  1. 1
  2. The Chinese University of Hong Kong (CUHK)  Established in 1963  Shatin Campus:  1.37 km2  150+ buildings  20,000+ students (UG & PG)  Adding 3,000+ UG students starting 2012  6,000+ staff  8 Faculties + Graduate School  9 Colleges  200+ departments/units  100,000+ alumni 2
  3. Challenges  Highly decentralized  Not enough sharing of resources so higher cost  One central data center but a lot of server rooms and small data centers around campus  No DR site for data center  Out of data center space  2012: More buildings, more colleges and more students and staff  Support teaching, learning, research and administration 3
  4. Internal Services Provider  Subscription model  Users pay rental charge to enjoy the services  Users do not need to buy hardware and relevant software  Optional to users  Need to compete with others  Have to be competitive  Have to be market/user oriented  Have to make continuous improvement 4
  5. Service Catalog  VM/PM + SAN + Backup  With or without virtual Firewall  Server Racks  IP Phone + Data Ports  Support departmental WiFi access points  Physical Security  Central Door Access / Carpark / CCTV / Burglar Alarms 5
  6. Key Characteristics  For sharing among multiple users  Less wastage  Charge by “usage”  Can support users’ dynamic resource demand  Less customization 6
  7. Design & Support  Standardization  Scalability  Keep things simple  Automation  Work Order Tracking  Inventory / Accounting / Charging  Need to keep a balance between support of dynamic demand and simplicity  Go for simple charging model 7
  8. Data Center in Pi Chiu Building  24 x 7 operations  30+ years old  <400m2  Non-standard raised floor  24” x 24”  10” deep  UPS: 300KVA + 400KVA  Gen Set: 300KVA + 800KVA  CRAC unit: 6 (+ 1 by end of 2011)  FM200  Housing ~1,000 physical servers -> running out of space  Data Center Management Improvement over the last few years  Stricter Physical Security  Keep track of all machines installed inside  All cabinets locked  No more new data cabling underneath raised floor to improve airflow 8
  9. Twin Site  New Data Center of < 800 m2  To be ready in early 2013  800KVA capacity  Will use the latest standards (Tier 3 as target)  Will be more advanced than Pi Chiu  Active-active, mutual backup  Will be manned  Need to think about how to distribute manpower among the 2 data centers  HKIX will have a POP there  Will support departmental server rack requirements 9
  10. Greener Data Center  More efficient power & cooling  Equipment placement  Airflow issue  Cold Aisle / Hot Aisle  Careful location selection for CRAC units and outlets for cold air  Airflow underneath raised floor should not be blocked  No data cables underneath  Data cables will be laid over cable trays above racks 10
  11. Cabling and Networking for Data Centers  Too many data cables underneath raised floor blocking airflow in Pi Chiu  Have to change this  Unified fabric to support main communications needs within data centers: Ethernet (for data) and Fiber Channel (for storage)  Top of Rack: Unified networking equipment, Cat5e within rack  End of Row / Data Center Core: To support 10G links to individual racks, MMF across racks  Only MMF are to be laid above the racks  Gradual migration for Pi Chiu 11
  12. VM + SAN + Backup  Server Consolidation by virtualization  Look for scalability and easy expansion  Fast deployment of new VM  High availability requirements  VMware site license  Storage Integration  Consolidation of SAN networks  Start using FCoE  Central management  Centralized Backup  Offsite Backup  Development VM platform to replace development servers in workshops 12
  13. New Infrastructure Service Ideas  Central equipment/servers which can scale up to support many users around campus  For consolidation and cost savings, to use existing structured cabling system  Everything over the same structured cabling system with star topology  Cat-5e for horizontal and vertical  SMF for inter-building (and vertical if necessary)  MMF (high-end 50μm) for inside data centers  Everything over IP / Ethernet  Have to enhance redundancy all around the network infrastructure including power redundancy  New service under consideration: Digital Signage 13
  14. Other Issues to Keep in Mind  IPv6  DNSSEC  Multicast  IAM 14
  15. Our Advantages  HKIX  Options of Fixed Network Operators  One of the two HARNET backbone hubs 15
  16. Considerations of Public Cloud  Will use public cloud service if/when necessary  Feel more comfortable if the service is being provided by servers/storage situated in HK  For better connectivity, the public cloud network to be chosen has to be connected to HKIX, if not using dedicated connection (extra cost involved) 16
  17. Thank you! 17