SlideShare a Scribd company logo
1 of 52
Download to read offline
I S O / T S 1 6 9 4 9 R E G I S T E R E D • I S O 1 4 0 0 1 R E G I S T E R E D • w w w . l i t e n s . c o m
DESIGN FMEA
Training developed for Litens Automotive
developed by Julian Kalac, P.Eng
Educational training for
Litens Automotive
AGENDA TRAINING
 Recap on DFMEA BASICS , FAILURE VS CAUSE,
 DFMEA consequences of not doing it properly
 PREVENTION CONTROLS
 CRITICAL DIMENSIONS/TOLERANCES
 Good vs Bad DFMEA Litens Examples
 Design of Experiment –2 𝑛 Factorial design
 REVIEW / DEVELOPMENT OF YOUR DFMEA
 CRITICAL DIMENSIONS AND TOLERANCES
September 15, 2016
Page 2
WORKING
DFMEA
1-2HRS
TRAINING
2-3HRS
OBJECTIVE
 Review the basics of Design FMEA
 Consequences of poorly done DFMEA (GM Ignition Switch)
 Learn to identify Single Point Of Failures SPOF, and ho to prevent them
 Learn to use DOE to analyze surrogate data to optimize new designs
 Learn basics about Design for Six Sigma (DFSS), process capability and
design for loss of function
 Review your Designs and DFMEA
September 15, 2016
Page 3
CANADIAN LAW
• Under Canadian law, manufacturers have a duty
1. DUTY TO WARN consumers of the dangers inherent in the
use of their products of which the manufacturer has, or
ought to have, knowledge.
2. NEGLIGENT DESIGN –manufacturer will be held liable
under Canadian Law for foreseeable injury or damage
caused by products that were negligently designed.
3. DEFECTIVE PRODUCT - manufacturer will also be held
liable for any manufacturing defects
FMEA are specifically developed for that purpose.
September 15, 2016 Page 4
WHAT IS DFMEA ?
• Failure Mode and Effects Analysis (FMEA) is an engineering analysis tool used to
identify and prevent failures before they actually happen
• DFMEA are used early in the development phase while the design can be
changed as a Design Verification method
• The most efficient way to do a DFMEA is during the design review when, the
entire design is being reviewed and the FMEA form can be used as a guide
• DFMEA IS NOT A FORM TO FILL OUT FOR COMPLIANCE REASONS
September 15,
2016
Page 5
September 15, 2016
WHAT IS DFMEA ?
Page 6
Why is FMEA important?
1. Due Diligence – Product Safety Risks, Design Reliability,
Regulations AIAG, CSA, OHSA, TS-16949 Design Verification,
2. Required for all new designs Proactively Identify and Prevent
Design Failures (safety and performance) before the design is
released into production
3. Reduces warranty costs - far less expensive to prevent problems
early in product development than fix problems after launch.
4. Litens VP Engineering –Critical Dimensions MUST be DERIVED
FROM DFMEA and tolerances justified –WHY IS THAT IMPORTANT?
WHAT ARE OUTPUTS OF A DFMEA
1. list of Critical Component Dimensions , their specifications
(dim/tolerance) and evidence SHOWING how the Critical
Tolerance relates to the Cause of Failure
2. A list of potential Failure Modes and Causes, prioritized by RPN
3. A list of action items that have been taken or will be taken to
PREVENT the Failures Modes/Causes before PPAP
4. DVP Verification Plan (Conditions, Acceptance Criteria)
5. Lessons learned
FMEAs are legal documents
It is important for the FMEA team to
understand that FMEAs are legal
documents that support the
demonstration of due care in product
development. As legal documents, they
are subject to subpoena for legal
proceedings.
FMEAs, published by John Wiley & Sons. [1]
September 15, 2016 Page 9
FMEA SYSTEM BREAKDOWN
Is Sub-system = Sub-Assy ??
Types of FMEA
SYSTEM FMEA/CONCEPT FMEA
• Analysis is at highest-level of an entire system, (Vehicle)
made up of various subsystems (electrical, front suspension,
• The focus is on top level interfaces/interactions between
different subsystems and surrounding environment
• Looks at Single-point failures (where a single component
failure can result in complete failure of the entire system)
• Example of System FMEA is an Application FMEA, focused
on Application of an existing design
DESIGN FMEA
• Design FMEA evaluates the entire Product Design all
levels contained within the boundaries of the product , (Final
Assy, components, sub-assy)
• The scope of the Design FMEA includes the subsystem or
component itself, as well as the interfaces between adjacent
components.
• Critical dimensions are developed from critical failure modes
within the DFMEA
• DVP&R Tests criteria are developed and confirmed
Process FMEA
• Process FMEA focuses on the design of the assembly
process, development of process specifications in order to
meet the critical dimensions specified in the DFMEA
• The scope of a Process FMEA can include manufacturing
and assembly operations, shipping, incoming parts,
transporting of materials, storage, conveyors, tool
maintenance, and labeling.
WHEN TO DO A DFMEA?
Case 1: NEW DESIGNS, new technology, or new process. The scope
of the FMEA is the complete design, technology or process.
Case 2: MODIFICATIONS TO EXISTING DESIGN or process (assumes
there is a FMEA for the existing design or process). The scope of the
FMEA should focus on the modification to design or process, possible
interactions due to the modification, and field history.
Case 3: APPLICATION - Use of existing design in a new
environment, or Application . The scope assumes there is an FMEA
for the existing design or processes of the FMEA is the impact of the
new APPLICATION or Environment on the existing design or process.
September 15, 2016
Page 17
September 15, 2016
Consequences of not doing a DFMEA
Page 18
September 15, 2016
DO NOT WAIT FOR THIS TO HAPPEN PREVENTED
Page 19
September 15, 2016
BECAUSE THIS IS THE EFFECT
Page 20
September 15, 2016
GM IGNITION SWITCH FAILURE
Page 21
OVER 300 deaths
23 Mil cars recalled
from 2004 2014
GOOD PRACTICES TO AVOID BAD EVIDENCE
FMEA
•It has to be done correctly:
•A well-done and properly completed FMEA can be a
strong ally in the defense for the manufacturer in
product litigation.
•On the other hand, a poorly done and haphazard
completion of an FMEA can be used to support the
prosecution.
September 15, 2016 Page 22
September 15, 2016
IDENTIFY POTENTIAL FAILURE MODES WITH IGNITION SWITCH
Page 24
September 15, 2016
GM IGNITION SWITCH FMEA
Page 26
GM IGNITION SWITCH FMEA
FAILURE MODE FAILIURE EFFECT S CAUSE OF FAILURE O
DESIGN
CONTROLS
D RPN RECOMMENDED ACTION
STALLS VEHICLE ON
HIGHWAY---NOT
SAFETY CAN STEER
CAR OFF TO THE SIDE-
-DRIVER NUISANCE
10
IGNITION SWITCH
REQUIRES LOW TORQUE
TO TURN --KEY CHAIN
TOO HEAVY --
1
FOB
SPECIFICATI
ON FOR
WEIGHT
1 8
ISSUE TSB TO REMOVE ALL
KEYS FROM FOB -CLOSE
FMEA
DRIVER NUISANCE 8 IGNITION SWITCH LOW TORQUE 2
VEHICLE
RESTART
1 8 NONE CLOSE FMEA
Requirement not defined in units
of measure (VALUES)
Lessons Learned from GM ignition Switch
 The Federal Crown Prosecutor report suggest that the original GM
ignition switch specification contained vague and ambiguous
targets for the detent torque, which were never achieved, and
provides no evidence that the specification or acceptance criteria
were developed using failure modes effects analysis or similar
techniques.
 As a direct result GM engineers failed to understand the significance
of the available evidence for over ten years - and they never asked "Is
the specification is fit for the purpose?" - with serious consequences
for the company and it's consumers.
September 15, 2016
Page 27
September 15, 2016
EXPLOSIVE PINTO FUEL TANK DESIGN
Page 28
DFMEA and PFMEA connection
Critical / special
characteristics
Brooks Approval:
Date Approved:
Effectivity Date:
Part Number: PCP Number Prepared by:
Part Number Revision: PCP Revision Checked by:
Part Name: PCP Rev Date: Approval:
Characteristic Description
Specification
&
Tolerance
Key
Dim
Measurement Technique
Sample size&
Frequency
Record
CoC Verification Every lot
Dimensions caliper
AQL 1.0
Every lot
diameter Ø160±1 CMM
diameter Ø130±1 CMM
diameter Ø120 G6 Y CMM
diameter Ø65±.0.1 CMM
chamfer C2 CMM
dim 10 -0.1/0 HG
dim 5±0.2 HG
dim control 19 to19.2 Caliper
Roughness 63 √ C SRT/Comparator
3rd Process,
0.02 Y CMM
0.02B Y CMM
Ø0.02B Y CMM
4th process
Hole Ø5H8 PG
dim 26.5±0.03 Y CMM
Tap M6 Tap hole Thread Gauge
Hole
Ø4.5(all the hole
dimension)
CMM
50 De-Burring De-burring tools work instruction #: xxxx
Break All Sharp
Edges and burrs
visual Inspection
AQL1.0
every lot
Record on QA Plan
XXXX
StopDe-
burringRework &
CAR
Tap M6 Tap hole Thread Gauge
Hole Ø5H8 PG
Roughness 63 √ C SRT/Comparator
Appearance to Spec XXXX Visual inspection
70
Treatment/Finish
ing
Treatment House
Specification #:xxxx
Treatment PCP #:xxxxx
Electroless Nickel Plating [0.003-0.005mm]
X-Ray Visual
inspection
AQL0.65
Every lot
COC from Supplier Rework
Qualified Plater
(ABC Company)
diameter Ø120 G6 CMM
hole Ø5H8 PG
tap M6 Tap hole TG
roughness All surface Roughness SRT/Comparator
Appearance
No stain, masking,
color to sample
Visual inspection
90 Packaging
work instruction xxx-
xxxx
Visual
Each Lot
Received
STD packaging
method
Repack and
Validate
Supplier Name:
Process Control Plan
Supplier Number:
Workcell / Location
Process
Step
Number
Process Name /
Operation
Description
Machine, Device, Jig,
Tools for
Manufacturing
Ref Doc. Number/
Specification No
Control Methods/Measurement
Reaction Plan
Remarks
(Special Process)
10
work instruction xxx-
xxxx
STEEL, CORROSION RESISTING, 304 OR 304L
IQC inspection
sheet
Product / Process Characteristics
Receive Raw
Material
Incoming
Return to Supplier.
RMA process XXX
Notify production of new
delivery date.
40
Manufacture work
instruction #: xxxx
Machining
Hole, Profile
cutting, Tap
holes
30
Manufacture work
instruction #: xxxx
Bottom plane
CNC Milling#:xxx
Tool #:xxx
Fixture#:xxx
20
Drawing #:xxx
Manufacture work
instruction #: xxxx
80
Post-treat Inspection
procedure xxxx
Pre-Treatment
Post-Treatment
Inspection
60
Specification #:xxxx
Treatment PCP #:xxxxx
Machining
N/A
CNC Lathe#:xxx
CNC Program #:xxxx
Tool#:xxxx
Fixture#:xxxx
Grinding#:xxx
Tool #:xxx
Fixture#:xxx
2pcs Every
machine Set up
1pcs every two
hours
In-Process
In-Process Insp.
From CMM
2pcs Every
machine Set up
1pcs every hour
In-Process
In-Process Insp.
From CMM
2pcs Every
machine Set up
1pcs every two
hours
In-Process
In-Process Insp.
From CMM
AQL0.65
Every lot
Pre-treatment
inspection record
AQL0.65 for
critical
dimensions and
100% for Visual
inspection
COC from
supplier and Post
treatment
inspection record
Rework/CAR send
for rework
Raise CAR send for
rework
Stop machining/
Fine-tune the
Setting and re-
inspect
Notify Supervisor
Stop machining/
Fine-tune the
Setting
Qualified Operator
Stop machining/
Fine-tune the
Setting
Critical Dimensions &
tolerances from DFMEA
DFMEA and DVP&R connection
Test description input
to the DVP&R.
Email: Email:
Phone: Phone:
Fax: Fax:
Sample
Size or
Truck #
Req. Start End Start End
1)
Material Compliance
DRD# 3.2.3.1.1
Rev #
Dated ##/##/##
Per CEMS D-28
Rev #
Dated ##/##/##
1a) No 6.3 Resin Requirements Table 2 1 day PV
All Must
Pass
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 1 2013-12-31 2013-12-31 1 Lot
1b) No
6.3 Specific Gravity Table 4 Per ASTM
D792
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 2 2013-12-31 2013-12-31 1 Lot
1c) No
6.3 Tensile Strength - Ultimate
Table 4
Per ASTM
D638
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 3-4 2013-12-31 2013-12-31 1 Lot
1d ) No 6.3 Ultimate Elongation Table 4
Per ASTM
D638
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 5-6 2013-12-31 2013-12-31 1 Lot
1e) No 6.3 Flexural Modulus Table 4
Per ASTM D
790
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84555 by
GE
D 5-6 2013-12-31 2013-12-31 1 Lot
1f) No
6.3 Flexural Strength Table 4 Per ASTM D
790
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 7-8 2013-12-31 2013-12-31 1 Lot
1g) No
6.3 Impact Resistance Table 4
Per CEMS-DT-4 /
Rev #
Dated ##/##/##
Per ASTM D
790
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 9-10 2013-12-31 2013-12-31 1 Lot
1h) No
6.3 Deflection Temperature
Table 4
Per ASTM D
790
1 day PV
All Must
Pass
Test
Plaques
D 1 Lot 2013-12-31 2013-12-31
84576 by
GE
D 11-12 2013-12-31 2013-12-31 1 Lot
1i) No 6.3 Color Table 4 1 day PV
All Must
Pass
Molded Part
Detail D.01
D 2 Parts 2013-12-31 2013-12-31 ASD256 D 13-14 2013-12-31 2013-12-31 2 Parts
1j) No
6.3 Dimensional Stability Table
4
4 hours PV
All Must
Pass
Molded Part B 2 Parts 2013-12-31 2013-12-31
ETA Lab
Rpt 56843
C 13-14 2013-12-31 2013-12-31 2 Parts
2) No 6.3 Table 4 Other Characteristics 1 day PV
All Must
Pass
Plated part C 1 Part 2013-12-31 2013-12-31
HB dated
8/21/06
C 15-16 2013-12-31 2013-12-31 8 parts
3) No 6.3 Table 4 Other Characteristics 1000 Hours PV
All Must
Pass
Painted part C 1 Part 2013-12-31 2013-12-31
LCL
Reported C 17-18 2013-12-31 2013-12-31 9 Parts
Z2 = Finish Paint per TMS-9008 Color: Argent, NAV
8752
Pass Accept
Testing completed by Supplier
see Paint Tab
Grille, Painted, Fixed
Testing to be
completed by Supplier
Z1 = Chrome Plate per MS-7071B_fk Pass Accept
Testing completed by FGH
Platers, Inc, See Chrome Plate
Tab
Salt Spray applied at 16,
32 56 Hours (Grille,
Chrome, Fixed )
Testing to be
completed by FGH
Platers, Inc, See
Chrome Plate Tab
AA88 = 4 hours at 88° C
Parts will conform to the dimensions and tolerances shown
on the engineering drawings after four hours exposure in
an oven at the temperature indicated by the numeral of the
suffix AA - symbol expressed in degrees Celsius.
Pass Accept
Part Testing Performed by ABC
on Molded Part
Molded part (No
Assembly)
Part Testing to be
performed by ABC
AC1 = Integrally colored Part Pass Accept Verified by ABC To be verified by ABC
S90 = 90° min. deflection temperature at 1820 Kpa
98 C
Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
R235 = 36 in/lbs force at minus 30° F
Parts will show no evidence of cracking when impact
tested at point or points indicated on engineering drawing.
299 in-lbs. - Material
Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
N60 = 60 MPa min.
72 MPa
Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
M17 = 1700 MPa min.
2060 MPa
Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
L100 = 100% min. 150% Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
K-40 = 40 MPa min. 50 MPa Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
DF1140 = 1.140+/- 0.05 01-Jan-00 Accept
Material Testing Performed by
GE on Test Plaques
Material to be tested
by GE
PC+ABS = Polycarbonate + Acrylonitrile / Butadiene /
Styrene
PC+ABS = Polycarbonate
+ Acrylonitrile / Butadiene /
Styrene
Accept
Material Testing Performed by
GE
Material to be tested
by GE
Sample ID
Actual Timing Sample
Size Tested
PC + ABS DF1140 K40 L100 M17 N60 R235 S90 /
AC1 AA88 Z1 Z2
Test Location / Test
Verification Resp.
Rqmt
Source
Sample
Type
Scheduled Timing
Report #
Sample
Level
Actual Results
Test Results Status
Accept / Reject
Tests Completed by Notes / Remarks Test Stage
Target
Rqmts
Test
Number
Compliance /
Regulatory /
S C/CC/KP C
Specification / Test Name
Test Method
or Test
Procedure
Duration of
Test
Acceptance Criteria
630-123-4568 815-123-4568
Testing details and Results Planning information Actual Timing
steve.peterson@navistar.com j.foley@onetwothree.com
Test Stage ED = Engineering Devel't Test, DV = Design Verification, PV = Production Verification, CCT = Continued Compliance Testing
Target Requirements. State required probability or reliability and confidence of meeting criteria, e.g. R90, C90 or all must pass. Sample
Type / Level A = Prototype (Handmade), B = Prototype (Tooled), C = Production Tool (Not Process), D = Production Tool & Process
630-123-4567 815-123-4567
Title: Chief Engineer Title: Engineering MGR
Grille, Chrome, Fixed 123659749 C
State: MN Country:
Zip / Postal Code: 60586
X
Component (s):
w/ Navistar Part
Number(s)
Rev
USA
Grille, Chrome, FIxed 1315449691 D
Navistar Design Engineer Supplier Design Engineer (Key Contact)
Grille, Asm 23614649 A
Name: Steve Peterson Name: James Foley
Grille, Asm
Assembly Name:
w/ Navistar Part
Number(s)
Rev Supplier
Address:
12364 Jackson St.
23614649 B
City: Andrewsville
Date:
1236364 A 2012-02-13
Subsystem: Grille Fixed Supplier Code: 12345 Affected Navistar Program(s): XVY 1235
DESIGN VERIFICATION PLAN AND REPORT
ISQ-011-FO
Rev: A Date: 04/01/2013
System: Exterior Trim Supplier Name: One, Two, Three 123 Inc.
Core Team:
(list names)
A. Hernandez, B. McGruff, S. Orlander, K.
Keller
DVP&R Number: Revision Level:
DVP&R example
Acceptance Test Criteria from DFMEA--
-example Min Torque= 70Nm
FAILURES, SYMPTOMS AND ROOT
CAUSE ANALYSIS
Design FMEA
34
Failure Mode
ANTI-FUNCTION
(FAILURE MODE)
2016-09-15
FMEA Thought Process
35
9/28/2013
DFMEA --# 1 QUESTION: WHAT CAN GO WRONG?
36
1. Ask Leading question
“what can go wrong inside the design that would prevent it
from functioning?”
2. Once a Failure is identified then ask the question:
If this failure occurred, then what could happen?
Failure Modes & Causes
Failure Modes: Identify the manner in which an item could potentially
fail to meet it’s design intent. Example
 BROKEN Spring, DEFORMED Housing, Seal Leak
 Piston SEIZES , Valve Port BLOCKED, Oil Contaminated
CAUSE: is the component feature that created the failure condition
 Broken Spring Cause: Yield strength of spring exceeded
September 15, 2016
Page 37
 A single point of failure (SPOF) is an undesired component/part if it
fails, will cause the entire system to fail,
 SPOF can be an Assembly (master brake cylinder Assy) or a single
component (air bag sensor)
 It could be at the top level of the system (air bag sensor) or deep
internal not visible to the user (master brake cylinder)
 SPOF are identified in FMEA as Critical (Y C) or Special Characteristics
(SC) and will relate directly to a severe failure mode (sev 8 or higher)
September 15, 2016
SINGLE POINT OF FAILURE (SPOF)
Page 38
39
Failure Mode = FloodWithWater
Symptoms = Pipes Leaking
POSSIBLE ROOT CAUSE(S) =
1. Condensation from pipes due to
temperature change OR/AND
2. Faulty Gasket OR/AND ,
3. Corroded Pipe Fittings OR
4. Over-Pressurized Pipes OR
5. ………………
$$
$
$$
$ $
$
$
$
$
Root Causes vs. Symptoms of Failure Modes
DFMEA INPUTS/OUTPUTS
The following elements/tools may provide input to the DFMEA:
• Requirements, (Customer, Product Specs, Regulatory, etc.)
• Historical performance-Warranty/Field Returns, failures, Recalls,
• Free Body Diagram
• P-Diagram
• FEA Analysis
• Boundary Diagram and Interface Matrix
• Functional Block Diagram
• WC -Tolerance Stack Up Analysis, RSS, % Contribution, Monte Carlo,
• Stack Up Analysis
• DESIGN of Experiment DOE
DFMEA INPUTS
DFMEA OUTPUTS (MANDATORY)
1. A list of Critical Component Characteristics and their
specifications (dim/tolerance) (PFMEA & CONTROL PLAN)
2. A list of potential Failure Modes and Causes, prioritized by RPN
3. A list of Design action items to PREVENT the Failures/Causes
4. DVP Verification Plan (Conditions, Acceptance Criteria)
5. Lessons learned
BOUNDARY DIAGRAM—SYSTEM
Catalytic Converter Assy
September 15, 2016
INTERFACE MATRIX –FAILURE MODES
Page 44
P-DIAGRAM—CAUSES OF FAILURE
Catalytic
Converter Assy
Y= f (x1, x2, x3,….)
Y=OUTPUTX=INPUT
2 Flange Hard Stop Sensor Mount Front + 28.700 0.050 -0.050 28.750 28.650 28.750 28.650 0.100
3 Sensor Mount Front Sensor Mount Rear + 2.000 0.050 -0.050 2.050 1.950 2.050 1.950 0.100
4 Sensor Mount Rear Housing Rear + 30.100 0.050 -0.050 30.150 30.050 30.150 30.050 0.100
5 Housing Rear Exterior Gap Rear - 16.500 0.050 -0.050 16.550 16.450 -16.450 -16.550 0.100
A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: 0.57 0.07
0.112
Mean + Statistical Tolerance = 0.432
Mean - Statistical Tolerance = 0.208
Total Target Dimension= 0.224
Prepared By: Julian Kalac Date: 11-Jun-16
Stack Description: To determine the varying distance between the rear of the coax board and interior wall of the rear housing
Starting Point: Flange Stop Surface
Ending Point: Housing Rear
From To
Upper
Tolerance
Lower
Tolerance
Upper
Limit
Lower
Limit
1 Sensor Board Rear Shims + 0.127 0.000 0.000 0.127 0.127 0.127 0.127 0.000
2 Shims Sensor Board Rear + 0.787 0.079 -0.079 0.866 0.709 0.866 0.709 0.157
3 Sensor Board Rear Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174
4 Stand Off FPGA Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316
5 FPGA Board Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174
6 Stand Off MISC Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316
7 MISC Board Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174
8 Stand Off Coax Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316
9 Coax Board Interior Read Housing + 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
10 Interior Read Housing Housing Rear Rear + 7.200 0.050 -0.050 7.250 7.150 7.250 7.150 0.100
11 Housing Rear Rear Sensor Mount Rear - 30.250 0.050 -0.050 30.300 30.200 -30.200 -30.300 0.100
A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: -2.9971 -4.8245
0.330
Mean + Statistical Tolerance = -3.581
Mean - Statistical Tolerance = -4.241
Total Target Dimension= 3.911
**For component/dimensions in parrellel (standoff and connectors) the average standard deviation is used, [AveTolerance]=[Tolerance]/[sqrt(number of parrellel features)]
Prepared By: Julian Kalac Date: 11-Jun-16
Stack Description: To determine the varying distance between the optical center of the housing and sensor
Starting Point: Optical Center
Ending Point: Sensor Center
From To
Upper
Tolerance
Lower
Tolerance
Upper
Limit
Lower
Limit
1 Optical Center on Housing Front 2 Alignment Holes Axes + 0.000 0.035 -0.035 0.035 -0.035 0.035 -0.035 0.070
2 2 Alignment Holes Axes Hole Side (1/2 Dia) + 0.000 0.005 -0.005 0.005 -0.005 0.005 -0.005 0.010
3 Hole Side (1/2 Dia) Dowel Axes + 0.000 0.001 -0.001 0.001 -0.001 0.001 -0.001 0.001
4 Dowel Axes Reference Planes on Sensor Mount + 0.000 0.050 -0.050 0.050 -0.050 0.050 -0.050 0.100
5 Reference Planes on Sensor Mount 3 PCB Screw Holes Axes + 0.000 0.029 -0.029 0.029 -0.029 0.029 -0.029 0.058
6 3 PCB Screw Holes Axes Sensor Placement on PCB + 0.000 0.025 -0.025 0.025 -0.025 0.025 -0.025 0.050
A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: 0.1444 -0.1444
0.123
Mean + Statistical Tolerance = 0.123
Mean - Statistical Tolerance = -0.123
Total Target Dimension= 0.000
Statistical tolerance [sqrt(sum of sqrd tol)*3] =
STACK-UP SPREADSHEET
Description
Stack Direction +/-
Target
Dimension
Bi/Unilateral Dimension Limit Dimension
+ Max
- Min
+ Min
- Max
Tolerance
Limit Dimension
+ Max
- Min
+ Min
- Max
Tolerance
Statistical tolerance [sqrt(sum of sqrd tol)*3] =
Statistical tolerance [sqrt(sum of sqrd tol)*3] =
STACK-UP SPREADSHEET
Description
Stack Direction +/-
Target
Dimension
Bi/Unilateral Dimension
STACK UP ANALYSIS---DESIGN PREVENTION
September 15, 2016
FEA ---DESIGN PREVENTION
Page 47
WHAT ARE YOU PREVENTING ?
1. MAX LOAD FAILURE
2. FATIGUE FAILURE
3. SINGLE POINT FAILURE
 Remaining Life Analysis ( RLA )
 Durability Analysis
 Failure Prediction Analysis
 High Cycle Fatigue Calculations
 Correlation to Real-world situations
 Comparison of Alternate materials for extended life and warranty
 Life extension analysis
September 15, 2016
Fatigue Analysis - DESIGN PREVENTION
Page 48
Monte Carlo Analysis---DESIGN PREVENTION
PREVENTION CONTROLS  DETECTION CONTROLS
1. Design Specifications
2. Critical Characteristics
3. Test to Failure
4. Durability Testing
5. Design Validation Testing
6. End of Line Testing
METHODS FOR PREVENTION AND DETECTION
1. Stack up Analysis
2. DOE—Design of Experiment
3. FEA Analysis
4. Engineering Design
Standards, ANSI, CSA, ASTM,
NFPA, ISO
FMEA RPN
51
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0
5
10
15
20
25
30
35
40
45
PRIORITIZING FAILURES 80/20 RULE
RPN CUMULATIVE PERCENT Expon. (RPN )
Top 2 failures= 80% TOTAL FAILURES
September 15, 2016
DO NOT WAIT FOR THIS TO HAPPEN PREVENTED
Page 52
NEXT LET’S REVIEW OF YOUR
DESIGN FMEA
September 15, 2016
Page 53
THANK YOU

More Related Content

What's hot

FMEA Introduction.ppt
FMEA Introduction.pptFMEA Introduction.ppt
FMEA Introduction.pptbowerj
 
Fmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_engFmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_engerkinguler
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect AnalysisNafis Ahmad
 
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)Inter Alliance Werardt
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Anand Subramaniam
 
Failure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaFailure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaJitesh Gaurav
 
Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)Anand Subramaniam
 
Failure modes effect analysis
Failure modes effect analysisFailure modes effect analysis
Failure modes effect analysismaheskumargkm
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Abbas (Bob) Youssef MBA, PhD
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentationPRASHANT KSHIRSAGAR
 

What's hot (20)

Best Damn D-FMEA Method!
Best Damn D-FMEA Method!Best Damn D-FMEA Method!
Best Damn D-FMEA Method!
 
FMEA Introduction.ppt
FMEA Introduction.pptFMEA Introduction.ppt
FMEA Introduction.ppt
 
Ppap training ppt
Ppap training   ppt Ppap training   ppt
Ppap training ppt
 
Fmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_engFmea alignment aiag_and_vda_-_eng
Fmea alignment aiag_and_vda_-_eng
 
Process fmea
Process fmea Process fmea
Process fmea
 
Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)Failure Modes and Effect Analysis (FMEA)
Failure Modes and Effect Analysis (FMEA)
 
Failure Mode & Effect Analysis
Failure Mode & Effect AnalysisFailure Mode & Effect Analysis
Failure Mode & Effect Analysis
 
DFMEA
DFMEADFMEA
DFMEA
 
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
PPT ON DESIGN FAILURE MODE AND EFFECT ANALYSIS (DFMEA)
 
Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)Process Failure Modes & Effects Analysis (PFMEA)
Process Failure Modes & Effects Analysis (PFMEA)
 
Failure mode effect_analysis_fmea
Failure mode effect_analysis_fmeaFailure mode effect_analysis_fmea
Failure mode effect_analysis_fmea
 
Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)Failure Modes & Effects Analysis (FMEA)
Failure Modes & Effects Analysis (FMEA)
 
FMEA Presentation
FMEA PresentationFMEA Presentation
FMEA Presentation
 
Process F.M.E.A
Process F.M.E.AProcess F.M.E.A
Process F.M.E.A
 
PFMEA
PFMEA PFMEA
PFMEA
 
Failure modes effect analysis
Failure modes effect analysisFailure modes effect analysis
Failure modes effect analysis
 
PPAP
PPAPPPAP
PPAP
 
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
Bob (ababs) Youssef FMEA Workshop Training at Hughes rev3
 
Advanced Product Quality Planning presentation
Advanced Product Quality Planning presentationAdvanced Product Quality Planning presentation
Advanced Product Quality Planning presentation
 
Ppap la
Ppap laPpap la
Ppap la
 

Viewers also liked

DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE Julian Kalac P.Eng
 
DFMEA DR & DVP 261113 KCV
DFMEA DR & DVP 261113 KCVDFMEA DR & DVP 261113 KCV
DFMEA DR & DVP 261113 KCVKamal Vora
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]ExerciseLeanLLC
 
DFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostDFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostRicardo Gonzalez Luna
 
Dfmea for engine systems
Dfmea for engine systemsDfmea for engine systems
Dfmea for engine systemsKamal Vora
 
Common DFMEA Mistakes
Common DFMEA MistakesCommon DFMEA Mistakes
Common DFMEA MistakesRoger Hill
 
FMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerFMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerNukool Thanuanram
 
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACMACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACJulian Kalac P.Eng
 
Fmea01
Fmea01Fmea01
Fmea01miad
 
Webinar #6 DFMEA
Webinar   #6   DFMEAWebinar   #6   DFMEA
Webinar #6 DFMEAProdeos
 
Services Of Exercise Lean Group
Services Of Exercise Lean GroupServices Of Exercise Lean Group
Services Of Exercise Lean GroupExerciseLeanLLC
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011ExerciseLeanLLC
 
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]ExerciseLeanLLC
 
F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]ExerciseLeanLLC
 
6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]ExerciseLeanLLC
 

Viewers also liked (20)

DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
DFMEA DUE DILIGENCE TRAINING FOR LITENS AUTOMOTIVE
 
DFMEA DR & DVP 261113 KCV
DFMEA DR & DVP 261113 KCVDFMEA DR & DVP 261113 KCV
DFMEA DR & DVP 261113 KCV
 
Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]Fmea Handbook V4.1[1][1]
Fmea Handbook V4.1[1][1]
 
DFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and CostDFMEA: Reduce Design Errors, Time and Cost
DFMEA: Reduce Design Errors, Time and Cost
 
Dfmea for engine systems
Dfmea for engine systemsDfmea for engine systems
Dfmea for engine systems
 
Common DFMEA Mistakes
Common DFMEA MistakesCommon DFMEA Mistakes
Common DFMEA Mistakes
 
FMEA 4th Edition for Beginer
FMEA 4th Edition for BeginerFMEA 4th Edition for Beginer
FMEA 4th Edition for Beginer
 
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALACMACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
MACHINE SAFEGUARDING TRAINING & PSHR requirements by JULIAN KALAC
 
Fmea01
Fmea01Fmea01
Fmea01
 
FMEA presentation
FMEA presentationFMEA presentation
FMEA presentation
 
Webinar #6 DFMEA
Webinar   #6   DFMEAWebinar   #6   DFMEA
Webinar #6 DFMEA
 
Fmea design la
Fmea design laFmea design la
Fmea design la
 
Dfmea
DfmeaDfmea
Dfmea
 
The 10 most common fmea mistakes
The 10 most common fmea mistakes The 10 most common fmea mistakes
The 10 most common fmea mistakes
 
MWV CONTROL VS SPEC
MWV CONTROL VS SPECMWV CONTROL VS SPEC
MWV CONTROL VS SPEC
 
Services Of Exercise Lean Group
Services Of Exercise Lean GroupServices Of Exercise Lean Group
Services Of Exercise Lean Group
 
System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011System Kaizen Process Feb 6 2011
System Kaizen Process Feb 6 2011
 
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
Certificate 20of 20 Participation 20 Silico 20 Petak 20 Fmea[1]
 
F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]F119 Team Report Out Dec 16, 2009[1]
F119 Team Report Out Dec 16, 2009[1]
 
6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]6 S System[1] In Spanish[1]
6 S System[1] In Spanish[1]
 

Similar to DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE

Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...J. García - Verdugo
 
Total Quality Management
Total Quality ManagementTotal Quality Management
Total Quality ManagementKarthikeyan I
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECAMichael Herman
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)Prashant Rasekar
 
Failure mode
Failure modeFailure mode
Failure modeGia Lara
 
504 h0002 (gs 0002) - design fmea
504 h0002 (gs 0002) - design fmea504 h0002 (gs 0002) - design fmea
504 h0002 (gs 0002) - design fmeaEfari Bahcevan
 
Risk management in complex changeovers through cfmea
Risk management in complex changeovers through cfmeaRisk management in complex changeovers through cfmea
Risk management in complex changeovers through cfmeaDr. Bikram Jit Singh
 
ASQ RD Webinar: Design for reliability a roadmap for design robustness
ASQ RD Webinar: Design for reliability   a roadmap for design robustnessASQ RD Webinar: Design for reliability   a roadmap for design robustness
ASQ RD Webinar: Design for reliability a roadmap for design robustnessASQ Reliability Division
 
DFMEA – Complete Guide for Design.pdf
DFMEA – Complete Guide for Design.pdfDFMEA – Complete Guide for Design.pdf
DFMEA – Complete Guide for Design.pdfAkash Gupta
 
Ajay_Training_Report[1]
Ajay_Training_Report[1]Ajay_Training_Report[1]
Ajay_Training_Report[1]AJAY KUMAR
 
Evolution of Vehicle aftter it has been released, How its made and managed
Evolution of Vehicle aftter it has been released, How its made and managedEvolution of Vehicle aftter it has been released, How its made and managed
Evolution of Vehicle aftter it has been released, How its made and managedSamuel Festus
 

Similar to DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE (20)

Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...
Javier Garcia - Verdugo Sanchez - Six Sigma Training - W1 Failure Mode and Ef...
 
FMICA ppt
FMICA pptFMICA ppt
FMICA ppt
 
Total Quality Management
Total Quality ManagementTotal Quality Management
Total Quality Management
 
Introduction to FMEA/FMECA
Introduction to FMEA/FMECAIntroduction to FMEA/FMECA
Introduction to FMEA/FMECA
 
Design & Process FMEA Manual
Design & Process FMEA ManualDesign & Process FMEA Manual
Design & Process FMEA Manual
 
Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)Failure Mode & Effects Analysis (FMEA)
Failure Mode & Effects Analysis (FMEA)
 
Df Maint Tutorial
Df Maint TutorialDf Maint Tutorial
Df Maint Tutorial
 
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
PFMEA, Risk Reduction and Effectiveness – Advance (AIAG FMEA #4 Edition)
 
Failure mode
Failure modeFailure mode
Failure mode
 
504 h0002 (gs 0002) - design fmea
504 h0002 (gs 0002) - design fmea504 h0002 (gs 0002) - design fmea
504 h0002 (gs 0002) - design fmea
 
Risk management in complex changeovers through cfmea
Risk management in complex changeovers through cfmeaRisk management in complex changeovers through cfmea
Risk management in complex changeovers through cfmea
 
ASQ RD Webinar: Design for reliability a roadmap for design robustness
ASQ RD Webinar: Design for reliability   a roadmap for design robustnessASQ RD Webinar: Design for reliability   a roadmap for design robustness
ASQ RD Webinar: Design for reliability a roadmap for design robustness
 
DFMEA – Complete Guide for Design.pdf
DFMEA – Complete Guide for Design.pdfDFMEA – Complete Guide for Design.pdf
DFMEA – Complete Guide for Design.pdf
 
Ajay_Training_Report[1]
Ajay_Training_Report[1]Ajay_Training_Report[1]
Ajay_Training_Report[1]
 
FMEA_Guide-Q1.ppt
FMEA_Guide-Q1.pptFMEA_Guide-Q1.ppt
FMEA_Guide-Q1.ppt
 
FMEA
FMEAFMEA
FMEA
 
Birmingham apcs
Birmingham apcsBirmingham apcs
Birmingham apcs
 
Fmea process la
Fmea process laFmea process la
Fmea process la
 
Evolution of Vehicle aftter it has been released, How its made and managed
Evolution of Vehicle aftter it has been released, How its made and managedEvolution of Vehicle aftter it has been released, How its made and managed
Evolution of Vehicle aftter it has been released, How its made and managed
 
Process fmea work_instructions
Process fmea work_instructionsProcess fmea work_instructions
Process fmea work_instructions
 

More from Julian Kalac P.Eng

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.EngJulian Kalac P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowJulian Kalac P.Eng
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSJulian Kalac P.Eng
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Julian Kalac P.Eng
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment Julian Kalac P.Eng
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS Julian Kalac P.Eng
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVERJulian Kalac P.Eng
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureJulian Kalac P.Eng
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018Julian Kalac P.Eng
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutJulian Kalac P.Eng
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverJulian Kalac P.Eng
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHJulian Kalac P.Eng
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over timeJulian Kalac P.Eng
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS Julian Kalac P.Eng
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACJulian Kalac P.Eng
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian KalacJulian Kalac P.Eng
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACJulian Kalac P.Eng
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACJulian Kalac P.Eng
 

More from Julian Kalac P.Eng (20)

VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.EngVOLVO EATS RACK LEAN TRANSFORMATION  by Julian Kalac, P.Eng
VOLVO EATS RACK LEAN TRANSFORMATION by Julian Kalac, P.Eng
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORSLEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
 
Design for Six Sigma in Automotive
Design for Six Sigma in Automotive Design for Six Sigma in Automotive
Design for Six Sigma in Automotive
 
1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment 1000 Ton Transfer Press Risk Assessment
1000 Ton Transfer Press Risk Assessment
 
Lean logistics
Lean logisticsLean logistics
Lean logistics
 
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
PRE-START HEALTH SAFETY REVIEW REPORT of 1000 TON MECHANICAL TRANSFER PRESS
 
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
1000 TON TRANSFER PRESS SAFE WORK PROCEDURE ;DIE SETUP/CHANGEOVER
 
Live wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedureLive wire testing lock out tag out safe work procedure
Live wire testing lock out tag out safe work procedure
 
Julian Kalac lean 6 sigma project list--2018
 Julian Kalac lean 6 sigma  project list--2018 Julian Kalac lean 6 sigma  project list--2018
Julian Kalac lean 6 sigma project list--2018
 
Machine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag OutMachine Safeguarding with Lock Out Tag Out
Machine Safeguarding with Lock Out Tag Out
 
Custom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeoverCustom Lean Eyelet machine SOP with 5 min changeover
Custom Lean Eyelet machine SOP with 5 min changeover
 
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCHFCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
FCI AUTOMOTIVE 2005 FORD MINIVAN ABS-VSC LAUNCH
 
Process Capability shift over time
Process Capability shift over timeProcess Capability shift over time
Process Capability shift over time
 
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
JULIAN KALAC -EXAMPLES OF LEAN SIX SIGMA BLACK BELT PROJECTS
 
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALACLEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
LEAN Setup Reduction (SMED) training for welding by JULIAN KALAC
 
Continuous improvement by Julian Kalac
Continuous improvement  by Julian KalacContinuous improvement  by Julian Kalac
Continuous improvement by Julian Kalac
 
The hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALACThe hidden factory by JULIAN KALAC
The hidden factory by JULIAN KALAC
 
Lean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALACLean Supply Chain Management--by JULIAN KALAC
Lean Supply Chain Management--by JULIAN KALAC
 
LOTO LIVE WIRE CS
LOTO LIVE WIRE CSLOTO LIVE WIRE CS
LOTO LIVE WIRE CS
 

Recently uploaded

Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsPooky Knightsmith
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptxDhatriParmar
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)lakshayb543
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxkarenfajardo43
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmStan Meyer
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleCeline George
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptxmary850239
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptxmary850239
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Seán Kennedy
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4JOYLYNSAMANIEGO
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWQuiz Club NITW
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQuiz Club NITW
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1GloryAnnCastre1
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfPrerana Jadhav
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvRicaMaeCastro1
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxDhatriParmar
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Projectjordimapav
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfPatidar M
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...DhatriParmar
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptxmary850239
 

Recently uploaded (20)

Mental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young mindsMental Health Awareness - a toolkit for supporting young minds
Mental Health Awareness - a toolkit for supporting young minds
 
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
Unraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptxUnraveling Hypertext_ Analyzing  Postmodern Elements in  Literature.pptx
Unraveling Hypertext_ Analyzing Postmodern Elements in Literature.pptx
 
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
Visit to a blind student's school🧑‍🦯🧑‍🦯(community medicine)
 
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptxGrade Three -ELLNA-REVIEWER-ENGLISH.pptx
Grade Three -ELLNA-REVIEWER-ENGLISH.pptx
 
Oppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and FilmOppenheimer Film Discussion for Philosophy and Film
Oppenheimer Film Discussion for Philosophy and Film
 
Multi Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP ModuleMulti Domain Alias In the Odoo 17 ERP Module
Multi Domain Alias In the Odoo 17 ERP Module
 
4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx4.16.24 Poverty and Precarity--Desmond.pptx
4.16.24 Poverty and Precarity--Desmond.pptx
 
4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx4.16.24 21st Century Movements for Black Lives.pptx
4.16.24 21st Century Movements for Black Lives.pptx
 
Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...Student Profile Sample - We help schools to connect the data they have, with ...
Student Profile Sample - We help schools to connect the data they have, with ...
 
Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4Daily Lesson Plan in Mathematics Quarter 4
Daily Lesson Plan in Mathematics Quarter 4
 
Mythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITWMythology Quiz-4th April 2024, Quiz Club NITW
Mythology Quiz-4th April 2024, Quiz Club NITW
 
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITWQ-Factor General Quiz-7th April 2024, Quiz Club NITW
Q-Factor General Quiz-7th April 2024, Quiz Club NITW
 
Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1Reading and Writing Skills 11 quarter 4 melc 1
Reading and Writing Skills 11 quarter 4 melc 1
 
Narcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdfNarcotic and Non Narcotic Analgesic..pdf
Narcotic and Non Narcotic Analgesic..pdf
 
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnvESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
ESP 4-EDITED.pdfmmcncncncmcmmnmnmncnmncmnnjvnnv
 
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptxMan or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
Man or Manufactured_ Redefining Humanity Through Biopunk Narratives.pptx
 
ClimART Action | eTwinning Project
ClimART Action    |    eTwinning ProjectClimART Action    |    eTwinning Project
ClimART Action | eTwinning Project
 
Active Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdfActive Learning Strategies (in short ALS).pdf
Active Learning Strategies (in short ALS).pdf
 
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
Blowin' in the Wind of Caste_ Bob Dylan's Song as a Catalyst for Social Justi...
 
4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx4.11.24 Poverty and Inequality in America.pptx
4.11.24 Poverty and Inequality in America.pptx
 

DESIGN FMEA TRAINING FOR LITENS AUTOMOTIVE

  • 1. I S O / T S 1 6 9 4 9 R E G I S T E R E D • I S O 1 4 0 0 1 R E G I S T E R E D • w w w . l i t e n s . c o m DESIGN FMEA Training developed for Litens Automotive developed by Julian Kalac, P.Eng Educational training for Litens Automotive
  • 2. AGENDA TRAINING  Recap on DFMEA BASICS , FAILURE VS CAUSE,  DFMEA consequences of not doing it properly  PREVENTION CONTROLS  CRITICAL DIMENSIONS/TOLERANCES  Good vs Bad DFMEA Litens Examples  Design of Experiment –2 𝑛 Factorial design  REVIEW / DEVELOPMENT OF YOUR DFMEA  CRITICAL DIMENSIONS AND TOLERANCES September 15, 2016 Page 2 WORKING DFMEA 1-2HRS TRAINING 2-3HRS
  • 3. OBJECTIVE  Review the basics of Design FMEA  Consequences of poorly done DFMEA (GM Ignition Switch)  Learn to identify Single Point Of Failures SPOF, and ho to prevent them  Learn to use DOE to analyze surrogate data to optimize new designs  Learn basics about Design for Six Sigma (DFSS), process capability and design for loss of function  Review your Designs and DFMEA September 15, 2016 Page 3
  • 4. CANADIAN LAW • Under Canadian law, manufacturers have a duty 1. DUTY TO WARN consumers of the dangers inherent in the use of their products of which the manufacturer has, or ought to have, knowledge. 2. NEGLIGENT DESIGN –manufacturer will be held liable under Canadian Law for foreseeable injury or damage caused by products that were negligently designed. 3. DEFECTIVE PRODUCT - manufacturer will also be held liable for any manufacturing defects FMEA are specifically developed for that purpose. September 15, 2016 Page 4
  • 5. WHAT IS DFMEA ? • Failure Mode and Effects Analysis (FMEA) is an engineering analysis tool used to identify and prevent failures before they actually happen • DFMEA are used early in the development phase while the design can be changed as a Design Verification method • The most efficient way to do a DFMEA is during the design review when, the entire design is being reviewed and the FMEA form can be used as a guide • DFMEA IS NOT A FORM TO FILL OUT FOR COMPLIANCE REASONS September 15, 2016 Page 5
  • 6. September 15, 2016 WHAT IS DFMEA ? Page 6
  • 7. Why is FMEA important? 1. Due Diligence – Product Safety Risks, Design Reliability, Regulations AIAG, CSA, OHSA, TS-16949 Design Verification, 2. Required for all new designs Proactively Identify and Prevent Design Failures (safety and performance) before the design is released into production 3. Reduces warranty costs - far less expensive to prevent problems early in product development than fix problems after launch. 4. Litens VP Engineering –Critical Dimensions MUST be DERIVED FROM DFMEA and tolerances justified –WHY IS THAT IMPORTANT?
  • 8. WHAT ARE OUTPUTS OF A DFMEA 1. list of Critical Component Dimensions , their specifications (dim/tolerance) and evidence SHOWING how the Critical Tolerance relates to the Cause of Failure 2. A list of potential Failure Modes and Causes, prioritized by RPN 3. A list of action items that have been taken or will be taken to PREVENT the Failures Modes/Causes before PPAP 4. DVP Verification Plan (Conditions, Acceptance Criteria) 5. Lessons learned
  • 9. FMEAs are legal documents It is important for the FMEA team to understand that FMEAs are legal documents that support the demonstration of due care in product development. As legal documents, they are subject to subpoena for legal proceedings. FMEAs, published by John Wiley & Sons. [1] September 15, 2016 Page 9
  • 10. FMEA SYSTEM BREAKDOWN Is Sub-system = Sub-Assy ??
  • 12. SYSTEM FMEA/CONCEPT FMEA • Analysis is at highest-level of an entire system, (Vehicle) made up of various subsystems (electrical, front suspension, • The focus is on top level interfaces/interactions between different subsystems and surrounding environment • Looks at Single-point failures (where a single component failure can result in complete failure of the entire system) • Example of System FMEA is an Application FMEA, focused on Application of an existing design
  • 13. DESIGN FMEA • Design FMEA evaluates the entire Product Design all levels contained within the boundaries of the product , (Final Assy, components, sub-assy) • The scope of the Design FMEA includes the subsystem or component itself, as well as the interfaces between adjacent components. • Critical dimensions are developed from critical failure modes within the DFMEA • DVP&R Tests criteria are developed and confirmed
  • 14. Process FMEA • Process FMEA focuses on the design of the assembly process, development of process specifications in order to meet the critical dimensions specified in the DFMEA • The scope of a Process FMEA can include manufacturing and assembly operations, shipping, incoming parts, transporting of materials, storage, conveyors, tool maintenance, and labeling.
  • 15. WHEN TO DO A DFMEA? Case 1: NEW DESIGNS, new technology, or new process. The scope of the FMEA is the complete design, technology or process. Case 2: MODIFICATIONS TO EXISTING DESIGN or process (assumes there is a FMEA for the existing design or process). The scope of the FMEA should focus on the modification to design or process, possible interactions due to the modification, and field history. Case 3: APPLICATION - Use of existing design in a new environment, or Application . The scope assumes there is an FMEA for the existing design or processes of the FMEA is the impact of the new APPLICATION or Environment on the existing design or process.
  • 16.
  • 18. September 15, 2016 Consequences of not doing a DFMEA Page 18
  • 19. September 15, 2016 DO NOT WAIT FOR THIS TO HAPPEN PREVENTED Page 19
  • 20. September 15, 2016 BECAUSE THIS IS THE EFFECT Page 20
  • 21. September 15, 2016 GM IGNITION SWITCH FAILURE Page 21 OVER 300 deaths 23 Mil cars recalled from 2004 2014
  • 22. GOOD PRACTICES TO AVOID BAD EVIDENCE FMEA •It has to be done correctly: •A well-done and properly completed FMEA can be a strong ally in the defense for the manufacturer in product litigation. •On the other hand, a poorly done and haphazard completion of an FMEA can be used to support the prosecution. September 15, 2016 Page 22
  • 23. September 15, 2016 IDENTIFY POTENTIAL FAILURE MODES WITH IGNITION SWITCH Page 24
  • 24. September 15, 2016 GM IGNITION SWITCH FMEA Page 26 GM IGNITION SWITCH FMEA FAILURE MODE FAILIURE EFFECT S CAUSE OF FAILURE O DESIGN CONTROLS D RPN RECOMMENDED ACTION STALLS VEHICLE ON HIGHWAY---NOT SAFETY CAN STEER CAR OFF TO THE SIDE- -DRIVER NUISANCE 10 IGNITION SWITCH REQUIRES LOW TORQUE TO TURN --KEY CHAIN TOO HEAVY -- 1 FOB SPECIFICATI ON FOR WEIGHT 1 8 ISSUE TSB TO REMOVE ALL KEYS FROM FOB -CLOSE FMEA DRIVER NUISANCE 8 IGNITION SWITCH LOW TORQUE 2 VEHICLE RESTART 1 8 NONE CLOSE FMEA Requirement not defined in units of measure (VALUES)
  • 25. Lessons Learned from GM ignition Switch  The Federal Crown Prosecutor report suggest that the original GM ignition switch specification contained vague and ambiguous targets for the detent torque, which were never achieved, and provides no evidence that the specification or acceptance criteria were developed using failure modes effects analysis or similar techniques.  As a direct result GM engineers failed to understand the significance of the available evidence for over ten years - and they never asked "Is the specification is fit for the purpose?" - with serious consequences for the company and it's consumers. September 15, 2016 Page 27
  • 26. September 15, 2016 EXPLOSIVE PINTO FUEL TANK DESIGN Page 28
  • 27. DFMEA and PFMEA connection Critical / special characteristics
  • 28. Brooks Approval: Date Approved: Effectivity Date: Part Number: PCP Number Prepared by: Part Number Revision: PCP Revision Checked by: Part Name: PCP Rev Date: Approval: Characteristic Description Specification & Tolerance Key Dim Measurement Technique Sample size& Frequency Record CoC Verification Every lot Dimensions caliper AQL 1.0 Every lot diameter Ø160±1 CMM diameter Ø130±1 CMM diameter Ø120 G6 Y CMM diameter Ø65±.0.1 CMM chamfer C2 CMM dim 10 -0.1/0 HG dim 5±0.2 HG dim control 19 to19.2 Caliper Roughness 63 √ C SRT/Comparator 3rd Process, 0.02 Y CMM 0.02B Y CMM Ø0.02B Y CMM 4th process Hole Ø5H8 PG dim 26.5±0.03 Y CMM Tap M6 Tap hole Thread Gauge Hole Ø4.5(all the hole dimension) CMM 50 De-Burring De-burring tools work instruction #: xxxx Break All Sharp Edges and burrs visual Inspection AQL1.0 every lot Record on QA Plan XXXX StopDe- burringRework & CAR Tap M6 Tap hole Thread Gauge Hole Ø5H8 PG Roughness 63 √ C SRT/Comparator Appearance to Spec XXXX Visual inspection 70 Treatment/Finish ing Treatment House Specification #:xxxx Treatment PCP #:xxxxx Electroless Nickel Plating [0.003-0.005mm] X-Ray Visual inspection AQL0.65 Every lot COC from Supplier Rework Qualified Plater (ABC Company) diameter Ø120 G6 CMM hole Ø5H8 PG tap M6 Tap hole TG roughness All surface Roughness SRT/Comparator Appearance No stain, masking, color to sample Visual inspection 90 Packaging work instruction xxx- xxxx Visual Each Lot Received STD packaging method Repack and Validate Supplier Name: Process Control Plan Supplier Number: Workcell / Location Process Step Number Process Name / Operation Description Machine, Device, Jig, Tools for Manufacturing Ref Doc. Number/ Specification No Control Methods/Measurement Reaction Plan Remarks (Special Process) 10 work instruction xxx- xxxx STEEL, CORROSION RESISTING, 304 OR 304L IQC inspection sheet Product / Process Characteristics Receive Raw Material Incoming Return to Supplier. RMA process XXX Notify production of new delivery date. 40 Manufacture work instruction #: xxxx Machining Hole, Profile cutting, Tap holes 30 Manufacture work instruction #: xxxx Bottom plane CNC Milling#:xxx Tool #:xxx Fixture#:xxx 20 Drawing #:xxx Manufacture work instruction #: xxxx 80 Post-treat Inspection procedure xxxx Pre-Treatment Post-Treatment Inspection 60 Specification #:xxxx Treatment PCP #:xxxxx Machining N/A CNC Lathe#:xxx CNC Program #:xxxx Tool#:xxxx Fixture#:xxxx Grinding#:xxx Tool #:xxx Fixture#:xxx 2pcs Every machine Set up 1pcs every two hours In-Process In-Process Insp. From CMM 2pcs Every machine Set up 1pcs every hour In-Process In-Process Insp. From CMM 2pcs Every machine Set up 1pcs every two hours In-Process In-Process Insp. From CMM AQL0.65 Every lot Pre-treatment inspection record AQL0.65 for critical dimensions and 100% for Visual inspection COC from supplier and Post treatment inspection record Rework/CAR send for rework Raise CAR send for rework Stop machining/ Fine-tune the Setting and re- inspect Notify Supervisor Stop machining/ Fine-tune the Setting Qualified Operator Stop machining/ Fine-tune the Setting Critical Dimensions & tolerances from DFMEA
  • 29. DFMEA and DVP&R connection Test description input to the DVP&R.
  • 30. Email: Email: Phone: Phone: Fax: Fax: Sample Size or Truck # Req. Start End Start End 1) Material Compliance DRD# 3.2.3.1.1 Rev # Dated ##/##/## Per CEMS D-28 Rev # Dated ##/##/## 1a) No 6.3 Resin Requirements Table 2 1 day PV All Must Pass D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 1 2013-12-31 2013-12-31 1 Lot 1b) No 6.3 Specific Gravity Table 4 Per ASTM D792 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 2 2013-12-31 2013-12-31 1 Lot 1c) No 6.3 Tensile Strength - Ultimate Table 4 Per ASTM D638 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 3-4 2013-12-31 2013-12-31 1 Lot 1d ) No 6.3 Ultimate Elongation Table 4 Per ASTM D638 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 5-6 2013-12-31 2013-12-31 1 Lot 1e) No 6.3 Flexural Modulus Table 4 Per ASTM D 790 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84555 by GE D 5-6 2013-12-31 2013-12-31 1 Lot 1f) No 6.3 Flexural Strength Table 4 Per ASTM D 790 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 7-8 2013-12-31 2013-12-31 1 Lot 1g) No 6.3 Impact Resistance Table 4 Per CEMS-DT-4 / Rev # Dated ##/##/## Per ASTM D 790 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 9-10 2013-12-31 2013-12-31 1 Lot 1h) No 6.3 Deflection Temperature Table 4 Per ASTM D 790 1 day PV All Must Pass Test Plaques D 1 Lot 2013-12-31 2013-12-31 84576 by GE D 11-12 2013-12-31 2013-12-31 1 Lot 1i) No 6.3 Color Table 4 1 day PV All Must Pass Molded Part Detail D.01 D 2 Parts 2013-12-31 2013-12-31 ASD256 D 13-14 2013-12-31 2013-12-31 2 Parts 1j) No 6.3 Dimensional Stability Table 4 4 hours PV All Must Pass Molded Part B 2 Parts 2013-12-31 2013-12-31 ETA Lab Rpt 56843 C 13-14 2013-12-31 2013-12-31 2 Parts 2) No 6.3 Table 4 Other Characteristics 1 day PV All Must Pass Plated part C 1 Part 2013-12-31 2013-12-31 HB dated 8/21/06 C 15-16 2013-12-31 2013-12-31 8 parts 3) No 6.3 Table 4 Other Characteristics 1000 Hours PV All Must Pass Painted part C 1 Part 2013-12-31 2013-12-31 LCL Reported C 17-18 2013-12-31 2013-12-31 9 Parts Z2 = Finish Paint per TMS-9008 Color: Argent, NAV 8752 Pass Accept Testing completed by Supplier see Paint Tab Grille, Painted, Fixed Testing to be completed by Supplier Z1 = Chrome Plate per MS-7071B_fk Pass Accept Testing completed by FGH Platers, Inc, See Chrome Plate Tab Salt Spray applied at 16, 32 56 Hours (Grille, Chrome, Fixed ) Testing to be completed by FGH Platers, Inc, See Chrome Plate Tab AA88 = 4 hours at 88° C Parts will conform to the dimensions and tolerances shown on the engineering drawings after four hours exposure in an oven at the temperature indicated by the numeral of the suffix AA - symbol expressed in degrees Celsius. Pass Accept Part Testing Performed by ABC on Molded Part Molded part (No Assembly) Part Testing to be performed by ABC AC1 = Integrally colored Part Pass Accept Verified by ABC To be verified by ABC S90 = 90° min. deflection temperature at 1820 Kpa 98 C Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE R235 = 36 in/lbs force at minus 30° F Parts will show no evidence of cracking when impact tested at point or points indicated on engineering drawing. 299 in-lbs. - Material Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE N60 = 60 MPa min. 72 MPa Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE M17 = 1700 MPa min. 2060 MPa Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE L100 = 100% min. 150% Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE K-40 = 40 MPa min. 50 MPa Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE DF1140 = 1.140+/- 0.05 01-Jan-00 Accept Material Testing Performed by GE on Test Plaques Material to be tested by GE PC+ABS = Polycarbonate + Acrylonitrile / Butadiene / Styrene PC+ABS = Polycarbonate + Acrylonitrile / Butadiene / Styrene Accept Material Testing Performed by GE Material to be tested by GE Sample ID Actual Timing Sample Size Tested PC + ABS DF1140 K40 L100 M17 N60 R235 S90 / AC1 AA88 Z1 Z2 Test Location / Test Verification Resp. Rqmt Source Sample Type Scheduled Timing Report # Sample Level Actual Results Test Results Status Accept / Reject Tests Completed by Notes / Remarks Test Stage Target Rqmts Test Number Compliance / Regulatory / S C/CC/KP C Specification / Test Name Test Method or Test Procedure Duration of Test Acceptance Criteria 630-123-4568 815-123-4568 Testing details and Results Planning information Actual Timing steve.peterson@navistar.com j.foley@onetwothree.com Test Stage ED = Engineering Devel't Test, DV = Design Verification, PV = Production Verification, CCT = Continued Compliance Testing Target Requirements. State required probability or reliability and confidence of meeting criteria, e.g. R90, C90 or all must pass. Sample Type / Level A = Prototype (Handmade), B = Prototype (Tooled), C = Production Tool (Not Process), D = Production Tool & Process 630-123-4567 815-123-4567 Title: Chief Engineer Title: Engineering MGR Grille, Chrome, Fixed 123659749 C State: MN Country: Zip / Postal Code: 60586 X Component (s): w/ Navistar Part Number(s) Rev USA Grille, Chrome, FIxed 1315449691 D Navistar Design Engineer Supplier Design Engineer (Key Contact) Grille, Asm 23614649 A Name: Steve Peterson Name: James Foley Grille, Asm Assembly Name: w/ Navistar Part Number(s) Rev Supplier Address: 12364 Jackson St. 23614649 B City: Andrewsville Date: 1236364 A 2012-02-13 Subsystem: Grille Fixed Supplier Code: 12345 Affected Navistar Program(s): XVY 1235 DESIGN VERIFICATION PLAN AND REPORT ISQ-011-FO Rev: A Date: 04/01/2013 System: Exterior Trim Supplier Name: One, Two, Three 123 Inc. Core Team: (list names) A. Hernandez, B. McGruff, S. Orlander, K. Keller DVP&R Number: Revision Level: DVP&R example Acceptance Test Criteria from DFMEA-- -example Min Torque= 70Nm
  • 31. FAILURES, SYMPTOMS AND ROOT CAUSE ANALYSIS
  • 34. 9/28/2013 DFMEA --# 1 QUESTION: WHAT CAN GO WRONG? 36 1. Ask Leading question “what can go wrong inside the design that would prevent it from functioning?” 2. Once a Failure is identified then ask the question: If this failure occurred, then what could happen?
  • 35. Failure Modes & Causes Failure Modes: Identify the manner in which an item could potentially fail to meet it’s design intent. Example  BROKEN Spring, DEFORMED Housing, Seal Leak  Piston SEIZES , Valve Port BLOCKED, Oil Contaminated CAUSE: is the component feature that created the failure condition  Broken Spring Cause: Yield strength of spring exceeded September 15, 2016 Page 37
  • 36.  A single point of failure (SPOF) is an undesired component/part if it fails, will cause the entire system to fail,  SPOF can be an Assembly (master brake cylinder Assy) or a single component (air bag sensor)  It could be at the top level of the system (air bag sensor) or deep internal not visible to the user (master brake cylinder)  SPOF are identified in FMEA as Critical (Y C) or Special Characteristics (SC) and will relate directly to a severe failure mode (sev 8 or higher) September 15, 2016 SINGLE POINT OF FAILURE (SPOF) Page 38
  • 37. 39 Failure Mode = FloodWithWater Symptoms = Pipes Leaking POSSIBLE ROOT CAUSE(S) = 1. Condensation from pipes due to temperature change OR/AND 2. Faulty Gasket OR/AND , 3. Corroded Pipe Fittings OR 4. Over-Pressurized Pipes OR 5. ……………… $$ $ $$ $ $ $ $ $ $ Root Causes vs. Symptoms of Failure Modes
  • 39. The following elements/tools may provide input to the DFMEA: • Requirements, (Customer, Product Specs, Regulatory, etc.) • Historical performance-Warranty/Field Returns, failures, Recalls, • Free Body Diagram • P-Diagram • FEA Analysis • Boundary Diagram and Interface Matrix • Functional Block Diagram • WC -Tolerance Stack Up Analysis, RSS, % Contribution, Monte Carlo, • Stack Up Analysis • DESIGN of Experiment DOE DFMEA INPUTS
  • 40. DFMEA OUTPUTS (MANDATORY) 1. A list of Critical Component Characteristics and their specifications (dim/tolerance) (PFMEA & CONTROL PLAN) 2. A list of potential Failure Modes and Causes, prioritized by RPN 3. A list of Design action items to PREVENT the Failures/Causes 4. DVP Verification Plan (Conditions, Acceptance Criteria) 5. Lessons learned
  • 42. September 15, 2016 INTERFACE MATRIX –FAILURE MODES Page 44
  • 43. P-DIAGRAM—CAUSES OF FAILURE Catalytic Converter Assy Y= f (x1, x2, x3,….) Y=OUTPUTX=INPUT
  • 44. 2 Flange Hard Stop Sensor Mount Front + 28.700 0.050 -0.050 28.750 28.650 28.750 28.650 0.100 3 Sensor Mount Front Sensor Mount Rear + 2.000 0.050 -0.050 2.050 1.950 2.050 1.950 0.100 4 Sensor Mount Rear Housing Rear + 30.100 0.050 -0.050 30.150 30.050 30.150 30.050 0.100 5 Housing Rear Exterior Gap Rear - 16.500 0.050 -0.050 16.550 16.450 -16.450 -16.550 0.100 A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: 0.57 0.07 0.112 Mean + Statistical Tolerance = 0.432 Mean - Statistical Tolerance = 0.208 Total Target Dimension= 0.224 Prepared By: Julian Kalac Date: 11-Jun-16 Stack Description: To determine the varying distance between the rear of the coax board and interior wall of the rear housing Starting Point: Flange Stop Surface Ending Point: Housing Rear From To Upper Tolerance Lower Tolerance Upper Limit Lower Limit 1 Sensor Board Rear Shims + 0.127 0.000 0.000 0.127 0.127 0.127 0.127 0.000 2 Shims Sensor Board Rear + 0.787 0.079 -0.079 0.866 0.709 0.866 0.709 0.157 3 Sensor Board Rear Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174 4 Stand Off FPGA Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316 5 FPGA Board Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174 6 Stand Off MISC Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316 7 MISC Board Stand Off + 4.500 0.087 -0.087 4.587 4.413 4.587 4.413 0.174 8 Stand Off Coax Board + 1.575 0.158 -0.158 1.733 1.417 1.733 1.417 0.316 9 Coax Board Interior Read Housing + 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 10 Interior Read Housing Housing Rear Rear + 7.200 0.050 -0.050 7.250 7.150 7.250 7.150 0.100 11 Housing Rear Rear Sensor Mount Rear - 30.250 0.050 -0.050 30.300 30.200 -30.200 -30.300 0.100 A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: -2.9971 -4.8245 0.330 Mean + Statistical Tolerance = -3.581 Mean - Statistical Tolerance = -4.241 Total Target Dimension= 3.911 **For component/dimensions in parrellel (standoff and connectors) the average standard deviation is used, [AveTolerance]=[Tolerance]/[sqrt(number of parrellel features)] Prepared By: Julian Kalac Date: 11-Jun-16 Stack Description: To determine the varying distance between the optical center of the housing and sensor Starting Point: Optical Center Ending Point: Sensor Center From To Upper Tolerance Lower Tolerance Upper Limit Lower Limit 1 Optical Center on Housing Front 2 Alignment Holes Axes + 0.000 0.035 -0.035 0.035 -0.035 0.035 -0.035 0.070 2 2 Alignment Holes Axes Hole Side (1/2 Dia) + 0.000 0.005 -0.005 0.005 -0.005 0.005 -0.005 0.010 3 Hole Side (1/2 Dia) Dowel Axes + 0.000 0.001 -0.001 0.001 -0.001 0.001 -0.001 0.001 4 Dowel Axes Reference Planes on Sensor Mount + 0.000 0.050 -0.050 0.050 -0.050 0.050 -0.050 0.100 5 Reference Planes on Sensor Mount 3 PCB Screw Holes Axes + 0.000 0.029 -0.029 0.029 -0.029 0.029 -0.029 0.058 6 3 PCB Screw Holes Axes Sensor Placement on PCB + 0.000 0.025 -0.025 0.025 -0.025 0.025 -0.025 0.050 A positive or negative Max or Min total indicates only the DIRECTION from the STARTING point to the END point of the stack. Totals: 0.1444 -0.1444 0.123 Mean + Statistical Tolerance = 0.123 Mean - Statistical Tolerance = -0.123 Total Target Dimension= 0.000 Statistical tolerance [sqrt(sum of sqrd tol)*3] = STACK-UP SPREADSHEET Description Stack Direction +/- Target Dimension Bi/Unilateral Dimension Limit Dimension + Max - Min + Min - Max Tolerance Limit Dimension + Max - Min + Min - Max Tolerance Statistical tolerance [sqrt(sum of sqrd tol)*3] = Statistical tolerance [sqrt(sum of sqrd tol)*3] = STACK-UP SPREADSHEET Description Stack Direction +/- Target Dimension Bi/Unilateral Dimension STACK UP ANALYSIS---DESIGN PREVENTION
  • 45. September 15, 2016 FEA ---DESIGN PREVENTION Page 47 WHAT ARE YOU PREVENTING ? 1. MAX LOAD FAILURE 2. FATIGUE FAILURE 3. SINGLE POINT FAILURE
  • 46.  Remaining Life Analysis ( RLA )  Durability Analysis  Failure Prediction Analysis  High Cycle Fatigue Calculations  Correlation to Real-world situations  Comparison of Alternate materials for extended life and warranty  Life extension analysis September 15, 2016 Fatigue Analysis - DESIGN PREVENTION Page 48
  • 48. PREVENTION CONTROLS  DETECTION CONTROLS 1. Design Specifications 2. Critical Characteristics 3. Test to Failure 4. Durability Testing 5. Design Validation Testing 6. End of Line Testing METHODS FOR PREVENTION AND DETECTION 1. Stack up Analysis 2. DOE—Design of Experiment 3. FEA Analysis 4. Engineering Design Standards, ANSI, CSA, ASTM, NFPA, ISO
  • 49. FMEA RPN 51 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 0 5 10 15 20 25 30 35 40 45 PRIORITIZING FAILURES 80/20 RULE RPN CUMULATIVE PERCENT Expon. (RPN ) Top 2 failures= 80% TOTAL FAILURES
  • 50. September 15, 2016 DO NOT WAIT FOR THIS TO HAPPEN PREVENTED Page 52
  • 51. NEXT LET’S REVIEW OF YOUR DESIGN FMEA September 15, 2016 Page 53