SlideShare a Scribd company logo
1 of 49
Download to read offline
PROJECT 4: REVIEW OF BLAKELY
MOUNTAIN DAM, ARKANSAS
CE 6313: DESIGN OF EARTH DAMS
Group 1
Mohammad Faysal, Yohannes Okubay & Asif Ahmed
 Project Description
 Review of Existing Design parameters
 Seepage flow analysis by flow net
 Flow analysis in Plaxis
 Slope stability analysis in Plaxis
 Dam Settlement Analysis
 Construction Plan and compaction methodology
 Dam instrumentation and Monitoring
Outline
 Blackly Mountain Dam located in Arkansas
 1200 ft long and 230 ft high earth dam
 Constructed between 1950to 1952
 Purpose of the dam flood control and hydropower
 Drainage area of 1105 sq.mi
 Has two tunnels one for power intake and one for flood
control
Blakely Dam
Project Description
Plan and Zonation of Dam
Borrow Area
6,687,000 cu yd
>3,800,000 cu yd
Review of Existing Design parameters
Soil Type Soil Classification
Impervious (I and II) Salty Clay , Sandy clay (I); clay sand , and clay
silt(II)
Fine random (III and V-a) Sandy silt , silty sand, and sand with more than
5 % finer than No.200 sieve (III); or a
combination of soil types I , II and or III where
individual soil strata are less than about 3 ft.
thick , containing more than 15 % finer than the
no.200 sieve and about 50 % or less gravel (V-
a).
Coarse random (V-b) A material with less than 15% finer than No.200
sieve and about 50% or more gravel.
Pervious (IV) Sand and /or gravel (less than 5% finer than the
no.200 sieve and or free drainage).
Borrow Materials
Design shear strength for mix 1, 2 and 3 Design curves for QT, QcT and DS
Task 2: Seepage Analysis
Two Methods:
 Flow net
 Impervious Foundation
 Pervious Foundation
 Plax Flow (FEM method using PLAXIS)
 Impervious Foundation
 Pervious Foundation Soil type
Qc Test
ϒm (pcf) ϒsat (pcf)
Permeability, k
(ft/day)
Elastic
Modul
us, E
(psf)
C (psf) ф ( ᵒ ) Kh Kv
Type I & II 700 25 131 135 0.06
6.91E-
03
1.04E+
06
Type III &
Va
700 25 131 135 0.0124
1.38E-
03
2.00E+
05
Type Vb 700 25 131 135
2.77E-
03
2.77E-
03
1.05E+
06
Type IV 0 35 131 135 0.138 0.138
1.05E+
06
Rock 16000 10 169 178 1.38 1.38
2.80E+
08
Gravel-
Sand 0 35 109 121 276.48 276.48
1.46E+
06
Task 2: Seepage Analysis
 Flow net
 Impervious Foundation
 Pervious Foundation
Task 2: Seepage Analysis
 Plax Flow (FEM method using PLAXIS)
 Impervious Foundation
 Pervious Foundation
Condition
Water
Elev. (ft)
Embankment
seepage,
gpd/ft
(Flownet)
Total Seepage,
gpd (Flow net)
Embankment
seepage,
gpd/ft (Plaxis)
Total
Seepage,
gpd
Steady State 592 0.48 350 3.51 2106
0
0.5
1
1.5
2
2.5
3
3.5
4
FlowVolume(gpd/ft)
Flow Net Plax Flow
Task 2: Seepage Analysis
 Plax Flow (FEM method using PLAXIS)
 Pervious Foundation
955
960
965
970
975
980
985
FlowVolume(gpd/ft)
Flow Net Plax Flow
Total Seepage Volume (per foot)
Condition
Water
Elev. (ft)
Total
seepage,
gpd/ft
(Flownet)
Total
Seepage, gpd
(Flow net)
Total
seepage,
gpd/ft
(Plaxis)
Total
Seepage,
gpd
Steady
State
592 965 580000 982 589200
Task 3: Stability Analysis (Circular Arc Method)
Task 3: Stability Analysis using PLAXIS (After Construction)
After Construction
Water Table at elev. = 380 ft,
F.S. = 1.73
Rapid Draw Down
Water Table at elev. = 610 to 480 ft,
Time Interval = 0.5 day (Assume)
F.S. = 1.19
Task 3: Stability Analysis using PLAXIS (After Construction)
Steady State
Water Table at elev. = 592 ft,
F.S. = 1.55
Condition
Water
Elev. (ft)
Critical
Location
FS (Report)
Critical
Slope
Plaxis
FS
(PLAXI
S)
Reqd. F.S.
Remark
s
After
Constructio
n (No
Seepage)
380 D/S 1.79 D/S 1.73 1.25 Stable
Steady State
Seepage
592 D/S 1.77 D/S 1.55 1.5 Stable
Rapid
Drawdown
610 - 480 U/S 1 U/S 1.19 1.00 Stable
Task 3: Stability Analysis using PLAXIS (After Construction)
Condition
Water
Elev. (ft)
Critical
Location
FS (Report)
Critical
Slope
Plaxis
FS
(PLAXIS
)
Reqd.
F.S.
Remark
s
After
Constructio
n (No
Seepage)
380 D/S 1.79 D/S 1.73 1.25 Stable
Steady State
Seepage
592 D/S 1.77 D/S 1.55 1.5 Stable
Rapid
Drawdown
610 - 480 U/S 1 U/S 1.19 1.00 Stable
0
0.2
0.4
0.6
0.8
1
1.2
1.4
1.6
1.8
2
After Construction (No Seepage) Steady State Seepage Rapid Drawdown
FactorofSafety
Factor of Safety Comparison
Circular Arc Method PLAXIS
Uplift Pressure
Task 4: Settlement
 Foundation Settlement
 Embankment Settlement
Settlement using 1-D analysis
εa= γd(ωc/γ)(1/Ds -1)*100
γd= 116 pcf
ωc= 0.136
e0= 0.428
Gs= 2.65
Ds= 0.842056075
γ 62.4 pcf
εa= 4.742138365 %
LayerNo Layer
Thicknes
s (ft)
Unit
Weight of
Soil (pcf)
Average
Stress
(psf)
Average
Stress
(tsf)
Void
Ratio,e
Vertical
Strain
TotalCompressioninLayer
(ft)
TotalCompressionbelow
TopLayer
CompressionofLayer
DuringConstruction
Compressionbelowtop
layerduringconstruction
PostConstruction
CompressionofLayer
Compressionpriorto
reachinglayertop
TotalSettlement
Settlementduring
Construction
PostConstruction
Settlement
1 23 135 1506.5 0.75325 0.402 1.8207283 0.418768 12.11204 0.418768 9.82493 0 9.82493 2.287115 0 2.287115
2 23 135 4611.5 2.30575 0.378 3.5014006 0.805322 11.69328 0.805322 9.406162 0 8.72969 2.963585 0.676471 2.287115
3 23 135 7716.5 3.85825 0.37 4.0616246 0.934174 10.88796 0.934174 8.60084 0 7.63445 3.253501 0.966387 2.287115
4 23 135 10821.5 5.41075 0.36 4.7619048 1.095238 9.953782 1.095238 7.666667 0 6.53922 3.414566 1.127451 2.287115
5 23 135 13926.5 6.96325 0.354 5.1820728 1.191877 8.858543 1.095238 6.571429 0.096639 5.44398 3.414566 1.127451 2.287115
6 23 135 17031.5 8.51575 0.345 5.8123249 1.336835 7.666667 1.095238 5.47619 0.241597 4.34874 3.317927 1.127451 2.190476
7 23 135 20136.5 10.06825 0.339 6.232493 1.433473 6.329832 1.095238 4.380952 0.338235 3.2535 3.076331 1.127451 1.94888
8 23 135 23241.5 11.62075 0.33 6.8627451 1.578431 4.896359 1.095238 3.285714 0.483193 2.15826 2.738095 1.127451 1.610644
9 23 135 26346.5 13.17325 0.327 7.0728291 1.626751 3.317927 1.095238 2.190476 0.531513 1.22409 2.093838 0.966387 1.127451
10 23 135 29451.5 14.72575 0.323 7.3529412 1.691176 1.691176 1.095238 1.095238 0.595938 0.41877 1.272409 0.676471 0.595938
12.11204 9.82493
Settlement using Parabolic Equation
 S = (γw/E)(h-y)y
 where,
 S= settlement of a point within the dam
 h= height of dam
 y= amount of fill beneath the point of interest
 E= 1-D secant modulus to a stress level equivalent to the mid height of dam
Settlement using Parabolic Equation
Fill Height
beneath point
"y" (ft)
γw
(pcf)
Heigh
t of
Dam,
ft
E50
Settleme
nt, S (ft)
230 131 230 240000 0
207 131 230 240000 2.5987125
184 131 230 240000 4.6199333
161 131 230 240000 6.0636625
138 131 230 240000 6.9299
115 131 230 240000 7.2186458
92 131 230 240000 6.9299
69 131 230 240000 6.0636625
46 131 230 240000 4.6199333
23 131 230 240000 2.5987125
0 131 230 240000 0
E50= 12000/0.05 = 240000 psf
5% strain rate
Comparison of Settlement
Method 1-D Analysis
Parabolic
Equation
Estimated
in Design
Phase
Settlement
Plate
Value
9.82 ft 7.21 ft 8 ft 6.5-7 ft
Cracking Potential
Cracking Potential
(u/s)
Cracking Potential
(d/s)
H (ft)= 230 230
β= 18.33 21.8
Max Post Construction
Settlement (ft) =
2.287 2.287
Cracking Potential=
Max Post Cons
Settlement/Hcotβ
Max Post Cons
Settlement/Hcotβ
=0.003294268 =0.003977108
Emery, 2011
Camber Design
Dam
Statio
n
Embankment
Height
1
Percent
of
Height
Post construction
Foundation
Settlement
Cambe
r (ft)
0 0 0 0 0
1 47.33333333 0.47333 0 0.5
2 94.66666667 0.94667 0 1
3 142 1.42 0 1.5
4 189.3333333 1.89333 0 2
5 230 2.3 0 2.5
6 180.3 1.803 0 2
7 135.3 1.353 0 1.5
8 90.2 0.902 0 1
9 45.1 0.451 0 0.5
10 0 0 0 0
Task 5: Compaction (Test Fill)
 Standard Proctor Test
 Modified Proctor
New Waddell Dam, Arizona
Dam Section
Description of Test Fill
Type of
Soil
Type II, Type III
Roller
Weight
2800 lb/ft
Tamping
Feet Area
7 sq Inch, 14 sq inch
Pressure
Intensity
600 psi, 300 psi
Number
of Passes
6,12,24
Moisture
Content
2% wet, 2% dry of
optimum
Section
Lift
Five 6 inch lift
Result of Type II Soil
121
122
118
121.5
Result of Type II Soil
12.5%
Result of Type II Soil
Result of Type III Soil
121 121
119
120
Result of Type III Soil
11%
Result of Type III Soil
300 psi over 600 psi
Summary
 300 psi roller produced about 2 to 4 pcf greater density than the 600 psi roller
 Little gain in density beyond 6-8 passes
 300 psi, 6 passes, 6 inch lift, 1.5% dry to 1.5% wet of the optimum
Roller
Roller
Roller
Roller
Roller
Name Suitability Pressure
Sheepsfoot Fine grained soil 150-400 psi
Ruuber tire Coarse grained soil 60-80 psi
Smooth wheel roller Subgrade, fine grained soil High Pressure
Vibrating roller Coarse grained soil -
Sheepsfoot Roller, 60 inch dia, 14 sq inch tamping foot
Summary of Compaction
Zone
Compacte
d Layer
Thickness
Compaction
Equipment
Foot pressure
used (psi)
Number of
Passes
Fine
Material
6 Sheepsfoot Roller 300 6
Relatively
Pervious
Zone
12 Crawler Tractor 6-1/2 3
Filter
Blanket
18 Crawler Tractor 6-1/2 3
 The purpose of instrumentation and monitoring is to maintain and improve
dam safety by providing information to evaluate dam performance (as
expected) and warn of changes that could endanger the safety of a dam.
Common causes of earth dam failures are
Task 6: Dam Instrumentation
 Overtopping
 Seepage and Piping
 Uplift failure
 Deformation
 Settlement
Common causes of earth dam failures
 6 foundation 33 embankment piezometers
 1 Settlement measuring apparatus ( consolidation )
 3 Nos. 12- in out let drains to measure seepage
 Observation wells
 Rubber ball method
Evaluation of existing instrumentation of Blackly Dam
The existing instruments in the dam are working perfectly
Piezometer Data
 Perfect performance of the dam according to its design for nearly 63
years for seepage , Slope stability and consolidation are with in the
design limit
 Since the installed instruments are performing well , they need to be
maintained properly
 With availability of technology its recommended to automate the data
acquisition process to reflect the real time scenario
Proposed Instrumentation
Resistivity Imaging
56 Electrodes: 56*20 = 1120 ft (1120*0.2 = 224 ft)
40 ft
1200ft
H = 230 ft
THANK YOU

More Related Content

What's hot

Prediction of swelling pressure of expansive soils using compositional and
Prediction of  swelling pressure of expansive soils using compositional andPrediction of  swelling pressure of expansive soils using compositional and
Prediction of swelling pressure of expansive soils using compositional and
IAEME Publication
 

What's hot (20)

Soil compaction
Soil compactionSoil compaction
Soil compaction
 
Prediction of swelling pressure of expansive soils using compositional and
Prediction of  swelling pressure of expansive soils using compositional andPrediction of  swelling pressure of expansive soils using compositional and
Prediction of swelling pressure of expansive soils using compositional and
 
Unit3 hbn
Unit3 hbnUnit3 hbn
Unit3 hbn
 
ogee design
ogee designogee design
ogee design
 
Numerical modeling of concrete in Abaqus
Numerical modeling of concrete in Abaqus Numerical modeling of concrete in Abaqus
Numerical modeling of concrete in Abaqus
 
Dynamic Soil Properties
Dynamic Soil PropertiesDynamic Soil Properties
Dynamic Soil Properties
 
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)Geotechnical Engineering-II [Lec #3: Direct Shear Test)
Geotechnical Engineering-II [Lec #3: Direct Shear Test)
 
Ground improvement techniques
Ground improvement techniquesGround improvement techniques
Ground improvement techniques
 
Introduction to Soil mechanics
Introduction to Soil mechanicsIntroduction to Soil mechanics
Introduction to Soil mechanics
 
Analysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundationAnalysis of vertically loaded pile foundation
Analysis of vertically loaded pile foundation
 
Index properties, relationship & tests
Index properties, relationship & testsIndex properties, relationship & tests
Index properties, relationship & tests
 
Sachpazis: Slope Stability Analysis
Sachpazis: Slope Stability AnalysisSachpazis: Slope Stability Analysis
Sachpazis: Slope Stability Analysis
 
Class 7 Consolidation Test ( Geotechnical Engineering )
Class 7    Consolidation Test ( Geotechnical Engineering )Class 7    Consolidation Test ( Geotechnical Engineering )
Class 7 Consolidation Test ( Geotechnical Engineering )
 
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
 
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
Bearing capacity theory is code ,vesic ,hansen, meyerhof, skemptons( usefulse...
 
Lecture 2 bearing capacity
Lecture 2 bearing capacityLecture 2 bearing capacity
Lecture 2 bearing capacity
 
6 effective stress capillarity_permeability
6 effective stress capillarity_permeability6 effective stress capillarity_permeability
6 effective stress capillarity_permeability
 
Plaxis 3d tutorial manual
Plaxis 3d tutorial manualPlaxis 3d tutorial manual
Plaxis 3d tutorial manual
 
Bearing capacity of soil
Bearing capacity of soilBearing capacity of soil
Bearing capacity of soil
 
Shear strength of soils
Shear strength of soils Shear strength of soils
Shear strength of soils
 

Viewers also liked

2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
The Business Council of Mongolia
 
Kåre Rude Andersen - Be a hero – optimize scom and present your services
Kåre Rude Andersen - Be a hero – optimize scom and present your servicesKåre Rude Andersen - Be a hero – optimize scom and present your services
Kåre Rude Andersen - Be a hero – optimize scom and present your services
Nordic Infrastructure Conference
 
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
Nordic Infrastructure Conference
 

Viewers also liked (17)

Total Geometry
Total GeometryTotal Geometry
Total Geometry
 
The five biggest dams in india
The five biggest dams in indiaThe five biggest dams in india
The five biggest dams in india
 
TEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONSTEHRI DAM & ITS IMPLICATIONS
TEHRI DAM & ITS IMPLICATIONS
 
Dam safety & Safety Devices
Dam safety & Safety DevicesDam safety & Safety Devices
Dam safety & Safety Devices
 
Dam of india
Dam of indiaDam of india
Dam of india
 
презентация учнівського самоврядування15 16
презентация учнівського самоврядування15 16презентация учнівського самоврядування15 16
презентация учнівського самоврядування15 16
 
2013, REPORT, Real Estate Report 2013, Mongolian Properties
2013, REPORT, Real Estate Report 2013, Mongolian Properties2013, REPORT, Real Estate Report 2013, Mongolian Properties
2013, REPORT, Real Estate Report 2013, Mongolian Properties
 
04.01.2008, NEWSWIRE, Issue 10
04.01.2008, NEWSWIRE, Issue 1004.01.2008, NEWSWIRE, Issue 10
04.01.2008, NEWSWIRE, Issue 10
 
2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
2011, REPORT, Transition Report 2011 (full report), EBRD and the Economic Res...
 
Kåre Rude Andersen - Be a hero – optimize scom and present your services
Kåre Rude Andersen - Be a hero – optimize scom and present your servicesKåre Rude Andersen - Be a hero – optimize scom and present your services
Kåre Rude Andersen - Be a hero – optimize scom and present your services
 
Rpp bab kebersihan
Rpp bab kebersihanRpp bab kebersihan
Rpp bab kebersihan
 
Mike Resseler - Deduplication in windows server 2012 r2
Mike Resseler - Deduplication in windows server 2012 r2Mike Resseler - Deduplication in windows server 2012 r2
Mike Resseler - Deduplication in windows server 2012 r2
 
портфоліо душнюк лілія
портфоліо душнюк ліліяпортфоліо душнюк лілія
портфоліо душнюк лілія
 
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
Justin Morris - Enhancing your lync 2013 rollout to make it a killer success ...
 
Managerial economics
Managerial economicsManagerial economics
Managerial economics
 
Encouragers
EncouragersEncouragers
Encouragers
 
Las huellas del tiempo
Las huellas del tiempoLas huellas del tiempo
Las huellas del tiempo
 

Similar to Project 4 Presentation

Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Pagkratios Chitas
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)
Pagkratios Chitas
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpoint
neha47
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
Leo Youngman
 
Seismic cpt (scpt) peter robertson
Seismic cpt (scpt)   peter robertsonSeismic cpt (scpt)   peter robertson
Seismic cpt (scpt) peter robertson
cfpbolivia
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_al
Pankaj Gupta
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
Travis Smith
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKA
Keith Kong
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
olaboughannam1
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
olaboughannam1
 

Similar to Project 4 Presentation (20)

Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
Full Paper - Ratcheting Uplift of Buried Pipelines in Sand (P. Chitas)
 
Seismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway TunnelSeismic Capacity Assessment of Sanyi Old Railway Tunnel
Seismic Capacity Assessment of Sanyi Old Railway Tunnel
 
addition consideration in pile
addition consideration in pileaddition consideration in pile
addition consideration in pile
 
Applications of Vane Shear Test in Geotechnical soil investigations
Applications of Vane Shear Test in Geotechnical soil investigationsApplications of Vane Shear Test in Geotechnical soil investigations
Applications of Vane Shear Test in Geotechnical soil investigations
 
Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)Presentation (Pagkratios Chitas)
Presentation (Pagkratios Chitas)
 
Thesis Powerpoint
Thesis PowerpointThesis Powerpoint
Thesis Powerpoint
 
Analysis of Stone Column
Analysis of Stone ColumnAnalysis of Stone Column
Analysis of Stone Column
 
Spe yp monthly session hydraulic fracturing technology - april 2021
Spe yp monthly session   hydraulic fracturing technology - april 2021Spe yp monthly session   hydraulic fracturing technology - april 2021
Spe yp monthly session hydraulic fracturing technology - april 2021
 
Modeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft LoadingModeling of Flexible and Rigid Pavements under Aircraft Loading
Modeling of Flexible and Rigid Pavements under Aircraft Loading
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Seismic cpt (scpt) peter robertson
Seismic cpt (scpt)   peter robertsonSeismic cpt (scpt)   peter robertson
Seismic cpt (scpt) peter robertson
 
P07011_Gupta_et_al
P07011_Gupta_et_alP07011_Gupta_et_al
P07011_Gupta_et_al
 
DECOMVILLE (EL MUNDO PERDIDO DE KUMANNG)
DECOMVILLE (EL MUNDO PERDIDO DE KUMANNG)DECOMVILLE (EL MUNDO PERDIDO DE KUMANNG)
DECOMVILLE (EL MUNDO PERDIDO DE KUMANNG)
 
Reconsidering some basic aspects of soil mechanics - Laurie Wesley, Universit...
Reconsidering some basic aspects of soil mechanics - Laurie Wesley, Universit...Reconsidering some basic aspects of soil mechanics - Laurie Wesley, Universit...
Reconsidering some basic aspects of soil mechanics - Laurie Wesley, Universit...
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
 
Rock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKARock Mechanics and Rock Cavern Design_ICE HKA
Rock Mechanics and Rock Cavern Design_ICE HKA
 
1.0 Flyover 0+620.pdf
1.0 Flyover 0+620.pdf1.0 Flyover 0+620.pdf
1.0 Flyover 0+620.pdf
 
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
Geotechnical Engineering-II [Lec #28: Finite Slope Stability Analysis]
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
 
Presentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptxPresentation - Case Study on Site Investigation Plan at Chek.pptx
Presentation - Case Study on Site Investigation Plan at Chek.pptx
 

Project 4 Presentation

  • 1. PROJECT 4: REVIEW OF BLAKELY MOUNTAIN DAM, ARKANSAS CE 6313: DESIGN OF EARTH DAMS Group 1 Mohammad Faysal, Yohannes Okubay & Asif Ahmed
  • 2.  Project Description  Review of Existing Design parameters  Seepage flow analysis by flow net  Flow analysis in Plaxis  Slope stability analysis in Plaxis  Dam Settlement Analysis  Construction Plan and compaction methodology  Dam instrumentation and Monitoring Outline
  • 3.  Blackly Mountain Dam located in Arkansas  1200 ft long and 230 ft high earth dam  Constructed between 1950to 1952  Purpose of the dam flood control and hydropower  Drainage area of 1105 sq.mi  Has two tunnels one for power intake and one for flood control Blakely Dam Project Description
  • 5. Borrow Area 6,687,000 cu yd >3,800,000 cu yd
  • 6. Review of Existing Design parameters Soil Type Soil Classification Impervious (I and II) Salty Clay , Sandy clay (I); clay sand , and clay silt(II) Fine random (III and V-a) Sandy silt , silty sand, and sand with more than 5 % finer than No.200 sieve (III); or a combination of soil types I , II and or III where individual soil strata are less than about 3 ft. thick , containing more than 15 % finer than the no.200 sieve and about 50 % or less gravel (V- a). Coarse random (V-b) A material with less than 15% finer than No.200 sieve and about 50% or more gravel. Pervious (IV) Sand and /or gravel (less than 5% finer than the no.200 sieve and or free drainage). Borrow Materials
  • 7. Design shear strength for mix 1, 2 and 3 Design curves for QT, QcT and DS
  • 8. Task 2: Seepage Analysis Two Methods:  Flow net  Impervious Foundation  Pervious Foundation  Plax Flow (FEM method using PLAXIS)  Impervious Foundation  Pervious Foundation Soil type Qc Test ϒm (pcf) ϒsat (pcf) Permeability, k (ft/day) Elastic Modul us, E (psf) C (psf) ф ( ᵒ ) Kh Kv Type I & II 700 25 131 135 0.06 6.91E- 03 1.04E+ 06 Type III & Va 700 25 131 135 0.0124 1.38E- 03 2.00E+ 05 Type Vb 700 25 131 135 2.77E- 03 2.77E- 03 1.05E+ 06 Type IV 0 35 131 135 0.138 0.138 1.05E+ 06 Rock 16000 10 169 178 1.38 1.38 2.80E+ 08 Gravel- Sand 0 35 109 121 276.48 276.48 1.46E+ 06
  • 9. Task 2: Seepage Analysis  Flow net  Impervious Foundation  Pervious Foundation
  • 10. Task 2: Seepage Analysis  Plax Flow (FEM method using PLAXIS)  Impervious Foundation  Pervious Foundation Condition Water Elev. (ft) Embankment seepage, gpd/ft (Flownet) Total Seepage, gpd (Flow net) Embankment seepage, gpd/ft (Plaxis) Total Seepage, gpd Steady State 592 0.48 350 3.51 2106 0 0.5 1 1.5 2 2.5 3 3.5 4 FlowVolume(gpd/ft) Flow Net Plax Flow
  • 11. Task 2: Seepage Analysis  Plax Flow (FEM method using PLAXIS)  Pervious Foundation 955 960 965 970 975 980 985 FlowVolume(gpd/ft) Flow Net Plax Flow Total Seepage Volume (per foot) Condition Water Elev. (ft) Total seepage, gpd/ft (Flownet) Total Seepage, gpd (Flow net) Total seepage, gpd/ft (Plaxis) Total Seepage, gpd Steady State 592 965 580000 982 589200
  • 12. Task 3: Stability Analysis (Circular Arc Method)
  • 13. Task 3: Stability Analysis using PLAXIS (After Construction) After Construction Water Table at elev. = 380 ft, F.S. = 1.73 Rapid Draw Down Water Table at elev. = 610 to 480 ft, Time Interval = 0.5 day (Assume) F.S. = 1.19
  • 14. Task 3: Stability Analysis using PLAXIS (After Construction) Steady State Water Table at elev. = 592 ft, F.S. = 1.55 Condition Water Elev. (ft) Critical Location FS (Report) Critical Slope Plaxis FS (PLAXI S) Reqd. F.S. Remark s After Constructio n (No Seepage) 380 D/S 1.79 D/S 1.73 1.25 Stable Steady State Seepage 592 D/S 1.77 D/S 1.55 1.5 Stable Rapid Drawdown 610 - 480 U/S 1 U/S 1.19 1.00 Stable
  • 15. Task 3: Stability Analysis using PLAXIS (After Construction) Condition Water Elev. (ft) Critical Location FS (Report) Critical Slope Plaxis FS (PLAXIS ) Reqd. F.S. Remark s After Constructio n (No Seepage) 380 D/S 1.79 D/S 1.73 1.25 Stable Steady State Seepage 592 D/S 1.77 D/S 1.55 1.5 Stable Rapid Drawdown 610 - 480 U/S 1 U/S 1.19 1.00 Stable 0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2 After Construction (No Seepage) Steady State Seepage Rapid Drawdown FactorofSafety Factor of Safety Comparison Circular Arc Method PLAXIS
  • 17. Task 4: Settlement  Foundation Settlement  Embankment Settlement
  • 18. Settlement using 1-D analysis εa= γd(ωc/γ)(1/Ds -1)*100 γd= 116 pcf ωc= 0.136 e0= 0.428 Gs= 2.65 Ds= 0.842056075 γ 62.4 pcf εa= 4.742138365 %
  • 19. LayerNo Layer Thicknes s (ft) Unit Weight of Soil (pcf) Average Stress (psf) Average Stress (tsf) Void Ratio,e Vertical Strain TotalCompressioninLayer (ft) TotalCompressionbelow TopLayer CompressionofLayer DuringConstruction Compressionbelowtop layerduringconstruction PostConstruction CompressionofLayer Compressionpriorto reachinglayertop TotalSettlement Settlementduring Construction PostConstruction Settlement 1 23 135 1506.5 0.75325 0.402 1.8207283 0.418768 12.11204 0.418768 9.82493 0 9.82493 2.287115 0 2.287115 2 23 135 4611.5 2.30575 0.378 3.5014006 0.805322 11.69328 0.805322 9.406162 0 8.72969 2.963585 0.676471 2.287115 3 23 135 7716.5 3.85825 0.37 4.0616246 0.934174 10.88796 0.934174 8.60084 0 7.63445 3.253501 0.966387 2.287115 4 23 135 10821.5 5.41075 0.36 4.7619048 1.095238 9.953782 1.095238 7.666667 0 6.53922 3.414566 1.127451 2.287115 5 23 135 13926.5 6.96325 0.354 5.1820728 1.191877 8.858543 1.095238 6.571429 0.096639 5.44398 3.414566 1.127451 2.287115 6 23 135 17031.5 8.51575 0.345 5.8123249 1.336835 7.666667 1.095238 5.47619 0.241597 4.34874 3.317927 1.127451 2.190476 7 23 135 20136.5 10.06825 0.339 6.232493 1.433473 6.329832 1.095238 4.380952 0.338235 3.2535 3.076331 1.127451 1.94888 8 23 135 23241.5 11.62075 0.33 6.8627451 1.578431 4.896359 1.095238 3.285714 0.483193 2.15826 2.738095 1.127451 1.610644 9 23 135 26346.5 13.17325 0.327 7.0728291 1.626751 3.317927 1.095238 2.190476 0.531513 1.22409 2.093838 0.966387 1.127451 10 23 135 29451.5 14.72575 0.323 7.3529412 1.691176 1.691176 1.095238 1.095238 0.595938 0.41877 1.272409 0.676471 0.595938 12.11204 9.82493
  • 20. Settlement using Parabolic Equation  S = (γw/E)(h-y)y  where,  S= settlement of a point within the dam  h= height of dam  y= amount of fill beneath the point of interest  E= 1-D secant modulus to a stress level equivalent to the mid height of dam
  • 21. Settlement using Parabolic Equation Fill Height beneath point "y" (ft) γw (pcf) Heigh t of Dam, ft E50 Settleme nt, S (ft) 230 131 230 240000 0 207 131 230 240000 2.5987125 184 131 230 240000 4.6199333 161 131 230 240000 6.0636625 138 131 230 240000 6.9299 115 131 230 240000 7.2186458 92 131 230 240000 6.9299 69 131 230 240000 6.0636625 46 131 230 240000 4.6199333 23 131 230 240000 2.5987125 0 131 230 240000 0 E50= 12000/0.05 = 240000 psf 5% strain rate
  • 22. Comparison of Settlement Method 1-D Analysis Parabolic Equation Estimated in Design Phase Settlement Plate Value 9.82 ft 7.21 ft 8 ft 6.5-7 ft
  • 23. Cracking Potential Cracking Potential (u/s) Cracking Potential (d/s) H (ft)= 230 230 β= 18.33 21.8 Max Post Construction Settlement (ft) = 2.287 2.287 Cracking Potential= Max Post Cons Settlement/Hcotβ Max Post Cons Settlement/Hcotβ =0.003294268 =0.003977108 Emery, 2011
  • 24. Camber Design Dam Statio n Embankment Height 1 Percent of Height Post construction Foundation Settlement Cambe r (ft) 0 0 0 0 0 1 47.33333333 0.47333 0 0.5 2 94.66666667 0.94667 0 1 3 142 1.42 0 1.5 4 189.3333333 1.89333 0 2 5 230 2.3 0 2.5 6 180.3 1.803 0 2 7 135.3 1.353 0 1.5 8 90.2 0.902 0 1 9 45.1 0.451 0 0.5 10 0 0 0 0
  • 25. Task 5: Compaction (Test Fill)  Standard Proctor Test  Modified Proctor New Waddell Dam, Arizona
  • 27. Description of Test Fill Type of Soil Type II, Type III Roller Weight 2800 lb/ft Tamping Feet Area 7 sq Inch, 14 sq inch Pressure Intensity 600 psi, 300 psi Number of Passes 6,12,24 Moisture Content 2% wet, 2% dry of optimum Section Lift Five 6 inch lift
  • 28. Result of Type II Soil 121 122 118 121.5
  • 29. Result of Type II Soil 12.5%
  • 30. Result of Type II Soil
  • 31. Result of Type III Soil 121 121 119 120
  • 32. Result of Type III Soil 11%
  • 33. Result of Type III Soil
  • 34. 300 psi over 600 psi
  • 35. Summary  300 psi roller produced about 2 to 4 pcf greater density than the 600 psi roller  Little gain in density beyond 6-8 passes  300 psi, 6 passes, 6 inch lift, 1.5% dry to 1.5% wet of the optimum
  • 40. Roller Name Suitability Pressure Sheepsfoot Fine grained soil 150-400 psi Ruuber tire Coarse grained soil 60-80 psi Smooth wheel roller Subgrade, fine grained soil High Pressure Vibrating roller Coarse grained soil - Sheepsfoot Roller, 60 inch dia, 14 sq inch tamping foot
  • 41. Summary of Compaction Zone Compacte d Layer Thickness Compaction Equipment Foot pressure used (psi) Number of Passes Fine Material 6 Sheepsfoot Roller 300 6 Relatively Pervious Zone 12 Crawler Tractor 6-1/2 3 Filter Blanket 18 Crawler Tractor 6-1/2 3
  • 42.  The purpose of instrumentation and monitoring is to maintain and improve dam safety by providing information to evaluate dam performance (as expected) and warn of changes that could endanger the safety of a dam. Common causes of earth dam failures are Task 6: Dam Instrumentation
  • 43.
  • 44.  Overtopping  Seepage and Piping  Uplift failure  Deformation  Settlement Common causes of earth dam failures
  • 45.  6 foundation 33 embankment piezometers  1 Settlement measuring apparatus ( consolidation )  3 Nos. 12- in out let drains to measure seepage  Observation wells  Rubber ball method Evaluation of existing instrumentation of Blackly Dam The existing instruments in the dam are working perfectly
  • 47.  Perfect performance of the dam according to its design for nearly 63 years for seepage , Slope stability and consolidation are with in the design limit  Since the installed instruments are performing well , they need to be maintained properly  With availability of technology its recommended to automate the data acquisition process to reflect the real time scenario Proposed Instrumentation
  • 48. Resistivity Imaging 56 Electrodes: 56*20 = 1120 ft (1120*0.2 = 224 ft) 40 ft 1200ft H = 230 ft