Presentation - Case Study on Site Investigation Plan at Chek.pptx
Project 4 Presentation
1. PROJECT 4: REVIEW OF BLAKELY
MOUNTAIN DAM, ARKANSAS
CE 6313: DESIGN OF EARTH DAMS
Group 1
Mohammad Faysal, Yohannes Okubay & Asif Ahmed
2. Project Description
Review of Existing Design parameters
Seepage flow analysis by flow net
Flow analysis in Plaxis
Slope stability analysis in Plaxis
Dam Settlement Analysis
Construction Plan and compaction methodology
Dam instrumentation and Monitoring
Outline
3. Blackly Mountain Dam located in Arkansas
1200 ft long and 230 ft high earth dam
Constructed between 1950to 1952
Purpose of the dam flood control and hydropower
Drainage area of 1105 sq.mi
Has two tunnels one for power intake and one for flood
control
Blakely Dam
Project Description
6. Review of Existing Design parameters
Soil Type Soil Classification
Impervious (I and II) Salty Clay , Sandy clay (I); clay sand , and clay
silt(II)
Fine random (III and V-a) Sandy silt , silty sand, and sand with more than
5 % finer than No.200 sieve (III); or a
combination of soil types I , II and or III where
individual soil strata are less than about 3 ft.
thick , containing more than 15 % finer than the
no.200 sieve and about 50 % or less gravel (V-
a).
Coarse random (V-b) A material with less than 15% finer than No.200
sieve and about 50% or more gravel.
Pervious (IV) Sand and /or gravel (less than 5% finer than the
no.200 sieve and or free drainage).
Borrow Materials
13. Task 3: Stability Analysis using PLAXIS (After Construction)
After Construction
Water Table at elev. = 380 ft,
F.S. = 1.73
Rapid Draw Down
Water Table at elev. = 610 to 480 ft,
Time Interval = 0.5 day (Assume)
F.S. = 1.19
14. Task 3: Stability Analysis using PLAXIS (After Construction)
Steady State
Water Table at elev. = 592 ft,
F.S. = 1.55
Condition
Water
Elev. (ft)
Critical
Location
FS (Report)
Critical
Slope
Plaxis
FS
(PLAXI
S)
Reqd. F.S.
Remark
s
After
Constructio
n (No
Seepage)
380 D/S 1.79 D/S 1.73 1.25 Stable
Steady State
Seepage
592 D/S 1.77 D/S 1.55 1.5 Stable
Rapid
Drawdown
610 - 480 U/S 1 U/S 1.19 1.00 Stable
15. Task 3: Stability Analysis using PLAXIS (After Construction)
Condition
Water
Elev. (ft)
Critical
Location
FS (Report)
Critical
Slope
Plaxis
FS
(PLAXIS
)
Reqd.
F.S.
Remark
s
After
Constructio
n (No
Seepage)
380 D/S 1.79 D/S 1.73 1.25 Stable
Steady State
Seepage
592 D/S 1.77 D/S 1.55 1.5 Stable
Rapid
Drawdown
610 - 480 U/S 1 U/S 1.19 1.00 Stable
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
After Construction (No Seepage) Steady State Seepage Rapid Drawdown
FactorofSafety
Factor of Safety Comparison
Circular Arc Method PLAXIS
20. Settlement using Parabolic Equation
S = (γw/E)(h-y)y
where,
S= settlement of a point within the dam
h= height of dam
y= amount of fill beneath the point of interest
E= 1-D secant modulus to a stress level equivalent to the mid height of dam
22. Comparison of Settlement
Method 1-D Analysis
Parabolic
Equation
Estimated
in Design
Phase
Settlement
Plate
Value
9.82 ft 7.21 ft 8 ft 6.5-7 ft
23. Cracking Potential
Cracking Potential
(u/s)
Cracking Potential
(d/s)
H (ft)= 230 230
β= 18.33 21.8
Max Post Construction
Settlement (ft) =
2.287 2.287
Cracking Potential=
Max Post Cons
Settlement/Hcotβ
Max Post Cons
Settlement/Hcotβ
=0.003294268 =0.003977108
Emery, 2011
27. Description of Test Fill
Type of
Soil
Type II, Type III
Roller
Weight
2800 lb/ft
Tamping
Feet Area
7 sq Inch, 14 sq inch
Pressure
Intensity
600 psi, 300 psi
Number
of Passes
6,12,24
Moisture
Content
2% wet, 2% dry of
optimum
Section
Lift
Five 6 inch lift
35. Summary
300 psi roller produced about 2 to 4 pcf greater density than the 600 psi roller
Little gain in density beyond 6-8 passes
300 psi, 6 passes, 6 inch lift, 1.5% dry to 1.5% wet of the optimum
40. Roller
Name Suitability Pressure
Sheepsfoot Fine grained soil 150-400 psi
Ruuber tire Coarse grained soil 60-80 psi
Smooth wheel roller Subgrade, fine grained soil High Pressure
Vibrating roller Coarse grained soil -
Sheepsfoot Roller, 60 inch dia, 14 sq inch tamping foot
41. Summary of Compaction
Zone
Compacte
d Layer
Thickness
Compaction
Equipment
Foot pressure
used (psi)
Number of
Passes
Fine
Material
6 Sheepsfoot Roller 300 6
Relatively
Pervious
Zone
12 Crawler Tractor 6-1/2 3
Filter
Blanket
18 Crawler Tractor 6-1/2 3
42. The purpose of instrumentation and monitoring is to maintain and improve
dam safety by providing information to evaluate dam performance (as
expected) and warn of changes that could endanger the safety of a dam.
Common causes of earth dam failures are
Task 6: Dam Instrumentation
43.
44. Overtopping
Seepage and Piping
Uplift failure
Deformation
Settlement
Common causes of earth dam failures
45. 6 foundation 33 embankment piezometers
1 Settlement measuring apparatus ( consolidation )
3 Nos. 12- in out let drains to measure seepage
Observation wells
Rubber ball method
Evaluation of existing instrumentation of Blackly Dam
The existing instruments in the dam are working perfectly
47. Perfect performance of the dam according to its design for nearly 63
years for seepage , Slope stability and consolidation are with in the
design limit
Since the installed instruments are performing well , they need to be
maintained properly
With availability of technology its recommended to automate the data
acquisition process to reflect the real time scenario
Proposed Instrumentation