includes vertical supports tied in to the foundation of the structure the wall is being built on. ➢ This type of brick format is used mostly in interior settings because it is only applicable in thin- walled settings. As a matter of fact, the stretcher bond wall is only usable in the thinnest of brick wall settings. This is because it is only as thick as one half of a brick.
  • 4. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 4 | P a g e THEORY BONDS A wall relies on the way the bricks are bonded for its strength. The vertical joints between bricks in adjacent courses must not coincide either on the face of the wall or across its thickness. There is a variety of possible bonds. A half-brick wall up to 1m high can be built in stretcher or open bond. You should bond in piers (328 x 215mm) at the ends of the wall and at a maximum of 1.8m centres. A 215mm wall can be built using either English or Flemish bond. Careful cutting is needed at junctions and corners to avoid continuous vertical joints through two or more courses of brick. WALLS PLASTERING After you have cement rendered the brick walls of your room, you have to prepare them for the paint coats by applying the plaster. ✓ Plastering a brick wall is not a complex task, being similar to plastering a drywall, but you have to follow a couple of guidelines, as to get the job done in a professional manner. Consequently, you must apply two coats of plaster, the first one a little more coarse, while the second one should be very fine. After the two coats have dried out, you have to sand thoroughly the surface, as to make it even and neat. ✓ Make sure the surface is ready to apply plaster. If we speak of a new construction, then you should make sure you have cement rendered the walls and let them dry for a couple of days. ✓ If you want to plaster an old room, then you have to remove the coats of paint and sand the surface thoroughly. In addition, cover the walls with PVA bonding, according to the manufacturer’s instructions, as to make sure the plaster will adhere to the walls. In order to mix the plaster, you need several tools: a clean construction bucket and a drill mixer / margin trowel. Pour water in the bucket (1/3 of the volume) and then add gradually the plaster. After a couple of minutes you have to mix thoroughly the compounds, until you get a material with the consistency of cream. If the plaster doesn’t fall off the trowel, it means that it has the right consistency SAFETY AND HEALTH WHAT IS A SAFE SITE? Many definition of safety have been offered over the years but we prefer that which suggests that a construction site is safe when person can go about their normal daily work without undue risk. This, we feel, is a realistic definition, for it accepts that there is risk situation in all everyday activities and does not pretend that a workplace can be entirely accident proof. SAFETY REGULATION There are several safety regulations in construction such as wear a suitable clothes like wear a helmet, safety boot etc.
  • 5. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 5 | P a g e HELMET HAND GLOVE SAFETY BOOTS MATERIALS / APPARATUS / TOOLS The basic tools used in masonry are: CEMENT SAND WATER STEEL SQUARE CHALK BOX PAIL BRICK CHISELS BRICK JOINTER TROWEL BRICK MEASURING TAPE LEVEL
  • 6. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 6 | P a g e PROCEDURES 1. Put mortar for plaster on a dust mask. 2. Add water to a bucket. It should be between cool and room temperature. You will learn through trial and error how much water to use, but most people tend to underestimate the amount of water needed. If you want to avoid clean-up, line your bucket with a plastic bag, then discard the whole thing at the end. 3. Using a cup or scoop, start adding plaster to the water. Sprinkle the plaster out evenly over the whole surface of the water. You don't have to be in a big hurry, but don't work too slowly or the plaster will start to set. Some people prefer to sift the plaster into the water. At first the plaster will sit on the surface of the water very briefly before it disappears beneath the surface of the water. (This is called "slaking".) 4. Keep adding plaster, sprinkling it in the same manner. After a while the plaster will be visible for a few seconds before it disappears into the water. You are getting close... Keep adding plaster. When you add plaster and can count to 5 before it disappears, you have enough. Let it sit for 1-2 minutes to wet the plaster particles (this helps reduce air bubbles). 5. Mix. You want to make sure that you aren't adding air to your plaster, or you will get bubbles which will cause problems later. So if you use an electric mixer make sure to keep the blade deep in the plaster. Or, just take your hand (a glove is useful) and place it at the bottom of the bucket, and slowly move your hand back and forth across the bottom of the bucket. This slowly wets all the particles. 6. When you can draw a line in the plaster and it doesn't immediately flatten back out, the plaster is ready to pour. BRICK HAMMER SHOVEL HAWK FLOAT CONSTRUCTION
  • 7. DCC10022 – BRICKWORKS AND CONCRETE LABORATORY 7 | P a g e 7. POURING ➢ The goal in pouring the plaster is to avoid introducing air pockets, particularly at the surface that you are going to be using. ➢ Pour slowly. ➢ Some people allow the stream of plaster to run off the palm of their hand, thus slowing it down. ➢ It is helpful to apply a thin coating all over the surface and allow it to set a little before pouring the final amount necessary for the mold. If the air bubbles come to the top of the thin surface, they will be away from the actual surface you will be using. (This is especially useful if you are pouring upside down, i.e. will use the bottom surface of the mold you are pouring.) 8. After pouring, pick up your container and softly tap it on the table or the floor. Or if it is too big, tap the edges and shake from side to side. You are trying to get air bubbles to the surface. 9. And perhaps the ultimate trick. Use rubbing or denatured alcohol in a spray bottle (some people dilute, some don't). When the plaster mixing is almost complete, spray a couple bursts into the plaster. This breaks down the surface tension of bubbles on top and they disappear. After pouring you can repeat this when there are bubbles that have risen to the top of the mould. (This is especially useful if you will be using the top surface of the mould you are pouring.) 10.Smooth the top of your plaster item with a rib or something like that, and let it set. Clean your bucket and tools at this time. 11.If you are pouring a very large mould, or for some reason didn't mix enough plaster in the first batch, immediately start mixing the second batch. When it is ready you can pour it over the existing plaster. Scratch crisscross lines into the top of the first layer before pouring the second layer to help them adhere together. 12.There will be a point where the plaster is hard, but still wet enough to easily carve. This is a good time to put the item on your wheel and trim it, or trim off the rough edges by hand, or start carving your designs. 13. It can take many months for a large plaster mould to completely dry out, so it will continue to get lighter as that happens. But it is usable immediately. If using the same piece of plaster over and over, it will eventually become too wet to release the clay. Let it dry and it will again work fine. If you can't wait for the plaster to dry, you can sprinkle with talc. Here is a beautiful thing about plaster. If you ever want to carve into it later, you can soak it in water, re-wet it, and it will become.