             Department of Community Planning and Economic Development
                                 Planning Division

                            Certificate of Appropriateness
                                       BZH-26933

Date:                       July 26, 2011

Proposal:                   Request for COA to complete preservation and stabilization
                            work

Applicant:                  Historic Sites and Museums, Minnesota Historical Society,
                            Sarah Beimers, Senior Project Manager, 651-259-3474

Address of Property:        104 8th Avenue South

Project Name:               Washburn Crosby Elevator No. 1 Exterior Preservation

Contact Person and Phone: Todd Grover, (612) 341-4051

Planning Staff and Phone:   Aaron Hanauer, (612) 673-2494

Date Application
      Deemed Complete:      July 11, 2011

Publication Date:           July 19, 2011

Public Hearing:             July 26, 2011

Appeal Period Expiration:   August 5, 2011

Ward:                       7

Neighborhood Organization: Downtown East




                                                                                                 1
Posted by http://MillCityTimes.com

               Department of Community Planning and Economic Development
                                   Planning Division



Attachments:

                            Attachment A: Materials submitted by CPED- (A1-A8)
                            • A1: Zoning Map
                            • A2: Saint Anthony Falls Historic District Map
                            • A3-A4: Historic Images
                            • A5-A8: Aerials

                            Attachment B: Materials submitted by Applicant– (B1-B27)
                            • B1: Council Member Communication
                            • B2: Neighborhood Association Communication
                            • B3-B5: Certificate of Appropriateness Application Form
                            • B6-B7: Project Description
                            • B8: Statement to Required Findings
                            • B9-B15.1: Images
                            • B15.2-B15.5: Elevations Showing Existing Conditions
                            • B15.6-B15.12: Proposed Roof Decking Material
                            • B16-B27: Plan Set




                                                                                             2
Posted by http://MillCityTimes.com

             Department of Community Planning and Economic Development
                                 Planning Division




Washburn Crosby Elevator Number 1, 1911, Source: Minnesota Historical Society


                                                                                             3
Posted by http://MillCityTimes.com

             Department of Community Planning and Economic Development
                                 Planning Division




Washburn Crosby Elevator Number 1, 2011, Source: MacDonald and Mack Architects


                                                                                           4
Posted by http://MillCityTimes.com

         Department of Community Planning and Economic Development
                             Planning Division


CLASSIFICATION:
Local Historic            Saint Anthony Falls Historic District
District
Period of                 1858-1940
Significance
Criteria of               Architecture and Social Significance
significance
Date of local             1971
designation
Applicable Design         Saint Anthony Falls Historic District Guidelines
Guidelines
                          Secretary of Interior Standards for Treatment of
                          Historic Properties



PROPERTY
INFORMATION
Current name             Washburn Crosby Elevator Number 1
Historic Name            Washburn Crosby Elevator Number 1
Current Address          104 8th Avenue South
Historic Address         721-729 1st Street South
Original                 1906-1908
Construction Date
Original Contractor      Haglin Stahr Company
Historic Use             Grain Storage
Current Use              Vacant
Proposed Use             Stabilization




                                                                                           5
Posted by http://MillCityTimes.com

               Department of Community Planning and Economic Development
                                   Planning Division

BACKGROUND:

Historic Background

Washburn Crosby Elevator No.1 was constructed in 1906-08 by the Haglin Stahr Company
and built east of the Washburn ''A'' Mill. It was one of the first large scale concrete grain
storage facilities to be built in the country with exposed circular bin construction. It is also an
early example of a continuous pour, slip form construction. Slip form construction is the use of
a mold that is pulled or raised as concrete is placed. This type of construction, developed by
Charles Haglin, spurred the massive construction efforts of these elevators across the country.

The Washburn “A” Mill Complex is one of three national historic landmarks in the City of
Minneapolis (the Pillsbury A Mill and Christ Church Lutheran are the other two).

Elevator Number One is comprised of 15 cylindrical bins, arranged in three rows of five
(Attachment B16). The plan is approximately 125 feet by 79 feet and the bins rise to 112 feet in
height. The Headhouse extends another 95 feet above the bins. The reinforced concrete
foundation extends 34 feet below grade. The walls of the bins are of reinforced concrete and
vary from 9 to 10 inches thick. The roof of the bins is a reinforced concrete slab that appears to
form part of the support for the Headhouse. Two Gold Medal Flour signs are attached to the
headhouse.

Application Background

A structural assessment of the grain elevator roof was completed in 2010 after substantial
pieces of concrete were falling from the underside of the roof. The scope of the 2010 structural
assessment was expanded to the headhouse to analyze the connection between the bin roof
and the headhouse. The structural assessment summary concluded the following:
   • The exterior walls of the bins are in good condition. There are selective and isolated
       areas that are in need of repair, but there are no major or immediate issues regarding
       the bins.
   • The roof of the bins is in extremely poor shape and has failed. The roof cannot be
       repaired as the accelerated deterioration of the concrete has mitigated its structural
       capacity. This roof can no longer be used in its current condition and must be replaced.
       Temporary protection methods may be utilized to prevent a safety hazard of the
       deteriorated elements.
   • Primary and intermediate roofs on the headhouse are in good condition, with isolated
       areas of repair.
   • Aside from the primary roof of the headhouse, all built-up roofing is in poor condition.
       The roofing should be removed and replaced. There are isolated areas on the bin walls
       and headhouse walls that need repair to the spalling concrete due to shale or shallow
       rebar deterioration.
   • There are isolated areas of significant water infiltration of the concrete roof/walls where
       the concrete should be removed and replaced.




                                                                                                      6
Posted by http://MillCityTimes.com

                Department of Community Planning and Economic Development
                                    Planning Division

SUMMARY OF APPLICANT’S PROPOSAL
The Applicant states that their work falls into three types of work 1. repairing of historic materials
and features, 2. limited replacement in kind of extensively deteriorated portions of historic features,
3. stabilization of deteriorated historic materials and features (Attachment B6). Specifically, there
are six parts to their scope of work:
    1. concrete repair: On the exterior of Elevator No. 1 and Headhouse there are numerous
        areas where concrete is deteriorating, cracking and spalling (Attachment B15.2-B15-5 and
        B19-B19.4 and B28-B31 drawings). The cracking is typically at cold joints that have had
        water infiltration. The spalling is typically due to shallow rebar placement and shale
        aggregate in the concrete mix.

       The Minnesota Historical Society (MHS) proposes to repair the areas where it is deteriorated
       by removing corrosive and loose concrete and applying a concrete patch that will match the
       surface profile of surrounding concrete (Attachment B26, Drawing 3). Large cracks (greater
       than 1/16” of an inch), are proposed to be filled and then cleaned up to have the surface of
       the crack be flush with the outside of the surrounding area (Attachment B26, Drawing 4).

       Included in the scope of concrete repair is the rebuilding of the west parapet that has a
       significant amount of concrete deterioration (Attachment B15, 15.1, B21, and B26). The
       Applicant is proposing to remove deteriorated concrete down to stable material. Then rebuild
       the parapet to match the height and profile of the original and east parapet.

   2. parging installation: The exterior of Elevator Number 1 is covered by a cement parging.
      Parging is a thin, paintable mixture of cement, sand, and colorant that provides a protective
      and breathable surface to the concrete (see Attachment B10 for historic image showing the
      application of the parging and Attachment B14 showing parging deterioration). The areas
      where the parging has deteriorated, accelerated carbonation and water penetration into the
      concrete has been identified. The MHS is proposing to scrape off the old parging and
      replace with a new parging to match original in areas where concrete is repaired or where
      the parging is missing (Attachment B15.2-B15.5 for existing conditions and B19-19.4 for
      proposed work). The new parging will be noticeably different for approximately ten years,
      until it weatherizes and blends in with the original parging.

   3. bin roof replacement: The Applicant states that the bin roof is failing, cannot be repaired,
      and needs to be replaced (Attachment B9, B10, B12, B13). The Applicant’s structural
      analysis confirms this analysis:
        “The cores [of the bin roof] were not in good condition; none of them had enough
        integrity to provide a strength test. Thus, the concrete strength in the roof is variable
        and low. Petrographic analysis of these cores showed bleedwater voids, indicative of
        a high water-to-cement ratio during construction as well as freeze-thaw damage. Both
        of these contribute to low initial and remaining strength. Finally, on the west side
        adjacent to the Feed Elevator, there is a visible sag in the roof that appears to be
        about two feet.”
      The bin roof slab was poured monolithically and is approximately 6 inches thick. The
      Applicant states that a replacement roof will require a new roof using pre-cast planks on new
      steel structure members (Attachment B17 for bin roof plan and B19-B19.4 for elevations).


                                                                                                         7
Posted by http://MillCityTimes.com

            Department of Community Planning and Economic Development
                                Planning Division

   The goal of the roof replacement is to match, as closely as possible, the details and
   dimensions of the original construction. The Applicant states that “The pre-cast planks were
   chosen because of the difficulty with installing site-cast concrete where the forms for the roof
   will be inaccessible after the concrete pour because there is no access to the underside of
   the roof inside the bins. The Applicant also adds that, “Typically pre-cast planks are smooth
   with a champher at the plank joint and do not visually replicate site-cast concrete. The
   specified pre-cast planks for this project are going to be custom wet-cast planks that will
   have a board formed bottom and square edge sides. This will ensure that the view from the
   ground will replicate the site-cast concrete of the original and the joints will be imperceptible.
   The details at the edge of the roof, including the profiles of the steel channel and copper
   flashing profile, will match the original (Attachment B7).” After the installation of the new roof,
   the Applicant proposes to reinstall the metal bins that sit on top of the roof (Attachment B9
   and B17).

4. Additional Roofing: The headhouse contains multiple roofs (Attachment B17-B18, B22).
   The roofs are concrete roofs that have had asphalt applied to them over the years. The
   roofs, except for the uppermost head house roof, are failing (Attachment B13). MHS is
   proposing to remove all asphalt roofing, except for the head house roof, make concrete
   repairs to these roof decks, and install a cold fluid applied waterproofing (Attachment B15.6-
   B15.12 for details). The Applicant states that this is a material that is typically used on the
   top of parking decks. The Applicant also states that advantage of this material is that it is
   durable, will not degrade in sunlight, as asphalt does, and it comes in colors that can
   replicate the original concrete roof appearance.

5. Infill of doors: There are three door openings on the southwest elevation of the building
   that allowed equipment and materials to be brought to the upper floors (Attachment B10,
   B14, B19.1 and page 4 of staff report). Two of these openings have missing doors. MHS
   proposed to install temporary frame walls with a painted plywood panel in the recessed
   opening to prevent water and vermin intrusion into the buildings (Attachment B21).

6. Covering of windows: The building has numerous steel sash windows on each elevation.
   Many of them are broken and deteriorating because they are exposed to the elements. The
   open windows also allow water to penetrate the enclosure where accelerated deterioration
   of the concrete around the open windows can be seen. MHS proposes to install a painted
   steel plate on the exterior of the window opening that will overlap the exterior wall by three
   inches to protect the windows from further deterioration and also prevent water from
   entering the building (Attachment B21, Drawing 8, Window enclosure plan and section
   detail). The Applicant states that many windows have the potential to be rehabilitated, but
   this work cannot be done at this time. This measure will provide the protection from the
   elements to reduce further deterioration of the window sashes and surrounding concrete so
   that future rehabilitation, to the greatest extent possible, can be accomplished. This detail
   does not require any mechanical fastening of the cover to concrete, thus preserving the
   integrity of the wall surrounding the window.

7. Gold Metal Flour sign mounting points: The Applicant is proposing to analyze the
   caulking of the Gold Metal Flour sign for security (Attachment B14.1-B14.2). If additional
   work is needed the Applicant will notify CPED Preservation and Design staff.

                                                                                                      8
Posted by http://MillCityTimes.com

               Department of Community Planning and Economic Development
                                   Planning Division


PUBLIC COMMENT:

Public notices for the Certificate of Appropriateness were mailed on Tuesday, July 14, 2011.
As of July 19, 2011 no letters have been received.




                                                                                                   9
Posted by http://MillCityTimes.com

                      Department of Community Planning and Economic Development
                                          Planning Division


CETIFICATE OF APPROPRIATENESS: Certificate of Appropriateness to rehabilitate the
U                                                 U




steel fence as part of Phase I of the fence restoration project.

    Findings as required by the Minneapolis Preservation Code:

    The Planning Division of the Minneapolis Community Planning and Economic Development
    Department has analyzed the application based on the findings required by the Minneapolis
    Preservation Ordinance. Before approving a certificate of appropriateness, and based upon
    the evidence presented in each application submitted, the commission shall make findings
    based upon, but not limited to, the following:

          (1) The alteration is compatible with and continues to support the criteria of
              significance and period of significance for which the landmark or historic district
              was designated.

          CPED believes the proposed preservation, stabilization, and limited replacement in kind
          work is compatible with and continues to support the criteria of significance and period of
          significance for which the Washburn A Mill Complex is a National Historic Landmark and
          contributing building(s) to the Saint Anthony Falls Historic District.

          The Washburn A Mill Complex is significant as a national historic landmark because it as
          an example of a radical transformation of the flour milling industry in the late 19th and early
          20th centuries that made it a modern mass-production industry. The Washburn A Mill
          (1874) is the only structure that remains from the original Minneapolis milling complex
          established by Cadwallader C. Washburn. The Washburn Crosby Elevator No. 1 is part of
          the milling complex that represents an important part of the nation and Minneapolis’ flour
          milling history as it is one of the first grain elevators in the United States to be built in an
          exposed circular bin construction style.

    (2) The alteration is compatible with and supports the interior and/or exterior
        designation in which the property was designated.

           CPED believes the proposed preservation, stabilization, and limited replacement in kind
           work is compatible with and continues to support the exterior designation in which the
           property was designated. The proposed work will help preserve the integrity of the
           landmark by making necessary repairs and stabilizing the condition of the elevators.

    (3)    The alteration is compatible with and will ensure continued integrity of the
           landmark or historic district for which the district was designated.

           The Applicant has demonstrated that the items proposed to be replaced are beyond
           repair, and that their proposed preservation and stabilization work will preserve and
           strengthen the historic fabric of the grain elevators.

           CPED believes the proposed preservation, stabilization, and limited replacement in kind
           work is compatible with and will ensure continued integrity of the Washburn Crosby

                                                                                                             10
Posted by http://MillCityTimes.com

              Department of Community Planning and Economic Development
                                  Planning Division

    Elevator No. 1. The goal of the proposed work is to preserve the integrity of the landmark
    by stabilizing/rehabilitating the historic fabric of the elevators, and only replacing material
    that is beyond repair.

(4) The alteration will not materially impair the significance and integrity of the
    landmark, historic district or nominated property under interim protection as
    evidenced by the consistency of alterations with the applicable design guidelines
    adopted by the commission.

    The Saint Anthony Falls Historic District Guidelines were adopted in 1980. The subject
    property is located in Subdistrict E, Right (West) Bank Milling Subdistrict.

    As the Saint Anthony Falls Historic District Guideline’s general purpose states, “these
    regulations apply to any and all new construction and rehabilitation of existing buildings
    and structures within the St. Anthony Falls Historic District.”

    The guidelines do not have specific guidelines for the preservation and rehabilitation of a
    property. However, among the purposes of the guidelines is to, “preserve the memory of
    past events.”

    The Applicant’s proposal to complete repair, limited replacement in kind of extensively
    deteriorated portions of historic features, and stabilizing deteriorated historic materials
    and features is consistent with the general purpose of the Saint Anthony Falls Historic
    District Guidelines.

(5) The alteration will not materially impair the significance and integrity of the
    landmark, historic district or nominated property under interim protection as
    evidenced by the consistency of alterations with the recommendations contained
    in The Secretary of the Interior's Standards for the Treatment of Historic Properties.

    CPED agrees with the Applicant that the proposed preservation plan is compatible with
    the Secretary of the Interior’s Standards for the Treatment of Historic Properties
    guidelines for Preserving Historic Buildings. Specifically, CPED believes that the
    proposed work is in compliance with the following Standards:
       Standard 3. Work needed to stabilize, consolidate, and conserve existing historic
       materials and features will be physically and visually compatible.

       Standard 6. The existing condition of historic features will be evaluated to determine
       the appropriate level of intervention needed. Where the severity of deterioration
       requires repair or limited replacement of a distinctive feature, the new material will
       match the old in composition, design, color, and texture.

    The Applicant has provided evidence that they are only replacing material which is
    beyond repair (grain elevator bin roof). The Applicant has also demonstrated that their
    proposal to improve the condition of the historic material (concrete) will be physically and
    visually compatible, and that they are taking measures to protect historic materials from


                                                                                                      11
Posted by http://MillCityTimes.com

                Department of Community Planning and Economic Development
                                    Planning Division

      further damage until a later date when they can be rehabilitated (window and door
      openings).

(6) The certificate of appropriateness conforms to all applicable regulations of this
    preservation ordinance and is consistent with the applicable policies of the
    comprehensive plan and applicable preservation policies in small area plans
    adopted by the city council.

      CPED believes the Applicant’s proposed preservation plan will help preserve the
      Washburn Crosby Elevator No. 1 and is in compliance with Policy 8.1 of the Minneapolis
      Comprehensive Plan.
        Policy 8.1: Preserve, and maintain historic resources which serve as reminders of the
        city's architecture, history, and culture.

(7)   Destruction of any property. Before approving a certificate of appropriateness that
      involves the destruction, in whole or in part, of any landmark, property in an
      historic district or nominated property under interim protection, the commission
      shall make findings that the destruction is necessary to correct an unsafe or
      dangerous condition on the property, or that there are no reasonable alternatives
      to the destruction. In determining whether reasonable alternatives exist, the
      commission shall consider, but not be limited to, the significance of the property,
      the integrity of the property and the economic value or usefulness of the existing
      structure, including its current use, costs of renovation and feasible alternative
      uses. The commission may delay a final decision for a reasonable period of time to
      allow parties interested in preserving the property a reasonable opportunity to act
      to protect it.

      The project does not constitute the destruction of the subject property.

Before approving a certificate of appropriateness, and based upon the evidence
presented in each application submitted, the commission shall make findings that
alterations are proposed in a manner that demonstrates that the applicant has made
adequate consideration of the following documents and regulations:

(8)   Adequate consideration of the description and statement of significance in the
      original nomination upon which designation of the landmark or historic district was
      based.

      CPED believes the Applicant gave adequate consideration of the description and
      statement of significance in the original nomination upon which the designation of the
      Saint Anthony Falls Historic District took place. To guide the work, the Applicant reviewed
      two previous studies to aid in the ongoing preservation and building maintenance:
      Elevator Assessment by BKBM Professional Engineers in 2000, and the Washburn Grain
      Elevator Complex Reuse Study by Thomas R. Zahn and Miller Dunwiddie Architects in
      2007. In addition, the Applicant completed additional research looking for original
      drawings and information that would provide guidance for the preservation of this
      important Saint Anthony Falls Historic District landmark.

                                                                                                      12
Posted by http://MillCityTimes.com

               Department of Community Planning and Economic Development
                                   Planning Division


(9)   Where applicable, Adequate consideration of Title 20 of the Minneapolis Code of
      Ordinances, Zoning Code, Chapter 530, Site Plan Review.

      The CPED-Development Services or CPED-Zoning Team will review the proposed plans
      to ensure compliance with the Minneapolis Zoning Code.


(10) The typology of treatments delineated in the Secretary of the Interior's Standards
     for the Treatment of Historic Properties and the associated guidelines for
     preserving, rehabilitating, reconstructing, and restoring historic buildings.

      For the Washburn Crosby Elevator No. 1 project, the Applicant has proposed to follow the
      Secretary of the Interior’s Standards for Preserving Historic Buildings.




                                                                                                   13
Posted by http://MillCityTimes.com

               Department of Community Planning and Economic Development
                                   Planning Division


STAFF RECOMMENDATION

CPED-Planning staff recommends that the Heritage Preservation Commission adopt staff
findings and approve the Certificate of Appropriateness with the following condition(s):
       1) For the Gold Medal Flour, any work beyond the condition analysis shall be reviewed
          by CPED-Planning Preservation Staff.
       2) CPED-Planning Preservation Staff shall review and approve the final plans and
          elevations prior to building permit issuance.
       3) The Certificate of Appropriateness approval shall expire if it is not acted upon within
          one year of approval, unless extended by the Planning Director in writing prior to
          one-year anniversary date of approvals.
       4) By ordinance, all approvals granted in this Certificate of Appropriateness shall
          remain in effect as long as all of the conditions and guarantees of such approvals
          are observed. Failure to comply with such conditions and guarantees shall
          constitute a violation of this Certificate of Appropriateness and may result in
          termination of the approval.




                                                                                                     14

Mais conteúdo relacionado

Mais procurados

Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder PortfolioDominic Holder
 
Flatlick Sewer Rehabilitation Phase III
Flatlick Sewer Rehabilitation Phase IIIFlatlick Sewer Rehabilitation Phase III
Flatlick Sewer Rehabilitation Phase IIIFairfax County
 
Coon Branch at Annandale Community Park-Stream Restoration Project
Coon Branch at Annandale Community Park-Stream Restoration ProjectCoon Branch at Annandale Community Park-Stream Restoration Project
Coon Branch at Annandale Community Park-Stream Restoration ProjectFairfax County
 
Dead Run at Georgetown Pike Stream Restoration
Dead Run at Georgetown Pike Stream Restoration Dead Run at Georgetown Pike Stream Restoration
Dead Run at Georgetown Pike Stream Restoration Fairfax County
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Fairfax County
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structuresSenthilnathan Kalidas
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Fairfax County
 
2015 Land Conservation and Tree Preservation Awards
2015 Land Conservation and Tree Preservation Awards 2015 Land Conservation and Tree Preservation Awards
2015 Land Conservation and Tree Preservation Awards Fairfax County
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationFairfax County
 
Southeast Quadrant Bailey's Demolition
Southeast Quadrant Bailey's DemolitionSoutheast Quadrant Bailey's Demolition
Southeast Quadrant Bailey's DemolitionFairfax County
 
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020Fairfax County
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionFairfax County
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Fairfax County
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County
 
How to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site RedevelopmentHow to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site RedevelopmentBethany Meys, MPH
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Fairfax County
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Fairfax County
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectFairfax County
 

Mais procurados (20)

Dominic Holder Portfolio
Dominic Holder PortfolioDominic Holder Portfolio
Dominic Holder Portfolio
 
Flatlick Sewer Rehabilitation Phase III
Flatlick Sewer Rehabilitation Phase IIIFlatlick Sewer Rehabilitation Phase III
Flatlick Sewer Rehabilitation Phase III
 
Coon Branch at Annandale Community Park-Stream Restoration Project
Coon Branch at Annandale Community Park-Stream Restoration ProjectCoon Branch at Annandale Community Park-Stream Restoration Project
Coon Branch at Annandale Community Park-Stream Restoration Project
 
Dead Run at Georgetown Pike Stream Restoration
Dead Run at Georgetown Pike Stream Restoration Dead Run at Georgetown Pike Stream Restoration
Dead Run at Georgetown Pike Stream Restoration
 
Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021Little Pimmit Run Community Meeting 10-4-2021
Little Pimmit Run Community Meeting 10-4-2021
 
Dissertation on skyscrapers the high-rise structures
Dissertation on skyscrapers   the high-rise structuresDissertation on skyscrapers   the high-rise structures
Dissertation on skyscrapers the high-rise structures
 
Comp Plan - UDO Annual Review
Comp Plan - UDO Annual ReviewComp Plan - UDO Annual Review
Comp Plan - UDO Annual Review
 
Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016Huntington Levee Community Meeting: Feb. 23, 2016
Huntington Levee Community Meeting: Feb. 23, 2016
 
2015 Land Conservation and Tree Preservation Awards
2015 Land Conservation and Tree Preservation Awards 2015 Land Conservation and Tree Preservation Awards
2015 Land Conservation and Tree Preservation Awards
 
Paul Spring Branch Stream Restoration
Paul Spring Branch Stream RestorationPaul Spring Branch Stream Restoration
Paul Spring Branch Stream Restoration
 
Southeast Quadrant Bailey's Demolition
Southeast Quadrant Bailey's DemolitionSoutheast Quadrant Bailey's Demolition
Southeast Quadrant Bailey's Demolition
 
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
Dead Run at Georgetown Pike Stream Restoration Community Meeting Oct 7, 2020
 
Stringfellow Park and Ride Expansion
Stringfellow Park and Ride ExpansionStringfellow Park and Ride Expansion
Stringfellow Park and Ride Expansion
 
Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1Pohick Creek Restoration Project - Phase 1
Pohick Creek Restoration Project - Phase 1
 
Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016Fairfax County Land Conservation Awards 2016
Fairfax County Land Conservation Awards 2016
 
How to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site RedevelopmentHow to Clear the First Hurdle in Site Redevelopment
How to Clear the First Hurdle in Site Redevelopment
 
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
Little Pimmit Run at Woodland Terrace Community Meeting 09 30-2020
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014
 
Northriverside Research web
Northriverside Research webNorthriverside Research web
Northriverside Research web
 
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration ProjectDead Run at Dominican Retreat- Segment 1 Stream Restoration Project
Dead Run at Dominican Retreat- Segment 1 Stream Restoration Project
 

Semelhante a Washburn Crosby Elevator 1 Preservation Project

Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof ReplacementFairfax County
 
Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-19501066heritage
 
Item # 4 - 240 Corona (Significance & Compatibility Review)
Item # 4 - 240 Corona (Significance & Compatibility Review)Item # 4 - 240 Corona (Significance & Compatibility Review)
Item # 4 - 240 Corona (Significance & Compatibility Review)ahcitycouncil
 
Scotts Run Tributary at Windy Hill Road Stream Stabilization
Scotts Run Tributary at Windy Hill Road Stream StabilizationScotts Run Tributary at Windy Hill Road Stream Stabilization
Scotts Run Tributary at Windy Hill Road Stream StabilizationFairfax County
 
Item # 5 301 College (Compatibility)
Item # 5   301 College (Compatibility)Item # 5   301 College (Compatibility)
Item # 5 301 College (Compatibility)ahcitycouncil
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road WalkwayFairfax County
 
Item # 5 - 117 Claywell (Significance & Compatibility Review)
Item # 5 - 117 Claywell (Significance & Compatibility Review)Item # 5 - 117 Claywell (Significance & Compatibility Review)
Item # 5 - 117 Claywell (Significance & Compatibility Review)ahcitycouncil
 
Item # 5 - 540 Lamont Ave.
Item # 5 - 540 Lamont Ave.Item # 5 - 540 Lamont Ave.
Item # 5 - 540 Lamont Ave.ahcitycouncil
 
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp019 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01sherylyn_garner08
 
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp019-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01Sherylyn Garner
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond ImprovementFairfax County
 
Urban Design Portfolio web
Urban Design Portfolio webUrban Design Portfolio web
Urban Design Portfolio webCarl Mogensen
 
Chichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayChichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayFairfax County
 
Item # 4 - 117 Claywell (Significance & Compatibility review)
Item # 4 - 117 Claywell (Significance & Compatibility review)Item # 4 - 117 Claywell (Significance & Compatibility review)
Item # 4 - 117 Claywell (Significance & Compatibility review)ahcitycouncil
 
Re - 1100 2nd Street S Environmental_RCA
Re - 1100 2nd Street S Environmental_RCARe - 1100 2nd Street S Environmental_RCA
Re - 1100 2nd Street S Environmental_RCAMill City Times
 

Semelhante a Washburn Crosby Elevator 1 Preservation Project (20)

B5 A Miraculous Transformation
B5 A Miraculous TransformationB5 A Miraculous Transformation
B5 A Miraculous Transformation
 
Historic Jail Roof Replacement
Historic Jail Roof ReplacementHistoric Jail Roof Replacement
Historic Jail Roof Replacement
 
Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950Council housing in Hollington, 1920-1950
Council housing in Hollington, 1920-1950
 
H-Town Day: Minnette Boesel
H-Town Day:  Minnette BoeselH-Town Day:  Minnette Boesel
H-Town Day: Minnette Boesel
 
Item # 4 - 240 Corona (Significance & Compatibility Review)
Item # 4 - 240 Corona (Significance & Compatibility Review)Item # 4 - 240 Corona (Significance & Compatibility Review)
Item # 4 - 240 Corona (Significance & Compatibility Review)
 
can berra.ppt
can berra.pptcan berra.ppt
can berra.ppt
 
Scotts Run Tributary at Windy Hill Road Stream Stabilization
Scotts Run Tributary at Windy Hill Road Stream StabilizationScotts Run Tributary at Windy Hill Road Stream Stabilization
Scotts Run Tributary at Windy Hill Road Stream Stabilization
 
Item # 5 301 College (Compatibility)
Item # 5   301 College (Compatibility)Item # 5   301 College (Compatibility)
Item # 5 301 College (Compatibility)
 
Telegraph Road Walkway
Telegraph Road WalkwayTelegraph Road Walkway
Telegraph Road Walkway
 
Item # 5 - 117 Claywell (Significance & Compatibility Review)
Item # 5 - 117 Claywell (Significance & Compatibility Review)Item # 5 - 117 Claywell (Significance & Compatibility Review)
Item # 5 - 117 Claywell (Significance & Compatibility Review)
 
190 S Orange
190 S Orange190 S Orange
190 S Orange
 
Item # 5 - 540 Lamont Ave.
Item # 5 - 540 Lamont Ave.Item # 5 - 540 Lamont Ave.
Item # 5 - 540 Lamont Ave.
 
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp019 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
9 10ebcctbrownfieldsseminarfinal 100914104154 Phpapp01
 
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp019-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
9-10ebcctbrownfieldsseminarfinal-100914104154-phpapp01
 
Meadow Run Pond Improvement
Meadow Run Pond ImprovementMeadow Run Pond Improvement
Meadow Run Pond Improvement
 
Urban Design Portfolio web
Urban Design Portfolio webUrban Design Portfolio web
Urban Design Portfolio web
 
Chichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane WalkwayChichester Lane at Lismore Lane Walkway
Chichester Lane at Lismore Lane Walkway
 
Item # 4 - 117 Claywell (Significance & Compatibility review)
Item # 4 - 117 Claywell (Significance & Compatibility review)Item # 4 - 117 Claywell (Significance & Compatibility review)
Item # 4 - 117 Claywell (Significance & Compatibility review)
 
Re - 1100 2nd Street S Environmental_RCA
Re - 1100 2nd Street S Environmental_RCARe - 1100 2nd Street S Environmental_RCA
Re - 1100 2nd Street S Environmental_RCA
 
RFP
RFPRFP
RFP
 

Mais de Mill City Times

Great River Outing - Gems Along the Mississippi Trail
Great River Outing - Gems Along the Mississippi TrailGreat River Outing - Gems Along the Mississippi Trail
Great River Outing - Gems Along the Mississippi TrailMill City Times
 
Minneapolis RiverCurrent 11-10-11
Minneapolis RiverCurrent 11-10-11Minneapolis RiverCurrent 11-10-11
Minneapolis RiverCurrent 11-10-11Mill City Times
 
1100 2nd St S RFP_2010 2
1100 2nd St S RFP_2010 21100 2nd St S RFP_2010 2
1100 2nd St S RFP_2010 2Mill City Times
 
DMNA November Board Meeting Agenda 11-8-11
DMNA November Board Meeting Agenda 11-8-11DMNA November Board Meeting Agenda 11-8-11
DMNA November Board Meeting Agenda 11-8-11Mill City Times
 
Minneapolis RiverCurrent 11-3-11
Minneapolis RiverCurrent 11-3-11Minneapolis RiverCurrent 11-3-11
Minneapolis RiverCurrent 11-3-11Mill City Times
 
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...Mill City Times
 
Chute Square Park Press Release 102711
Chute Square Park Press Release 102711Chute Square Park Press Release 102711
Chute Square Park Press Release 102711Mill City Times
 
Minneapolis RiverCurrent 10-28-11
Minneapolis RiverCurrent 10-28-11Minneapolis RiverCurrent 10-28-11
Minneapolis RiverCurrent 10-28-11Mill City Times
 
Minneapolis RiverCurrent 10-19-11
Minneapolis RiverCurrent 10-19-11Minneapolis RiverCurrent 10-19-11
Minneapolis RiverCurrent 10-19-11Mill City Times
 
East Downtown Council Job Posting for Executive Assistant
East Downtown Council Job Posting for Executive AssistantEast Downtown Council Job Posting for Executive Assistant
East Downtown Council Job Posting for Executive AssistantMill City Times
 
Minneapolis RiverCurrent 10-13-11
Minneapolis RiverCurrent 10-13-11Minneapolis RiverCurrent 10-13-11
Minneapolis RiverCurrent 10-13-11Mill City Times
 
Vikings Stadium Proposal Risk Analysis Report
Vikings Stadium Proposal Risk Analysis ReportVikings Stadium Proposal Risk Analysis Report
Vikings Stadium Proposal Risk Analysis ReportMill City Times
 
Third Ward NeighborhoodFest 2011
Third Ward NeighborhoodFest 2011Third Ward NeighborhoodFest 2011
Third Ward NeighborhoodFest 2011Mill City Times
 
DMNA Annual Meeting Agenda 10-11-11
DMNA Annual Meeting Agenda 10-11-11DMNA Annual Meeting Agenda 10-11-11
DMNA Annual Meeting Agenda 10-11-11Mill City Times
 
Minneapolis RiverCurrent 10-6-11
Minneapolis RiverCurrent 10-6-11Minneapolis RiverCurrent 10-6-11
Minneapolis RiverCurrent 10-6-11Mill City Times
 
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...Mill City Times
 
Minneapolis RiverCurrent 9-29-11
Minneapolis RiverCurrent 9-29-11Minneapolis RiverCurrent 9-29-11
Minneapolis RiverCurrent 9-29-11Mill City Times
 
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011Above the Falls Policy Review and Implementation Study Presentation 9-27-2011
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011Mill City Times
 
Minneapolis RiverCurrent 9-22-11
Minneapolis RiverCurrent 9-22-11Minneapolis RiverCurrent 9-22-11
Minneapolis RiverCurrent 9-22-11Mill City Times
 

Mais de Mill City Times (20)

Gold Medal Plaza
Gold Medal PlazaGold Medal Plaza
Gold Medal Plaza
 
Great River Outing - Gems Along the Mississippi Trail
Great River Outing - Gems Along the Mississippi TrailGreat River Outing - Gems Along the Mississippi Trail
Great River Outing - Gems Along the Mississippi Trail
 
Minneapolis RiverCurrent 11-10-11
Minneapolis RiverCurrent 11-10-11Minneapolis RiverCurrent 11-10-11
Minneapolis RiverCurrent 11-10-11
 
1100 2nd St S RFP_2010 2
1100 2nd St S RFP_2010 21100 2nd St S RFP_2010 2
1100 2nd St S RFP_2010 2
 
DMNA November Board Meeting Agenda 11-8-11
DMNA November Board Meeting Agenda 11-8-11DMNA November Board Meeting Agenda 11-8-11
DMNA November Board Meeting Agenda 11-8-11
 
Minneapolis RiverCurrent 11-3-11
Minneapolis RiverCurrent 11-3-11Minneapolis RiverCurrent 11-3-11
Minneapolis RiverCurrent 11-3-11
 
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...
WORKING TOGETHER TO ACHIEVE HEALTHY WATERS - Environmental Initiative Policy ...
 
Chute Square Park Press Release 102711
Chute Square Park Press Release 102711Chute Square Park Press Release 102711
Chute Square Park Press Release 102711
 
Minneapolis RiverCurrent 10-28-11
Minneapolis RiverCurrent 10-28-11Minneapolis RiverCurrent 10-28-11
Minneapolis RiverCurrent 10-28-11
 
Minneapolis RiverCurrent 10-19-11
Minneapolis RiverCurrent 10-19-11Minneapolis RiverCurrent 10-19-11
Minneapolis RiverCurrent 10-19-11
 
East Downtown Council Job Posting for Executive Assistant
East Downtown Council Job Posting for Executive AssistantEast Downtown Council Job Posting for Executive Assistant
East Downtown Council Job Posting for Executive Assistant
 
Minneapolis RiverCurrent 10-13-11
Minneapolis RiverCurrent 10-13-11Minneapolis RiverCurrent 10-13-11
Minneapolis RiverCurrent 10-13-11
 
Vikings Stadium Proposal Risk Analysis Report
Vikings Stadium Proposal Risk Analysis ReportVikings Stadium Proposal Risk Analysis Report
Vikings Stadium Proposal Risk Analysis Report
 
Third Ward NeighborhoodFest 2011
Third Ward NeighborhoodFest 2011Third Ward NeighborhoodFest 2011
Third Ward NeighborhoodFest 2011
 
DMNA Annual Meeting Agenda 10-11-11
DMNA Annual Meeting Agenda 10-11-11DMNA Annual Meeting Agenda 10-11-11
DMNA Annual Meeting Agenda 10-11-11
 
Minneapolis RiverCurrent 10-6-11
Minneapolis RiverCurrent 10-6-11Minneapolis RiverCurrent 10-6-11
Minneapolis RiverCurrent 10-6-11
 
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...
Resolution Adopting Amended Chapter 11 of the Minneapolis Park and Recreation...
 
Minneapolis RiverCurrent 9-29-11
Minneapolis RiverCurrent 9-29-11Minneapolis RiverCurrent 9-29-11
Minneapolis RiverCurrent 9-29-11
 
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011Above the Falls Policy Review and Implementation Study Presentation 9-27-2011
Above the Falls Policy Review and Implementation Study Presentation 9-27-2011
 
Minneapolis RiverCurrent 9-22-11
Minneapolis RiverCurrent 9-22-11Minneapolis RiverCurrent 9-22-11
Minneapolis RiverCurrent 9-22-11
 

Último

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524najka9823
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdfShaun Heinrichs
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfRbc Rbcua
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Pereraictsugar
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyotictsugar
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Seta Wicaksana
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationAnamaria Contreras
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 

Último (20)

Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR8447779800, Low rate Call girls in Dwarka mor Delhi NCR
8447779800, Low rate Call girls in Dwarka mor Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524Call Girls Contact Number Andheri 9920874524
Call Girls Contact Number Andheri 9920874524
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf1911 Gold Corporate Presentation Apr 2024.pdf
1911 Gold Corporate Presentation Apr 2024.pdf
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
APRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdfAPRIL2024_UKRAINE_xml_0000000000000 .pdf
APRIL2024_UKRAINE_xml_0000000000000 .pdf
 
Kenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith PereraKenya Coconut Production Presentation by Dr. Lalith Perera
Kenya Coconut Production Presentation by Dr. Lalith Perera
 
Investment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy CheruiyotInvestment in The Coconut Industry by Nancy Cheruiyot
Investment in The Coconut Industry by Nancy Cheruiyot
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...Ten Organizational Design Models to align structure and operations to busines...
Ten Organizational Design Models to align structure and operations to busines...
 
PSCC - Capability Statement Presentation
PSCC - Capability Statement PresentationPSCC - Capability Statement Presentation
PSCC - Capability Statement Presentation
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 

Washburn Crosby Elevator 1 Preservation Project

  • 1. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division Certificate of Appropriateness BZH-26933 Date: July 26, 2011 Proposal: Request for COA to complete preservation and stabilization work Applicant: Historic Sites and Museums, Minnesota Historical Society, Sarah Beimers, Senior Project Manager, 651-259-3474 Address of Property: 104 8th Avenue South Project Name: Washburn Crosby Elevator No. 1 Exterior Preservation Contact Person and Phone: Todd Grover, (612) 341-4051 Planning Staff and Phone: Aaron Hanauer, (612) 673-2494 Date Application Deemed Complete: July 11, 2011 Publication Date: July 19, 2011 Public Hearing: July 26, 2011 Appeal Period Expiration: August 5, 2011 Ward: 7 Neighborhood Organization: Downtown East 1
  • 2. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division Attachments: Attachment A: Materials submitted by CPED- (A1-A8) • A1: Zoning Map • A2: Saint Anthony Falls Historic District Map • A3-A4: Historic Images • A5-A8: Aerials Attachment B: Materials submitted by Applicant– (B1-B27) • B1: Council Member Communication • B2: Neighborhood Association Communication • B3-B5: Certificate of Appropriateness Application Form • B6-B7: Project Description • B8: Statement to Required Findings • B9-B15.1: Images • B15.2-B15.5: Elevations Showing Existing Conditions • B15.6-B15.12: Proposed Roof Decking Material • B16-B27: Plan Set 2
  • 3. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division Washburn Crosby Elevator Number 1, 1911, Source: Minnesota Historical Society 3
  • 4. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division Washburn Crosby Elevator Number 1, 2011, Source: MacDonald and Mack Architects 4
  • 5. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division CLASSIFICATION: Local Historic Saint Anthony Falls Historic District District Period of 1858-1940 Significance Criteria of Architecture and Social Significance significance Date of local 1971 designation Applicable Design Saint Anthony Falls Historic District Guidelines Guidelines Secretary of Interior Standards for Treatment of Historic Properties PROPERTY INFORMATION Current name Washburn Crosby Elevator Number 1 Historic Name Washburn Crosby Elevator Number 1 Current Address 104 8th Avenue South Historic Address 721-729 1st Street South Original 1906-1908 Construction Date Original Contractor Haglin Stahr Company Historic Use Grain Storage Current Use Vacant Proposed Use Stabilization 5
  • 6. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division BACKGROUND: Historic Background Washburn Crosby Elevator No.1 was constructed in 1906-08 by the Haglin Stahr Company and built east of the Washburn ''A'' Mill. It was one of the first large scale concrete grain storage facilities to be built in the country with exposed circular bin construction. It is also an early example of a continuous pour, slip form construction. Slip form construction is the use of a mold that is pulled or raised as concrete is placed. This type of construction, developed by Charles Haglin, spurred the massive construction efforts of these elevators across the country. The Washburn “A” Mill Complex is one of three national historic landmarks in the City of Minneapolis (the Pillsbury A Mill and Christ Church Lutheran are the other two). Elevator Number One is comprised of 15 cylindrical bins, arranged in three rows of five (Attachment B16). The plan is approximately 125 feet by 79 feet and the bins rise to 112 feet in height. The Headhouse extends another 95 feet above the bins. The reinforced concrete foundation extends 34 feet below grade. The walls of the bins are of reinforced concrete and vary from 9 to 10 inches thick. The roof of the bins is a reinforced concrete slab that appears to form part of the support for the Headhouse. Two Gold Medal Flour signs are attached to the headhouse. Application Background A structural assessment of the grain elevator roof was completed in 2010 after substantial pieces of concrete were falling from the underside of the roof. The scope of the 2010 structural assessment was expanded to the headhouse to analyze the connection between the bin roof and the headhouse. The structural assessment summary concluded the following: • The exterior walls of the bins are in good condition. There are selective and isolated areas that are in need of repair, but there are no major or immediate issues regarding the bins. • The roof of the bins is in extremely poor shape and has failed. The roof cannot be repaired as the accelerated deterioration of the concrete has mitigated its structural capacity. This roof can no longer be used in its current condition and must be replaced. Temporary protection methods may be utilized to prevent a safety hazard of the deteriorated elements. • Primary and intermediate roofs on the headhouse are in good condition, with isolated areas of repair. • Aside from the primary roof of the headhouse, all built-up roofing is in poor condition. The roofing should be removed and replaced. There are isolated areas on the bin walls and headhouse walls that need repair to the spalling concrete due to shale or shallow rebar deterioration. • There are isolated areas of significant water infiltration of the concrete roof/walls where the concrete should be removed and replaced. 6
  • 7. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division SUMMARY OF APPLICANT’S PROPOSAL The Applicant states that their work falls into three types of work 1. repairing of historic materials and features, 2. limited replacement in kind of extensively deteriorated portions of historic features, 3. stabilization of deteriorated historic materials and features (Attachment B6). Specifically, there are six parts to their scope of work: 1. concrete repair: On the exterior of Elevator No. 1 and Headhouse there are numerous areas where concrete is deteriorating, cracking and spalling (Attachment B15.2-B15-5 and B19-B19.4 and B28-B31 drawings). The cracking is typically at cold joints that have had water infiltration. The spalling is typically due to shallow rebar placement and shale aggregate in the concrete mix. The Minnesota Historical Society (MHS) proposes to repair the areas where it is deteriorated by removing corrosive and loose concrete and applying a concrete patch that will match the surface profile of surrounding concrete (Attachment B26, Drawing 3). Large cracks (greater than 1/16” of an inch), are proposed to be filled and then cleaned up to have the surface of the crack be flush with the outside of the surrounding area (Attachment B26, Drawing 4). Included in the scope of concrete repair is the rebuilding of the west parapet that has a significant amount of concrete deterioration (Attachment B15, 15.1, B21, and B26). The Applicant is proposing to remove deteriorated concrete down to stable material. Then rebuild the parapet to match the height and profile of the original and east parapet. 2. parging installation: The exterior of Elevator Number 1 is covered by a cement parging. Parging is a thin, paintable mixture of cement, sand, and colorant that provides a protective and breathable surface to the concrete (see Attachment B10 for historic image showing the application of the parging and Attachment B14 showing parging deterioration). The areas where the parging has deteriorated, accelerated carbonation and water penetration into the concrete has been identified. The MHS is proposing to scrape off the old parging and replace with a new parging to match original in areas where concrete is repaired or where the parging is missing (Attachment B15.2-B15.5 for existing conditions and B19-19.4 for proposed work). The new parging will be noticeably different for approximately ten years, until it weatherizes and blends in with the original parging. 3. bin roof replacement: The Applicant states that the bin roof is failing, cannot be repaired, and needs to be replaced (Attachment B9, B10, B12, B13). The Applicant’s structural analysis confirms this analysis: “The cores [of the bin roof] were not in good condition; none of them had enough integrity to provide a strength test. Thus, the concrete strength in the roof is variable and low. Petrographic analysis of these cores showed bleedwater voids, indicative of a high water-to-cement ratio during construction as well as freeze-thaw damage. Both of these contribute to low initial and remaining strength. Finally, on the west side adjacent to the Feed Elevator, there is a visible sag in the roof that appears to be about two feet.” The bin roof slab was poured monolithically and is approximately 6 inches thick. The Applicant states that a replacement roof will require a new roof using pre-cast planks on new steel structure members (Attachment B17 for bin roof plan and B19-B19.4 for elevations). 7
  • 8. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division The goal of the roof replacement is to match, as closely as possible, the details and dimensions of the original construction. The Applicant states that “The pre-cast planks were chosen because of the difficulty with installing site-cast concrete where the forms for the roof will be inaccessible after the concrete pour because there is no access to the underside of the roof inside the bins. The Applicant also adds that, “Typically pre-cast planks are smooth with a champher at the plank joint and do not visually replicate site-cast concrete. The specified pre-cast planks for this project are going to be custom wet-cast planks that will have a board formed bottom and square edge sides. This will ensure that the view from the ground will replicate the site-cast concrete of the original and the joints will be imperceptible. The details at the edge of the roof, including the profiles of the steel channel and copper flashing profile, will match the original (Attachment B7).” After the installation of the new roof, the Applicant proposes to reinstall the metal bins that sit on top of the roof (Attachment B9 and B17). 4. Additional Roofing: The headhouse contains multiple roofs (Attachment B17-B18, B22). The roofs are concrete roofs that have had asphalt applied to them over the years. The roofs, except for the uppermost head house roof, are failing (Attachment B13). MHS is proposing to remove all asphalt roofing, except for the head house roof, make concrete repairs to these roof decks, and install a cold fluid applied waterproofing (Attachment B15.6- B15.12 for details). The Applicant states that this is a material that is typically used on the top of parking decks. The Applicant also states that advantage of this material is that it is durable, will not degrade in sunlight, as asphalt does, and it comes in colors that can replicate the original concrete roof appearance. 5. Infill of doors: There are three door openings on the southwest elevation of the building that allowed equipment and materials to be brought to the upper floors (Attachment B10, B14, B19.1 and page 4 of staff report). Two of these openings have missing doors. MHS proposed to install temporary frame walls with a painted plywood panel in the recessed opening to prevent water and vermin intrusion into the buildings (Attachment B21). 6. Covering of windows: The building has numerous steel sash windows on each elevation. Many of them are broken and deteriorating because they are exposed to the elements. The open windows also allow water to penetrate the enclosure where accelerated deterioration of the concrete around the open windows can be seen. MHS proposes to install a painted steel plate on the exterior of the window opening that will overlap the exterior wall by three inches to protect the windows from further deterioration and also prevent water from entering the building (Attachment B21, Drawing 8, Window enclosure plan and section detail). The Applicant states that many windows have the potential to be rehabilitated, but this work cannot be done at this time. This measure will provide the protection from the elements to reduce further deterioration of the window sashes and surrounding concrete so that future rehabilitation, to the greatest extent possible, can be accomplished. This detail does not require any mechanical fastening of the cover to concrete, thus preserving the integrity of the wall surrounding the window. 7. Gold Metal Flour sign mounting points: The Applicant is proposing to analyze the caulking of the Gold Metal Flour sign for security (Attachment B14.1-B14.2). If additional work is needed the Applicant will notify CPED Preservation and Design staff. 8
  • 9. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division PUBLIC COMMENT: Public notices for the Certificate of Appropriateness were mailed on Tuesday, July 14, 2011. As of July 19, 2011 no letters have been received. 9
  • 10. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division CETIFICATE OF APPROPRIATENESS: Certificate of Appropriateness to rehabilitate the U U steel fence as part of Phase I of the fence restoration project. Findings as required by the Minneapolis Preservation Code: The Planning Division of the Minneapolis Community Planning and Economic Development Department has analyzed the application based on the findings required by the Minneapolis Preservation Ordinance. Before approving a certificate of appropriateness, and based upon the evidence presented in each application submitted, the commission shall make findings based upon, but not limited to, the following: (1) The alteration is compatible with and continues to support the criteria of significance and period of significance for which the landmark or historic district was designated. CPED believes the proposed preservation, stabilization, and limited replacement in kind work is compatible with and continues to support the criteria of significance and period of significance for which the Washburn A Mill Complex is a National Historic Landmark and contributing building(s) to the Saint Anthony Falls Historic District. The Washburn A Mill Complex is significant as a national historic landmark because it as an example of a radical transformation of the flour milling industry in the late 19th and early 20th centuries that made it a modern mass-production industry. The Washburn A Mill (1874) is the only structure that remains from the original Minneapolis milling complex established by Cadwallader C. Washburn. The Washburn Crosby Elevator No. 1 is part of the milling complex that represents an important part of the nation and Minneapolis’ flour milling history as it is one of the first grain elevators in the United States to be built in an exposed circular bin construction style. (2) The alteration is compatible with and supports the interior and/or exterior designation in which the property was designated. CPED believes the proposed preservation, stabilization, and limited replacement in kind work is compatible with and continues to support the exterior designation in which the property was designated. The proposed work will help preserve the integrity of the landmark by making necessary repairs and stabilizing the condition of the elevators. (3) The alteration is compatible with and will ensure continued integrity of the landmark or historic district for which the district was designated. The Applicant has demonstrated that the items proposed to be replaced are beyond repair, and that their proposed preservation and stabilization work will preserve and strengthen the historic fabric of the grain elevators. CPED believes the proposed preservation, stabilization, and limited replacement in kind work is compatible with and will ensure continued integrity of the Washburn Crosby 10
  • 11. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division Elevator No. 1. The goal of the proposed work is to preserve the integrity of the landmark by stabilizing/rehabilitating the historic fabric of the elevators, and only replacing material that is beyond repair. (4) The alteration will not materially impair the significance and integrity of the landmark, historic district or nominated property under interim protection as evidenced by the consistency of alterations with the applicable design guidelines adopted by the commission. The Saint Anthony Falls Historic District Guidelines were adopted in 1980. The subject property is located in Subdistrict E, Right (West) Bank Milling Subdistrict. As the Saint Anthony Falls Historic District Guideline’s general purpose states, “these regulations apply to any and all new construction and rehabilitation of existing buildings and structures within the St. Anthony Falls Historic District.” The guidelines do not have specific guidelines for the preservation and rehabilitation of a property. However, among the purposes of the guidelines is to, “preserve the memory of past events.” The Applicant’s proposal to complete repair, limited replacement in kind of extensively deteriorated portions of historic features, and stabilizing deteriorated historic materials and features is consistent with the general purpose of the Saint Anthony Falls Historic District Guidelines. (5) The alteration will not materially impair the significance and integrity of the landmark, historic district or nominated property under interim protection as evidenced by the consistency of alterations with the recommendations contained in The Secretary of the Interior's Standards for the Treatment of Historic Properties. CPED agrees with the Applicant that the proposed preservation plan is compatible with the Secretary of the Interior’s Standards for the Treatment of Historic Properties guidelines for Preserving Historic Buildings. Specifically, CPED believes that the proposed work is in compliance with the following Standards: Standard 3. Work needed to stabilize, consolidate, and conserve existing historic materials and features will be physically and visually compatible. Standard 6. The existing condition of historic features will be evaluated to determine the appropriate level of intervention needed. Where the severity of deterioration requires repair or limited replacement of a distinctive feature, the new material will match the old in composition, design, color, and texture. The Applicant has provided evidence that they are only replacing material which is beyond repair (grain elevator bin roof). The Applicant has also demonstrated that their proposal to improve the condition of the historic material (concrete) will be physically and visually compatible, and that they are taking measures to protect historic materials from 11
  • 12. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division further damage until a later date when they can be rehabilitated (window and door openings). (6) The certificate of appropriateness conforms to all applicable regulations of this preservation ordinance and is consistent with the applicable policies of the comprehensive plan and applicable preservation policies in small area plans adopted by the city council. CPED believes the Applicant’s proposed preservation plan will help preserve the Washburn Crosby Elevator No. 1 and is in compliance with Policy 8.1 of the Minneapolis Comprehensive Plan. Policy 8.1: Preserve, and maintain historic resources which serve as reminders of the city's architecture, history, and culture. (7) Destruction of any property. Before approving a certificate of appropriateness that involves the destruction, in whole or in part, of any landmark, property in an historic district or nominated property under interim protection, the commission shall make findings that the destruction is necessary to correct an unsafe or dangerous condition on the property, or that there are no reasonable alternatives to the destruction. In determining whether reasonable alternatives exist, the commission shall consider, but not be limited to, the significance of the property, the integrity of the property and the economic value or usefulness of the existing structure, including its current use, costs of renovation and feasible alternative uses. The commission may delay a final decision for a reasonable period of time to allow parties interested in preserving the property a reasonable opportunity to act to protect it. The project does not constitute the destruction of the subject property. Before approving a certificate of appropriateness, and based upon the evidence presented in each application submitted, the commission shall make findings that alterations are proposed in a manner that demonstrates that the applicant has made adequate consideration of the following documents and regulations: (8) Adequate consideration of the description and statement of significance in the original nomination upon which designation of the landmark or historic district was based. CPED believes the Applicant gave adequate consideration of the description and statement of significance in the original nomination upon which the designation of the Saint Anthony Falls Historic District took place. To guide the work, the Applicant reviewed two previous studies to aid in the ongoing preservation and building maintenance: Elevator Assessment by BKBM Professional Engineers in 2000, and the Washburn Grain Elevator Complex Reuse Study by Thomas R. Zahn and Miller Dunwiddie Architects in 2007. In addition, the Applicant completed additional research looking for original drawings and information that would provide guidance for the preservation of this important Saint Anthony Falls Historic District landmark. 12
  • 13. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division (9) Where applicable, Adequate consideration of Title 20 of the Minneapolis Code of Ordinances, Zoning Code, Chapter 530, Site Plan Review. The CPED-Development Services or CPED-Zoning Team will review the proposed plans to ensure compliance with the Minneapolis Zoning Code. (10) The typology of treatments delineated in the Secretary of the Interior's Standards for the Treatment of Historic Properties and the associated guidelines for preserving, rehabilitating, reconstructing, and restoring historic buildings. For the Washburn Crosby Elevator No. 1 project, the Applicant has proposed to follow the Secretary of the Interior’s Standards for Preserving Historic Buildings. 13
  • 14. Posted by http://MillCityTimes.com Department of Community Planning and Economic Development Planning Division STAFF RECOMMENDATION CPED-Planning staff recommends that the Heritage Preservation Commission adopt staff findings and approve the Certificate of Appropriateness with the following condition(s): 1) For the Gold Medal Flour, any work beyond the condition analysis shall be reviewed by CPED-Planning Preservation Staff. 2) CPED-Planning Preservation Staff shall review and approve the final plans and elevations prior to building permit issuance. 3) The Certificate of Appropriateness approval shall expire if it is not acted upon within one year of approval, unless extended by the Planning Director in writing prior to one-year anniversary date of approvals. 4) By ordinance, all approvals granted in this Certificate of Appropriateness shall remain in effect as long as all of the conditions and guarantees of such approvals are observed. Failure to comply with such conditions and guarantees shall constitute a violation of this Certificate of Appropriateness and may result in termination of the approval. 14