SlideShare uma empresa Scribd logo
1 de 40
Rail Technical Strategy:
Capability Delivery Plan
KC06 More Space on Trains
James Brown
Work Package Owner
RTS:CDP
MoreSpaceonTrains
KC06
RTS:CDP
MoreSpaceonTrains
KC06
JamesBrown
DataandPerformanceEngineer
Data and Performance Engineer
• Sensors & Big Data Analytics
• General innovation programs within Angel Trains’ Technology Team
Rolling Stock Experience:
• Wabtec
• Alstom
• Scotrail
• VTEC
Previous Experience
• Oil & Gas
• Nuclear Defence
• Nuclear Power
• Banking
Rail Technical Strategy
• Industry committed to one plan
sponsored by RDG, RSG and Network
Rail
• Expertise will be utilised from across the
whole UK to deliver the programme,
including from other sectors
• Delivering system level technology
demonstrators
• Building new technical capability
• Supporting key industry programmes
including Digital Rail
This approach is successful in other sectors
KC06
RTS:CDP
MoreSpaceonTrains
Work Package Owners
Dr Karen Lane
‘Running Trains Closer Together’
and ‘Service Timed to the
Second’
Janine Fountain
‘Minimal Disruption to Train
Services’
Crispin Humm
‘Efficient passenger flow
through stations and trains’ and
‘Personalised customer
experience’
Karl Butler-Garnham
‘More Value from Data’
Ouahcene Ourahmoune
‘Optimum energy use’
James Brown
‘More Space on Trains’
Ben Carrington
‘Intelligent Train’
Richard Errington
‘Flexible Freight’
Neil Tinworth
‘Low Cost Railway’
James Hardy
‘Accelerate Research,
Development and Technology
Deployment’
David Rowe
‘Research, Development and
Technology into Industry Planning’
KC06
RTS:CDP
MoreSpaceonTrains
KC06: More Space on Trains
• Maximise the size of trains running on the
network
• Optimise the use of space available
• Maximise the utilisation of this space
• Timescale out to 2044
• Currently 61 projects identified for CP6
RTS:CDP
MoreSpaceonTrains
KC06
Scope
• Rolling Stock economies of scale
• Increased passenger capacity, customer
experience and accessibility
• Increased freight capacity and efficiency
• All benefits to be fully quantified as part
of project
Benefit
• By 2044
• 90%+ of the UK network to be cleared for
greater than UIC GB+ gauge.
• All intercity routes to be cleared to UIC GC
gauge
• Double stack freight running on key
freight routes
• Average Passenger Km per Car Km up 25%
Objective
• Objectives are already technically
achievable, however the commercial
incentives aren’t in place at the current
cost level
• Hence focus is on:
• Lowering the cost
• Increasing the benefits
• Aligning incentives
• Making the most of what we have
Challenge
More Space
on Trains
Creating the
Business Case
Increasing
Structural
Gauge
Improving the
Gauging
Process
Increasing the
Vehicle
Envelope
Maximising
Interior Space
Programme Structure
RTS:CDP
MoreSpaceonTrains
KC06
Programme Principles
• To demonstrate new capabilities for UK
rail – it is then up to the Industry to
deliver
• Focus on taking new technologies to the
demonstrator stage
• Take a whole system and long term view
of the industry
RTS:CDP
MoreSpaceonTrains
KC06
Scope
1. Focus on system level issues that
affect multiples parties.
2. Focus on technical issues and
standards based issues that
would be difficult for individual
parties to solve.
3. Identify industry corporate
sponsors of all projects to
ensure delivery pathways are
identified and carried forward.
4. Think big and think long term
5. Ensure engagement with
stakeholders outside of the rail
industry.
Principles
• Risk of:
• public investment removing incentives for
private R&D
• long term vision conflicting with short
term drivers
• projects developed in isolation not then
being carried into delivery phase
• simply carrying on “Business as usual”
Issues
Aim of Presentation
• Plan supported by V/S SIC and RSSB’s Technical Leadership
Group, now engaging with wider industry
• Looking for potential project sponsors
• Looking for potential suppliers
• Looking for Feedback
• Existing Pain points
• Avoid pushing out private R&D
• If interested, number of sessions being arranged where
you can learn more
RTS:CDP
MoreSpaceonTrains
KC06
KC06:01 –Creating the
Business Case
RTS:CDP
MoreSpaceonTrains
KC06
• Gauging faces a combination of economic
problems:
• Network Effects
• Tyranny of small decisions
• Regardless of technology, increasing
gauge will always be more expensive
• How do we justify expense when benefit
not felt till years afterwards?
Challenge
• Work out the most efficient economic
approach to gauging improvement
• Quantify the benefits of increased rolling
stock space
• Quantify the economy of scale benefits to
be had by adopting UIC gauges
• Identify suitable Funding Models and
routes to market
Solutions
• V/S SIC Gauging Strategy
Existing Work
• Gauging prioritisation economic model
• Double stack freight economic study
• Modelling impact of increased train space
on passenger loading
• Consultation with manufacturers/ROSCOs
to identify economy of scale benefits
• Consultation with NR/DfT on funding
models
Proposed Work
KC06:01 –Funding Models
RTS:CDP
MoreSpaceonTrains
KC06
• Gauging projects, on individual pieces of
infrastructure, will never have a positive
business case, as the benefits are only
realised when entire systems are converted.
• This type of “network effects” problem is
known as the “chicken and egg” problem in
the telecoms or internet industry.
• Require unique business and funding
strategies to overcome
Description
• ROSCOs unwilling to purchase larger gauge
trains that may become “captive”. Address via
creation of a gauging section 54?
• Inverse funding – Offer route managers a
“gauging” bonus from central NR/DfT fund –
amount declines as more of the network is
gauged
• Sell infrastructure constraints – private
companies fund the rebuilding of problem
infrastructure and then lease back to the
network
• Increase VTAC based on gauge capacity of the
track to incentivise NR to increase?
Solutions
Strategies:
1. Signal long term commitment – invest enough money
that gives market confident your new system is here to
stay. Railway comparable – government mandate.
2. Use backwards or sideways compatibility to grow market
size. Railway comparable develop technology to ensure
older rolling stock remains compatible. Make
connections to European or HS2 markets.
3. Exploit niches to create “beachheads” e.g. Facebook
initially targeting Universities. Railway comparable –
convert short but very high density rail corridors first.
E.g. Barking to London Gateway. London commuter
services.
4. Lock key suppliers in – e.g. Sony convincing music
publishers to produce CDs. Railway comparable –
convince manufacturers to stop producing new UK gauge
vehicles (don’t support)
5. Create standalone value beyond network effect – VCRs
were successful as even without any market in video
cassettes the standalone value of time shifting TV was
high. Railway comparable – short double stack freight
routes.
6. Vertically integrate – Video game consoles producing
both the hardware and content. Railway comparable –
Alliances enabling both NR and TOC to share in benefit of
re-gauging. Privately funded industrial railroads -
convince northern car manufacturers to fund railway
construction to port of Tyne? (Only about 3 miles of
track to connect to ECML)
Learning from Technology: Solving
Chicken and Egg problem
-2000
-1500
-1000
-500
0
500
1000
1500
2000
1
9
17
25
33
41
49
57
65
73
81
89
97
Lower Gauge
Route by Route
Route by Route -
NPV
Rolling Change
Rolling Change -
NPV
KC06:01 –Gauging
Prioritisation Economic Model
RTS:CDP
MoreSpaceonTrains
KC06
• Do we increase gauge on a route by route basis,
or rolling basis as infrastructure is replaced?
• Cost benefits are only realised when entire
route is complete, and these benefits grow
through network effect
• Cost impact higher for replacing route by route
• Lower gauge also has negative costs while
routes are only partially adapted
• What is the optimum rollout strategy?
Description
• Create an economic model that combines
all the issues described above. Initial draft
results can be seen to the right.
• Model will enable impact of different cost
saving measures to be identified in a
systems context
• Combine model with NR gauging database
and NR asset register. Enable identifying
routes on which to increase gauge first
Solution
-1000
-500
0
500
1000
1500
2000
1
9
17
25
33
41
49
57
65
73
81
89
97
Upper Gauge
Route by Route
Route by Route -
NPV
Rolling Change
Rolling Change -
NPV
KC06:01 –Double Stack Freight
RTS:CDP
MoreSpaceonTrains
KC06
• Incentivising gauge increase is very difficult
initially prior to network effects
• Need to identify individual routes where the
cost benefits are large enough to outweigh
drawbacks
• HS2 is one, but double stack freight may be
another
• Proven concept in America, potential 50%
freight cost saving could justify gauging
increases even on short routes.
• No UIC gauge but trial Rotterdam route built
Description
• Carry out desktop study into potential
benefits of dual stack in UK context
• Develop standards and wagon design for
UK network
• Identify and cost demonstrator route
Solution
KC06:01 –Train Space
Modelling
RTS:CDP
MoreSpaceonTrains
KC06
• Increasing train width and minimising
components creates added space,
but what is the value of this?
• Without a value on space, making
the business case is more challenging
• Increased space should enable
increased capacity, reduced dwell
time and increased accessibility
Description
• Carry out university study into the impact
and benefits of increased interior space
• Outputs will be economic impacts of
increased space with which to use to
justify other demonstrator projects
• Will also identify whether increase in
space is most efficiently used for
increasing amount of 3+2 seating or
increasing aisle widths
Solution
KC06:01 –Economies of Scale
RTS:CDP
MoreSpaceonTrains
KC06
• Achieving UIC gauges will enable the
purchase of standard European rolling stock.
• This would enable far larger fleet sizes with
resulting economies of scale in both
manufacture and maintenance
• Would also potentially enable a cross
European ROSCO market, driving down
financing costs
• Would also enable export of UK rolling stock
expertise and manufacturing capabilities
Description
• Collaborate with manufacturers to
determine likely cost savings possible
• Consult with ROSCOs to identify impact of
European standardisation on rail vehicle
leasing.
• Work with DfT/BIS to calculate “social
value” of resulting export opportunities
on job creation
Solution
KC06:01 –Gauging Lobbying
RTS:CDP
MoreSpaceonTrains
KC06
Description
Solution
• Part of the “Tyranny of Small decisions”
problem, is actors lack of knowledge of
the larger system.
• Industry players aren’t aware of any
efforts or possibility to increase gauge
and hence continue “business as usual”
• GA missed gauging opportunity, HS2 at
risk of following.
• Key aspect of the work package will be
engaging with stakeholders and
communicating industry plans to the
industry and wider public.
• Need to work at bringing external
influence to prevent individual projects
seeking to reduce cost of gauging at the
expense of the wider network
KC06:02 – Structural Gauge
RTS:CDP
MoreSpaceonTrains
KC06
• How to increase the structural gauge
• At lower cost
• With less disruption
• And ensuring futureproofing
• Can be broken down into
• Track
• Structures
• Electrical systems
Challenge
• Overseeing existing RSSB and NR
programs
• Creation of adaptable catenary structure
• Creation of adaptable platforms
Proposed work
• Range of NR research programs such as
bridge raising, new track types, low profile
OLE etc.
• Large amount of NR “Business as usual”
work
Existing Work
• Requires both iterative improvements and
more radical technical developments
• Key focus is on minimising network effect
costs particularly for lower gauge
clearance and electrical systems
• Need to balance against other
infrastructure manager concerns
Solutions
KC06:02 - Track
RTS:CDP
MoreSpaceonTrains
KC06
• Track offers opportunities to:
• Lower profile giving additional clearance
• Greater fixity reducing movement
allowance
• Major issue is around UK “Six foot” –
major constraint to European width
vehicles. Lowering cost and quicker
solutions required to solve
Description
Solution
• Majority of work covered in NR’s ongoing
work streams and by KC12 – Low cost
railway
• Large amount of work also being
undertaken in KC2 –Minimal Disruption
• Hence main scope is maintaining oversight
and co-ordination with ongoing projects
KC06:02 - Structures
RTS:CDP
MoreSpaceonTrains
KC06
• Platform heights pose one of the biggest
network effect costs when changing gauging.
• How can they be changed without imposing
negative costs on the rest of the network?
• How can we also achieve level access?
• Reducing cost of other structures important
but considered NR “Business as usual”
Description
• Can platform gap fillers or vehicle ramps
be made sufficient for the UK market –
Adoption of existing RSSB research and
taking to trial
• Can adjustable platform structures be
designed that allow modifications to be
made quickly and cheaply? – Design
competition
Solutions
KC06:02 – Electrical Systems
RTS:CDP
MoreSpaceonTrains
KC06
• New OLE’s still being installed that are
outside our future gauge aspirations
• Yet increased OLE heights impose
additional costs on older rolling stock
• Reducing costs and speed of replacing and
installing OLE also required but covered in
NR and other WPO scopes
Description
• Require new “Adaptable” OLE designs.
That can be installed at current heights
yet can be changed in future at low cost
for larger gauge – Design Competition
• Ongoing management and input into
ongoing NR work streams.
Solutions
KC06:03 –Gauging Process
RTS:CDP
MoreSpaceonTrains
KC06
• How to:
• Reduce the cost of gauging
• Improve how we monitor gauge
• And improve the way we control gauge
limitations
• Application of digital solutions to
traditional problem
Challenge
• Current gauging approach risk is 10^31,
plenty of scope for reduction of
tolerances.
• Currently reliant on yellow measurement
trains – digital costs are now so low to
enable use of regular passenger trains
• The digital railway enables more complex
signalling rules allowing the integration of
gauging control to avoid infrastructure
work
Proposed work
• NR work on fitting 3D surveying
equipment to passenger vehicles
• D Gauge work on pantograph probabilistic
gauging
• V/S SIC work on standard gauges
Existing Work
• Supporting the adoption of probabilistic
gauging techniques
• Enabling the continuous monitoring of
gauge
• Integration of gauging into the signalling
system to enable:
• Smart train dynamics control
• Gauging signalling constraints
Solutions
KC06:03–Probabilistic Gauging
RTS:CDP
MoreSpaceonTrains
KC06
Description
Solutions
• Current gauging method provides
absolute clearance limits based on a
variety of factors – Yet the odds of all of
these factors coming into the play at the
exact same time is almost impossible
• Other industries such as nuclear have
shown only way to manage similar risks is
via probabilistic methods
• Supporting continued development of
statistical tools for carrying out gauging
assessments and statistical review of
existing standards
• Carrying out of testing to certify statistical
results correspond to real world
behaviour
KC06:03 – On Board Gauge
Monitoring
RTS:CDP
MoreSpaceonTrains
KC06
Description
Solutions
• Industry is currently dependent on NR
yellow trains for gauging measurement –
yet this is expensive and long time periods
increases the allowances need for changes
in between surveys
• Industry also nervous about reducing
clearances when no system exists to check
whether these work in practice
• Technology now exists to miniaturise
yellow train equipment sufficiently to fit
onto passenger rolling stock
• Big Data analytics also allow for lower
accuracy sensors to be used as long as we
get numerous repeat measurements
• FFCCTV provides opportunity for low
accuracy gauging measurement – safety
net to avoid bridge strikes etc.
KC06:03 – Gauging Signalling
Control
RTS:CDP
MoreSpaceonTrains
KC06
Description
Solution
• Two trains passing on a tight bend is one of the
main gauging constraints currently, yet this
occurs very rarely.
• Some pieces of infrastructure simply won’t be
able to replace – but many of these structures
do have clearance if track separation was
reduced.
• New in cab signalling allows opportunity for
more complex signalling rules.
• Develop standards for incorporating gauge
constraints into the signalling system –
ensuring two trains never go round a corner
at the same time etc.
• Develop advanced DAS systems that can help
avoid these constraining capacity via varying
train operation (avoid a passing on a corner
by increasing speed slightly etc.)
• Allows network effect benefits to be reached
quicker with there then being an easier
business case to change tight infrastructure
afterwards
KC06:03 – Smart Train
Dynamics Control
RTS:CDP
MoreSpaceonTrains
KC06
• Already accepted controlling train dynamics
based on infrastructure requirements –
Pendolino tilt
• Large amount of gauging clearances currently
caused by possible but physically very unlikely
situations – trains swaying into a corner for
example
• Removing the entire possibility of such events
could improve confidence with probabilistic
gauging
Description
• Develop “smart” train suspension systems
that can have limits imposed on them
based on inputs from digital signalling –
take learning from automotive industry
Solutions
KC06:04 –Vehicle Envelope
RTS:CDP
MoreSpaceonTrains
KC06
• How do we maximise the vehicle
envelope to make the most of what
capacity already exists?
• How do we most effectively make use of
additional clearance as it is created?
• How can we better adapt train capacities
to meet the needs of peak loads?
Challenge
• Work to miniaturise exterior components
particularly batteries and brake systems
• New designs to take advantage of freed
up underframe space
• Reducing OLE electrical clearances
• Optimising vehicle articulation
• Developing methods of varying train set
lengths in service
Solutions
• Ongoing manufacturer work to reduce
equipment size and weight
• Some low TRL projects by RSSB
Existing Work
• Step changes in equipment sizes are
possible if follow in footsteps of
automotive sector – Electric driven brake
callipers, lithium batteries etc.
• OLE clearance and corner overhangs can
both be addressed via vehicle changes
• Start preparing the technology vision for
how train will couple in 20 years time.
Proposed Work
KC06:04 – Exterior Equipment
Miniaturisation
RTS:CDP
MoreSpaceonTrains
KC06
• Modern EMUs now have large amounts of
unused underframe space.
• If underframe could be completely cleared
would allow the dropping of the floor,
enabling level access at European
standard platform heights
• DMU miniaturisation increases space for
hybridisation and range extension
Description
• Trial the use of electrically driven brake
callipers as seen on many electric cars –
removes the requirement for air tanks and
compressors freeing up the underframe.
Carrying on the work of project T860
• Support and co-ordinate other efforts at
equipment miniaturisation
Solutions
KC06:04 – Dropped Floor
Designs
RTS:CDP
MoreSpaceonTrains
KC06
• If successful in miniaturising underframe
equipment – how can this space be used
in the UK market?
• Continental designs exist for level access
at European platform heights
• Is space best used for passengers, freight
or moving equipment from interior to
exterior?
Description
• Develop UK suitable dropped floor
designs
Solutions
KC06:04 – Low Profile
Pantograph
RTS:CDP
MoreSpaceonTrains
KC06
• We currently lose around 270mm both above
and below the OLE in electrical clearance. The
single largest source of clearance requirement
• Required to provide protection from Impulse
Voltages – however protection can also be
provided via insulation
Description
• Develop new insulation methods for both
bridge structure and vehicle roofs
sufficient to allow reduction of electrical
clearance
• Develop lower profile pantographs that
can work at these lower heights
Solutions
KC06:04 – Vehicle Articulation
RTS:CDP
MoreSpaceonTrains
KC06
• Drive towards longer vehicles to reduce
bogie costs and space lost to
vestibules/couplings
• However longer vehicles lead to lower
width due to corner overhang
• What is the future optimum? Can we
make shorter length vehicles cheaper or
can we make longer vehicles wider?
Description
• Low TRL Work to investigate of the
incorporation of articulation in vehicle
body shells themselves
• Investigate use of articulated bogies for
UK market and minimising coupler
lengths.
Solutions
R² = 0.7059
2.6
2.65
2.7
2.75
2.8
2.85
2.9
2.95
3
3.05
3.1
15 20 25 30
Carriage Length Vs Width
Width
Poly. (Width)
KC06:04 – Increasing/ Varying
Train Lengths
RTS:CDP
MoreSpaceonTrains
KC06
• Need to increase platform lengths seen as
barrier to increased train lengths – but does it
need to be?
• Inter vehicle coupling currently slow and only
possible in stations – speeding this up or
enabling while travelling would enable far
better tailoring of vehicle capacity to demand
Description
• Research into the possibility of extending
vehicle lengths past station lengths – how
to manage passenger flows into overhang
carriages without increasing dwell times?
• Support development of higher reliability
and higher speed inter unit couplers.
• Develop the ability for unit to couple at
speed
Solutions
KC06:04 – Double Decker
Trains
RTS:CDP
MoreSpaceonTrains
KC06
• Will UK ever see double decker trains
(again)?
• Potential capacity increase but risk of
dwell time increase
• Capacity already exists in both
manufacturers and UK research base
• Key expectation of WPO
Description
• Co-ordination role of existing research and
manufacturer designs
• Potential work in identifying routes where
the business case is justified to push for
trials.
• Supporting the trial of a European vehicle
on UK infrastructure to test use in UK
market
Solutions
KC06:05 –Maximising Interior
Space
RTS:CDP
MoreSpaceonTrains
KC06
• How do we maximise the space available
within the vehicle envelope? Both by
increasing the space and improving how
we use it
• How do we do this both for legacy fleets
and new build?
• Plenty of designs already exist, focus
needs to be on addressing technical
blockers
Challenge
• Research into passenger flow and
optimising interior layouts to support
• Support adoption of composites to
minimise interior structural components
• Create optimised cabs designs
• Create time limited season ticket.
Solutions
• RSSB train of the future competition
Existing Work
• On many services space exists but is under
used, need to develop improved ways of
distributing passengers and balancing the
need of peak an off-peak travellers
• On commuter lines majority of the day is
spent carrying empty space, we need to
better incentivise its use
• Numerous components are suitable for
miniaturisation
Proposed Work
KC06:05 – Optimised Cab
Design
RTS:CDP
MoreSpaceonTrains
KC06
• Especially on multi unit vehicles, the
driver cab can take up a large proportion
of space, yet sit empty at least 50% of the
time.
• Differences in cab designs impose costs
and risks on operators of mixed fleets.
Description
• Develop a range of optimised,
standardised cab designs looking at:
• Half width designs
• Cabs that can be used by passengers when
not in use
• Use of FFCCTV to remove need to be at
front of train
• Looking at both new build and retrofit.
Solution
KC06:05 – Interior Component
Miniaturisation
RTS:CDP
MoreSpaceonTrains
KC06
• Large amount of space on rolling stock is “dead
space”, equipment cupboards, space around
seats, under tables etc. Can equipment be
miniaturised to free this up?
• Primarily ROSCO and manufacturer
responsibility – but new materials may support
Description
• Carry out 3d surveys of vehicles and
identify where biggest space savings can
be made
• Support the development and trial of
composite seats, luggage racks and tables.
Solution
KC06:05 – Improving
Passenger Interior Flow
RTS:CDP
MoreSpaceonTrains
KC06
• Particularly in crowded conditions, space usage
can become inefficient – empty seats,
passengers blocking doorways etc. How can we
encourage optimum passengers flow within
vehicles
• Problem can be managed by both physical train
design and by communication to passengers
whereas consciously or subconsciously
Description
• Low TRL research program into variety of
ideas such:
• Offset train doors
• Optimum aisle widths
• Optimum lighting and signage
• Optimum methods of communicating
crowding information
• Optimum platform design.
Solution
KC06:05 – Innovative Interior
Designs
RTS:CDP
MoreSpaceonTrains
KC06
• Numerous different interior seating options
exist yet few have been trialled in UK market
– can any improve capacity or passenger
comfort?
• Need to balance peak load capacity with off
peak comfort requirements
• DfT specification present blocker for
innovation in this area
• Some stakeholders reluctant to take on
designs that increase maintenance
requirements
Description
• Take on overseeing role of innovative
design proposals and support the best in
getting to trial
• Encourage focus on designs that are
passively flexible
• Lobby DfT to relax specifications in this
area
Solutions
KC06:05 – Optimising
Passenger Demand
RTS:CDP
MoreSpaceonTrains
KC06
• We are hitting serious overcrowding, yet off-peak
these same trains can be empty
• Being able to shift some of this demand would
achieve the exact same as increasing the amount of
space on trains.
• Existing negative “push factors” of lack of seating
etc. don’t work need positive “pull” factors
• Currently our cheapest tickets go to unpredictable
peak travellers – season ticket holders
Description
• Develop and trial “time limited” season
tickets e.g. for travel 6-7am. 2/3rd price
reduction if they travel outside of this.
• Either incorporate into existing system
e.g. C2C smart tickets
• Or trial with parallel ticketing system e.g.
LM block chain Experiment
Solution
Where will we be with the
Capability in 5 years
RTS:CDP
MoreSpaceonTrains
KC06
• Corporate sponsors aligned with all projects
• Value of additional space quantified for financial modelling
• Clear economic strategy for integrating gauging increase into industry plans
Gauging Business Case Defined
• Gauging fully integrated into Digital Railway Plans
• Demonstrator route for low cost upgrade of route clearance to W10 ready for CP7
Gauging Constraints Integrated Into Signalling System
• Adaptable OLE structure designed and demonstrator installed on part of network
Adaptable OLE
• Standards and wagon designs in place and tested
• Demonstrator route identified and designed ready for CP7
Double Stack Freight
WPO KC6
KC06:01
Government
Network Rail
FOC’s
Rolling Stock
Owners/Builders
KC06:02
Network Rail
KC06:03
Digital Rail
Network Rail
RSSB
Rolling Stock
Owners/Builders
KC06:04
Rolling Stock
Owners/
Builders
KC06:05
TOCs
Rolling Stock
Owners/Builders
Passengers
Disabled
Travellers
V/S SIC Other SICs
Stakeholder Group
RTS:CDP
MoreSpaceonTrains
KC06
Direct InterfaceDirect Interface
Interface via
other WPO
Feedback?
Please contact james.brown@angeltrains.co.uk
KC06
RTS:CDP
MoreSpaceonTrains
• Are you already working in any of these areas?
• Have you experienced any problems in trying to
bring in innovations in this area?
• Are there any projects you would like to get involved
in?
• What do you think of the projects highlighted here?

Mais conteĂşdo relacionado

Mais procurados

Kuwait PPP Transport Projects
Kuwait PPP Transport ProjectsKuwait PPP Transport Projects
Kuwait PPP Transport ProjectsIbrahim Al-Hudhaif
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Shyam Raman
 
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013Chris White
 
Regional Integrated Supply Chain Strategy for Rail
Regional Integrated Supply Chain  Strategy for Rail Regional Integrated Supply Chain  Strategy for Rail
Regional Integrated Supply Chain Strategy for Rail Ibrahim Al-Hudhaif
 
NJFuture Redevelopment Forum 2016 Rooney
NJFuture Redevelopment Forum 2016 RooneyNJFuture Redevelopment Forum 2016 Rooney
NJFuture Redevelopment Forum 2016 RooneyNew Jersey Future
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challengesInstitute for Transport Studies (ITS)
 
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019Association for Project Management
 
Container Terminal Development on the Continent: Africa Perspective
Container Terminal Development on the Continent: Africa PerspectiveContainer Terminal Development on the Continent: Africa Perspective
Container Terminal Development on the Continent: Africa PerspectiveWSP
 
Master thesis presentation
Master thesis presentationMaster thesis presentation
Master thesis presentationPradhyuman Raj
 
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...WSP
 
Analysis of different sector coupling paths for CO2 mitigation in the German ...
Analysis of different sector coupling paths for CO2 mitigation in the German ...Analysis of different sector coupling paths for CO2 mitigation in the German ...
Analysis of different sector coupling paths for CO2 mitigation in the German ...IEA-ETSAP
 
JCB meeting presentation on HydRON
JCB meeting presentation on HydRON JCB meeting presentation on HydRON
JCB meeting presentation on HydRON KTN
 
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915Association for Project Management
 
Winning strategy for Moscow St Petersburg for Deutsche Bahn
Winning strategy for Moscow St Petersburg for Deutsche BahnWinning strategy for Moscow St Petersburg for Deutsche Bahn
Winning strategy for Moscow St Petersburg for Deutsche BahnThomas Cluzel
 
Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments Sener Salci
 

Mais procurados (20)

World experience-in-railway-restructuring
World experience-in-railway-restructuringWorld experience-in-railway-restructuring
World experience-in-railway-restructuring
 
Rail Passenger Demand Forecasting - a view from the industry
Rail Passenger Demand Forecasting - a view from the industryRail Passenger Demand Forecasting - a view from the industry
Rail Passenger Demand Forecasting - a view from the industry
 
Kuwait PPP Transport Projects
Kuwait PPP Transport ProjectsKuwait PPP Transport Projects
Kuwait PPP Transport Projects
 
Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...Strategic analysis of communications based train control systems in the weste...
Strategic analysis of communications based train control systems in the weste...
 
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
Fuel Cell Electric Buses in California Fuel Cell Seminar 2013
 
Regional Integrated Supply Chain Strategy for Rail
Regional Integrated Supply Chain  Strategy for Rail Regional Integrated Supply Chain  Strategy for Rail
Regional Integrated Supply Chain Strategy for Rail
 
NJFuture Redevelopment Forum 2016 Rooney
NJFuture Redevelopment Forum 2016 RooneyNJFuture Redevelopment Forum 2016 Rooney
NJFuture Redevelopment Forum 2016 Rooney
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019
Sponsorship on the Network Rail Thameslink Programme, London, 4 September 2019
 
Container Terminal Development on the Continent: Africa Perspective
Container Terminal Development on the Continent: Africa PerspectiveContainer Terminal Development on the Continent: Africa Perspective
Container Terminal Development on the Continent: Africa Perspective
 
Stations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stationsStations as Places - designing & planning rail stations
Stations as Places - designing & planning rail stations
 
Status of Galileo
Status of Galileo Status of Galileo
Status of Galileo
 
Master thesis presentation
Master thesis presentationMaster thesis presentation
Master thesis presentation
 
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...
Mobility Pricing: How to Harness Mobility Pricing to Reduce Congestion, Promo...
 
Galileo differentiators for mass market
Galileo differentiators for mass marketGalileo differentiators for mass market
Galileo differentiators for mass market
 
Analysis of different sector coupling paths for CO2 mitigation in the German ...
Analysis of different sector coupling paths for CO2 mitigation in the German ...Analysis of different sector coupling paths for CO2 mitigation in the German ...
Analysis of different sector coupling paths for CO2 mitigation in the German ...
 
JCB meeting presentation on HydRON
JCB meeting presentation on HydRON JCB meeting presentation on HydRON
JCB meeting presentation on HydRON
 
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915
Delivering the Forth Replacement Crossing (Lawrence Shackman) SCOT100915
 
Winning strategy for Moscow St Petersburg for Deutsche Bahn
Winning strategy for Moscow St Petersburg for Deutsche BahnWinning strategy for Moscow St Petersburg for Deutsche Bahn
Winning strategy for Moscow St Petersburg for Deutsche Bahn
 
Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments Economics of Electricity Transmission Line Rehabilitation Investments
Economics of Electricity Transmission Line Rehabilitation Investments
 

Semelhante a Maximising Space on UK Trains

Sustainable future through innovation
Sustainable future through innovationSustainable future through innovation
Sustainable future through innovationTristan Wiggill
 
First group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways CompetitionFirst group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways CompetitionKTN
 
CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 James Nesbitt
 
Stefan van der Elst (KE-Works - NL)
Stefan van der Elst (KE-Works - NL)Stefan van der Elst (KE-Works - NL)
Stefan van der Elst (KE-Works - NL)I4MS_eu
 
AITPM Conference Presentation -Callan Stirzaker
AITPM Conference Presentation -Callan StirzakerAITPM Conference Presentation -Callan Stirzaker
AITPM Conference Presentation -Callan StirzakerJumpingJaq
 
Cross-sector Battery Systems Innovation Network | Launch event
Cross-sector Battery Systems Innovation Network | Launch eventCross-sector Battery Systems Innovation Network | Launch event
Cross-sector Battery Systems Innovation Network | Launch eventKTN
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Leonardo ENERGY
 
1520 Sochi conference 2015 Round Table INNOVATIONS TMH
1520 Sochi conference 2015 Round Table INNOVATIONS TMH1520 Sochi conference 2015 Round Table INNOVATIONS TMH
1520 Sochi conference 2015 Round Table INNOVATIONS TMHJan C. Harder
 
Cross-Sector Battery Systems Innovation Network: Batteries for Rail
Cross-Sector Battery Systems Innovation Network: Batteries for RailCross-Sector Battery Systems Innovation Network: Batteries for Rail
Cross-Sector Battery Systems Innovation Network: Batteries for RailKTN
 
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014Electrification Infrastructure: Whole Life Cost Reduction Congress 2014
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014marketinglbcg
 
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...KTN
 
Capacity charging mechanism for shared CO2 transportation and storage infrast...
Capacity charging mechanism for shared CO2 transportation and storage infrast...Capacity charging mechanism for shared CO2 transportation and storage infrast...
Capacity charging mechanism for shared CO2 transportation and storage infrast...Global CCS Institute
 
Innovation in Transnet
Innovation in TransnetInnovation in Transnet
Innovation in TransnetTristan Wiggill
 
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...Forth
 
Infrastructure Innovations in the Rail Industry #COMIT2017
Infrastructure Innovations in the Rail Industry #COMIT2017Infrastructure Innovations in the Rail Industry #COMIT2017
Infrastructure Innovations in the Rail Industry #COMIT2017Comit Projects Ltd
 
Global logistics management
Global logistics managementGlobal logistics management
Global logistics managementShagai Ebo
 
Atkins global rail opportunities 6th March 2014
Atkins global rail opportunities 6th March 2014Atkins global rail opportunities 6th March 2014
Atkins global rail opportunities 6th March 2014Matt Cody
 
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...SIFOfgem
 
Journey with TTSL
Journey with TTSLJourney with TTSL
Journey with TTSLAnkan Debgupta
 
Global rail opportunities- Atkins March 2014
Global rail opportunities- Atkins March 2014Global rail opportunities- Atkins March 2014
Global rail opportunities- Atkins March 2014Shyam Raman
 

Semelhante a Maximising Space on UK Trains (20)

Sustainable future through innovation
Sustainable future through innovationSustainable future through innovation
Sustainable future through innovation
 
First group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways CompetitionFirst group presentation in support of Digital Railways Competition
First group presentation in support of Digital Railways Competition
 
CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014 CBTC Communications Based Train Control conference March 12th 2014
CBTC Communications Based Train Control conference March 12th 2014
 
Stefan van der Elst (KE-Works - NL)
Stefan van der Elst (KE-Works - NL)Stefan van der Elst (KE-Works - NL)
Stefan van der Elst (KE-Works - NL)
 
AITPM Conference Presentation -Callan Stirzaker
AITPM Conference Presentation -Callan StirzakerAITPM Conference Presentation -Callan Stirzaker
AITPM Conference Presentation -Callan Stirzaker
 
Cross-sector Battery Systems Innovation Network | Launch event
Cross-sector Battery Systems Innovation Network | Launch eventCross-sector Battery Systems Innovation Network | Launch event
Cross-sector Battery Systems Innovation Network | Launch event
 
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
Overview of the FlexPlan project. Focus on EU regulatory analysis and TSO-DSO...
 
1520 Sochi conference 2015 Round Table INNOVATIONS TMH
1520 Sochi conference 2015 Round Table INNOVATIONS TMH1520 Sochi conference 2015 Round Table INNOVATIONS TMH
1520 Sochi conference 2015 Round Table INNOVATIONS TMH
 
Cross-Sector Battery Systems Innovation Network: Batteries for Rail
Cross-Sector Battery Systems Innovation Network: Batteries for RailCross-Sector Battery Systems Innovation Network: Batteries for Rail
Cross-Sector Battery Systems Innovation Network: Batteries for Rail
 
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014Electrification Infrastructure: Whole Life Cost Reduction Congress 2014
Electrification Infrastructure: Whole Life Cost Reduction Congress 2014
 
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...
Network Rail & Innovate UK: Scope of "SBRI Innovation in Automated Tunnel Exa...
 
Capacity charging mechanism for shared CO2 transportation and storage infrast...
Capacity charging mechanism for shared CO2 transportation and storage infrast...Capacity charging mechanism for shared CO2 transportation and storage infrast...
Capacity charging mechanism for shared CO2 transportation and storage infrast...
 
Innovation in Transnet
Innovation in TransnetInnovation in Transnet
Innovation in Transnet
 
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...
Policies For A Mature, Flourishing, Equitable EV Charging Ecosystem by Chris ...
 
Infrastructure Innovations in the Rail Industry #COMIT2017
Infrastructure Innovations in the Rail Industry #COMIT2017Infrastructure Innovations in the Rail Industry #COMIT2017
Infrastructure Innovations in the Rail Industry #COMIT2017
 
Global logistics management
Global logistics managementGlobal logistics management
Global logistics management
 
Atkins global rail opportunities 6th March 2014
Atkins global rail opportunities 6th March 2014Atkins global rail opportunities 6th March 2014
Atkins global rail opportunities 6th March 2014
 
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...
Show and Tell - Data and Digitalisation, Gas Network Asset Monitoring and Ana...
 
Journey with TTSL
Journey with TTSLJourney with TTSL
Journey with TTSL
 
Global rail opportunities- Atkins March 2014
Global rail opportunities- Atkins March 2014Global rail opportunities- Atkins March 2014
Global rail opportunities- Atkins March 2014
 

Último

Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptNarmatha D
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...121011101441
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxNiranjanYadav41
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Coursebim.edu.pl
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communicationpanditadesh123
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentBharaniDharan195623
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectssuserb6619e
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptMadan Karki
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxVelmuruganTECE
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvLewisJB
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfChristianCDAM
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substationstephanwindworld
 

Último (20)

Industrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.pptIndustrial Safety Unit-IV workplace health and safety.ppt
Industrial Safety Unit-IV workplace health and safety.ppt
 
Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...Instrumentation, measurement and control of bio process parameters ( Temperat...
Instrumentation, measurement and control of bio process parameters ( Temperat...
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
BSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptxBSNL Internship Training presentation.pptx
BSNL Internship Training presentation.pptx
 
Katarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School CourseKatarzyna Lipka-Sidor - BIM School Course
Katarzyna Lipka-Sidor - BIM School Course
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
POWER SYSTEMS-1 Complete notes examples
POWER SYSTEMS-1 Complete notes  examplesPOWER SYSTEMS-1 Complete notes  examples
POWER SYSTEMS-1 Complete notes examples
 
multiple access in wireless communication
multiple access in wireless communicationmultiple access in wireless communication
multiple access in wireless communication
 
Configuration of IoT devices - Systems managament
Configuration of IoT devices - Systems managamentConfiguration of IoT devices - Systems managament
Configuration of IoT devices - Systems managament
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in projectDM Pillar Training Manual.ppt will be useful in deploying TPM in project
DM Pillar Training Manual.ppt will be useful in deploying TPM in project
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
Indian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.pptIndian Dairy Industry Present Status and.ppt
Indian Dairy Industry Present Status and.ppt
 
Internet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptxInternet of things -Arshdeep Bahga .pptx
Internet of things -Arshdeep Bahga .pptx
 
Work Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvvWork Experience-Dalton Park.pptxfvvvvvvv
Work Experience-Dalton Park.pptxfvvvvvvv
 
Ch10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdfCh10-Global Supply Chain - Cadena de Suministro.pdf
Ch10-Global Supply Chain - Cadena de Suministro.pdf
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Earthing details of Electrical Substation
Earthing details of Electrical SubstationEarthing details of Electrical Substation
Earthing details of Electrical Substation
 

Maximising Space on UK Trains

  • 1. Rail Technical Strategy: Capability Delivery Plan KC06 More Space on Trains James Brown Work Package Owner RTS:CDP MoreSpaceonTrains KC06
  • 2. RTS:CDP MoreSpaceonTrains KC06 JamesBrown DataandPerformanceEngineer Data and Performance Engineer • Sensors & Big Data Analytics • General innovation programs within Angel Trains’ Technology Team Rolling Stock Experience: • Wabtec • Alstom • Scotrail • VTEC Previous Experience • Oil & Gas • Nuclear Defence • Nuclear Power • Banking
  • 3. Rail Technical Strategy • Industry committed to one plan sponsored by RDG, RSG and Network Rail • Expertise will be utilised from across the whole UK to deliver the programme, including from other sectors • Delivering system level technology demonstrators • Building new technical capability • Supporting key industry programmes including Digital Rail This approach is successful in other sectors KC06 RTS:CDP MoreSpaceonTrains
  • 4. Work Package Owners Dr Karen Lane ‘Running Trains Closer Together’ and ‘Service Timed to the Second’ Janine Fountain ‘Minimal Disruption to Train Services’ Crispin Humm ‘Efficient passenger flow through stations and trains’ and ‘Personalised customer experience’ Karl Butler-Garnham ‘More Value from Data’ Ouahcene Ourahmoune ‘Optimum energy use’ James Brown ‘More Space on Trains’ Ben Carrington ‘Intelligent Train’ Richard Errington ‘Flexible Freight’ Neil Tinworth ‘Low Cost Railway’ James Hardy ‘Accelerate Research, Development and Technology Deployment’ David Rowe ‘Research, Development and Technology into Industry Planning’ KC06 RTS:CDP MoreSpaceonTrains
  • 5. KC06: More Space on Trains • Maximise the size of trains running on the network • Optimise the use of space available • Maximise the utilisation of this space • Timescale out to 2044 • Currently 61 projects identified for CP6 RTS:CDP MoreSpaceonTrains KC06 Scope • Rolling Stock economies of scale • Increased passenger capacity, customer experience and accessibility • Increased freight capacity and efficiency • All benefits to be fully quantified as part of project Benefit • By 2044 • 90%+ of the UK network to be cleared for greater than UIC GB+ gauge. • All intercity routes to be cleared to UIC GC gauge • Double stack freight running on key freight routes • Average Passenger Km per Car Km up 25% Objective • Objectives are already technically achievable, however the commercial incentives aren’t in place at the current cost level • Hence focus is on: • Lowering the cost • Increasing the benefits • Aligning incentives • Making the most of what we have Challenge
  • 6. More Space on Trains Creating the Business Case Increasing Structural Gauge Improving the Gauging Process Increasing the Vehicle Envelope Maximising Interior Space Programme Structure RTS:CDP MoreSpaceonTrains KC06
  • 7. Programme Principles • To demonstrate new capabilities for UK rail – it is then up to the Industry to deliver • Focus on taking new technologies to the demonstrator stage • Take a whole system and long term view of the industry RTS:CDP MoreSpaceonTrains KC06 Scope 1. Focus on system level issues that affect multiples parties. 2. Focus on technical issues and standards based issues that would be difficult for individual parties to solve. 3. Identify industry corporate sponsors of all projects to ensure delivery pathways are identified and carried forward. 4. Think big and think long term 5. Ensure engagement with stakeholders outside of the rail industry. Principles • Risk of: • public investment removing incentives for private R&D • long term vision conflicting with short term drivers • projects developed in isolation not then being carried into delivery phase • simply carrying on “Business as usual” Issues
  • 8. Aim of Presentation • Plan supported by V/S SIC and RSSB’s Technical Leadership Group, now engaging with wider industry • Looking for potential project sponsors • Looking for potential suppliers • Looking for Feedback • Existing Pain points • Avoid pushing out private R&D • If interested, number of sessions being arranged where you can learn more RTS:CDP MoreSpaceonTrains KC06
  • 9. KC06:01 –Creating the Business Case RTS:CDP MoreSpaceonTrains KC06 • Gauging faces a combination of economic problems: • Network Effects • Tyranny of small decisions • Regardless of technology, increasing gauge will always be more expensive • How do we justify expense when benefit not felt till years afterwards? Challenge • Work out the most efficient economic approach to gauging improvement • Quantify the benefits of increased rolling stock space • Quantify the economy of scale benefits to be had by adopting UIC gauges • Identify suitable Funding Models and routes to market Solutions • V/S SIC Gauging Strategy Existing Work • Gauging prioritisation economic model • Double stack freight economic study • Modelling impact of increased train space on passenger loading • Consultation with manufacturers/ROSCOs to identify economy of scale benefits • Consultation with NR/DfT on funding models Proposed Work
  • 10. KC06:01 –Funding Models RTS:CDP MoreSpaceonTrains KC06 • Gauging projects, on individual pieces of infrastructure, will never have a positive business case, as the benefits are only realised when entire systems are converted. • This type of “network effects” problem is known as the “chicken and egg” problem in the telecoms or internet industry. • Require unique business and funding strategies to overcome Description • ROSCOs unwilling to purchase larger gauge trains that may become “captive”. Address via creation of a gauging section 54? • Inverse funding – Offer route managers a “gauging” bonus from central NR/DfT fund – amount declines as more of the network is gauged • Sell infrastructure constraints – private companies fund the rebuilding of problem infrastructure and then lease back to the network • Increase VTAC based on gauge capacity of the track to incentivise NR to increase? Solutions Strategies: 1. Signal long term commitment – invest enough money that gives market confident your new system is here to stay. Railway comparable – government mandate. 2. Use backwards or sideways compatibility to grow market size. Railway comparable develop technology to ensure older rolling stock remains compatible. Make connections to European or HS2 markets. 3. Exploit niches to create “beachheads” e.g. Facebook initially targeting Universities. Railway comparable – convert short but very high density rail corridors first. E.g. Barking to London Gateway. London commuter services. 4. Lock key suppliers in – e.g. Sony convincing music publishers to produce CDs. Railway comparable – convince manufacturers to stop producing new UK gauge vehicles (don’t support) 5. Create standalone value beyond network effect – VCRs were successful as even without any market in video cassettes the standalone value of time shifting TV was high. Railway comparable – short double stack freight routes. 6. Vertically integrate – Video game consoles producing both the hardware and content. Railway comparable – Alliances enabling both NR and TOC to share in benefit of re-gauging. Privately funded industrial railroads - convince northern car manufacturers to fund railway construction to port of Tyne? (Only about 3 miles of track to connect to ECML) Learning from Technology: Solving Chicken and Egg problem
  • 11. -2000 -1500 -1000 -500 0 500 1000 1500 2000 1 9 17 25 33 41 49 57 65 73 81 89 97 Lower Gauge Route by Route Route by Route - NPV Rolling Change Rolling Change - NPV KC06:01 –Gauging Prioritisation Economic Model RTS:CDP MoreSpaceonTrains KC06 • Do we increase gauge on a route by route basis, or rolling basis as infrastructure is replaced? • Cost benefits are only realised when entire route is complete, and these benefits grow through network effect • Cost impact higher for replacing route by route • Lower gauge also has negative costs while routes are only partially adapted • What is the optimum rollout strategy? Description • Create an economic model that combines all the issues described above. Initial draft results can be seen to the right. • Model will enable impact of different cost saving measures to be identified in a systems context • Combine model with NR gauging database and NR asset register. Enable identifying routes on which to increase gauge first Solution -1000 -500 0 500 1000 1500 2000 1 9 17 25 33 41 49 57 65 73 81 89 97 Upper Gauge Route by Route Route by Route - NPV Rolling Change Rolling Change - NPV
  • 12. KC06:01 –Double Stack Freight RTS:CDP MoreSpaceonTrains KC06 • Incentivising gauge increase is very difficult initially prior to network effects • Need to identify individual routes where the cost benefits are large enough to outweigh drawbacks • HS2 is one, but double stack freight may be another • Proven concept in America, potential 50% freight cost saving could justify gauging increases even on short routes. • No UIC gauge but trial Rotterdam route built Description • Carry out desktop study into potential benefits of dual stack in UK context • Develop standards and wagon design for UK network • Identify and cost demonstrator route Solution
  • 13. KC06:01 –Train Space Modelling RTS:CDP MoreSpaceonTrains KC06 • Increasing train width and minimising components creates added space, but what is the value of this? • Without a value on space, making the business case is more challenging • Increased space should enable increased capacity, reduced dwell time and increased accessibility Description • Carry out university study into the impact and benefits of increased interior space • Outputs will be economic impacts of increased space with which to use to justify other demonstrator projects • Will also identify whether increase in space is most efficiently used for increasing amount of 3+2 seating or increasing aisle widths Solution
  • 14. KC06:01 –Economies of Scale RTS:CDP MoreSpaceonTrains KC06 • Achieving UIC gauges will enable the purchase of standard European rolling stock. • This would enable far larger fleet sizes with resulting economies of scale in both manufacture and maintenance • Would also potentially enable a cross European ROSCO market, driving down financing costs • Would also enable export of UK rolling stock expertise and manufacturing capabilities Description • Collaborate with manufacturers to determine likely cost savings possible • Consult with ROSCOs to identify impact of European standardisation on rail vehicle leasing. • Work with DfT/BIS to calculate “social value” of resulting export opportunities on job creation Solution
  • 15. KC06:01 –Gauging Lobbying RTS:CDP MoreSpaceonTrains KC06 Description Solution • Part of the “Tyranny of Small decisions” problem, is actors lack of knowledge of the larger system. • Industry players aren’t aware of any efforts or possibility to increase gauge and hence continue “business as usual” • GA missed gauging opportunity, HS2 at risk of following. • Key aspect of the work package will be engaging with stakeholders and communicating industry plans to the industry and wider public. • Need to work at bringing external influence to prevent individual projects seeking to reduce cost of gauging at the expense of the wider network
  • 16. KC06:02 – Structural Gauge RTS:CDP MoreSpaceonTrains KC06 • How to increase the structural gauge • At lower cost • With less disruption • And ensuring futureproofing • Can be broken down into • Track • Structures • Electrical systems Challenge • Overseeing existing RSSB and NR programs • Creation of adaptable catenary structure • Creation of adaptable platforms Proposed work • Range of NR research programs such as bridge raising, new track types, low profile OLE etc. • Large amount of NR “Business as usual” work Existing Work • Requires both iterative improvements and more radical technical developments • Key focus is on minimising network effect costs particularly for lower gauge clearance and electrical systems • Need to balance against other infrastructure manager concerns Solutions
  • 17. KC06:02 - Track RTS:CDP MoreSpaceonTrains KC06 • Track offers opportunities to: • Lower profile giving additional clearance • Greater fixity reducing movement allowance • Major issue is around UK “Six foot” – major constraint to European width vehicles. Lowering cost and quicker solutions required to solve Description Solution • Majority of work covered in NR’s ongoing work streams and by KC12 – Low cost railway • Large amount of work also being undertaken in KC2 –Minimal Disruption • Hence main scope is maintaining oversight and co-ordination with ongoing projects
  • 18. KC06:02 - Structures RTS:CDP MoreSpaceonTrains KC06 • Platform heights pose one of the biggest network effect costs when changing gauging. • How can they be changed without imposing negative costs on the rest of the network? • How can we also achieve level access? • Reducing cost of other structures important but considered NR “Business as usual” Description • Can platform gap fillers or vehicle ramps be made sufficient for the UK market – Adoption of existing RSSB research and taking to trial • Can adjustable platform structures be designed that allow modifications to be made quickly and cheaply? – Design competition Solutions
  • 19. KC06:02 – Electrical Systems RTS:CDP MoreSpaceonTrains KC06 • New OLE’s still being installed that are outside our future gauge aspirations • Yet increased OLE heights impose additional costs on older rolling stock • Reducing costs and speed of replacing and installing OLE also required but covered in NR and other WPO scopes Description • Require new “Adaptable” OLE designs. That can be installed at current heights yet can be changed in future at low cost for larger gauge – Design Competition • Ongoing management and input into ongoing NR work streams. Solutions
  • 20. KC06:03 –Gauging Process RTS:CDP MoreSpaceonTrains KC06 • How to: • Reduce the cost of gauging • Improve how we monitor gauge • And improve the way we control gauge limitations • Application of digital solutions to traditional problem Challenge • Current gauging approach risk is 10^31, plenty of scope for reduction of tolerances. • Currently reliant on yellow measurement trains – digital costs are now so low to enable use of regular passenger trains • The digital railway enables more complex signalling rules allowing the integration of gauging control to avoid infrastructure work Proposed work • NR work on fitting 3D surveying equipment to passenger vehicles • D Gauge work on pantograph probabilistic gauging • V/S SIC work on standard gauges Existing Work • Supporting the adoption of probabilistic gauging techniques • Enabling the continuous monitoring of gauge • Integration of gauging into the signalling system to enable: • Smart train dynamics control • Gauging signalling constraints Solutions
  • 21. KC06:03–Probabilistic Gauging RTS:CDP MoreSpaceonTrains KC06 Description Solutions • Current gauging method provides absolute clearance limits based on a variety of factors – Yet the odds of all of these factors coming into the play at the exact same time is almost impossible • Other industries such as nuclear have shown only way to manage similar risks is via probabilistic methods • Supporting continued development of statistical tools for carrying out gauging assessments and statistical review of existing standards • Carrying out of testing to certify statistical results correspond to real world behaviour
  • 22. KC06:03 – On Board Gauge Monitoring RTS:CDP MoreSpaceonTrains KC06 Description Solutions • Industry is currently dependent on NR yellow trains for gauging measurement – yet this is expensive and long time periods increases the allowances need for changes in between surveys • Industry also nervous about reducing clearances when no system exists to check whether these work in practice • Technology now exists to miniaturise yellow train equipment sufficiently to fit onto passenger rolling stock • Big Data analytics also allow for lower accuracy sensors to be used as long as we get numerous repeat measurements • FFCCTV provides opportunity for low accuracy gauging measurement – safety net to avoid bridge strikes etc.
  • 23. KC06:03 – Gauging Signalling Control RTS:CDP MoreSpaceonTrains KC06 Description Solution • Two trains passing on a tight bend is one of the main gauging constraints currently, yet this occurs very rarely. • Some pieces of infrastructure simply won’t be able to replace – but many of these structures do have clearance if track separation was reduced. • New in cab signalling allows opportunity for more complex signalling rules. • Develop standards for incorporating gauge constraints into the signalling system – ensuring two trains never go round a corner at the same time etc. • Develop advanced DAS systems that can help avoid these constraining capacity via varying train operation (avoid a passing on a corner by increasing speed slightly etc.) • Allows network effect benefits to be reached quicker with there then being an easier business case to change tight infrastructure afterwards
  • 24. KC06:03 – Smart Train Dynamics Control RTS:CDP MoreSpaceonTrains KC06 • Already accepted controlling train dynamics based on infrastructure requirements – Pendolino tilt • Large amount of gauging clearances currently caused by possible but physically very unlikely situations – trains swaying into a corner for example • Removing the entire possibility of such events could improve confidence with probabilistic gauging Description • Develop “smart” train suspension systems that can have limits imposed on them based on inputs from digital signalling – take learning from automotive industry Solutions
  • 25. KC06:04 –Vehicle Envelope RTS:CDP MoreSpaceonTrains KC06 • How do we maximise the vehicle envelope to make the most of what capacity already exists? • How do we most effectively make use of additional clearance as it is created? • How can we better adapt train capacities to meet the needs of peak loads? Challenge • Work to miniaturise exterior components particularly batteries and brake systems • New designs to take advantage of freed up underframe space • Reducing OLE electrical clearances • Optimising vehicle articulation • Developing methods of varying train set lengths in service Solutions • Ongoing manufacturer work to reduce equipment size and weight • Some low TRL projects by RSSB Existing Work • Step changes in equipment sizes are possible if follow in footsteps of automotive sector – Electric driven brake callipers, lithium batteries etc. • OLE clearance and corner overhangs can both be addressed via vehicle changes • Start preparing the technology vision for how train will couple in 20 years time. Proposed Work
  • 26. KC06:04 – Exterior Equipment Miniaturisation RTS:CDP MoreSpaceonTrains KC06 • Modern EMUs now have large amounts of unused underframe space. • If underframe could be completely cleared would allow the dropping of the floor, enabling level access at European standard platform heights • DMU miniaturisation increases space for hybridisation and range extension Description • Trial the use of electrically driven brake callipers as seen on many electric cars – removes the requirement for air tanks and compressors freeing up the underframe. Carrying on the work of project T860 • Support and co-ordinate other efforts at equipment miniaturisation Solutions
  • 27. KC06:04 – Dropped Floor Designs RTS:CDP MoreSpaceonTrains KC06 • If successful in miniaturising underframe equipment – how can this space be used in the UK market? • Continental designs exist for level access at European platform heights • Is space best used for passengers, freight or moving equipment from interior to exterior? Description • Develop UK suitable dropped floor designs Solutions
  • 28. KC06:04 – Low Profile Pantograph RTS:CDP MoreSpaceonTrains KC06 • We currently lose around 270mm both above and below the OLE in electrical clearance. The single largest source of clearance requirement • Required to provide protection from Impulse Voltages – however protection can also be provided via insulation Description • Develop new insulation methods for both bridge structure and vehicle roofs sufficient to allow reduction of electrical clearance • Develop lower profile pantographs that can work at these lower heights Solutions
  • 29. KC06:04 – Vehicle Articulation RTS:CDP MoreSpaceonTrains KC06 • Drive towards longer vehicles to reduce bogie costs and space lost to vestibules/couplings • However longer vehicles lead to lower width due to corner overhang • What is the future optimum? Can we make shorter length vehicles cheaper or can we make longer vehicles wider? Description • Low TRL Work to investigate of the incorporation of articulation in vehicle body shells themselves • Investigate use of articulated bogies for UK market and minimising coupler lengths. Solutions R² = 0.7059 2.6 2.65 2.7 2.75 2.8 2.85 2.9 2.95 3 3.05 3.1 15 20 25 30 Carriage Length Vs Width Width Poly. (Width)
  • 30. KC06:04 – Increasing/ Varying Train Lengths RTS:CDP MoreSpaceonTrains KC06 • Need to increase platform lengths seen as barrier to increased train lengths – but does it need to be? • Inter vehicle coupling currently slow and only possible in stations – speeding this up or enabling while travelling would enable far better tailoring of vehicle capacity to demand Description • Research into the possibility of extending vehicle lengths past station lengths – how to manage passenger flows into overhang carriages without increasing dwell times? • Support development of higher reliability and higher speed inter unit couplers. • Develop the ability for unit to couple at speed Solutions
  • 31. KC06:04 – Double Decker Trains RTS:CDP MoreSpaceonTrains KC06 • Will UK ever see double decker trains (again)? • Potential capacity increase but risk of dwell time increase • Capacity already exists in both manufacturers and UK research base • Key expectation of WPO Description • Co-ordination role of existing research and manufacturer designs • Potential work in identifying routes where the business case is justified to push for trials. • Supporting the trial of a European vehicle on UK infrastructure to test use in UK market Solutions
  • 32. KC06:05 –Maximising Interior Space RTS:CDP MoreSpaceonTrains KC06 • How do we maximise the space available within the vehicle envelope? Both by increasing the space and improving how we use it • How do we do this both for legacy fleets and new build? • Plenty of designs already exist, focus needs to be on addressing technical blockers Challenge • Research into passenger flow and optimising interior layouts to support • Support adoption of composites to minimise interior structural components • Create optimised cabs designs • Create time limited season ticket. Solutions • RSSB train of the future competition Existing Work • On many services space exists but is under used, need to develop improved ways of distributing passengers and balancing the need of peak an off-peak travellers • On commuter lines majority of the day is spent carrying empty space, we need to better incentivise its use • Numerous components are suitable for miniaturisation Proposed Work
  • 33. KC06:05 – Optimised Cab Design RTS:CDP MoreSpaceonTrains KC06 • Especially on multi unit vehicles, the driver cab can take up a large proportion of space, yet sit empty at least 50% of the time. • Differences in cab designs impose costs and risks on operators of mixed fleets. Description • Develop a range of optimised, standardised cab designs looking at: • Half width designs • Cabs that can be used by passengers when not in use • Use of FFCCTV to remove need to be at front of train • Looking at both new build and retrofit. Solution
  • 34. KC06:05 – Interior Component Miniaturisation RTS:CDP MoreSpaceonTrains KC06 • Large amount of space on rolling stock is “dead space”, equipment cupboards, space around seats, under tables etc. Can equipment be miniaturised to free this up? • Primarily ROSCO and manufacturer responsibility – but new materials may support Description • Carry out 3d surveys of vehicles and identify where biggest space savings can be made • Support the development and trial of composite seats, luggage racks and tables. Solution
  • 35. KC06:05 – Improving Passenger Interior Flow RTS:CDP MoreSpaceonTrains KC06 • Particularly in crowded conditions, space usage can become inefficient – empty seats, passengers blocking doorways etc. How can we encourage optimum passengers flow within vehicles • Problem can be managed by both physical train design and by communication to passengers whereas consciously or subconsciously Description • Low TRL research program into variety of ideas such: • Offset train doors • Optimum aisle widths • Optimum lighting and signage • Optimum methods of communicating crowding information • Optimum platform design. Solution
  • 36. KC06:05 – Innovative Interior Designs RTS:CDP MoreSpaceonTrains KC06 • Numerous different interior seating options exist yet few have been trialled in UK market – can any improve capacity or passenger comfort? • Need to balance peak load capacity with off peak comfort requirements • DfT specification present blocker for innovation in this area • Some stakeholders reluctant to take on designs that increase maintenance requirements Description • Take on overseeing role of innovative design proposals and support the best in getting to trial • Encourage focus on designs that are passively flexible • Lobby DfT to relax specifications in this area Solutions
  • 37. KC06:05 – Optimising Passenger Demand RTS:CDP MoreSpaceonTrains KC06 • We are hitting serious overcrowding, yet off-peak these same trains can be empty • Being able to shift some of this demand would achieve the exact same as increasing the amount of space on trains. • Existing negative “push factors” of lack of seating etc. don’t work need positive “pull” factors • Currently our cheapest tickets go to unpredictable peak travellers – season ticket holders Description • Develop and trial “time limited” season tickets e.g. for travel 6-7am. 2/3rd price reduction if they travel outside of this. • Either incorporate into existing system e.g. C2C smart tickets • Or trial with parallel ticketing system e.g. LM block chain Experiment Solution
  • 38. Where will we be with the Capability in 5 years RTS:CDP MoreSpaceonTrains KC06 • Corporate sponsors aligned with all projects • Value of additional space quantified for financial modelling • Clear economic strategy for integrating gauging increase into industry plans Gauging Business Case Defined • Gauging fully integrated into Digital Railway Plans • Demonstrator route for low cost upgrade of route clearance to W10 ready for CP7 Gauging Constraints Integrated Into Signalling System • Adaptable OLE structure designed and demonstrator installed on part of network Adaptable OLE • Standards and wagon designs in place and tested • Demonstrator route identified and designed ready for CP7 Double Stack Freight
  • 39. WPO KC6 KC06:01 Government Network Rail FOC’s Rolling Stock Owners/Builders KC06:02 Network Rail KC06:03 Digital Rail Network Rail RSSB Rolling Stock Owners/Builders KC06:04 Rolling Stock Owners/ Builders KC06:05 TOCs Rolling Stock Owners/Builders Passengers Disabled Travellers V/S SIC Other SICs Stakeholder Group RTS:CDP MoreSpaceonTrains KC06 Direct InterfaceDirect Interface Interface via other WPO
  • 40. Feedback? Please contact james.brown@angeltrains.co.uk KC06 RTS:CDP MoreSpaceonTrains • Are you already working in any of these areas? • Have you experienced any problems in trying to bring in innovations in this area? • Are there any projects you would like to get involved in? • What do you think of the projects highlighted here?

Notas do Editor

  1. Normal OLE height is 4.7m
  2. Brief outline of what will be achieved in the next 5 years in your capability What demonstrators will be delivered? How will things have changed