Evaluating community projects
A practical guide
Marilyn Taylor, Derrick Purdue, Mandy Wilson and Pete Wilde
These guidelines were initially developed as part of the JRF Neighbourhood Programme.
This programme is made up of 20 community or voluntary organisations all wanting to
exercise a more strategic influence in their neighbourhood. The guidelines were originally
written to help these organisations evaluate their work. They provide step-by-step advice
on how to evaluate a community project which will be of interest to a wider audience.
Contents
All about evaluation 2
What is evaluation? 2
Why evaluate? 2
Key principles of evaluation
How to evaluate: a step-by-step approach 3
Step 1: Review the situation 3
Step 2: Gather evidence for the evaluation 4
Step 3: Analyse the evidence 6
Step 4: Make use of what you have found out 6
Step 5: Share your findings with others 7
Annex A: Reviewing the situation (example) 8
Annex B: Reviewing the situation (record sheet) 10
Annex C: Evaluation planning table 11
2 Evaluating community projects
All about evaluation
What is evaluation?
Put simply, evaluation by members of a project or
organisation will help people to learn from their
day-to-day work. It can be used by a group of
people, or by individuals working alone. It assesses
the effectiveness of a piece of work, a project or
a programme. It can also highlight whether your
project is moving steadily and successfully towards
achieving what it set out to do, or whether it is
moving in a different direction. You can then
celebrate and build on successes as well as learn
from what has not worked so well.
Why evaluate?
Although evaluation may seem like an unnecessary
additional task if you are already short of time
and resources, it can save you both time and
resources by keeping participants focused on, and
working towards, the ultimate goal of the project.
If necessary, it can refocus activity away from
unproductive or unnecessary work.
Evaluation can help you to:
• learn from your experience;
• record what you have learnt, and share it
with other stakeholders;
• check your progress;
• check whether what you are doing is still
what local people want or need;
• identify strengths and weaknesses in your
project;
• create a basis for future planning;
• demonstrate whether you have used your
resources – time and money – effectively;
• explain to funders, and others involved in
your work, what you have achieved and how
successful it is.
Key principles of
evaluation
Evaluation is most effective when:
• it is a continuous (not just one-off) process
informing planning and delivery as the
project develops;
• it involves all those with an interest in the
project in defining the questions they want
answered;
• it uses imaginative and creative approaches,
which engage those involved;
• it helps projects to be more accountable to
the wider community;
• it is used to challenge discriminatory and
oppressive policies and practice, and to
overcome inequality and disadvantage;
• it highlights and celebrates successes and
achievements;
• it encourages an honest appraisal of
progress, so that you can learn from what
hasn’t worked as well as what has.
2
How to evaluate: a step-
by-step approach
Step 1: Review the situation
Evaluating a project is like taking a journey. First
you need to plan your journey – you need to
decide where you want to get to; then work out
how you are going to get there, and what you need
to equip yourself with for the journey; you will also
need to look out for the signposts and milestones
that will tell you whether you are on the right road
and whether you are likely to get there on time.
When starting to evaluate a community project, it
is helpful to begin by writing down how you are
going to tackle each stage of this journey.
To complete Annex B you will need to ask yourself
the following questions:
What problems are you trying to solve?
Before you can evaluate your progress, you need
to be clear about what you are trying to achieve.
Community projects usually want to solve one or
more local problem. What are these problems?
What would make change happen?
What needs to change if the problem is to be
solved, and why? Think about what might have
caused the problem, and what needs to happen to
make a difference.
How do you plan to make change happen?
What can you do to solve the problem? Look at
your answer to the last question and think about
what your project can do. Try to be as precise as
possible. Break your broad or long-term goals
down into short- and medium-term goals. What
actions are you going to take to achieve these
goals? What resources will you need?
What results do you want to see?
How will you know when you have achieved your
short-, medium- and long-term goals? What will
be different about the original problem at the
end of the project, if you are successful? Try to
be as precise as possible about what you want to
achieve. The achievements should all be related to
the original problem you wanted to work on.
How can you measure progress?
In order to know whether you are on the right
track to achieve your goals and how far you
have got, you will need to decide on a few key
questions, and collect evidence to answer them.
What will tell you whether you are on the right
track? What signs, milestones or ‘indicators’
should you be looking for?
Annex A (pages 8-9) is a table reflecting
the range of community empowerment
issues being faced by projects in the JRF
Neighbourhood Programme. It was produced
to help projects think about what they were
trying to achieve,
Annex B (page 10) is a blank, expanded
version of the same table. It can be used by
any project, tackling any issue. It provides the
framework for your own evaluation process.
The best way of using it is to bring together a
small group – say project staff, some board or
committee members and any other key players
– to discuss it and fill it in. It is a way of
gathering the views of other people involved
in the project, to see if their expectations are
similar or different.
3Evaluating community projects
4 Evaluating community projects
Step 2: Gather evidence for the evaluation
This is a key part of the evaluation process. You
need to find evidence to show whether or not you
have reached the goals you set yourself in Annex B
(be they short-, medium- or long-term).
Different types of evidence should be collected:
• numbers (for example, the number of people
you have reached, the number of people
getting work, the number of good stories in
the press, changes in crime levels);
• people’s opinions, views and experiences
(for example, people’s stories about their
experience on the programme, photos of the
area ‘before and after’, people’s views on
whether they think they have more power);
• who has benefited and who has not.
Establish a baseline
Be as clear as you can about where you are
starting from. If you know where you are starting
from, it will be easier to assess the distance
you have travelled during the project. What
information do you already have? Make sure you
have collected together in a central file material
that will be useful to you later.
Relevant paperwork for creating a baseline might
include: the programme proposal, past research
reports and any statistical data you have on the
area, press reports and, if relevant, minutes of key
preliminary meetings.
Set up systems to gather data on a regular
basis
Clarify what information you will require to
help you to answer or explore the questions
set out in Step 1. Think about the records you
will be collecting anyway as part of your project
management that will provide some of the
information you need.
Relevant paperwork that should be gathered on a
regular basis might include: action plans and work
programmes, minutes of meetings, reviews and
reports, and records of attendance at groups and
events.
Decide what additional information you
will gather specifically for the evaluation,
and how you will gather it
The following menu lists ways of gathering
information. You should choose two or three
methods in order to get a rounded picture. Also,
different ways of gathering information will suit
different projects. Which you choose to use, and
how much time you spend gathering data, should
by tailored to the capacity of your organisation.
Annex C (page 11) will help you to plan what
information you will need to gather in order
to judge the project’s progress, and so support
decisions about what needs to change.
For each measure of progress (indicator), it will
be important to find out what information you
have already, what additional information you
will need to collect, what methods you will use
to gather it, who will take responsibility for
collecting the information, and the timescale.
5Evaluating community projects
Ways of gathering
additional information:
a menu
• A questionnaire survey
A questionnaire survey can be used to find out
more about the views and experiences of users,
the wider community, agencies, etc. Use tick-
boxes or questions that can be answered with a
yes or no if you want to survey a lot of people,
or ask a lot of questions. Questions that allow
people to say more than just yes or no will give
you more detailed information, but they take
longer to fill in, a lot more time to analyse, and
fewer people will fill them in. Responses to
questionnaires are often low so think about
offering a prize.
• In-depth interviews
It is usually best to limit the number of in-depth
interviews to those people whose involvement
with the project gives them particular insights
or valuable experience – but try to talk to a
range of people who are likely to have different
perspectives and views on your project.
• Feedback forms
You can find out whether people have found
your training and other events useful by asking
them to fill in a short form. Ask them, for
example, what they found most and least useful;
what they might do differently as a result; what
could be improved.
• Focus groups and round tables
A ‘focus group’ gathers together about half
a dozen people who are broadly similar (for
example, they are all single parents with young
children) to discuss themes or questions you
want to address in the evaluation. A ‘round
table’ discussion is a similar idea, which brings
together people with different perspectives
(for example, teenage parents, teachers, health
visitors).
• Diaries
Ask key people to keep diaries of their
involvement with the project.
• Press reports
Gather and review press reports on the area (for
example, you could see whether positive reports
about the area are increasing).
• Observation
Take photographs of your area over time, to see
if you can observe any changes. Observe who
contributes to meetings or comes to your centre,
and see whether this changes over time. This
will give you an idea of which types of people
you are reaching (men, women, younger, older)
and which of these types of people are playing a
more confident role in the project.
• Case studies
In order to make the evaluation manageable, you
might want to pick a few pieces of work (case
studies) to explore in detail, rather than trying
to explore everything. Pick pieces of work that
illustrate your main objectives.
• Evaluation workshops and review
meetings
Hold special workshops/review meetings of
people who are involved in your project and use
pictures, photographs or models, as well as the
spoken word, to get feedback from participants.
6 Evaluating community projects
Step 3: Analyse the evidence
You will now have gathered together quite a lot
of information. Working out what it is telling you
is the next stage. Does the information you have
gathered show that you have reached your goals?
Does it highlight any achievements? Does it show
up any problem issues that need to be tackled? Be
alert to unexpected outcomes, both desirable and
undesirable.
For example, evidence of good community cohesion
might be that events have been organised which
draw together people from across the community
or groups who were previously in conflict. Other
evidence of community cohesion might be
recording stories of how conflicts have been
resolved, or the views of formerly distant groups
now working as partners. The views of different
people involved in, or affected by, the project
(including those taking part and service users) can
often be as important as numbers in providing
evidence of change.
Don’t collect too much information or you will be
overwhelmed when you come to pull it together
and write up your notes. Allow plenty of time to
pull the information together. Even if only one
or two people initially do the work, it is worth
feeding the initial findings back to a wider group of
stakeholders to add their insights.
Step 4: Make use of what you have
found out
If there are goals or objectives you have not met,
or if you haven’t got as far as you had hoped, you
need to think about why, and what you can learn
from that. There could be a variety of explanations.
Here are a few ideas to consider:
Problems with external circumstances
• The environment in which you are working
has changed or worked against you (for
example, local or national policies have
changed, or a major employer has closed
down).
Problems with carrying out your plans
• You have departed from your original aims.
• You didn’t allow enough time or resources.
• Changes in your organisation have meant
that you have not been able to do what
you said you would do (for example, a key
worker left).
• The quality of performance of your
organisation has been lower than expected
(for example, workers or members have not
completed tasks they said they would do).
Problems with the ideas behind what you
want to achieve
• The plans you came up with initially to make
things happen have not been successful.
• Your original aims were inappropriate
(perhaps they turned out to be not what
people wanted).
• Different people involved in the project were
working against each other and towards
different goals.
7Evaluating community projects
Step 5: Share your findings with others
Sharing your findings with others is important
because it can help other people in the project, or
associated with it, to recognise any problems or
issues that are preventing the project from making
progress. It can help everyone to learn from any
mistakes that have been made, or pick up on any
successful ideas that have been put into action.
Remember that sharing findings can provide an
opportunity to celebrate success as much as to
learn from difficulties.
• Think about who you are sharing your
findings with, and how best to communicate
with them.
• Is there going to be a written report and/or
other ways of reporting the findings of the
evaluation? Try to ensure that any report
uses clear, plain language, and follows a
logical order.
• Will you need to report the findings to
different audiences using different formats?
It may be necessary to produce both a
comprehensive report of the evaluation
exercise and a much briefer report or
summary of key findings.
• How will you ensure that the findings inform
practical changes in your project’s work
plan? For example, you could hold a special
meeting or workshop for those involved in
the project at which you both feed back key
findings and also collectively consider future
action plans in the light of these findings.
JRF Neighbourhood
Programme
The Joseph Rowntree Foundation
Neighbourhood Programme offers a range of
‘light touch’ support to 20 groups and projects
in England, Scotland and Wales.
These resources include: access to facilitation
support from a team of regionally based
facilitators; access to small amounts of
credit; national and regional networking
opportunities; a website; brokerage; the
opportunity to share effective practice and
learning more widely.
The programme includes cross-cutting studies
on funding, community involvement, diversity
and community cohesion, and changing
relationships with power holders. Evaluation
of the programme was built in from the start
and has been carried out by Marilyn Taylor
and Derrick Purdue (UWE) and Mandy Wilson
and Pete Wilde (COGS).This document, and
a summary based on the Interim Evaluation
of the Neighbourhood Programme, 'Lending
a hand', are both available from the Joseph
Rowntree Foundation website (www.jrf.org.uk).
About the authors
The authors form the evaluation team for the JRF Neighbourhoods Programme. Marilyn Taylor and Derrick Purdue work in the
Cities Research Centre, University of the West of England, Bristol. Marilyn Taylor, who leads the team, is Professor of Urban
Governance and Regeneration; Derrick Purdue is a Research Fellow. Mandy Wilson and Pete Wilde are Directors of COGS Ltd
(Communities and Organisations: Growth and Support), Sheffield.
8 Evaluating community projects
AnnexAReviewingthesituation(step1)–example
Analysis
NoonehasanalysedlocalproblemsandassetsConsultationisneededwithlocalcommunitiesProfilecommunityneedsandassetsAplanofactionthatlocal
toidentifytheirneedsandplanactioncommunitiesfeelapartof
Drawupanactionplanwithshort-and
Lackofdirection–activitytendstobereactivemedium-termobjectivestoguidework
ratherthanproactive
Engagement
Peoplearenotengaged,littleactivityisgoingCommunitydevelopmentisneededtoSetupcommunitydevelopmentandoutreachLocalcommunitiesareengagedinavarietyof
onlocallytotackleproblemsencouragepeopletoengagewiththeprojectprojectsactivitiesandtacklinglocalproblems
Developastrategytocommunicatewith
peopleandtellpeoplewhattheprojectis
allabout
Capacity
Lackofleadership;lackoforganisationalSustainableleadershipandorganisationalProvideopportunitiestodevelop:Effectiveandsustainableorganisationsand
ability;lowlevelofskills;lowlevelofresourcesabilityareneededtoplanandco-ordinate•leadersandorganisationsaccountableleadership
actionandraisefunds•managementskills
•teambuildingandaccountabilitySustainablefundingandassets
•fundraisingskills
Cohesion
ThecommunityisdividedandfragmentedCommonground,mutualrespectandDevelopnegotiating,mediationandconflictLocalcommunitiesactingeffectivelytogether
understandingbetweencommunitiesandresolutionskills
individuals
Holdeventsandmeetingstobringdifferent
groupstogether
Whatproblemsareyoutryingtosolve?Whatwouldmakechangehappen?Howdoyouplantomakechangehappen?Whatresultsdoyouwanttosee?
(Rationale)(AimsandObjectives)(Outcomes)
9Evaluating community projects
Powerandinfluence
ThosewhohavepowerignoretheneedsofthePeopleinpowerneedagreaterunderstandingDeveloppolitical,promotionalandBetakenseriouslybypowerholders;work
community;policyisnotgearedtolocalneedoftheneedsofthecommunityandtheskillsnegotiatingskillsmoreeffectivelywiththem;makechanges
andthecommunityisnotinvolvedindecisiontocommunicateeffectivelywithlocalpeopleinpolicyandpractice
makingDevelopgreaterunderstandingandrapportwith
statutorybodiesandotherpartnersEffectivemanagementofcommunityassets
Confidenceandcommunity-ownedassets,andservices
ratherthanlocalauthority-ownedassets,canCapacitybuildingwithstatutorybodiesand
givethecommunitygreaterpowerotherpartnerssothattheyengagemore
effectivelywithcommunities
Developtheskillsandresourcestobuildup
community-ownedassetsandservices
Whatproblemsareyoutryingtosolve?Whatwouldmakechangehappen?Howdoyouplantomakechangehappen?Whatresultsdoyouwanttosee?
(Rationale)(AimsandObjectives)(Outcomes)
10 Evaluating community projects
AnnexBReviewingthesituation(Step1)–arecordsheetforprojects
WhatproblemsareyoutryingWhatwouldmakechangeHowdoyouplantomakeWhatresultsdoyouwanttoHowcanyoumeasureprogress?
tosolve?happen?(Rationale)changehappen?see?(Outcomes)(Indicators)
(AimsandObjectives)
11Evaluating community projects
AnnexCEvaluationplanningtable
IndicatorsWhatinformationdoyouWhatadditionalWhatmethodswillyouuseWhowilltakeresponsibilityWhendotheyneedtodo
alreadyhave?informationwillyouneed?togathertheadditionalforgatheringthisitby?
information?information?
Ref: 0225
Published 2005 by the Joseph Rowntree Foundation, The Homestead, 40 Water End, York YO30 6WP.
This project is part of the JRF’s research and development programme. The views expressed,
however, are those of the authors and not necessarily those of the Foundation.
Other formats available. Tel: 01904 615905, Email: info@jrf.org.uk

More Related Content

What's hot

Launch Communication Plan
Launch Communication PlanLaunch Communication Plan
Launch Communication PlanAveretek
 
Communication Workshop: Developing a strategy
Communication Workshop: Developing a strategyCommunication Workshop: Developing a strategy
Communication Workshop: Developing a strategyNicola Hodge
 
Stakeholder analysis scm
Stakeholder analysis scmStakeholder analysis scm
Stakeholder analysis scmADRIANFRANKLIN5
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsMichael Punzo
 
Checklist Communication Strategy Development
Checklist Communication Strategy DevelopmentChecklist Communication Strategy Development
Checklist Communication Strategy DevelopmentEwen Le Borgne
 
Measuring the success of your product
 Measuring the success of your product  Measuring the success of your product
Measuring the success of your product Rohela Raouf
 
Project meetings ddddd
Project meetings dddddProject meetings ddddd
Project meetings dddddDavinder Singh
 
Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3andre rahman
 
Communication Plan Workshop
Communication Plan WorkshopCommunication Plan Workshop
Communication Plan WorkshopTargetX
 
Communication Strategy - Workshop to Obtain Stakeholder Input
Communication Strategy - Workshop to Obtain Stakeholder InputCommunication Strategy - Workshop to Obtain Stakeholder Input
Communication Strategy - Workshop to Obtain Stakeholder InputJohn Mauremootoo
 
What is the Risk in Steering Committee?
What is the Risk in Steering Committee?What is the Risk in Steering Committee?
What is the Risk in Steering Committee?Christine Aykac
 
Effective logframes for international development
Effective logframes for international developmentEffective logframes for international development
Effective logframes for international developmentNIDOS
 
Learning focused Evaluation
Learning focused EvaluationLearning focused Evaluation
Learning focused EvaluationMichele Garvey
 

What's hot (18)

Launch Communication Plan
Launch Communication PlanLaunch Communication Plan
Launch Communication Plan
 
Communication Workshop: Developing a strategy
Communication Workshop: Developing a strategyCommunication Workshop: Developing a strategy
Communication Workshop: Developing a strategy
 
Stakeholder analysis scm
Stakeholder analysis scmStakeholder analysis scm
Stakeholder analysis scm
 
ISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectationsISQS4350-ManagingStakeholderExpectations
ISQS4350-ManagingStakeholderExpectations
 
Program planning
Program planningProgram planning
Program planning
 
Checklist Communication Strategy Development
Checklist Communication Strategy DevelopmentChecklist Communication Strategy Development
Checklist Communication Strategy Development
 
Measuring the success of your product
 Measuring the success of your product  Measuring the success of your product
Measuring the success of your product
 
Manage Stakeholder Relations
Manage Stakeholder RelationsManage Stakeholder Relations
Manage Stakeholder Relations
 
Project meetings ddddd
Project meetings dddddProject meetings ddddd
Project meetings ddddd
 
Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3Stakeholder analysis-toolkit-v3
Stakeholder analysis-toolkit-v3
 
Communication Plan Workshop
Communication Plan WorkshopCommunication Plan Workshop
Communication Plan Workshop
 
Communication Strategy - Workshop to Obtain Stakeholder Input
Communication Strategy - Workshop to Obtain Stakeholder InputCommunication Strategy - Workshop to Obtain Stakeholder Input
Communication Strategy - Workshop to Obtain Stakeholder Input
 
Managing difficult stakeholders - how to...
Managing difficult stakeholders - how to...Managing difficult stakeholders - how to...
Managing difficult stakeholders - how to...
 
Stakeholder Management
Stakeholder ManagementStakeholder Management
Stakeholder Management
 
What is the Risk in Steering Committee?
What is the Risk in Steering Committee?What is the Risk in Steering Committee?
What is the Risk in Steering Committee?
 
Effective logframes for international development
Effective logframes for international developmentEffective logframes for international development
Effective logframes for international development
 
The Other Side of Project Management
The Other Side of Project ManagementThe Other Side of Project Management
The Other Side of Project Management
 
Learning focused Evaluation
Learning focused EvaluationLearning focused Evaluation
Learning focused Evaluation
 

Similar to Evaluating community projects

6. international-pen-guidance-notes-for-centres monitoring-and-evaluation
6. international-pen-guidance-notes-for-centres monitoring-and-evaluation6. international-pen-guidance-notes-for-centres monitoring-and-evaluation
6. international-pen-guidance-notes-for-centres monitoring-and-evaluationFolasayo Ayegbayo
 
Week 7: Missions and Measures
Week 7: Missions and MeasuresWeek 7: Missions and Measures
Week 7: Missions and MeasuresGabrielle Lyon
 
Evaluating and communicating your project
Evaluating and communicating your project Evaluating and communicating your project
Evaluating and communicating your project mycommunitylocality
 
Collaborative 2 ingrid margarita and sandra
Collaborative 2 ingrid margarita and sandraCollaborative 2 ingrid margarita and sandra
Collaborative 2 ingrid margarita and sandraSandra Guevara
 
Ev dem evaluation guide and toolkit
Ev dem evaluation guide and toolkitEv dem evaluation guide and toolkit
Ev dem evaluation guide and toolkitEveryday Democracy
 
An Evaluation Guide for Community Engagement
An Evaluation Guide for Community EngagementAn Evaluation Guide for Community Engagement
An Evaluation Guide for Community EngagementEveryday Democracy
 
Session1 strategic planning presentation1
Session1 strategic planning presentation1Session1 strategic planning presentation1
Session1 strategic planning presentation1Sheena Baker
 
Program Evaluation In the Non-Profit Sector
Program Evaluation In the Non-Profit SectorProgram Evaluation In the Non-Profit Sector
Program Evaluation In the Non-Profit Sectorwishart5
 
Tools of project planning and desgn
Tools of project planning and desgnTools of project planning and desgn
Tools of project planning and desgnMORTUZATOHAN
 
Full Program Design
Full Program DesignFull Program Design
Full Program Designforeman
 
concept of evaluation "Character insight"
concept of evaluation "Character insight"concept of evaluation "Character insight"
concept of evaluation "Character insight"Shafiyazahoor327
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation MoseStaton39
 
Workbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxWorkbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxAASTHA76
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation MikeEly930
 
Centre for ageing better theory of change slides b (1)
Centre for ageing better theory of change slides b (1)Centre for ageing better theory of change slides b (1)
Centre for ageing better theory of change slides b (1)Centre for Ageing Better
 
Evaluation training for wellcome trust 15th may
Evaluation training for wellcome trust 15th mayEvaluation training for wellcome trust 15th may
Evaluation training for wellcome trust 15th mayBruce Etherington
 

Similar to Evaluating community projects (20)

6. international-pen-guidance-notes-for-centres monitoring-and-evaluation
6. international-pen-guidance-notes-for-centres monitoring-and-evaluation6. international-pen-guidance-notes-for-centres monitoring-and-evaluation
6. international-pen-guidance-notes-for-centres monitoring-and-evaluation
 
Week 7: Missions and Measures
Week 7: Missions and MeasuresWeek 7: Missions and Measures
Week 7: Missions and Measures
 
Evaluating and communicating your project
Evaluating and communicating your project Evaluating and communicating your project
Evaluating and communicating your project
 
Collaborative 2 ingrid margarita and sandra
Collaborative 2 ingrid margarita and sandraCollaborative 2 ingrid margarita and sandra
Collaborative 2 ingrid margarita and sandra
 
Ev dem evaluation guide and toolkit
Ev dem evaluation guide and toolkitEv dem evaluation guide and toolkit
Ev dem evaluation guide and toolkit
 
An Evaluation Guide for Community Engagement
An Evaluation Guide for Community EngagementAn Evaluation Guide for Community Engagement
An Evaluation Guide for Community Engagement
 
Session1 strategic planning presentation1
Session1 strategic planning presentation1Session1 strategic planning presentation1
Session1 strategic planning presentation1
 
Program Evaluation In the Non-Profit Sector
Program Evaluation In the Non-Profit SectorProgram Evaluation In the Non-Profit Sector
Program Evaluation In the Non-Profit Sector
 
Needs assessment
Needs assessmentNeeds assessment
Needs assessment
 
Proposal writing
Proposal writingProposal writing
Proposal writing
 
Tools of project planning and desgn
Tools of project planning and desgnTools of project planning and desgn
Tools of project planning and desgn
 
Full Program Design
Full Program DesignFull Program Design
Full Program Design
 
Logical framework
Logical  frameworkLogical  framework
Logical framework
 
concept of evaluation "Character insight"
concept of evaluation "Character insight"concept of evaluation "Character insight"
concept of evaluation "Character insight"
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation
 
Workbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docxWorkbook for Designing a Process Evaluation .docx
Workbook for Designing a Process Evaluation .docx
 
Workbook for Designing a Process Evaluation
 Workbook for Designing a Process Evaluation  Workbook for Designing a Process Evaluation
Workbook for Designing a Process Evaluation
 
Centre for ageing better theory of change slides b (1)
Centre for ageing better theory of change slides b (1)Centre for ageing better theory of change slides b (1)
Centre for ageing better theory of change slides b (1)
 
Evaluation training for wellcome trust 15th may
Evaluation training for wellcome trust 15th mayEvaluation training for wellcome trust 15th may
Evaluation training for wellcome trust 15th may
 
P process plus sa (1)
P process plus sa (1)P process plus sa (1)
P process plus sa (1)
 

More from Manish Nepal

Combustion chamber
Combustion chamberCombustion chamber
Combustion chamberManish Nepal
 
Project evaluation
Project evaluationProject evaluation
Project evaluationManish Nepal
 
Spare parts management
Spare parts managementSpare parts management
Spare parts managementManish Nepal
 
Vehicle operations maintenance
Vehicle operations maintenanceVehicle operations maintenance
Vehicle operations maintenanceManish Nepal
 
Steel and cast iron
Steel and cast ironSteel and cast iron
Steel and cast ironManish Nepal
 
Mechanical engineering project ideas
Mechanical engineering project ideasMechanical engineering project ideas
Mechanical engineering project ideasManish Nepal
 
What is rack and pinion steering mechanism
What is rack and pinion steering mechanismWhat is rack and pinion steering mechanism
What is rack and pinion steering mechanismManish Nepal
 
Mechanical engineering important fluid mechanics mcq
Mechanical engineering important fluid mechanics  mcq Mechanical engineering important fluid mechanics  mcq
Mechanical engineering important fluid mechanics mcq Manish Nepal
 
Basic car terminologies ppt
Basic car terminologies pptBasic car terminologies ppt
Basic car terminologies pptManish Nepal
 
Automotive electrical circuits and wiring book
Automotive electrical circuits and wiring book Automotive electrical circuits and wiring book
Automotive electrical circuits and wiring book Manish Nepal
 
Mechanical engineering interview questions with answers
Mechanical engineering interview questions with answersMechanical engineering interview questions with answers
Mechanical engineering interview questions with answersManish Nepal
 
Mechanism (engineering)
Mechanism (engineering)Mechanism (engineering)
Mechanism (engineering)Manish Nepal
 
Structures of solids
Structures of solidsStructures of solids
Structures of solidsManish Nepal
 

More from Manish Nepal (15)

Combustion chamber
Combustion chamberCombustion chamber
Combustion chamber
 
Project evaluation
Project evaluationProject evaluation
Project evaluation
 
Spare parts management
Spare parts managementSpare parts management
Spare parts management
 
Vehicle operations maintenance
Vehicle operations maintenanceVehicle operations maintenance
Vehicle operations maintenance
 
Steel and cast iron
Steel and cast ironSteel and cast iron
Steel and cast iron
 
Mechanical engineering project ideas
Mechanical engineering project ideasMechanical engineering project ideas
Mechanical engineering project ideas
 
What is rack and pinion steering mechanism
What is rack and pinion steering mechanismWhat is rack and pinion steering mechanism
What is rack and pinion steering mechanism
 
Mechanical engineering important fluid mechanics mcq
Mechanical engineering important fluid mechanics  mcq Mechanical engineering important fluid mechanics  mcq
Mechanical engineering important fluid mechanics mcq
 
Basic car terminologies ppt
Basic car terminologies pptBasic car terminologies ppt
Basic car terminologies ppt
 
Automotive electrical circuits and wiring book
Automotive electrical circuits and wiring book Automotive electrical circuits and wiring book
Automotive electrical circuits and wiring book
 
Mechanical engineering interview questions with answers
Mechanical engineering interview questions with answersMechanical engineering interview questions with answers
Mechanical engineering interview questions with answers
 
Mechanism (engineering)
Mechanism (engineering)Mechanism (engineering)
Mechanism (engineering)
 
Types of steel
Types of steelTypes of steel
Types of steel
 
Structures of solids
Structures of solidsStructures of solids
Structures of solids
 
Alloys
AlloysAlloys
Alloys
 

Recently uploaded

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...Erbil Polytechnic University
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptbibisarnayak0
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectErbil Polytechnic University
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating SystemRashmi Bhat
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 

Recently uploaded (20)

"Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ..."Exploring the Essential Functions and Design Considerations of Spillways in ...
"Exploring the Essential Functions and Design Considerations of Spillways in ...
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Autonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.pptAutonomous emergency braking system (aeb) ppt.ppt
Autonomous emergency braking system (aeb) ppt.ppt
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Risk Management in Engineering Construction Project
Risk Management in Engineering Construction ProjectRisk Management in Engineering Construction Project
Risk Management in Engineering Construction Project
 
Virtual memory management in Operating System
Virtual memory management in Operating SystemVirtual memory management in Operating System
Virtual memory management in Operating System
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 

Evaluating community projects

  • 1. Evaluating community projects A practical guide Marilyn Taylor, Derrick Purdue, Mandy Wilson and Pete Wilde These guidelines were initially developed as part of the JRF Neighbourhood Programme. This programme is made up of 20 community or voluntary organisations all wanting to exercise a more strategic influence in their neighbourhood. The guidelines were originally written to help these organisations evaluate their work. They provide step-by-step advice on how to evaluate a community project which will be of interest to a wider audience. Contents All about evaluation 2 What is evaluation? 2 Why evaluate? 2 Key principles of evaluation How to evaluate: a step-by-step approach 3 Step 1: Review the situation 3 Step 2: Gather evidence for the evaluation 4 Step 3: Analyse the evidence 6 Step 4: Make use of what you have found out 6 Step 5: Share your findings with others 7 Annex A: Reviewing the situation (example) 8 Annex B: Reviewing the situation (record sheet) 10 Annex C: Evaluation planning table 11
  • 2. 2 Evaluating community projects All about evaluation What is evaluation? Put simply, evaluation by members of a project or organisation will help people to learn from their day-to-day work. It can be used by a group of people, or by individuals working alone. It assesses the effectiveness of a piece of work, a project or a programme. It can also highlight whether your project is moving steadily and successfully towards achieving what it set out to do, or whether it is moving in a different direction. You can then celebrate and build on successes as well as learn from what has not worked so well. Why evaluate? Although evaluation may seem like an unnecessary additional task if you are already short of time and resources, it can save you both time and resources by keeping participants focused on, and working towards, the ultimate goal of the project. If necessary, it can refocus activity away from unproductive or unnecessary work. Evaluation can help you to: • learn from your experience; • record what you have learnt, and share it with other stakeholders; • check your progress; • check whether what you are doing is still what local people want or need; • identify strengths and weaknesses in your project; • create a basis for future planning; • demonstrate whether you have used your resources – time and money – effectively; • explain to funders, and others involved in your work, what you have achieved and how successful it is. Key principles of evaluation Evaluation is most effective when: • it is a continuous (not just one-off) process informing planning and delivery as the project develops; • it involves all those with an interest in the project in defining the questions they want answered; • it uses imaginative and creative approaches, which engage those involved; • it helps projects to be more accountable to the wider community; • it is used to challenge discriminatory and oppressive policies and practice, and to overcome inequality and disadvantage; • it highlights and celebrates successes and achievements; • it encourages an honest appraisal of progress, so that you can learn from what hasn’t worked as well as what has. 2
  • 3. How to evaluate: a step- by-step approach Step 1: Review the situation Evaluating a project is like taking a journey. First you need to plan your journey – you need to decide where you want to get to; then work out how you are going to get there, and what you need to equip yourself with for the journey; you will also need to look out for the signposts and milestones that will tell you whether you are on the right road and whether you are likely to get there on time. When starting to evaluate a community project, it is helpful to begin by writing down how you are going to tackle each stage of this journey. To complete Annex B you will need to ask yourself the following questions: What problems are you trying to solve? Before you can evaluate your progress, you need to be clear about what you are trying to achieve. Community projects usually want to solve one or more local problem. What are these problems? What would make change happen? What needs to change if the problem is to be solved, and why? Think about what might have caused the problem, and what needs to happen to make a difference. How do you plan to make change happen? What can you do to solve the problem? Look at your answer to the last question and think about what your project can do. Try to be as precise as possible. Break your broad or long-term goals down into short- and medium-term goals. What actions are you going to take to achieve these goals? What resources will you need? What results do you want to see? How will you know when you have achieved your short-, medium- and long-term goals? What will be different about the original problem at the end of the project, if you are successful? Try to be as precise as possible about what you want to achieve. The achievements should all be related to the original problem you wanted to work on. How can you measure progress? In order to know whether you are on the right track to achieve your goals and how far you have got, you will need to decide on a few key questions, and collect evidence to answer them. What will tell you whether you are on the right track? What signs, milestones or ‘indicators’ should you be looking for? Annex A (pages 8-9) is a table reflecting the range of community empowerment issues being faced by projects in the JRF Neighbourhood Programme. It was produced to help projects think about what they were trying to achieve, Annex B (page 10) is a blank, expanded version of the same table. It can be used by any project, tackling any issue. It provides the framework for your own evaluation process. The best way of using it is to bring together a small group – say project staff, some board or committee members and any other key players – to discuss it and fill it in. It is a way of gathering the views of other people involved in the project, to see if their expectations are similar or different. 3Evaluating community projects
  • 4. 4 Evaluating community projects Step 2: Gather evidence for the evaluation This is a key part of the evaluation process. You need to find evidence to show whether or not you have reached the goals you set yourself in Annex B (be they short-, medium- or long-term). Different types of evidence should be collected: • numbers (for example, the number of people you have reached, the number of people getting work, the number of good stories in the press, changes in crime levels); • people’s opinions, views and experiences (for example, people’s stories about their experience on the programme, photos of the area ‘before and after’, people’s views on whether they think they have more power); • who has benefited and who has not. Establish a baseline Be as clear as you can about where you are starting from. If you know where you are starting from, it will be easier to assess the distance you have travelled during the project. What information do you already have? Make sure you have collected together in a central file material that will be useful to you later. Relevant paperwork for creating a baseline might include: the programme proposal, past research reports and any statistical data you have on the area, press reports and, if relevant, minutes of key preliminary meetings. Set up systems to gather data on a regular basis Clarify what information you will require to help you to answer or explore the questions set out in Step 1. Think about the records you will be collecting anyway as part of your project management that will provide some of the information you need. Relevant paperwork that should be gathered on a regular basis might include: action plans and work programmes, minutes of meetings, reviews and reports, and records of attendance at groups and events. Decide what additional information you will gather specifically for the evaluation, and how you will gather it The following menu lists ways of gathering information. You should choose two or three methods in order to get a rounded picture. Also, different ways of gathering information will suit different projects. Which you choose to use, and how much time you spend gathering data, should by tailored to the capacity of your organisation. Annex C (page 11) will help you to plan what information you will need to gather in order to judge the project’s progress, and so support decisions about what needs to change. For each measure of progress (indicator), it will be important to find out what information you have already, what additional information you will need to collect, what methods you will use to gather it, who will take responsibility for collecting the information, and the timescale.
  • 5. 5Evaluating community projects Ways of gathering additional information: a menu • A questionnaire survey A questionnaire survey can be used to find out more about the views and experiences of users, the wider community, agencies, etc. Use tick- boxes or questions that can be answered with a yes or no if you want to survey a lot of people, or ask a lot of questions. Questions that allow people to say more than just yes or no will give you more detailed information, but they take longer to fill in, a lot more time to analyse, and fewer people will fill them in. Responses to questionnaires are often low so think about offering a prize. • In-depth interviews It is usually best to limit the number of in-depth interviews to those people whose involvement with the project gives them particular insights or valuable experience – but try to talk to a range of people who are likely to have different perspectives and views on your project. • Feedback forms You can find out whether people have found your training and other events useful by asking them to fill in a short form. Ask them, for example, what they found most and least useful; what they might do differently as a result; what could be improved. • Focus groups and round tables A ‘focus group’ gathers together about half a dozen people who are broadly similar (for example, they are all single parents with young children) to discuss themes or questions you want to address in the evaluation. A ‘round table’ discussion is a similar idea, which brings together people with different perspectives (for example, teenage parents, teachers, health visitors). • Diaries Ask key people to keep diaries of their involvement with the project. • Press reports Gather and review press reports on the area (for example, you could see whether positive reports about the area are increasing). • Observation Take photographs of your area over time, to see if you can observe any changes. Observe who contributes to meetings or comes to your centre, and see whether this changes over time. This will give you an idea of which types of people you are reaching (men, women, younger, older) and which of these types of people are playing a more confident role in the project. • Case studies In order to make the evaluation manageable, you might want to pick a few pieces of work (case studies) to explore in detail, rather than trying to explore everything. Pick pieces of work that illustrate your main objectives. • Evaluation workshops and review meetings Hold special workshops/review meetings of people who are involved in your project and use pictures, photographs or models, as well as the spoken word, to get feedback from participants.
  • 6. 6 Evaluating community projects Step 3: Analyse the evidence You will now have gathered together quite a lot of information. Working out what it is telling you is the next stage. Does the information you have gathered show that you have reached your goals? Does it highlight any achievements? Does it show up any problem issues that need to be tackled? Be alert to unexpected outcomes, both desirable and undesirable. For example, evidence of good community cohesion might be that events have been organised which draw together people from across the community or groups who were previously in conflict. Other evidence of community cohesion might be recording stories of how conflicts have been resolved, or the views of formerly distant groups now working as partners. The views of different people involved in, or affected by, the project (including those taking part and service users) can often be as important as numbers in providing evidence of change. Don’t collect too much information or you will be overwhelmed when you come to pull it together and write up your notes. Allow plenty of time to pull the information together. Even if only one or two people initially do the work, it is worth feeding the initial findings back to a wider group of stakeholders to add their insights. Step 4: Make use of what you have found out If there are goals or objectives you have not met, or if you haven’t got as far as you had hoped, you need to think about why, and what you can learn from that. There could be a variety of explanations. Here are a few ideas to consider: Problems with external circumstances • The environment in which you are working has changed or worked against you (for example, local or national policies have changed, or a major employer has closed down). Problems with carrying out your plans • You have departed from your original aims. • You didn’t allow enough time or resources. • Changes in your organisation have meant that you have not been able to do what you said you would do (for example, a key worker left). • The quality of performance of your organisation has been lower than expected (for example, workers or members have not completed tasks they said they would do). Problems with the ideas behind what you want to achieve • The plans you came up with initially to make things happen have not been successful. • Your original aims were inappropriate (perhaps they turned out to be not what people wanted). • Different people involved in the project were working against each other and towards different goals.
  • 7. 7Evaluating community projects Step 5: Share your findings with others Sharing your findings with others is important because it can help other people in the project, or associated with it, to recognise any problems or issues that are preventing the project from making progress. It can help everyone to learn from any mistakes that have been made, or pick up on any successful ideas that have been put into action. Remember that sharing findings can provide an opportunity to celebrate success as much as to learn from difficulties. • Think about who you are sharing your findings with, and how best to communicate with them. • Is there going to be a written report and/or other ways of reporting the findings of the evaluation? Try to ensure that any report uses clear, plain language, and follows a logical order. • Will you need to report the findings to different audiences using different formats? It may be necessary to produce both a comprehensive report of the evaluation exercise and a much briefer report or summary of key findings. • How will you ensure that the findings inform practical changes in your project’s work plan? For example, you could hold a special meeting or workshop for those involved in the project at which you both feed back key findings and also collectively consider future action plans in the light of these findings. JRF Neighbourhood Programme The Joseph Rowntree Foundation Neighbourhood Programme offers a range of ‘light touch’ support to 20 groups and projects in England, Scotland and Wales. These resources include: access to facilitation support from a team of regionally based facilitators; access to small amounts of credit; national and regional networking opportunities; a website; brokerage; the opportunity to share effective practice and learning more widely. The programme includes cross-cutting studies on funding, community involvement, diversity and community cohesion, and changing relationships with power holders. Evaluation of the programme was built in from the start and has been carried out by Marilyn Taylor and Derrick Purdue (UWE) and Mandy Wilson and Pete Wilde (COGS).This document, and a summary based on the Interim Evaluation of the Neighbourhood Programme, 'Lending a hand', are both available from the Joseph Rowntree Foundation website (www.jrf.org.uk). About the authors The authors form the evaluation team for the JRF Neighbourhoods Programme. Marilyn Taylor and Derrick Purdue work in the Cities Research Centre, University of the West of England, Bristol. Marilyn Taylor, who leads the team, is Professor of Urban Governance and Regeneration; Derrick Purdue is a Research Fellow. Mandy Wilson and Pete Wilde are Directors of COGS Ltd (Communities and Organisations: Growth and Support), Sheffield.
  • 8. 8 Evaluating community projects AnnexAReviewingthesituation(step1)–example Analysis NoonehasanalysedlocalproblemsandassetsConsultationisneededwithlocalcommunitiesProfilecommunityneedsandassetsAplanofactionthatlocal toidentifytheirneedsandplanactioncommunitiesfeelapartof Drawupanactionplanwithshort-and Lackofdirection–activitytendstobereactivemedium-termobjectivestoguidework ratherthanproactive Engagement Peoplearenotengaged,littleactivityisgoingCommunitydevelopmentisneededtoSetupcommunitydevelopmentandoutreachLocalcommunitiesareengagedinavarietyof onlocallytotackleproblemsencouragepeopletoengagewiththeprojectprojectsactivitiesandtacklinglocalproblems Developastrategytocommunicatewith peopleandtellpeoplewhattheprojectis allabout Capacity Lackofleadership;lackoforganisationalSustainableleadershipandorganisationalProvideopportunitiestodevelop:Effectiveandsustainableorganisationsand ability;lowlevelofskills;lowlevelofresourcesabilityareneededtoplanandco-ordinate•leadersandorganisationsaccountableleadership actionandraisefunds•managementskills •teambuildingandaccountabilitySustainablefundingandassets •fundraisingskills Cohesion ThecommunityisdividedandfragmentedCommonground,mutualrespectandDevelopnegotiating,mediationandconflictLocalcommunitiesactingeffectivelytogether understandingbetweencommunitiesandresolutionskills individuals Holdeventsandmeetingstobringdifferent groupstogether Whatproblemsareyoutryingtosolve?Whatwouldmakechangehappen?Howdoyouplantomakechangehappen?Whatresultsdoyouwanttosee? (Rationale)(AimsandObjectives)(Outcomes)
  • 9. 9Evaluating community projects Powerandinfluence ThosewhohavepowerignoretheneedsofthePeopleinpowerneedagreaterunderstandingDeveloppolitical,promotionalandBetakenseriouslybypowerholders;work community;policyisnotgearedtolocalneedoftheneedsofthecommunityandtheskillsnegotiatingskillsmoreeffectivelywiththem;makechanges andthecommunityisnotinvolvedindecisiontocommunicateeffectivelywithlocalpeopleinpolicyandpractice makingDevelopgreaterunderstandingandrapportwith statutorybodiesandotherpartnersEffectivemanagementofcommunityassets Confidenceandcommunity-ownedassets,andservices ratherthanlocalauthority-ownedassets,canCapacitybuildingwithstatutorybodiesand givethecommunitygreaterpowerotherpartnerssothattheyengagemore effectivelywithcommunities Developtheskillsandresourcestobuildup community-ownedassetsandservices Whatproblemsareyoutryingtosolve?Whatwouldmakechangehappen?Howdoyouplantomakechangehappen?Whatresultsdoyouwanttosee? (Rationale)(AimsandObjectives)(Outcomes)
  • 10. 10 Evaluating community projects AnnexBReviewingthesituation(Step1)–arecordsheetforprojects WhatproblemsareyoutryingWhatwouldmakechangeHowdoyouplantomakeWhatresultsdoyouwanttoHowcanyoumeasureprogress? tosolve?happen?(Rationale)changehappen?see?(Outcomes)(Indicators) (AimsandObjectives)
  • 12. Ref: 0225 Published 2005 by the Joseph Rowntree Foundation, The Homestead, 40 Water End, York YO30 6WP. This project is part of the JRF’s research and development programme. The views expressed, however, are those of the authors and not necessarily those of the Foundation. Other formats available. Tel: 01904 615905, Email: info@jrf.org.uk