SCHEDULE OVERRUN IN INFRASTRUCTURE PROJECTS IN INDIA IDENTIFICATION, PRIORITIZATION AND MITIGATION.pptx

  1. A presentation by Lalit Mohan Sharma Dept of Civil Engineering
  2. RELEVANCE OF THE TOPIC IN CURRENT SCENARIO
  3. OVER THE YEARS, INDIA HAS SEEN RISING INVESTMENTS IN INFRASTRUCTURE AS A PERCENTAGE OF GDP 4.5% 5.2% 5.1% 4.7% 4.5% 4.4% 4.9% 5.5% 6.2% 7.3% 6.8% 8.3% 8.5% 4.0% 4.5% 4.3% 4.1% 3.9% 3.3% 3.5% 4.0% 4.3% 4.8% 4.6% 4.6% 4.7% 0.6% 0.7% 0.9% 0.7% 0.6% 1.1% 1.4% 1.5% 1.9% 2.5% 2.2% 3.7% 3.8% 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 Total GFCF in Infrastructure as % of GDP Public Investment component of Infrastructure GFCF (as % of GDP) Private Investment component of Infrastructure GFCF (as % of GDP) GFCF- GROSS FIXED CAPITAL FORMATION
  4. … SPORADIC SUCCESS STORIES ACROSS VARIOUS SUB-SECTORS Initial success in PPP ►PPP model a major success in development of roads, ports and airports – bridging the funding gap ►Model concession agreements in place along with provisions for viability gap funding Telecom success story ►Massive adoption of mobile telephony – Teledensity jumped from 3% in 1999 to 76% in 2012 ►Strong regulatory support and initial progressive policies Improvement in rail operating performance in last two decades ►Big improvement on all operating characteristics like wagon turnaround, axle load, operating ratio and utilisation ►Introduction of initiatives like dynamic pricing, incentives for faster unloading, multiple unloading etc. These examples have shown that with government focus, regulatory interventions and funding, India is capable of making progress on infrastructure front Delhi metro rail ►One of the few metro systems in the world to turn in an operating profit ►Constructed in time and within budget – world class rolling stock, signaling and safety systems 13 18 26 36 52 71 76 2006 2007 2008 2009 2010 2011 2012 11 9 7 6 5 5 21 24 27 36 38 37 1990-91 1995-96 2000-01 2005-06 2010-11 2011-12 Wagon Turnaround time (Days) Gross Tonne-km / Engine hr (thousands) 1678 1278 843 883 2489 5363 4865 2005 2006 2007 2008 2009 2010 2011 Growthinteledensity(%)[Source:TRAI] Railwayoperatingparameters[Source:IRstatistics] Roads(kms)awardedunderPPP[Source:NHAI]
  5. EVEN THOUGH WE HAVE INCREASED PACE OF INFRASTRUCTURE CREATION, THERE HAS BEEN A DEFICIT IN ACHIEVEMENT AGAINST FIVE-YEAR PLANS 16.4 10.6 14.5 20.4 19.7 9.3 3.5 9.6 12.2 16.9 FY08 FY09 FY10 FY11 FY12 Target vs Actual Generation Capacity Addition (GW) Target Addition Acutal Addition Note: The original 11th plan target of 78.7 GW was revised to 62.4GW after poor achievement in the first year of the plan 2885 3519 3165 2500 2500 1685 2203 2693 1780 2247 FY08 FY09 FY10 FY11 FY12 Target vs Actual in National Highway development (km) Target Addition Actual Addition 500 350 250 1021 1300 156 350 258 709 727 FY08 FY09 FY10 FY11 FY12 Target vs Actual new railway line addition (kms) Target Addition Acutal Addition Physical achievements have consistently lagged behind five-year plan targets, creating an infrastructure deficit Source: Planning Commission documents Total deficit (FY08-12): 36% Total deficit (FY08-12): 31% Total deficit (FY08-12): 27%
  6. RESULTANTLY, INDIA LAGS BEHIND OTHER NATIONS ON INFRASTRUCTURE INDICATORS… Compared to other countries, India lags behind on some of the key indicators of infrastructure development Country Infrastructure Ranking1 Logistics Ranking2 Timeliness Ranking3 1- Quality of Trade & Transport Infrastructure 2- Competence & Quality of Logistics Services 3- Frequency with which shipments reach consignees with scheduled or expected delivery times Source: Logistics Performance Index, World Bank 2012 Overall rank Brazil 46 41 49 45 Australia 18 16 17 18 India 56 38 44 46 China 26 28 30 26 S. Africa 19 24 20 23 Russia 97 92 94 95 Philippines 97 92 94 52 Malaysia 27 30 28 29 Thailand 44 49 39 38 Indonesia 62 39 69 59
  7. …LARGELY DUE TO POLICY, PROCEDURAL AND FUNDING RELATED ISSUES… Stage in infra development lifecycle ► Multiple gates and approvals before even bidding starts ► Slack quality and viability checks lead to project cost overruns later Pre-tendering and bidding ► Rising budget deficit crowding out funds for infrastructure ► Norms for banks’ exposure to infrastructure limiting funds available for infrastructure ► Tightened RBI credit policies and global credit crunch reducing investments Funding ► Land acquisition delays and Resettlement and Rehabilitation (R&R) issues ► Weak/absent regulatory structures ► Lack of skilled manpower Construction and operations ► Absence of integrated planning and lack of coordination between agencies ► High AT&C losses in electricity, large % of non-revenue water ► Low allocation of funds for maintenance Infrastructure productivity Perceived issues faced currently by infrastructure Aggregate Technical and Commercial (AT&C)
  8. Policy Reforms Planning Implement ation • A general introduction to the Infrastructure sector and Investment trends • Gathering information on current status of Infrastructure in the country • Literature review to understand potential delay reasons to include study of various papers on Indian prospective as well as on International arena.  Reports from various organizations working in the field .  Interaction with senior management of funding agencies like Asian Development Bank , consultants, executing agencies like NBCCL and some prominent Govt Organizations • Use of AHP technique to prioritize potential delay causes • How delay can be negated , by taking in to account the experience shared by various organizations and Post Project Audit reports Under utilization of allocated funds Implications Delay in delivery of much sought- after infrastructure Delayed delivery of infrastructure Price Escalation Deterrent for economic growth PREVIEW OF PAPER
  9. BROAD HEADINGS OF THE STUDY
  10. CHAPTER-1 INTRODUCTION 1.1 Background 1.2 Investment pattern in infrastructure sector 1.3 Infrastructure development a prerequisite for economic growth 1.4 Delay in fund utilization CHAPTER-2 DELAY IN EXECUTION OF INFRASTRUCTURE PROJECTS 2.2 Introduction 2.3 Delay analysis CHAPTER-3 LITERATURE REVIEW 3.1 Introduction 3.2 International scenario 3.3 Literature review in Indian context CHAPTER-4 PROBLEM DEFINITION 4.1 Prominent delay factors 4.2 Aim and objective
  11. CHAPTER-5 RESEARCH METHODOLOGY 5.1 Preview of study 5.2 Technique adopted 5.3 Brief Introduction to Analytical hierarchy Process 5.4 Relative Importance of Criteria 5.5 Conduct of survey CHAPTER-6 MITIGATION 6.1 Introduction 6.2 Inappropriate Formulation of Project 6.3 Delay in Land Acquisition and obtaining environmental clearances 6.4 Adoption of inappropriate project procurement model 6.5 Lack of project monitoring 6.6 Resource constraint 6.7 Use of obsolete technology CHAPTER -7 SCOPE FOR FUTURE STUDIES CHAPTER-8 CONCLUSION
  12. 1.INTRODUCTION
  13. BACKGROUND Indian economy has grown many folds since independence. Over a period of time substantial amount of funds have been allocated for development of Infrastructure 5.3 6.2 7.1 8.1 9.2 10.4 0 2 4 6 8 10 12 2011-12 2012-13 2013-14 2014-15 2015-16 2016-17 Investment in 100 Thousand Cr Fin Year Investment Trends So far Anticipated 5.20% 7.50% 10.00% 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 12.00% 10th Plan(2003-07) 11th Plan(2008-12) 12th Plan (2012-17) % Share of GDP Linear (% Share of GDP)
  14. 4.10% 4.20% 4.80% 4.90% 5.00% 5.10% 1.70% 2.20% 2.40% 2.60% 2.90% 3.30% 6.40% 7.20% 7.50% 7.90% 8.40% 0.00% 2.00% 4.00% 6.00% 8.00% 10.00% 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 INVESTMENT IN INFRASTRUCTURE SECTOR AS % OF GDP Public Private Total 2885 3519 3165 2500 2500 1685 2203 2693 1780 2247 FY08 FY09 FY10 FY11 FY12 TARGET VS ACTUAL IN NATIONAL HIGHWAY DEVELOPMENT (KM) Target Addition Actual Addition 500 350 250 1021 1300 156 350 258 709 727 FY08 FY09 FY10 FY11 FY12 TARGET VS ACTUAL NEW RAILWAY LINE ADDITION (KMS) 0% 10% 20% 30% 40% Electricity Roadways Railways Telecom Oil & Gas 10th FYP Planned 10th FYP Actual 11th FYP Planned 11 FYP Actual A sizable percentage of GDP is being allocated for infrastructure sector There is 100% increase in private investment in infrastructure sector against 24.4% increase in Government share contribution of private sector has been lopsided. Telecom, Oil and Gas received the maximum share where as other sectors got marginal or no increase Much essential infrastructure sectors like Roadways, Railways and Electricity have shown a prominent decrease in fund allocation/utilization. Decreased funding in development of basic infrastructure facilities like Highways, Railways is a cause of concern Investment in these sectors is not being utilized due to some reasons resulting in surrender of funds The share of infrastructure investment in GDP is planned to be increased to more than 10% by the end of 12th five year plan 5.20% 7.50% 10.00% 0.00% 5.00% 10.00% 15.00% 10th Plan(2003-07) 11th Plan(2008-12) 12th Plan (2012-17) % Share of GDP
  15. Delay in Fund Utilization • Causing undue delay in availability of facilities • Poor satisfaction level of the population • Physical achievements in last couple of years have not matched the aggressive investment targets set Why Delay in Execution ? • Poor conception • Inapt planning • Non performing executing agencies • Lacunas in Government policies • Lateral flow of experience and information
  16. 2. DELAY IN EXECUTION OF INFRASTRUCTURE PROJECTS
  17. Infrastructure Projects Influence larger section of the society Have direct impact on the economic growth and living standard of the population Time consuming both in terms of planning and execution Require colossal amount of funding Characteristics
  18. SECTORS NOS OF PROJECT DELAY % COMPONENT WRT TOTAL NOS OF PROJECTS TOTAL AMOUNT IN CRORES Rs % INCREASE wrt TO ORG AMT AVERAGE COST PER PROJECT ( CRORES Rs) DELAY % COMPONENT AS PER REVISED AMOUNT ORIGINAL REVISED ORIGINAL REVISED Atomic Energy 1 2.00% 13171.00 17270.00 31.12% 13171.00 17270.00 12.92% Coal 2 4.00% 2500.56 3733.99 49.33% 1250.28 1867.00 2.79% Highways 10 20.00% 2216.29 3156.89 42.44% 221.63 315.69 2.36% Petroleum 5 10.00% 7292.94 12100.4 65.92% 1458.59 2420.08 9.05% Power 9 18.00% 22285.19 33421.29 49.97% 2476.13 3713.48 25.00% Railways 19 38.00% 10989.99 49765.22 352.82% 578.42 2619.22 37.23% Shipping and ports 1 2.00% 150.00 600.00 300.00% 150.00 600.00 0.45% Steel 1 2.00% 8692 12291 41.41% 8692.00 12291.00 9.19% Tele Communication 1 2.00% 149.15 158.72 6.42% 149.15 158.72 0.12% Water Resources 1 2.00% 542.9 1187 118.64% 542.90 1187.00 0.89% Total 50 67990.02 133684.51 96.62% DATA ANALYSIS OF 50 PROJECTS COSTING MORE THEN 150CR RUNNING BEHIND SCHEDULE : SOURCE MSOPI
  19. % OF DELAYED PROJECTS ( IN NOS) Atomic Energy, 2.00 Coal, 4.00 Highways, 20.00 Petrolium, 10.00 Power, 18.00 Railways, 38.00 Shipping and ports, 2.00 Steel, 2.00 Tele Communica tion, 2.00 Water Resources, 2.00 Atomic Energy, 12.92 Coal, 2.79 Highways, 2.36 Petrolium, 9.05 Power, 25 Railways, 37.23 Shipping and ports, 0.45 Steel, 9.19 Tele Communicati on, 0.12 Water Resources, 0.89 % OF DELAYED PROJECTS ( FIN SHARE) DELAY ANALYSIS OF 50 SAMPLE PROJECTS 38% of the Railway 20% Highway 18% Power projects are behind schedule Railways has a fin share of 37.23% (max) followed by Power sector at 25.00% which is otherwise at third place as per as numbers of delayed project and Atomic Energy with 12.92% share is at third place ( with meager 2% delayed projects as per numbers of projects) Highway Projects which are otherwise at second place ( 20% delayed projects) as per number concern, but only have a meager financial percentage (of delayed projects are 2.36% Average revised cost of the Highway projects is the least ( Rs-315.69 crores) as compared to Atomic energy projects ( Rs-17270.00 crores). Average revised cost of the Railway projects is ( Rs-2619.22 crores)
  20. • Major infrastructure sectors which are adversely affected by time and cost overrun have been identified as – ATOMIC ENERGY – COAL – HIGHWAYS – PETROLEUM – POWER – RAILWAYS 92.00% 89.35% Nos Fin Share 0.00% 100.00% 200.00% 300.00% 400.00% % Increase in Cost 0 10 20 30 40 50 60 70 80 Mar-93 Mar-94 Mar-95 Mar-96 Mar-97 Mar-98 Mar-99 Mar-_2000 Mar-01 Mar-02 Mar-03 Mar-04 Mar-05 Mar-06 Mar-07 Mar-08 Mar-09 Mar-10 Sep-11 Delayed Projects Year Delay Trends so far These sectors contribute towards 92% of the total numbers of delayed projects. Total revised amount of these projects is 89.35% of the total revised amount. Railway projects have shown a maximum price escalation trend at 352.82 % followed by shipping and ports at 300% with Tele Communication Projects at the least trend of 6.42% against average escalation trend of 96.62%. Highway projects have shown an escalation trend of 42.44% almost 50% less than the average trend.
  21. In order to formulate a viable strategy to handle Time and Cost overrun of the affected infrastructure sectors, it is imperative to identify various attributes responsible for delay. A project passes through various stages. Each stage has to be planned meticulously. Delay at one stage has a compounding effect on the subsequent stages, like wise time saved in one stage also has a compounding effect. Approval from competent authorities, designing, resource planning, fund flow, risk analysis, project procurement, and project management organization are few of the stages which need attention. Depending on the versatility of the Project Management Organization various activities can commence simultaneously thus resulting in overall time saving – less chances of Time overrun – less chances of Cost overrun.
  22. 3: LITERATURE REVIEW
  23. Characteristics of Infra Projects • one firm can supply a market’s entire demand for a goods or service at a price lower than two or more firms can. • Many infrastructure facilities have a significant component characterized by declining cost associated with increasing output throughout the range of the possible demand. Natural monopoly. • A tradable goods or service can be sold in another location distant from where it was produced • Most infrastructure services are non-tradable in nature. In some cases carriage may not be tradable but the content may Non-tradability • Sunk costs are investment costs which cannot be immediately recovered by the possible sale of the assets that were invested in • High sunk cost makes an investment irreversible which impacts the level of investment by industry High-sunk costs or asset specificity. • Public good is normally characterized by two factors – non-rivalness and non excludable. This means that consumption of the good by an individual does not reduce availability of the good for consumption by others and that no one can be effectively excluded from using the good. The characteristic of non-rivalness implies zero marginal cost of providing benefit of a public good Non-rivalness (up to congestion limits) in consumption. • Infrastructure creates external benefits or positive externalities • A road could lead to an increase in the value of adjoining land Presence of Externalities
  24. Developing Countries Political situation, Award Project to Lowest bid price. Progress Payment Delay by Owner. Shortage of Equipment Delay in approval of drawing, Inadequate early planning Delay in owner’s decision making process. Developed Countries Decision making and planning are often multi- actor processes with conflicting interests. Technology is often not standard. Often the project scope or ambition level will change significantly over time. Statistical evidence shows that such unplanned events are often unaccounted for, leaving budget contingencies sorely inadequate. Misinformation about costs, benefits, and risks is the norm. The result is cost overruns and/or benefit shortfalls with a majority of projects. Causes of Delay in
  25. Lack of commitment by client, contractor and vendors leading to accidents. Improper or obsolete construction methods. Delay in material delivery. Inefficient site management due to ambiguous specifications. Unskilled labour. Ineffective supervision. Inadequate experience of contractor. Poor site coordination due to lack of coordination between site and design office. Non-availability of drawings/designs on time. Unrealistic time schedule built in the contract, improper planning in ignoring extreme weather conditions which lead to low labour productivity and therefore lead to errors in time estimation. Improper planning for recruitment of skilled operators for specialized equipment. Improper planning the requirement of equipment and their utilization. Lack of clarity of project scope resulting in rework or scope creep due to misunderstanding by the contractor or project manager. Lack of communication with local authorities resulting in delays in permissions, lack of communication between contractor and client results in delay in approval of stages. Selection of contractor with inadequate experience or skill. Optimistic cost and time duration built in the contract Causes of Delay in Indian Scenario
  26. Executing agencies are often not ready for project implementation when the loan is approved. Thus, commencement of project implementation can be delayed up to two or more years. Project approval by the government or a competent authority such as Expenditure Finance Committee (EFC), Cabinet Committee on Economic Affair (CCEA) or Fiscal Responsibility & Budgetary Management (FRBM) clearance. Agreement on the fundamental purpose or intent of a project between the State Government, executing agencies and municipal bodies. Establishing and staffing Project Management Units (PMU) and Project Implementing Units (PIUs). Timely preparation of quality Detailed Project Reports (DPR), firming-up of cost estimates and acceptance of DPRs by the competent authorities. Preparation of Standard Bidding documents (SBD) and Request for Proposal (RFP) for procurement of goods, works and consulting services and delay in tendering and evaluation of bids. Statutory matters such as land and right-of-way acquisition, resettlement, obtaining forest and environmental clearances, removing encumbrances and securing no-objection from affected parties. Point of View of Funding Agencies
  27. Land Acquisition as a Major Constraint The genesis of land acquisition in India lies in the Bengal regulation act ( land acquisition act ) of 1824 The provisions of the act empower government to acquire any part of the land with or without consent of the owner A large part of the land mass is held by households who earn their livelihood from land. Agriculture sector contribute over 15 % in the national GDP and 10% in foreign earnings. As per World Bank report, it has a share of over 45% in the available job opportunities. Transition to an industrial or service economy from an agrarian economy is not easy Land acquisition process as a major deterrent of the progress of infrastructure project development.
  28. 4: PROBLEM DEFINITION
  29. •Improper justification of the project. •Justification is influenced by other reasons than need based. •Political reasons During Conception of the Project •In adequate early planning. •Unrealistic time schedules. •In appropriate formulation of project. •Lack of viable contingency plan/ inadequate risk analysis and risk management. •Land Acquisition and Environment clearance. •Lack of clarity in design and drawing resulting in frequent clarification during execution During Planning Stage •Award project to lowest bidder. •Lack of availability of capable executing agencies. •Capacity constraints of the contractors. During Project Procurement Stage •Inappropriate project management by the client and contractor. •Constraint of availability of skilled labor / Supervisor. •Inadequate availability of basic quality construction material like aggregate, bricks etc. •Improper /obsolete construction methods. •Frequent change in project scope during execution. •Lack of commitment by client (Timely release of payments etc), contractors and venders. •Delay in decision making. •Insufficient coordination. During Execution
  30. AIM AND OBJECTIVE THE AIM OF THIS STUDY IS TO IDENTIFY MAJOR CAUSES OF DELAY IN INFRASTRUCTURE PROJECTS IN INDIA AND SUGGEST REMEDIAL MEASURES TO MINIMIZE TIME OVERRUN THUS MINIMIZE COST OVERRUN.
  31. 5: RESEARCH METHODOLOGY
  32. F-1 •In appropriate formulation of project with unrealistic timeframe, lack of viable contingency plan resulting in changes in scope of work during execution and delay in decision making F-2 •Delay in Land acquisition and obtaining Environmental clearance F-3 •Adoption of inappropriate project procurement model and acceptance/appointment of lowest bidder for execution / as consultant F-4 •Lack of Project monitoring on part of client and contractor F-5 •Resource constraint- Non availability of skilled manpower and quality construction material F-6 •Use of obsolete technology Prominent factors responsible for delay
  33. Technique adopted Each sector will be analyzed using Analytical Hierarchy Process (AHP) model with respect to relative importance of various factors/Criteria During the analysis it is presumed that Project conception / Planning and execution only commences when availability of funds is ensured by the client / administrative authorities. Fund allocation is an administrative subject thus not taken as a constraint while analyzing the execution part of the infrastructure projects. Fundamentals of AHP • Intelligence (finding occasions for making a decision). • Design (finding possible courses of action). • Choice (choosing among courses of action).
  34. GOAL CRITERIA SUBCRITERIA ALTERNATIVE S
  35. Problem definition :-The first step of the decision process involves two components:- • Identify the problem and opportunities. • Identify the criteria and alternatives having a direct or indirect impact or the problem or the opportunities. Eliminating infeasible alternatives; - As part of problem definition, an array of variables are taken in to account. Each variable is studied in isolation with respect to the objective. Variable which falls within the preview of the study are taken in to account for further development of the model and rest all are discarded. This prioritization simplifies further analysis. Structuring a decision model :-After selecting a sizable number of criteria / alternatives the first step is, pair wise comparison and assigning a relative importance factor on a scale of 1 to 9. The process of formulation is explained with the help of a small example. Let there are three criteria’s namely ‘X’ , ‘Y’ and ‘Z’
  36. X Extreme Favor Very strong favor Strongly favor Slightly favor Equal Y 9 8 7 6 5 4 3 2 1 X Extreme Favor Very strong favor Strongly favor Slightly favor Equal Z 9 8 7 6 5 4 3 2 1 Y Extreme Favor Very strong favor Strongly favor Slightly favor Equal Z 9 8 7 6 5 4 3 2 1 X Y Z X 1 5 6 Y 1/5 1 3 Z 1/6 1/3 1 X Y Z AHP Matrix
  37. n= 3 Number of criteria (3 to 10) Scale: 1 Linear N= 1 Number of Participants (1 to 20) a: 0.1 Consensu s: n/a p= 0 selected Participant (0=consol.) 2 7 Consolidated Objective OPTIMIZATION Author LALIT Date 17-Mar- 14 EVM check: 4.931E-06 Table Criterion Comment Weights Rk 1 X 71.7% 1 2 Y 19.5% 2 3 Z 8.8% 3 Result Eigen value lambda : 3.094 Consistency Ratio 0.37 GCI: 0.2 8 CR: 9.8%
  38. A BRIEF ON IMPORTANCE OF DELAY FACTORS
  39. IN APPROPRIATE FORMULATION OF PROJECT WITH UNREALISTIC TIME FRAME, LACK OF VIABLE CONTINGENCY PLAN RESULTING IN CHANGES IN SCOPE OF WORK DURING EXECUTION AND DELAY IN DECISION MAKING (F-1) Project formulation at times, is based on other factors then the importance or necessity or feasibility itself. Planners resort to very optimistic time schedule, without taking in to account the complexity of crafting a plan in to an executable mechanism. Something akin to an automobile manufactures clamming fuel efficiency of the vehicle with a rider in fine prints ‘under ideal conditions’. The performance under working conditions divergently differs from ideal conditions. The improper formulation leads to a chain reaction. The site requirements during execution may go haywire then as planned with no viable contingency. If there are no viable contingencies planned, to further push the project at envisaged bottlenecks, may be the scope needs to be altered, in terms of design, in terms of funding, in terms of time frame and so on so forth. All above delay factors can be negated effectively and overall effects can be minimized if timely decisions are taken in the interest of the work, keeping aside the unwarranted hurdles and resistance at various levels in the organisational hierarchy
  40. DELAY IN LAND ACQUISITION AND ENVIRONMENTAL CLEARANCE (F-2) Infrastructure Projects are very large projects. As per the basic characteristics of the Infrastructure projects, these projects by nature itself affects large populations . The affected people, who have been deprived of their sole source of income, and the generation old lineage have been severed, may not get direct benefit of the project. More than a century and a half old, land acquisition laws still carry the legacy of ‘British Raj’. The Regulation Act ( Land Acquisition Act ) of 1824 supports the anarchical psychology of the ruler with little or no room for the grievances of the sufferers. The provisions of the act empower government to acquire any part of the land with or without consent of the owner. The compensation is paid based on the least rate paid on the sale deeds of the land in neighboring areas in recent past, leaving the owner in a lurch who has been deprived of the sole source of livelihood. Environmental impact :-All raw materials for the construction industry are obtained from one or the other from of quarrying. Starting from iron ore for manufacturing structural steel, to gypsum for cement and sand & aggregate etc there is dependency on natural resources. It is not only obtaining environmental clearances required for the project which is a small project in itself, but environmental aspects associated with the raw material also poses a potential delay factor for the progression of Infrastructure Projects.
  41. ADOPTION OF INAPPROPRIATE PROJECT PROCUREMENT MODEL AND ACCEPTANCE/APPOINTMENT OF LOWEST BIDDER FOR EXECUTION / AS CONSULTANT (F-3) Selection of appropriate project procurement model is a function of various independent variables like fund requirement , fund generation model , size and extend of the project , technical knowhow , socio – political environment , Government policies etc . Right selection of the executing agency will considerably reduce the probability of time /schedule over run. Selection of appropriate procurement model as per the need of the project will ensure availability right kind of contractors /executing agencies with requisite qualifications in terms of technical knowhow, financial capabilities etc. Improper selection of executing agency not only delays the work beyond permissible limits but also affects the quality of the work. India is also facing a shortage of good Engineering Procurement and Construction ( EPC) contractors that are capable of executing complex infrastructure projects. There are few companies in India with desired experience of executing large and complex Infrastructure projects. Availability of these contractors is a challenge as their order books are already overbooked.
  42. LACK OF PROJECT MONITORING ON PART OF CLIENT AND CONTRACTOR (F-4) Lack of planning and coordination. Poor communication between members of the project team and the project sponsor. Failure to identify problems and institute necessary design and programming changes. Lack of control over time and cost inputs. Improperly planned fund flow resulting in irregular/delayed payments.
  43. RESOURCE CONSTRAINT - NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL (F-5) 1.Manpower constraint No amount of automation, use of latest technology and labour saving devices can undermine the importance of skilled manpower A large nos of tradesman are required Availability of skilled man power is restricted Traditional systems of mustering manpower – through labour mates / Lamberdars
  44. 2.Material constraint Planners over look availability of basic raw materials Supply of basic raw materials like sand , aggregate , bricks etc is controlled by local influential's Gap in demand and supply Highly unpredictable rates RESOURCE CONSTRAINT - NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL (F-5)
  45. USE OF OBSOLETE TECHNOLOGY (F-6) Infrastructure projects cover a very large arena. Effective planning and execution entails use of state of art technology. Working with conventional methods may get desirable results for conventional projects. Infrastructure Projects are different from traditional construction projects in all aspects be it size of the project, quantum of work, number of agencies involved, extend of the project, affect on society etc. To ensure correct formulation and execution of Infrastructure project, uses of latest, innovative technology is a must.
  46. CONDUCT OF SURVEY Government Agencies EPC Contractors Financiers Project Affected Communities and NGOs Insurance and Guarantee Providers Regulators NHAI, IRCON , DMRC,IR,DEF INFRASTRUCTURE NBCCL , WADIA TECH , EPI , L&T NATIONAL BANKS ,ADB , INTERNATIONAL AGENCIES ,GOVT GOVT , INDUSTRY , COMMON MAN , NGOs PROJECT VEH NHRA , TRAI
  47. Factor Importance on numerical scale F-1 In appropriate formulation of project with unrealistic timeframe, lack of viable contingency plan leading to frequent changes in scope of work during execution and delay in decision making 1 2 3 4 5 6 7 8 9 F-2 Delay in Land acquisition and obtaining Environmental clearance 1 2 3 4 5 6 7 8 9 F-3 Adoption of inappropriate project procurement model and acceptance/appointment of lowest bidder for execution / as consultant. 1 2 3 4 5 6 7 8 9 F-4 Lack of Project monitoring on part of client and contractor 1 2 3 4 5 6 7 8 9 F-5 Resource constraint- Non availability of skilled manpower and quality construction material 1 2 3 4 5 6 7 8 9 F-6 Use of obsolete technology 1 2 3 4 5 6 7 8 9 QUESTIONNAIRE-1- TIME OVER RUN ANALYSIS •Six factors (F-1 to F-6) have been short listed; relevant to majority of infrastructure projects as a major reason for Time over Run. •1 to 9 numbers are written in front of each factor. ‘1’ stands for least importance and ‘9’ stands for maximum importance. •Please tick (√ ) one number in front of each factor expressing your opinion on its importance
  48. A B A to B or B to A Equally important Marginally important Slightly more important Important Very important Most important F-1 F-2 1 2 3 4 5 6 7 8 9 F-1 F-3 1 2 3 4 5 6 7 8 9 F-1 F-4 1 2 3 4 5 6 7 8 9 F-1 F-5 1 2 3 4 5 6 7 8 9 F-1 F-6 1 2 3 4 5 6 7 8 9 F-2 F-3 1 2 3 4 5 6 7 8 9 F-2 F-4 1 2 3 4 5 6 7 8 9 F-2 F-5 1 2 3 4 5 6 7 8 9 F-2 F-6 1 2 3 4 5 6 7 8 9 F-3 F-4 1 2 3 4 5 6 7 8 9 F-3 F-5 1 2 3 4 5 6 7 8 9 F-3 F-6 1 2 3 4 5 6 7 8 9 F-4 F-5 1 2 3 4 5 6 7 8 9 F-4 F-6 1 2 3 4 5 6 7 8 9 F-5 F-6 1 2 3 4 5 6 7 8 9 QUESTIONNAIRE-2 - RELATIVE IMPORTANCE OF FACTORS Please tick (√) one number in front of each comparison. Scale – 1 = Equally important, 2 to 3= Marginally important, 4 to 5= Slightly more important, 6 to 7= Important 8= Very important 9 = Most important e.g. F-1 # F-2 , if F-1 is as important as F-2 , the value is ‘1’ if F-1 # F-3 F-1 is very important as compared to F-3 , the value is ‘8’ Likewise for each comparison corresponding numerical value to be ticked Please also write whether you are comparing A →B or B→A
  49. Factor Importance on numerical scale F-1 In appropriate formulation of project with unrealistic timeframe, lack of viable contingency plan leading to frequent changes in scope of work during execution and delay in decision making 1 2 3 4 5 6 7 8 9 F-2 Delay in Land acquisition and obtaining Environmental clearance 1 2 3 4 5 6 7 8 9 F-3 Adoption of inappropriate project procurement model and acceptance/appointment of lowest bidder for execution / as consultant. 1 2 3 4 5 6 7 8 9 F-4 Lack of Project monitoring on part of client and contractor 1 2 3 4 5 6 7 8 9 F-5 Resource constraint- Non availability of skilled manpower and quality construction material 1 2 3 4 5 6 7 8 9 F-6 Use of obsolete technology 1 2 3 4 5 6 7 8 9 QUESTIONNAIRE-1- TIME OVER RUN ANALYSIS •Six factors (F-1 to F-6) have been short listed; relevant to majority of infrastructure projects as a major reason for Time over Run. •1 to 9 numbers are written in front of each factor. ‘1’ stands for least importance and ‘9’ stands for maximum importance. •Please tick (√ ) one number in front of each factor expressing your opinion on its importance
  50. 0% 5% 17% 78% In Appropriate formulation of project with unrealistic time frame, Lack of viable contingency plan leading to frequent changes in scope of work during execution and Delay in decision making 4% 7% 22% 67% Delay in Land acquisition and Environmental clearance - 25% 56% 11% 8% Adoption of inappropriate project procurement model and acceptance/appoin tment of lowest bidder for execution / as consultant 67% 27% 6% 0% Use of Obsolete Technology 2% 32% 63% 3% Resource constraint- Non availability of skilled manpower and quality construction material 43% 49% 8% 0% Lack of Project monitoring on part of client and contractor RESPONSE TO QUESTIONNAIRE -1 1 to 3 4 to 6 7 to 8 9
  51. A B A to B or B to A Equally important Marginally important Slightly more important Important Very important Most important F-1 F-2 1 2 3 4 5 6 7 8 9 F-1 F-3 1 2 3 4 5 6 7 8 9 F-1 F-4 1 2 3 4 5 6 7 8 9 F-1 F-5 1 2 3 4 5 6 7 8 9 F-1 F-6 1 2 3 4 5 6 7 8 9 F-2 F-3 1 2 3 4 5 6 7 8 9 F-2 F-4 1 2 3 4 5 6 7 8 9 F-2 F-5 1 2 3 4 5 6 7 8 9 F-2 F-6 1 2 3 4 5 6 7 8 9 F-3 F-4 1 2 3 4 5 6 7 8 9 F-3 F-5 1 2 3 4 5 6 7 8 9 F-3 F-6 1 2 3 4 5 6 7 8 9 F-4 F-5 1 2 3 4 5 6 7 8 9 F-4 F-6 1 2 3 4 5 6 7 8 9 F-5 F-6 1 2 3 4 5 6 7 8 9 QUESTIONNAIRE-2 - RELATIVE IMPORTANCE OF FACTORS Please tick (√) one number in front of each comparison. Scale – 1 = Equally important, 2 to 3= Marginally important, 4 to 5= Slightly more important, 6 to 7= Important 8= Very important 9 = Most important e.g. F-1 # F-2 , if F-1 is as important as F-2 , the value is ‘1’ if F-1 # F-3 F-1 is very important as compared to F-3 , the value is ‘8’ Likewise for each comparison corresponding numerical value to be ticked Please also write whether you are comparing A →B or B→A
  52. AHP Analytic Hierarchy Process n= 6 Input 1 Objective: RELATIVE IMPORTANCE OF DELAY FACTORS Only input data in the light green fields! Please compare the importance of the elements in relation to the objective and fill in the table: Which element of each pair is more important, A or B, and how much more on a scale 1-9 as given below. Once completed, you might adjust highlighted comparisons 1 to 3 to improve consistency. n Criteria Comment RGMM 1 F-1 Correct formulation of Porject 24% 2 F-2 Land Acquisition and Enviromental issues 48% 3 F-3 Project Procurment Model 13% 4 F-4 Project Monitoring 4% 5 F-5 Resource constranit -HR and Material 8% 6 F-6 Technology 3% 7 - 8 - 9 for 9&10 unprotect the input sheets and expand the - 10 question section ("+" in row 66) - 1 1 3/17/2014 a: 0.1 CR: 9% 1 Name Weight Date Consistenc y Ratio Scale Criteria more important ? Scale A i j A B - A or B (1-9) B 12 1 2 F-1 F-2 B 3 0.33 0.00 13 1 3 F-3 A 3 3.00 0.00 14 1 4 F-4 A 6 6.00 0.00 15 1 5 F-5 A 4 4.00 0.00 16 1 6 F-6 A 7 7.00 0.00 0 1 7 1.00 0.00 0 1 8 1.00 0.00 23 2 3 F-2 F-3 A 7 7.00 0.00 24 2 4 F-4 A 8 8.00 0.00 25 2 5 F-5 A 8 8.00 0.00 26 2 6 F-6 A 8 8.00 0.00 0 2 7 1.00 0.00 0 2 8 1.00 0.00 34 3 4 F-3 F-4 A 4 4.00 0.00 35 3 5 F-5 A 3 3.00 0.00 36 3 6 F-6 A 7 7.00 0.00 0 3 7 1.00 0.00 0 3 8 1.00 0.00 45 4 5 F-4 F-5 B 3 0.33 0.00 46 4 6 F-6 A 2 2.00 0.00 0 4 7 1.00 0.00 0 4 8 1.00 0.00 56 5 6 F-5 F-6 A 6 6.00 0.00 0 5 7 1.00 0.00 0 5 8 1.00 0.00 0 6 7 1.00 0.00 0 6 8 1.00 0.00 0 7 8 1.00 0.00
  53. AHP Analytic Hierarchy Process n= 6 Input 2 Objective: RELATIVE IMPORTANCE OF DELAY FACTORS Only input data in the light green fields! Please compare the importance of the elements in relation to the objective and fill in the table: Which element of each pair is more important, A or B, and how much more on a scale 1-9 as given below. Once completed, you might adjust highlighted comparisons 1 to 3 to improve consistency. n Criteria Comment RGMM 1 F-1 Correct formulation of Porject 12% 2 F-2 Land Acquisition and Enviromental issues 49% 3 F-3 Project Procurment Model 23% 4 F-4 Project Monitoring 8% 5 F-5 Resource constranit -HR and Material 5% 6 F-6 Technology 3% 7 - 8 - 9 for 9&10 unprotect the input sheets and expand the - 10 question section ("+" in row 66) - 1 3/17/2014 a: 0.1 CR: 8% 1 Name Weight Date Consistenc y Ratio Scale Criteria more important ? Scale A i j A B - A or B (1-9) B 12 1 2 F-1 F-2 B 7 0.14 0.00 13 1 3 F-3 B 2 0.50 0.00 14 1 4 F-4 A 2 2.00 0.00 15 1 5 F-5 A 3 3.00 0.00 16 1 6 F-6 A 4 4.00 0.00 0 1 7 1.00 0.00 0 1 8 1.00 0.00 23 2 3 F-2 F-3 A 4 4.00 0.00 24 2 4 F-4 A 6 6.00 0.00 25 2 5 F-5 A 7 7.00 0.00 26 2 6 F-6 A 9 9.00 0.00 0 2 7 1.00 0.00 0 2 8 1.00 0.00 34 3 4 F-3 F-4 A 5 5.00 0.00 35 3 5 F-5 A 6 6.00 0.00 36 3 6 F-6 A 8 8.00 0.00 0 3 7 1.00 0.00 0 3 8 1.00 0.00 45 4 5 F-4 F-5 A 3 3.00 0.00 46 4 6 F-6 A 5 5.00 0.00 0 4 7 1.00 0.00 0 4 8 1.00 0.00 56 5 6 F-5 F-6 A 3 3.00 0.00 0 5 7 1.00 0.00 0 5 8 1.00 0.00 0 6 7 1.00 0.00 0 6 8 1.00 0.00
  54. AHP Analytic Hierarchy Process (EVM multiple inputs) K. D. Goepel Version 12.08.2013 http://bpmsg.com Only input data in the light green fields and worksheets! n= 6 Number of criteria (3 to 10) Scale: 1 Linear N= 20 Number of Participants (1 to 20) a: 0.1 Co ns en su s: 75.3% p= 0 selected Participant (0=consol.) 2 7 Consolidated Objective RELATIVE IMPORTANCE OF DELAY FACTORS AuthorLALIT Date 17-Mar-14 EV M ch ec k: 2.4E-10 Table Criterion Comment Weights Rk 1F-1 Correct formulation of Porject 35.0% 1 2F-2 Land Acquisition and Enviromental issues 25.2% 2 3F-3 Project Procurment Model 13.7% 4 4F-4 Project Monitoring 7.5% 5 5F-5 Resource constranit -HR and Material 14.3% 3 6F-6 Technology 4.3% 6 7 0 8 0 9 for 9&10 unprotect the input sheets and expand the 0 10 question section ("+" in row 66) 0 Result Eigenvalue lambda: 6.126 Consistency Ratio 0.37 GCI: 0.07 CR: 2.0%
  55. 35.0% 25.2% 13.7% 7.5% 14.3% 4.3% RESPONSE TO QUESTIONNAIRE -2 Resource constraint- Non availability of skilled manpower and quality construction material Lack of Project monitoring on part of client and contractor Adoption of inappropriate project procurement model and acceptance/appoin tment of lowest bidder for execution / as consultant Delay in Land acquisition and Environmental clearance Use of Obsolete Technology In Appropriate formulation of project with unrealistic time frame, Lack of viable contingency plan leading to frequent changes in scope of work during execution and Delay in decision making
  56. CHAPTER-6 MITIGATION
  57. 1 IN APPROPRIATE FORMULATION OF PROJECT WITH UNREALISTIC TIMEFRAME, LACK OF VIABLE CONTINGENCY PLAN LEADING TO FREQUENT CHANGES IN SCOPE OF WORK DURING EXECUTION AND DELAY IN DECISION MAKING 2 DELAY IN LAND ACQUISITION AND OBTAINING ENVIRONMENTAL CLEARANCE 3 ADOPTION OF INAPPROPRIATE PROJECT PROCUREMENT MODEL AND ACCEPTANCE/APPOINTMENT OF LOWEST BIDDER FOR EXECUTION / AS CONSULTANT 4 LACK OF PROJECT MONITORING ON PART OF CLIENT AND CONTRACTOR 5 RESOURCE CONSTRAINT- NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL 6 USE OF OBSOLETE TECHNOLOGY PROMINENT DELAY FACTORS
  58. 1-IN APPROPRIATE FORMULATION OF PROJECT WITH UNREALISTIC TIMEFRAME, LACK OF VIABLE CONTINGENCY PLAN LEADING TO FREQUENT CHANGES IN SCOPE OF WORK DURING EXECUTION AND DELAY IN DECISION MAKING Type, Size and Location of the Infrastructure must be based on one and only one criteria i.e. ‘Actual need ‘Time spend in planning is directly proportional to time saved in execution.’ Planning in detail, in depth study of various options available will help in selection of the most viable option. Detailed study for identification of risk factors associated with the project and preparation of contingency plans. All contingencies must form part of the contract agreement between the client and execution agency so as to minimize time delay in decision making during execution. Technical design must be prepared with utmost caution. For large projects, authenticity of design to be ascertained by executing a pilot project. Lacunas noticed in pilot project will help in refining the design both from safety point of view and execution point of view. Design team must work in unison with execution agency, should act as facilitator. Design must encourage palletisation and modular construction for economy of resource and time. Database to be maintained for similar kind of projects executed in past with transparency. Database to be shared or available to agencies working on similar kind of projects. Formulation of realistic execution plan taking in to account all contingencies Actual Need based Detailed Planning Risk analysis and contingency Execution of Pilot projects for Large Infrastructure projects Maintenance of Data base Realistic Execution plan
  59. 1-IN APPROPRIATE FORMULATION OF PROJECT WITH UNREALISTIC TIMEFRAME, LACK OF VIABLE CONTINGENCY PLAN LEADING TO FREQUENT CHANGES IN SCOPE OF WORK DURING EXECUTION AND DELAY IN DECISION MAKING Timely decisions during execution will resolve all above discussed issues, even if over looked during planning stage. All Infrastructure projects are unique; have their own set of problems and solutions. Risk analysis and contingent planning will definitely iron out most of the hurdles of execution, but cannot relieve the executives/ managers / directors, the complete hierarchy of their responsibility to act as facilitators by taking timely decision. All infrastructure projects at all levels at every stages of execution will encounter unforeseen problems, may be related to design, environment, material, workers etc. Timely decision on part of the concern executives will help in considerably reducing the time over run. Decision making Accountability of the Hierarchy Flow of information top to bottom and bottom to top
  60. 2-DELAY IN LAND ACQUISITION AND OBTAINING ENVIRONMENTAL CLEARANCE Adoption of single window clearance system and appointment of central coordination agency with full powers even in the jurisdiction of the different states, specifically appointed for facilitation of infrastructure. Speedy and acceptable rehabilitation of the affected Cost of rehabilitation must form part of the project itself. Layout / Siting to be done very meticulously to identify disputed pockets Use of modern technology like Remote Sensing and GIS for selection of most suitable alignment of linear projects. Conduct of in detail Environment Impact Analysis (EIA) dovetailed with initial planning to ensure mitigation, well before actual commencement of the project. Award of contract only when adequate workable sites are available New construction techniques to be adopted, where ever possible to minimize use of land*. Environmental degradation by means of tree cutting, damage to flora and fauna must be minimized. Large scale plantation must form part of the project as a green initiative from infrastructure sector DMRC has been instrumental in adoption of new construction technique / suitable modifying the design to minimize land requirement. During Delhi metro construction DMRC adopted single segment construction for two tracks which reduced the land requirement per pier to 4m against 6 to 7 m for two separate girders Single Window Clearance Rehabilitation Cost of rehabilitation form part of the project Siting Environmental Impact Analysis New construction techniques Minimum damage to the environment
  61. 3-ADOPTION OF INAPPROPRIATE PROJECT PROCUREMENT MODEL AND ACCEPTANCE/APPOINTMENT OF LOWEST BIDDER FOR EXECUTION / AS CONSULTANT Involvement of execution agency at the planning stage along with the consultants. All works which are to be executed through contract must form part of the contract in correct quantities with right specifications. Evolve a system where Detailed Project Reports are reviewed before the commencement of tendering process so as to avoid large variations, adoption of non- uniform specifications for similar site conditions, sub-standard construction quality and inefficient project management on account of insufficient and inaccurate information / data contained in the DPRs The difference between client’s assessment of work and contractors quoting if more that 10% on the lower side, Client should insist on additional performance guarantee from the contractor, which can be enchased in the event of failure of compliance of contractual obligation. Financial institutions also must desist from dolling out easy loans on the name of the project to such contractors who quote non workable rates. Ensure standardization and uniformity in contract provisions and approval process which would enhance efficiency and help, avoid lapses; this would result in less contractual complications during project implementation Early involvement of execution agency Emphasis on DPR Correct Assessment Responsibility of Funding agencies Standardization of contract provisions / specifications
  62. 3-ADOPTION OF INAPPROPRIATE PROJECT PROCUREMENT MODEL AND ACCEPTANCE/APPOINTMENT OF LOWEST BIDDER FOR EXECUTION / AS CONSULTANT Performance of the executing agency to be judged keeping all environmental parameters in to account after reaching each time line objective Punitive actions to be taken on missing every time line objective. Recurring incidents of time line violation must be dealt firmly. Fix bidding capacity / handling capacity of consultants and contractors to ensure they are not over loaded and only take works as per their capacity. Incentive for timely completion may be initiated to encourage contractor to abide by the time schedule. In case of linear projects, the segmental approach of hiring more number of contractors, working on feasible small stretches and simultaneous commencement of work will help in meeting the time lines. Time period should be realistic. Optimistic scheduling must be avoided. Pre qualification bid must be encouraged for selection of eligible bidders. Periodic performance evolution Punitive action- Bidding capacity Incentives Segmental Approach Realistic Time schedule Prequalification bid
  63. 3-ADOPTION OF INAPPROPRIATE PROJECT PROCUREMENT MODEL AND ACCEPTANCE/APPOINTMENT OF LOWEST BIDDER FOR EXECUTION / AS CONSULTANT Lateral flow of information on performance of various contractors must be shared among all agencies. Non performing contractors must be barred from participation in bidding in all departments. Mobilization advance is given to the executing agency as a soft loan with an intend to ease out initial funding requirement. Utilization of the mobilization advance must be closely monitored. Preferably mobilization advance must be released in installments after satisfactory progress and utilization of initial installment released. Possibility to be explored to make direct payment of standard items like cement and steel procured by the contractors to the suppliers , to ensure proper utilization of money. Performance of contractors Ban on non performing contractors Utilization of Mobilization advance Direct payment by client to suppliers
  64. 4-LACK OF PROJECT MONITORING ON PART OF CLIENT AND CONTRACTOR Set up of well defined Project Monitoring Organization with specific responsibilities and accountability with specific targets. Timely flow of information from top to bottom in terms of targets and solution to specific problems of execution and, from bottom to top in terms of feedback and problems encountered during execution must be ensured. Periodic updates and review of targets. Lateral coordination among various agencies working at site must be ensured through a nodal agency. No team should work in isolation; all activities should be well synchronized. Quality control organization work as part of the Project Monitoring Organization should be proactive, and ensure quality work execution. This will save lot of time and trouble of rejection / demolition of defective work which may lead to litigations and thus impinge delay. Monitoring is not enough to ensure timely completion of projects it must be supported with action oriented solutions and also it will require improving system and procedures. Accountability Communication Review and Updates Coordination Proactive attitude Improved Procedures
  65. 5-RESOURCE CONSTRAINT- NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL Shortage of Skilled man power Establishment of a well defined Project Management Organization, formulation of working guide lines, unambiguous targets for core appointments and effective management & monitoring can, up to some extend help in negating the effects of shortage of manpower at management and supervisory level. Encourage use of labour saving devices. This aspect will be discussed in detail under ‘Use of obsolete technology’ heading. Motivation, performance related incentives, welfare and release of timely payments to the construction workers will ensure enhanced performance. Roll of ‘Labour Mates’ or ‘Lamberdars’ as sole employment agency for construction workers must be scrutinized. These so called employment agencies not only blackmail the contractors but also exploit the construction workers. Well defined strategies Use of labour saving devices Motivation Organized sector for labour
  66. 5-RESOURCE CONSTRAINT- NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL Shortage of Skilled man power Entry of organized sector to look in to the need of human resource requirement at all level in infrastructure sector must be explored. Implementation of Government schemes like Mahatma Gandhi National Rural Employment Guarantee Act (MNREGA) must be in synchronization with Infrastructure Project implementation. As per data available from the official web site of NREGA, ‘nrega.nic.in’ , during the financial year 2013-14 , a total of 644 districts comprising of 6576 blocks , 247643 Gram Panchayts and 778134 villages were covered under this scheme with a total expenditure on payment of wages as Rs 37648 crores. As evident from the data, NREGA has a very vast network across the country, this agency if synchronized with infrastructure project implementation, will not only ensure availability of construction workers for infrastructure development but also ease the Government of it financial burden of Rs 37648 crorers as welfare funds. The financial liability will automatically shift to concern infrastructure sector. This synchronization will also abolish the monopoly of so called labour employment agencies. Entry of Organized sector Synchronization with Govt Policies
  67. Shortage of quality construction material Encourage scientific quarrying methods by bringing in reforms in auction/allotment procedures for quarrying of earth resources. Standardization must be bring in, to the supply chain of noncore construction material. Inventory management takes precedence over all activities. Adequate funds must be allocated to maintain minimum inventory level. Availability of material during lean period of supply must be planned to ensure availability for sustenance of work and also to minimize the fund requirement which needs to be blocked for bulk procurement. Standardization of raw material supply by encouraging entry of organized sector and bring in more transparency in the system. Design and technical planners must make an endeavor to encourage use of locally available material to ensure timely availability and cut down cost. Recycling of construction waste to be encouraged to cut down cost and also as a green initiative on part of infrastructure sector. Encourage use of alternate construction materials. 5-RESOURCE CONSTRAINT- NON AVAILABILITY OF SKILLED MANPOWER AND QUALITY CONSTRUCTION MATERIAL Reforms Supply chain management Entry of organized sector Encourage use of local materials Recycling of construction waste Alternate construction materials
  68. Use of GIS , latest planning and designing software for at planning stage Use of moduler construction tech , Use of precast concrete system , Tunnel form work , Hybrid Concrete construction Use of correct T&P to save time and labour Recycling of construction waste Use of latest less time consuming non destructive techniques for quality control ( Acoustic Emission techniques) 6-USE OF OBSOLETE TECHNOLOGY Planning stage Modern contr Tech Use of T&P Recycling of waste Non destructiv e testing
  69. 7-SCOPE FOR FUTURE STUDIES
  70. Implication of extra time and cost incurred during planning and its cost benefit analysis on the overall Time – Cost schedule of the project. Need for land reforms – formulation of viable policies for land acquisition, compensation to the affected population in order to reduce long delays. Study on environmental impact of Infrastructure Projects, mitigation techniques and impact on Cost-Time schedule of the project. Standardization of noncore construction material like sand, bricks, aggregate etc. Socio economic impact and Cost benefit analysis. Cost effective recycling of construction waste. Basic frame work for introduction of organized sector in the field of construction workers – Single window HR solutions for Infrastructure projects. Modern construction techniques to reduce time and cost.
  71. 8-CONCLUSION
  72. WHILE INDIA HAS THE 2ND LARGEST ROAD NETWORK, SUBSTANTIAL (85%) FREIGHT MOVEMENT IS CONFINED TO 6% OF THE NETWORK. FURTHER, THE ASPIRATION OF 20 KM/DAY HAS NOT EVEN PENETRATED INTO PLANNING 85 63 53 15 37 47 Passenger Freight (BT) Freight (BTKM) Road Rail Source: Annual Report 2011‐12, Ministry of Road Transport & Highways Source: Planning Commission Substantial freight is carried through roads, however, lead distance for road transport is much shorter Despite being one of the largest road network in the world, the NH constitutes only 2% of the total road network in India 2% 4% 6% 88% NH/Expressway State Highways Major District Roads Other District Roads & Rural Roads National highways (2% of the total road length) carry 40% of the total road traffic in India State highways constitute 4% of the total road length National highways and State highways capacity (considering equivalent to single lane – 3.5m width) are around ~ 5% and ~ 6% respectively of total equivalent lane km in India The aspiration of 20 km /day of construction has never been considered in the planning process % Modal Share % of Road to Total Network 1,035 817 2,885 3,519 3,165 2,500 2,500 724 636 1,685 2,203 2,693 1,780 2,247 0 5 10 15 20 25 0 500 1,000 1,500 2,000 2,500 3,000 3,500 4,000 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 Target km Achievement km Target km/day Actual km/day Planned km/day Missing the physical targets of NH regularly Source: Planning Commission, EY analysis Road Rail Ports Airways & IWT Urban Rural Infra Construction Power
  73. 28% 46% 24% 2% Below Standard Single Lane Standard Single Lane Standard Double Lane Standard Multi Lane HIGHWAYS DEVELOPMENT IS SUBDUED BY POLICY AND FINANCIAL IMPERATIVES; SUBSTANTIAL REFORMS ARE REQUIRED Widening of NH has created substantial capacity ► Congested highways require significant width & length expansion ► 60% of State Highways are single lane or less and 75% of National Highways are 2-lane (one lane in each direction) or less ► Construction lagging behind aspirations (5 km/day vs 20km/day) ► Lack of institutional capacity and delays due to land acquisition, utility shifting & environmental clearance leading to time and cost overrun (7% of the projects) ► No clear plans for maintenance of highways ► Inadequate fund allocation for maintenance leading to premature failure of highway sections ► Private sector willing to contribute but remains cautious ► 40% of XIth plan investments (~USD 30 bn) came from private sector ► USD 3.2 bn of equity locked in earlier projects needs to be released to allow existing players to bid for new projects (report of BK Chaturvedi Committee) Source: MORTH Source: MORTH 2007 2012 2007 7% 53% 36% 4% 2011 33% 55% 12% Single Lane 2 Lane 4/6/8 Lane 21% 54% 25% Majority of SH are still single lane, some states have started SH development programs Road Rail Ports Airways & IWT Urban Rural Infra Construction Power
  74. • WHERE DO WE STAND ? • WHAT IS WRONG ? • HOW TO RECTIFY ? • HOW TO ENSURE TIMELY DELIVERY OF MUCH NEEDED INFRASTRUCTURE? AS PER THE STATISTICS AVAILABLE ON INFRASTRUCTURE THIS PAPER IGNITES THOUGHT PROCESS OF ALL ENGINEERS , MANAGEMENT WIZARDS AND FINANCERS
  75. Its a beginning