2. Refurbishment of social housing in
Queens Park, Westminster, London
2-bedroom, 2-storey Victorian terraced
properties built around1865
In a Conservation Area of approximately 400
other similar properties
Client - City West Homes
Contractor - United House
Project Manager – Anna Debenham
3. Project Architects: Energy
Conscious Design (ECD)
Lead Architect - Mark Elton
Associate Director at Energy Conscious Design
On the RIBA ‘sustainable futures’ committee
Special Interest in:
The potential for reducing carbon emissions through retrofit
of the existing stock
Refurbishment schemes that combine super-insulated fabric
improvements with integrated renewables
4. Key Improvements to Property
Internal wall insulated to the exterior solid walls
Roof insulated
Doors and windows improved and replaced
Acoustic insulation fitted to the party walls of bedrooms
Ground floor suspended timber floors removed and
replaced with an Eco-Slab floor system
Mechanical ventilation heat recovery (MVHR) installed
6. Project funding
Retrofit for the Future project is funded by
the Technology Strategy Board (TSB) to
find ‘innovative and replicable measures
to make deep cuts in carbon dioxide
emissions from existing properties in the
social housing sector’
7. Driving Innovation in Retrofit
UK Technology Strategy Board (TSB)
funding was specifically designed to
stimulate the implementation of
innovative cost effective solutions within
the demonstrator houses that can then
be applied across the UK.
8. Evaluation
SAP tests before and after retrofit
Used by BRE as a Pilot for their
‘BREEAM Domestic Refurbishment
standard
Evaluated alongside BRE EcoHomes
XB target criteria and discussed with the
local conservation officer
9. Typical Heat Loss Pattern
Generally agreed that 15% of heat is
lost through the ground floor but it can
be higher in older properties
Heat is lost through draughts in the floor
boards as well as through the fabric
11. ‘THERMAL ENVELOPE’
Insulate the property to keep heat inside
in winter and outside in summer and
maintain a constant internal temperature
Create an airtight seal to eliminate heat
loss from draughts
13. Retrofitting the Ground Floor
Schedule of Works
Disconnect Services
Remove joists and floor timbers
Fill void
Reroute and reinstall services
Lay new floor
14. Challenges of the Site when
Retrofitting the Ground floor
CHALLENGES OF THE BUILDING SITE
Work had to be carried out in a confined space which meant:
Confined space working Health and Safety Act had to be observed so no petrol
driven machinery
Materials and installation had to be handled manually
Labour intensive options not possible
No room for storing materials in building
Delivery of materials had to be tailored to the demands of restricted site access
The original Victorian features had to be protected
The integrity of the Substructure had to be maintained
Services had to be re routed
Void had to be filled and ventilated
The material effects of retrofit on adjoining properties had to be considered
Party Wall Act applied
Security had to be maintained at all times
15. Challenges of the Street When
Retrofitting the Ground floor
New Road and Street Works Act:
Health and Safety conditions Relate to the control of
deliveries
Needed road signs and barriers
Traffic control
Timed deliveries
Make good any damage to road or footpath
Local Council By Laws:
The by laws change depending on the Borough
Not able to start work before 9am
Road had to be cleared and swept by 5pm
No weekend working
Noise and dust restrictions
16. The traditional approach
15 tons of aggregates were
delivered, stored on the road and shoveled
and barrowed in to the house to fill the void
at a rate of a ton a day
Diesel driven whacker plate was used to
create a flat surface putting pressure on
substructure and creating toxic fumes in
confined space violating Health and Safety
laws
17. The Eco-Slab solution
FEATURES OF ECO-SLAB SYSTEM BENEFITS OF ECO-SLAB SYSTEM
‘Just in time engineering’ Minimal materials to store and
organise
Foaming concrete was delivered by a Lorry No complications or concerns with Council
mounted pump, located outside the working Bylaws,
area
Conditions of working in Confined
Foaming concrete used to fill deep void Spaces Health and Safety Act and New
Road and Street Works Act were satisfied
Replaced 15 tons of granular material
Pump set up, filled the void cleaned up
and left within one in an hour with no
manual handling
Minimal Impact on the Street:
Site Activity, Traffic movement, Noise and
Dust all substantially reduced
Minimal supervision to organise delivery
19. Method Statement for Retrofitting
Ground Floor with Eco-Slab
FEATURES OF ECO-SLAB SYSTEM BENEFITS OF ECO-SLAB SYSTEM
‘Just in time engineering’
Eco-Slab was programmed to be delivered Hand off loaded and no storage required
on a light commercial vehicle on day of
installation Unloading and installing completed in one
operation.
Installed by hand by a single semi skilled No machinery required so easily met
operative in one day ‘Confined space working Health and
Safety Act
Eco-Slab was laid directly onto the foam concrete No pressure or penetration of the existing
base walls
Service and ventilation void was provided by Allowed for simple rerouting of services and
100mm legs Under floor ventilation
75mm thick fibre reinforced wearing slab was Reinforcement was in the concrete so delivery and
poured to finished floor level fixing of reinforcement was not needed
All Local Council By Laws and New Road and
Street Works Act easily met as
noise, dust, site activity etc. reduced
20. Insulation Values & Carbon
Reductions
Eco-Slab is made from Carbon Enriched Jablite EPS which has an
A+ rating in the BRE Green Guide
The unique lap & ledge system ensured a continuous 100mm of
insulation throughout the ground floor
200mm Edge beam system gave a U value of zero at the wall/ floor
interface
The Eco-Slab floor provided the base for the thermal envelope
In conjunction with other technologies the energy use for the building was
reduced from 16000 kilo watts per year to 2000 kilo watts without
renewables
22. Conclusions
Traditional methods of construction cannot meet the demands and
complexities of professional retrofitting on the scale required
We need to employ new ways of working and new materials
Modern methods of construction and in particular ‘just in time engineering
can assist in meeting the challenges
The Eco-Slab system offers a fast and cost effective solution for
retrofitting the ground floor when working in a confined urban environment
It is particularly cost effective when retrofitting several houses in one area
and the costs of hiring the pump can be shared among several properties
The Eco-Slab retrofit system using foaming concrete and the Eco-Slab
base significantly reduced the operational and embodied carbon
compared to traditional retrofit methods and combined successfully with
other technologies to create a thermal envelope
www.eco-slab.com
Editor's Notes
Picture of refurbished house in Lothrop Road, Queens Park, Westminster
SAP reports are available on request
Creating a thermal envelope keeps a steady ambient temperature in the house except in the most extreme conditions and A mechanical ventilation heat recovery (MVHR) installed to ensure that there is a regular air change and fresh air brought into the house is warmed by the air leaving
The blue line along the floor wall interface shows where the cold is penetrating and cooling the house.
Typically in a Victorian House you will find a void or crawl space when you take up the floor boards, full of builders rubble and anything that has managed to slip down between the floor boards. In these houses the architect wanted to create a platform for the services to reroute the tangle of pipes and wires and then put the floor on top of the foaming concrete. The void also allowed the area beneath the slab to be ventilated.
As much a challenge as finding ways to reduced carbon was the logistics of working in such a constricted space in a busy terraced street
This is the solution that Eco-Slab provided to overcome the problems of the traditional approachand which was then used in the other 6 properties being retrofitted
The Eco-Slab is laid on top of the foaming concrete What is not shown here is a 200mm beam which sits is placed around the edge of the raft and gives equivalent insulation of 200mm to wall edge where most heat is lost.