SlideShare uma empresa Scribd logo
1 de 60
1
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

           Subpart P - Excavations
  1926.650 Scope, application, and definitions
                  Applicable
1926.650(b) Definitions applicable to this subpart.
Benching “(Benching system) means a method of
protecting employees from cave-ins by excavating the
sides of an excavation to form one or a series of
horizontal levels or steps, usually with vertical or
near-vertical surfaces between levels.”


                                                      2
OCCUPATIONAL SAFETY AND HEALTH
      OSHA              ADMINISTRATION

          Subpart P - Excavations
 1926.650 Scope, application, and definitions
                 Applicable
1926.650(b) Definitions applicable to this subpart.
Competent person “means one who is capable of
identifying existing and predictable hazards in the
surroundings, or working conditions which are
unsanitary, hazardous, or dangerous to employees,
and who has authorization to take prompt corrective
measures to eliminate them.”

                                                  3
OCCUPATIONAL SAFETY AND HEALTH
     OSHA                ADMINISTRATION

          Subpart P - Excavations
 1926.650 Scope, application, and definitions
                 Applicable
1926.650(b) Definitions applicable to this subpart.
Excavation “means any man-made cut, cavity, trench,
or depression in an earth surface, formed by earth
removal.”

Failure “means the breakage, displacement, or
permanent deformation of a structural member or
connection so as to reduce its structural integrity and
its supportive capabilities.”
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

          Subpart P - Excavations
 1926.650 Scope, application, and definitions
                 Applicable
1926.650(b) Definitions applicable to this subpart.
Stable rock “means natural solid mineral material that
can be excavated with vertical sides and will remain
intact while exposed. Unstable rock is considered to be
stable when the rock material on the side or sides of
the excavation is secured against caving-in or
movement by rock bolts or by another protective
system that has been designed by a registered
professional engineer.”
OCCUPATIONAL SAFETY AND HEALTH
        OSHA                ADMINISTRATION

            Subpart P - Excavations
   1926.650 Scope, application, and definitions
                   Applicable
1926.650(b) Definitions applicable to this subpart.
Trench (Trench excavation) “means a narrow excavation (in
relation to its length) made below the surface of the ground.
In general, the depth is greater than the width, but the width
of a trench (measured at the bottom) is not greater than 15
feet. If forms or other structures are installed or constructed
in an excavation so as to reduce the dimension measured
from the forms or structure to the side of the excavation to
15 feet or less (measured at the bottom of the excavation),
the excavation is also considered to be a trench.”
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements
1926.651(a) Surface encumbrances. “All surface
encumbrances that are located so as to create a hazard
to employees shall be removed or supported, as
necessary, to safeguard employees.”

1926.651(b) Underground installations. (1) “The
estimated location of utility installations, such as sewer,
telephone, fuel, electric, water lines, or any other
underground installations that reasonably may be
expected to be encountered during excavation work,
shall be determined prior to opening an excavation.”
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

           Subpart P - Excavations
  1926.651 Specific excavation requirements
1926.651(c) Access and egress – (1) Structural ramps. (i)
“Structural ramps that are used solely by employees as
a means of access or egress from excavations shall be
designed by a competent person. Structural ramps used
for access or egress of equipment shall be designed by a
competent person qualified in structural design, and
shall be constructed in accordance with the design.”


                                                       8
9
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements
1926.651(c)(2) Means of egress from trench excavations.
“A stairway, ladder, ramp or other safe means of egress
shall be located in trench excavations that are 4 feet or
more in depth so as to require no more than 25 feet of
lateral travel for employees.”




                                                       10
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements

1926.651(g)(1)(i) “Where oxygen deficiency
(atmospheres containing less than 19.5 percent oxygen)
or a hazardous atmosphere exists or could reasonably
be expected to exist, such as in excavations in landfill
areas or excavations in areas where hazardous
substances are stored nearby, the atmospheres in the
excavation shall be tested before employees enter
excavations greater than 4 feet in depth.”

                                                      11
12
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

           Subpart P - Excavations
  1926.651 Specific excavation requirements
1926.651(g)(2) Emergency rescue equipment. (i)
“Emergency rescue equipment, such as breathing
apparatus, a safety harness and line, or a basket
stretcher, shall be readily available where hazardous
atmospheric conditions exist or may reasonably be
expected to develop during work in an excavation. This
equipment shall be attended when in use.”


                                                    13
OCCUPATIONAL SAFETY AND HEALTH
         OSHA               ADMINISTRATION

              Subpart P - Excavations
     1926.651 Specific excavation requirements
1926.651(h) Protection from hazards associated with water
accumulation. (1) “Employees shall not work in excavations
in which there is accumulated water, or in excavations in
which water is accumulating, unless adequate precautions
have been taken to protect employees against the hazards
posed by water accumulation. The precautions necessary to
protect employees adequately vary with each situation, but
could include special support or shield systems to protect
from cave-ins, water removal to control the level of
accumulating water, or use of a safety harness and lifeline.”
                                                          14
15
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements
1926.651(i) Stability of adjacent structures. (1) “Where
the stability of adjoining buildings, walls, or other
structures is endangered by excavation operations,
support systems such as shoring, bracing, or
underpinning shall be provided to ensure the stability
of such structures for the protection of employees.”



                                                           16
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements
1926.651(j)(2) “Employees shall be protected from
excavated or other materials or equipment that could
pose a hazard by falling or rolling into excavations.
Protection shall be provided by placing and keeping
such materials or equipment at least 2 feet from the
edge of excavations, or by the use of retaining devices
that are sufficient to prevent materials or equipment
from falling or rolling into excavations, or by a
combination of both if necessary.”
                                                          17
18
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart P - Excavations
   1926.651 Specific excavation requirements
1926.651(k) Inspections. (1) “Daily inspections of
excavations, the adjacent areas, and protective systems
shall be made by a competent person for evidence that
could result in possible cave-ins, indications of failure
of protective systems, hazardous atmospheres, or other
hazardous conditions. An inspection shall be conducted
by the competent person prior to the start of work and
as needed throughout the shift. Inspections shall also be
made after every rainstorm or other hazard increasing
occurrence. These inspections are only required when
employee exposure can be reasonably anticipated.”
20
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems

1926.652(a) Protection of employees in excavations. (1)
“Each employee in an excavation shall be protected
from cave-ins by an adequate protective system
designed in accordance with paragraph (b) or (c) of this
section except when:”

1926.652(a)(1)(i) “Excavations are made entirely in
stable rock; or”
                                                      21
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
1926.652(a)(1)(ii) “Excavations are less than 5 feet in
depth and examination of the ground by a competent
person provides no indication of a potential cave-in.”

1926.652(a)(2) “Protective systems shall have the
capacity to resist without failure all loads that are
intended or could reasonably be expected to be
applied or transmitted to the system.”

                                                          22
OCCUPATIONAL SAFETY AND HEALTH
       OSHA              ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
1926.652(b) Design of sloping and benching systems.
“The slopes and configurations of sloping and benching
systems shall be selected and constructed by the
employer or his designee and shall be in accordance
with the requirements of paragraph (b)(1); or, in the
alternative, paragraph (b)(2); or, in the alternative,
paragraph (b)(3), or, in the alternative, paragraph (b)
(4), as follows;”

                                                     23
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(b)(1) Option (1) – Allowable configurations
and slopes. (i) “Excavations shall be sloped at an angle
not steeper than one and one-half horizontal to one
vertical (34 degrees measured from the horizontal),
unless the employer uses one of the other options listed
below;”



                                                      24
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(b)(2) Option (2) – Determination of slopes and
configurations using Appendices A and B. “Maximum
allowable slopes, and allowable configurations for
sloping and benching systems, shall be determined in
accordance with the conditions and requirements set
forth in appendices A and B to this subpart.”



                                                     25
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
Stable Rock “means natural solid mineral matter that
can be excavated with vertical sides and remain intact
while exposed”

 Type A “Means cohesive soils with an unconfined
compressive strength of 1.5 ton per square foot (tsf).”

Examples of cohesive soils are: clay, silty clay, sandy
clay, loam.
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
Type B (i) “means cohesive soil with an unconfined
compressive strength greater than 0.5 tsf but less than
1.5 tsf.”
(ii) “Granular cohesionless soils including: angular
gravel (similar to crushed rock), silt, silt loam, sandy
loam and,”
(iii) “Previously disturbed soils except those which would
otherwise be classed as Type C soil.”
(iv) “Type A, but is fissured or subject to vibration; or”
(v) “Dry rock that is not stable.”
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

            Subpart P - Excavations
  1926.652 Requirements for protective systems
  Appendix A to Subpart P – Soil Classification
Type C means
(ii)“Cohesive soil with an unconfined compressive
    strength of 0.5 tsf or less;”
(iii) “Granular soils including gravel, sand, and loamy
    sand; or”
(iv) “Submerged soil or soil from which water is freely
    seeping; or”
(v) “Submerged rock that is not stable.”
                                                          28
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
(2) Basis of classification. The classification of deposits
shall be made based on the results of at least one
visual and at least one manual analysis. Such analyses
shall be conducted by a competent person…………




                                                          29
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
(d) Acceptable visual and manual tests – (1) Visual
tests. “Visual analysis is conducted to determine
qualitative information regarding the excavation site
in general, the soil adjacent to the excavation, the soil
forming the sides of the open excavation, and the soil
taken as samples from excavated material.”


                                                            30
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
•Observe the side of the opened excavation and the
surface area adjacent to the excavation.
•Crack-like openings such as tension cracks could
indicate fissured material.
•If chunks of soil spall off a vertical side, the soil
could be fissured.
•Small spalls are evidence of moving ground and are
indications of potentially hazardous situations.
                                                         31
OCCUPATIONAL SAFETY AND HEALTH
       OSHA                ADMINISTRATION

            Subpart P - Excavations
  1926.652 Requirements for protective systems
  Appendix A to Subpart P – Soil Classification

•Observe the area adjacent to the excavation and the
excavation itself for evidence of existing utility and
other underground structures, and to identify
previously disturbed soil.
• Observe the opened side of the excavation to identify
layered systems. Examine layered systems to identify
if the layers slope toward the excavation. Estimate the
degree of slope of the layers.
                                                          32
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
(2) Manual tests. “Manual analysis of soil samples is
conducted to determine quantitative as well as
qualitative properties of soil and to provide more
information in order to classify soil properly.”




                                                        33
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
(i) Plasticity. “Mold a moist or wet sample of soil into a
ball and attempt to roll it into threads as thin as 1/8-
inch in diameter. Cohesive material can be successfully
rolled into threads without crumbling. For example if at
least a two inch length of 1/8-inch thread can be held on
one end without tearing, the soil is cohesive.”


                                                       34
Plasticity
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
(ii) Dry strength
•Soil that remains in clumps when excavated is
cohesive
•Soil that breaks up easily and does not stay in clumps
is granular
•Cemented soil is highly cohesive, will not break with
finger pressure
•Cohesive soil high in clay, does not break apart into
particles, can be formed
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
Appendix A to Subpart P – Soil Classification
•Retrieve a large clump of undisturbed spoil
•Attempt to penetrate the soil with the tip of the
thumb
•Type A soil can be penetrated only with great force
•Type B will penetrate to the full length of the thumb
nail.
•Type C will penetrate easily several inches and can
be molded by light finger pressure.
                                                     37
OCCUPATIONAL SAFETY AND HEALTH
      OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
 Appendix A to Subpart P – Soil Classification
Other strength tests. “Estimates of unconfined
compressive strength of soils can also be obtained by
use of a pocket penetrometer or by using a hand-
operated shearvane.”




                                                        38
• POCKET PENETROMETER.
  Penetrometers are direct-              Pocket
  reading, spring-operated
  instruments used to determine
                                      penetrometer
  the unconfined compressive
  strength of saturated cohesive
  soils.
• Once pushed into the soil, an
  indicator sleeve displays the
  reading.
• The instrument is calibrated in
  either tons per square foot (tsf)
  or kilograms per square
  centimeter (kPa).
• However, Penetrometers have
  error rates in the range of ±
  20-40%.
Pocket penetrometer
          • Push red ring on the
            barrel all the way
            toward the handle
          • Push shaft into the soil
            up to the red ring
          • Hold barrel so as to not
            to interfere with the
            spring inside the barrel
          • Read the unconfined
            compressive strength at
            bottom of the red slip
            ring
                                  40
Torvane Shear
• Select fresh clod or block
  of undisturbed soil from
  spoil pile
• Cut a smooth surface on
  the clod
• Insert vanes of device into
  the soil
• Retract vanes to show foot
  imprint
• Set indicator at zero
• Hold device firmly against
  soil and twist in clockwise
  manner until soil fails in
                                The direct instrument reading must be
  shear                          multiplied by 2 to provide results in
                                       tons per square foot (tsf)
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(b)(3) Option (3) – Designs using other
tabulated data. (i) “Designs of sloping or benching
systems shall be selected from and in accordance with
tabulated data, such as tables and charts.”

1926.652(b)(3)(iii) At least one copy of the tabulated
data which identifies the registered professional
engineer who approved the data…………………….

                                                         42
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
1926.652(b)(4) Option (4) – Design by a registered
professional engineer. (i) “Sloping and benching
systems not utilizing Option (1) or Option (2) or
Option (3) under paragraph (b) of this section shall be
approved by a registered professional engineer.”




                                                          43
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(c) Design of support systems, shield systems,
and other protective systems. “Designs of support
systems shield systems, and other protective systems
shall be selected and constructed by the employer or his
designee and shall be in accordance with the
requirements of paragraph (c)(1); or, in the alternative,
paragraph (c)(2); or, in the alternative, paragraph (c)
(3); or, in the alternative, paragraph (c)(4) as follows;”

                                                       44
OCCUPATIONAL SAFETY AND HEALTH
       OSHA              ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
1926.652(c)(1) Option (1) – Designs using Appendices
A, C and D. “Designs for timber shoring in trenches
shall be determined in accordance with the conditions
and requirements set forth in Appendix A and C to
this subpart. Designs for aluminum hydraulic shoring
shall be accordance with paragraph (c)(2) of this
section, but if manufacturer’s tabulated data cannot
be utilized, designs shall be in accordance with
Appendix D.”
                                                        45
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

           Subpart P - Excavations
 1926.652 Requirements for protective systems
1926.652(c)(2) Option 2 – Designs Using Manufacturer’s
Tabulated Data. (i) “Design of support systems, shield
systems, or other protective systems that are drawn
from manufacturer’s tabulated data shall be in
accordance with all specifications, recommendations,
and limitations issued or made by the manufacturer.”



                                                    46
OCCUPATIONAL SAFETY AND HEALTH
       OSHA               ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(c)(3) Option (3) – Designs using other
tabulated data. (i) “Designs of support systems, shield
systems, or other protective systems shall be selected
from and be in accordance with tabulated data, such as
tables and charts.”

1926.652(c)(3)(iii) At least one copy of the tabulated
data, which identifies the registered professional
engineer who approved the data……………………..
                                                         47
OCCUPATIONAL SAFETY AND HEALTH
      OSHA                ADMINISTRATION

          Subpart P - Excavations
1926.652 Requirements for protective systems
1926.652(c)(4) Option (4) – Design by a registered
professional engineer, (i) “Support systems, shield
systems, and other protective systems not utilizing
Option 1, Option 2 or Option 3, above, shall be
approved by a registered professional engineer.”




                                                      48
49
50
51
52
53
54
55
56
57
58
59
60

Mais conteúdo relacionado

Mais procurados

Subpart K - Electrical
Subpart K - ElectricalSubpart K - Electrical
Subpart K - ElectricalFFSafety
 
Subpart E - PPE
Subpart E  - PPESubpart E  - PPE
Subpart E - PPEFFSafety
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03vppradeepkumar
 
Subpart O - Motor Vehicles
Subpart O - Motor VehiclesSubpart O - Motor Vehicles
Subpart O - Motor VehiclesFFSafety
 
Excavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IExcavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IAtlantic Training, LLC.
 
Excavation Safety Training Module 1
Excavation Safety Training Module 1Excavation Safety Training Module 1
Excavation Safety Training Module 1Melissa Lewis
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations Amol Pawar
 
12 trenching and excavation safety
12 trenching and excavation safety12 trenching and excavation safety
12 trenching and excavation safetyCervelliere Limited
 
Excavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMExcavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMAtlantic Training, LLC.
 
Trenching & excavation
Trenching & excavationTrenching & excavation
Trenching & excavationrebel39tt
 
Subpart D - Health & Environment
Subpart D - Health & EnvironmentSubpart D - Health & Environment
Subpart D - Health & EnvironmentFFSafety
 
Subpart J - Welding
Subpart J  - WeldingSubpart J  - Welding
Subpart J - WeldingFFSafety
 
Excavations Safety Training by Safety Excellence
Excavations Safety Training by Safety ExcellenceExcavations Safety Training by Safety Excellence
Excavations Safety Training by Safety ExcellenceAtlantic Training, LLC.
 
Wks 4-excavations-excavation-safety-guide
Wks 4-excavations-excavation-safety-guideWks 4-excavations-excavation-safety-guide
Wks 4-excavations-excavation-safety-guideAkhilesh Singh
 

Mais procurados (20)

Subpart K - Electrical
Subpart K - ElectricalSubpart K - Electrical
Subpart K - Electrical
 
Subpart E - PPE
Subpart E  - PPESubpart E  - PPE
Subpart E - PPE
 
Excavation and-trenching safety 03
Excavation and-trenching safety 03Excavation and-trenching safety 03
Excavation and-trenching safety 03
 
Subpart O - Motor Vehicles
Subpart O - Motor VehiclesSubpart O - Motor Vehicles
Subpart O - Motor Vehicles
 
510 trenching 2015
510 trenching 2015510 trenching 2015
510 trenching 2015
 
Excavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&IExcavation and Trenching Onsite Wastewater Systems by L&I
Excavation and Trenching Onsite Wastewater Systems by L&I
 
OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements OSHA Trenching and Excavation Requirements
OSHA Trenching and Excavation Requirements
 
Excavation Safety Training Module 1
Excavation Safety Training Module 1Excavation Safety Training Module 1
Excavation Safety Training Module 1
 
Safety in Excavations
Safety in Excavations Safety in Excavations
Safety in Excavations
 
12 trenching and excavation safety
12 trenching and excavation safety12 trenching and excavation safety
12 trenching and excavation safety
 
Excavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHMExcavation, Trenching, and Soil Mechanics by FHM
Excavation, Trenching, and Soil Mechanics by FHM
 
Trenching & excavation
Trenching & excavationTrenching & excavation
Trenching & excavation
 
Subpart D - Health & Environment
Subpart D - Health & EnvironmentSubpart D - Health & Environment
Subpart D - Health & Environment
 
Trenching shoring
Trenching shoringTrenching shoring
Trenching shoring
 
Subpart J - Welding
Subpart J  - WeldingSubpart J  - Welding
Subpart J - Welding
 
Excavations Safety Training by Safety Excellence
Excavations Safety Training by Safety ExcellenceExcavations Safety Training by Safety Excellence
Excavations Safety Training by Safety Excellence
 
Excavation Safety Training by OSHAX.Org
Excavation Safety Training by OSHAX.OrgExcavation Safety Training by OSHAX.Org
Excavation Safety Training by OSHAX.Org
 
Wks 4-excavations-excavation-safety-guide
Wks 4-excavations-excavation-safety-guideWks 4-excavations-excavation-safety-guide
Wks 4-excavations-excavation-safety-guide
 
Excavation & Trenching by PATHS
Excavation & Trenching by PATHSExcavation & Trenching by PATHS
Excavation & Trenching by PATHS
 
EXCAVATIONS
EXCAVATIONSEXCAVATIONS
EXCAVATIONS
 

Destaque

Trenching in review 2016
Trenching in review 2016Trenching in review 2016
Trenching in review 2016John Newquist
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety Reliance
 
Trenching - The Year in Review 2015 csc conference
Trenching - The Year in Review 2015 csc conferenceTrenching - The Year in Review 2015 csc conference
Trenching - The Year in Review 2015 csc conferenceJohn Newquist
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in reviewvtsiri
 
SPR-Annual Staff Safety Training 2015
SPR-Annual Staff Safety Training 2015SPR-Annual Staff Safety Training 2015
SPR-Annual Staff Safety Training 2015John Sherman, CPRP
 
Forklift operator trainer's guide day one - rev
Forklift operator trainer's guide day one - revForklift operator trainer's guide day one - rev
Forklift operator trainer's guide day one - revacastrejon
 
Forklift safety
Forklift safetyForklift safety
Forklift safetyir_ham
 
Fall protection in construction
Fall protection in constructionFall protection in construction
Fall protection in constructionHatem Nasri
 
OSHA Eye and Face Protection
OSHA Eye and Face ProtectionOSHA Eye and Face Protection
OSHA Eye and Face ProtectionJo Woolery
 
Yüksekte Çalışmada Uluslararası Yaklaşımlar
Yüksekte Çalışmada Uluslararası YaklaşımlarYüksekte Çalışmada Uluslararası Yaklaşımlar
Yüksekte Çalışmada Uluslararası YaklaşımlarİGY Zirve
 
GMP Sub Part A & B
GMP Sub Part A & BGMP Sub Part A & B
GMP Sub Part A & BHARDIK PATEL
 
Subpart G - Signs and Signals
Subpart G - Signs and SignalsSubpart G - Signs and Signals
Subpart G - Signs and SignalsFFSafety
 
osha 1926 confined space construction 2015
osha 1926 confined space construction 2015osha 1926 confined space construction 2015
osha 1926 confined space construction 2015John Newquist
 

Destaque (20)

Trenching in review 2016
Trenching in review 2016Trenching in review 2016
Trenching in review 2016
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
Excavation & Trenching Safety
Excavation & Trenching Safety Excavation & Trenching Safety
Excavation & Trenching Safety
 
Trenching - The Year in Review 2015 csc conference
Trenching - The Year in Review 2015 csc conferenceTrenching - The Year in Review 2015 csc conference
Trenching - The Year in Review 2015 csc conference
 
OSHA Recordkeeping
OSHA RecordkeepingOSHA Recordkeeping
OSHA Recordkeeping
 
Trenching 2014 year in review
Trenching 2014 year in reviewTrenching 2014 year in review
Trenching 2014 year in review
 
Research
ResearchResearch
Research
 
SPR-Annual Staff Safety Training 2015
SPR-Annual Staff Safety Training 2015SPR-Annual Staff Safety Training 2015
SPR-Annual Staff Safety Training 2015
 
Forklift operator trainer's guide day one - rev
Forklift operator trainer's guide day one - revForklift operator trainer's guide day one - rev
Forklift operator trainer's guide day one - rev
 
Forklift safety
Forklift safetyForklift safety
Forklift safety
 
Fall protection in construction
Fall protection in constructionFall protection in construction
Fall protection in construction
 
OSHA Eye and Face Protection
OSHA Eye and Face ProtectionOSHA Eye and Face Protection
OSHA Eye and Face Protection
 
Confined_space_rescue_procedure
Confined_space_rescue_procedureConfined_space_rescue_procedure
Confined_space_rescue_procedure
 
Windsor Consulting Group 2017 OSHA Outreach Training Schedule
Windsor Consulting Group 2017 OSHA Outreach Training ScheduleWindsor Consulting Group 2017 OSHA Outreach Training Schedule
Windsor Consulting Group 2017 OSHA Outreach Training Schedule
 
Yüksekte Çalışmada Uluslararası Yaklaşımlar
Yüksekte Çalışmada Uluslararası YaklaşımlarYüksekte Çalışmada Uluslararası Yaklaşımlar
Yüksekte Çalışmada Uluslararası Yaklaşımlar
 
Incident
IncidentIncident
Incident
 
GMP Sub Part A & B
GMP Sub Part A & BGMP Sub Part A & B
GMP Sub Part A & B
 
Occupational Noise Exposure and Hearing Conservation
Occupational Noise Exposure and Hearing ConservationOccupational Noise Exposure and Hearing Conservation
Occupational Noise Exposure and Hearing Conservation
 
Subpart G - Signs and Signals
Subpart G - Signs and SignalsSubpart G - Signs and Signals
Subpart G - Signs and Signals
 
osha 1926 confined space construction 2015
osha 1926 confined space construction 2015osha 1926 confined space construction 2015
osha 1926 confined space construction 2015
 

Semelhante a Subpart P - Excavations

Subpart C Safety And Health
Subpart C   Safety And HealthSubpart C   Safety And Health
Subpart C Safety And HealthFFSafety
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
Subpart Q Concrete Written
Subpart Q   Concrete   WrittenSubpart Q   Concrete   Written
Subpart Q Concrete WrittenFFSafety
 
fall protection 2015
 fall protection 2015 fall protection 2015
fall protection 2015John Newquist
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material HandlingFFSafety
 
Personal Protective Equipment in the Construction Industry Training by NMENV
Personal Protective Equipment in the Construction Industry Training by NMENVPersonal Protective Equipment in the Construction Industry Training by NMENV
Personal Protective Equipment in the Construction Industry Training by NMENVAtlantic Training, LLC.
 
Ppe report
Ppe reportPpe report
Ppe reportmadz_mj
 
Osha top-5-scaffolding-violations-infographic
Osha top-5-scaffolding-violations-infographicOsha top-5-scaffolding-violations-infographic
Osha top-5-scaffolding-violations-infographicJames Rhoad
 
Excavation Awareness Training.pptx
Excavation Awareness Training.pptxExcavation Awareness Training.pptx
Excavation Awareness Training.pptxAdeniranIdris
 
mechanical lifting crane.pptx
mechanical lifting crane.pptxmechanical lifting crane.pptx
mechanical lifting crane.pptxAmirFarzamnia1
 
Working_At_Height_01.ppt
Working_At_Height_01.pptWorking_At_Height_01.ppt
Working_At_Height_01.ppthossam74752
 
Excavation safety
Excavation safetyExcavation safety
Excavation safetykaolapenang
 
Fall Protection, Gtech
Fall Protection, GtechFall Protection, Gtech
Fall Protection, GtechFFSafety
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015John Newquist
 
Residential fall prevention
Residential fall preventionResidential fall prevention
Residential fall preventionLBruceB
 
Mfc construction fy17
Mfc construction fy17Mfc construction fy17
Mfc construction fy17John Newquist
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolitionHni Amiera
 

Semelhante a Subpart P - Excavations (20)

510 trenching 2018
510 trenching 2018510 trenching 2018
510 trenching 2018
 
Subpart C Safety And Health
Subpart C   Safety And HealthSubpart C   Safety And Health
Subpart C Safety And Health
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
Subpart Q Concrete Written
Subpart Q   Concrete   WrittenSubpart Q   Concrete   Written
Subpart Q Concrete Written
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
fall protection 2015
 fall protection 2015 fall protection 2015
fall protection 2015
 
Subpart H - Material Handling
Subpart H -  Material HandlingSubpart H -  Material Handling
Subpart H - Material Handling
 
Ppe construction
Ppe constructionPpe construction
Ppe construction
 
Personal Protective Equipment in the Construction Industry Training by NMENV
Personal Protective Equipment in the Construction Industry Training by NMENVPersonal Protective Equipment in the Construction Industry Training by NMENV
Personal Protective Equipment in the Construction Industry Training by NMENV
 
Ppe report
Ppe reportPpe report
Ppe report
 
Osha top-5-scaffolding-violations-infographic
Osha top-5-scaffolding-violations-infographicOsha top-5-scaffolding-violations-infographic
Osha top-5-scaffolding-violations-infographic
 
Excavation Awareness Training.pptx
Excavation Awareness Training.pptxExcavation Awareness Training.pptx
Excavation Awareness Training.pptx
 
mechanical lifting crane.pptx
mechanical lifting crane.pptxmechanical lifting crane.pptx
mechanical lifting crane.pptx
 
Working_At_Height_01.ppt
Working_At_Height_01.pptWorking_At_Height_01.ppt
Working_At_Height_01.ppt
 
Excavation safety
Excavation safetyExcavation safety
Excavation safety
 
Fall Protection, Gtech
Fall Protection, GtechFall Protection, Gtech
Fall Protection, Gtech
 
Demolition Safety 2015
Demolition Safety 2015Demolition Safety 2015
Demolition Safety 2015
 
Residential fall prevention
Residential fall preventionResidential fall prevention
Residential fall prevention
 
Mfc construction fy17
Mfc construction fy17Mfc construction fy17
Mfc construction fy17
 
OSHA demolition
OSHA demolitionOSHA demolition
OSHA demolition
 

Mais de FFSafety

S A F E T Y P H O T O S P R E S E N T A T I O N
S A F E T Y  P H O T O S  P R E S E N T A T I O NS A F E T Y  P H O T O S  P R E S E N T A T I O N
S A F E T Y P H O T O S P R E S E N T A T I O NFFSafety
 
Site Photos, 0608
Site Photos, 0608Site Photos, 0608
Site Photos, 0608FFSafety
 
00999 Focus Four 131
00999 Focus Four 13100999 Focus Four 131
00999 Focus Four 131FFSafety
 
Recordkeeping 00150 22
Recordkeeping 00150 22Recordkeeping 00150 22
Recordkeeping 00150 22FFSafety
 
Subpart F - Fire Protection
Subpart F -  Fire ProtectionSubpart F -  Fire Protection
Subpart F - Fire ProtectionFFSafety
 
Focus Four Ppp
Focus Four PppFocus Four Ppp
Focus Four PppFFSafety
 
Scaffolding
ScaffoldingScaffolding
ScaffoldingFFSafety
 
Scaffolds C
Scaffolds CScaffolds C
Scaffolds CFFSafety
 
Safetyorient
SafetyorientSafetyorient
SafetyorientFFSafety
 
Scaffold 5
Scaffold 5Scaffold 5
Scaffold 5FFSafety
 

Mais de FFSafety (12)

S A F E T Y P H O T O S P R E S E N T A T I O N
S A F E T Y  P H O T O S  P R E S E N T A T I O NS A F E T Y  P H O T O S  P R E S E N T A T I O N
S A F E T Y P H O T O S P R E S E N T A T I O N
 
Site Photos, 0608
Site Photos, 0608Site Photos, 0608
Site Photos, 0608
 
00999 Focus Four 131
00999 Focus Four 13100999 Focus Four 131
00999 Focus Four 131
 
Recordkeeping 00150 22
Recordkeeping 00150 22Recordkeeping 00150 22
Recordkeeping 00150 22
 
Subpart F - Fire Protection
Subpart F -  Fire ProtectionSubpart F -  Fire Protection
Subpart F - Fire Protection
 
Article
ArticleArticle
Article
 
Focus Four Ppp
Focus Four PppFocus Four Ppp
Focus Four Ppp
 
Ppe C
Ppe CPpe C
Ppe C
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
Scaffolds C
Scaffolds CScaffolds C
Scaffolds C
 
Safetyorient
SafetyorientSafetyorient
Safetyorient
 
Scaffold 5
Scaffold 5Scaffold 5
Scaffold 5
 

Último

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.Curtis Poe
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsNathaniel Shimoni
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Farhan Tariq
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfLoriGlavin3
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesManik S Magar
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI AgeCprime
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxLoriGlavin3
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityIES VE
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Strongerpanagenda
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observabilityitnewsafrica
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfpanagenda
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxLoriGlavin3
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024BookNet Canada
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkPixlogix Infotech
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch TuesdayIvanti
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...itnewsafrica
 
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...itnewsafrica
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesBernd Ruecker
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxLoriGlavin3
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Mark Goldstein
 

Último (20)

How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.How AI, OpenAI, and ChatGPT impact business and software.
How AI, OpenAI, and ChatGPT impact business and software.
 
Time Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directionsTime Series Foundation Models - current state and future directions
Time Series Foundation Models - current state and future directions
 
Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...Genislab builds better products and faster go-to-market with Lean project man...
Genislab builds better products and faster go-to-market with Lean project man...
 
Moving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdfMoving Beyond Passwords: FIDO Paris Seminar.pdf
Moving Beyond Passwords: FIDO Paris Seminar.pdf
 
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotesMuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
MuleSoft Online Meetup Group - B2B Crash Course: Release SparkNotes
 
A Framework for Development in the AI Age
A Framework for Development in the AI AgeA Framework for Development in the AI Age
A Framework for Development in the AI Age
 
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptxMerck Moving Beyond Passwords: FIDO Paris Seminar.pptx
Merck Moving Beyond Passwords: FIDO Paris Seminar.pptx
 
Decarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a realityDecarbonising Buildings: Making a net-zero built environment a reality
Decarbonising Buildings: Making a net-zero built environment a reality
 
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better StrongerModern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
Modern Roaming for Notes and Nomad – Cheaper Faster Better Stronger
 
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security ObservabilityGlenn Lazarus- Why Your Observability Strategy Needs Security Observability
Glenn Lazarus- Why Your Observability Strategy Needs Security Observability
 
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdfSo einfach geht modernes Roaming fuer Notes und Nomad.pdf
So einfach geht modernes Roaming fuer Notes und Nomad.pdf
 
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptxDigital Identity is Under Attack: FIDO Paris Seminar.pptx
Digital Identity is Under Attack: FIDO Paris Seminar.pptx
 
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: Loan Stars - Tech Forum 2024
 
React Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App FrameworkReact Native vs Ionic - The Best Mobile App Framework
React Native vs Ionic - The Best Mobile App Framework
 
2024 April Patch Tuesday
2024 April Patch Tuesday2024 April Patch Tuesday
2024 April Patch Tuesday
 
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...Zeshan Sattar- Assessing the skill requirements and industry expectations for...
Zeshan Sattar- Assessing the skill requirements and industry expectations for...
 
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...Abdul Kader Baba- Managing Cybersecurity Risks  and Compliance Requirements i...
Abdul Kader Baba- Managing Cybersecurity Risks and Compliance Requirements i...
 
QCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architecturesQCon London: Mastering long-running processes in modern architectures
QCon London: Mastering long-running processes in modern architectures
 
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptxThe Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
The Fit for Passkeys for Employee and Consumer Sign-ins: FIDO Paris Seminar.pptx
 
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
Arizona Broadband Policy Past, Present, and Future Presentation 3/25/24
 

Subpart P - Excavations

  • 1. 1
  • 2. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.650 Scope, application, and definitions Applicable 1926.650(b) Definitions applicable to this subpart. Benching “(Benching system) means a method of protecting employees from cave-ins by excavating the sides of an excavation to form one or a series of horizontal levels or steps, usually with vertical or near-vertical surfaces between levels.” 2
  • 3. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.650 Scope, application, and definitions Applicable 1926.650(b) Definitions applicable to this subpart. Competent person “means one who is capable of identifying existing and predictable hazards in the surroundings, or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them.” 3
  • 4. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.650 Scope, application, and definitions Applicable 1926.650(b) Definitions applicable to this subpart. Excavation “means any man-made cut, cavity, trench, or depression in an earth surface, formed by earth removal.” Failure “means the breakage, displacement, or permanent deformation of a structural member or connection so as to reduce its structural integrity and its supportive capabilities.”
  • 5. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.650 Scope, application, and definitions Applicable 1926.650(b) Definitions applicable to this subpart. Stable rock “means natural solid mineral material that can be excavated with vertical sides and will remain intact while exposed. Unstable rock is considered to be stable when the rock material on the side or sides of the excavation is secured against caving-in or movement by rock bolts or by another protective system that has been designed by a registered professional engineer.”
  • 6. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.650 Scope, application, and definitions Applicable 1926.650(b) Definitions applicable to this subpart. Trench (Trench excavation) “means a narrow excavation (in relation to its length) made below the surface of the ground. In general, the depth is greater than the width, but the width of a trench (measured at the bottom) is not greater than 15 feet. If forms or other structures are installed or constructed in an excavation so as to reduce the dimension measured from the forms or structure to the side of the excavation to 15 feet or less (measured at the bottom of the excavation), the excavation is also considered to be a trench.”
  • 7. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(a) Surface encumbrances. “All surface encumbrances that are located so as to create a hazard to employees shall be removed or supported, as necessary, to safeguard employees.” 1926.651(b) Underground installations. (1) “The estimated location of utility installations, such as sewer, telephone, fuel, electric, water lines, or any other underground installations that reasonably may be expected to be encountered during excavation work, shall be determined prior to opening an excavation.”
  • 8. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(c) Access and egress – (1) Structural ramps. (i) “Structural ramps that are used solely by employees as a means of access or egress from excavations shall be designed by a competent person. Structural ramps used for access or egress of equipment shall be designed by a competent person qualified in structural design, and shall be constructed in accordance with the design.” 8
  • 9. 9
  • 10. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(c)(2) Means of egress from trench excavations. “A stairway, ladder, ramp or other safe means of egress shall be located in trench excavations that are 4 feet or more in depth so as to require no more than 25 feet of lateral travel for employees.” 10
  • 11. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(g)(1)(i) “Where oxygen deficiency (atmospheres containing less than 19.5 percent oxygen) or a hazardous atmosphere exists or could reasonably be expected to exist, such as in excavations in landfill areas or excavations in areas where hazardous substances are stored nearby, the atmospheres in the excavation shall be tested before employees enter excavations greater than 4 feet in depth.” 11
  • 12. 12
  • 13. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(g)(2) Emergency rescue equipment. (i) “Emergency rescue equipment, such as breathing apparatus, a safety harness and line, or a basket stretcher, shall be readily available where hazardous atmospheric conditions exist or may reasonably be expected to develop during work in an excavation. This equipment shall be attended when in use.” 13
  • 14. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(h) Protection from hazards associated with water accumulation. (1) “Employees shall not work in excavations in which there is accumulated water, or in excavations in which water is accumulating, unless adequate precautions have been taken to protect employees against the hazards posed by water accumulation. The precautions necessary to protect employees adequately vary with each situation, but could include special support or shield systems to protect from cave-ins, water removal to control the level of accumulating water, or use of a safety harness and lifeline.” 14
  • 15. 15
  • 16. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(i) Stability of adjacent structures. (1) “Where the stability of adjoining buildings, walls, or other structures is endangered by excavation operations, support systems such as shoring, bracing, or underpinning shall be provided to ensure the stability of such structures for the protection of employees.” 16
  • 17. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(j)(2) “Employees shall be protected from excavated or other materials or equipment that could pose a hazard by falling or rolling into excavations. Protection shall be provided by placing and keeping such materials or equipment at least 2 feet from the edge of excavations, or by the use of retaining devices that are sufficient to prevent materials or equipment from falling or rolling into excavations, or by a combination of both if necessary.” 17
  • 18. 18
  • 19. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.651 Specific excavation requirements 1926.651(k) Inspections. (1) “Daily inspections of excavations, the adjacent areas, and protective systems shall be made by a competent person for evidence that could result in possible cave-ins, indications of failure of protective systems, hazardous atmospheres, or other hazardous conditions. An inspection shall be conducted by the competent person prior to the start of work and as needed throughout the shift. Inspections shall also be made after every rainstorm or other hazard increasing occurrence. These inspections are only required when employee exposure can be reasonably anticipated.”
  • 20. 20
  • 21. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(a) Protection of employees in excavations. (1) “Each employee in an excavation shall be protected from cave-ins by an adequate protective system designed in accordance with paragraph (b) or (c) of this section except when:” 1926.652(a)(1)(i) “Excavations are made entirely in stable rock; or” 21
  • 22. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(a)(1)(ii) “Excavations are less than 5 feet in depth and examination of the ground by a competent person provides no indication of a potential cave-in.” 1926.652(a)(2) “Protective systems shall have the capacity to resist without failure all loads that are intended or could reasonably be expected to be applied or transmitted to the system.” 22
  • 23. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(b) Design of sloping and benching systems. “The slopes and configurations of sloping and benching systems shall be selected and constructed by the employer or his designee and shall be in accordance with the requirements of paragraph (b)(1); or, in the alternative, paragraph (b)(2); or, in the alternative, paragraph (b)(3), or, in the alternative, paragraph (b) (4), as follows;” 23
  • 24. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(b)(1) Option (1) – Allowable configurations and slopes. (i) “Excavations shall be sloped at an angle not steeper than one and one-half horizontal to one vertical (34 degrees measured from the horizontal), unless the employer uses one of the other options listed below;” 24
  • 25. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(b)(2) Option (2) – Determination of slopes and configurations using Appendices A and B. “Maximum allowable slopes, and allowable configurations for sloping and benching systems, shall be determined in accordance with the conditions and requirements set forth in appendices A and B to this subpart.” 25
  • 26. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification Stable Rock “means natural solid mineral matter that can be excavated with vertical sides and remain intact while exposed” Type A “Means cohesive soils with an unconfined compressive strength of 1.5 ton per square foot (tsf).” Examples of cohesive soils are: clay, silty clay, sandy clay, loam.
  • 27. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification Type B (i) “means cohesive soil with an unconfined compressive strength greater than 0.5 tsf but less than 1.5 tsf.” (ii) “Granular cohesionless soils including: angular gravel (similar to crushed rock), silt, silt loam, sandy loam and,” (iii) “Previously disturbed soils except those which would otherwise be classed as Type C soil.” (iv) “Type A, but is fissured or subject to vibration; or” (v) “Dry rock that is not stable.”
  • 28. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification Type C means (ii)“Cohesive soil with an unconfined compressive strength of 0.5 tsf or less;” (iii) “Granular soils including gravel, sand, and loamy sand; or” (iv) “Submerged soil or soil from which water is freely seeping; or” (v) “Submerged rock that is not stable.” 28
  • 29. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification (2) Basis of classification. The classification of deposits shall be made based on the results of at least one visual and at least one manual analysis. Such analyses shall be conducted by a competent person………… 29
  • 30. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification (d) Acceptable visual and manual tests – (1) Visual tests. “Visual analysis is conducted to determine qualitative information regarding the excavation site in general, the soil adjacent to the excavation, the soil forming the sides of the open excavation, and the soil taken as samples from excavated material.” 30
  • 31. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification •Observe the side of the opened excavation and the surface area adjacent to the excavation. •Crack-like openings such as tension cracks could indicate fissured material. •If chunks of soil spall off a vertical side, the soil could be fissured. •Small spalls are evidence of moving ground and are indications of potentially hazardous situations. 31
  • 32. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification •Observe the area adjacent to the excavation and the excavation itself for evidence of existing utility and other underground structures, and to identify previously disturbed soil. • Observe the opened side of the excavation to identify layered systems. Examine layered systems to identify if the layers slope toward the excavation. Estimate the degree of slope of the layers. 32
  • 33. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification (2) Manual tests. “Manual analysis of soil samples is conducted to determine quantitative as well as qualitative properties of soil and to provide more information in order to classify soil properly.” 33
  • 34. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification (i) Plasticity. “Mold a moist or wet sample of soil into a ball and attempt to roll it into threads as thin as 1/8- inch in diameter. Cohesive material can be successfully rolled into threads without crumbling. For example if at least a two inch length of 1/8-inch thread can be held on one end without tearing, the soil is cohesive.” 34
  • 36. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification (ii) Dry strength •Soil that remains in clumps when excavated is cohesive •Soil that breaks up easily and does not stay in clumps is granular •Cemented soil is highly cohesive, will not break with finger pressure •Cohesive soil high in clay, does not break apart into particles, can be formed
  • 37. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification •Retrieve a large clump of undisturbed spoil •Attempt to penetrate the soil with the tip of the thumb •Type A soil can be penetrated only with great force •Type B will penetrate to the full length of the thumb nail. •Type C will penetrate easily several inches and can be molded by light finger pressure. 37
  • 38. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems Appendix A to Subpart P – Soil Classification Other strength tests. “Estimates of unconfined compressive strength of soils can also be obtained by use of a pocket penetrometer or by using a hand- operated shearvane.” 38
  • 39. • POCKET PENETROMETER. Penetrometers are direct- Pocket reading, spring-operated instruments used to determine penetrometer the unconfined compressive strength of saturated cohesive soils. • Once pushed into the soil, an indicator sleeve displays the reading. • The instrument is calibrated in either tons per square foot (tsf) or kilograms per square centimeter (kPa). • However, Penetrometers have error rates in the range of ± 20-40%.
  • 40. Pocket penetrometer • Push red ring on the barrel all the way toward the handle • Push shaft into the soil up to the red ring • Hold barrel so as to not to interfere with the spring inside the barrel • Read the unconfined compressive strength at bottom of the red slip ring 40
  • 41. Torvane Shear • Select fresh clod or block of undisturbed soil from spoil pile • Cut a smooth surface on the clod • Insert vanes of device into the soil • Retract vanes to show foot imprint • Set indicator at zero • Hold device firmly against soil and twist in clockwise manner until soil fails in The direct instrument reading must be shear multiplied by 2 to provide results in tons per square foot (tsf)
  • 42. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(b)(3) Option (3) – Designs using other tabulated data. (i) “Designs of sloping or benching systems shall be selected from and in accordance with tabulated data, such as tables and charts.” 1926.652(b)(3)(iii) At least one copy of the tabulated data which identifies the registered professional engineer who approved the data……………………. 42
  • 43. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(b)(4) Option (4) – Design by a registered professional engineer. (i) “Sloping and benching systems not utilizing Option (1) or Option (2) or Option (3) under paragraph (b) of this section shall be approved by a registered professional engineer.” 43
  • 44. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(c) Design of support systems, shield systems, and other protective systems. “Designs of support systems shield systems, and other protective systems shall be selected and constructed by the employer or his designee and shall be in accordance with the requirements of paragraph (c)(1); or, in the alternative, paragraph (c)(2); or, in the alternative, paragraph (c) (3); or, in the alternative, paragraph (c)(4) as follows;” 44
  • 45. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(c)(1) Option (1) – Designs using Appendices A, C and D. “Designs for timber shoring in trenches shall be determined in accordance with the conditions and requirements set forth in Appendix A and C to this subpart. Designs for aluminum hydraulic shoring shall be accordance with paragraph (c)(2) of this section, but if manufacturer’s tabulated data cannot be utilized, designs shall be in accordance with Appendix D.” 45
  • 46. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(c)(2) Option 2 – Designs Using Manufacturer’s Tabulated Data. (i) “Design of support systems, shield systems, or other protective systems that are drawn from manufacturer’s tabulated data shall be in accordance with all specifications, recommendations, and limitations issued or made by the manufacturer.” 46
  • 47. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(c)(3) Option (3) – Designs using other tabulated data. (i) “Designs of support systems, shield systems, or other protective systems shall be selected from and be in accordance with tabulated data, such as tables and charts.” 1926.652(c)(3)(iii) At least one copy of the tabulated data, which identifies the registered professional engineer who approved the data…………………….. 47
  • 48. OCCUPATIONAL SAFETY AND HEALTH OSHA ADMINISTRATION Subpart P - Excavations 1926.652 Requirements for protective systems 1926.652(c)(4) Option (4) – Design by a registered professional engineer, (i) “Support systems, shield systems, and other protective systems not utilizing Option 1, Option 2 or Option 3, above, shall be approved by a registered professional engineer.” 48
  • 49. 49
  • 50. 50
  • 51. 51
  • 52. 52
  • 53. 53
  • 54. 54
  • 55. 55
  • 56. 56
  • 57. 57
  • 58. 58
  • 59. 59
  • 60. 60