2. 1. Key Point in utilities as per Schedule C guidelines
The design of the Railway station in Ahmedabad shall
be done such that access control can be introduced at a
later stage. However, since all Railway tickets are not
yet machine readable, the access control equipment
shall not be provided at this stage. However, necessary
enabling facilities for such an access control such as
electricity, data connections, etc. shall be provided to
ensure that these can be introduced later on.
3. 1. As per Schedule C Specific guidelines
The Contractor will be required to execute some works which are
essential prior to execution of project/ project components such
as permanent/ temporary relocation/ shifting, diversion and
restoration of existing utilities like signal cables or
communication cables, electrical cables, substations, water
pipelines, pumping stations, sewer lines, drainage pipelines etc.
All the hidden utilities shall be initially mapped with suitable
means in pre construction period and the execution for the
construction of the project shall be done so as not to disrupt the
existing operational services.
4. Cost of shifting/ relocation/ diversion of
Utilities like water mains, overhead and
underground water storage tanks, water
wells power cable, street lights, transformer,
telephone posts, signal & telecom cables,
sewer lines, storm water drains, Signal posts,
OHE installation, including their
appurtenances, shall be borne by contractor.
5. All utilities other than those specified in
charted utilities are defined as uncharted
utilities including those for the Control Room.
The payment of shifting/ relocation/ diversion
of such utilities shall be dealt as per Article-9
of RFP document.
6. The requisite NOC/ permission from utility
owning entity(ies) shall have to be obtained by
the Contractor before start of such works. The
responsibility for timely shifting/ relocation/
diversion of such utility before the construction of
the project or the project components shall lie
with the contractor. Care has to be taken by the
Contractor to ensure that the services especially
train operations continue uninterrupted and with
least possible unplanned stoppages.
7. a) Approval and sanction of Electrical load from
Local / State supply shall be arranged by
Contractor.
b) In total 3 Substations are proposed to be
constructed, 2 on Kalupur side and 1 on
Saraspur side.
c) Total requirement of approx. 14 MW electrical
demand is worked out, approx. 9 MW for Iconic
building, 4 MW for station building.
d) Diversion of Existing LT/ HT Cables as per site
requirements
8. Sl.N
o
Function
Building
Built up
area (in
Sq.ft)
Built
up area
(in
Sq.mt)
HVAC
Electrical
Power
Requirement
in KW
Electrical Power
Requirement
(KW)
PHE
Electrical
Power
Requirement
in KW
Total Electrical
Power
Requirement in
KW
1 Iconic building 2591721 240866 5,507.41 3,877.95 9,385.36
2 Station Building 1026111 95363 2,180.49 1,535.35 3,715.84
3 Govt offices 39267 3649 125.16 58.75 183.91
4
PHE Load
(STP+Pump)
10 350 360
Estimated Power Requirement in Kilo Watt (KW) 13,645.11
Estimated Power Requirement in Mega Watt (MW) 13.65
9. Supply & Installation of Light fixtures in all areas
(Interiors & exteriors) as to provide minimum lux
levels specified and shall not cause glare or other
problems for the users. The Contractor must
provide a minimum 10 years of warranty for the
light fixtures. The cables shall have sufficient
insulation, shall be fire retardant and these shall
not get heated up under the design loads.
10. The scope of supply and laying of cable from electricity
supply authority to Substation is not in Bidder’s Scope of
Work. Charges for any such work shall be borne by the
Authority, however the Contractor shall make necessary
applications and carry out necessary liasioning with the
concerned electricity supply authority.
Liasoning with power supply authority for power sanction.
Approval of electrical distribution scheme & layout form
CEIG other statutory bodies as applicable.
All statutory approvals for Electrical systems installed
under Contractor scope.
11. APFCR
As per
equipment
Requirement
Automatic power factor
capacitor bank along with
Panel at suitable locations for
improvement of P.F up to 0.99
to minimize maximum
demand,to avoid penalty
because poor
P.F and to destress all current
carrying equipment’s
Supply, installation, testing and commissioning
of APFCR panel and Capacitor banks for as per
statutory norms in State shall beprovided by
Contractor.
HT & LT
power and
control cable &
Bus Duct
LV Bus duct, HT & LT Power,
and control cable suitable for
System requirements.
Supply, installation, laying, termination and
connection of allthe electrical HT & LT Power
andControl cables, wires, cable trays,
interconnecting cabling for Station & Railway
shall be in the scope of Contractor as per
requirement.
Illumination
System
All lighting as per relevant
standard codes for the Railway
Station & Ahmedabad
TerminalBuilding
development area
Supply, installation, testing and commissioning
of lighting fixtures, fans etc. for station
development along with all the Hardware
requirements as per relevant standard codes
shall bedeveloped by Contractor.
12. UPS with SMF
battery
(Minimum 30
Min backup)
Centralized or distributed on-
line UPS with SMF battery
bank, Battery charger for
supplying critical load,
Emergency Lighting, ticket
booking etc. as per the
requirement of Station.
Supply, installation, Testing andcommissioning
of UPS with SMFbattery & Battery Charger shall
be in the scope of Contractor.
Power and
Switch Socket
Small power modules and
switch socket, Receptacles as
per requirement
Supply, Installation, Testing, andCommissioning
of All small power modules and Switch socket,
receptacles for Station development as per
requirementbased on location and utility shall
be in the scope of Contractor.
13. Sl.No Ups Required Locations Backup
Time
1 Telecommunication system 30 mins
2 Signalling system 2 hrs
3 Fire alarm and detection system 2 hrs
4 Master clock system 2 hrs
5 Public address system 30 min
6 Closed circuit television (CCTV) 2 hrs
7 PC work stations in SCR 2 hrs
8 M & E SCADA, Power Supply SCADA 2 hrs
9 Emergency lighting 2 hrs
10 Subway lighting 2 hrs
11 Subway emergency evacuation signage
lighting
2 hrs
12 Exit and emergency signage 2 hrs
14. The roof of station building, Iconic/MMTH building, roof of building 3 and 6 shall
be available for solar power generation. Contractor to install panels by using the
modern PV cells/ BIPV (building integrated photovoltaic) / rooftop panels. This solar PV
system shall be integrated with grid power supply.
It shall be consisting mainly the following details-
Solar panels
Module Mounting Structure
DC distribution Junction BOX
Solar grid support inverters
AC distribution Junction Box
Solar Generation Meter
Net Meter (also Includes Approval from supply company)
Cabling, Safety components And other required Accessories
Earthing System
Module for Remote monitoring
Lightning Arrestor
15. The indoor units shall be similar in operation and appearance as
conventional indoor units of split units and provide independent on-
off control, temperature setting etc. The system shall provide
considerable (nearly 30%) energy saving over traditional air-
conditioning system (consisting of split units) due to following
features:
Individual accurate temperature
Multiple compressors in outdoor unit (8 HP & Above) in
conjunction with inverter drive compressor to modulate refrigerant
flow based on requirement.
Minimizing heat transfer losses due to superior refrigerant piping
system with eco-friendly Refrigerant.
As defined in the National Building Code of India 2016, mechanical
ventilation for Basement car parking shall be designed to permit 6
ACPH for normal ventilation and 12 ACPH in case of fire. The
system shall comprise of ductless ventilation system i.e. multiple
ceiling hung jet fans keeping in view the following:
16. Prevent build-up of exhaust emission from vehicles by providing
adequate ventilation
Good air movement to ensure good environment.
Smoke control in the event of a fire.
Reduced operating costs by using co-sensors so that fans are operated
as and when required.
The mechanical ventilation system shall comprise of
makeup air fans to supply fresh air, multiple ceiling hung jet fans
which shall be provided to assist with the direction of the flow of air
and to propel air towards main exhaust fans. Both makeup & exhaust
fan shall be Dual speed Axial flow fans. During normal Basement
ventilation, main fans designed for 6 ACPH shall operate. And in case
of fire same fan will run with double speed to cater the additional
6ACH. In case of fire these additional fans shall get actuated and draw
the air from the car park and discharge independently alongside the
main Axial fan. The shaft receiving the exhaust from both fans shall be
sized for 12 ACPH for Basement.
17. Public Toilet 10 ACPH
AC Plant 20-25 ACPH
Kitchen 65 ACPH (Exhaust) & 60 ACPH (Fresh Air)
DG Room Air quantity is designed based on heat rejection from xx Nos. DG
sets and maximum allowable temperature rise of 10 deg. C over
ambient temperature.
Car Parking 6 (Normal Mode) / 12 (Fire Mode) ACPH Exhaust
6 (Normal Mode) / 12 (Fire Mode) - Fresh air makeup
Smoke exhaust in all
public area above Ground
12 ACPH Exhaust
12 ACPH Make up air
Smoke Exhaust for areas
in Basement
12 ACPH Exhaust
12 ACPH Make up air
Lift well pressurization To be mechanically pressurized for maintaining 50 Pa
Lift lobby pressurization To be mechanical pressurized for maintaining 30 Pa.
Staircase Pressurization Cross Ventilation – If open, 2 Nos. of 0.5 sq.mt clear opening on
adjacent/opposite sides shall be provided on each landing in
addition to 0.5 sq.mt of opening on topmost level then mechanical
ventilation is not required.
19. Building management system (BMS) is a computer-based control system installed in
buildings that controls and monitors the building's mechanical and electrical
equipment. BMS shall be able to Control and Monitor the following systems:
HVAC Systems: AHUs, VAVs, Car park Ventilation Fans, Chillers, pumps
Electrical Systems: HT/LT Panel breakers, Floor Panel incomer breakers, Electrical
Energy meter, Lighting control system, DG, UPS
Plumbing Systems: Control and monitoring of Water pumps, Tanks
Lifts: Status monitoring of Lifts
Fire Alarm system
Building automation system to monitor and control utilities from the BMS
workstations from command center & Security office. The BMS workstations to
connect to standalone freely configurable DDC controllers. MS network shall allow
peer-to-peer communication.
21. All Vehicular ingress and egress.
All main pedestrian entry and egress points to station structure (including
multi-modal connections whether at, above or below ground level,
entrance/Exit, Main Entrance/Exit, platforms, yards or any other locations.
All main entry points to paid area.
Main concourse area (cameras shall not be more than 100m from any point).
All platform area (cameras shall not be more than 100m from any point).
Fixed box type cameras shall normally be provided in Parking area, waiting
halls, ticket counters, reservation counters, offices entries
High speed PTZ dome cameras shall normally be provided in platforms, foot
over bridges etc. and for general perimeter surveillance.
Wireless system shall normally be used for far away locations, where cabling is
difficult to be installed & maintain like yards and extreme corners of stations
Ticket Counters and ticket vending machines (TVM's) (these areas shall be
within direct range of the CCTV cameras).
23. Access control operation: Once the access in authenticated the card reader application
will open the electromagnetic lock (EM lock) of the door or open turnstile gate for one
entry
Application Category:
Door Controls
Control Gates - Flap Barrier/Turnstile control for Passengers.
Boom barrier & Bollard control
Access Control System (ACS) location:
CCTV security Control room/Command Centre
Hub rooms
Main Electrical Room
Flap Barrier/Turnstile in Paid concourse separation
Boom barrier & Bollard interface
24. 1. The firefighting arrangement shall be designed as per the
requirement of local guidelines, NBC (with NFPA being
referred wherever NBC is silent) & engineering design
standard.
2. The entire fire safety installation shall be compliant with the
most stringent codes/ standard for the building to ensure the
highest safety standard and uniformity of system. Further,
before property is opened to the public, the fire protection
shall be fully operated and tested under simulated conditions
to demonstrate compliance with the most stringent
standards, codes and guidelines.
25. S.No. System Standard
a. Piping system Piping system confirming to IS:1239
b. Fire water static storage Fire water static storage to be provided in accordance with
NBC requirements
c. Fire Pumping system Pumping system comprising of independent pumps for
hydrant, sprinkler and jockey application
d. Hydrant system External and internal hydrant complete with hose reel
e. Sprinkler system Sprinkler rating and type shall be selected for respective
areas
f. Booster pump Booster pumps shall be installed on terraces of each
building
g. Trolley mounted CO2 system For Transformer Room/ LT Panel Room/ DG Room, as per
local by-laws
h. Handheld fire extinguisher Strategically placed at designated areas
26. Firefighting System shall be installed in covered and
open areas (Subways, Platforms, Basement, Building,
Concourse Area, Lift & Escalator area, Mezzanine Floor,
Substation, Electrical Rooms, Pump rooms. The detailed
drawing & design shall be developed by the Contractor of
AE before execution of work. The relevant required U/G
Tank, OHT room, rooms, pump room etc. shall be
constructed as per detailed drawing & design worked out
by the Contractor.
27. All Makes best in Standards as mentioned in
Schedule c and If any unspecified best in class need to
be considered.