BiLFINGER Approach to BIM
Cyber Physical Systems
Building Information Modelling to Management Information System
Document ...
▪ What is BIM?
▪ How can we react?
▪ How can we achieve BIM?
▪ What is our return on BIM?
▪ What’s the cost to implement B...
▪ Targets – running cost, capital cost, environment and functionality
▪ Comparison of predicted performance against target...
BIM is a verb or an adjective phrase to describe tools,
processes and technologies that are facilitated by
digital, machin...
Building Information Modeling (BIM)
BIM provides insight for
creating and managing
projects faster, more
economically, and...
MIS
BIM
CAFM
BMS
PIM
AIM
EMM
RAM
HS&E
HFMArchitectural
StructuralMechanical Product
Surveyors Financial
MIS
BIM
CAFM
BMS
PIM
AIM
EMM
RAM
HS&E
HFMArchitectural
Structural Mechanical Product
Surveyors Financial
MIS
CAFM
BMS
RAM
HS&E
HFM
Product
BIM
PIM
AIM
Architectural
Structural
Surveyors
EMM
Mechanical
Financial
Building Modeling
Shared in a collaborative
team working environment
Improve Project Delivery:-
▪ Time
▪ Cost
▪ Quality
MA...
▪ Building Information Model which
encompasses:
▪ Building Geometry
▪ Spatial Relationships
▪ Geographic Information
▪ Qua...
3D Model 3D Informed Model 3D Intelligent
Model
4D
Automated Robotic
and Planned Model
utilisation.
5D Cost element
for th...
Today
Site evaluation Analysis Documentation Work Orders Cost evaluation
Tomorrow
13
Site evaluation Analysis Documentation Work Orders Cost evaluation
Access to Areas Of Development
Construction
• The Build
• Error Free
• Involved Client, contractors,
designers
Retrofit
• ...
Implementation Of BIM
Software
Construction
• The Build
• Error Free
• Involved Client, contractors,
designers
• Developme...
The Goal
▪ 3D Layout
▪ Open Interactive Viewing
▪ Open to imports and Exports
▪ Accessible Information
▪ Creating Links to...
Starting Point
▪ BIM is not software it is the
collaboration of software expressed as
a Model
Navis Works BIM Viewer and Data
Extraction
http://www.youtube.com/watch?v=di_DBGqymxg)
www.autodesk.com/products/autodesk-...
Building Design Suite
www.youtube.com/watch?v=U5jc5F8gTh0&list=TLM3j1CE1CwwBrb_1Gap6bNO6-36v1TYbf
http://www.autodesk.com/...
1. Asset Number
• FM Maintainable Asset
Y/N
• Decommission Date
(Phasing?)
• Bar Code
• Asset Type / Group
• Asset Descrip...
Information Path for PIM Model
Interaction
Single
Completed Model
CDE Common
Data
Environment
• SharePoint (cloud
based Sy...
Model Setup for FM
22
• Placements
• Spaces
• Holistic Reports
• 3D Representations
PIM
• CAFM
• BMS
• Device Smart Wirele...
Information Path for PIM Model
Interaction
PIM
FM BIM division
Bilfinger Maintenance
Departments (The Team)
•Soft Faciliti...
Information Path for PIM Model
Interaction
AIM
CAFM Division
Smart Device
Interface
• Client interface
• Technical Interfa...
Bilfinger HSG FM CAFM-system
MS Dynamics NAV – standards
Neu-Isenburg, May 2014
Content
Overview MS Dynamics NAV – WorldFM
Workflow maintenance
Reporting
Workflow work order management
Implementation of...
▪ Overview
▪ Microsoft Dynamics NAV 6.02 (Microsoft SQL Server 2008 R2)
▪ In use since approx. 3 years
▪ System is used in...
Bilfinger IT system landscape
Seite 28optional
Main application
subsystems / interfaces
Customer systems
Key:
Facility Ser...
Use of Bilfinger IT systems in a customer
project
Customer Bilfinger HSG Facility Management GmbH
WorldFM
Reporting
Dashbo...
With our process oriented CAFM
we support service processes – additional
systems can be connected
Overview CAFM system „Wo...
Integrated Subsystems / Tools
Reporting Services
MS Office
MS Dynamics
NAV
Facility Services Portal
Implementation of World FM
The basis for the implementation
 The designation of a contact person – Key User
(good knowled...
BIM CAFM BMS H&S SFG20
Mobile
Tech
Customer
Portal(s)
Mobile
Tech
Client reporting
& Analysis
CDE (Collaborated Design Env...
Model Verification Workload
Client/
Employer
Approval
PIM & AIM
No
Archived
Design
Team
Approval
Published to Client/
Empl...
Seite 35
Plain Language
Questions
(PLQ)
Employer’s
Information
Request
EIR
Organizational
Information
Requirements
Asset
I...
Implementation of World FM
Phases for implementation
Setup of Citrix servers farm for different business
units
Setup of WF...
Preventive planned maintenance in MS Dynamics NAV
Building- &
asset structure
with activities
and schedules
Maintenance
pl...
In MS Dynamics NAV recurring activities (for example
planned maintenance according to VDMA) can be
planned an generated as...
Work order mangement is realized
in a continous workflow
 Work order is technical completed
 Work order can be charges a...
Development of a meaningful, agreed reporting
using reporting services
Examples
 Summaries
 Work orders reports regardin...
Access opportunities for WorldFM
Seite 41FM-IT | Team Impl. CAFM | 27.05.2013
 URL: https://fs-cloud.bilfinger.com/
 Req...
Access opportunities for WorldFM
Seite 42FM-IT | Team Impl. CAFM | 27.05.2013
Access via Citrix Connection Center
 Requir...
Bilfinger HSG Facility Management GmbH Phone: +49 6102 45 3526
Daniel Mihaljevic Mobil: +49 173 247 8615
IT project manage...
Thank You
Próximos SlideShares
Carregando em…5
×

Bim cafm presentation 23 june2014

CAFM

  • Seja o primeiro a comentar

Bim cafm presentation 23 june2014

  1. 1. BiLFINGER Approach to BIM Cyber Physical Systems Building Information Modelling to Management Information System Document Intended to describe the approach to BIFM Building information Facility Management (iBIM) intelligent building Models
  2. 2. ▪ What is BIM? ▪ How can we react? ▪ How can we achieve BIM? ▪ What is our return on BIM? ▪ What’s the cost to implement BIM? BIM
  3. 3. ▪ Targets – running cost, capital cost, environment and functionality ▪ Comparison of predicted performance against targets ▪ Simple operating instructions ▪ Early warnings of problems ▪ Metered data on the performance ▪ Ready access to all digital data about our asset ▪ Cost effective transfer of data from construction to operation ▪ Service provider having all required operational data ▪ Actual measured performance of our asset ▪ Fine tuning the actual performance ▪ Recorded performance ▪ Feedback to the design and construction team www.bimtaskgroup.org Newsletter, 20th edition | Week ending 2nd June 2013 Service level required by the clients
  4. 4. BIM is a verb or an adjective phrase to describe tools, processes and technologies that are facilitated by digital, machine–readable documentation about a building or piece of Infrastructure, its performance, its planning, its construction, and its operation. The Definition Of BIM Building Information Modeling describes an activity, not an object. “Rafael Sacks”
  5. 5. Building Information Modeling (BIM) BIM provides insight for creating and managing projects faster, more economically, and with less environmental impact. MANAGE BUILD DESIGN PLAN BIM is an intelligent model-based process
  6. 6. MIS BIM CAFM BMS PIM AIM EMM RAM HS&E HFMArchitectural StructuralMechanical Product Surveyors Financial
  7. 7. MIS BIM CAFM BMS PIM AIM EMM RAM HS&E HFMArchitectural Structural Mechanical Product Surveyors Financial
  8. 8. MIS CAFM BMS RAM HS&E HFM Product BIM PIM AIM Architectural Structural Surveyors EMM Mechanical Financial
  9. 9. Building Modeling Shared in a collaborative team working environment Improve Project Delivery:- ▪ Time ▪ Cost ▪ Quality MANAGE BUILD DESIGN PLAN The key word is Information
  10. 10. ▪ Building Information Model which encompasses: ▪ Building Geometry ▪ Spatial Relationships ▪ Geographic Information ▪ Quantities of Building Components ▪ Properties of Building Components Building Information Model ▪ Computer Assisted Facility Management (Model) which Utilizes: ▪ Building Geometry Services ▪ Spatial Relationships with Maintenance intent ▪ Geographic Information to asset locations ▪ Quantities of Building Components ▪ Properties of Building Components
  11. 11. 3D Model 3D Informed Model 3D Intelligent Model 4D Automated Robotic and Planned Model utilisation. 5D Cost element for the Model will have to be Laid out and derived to suit our off Take needs 6D Sustainability Analysis Pre construction and after construction. 7D Facility Management. Developed structure of information illustrating maintenance regimes done through a robotic analysis and CAFM Tie in. Navis works _ Collaboration tool for 4D, 5D, 6D Revit _ 3D Visualisation tool 3D, 4D, 5D CAFM _ FM Management tool for Utilising 4D, 5D, 6D to Produce a 7D Model 3D Model containing relevant information can be tracked by a unique tag. This unique tag must follow through to each section of the
  12. 12. Today Site evaluation Analysis Documentation Work Orders Cost evaluation
  13. 13. Tomorrow 13 Site evaluation Analysis Documentation Work Orders Cost evaluation
  14. 14. Access to Areas Of Development Construction • The Build • Error Free • Involved Client, contractors, designers Retrofit • Development • Structure • Improvements • Deliverables Reporting • Access to changes • Attached to design • Simulated assistance Auditing • Predetermined Costs • Itemised Lists • Product Codes • Creative interaction between all systems Surveying • Itemised List • Building Characteristics • Systematic Approach • Tracked Progress Development • New Ideas • Rapid Planning • Open to innervation • Easy to Modify • Evaluate Profile changes Facility Management
  15. 15. Implementation Of BIM Software Construction • The Build • Error Free • Involved Client, contractors, designers • Development • Structure • Improvements • Deliverables Reporting • Access to changes • Attached to design • Simulated assistance • Auditing • Predetermined Costs • Itemised Lists • Creative interaction between all systems Surveying • Itemised List • Building Characteristics • Systematic Approach • Development • New Ideas • Rapid Planning • Open to innervation
  16. 16. The Goal ▪ 3D Layout ▪ Open Interactive Viewing ▪ Open to imports and Exports ▪ Accessible Information ▪ Creating Links to All sides of the organisation ▪ Reduce Loss of Information ▪ Predict the outcomes to Project solution ▪ Move with the Times
  17. 17. Starting Point ▪ BIM is not software it is the collaboration of software expressed as a Model
  18. 18. Navis Works BIM Viewer and Data Extraction http://www.youtube.com/watch?v=di_DBGqymxg) www.autodesk.com/products/autodesk-vault-family/overview
  19. 19. Building Design Suite www.youtube.com/watch?v=U5jc5F8gTh0&list=TLM3j1CE1CwwBrb_1Gap6bNO6-36v1TYbf http://www.autodesk.com/suites/building-design-suite/overview
  20. 20. 1. Asset Number • FM Maintainable Asset Y/N • Decommission Date (Phasing?) • Bar Code • Asset Type / Group • Asset Description • Manufacturer • Supplier • Cost • Life Cycle Period 2. Statutory Maintenance frequencies • Maintenance Regime / standard eg SFG20 code • SLA (Weighting of Space) • Interface Flag (Trigger / validation) 3. Space Location • Department • Volume • Floor Area New or Decanted FM Maintainable Asset Y/N Space Location (Room / and location in room) Department ie Science / Humanities Install Date Commissioning Date Warranty expiry date Decommission Date (Phasing?) Asset Number Bar Code Asset Type / Group Asset Description Fixed Asset / Portable Serial Number Energy Load (Asset Specific) Manufacturer Supplier Cost Life Cycle Period Statutory Maintenance frequencies Maintenance Regime / standard eg SFG20 code SLA (Weighting of Space) BMS reference Condition (Dropdown)? Interface Flag (Trigger / validation) Health & Safety Attachments O&M 1. Asset Number • Bar Code • Asset Type / Group • Asset Description • Fixed Asset / Portable • Serial Number • Energy Load (Asset Specific) • Manufacturer • Supplier • Cost • Life Cycle Period • Condition (Dropdown)? 2. New or Decanted • Install Date • Commissioning Date • Warranty expiry date • Decommission Date (Phasing?) 3. Space Location (Room / and loc. in room) • Department • Volume • Floor Area 4. BMS reference 5. Interface Flag (Trigger / validation) 6. Health & Safety Attachments 7. O&M PIM FM Key triggers and requirements for Asset Model Asset Number (Direct Link to Maintenance History in CAFM) AIM/CAFM Facility Management
  21. 21. Information Path for PIM Model Interaction Single Completed Model CDE Common Data Environment • SharePoint (cloud based System) or • Privet Could Based Solution PIM (Project Information Model) • Original Developed model containing Information relative to the development of the Project AIM (Asset Information Model) • Utilised to extract and interface asset and facilities management systems
  22. 22. Model Setup for FM 22 • Placements • Spaces • Holistic Reports • 3D Representations PIM • CAFM • BMS • Device Smart Wireless AIM • Common Data Environment • Cyber Physical System • Itobo CED
  23. 23. Information Path for PIM Model Interaction PIM FM BIM division Bilfinger Maintenance Departments (The Team) •Soft Facilities Service Team •Hard Facilities Service Team
  24. 24. Information Path for PIM Model Interaction AIM CAFM Division Smart Device Interface • Client interface • Technical Interface • Management Interface Scholars Interface • Development structure • Engineering Interface • SFG 20 Validations • SLQ Required reports • PayMech • Departmental financial analysis Preventative Maintenance Reports • Operational Data for Site Management Maintenance Team Reactive Data Additional Required Interfaces
  25. 25. Bilfinger HSG FM CAFM-system MS Dynamics NAV – standards Neu-Isenburg, May 2014
  26. 26. Content Overview MS Dynamics NAV – WorldFM Workflow maintenance Reporting Workflow work order management Implementation of World FM Though the BIM Portal Access opportunities for WorldFM
  27. 27. ▪ Overview ▪ Microsoft Dynamics NAV 6.02 (Microsoft SQL Server 2008 R2) ▪ In use since approx. 3 years ▪ System is used in other European countries ▪ Central system – access via Citrix from every location ▪ Redundant data centers – high availability (Data centers are certified in accordance with the ISO/IEC 27001:2008 ▪ Selected functions ▪ Master data management ▪ Work order management ▪ Helpdesk tickets ▪ Preventive planned maintenance ▪ Activity planning ▪ Purchase orders & Sales invoices ▪ Reporting & Documentation ▪ Performance controlling With CAFM „Microsoft Dynamics NAV“ can be implemented integrated and transparent
  28. 28. Bilfinger IT system landscape Seite 28optional Main application subsystems / interfaces Customer systems Key: Facility Services Portal MS Reporting Services MS Office (Excel, Word) MS Dynamics NAV 2009 R2 – WorldFM Customer system BIM
  29. 29. Use of Bilfinger IT systems in a customer project Customer Bilfinger HSG Facility Management GmbH WorldFM Reporting Dashboard* Helpdesk (fault messages) Mobile solution* Facility Services Portal * currently still in the development phase Data transmission in real time Messages and orders in uniform web surface Informations of the order and message status in real time Provision of the requested reports Integration of a Dashboards • Mobile order acceptance & processing • Mobile feedback • Mobile signature AIM CDE Client PIM Client and Model interaction with CAFM – Asset Management
  30. 30. With our process oriented CAFM we support service processes – additional systems can be connected Overview CAFM system „World FM“ as a processing tool for fault reports MS Dynamics NAV MS Dynamics NAV CAFM Work order management as a central service process Customer orders Fault reports Maintenance plan Master data  Buildlings  assets  Planned activities  Suppliers  Customer  Personnel Onlineportal (optional)  Internet based access  Logging of fault reports Onlineportal optional
  31. 31. Integrated Subsystems / Tools Reporting Services MS Office MS Dynamics NAV Facility Services Portal
  32. 32. Implementation of World FM The basis for the implementation  The designation of a contact person – Key User (good knowledge of English are required)  Include assistance by translation of WorldFM  Organization of the IT infrastructure  Purchasing of IT hardware  Support & training of new WorldFM users  After the implementation of WorldFM:  1st level support through the KeyUser  2nd level support in cooperation with FM-IT Germany
  33. 33. BIM CAFM BMS H&S SFG20 Mobile Tech Customer Portal(s) Mobile Tech Client reporting & Analysis CDE (Collaborated Design Environment) GUI
  34. 34. Model Verification Workload Client/ Employer Approval PIM & AIM No Archived Design Team Approval Published to Client/ Employer No Yes Yes Yes WIP SHARED PUBLISHED by Team for Team Concept 1 Concept 2 Concept 3 Documentation & Calculations High Level Approval System
  35. 35. Seite 35 Plain Language Questions (PLQ) Employer’s Information Request EIR Organizational Information Requirements Asset Information Requirements (AIR) Asset Information Model (AIM) Project Information Model (PIM) Generates SpecifiesSpecifies Informs Contributes to Operational Phase Conceptual Phase Construction Phase Help Desk Technical Teams Management Accounts WO
  36. 36. Implementation of World FM Phases for implementation Setup of Citrix servers farm for different business units Setup of WFM database for different business units PIM and AIM data maintenance Import of AIM infoamtion and Data Sheets Reporting to CDE for CIR “Clients information Request Support / Training Project documentation Phase 1 Phase 3 Phase 4 Implementation of the language package The conceptual and substantive clarification Acquisition and configuration of the required infrastructure (HW/SW) Harmonized processes in co-operation with HZI Phase 2 Only for the first implementation project in the different business units Standard implementation process in the different projects
  37. 37. Preventive planned maintenance in MS Dynamics NAV Building- & asset structure with activities and schedules Maintenance plans and work orders Service- documentation on the work order Reporting In MS Dynamics NAV recurring activities (for example planned maintenance according to VDMA) can be planned an generated as work orders
  38. 38. In MS Dynamics NAV recurring activities (for example planned maintenance according to VDMA) can be planned an generated as work orders Preventive planned maintenance in MS Dynamics NAV Activity Position  Scheduling  cycle  Plans  Services  Materials Maintenance work orders WO WO WO Scheduling (weeks) 12 24 36       Plans Services Materials Plans Services Materials Building and asset structures are provided with activities for the planned maintenance. From this activities, maintenance calendars, and recurring work orders can be created. The service will be documented gapless.
  39. 39. Work order mangement is realized in a continous workflow  Work order is technical completed  Work order can be charges as a single or collective invoice  Possible purchase orders for external services  Service feedback  Posting & charging of used materials  Process starts with work order  Work orders can result from  Customer order  Maintenance  Faults Simplified work order workflow 1 32
  40. 40. Development of a meaningful, agreed reporting using reporting services Examples  Summaries  Work orders reports regarding order type and status  Helpdesk statistics  Maintenance calendars  Actual / target performance  Maintenance performance  Site reports (monthly, quarterly, annual)  Etc. The Definition of reporting contents, formats and cycles takes place during the transition phase with the customer. Reporting examples
  41. 41. Access opportunities for WorldFM Seite 41FM-IT | Team Impl. CAFM | 27.05.2013  URL: https://fs-cloud.bilfinger.com/  Requirements:  Bilfinger IT account  Approved WorldFM account  Current installation of the Citrix Connection Center
  42. 42. Access opportunities for WorldFM Seite 42FM-IT | Team Impl. CAFM | 27.05.2013 Access via Citrix Connection Center  Requirements:  Bilfinger IT account  Approved WorldFM account  Access to the Bilfinger network environment resp. connection via VPN  Current installation of the Citrix Connection Center
  43. 43. Bilfinger HSG Facility Management GmbH Phone: +49 6102 45 3526 Daniel Mihaljevic Mobil: +49 173 247 8615 IT project manager E-Mail: daniel.mihaljevic@bilfinger.com An der Gehespitz 50 Fax: +49 6102 45 3449 D-63263 Neu-Isenburg
  44. 44. Thank You

×