O slideshow foi denunciado.
Utilizamos seu perfil e dados de atividades no LinkedIn para personalizar e exibir anúncios mais relevantes. Altere suas preferências de anúncios quando desejar.

Easy steps to network construction and critical path determination

4.146 visualizações

Publicada em

Project Management, Easy steps to network construction and critical path determination

Publicada em: Engenharia
  • Seja o primeiro a comentar

Easy steps to network construction and critical path determination

  1. 1. Easy Steps to Network Construction and Critical Path Determination Project Management Dr. Mahmoud Abbas Mahmoud Asst. Prof. 2016
  2. 2. Easy Steps to Network Construction and Critical Path Determination Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG Example: For the activities given in the table: i) Draw the (AOA) network diagram. ii) Find the critical activities. iii) Find the critical path (CP). iv) Find project completion time. We will illustrate these steps with the following Example. Dr. Mahmoud Abbas Mahmoud
  3. 3. Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG
  4. 4. Note: Practically, nodes numbering can be start by (0) or (1). Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 1
  5. 5. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG
  6. 6. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2
  7. 7. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B
  8. 8. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3
  9. 9. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C
  10. 10. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D
  11. 11. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4
  12. 12. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E
  13. 13. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5
  14. 14. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F
  15. 15. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6
  16. 16. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G
  17. 17. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G ???????But (G) depend on both (D) and (E)
  18. 18. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G Use Dummy !
  19. 19. A 1 Dr. Mahmoud Abbas Mahmoud Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 2 B 3 C D 4 E 5 F 6 G Dummy
  20. 20. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0
  21. 21. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 (AOA) Network Drawing is Completed
  22. 22. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Critical Path Calculations
  23. 23. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass:
  24. 24. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass: Calculating the Earliest Start Time (ES):
  25. 25. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 Forward Pass: Calculating the Earliest Start Time (ES): Earliest Start Time (ES)j=Max [ (ES)i + Dij ]
  26. 26. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 Earliest Start Time (ES) for Start Event = (0) NOTE: (ES) for any Start Event = (0)
  27. 27. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0
  28. 28. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 10[0+10]= 10 0
  29. 29. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 Max [(0+7) , (10+5)] = Max [7,15]= 15
  30. 30. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 [10+ 6]= 16
  31. 31. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 Max [(15+9) , (16+0)] = Max [24,16]= 24
  32. 32. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Max [(16+8) , (24+12)] = Max [24,36]= 36
  33. 33. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Therefore, Project completion time is: 36 weeks
  34. 34. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 Backward Pass:
  35. 35. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36
  36. 36. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36
  37. 37. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC):
  38. 38. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 36 36 Calculating the Latest Completion Time (LC): Latest Completion Time (LC)i=Min [ (LC)j - Dij ]
  39. 39. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 16 24 24 36 36 36 – 12 = 24
  40. 40. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 24 16 24 24 36 36 Min [(36-8),(24-0)= Min[28,24] = 24
  41. 41. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 15 15 24 16 24 24 36 36 24 – 9 = 15
  42. 42. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 10 10 15 15 24 16 24 24 36 36 Min [(24-6),(15-5)= Min[18,10] = 10
  43. 43. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 Duration (week) Preceding Activity Activity 10-A 7-B 5AC 6AD 9B, CE 8DF 12D, EG 0 0 0 10 10 15 15 24 16 24 24 36 36 Min [(15-7),(10-10)= Min[8, 0] = 0
  44. 44. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  45. 45. A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 Dr. Mahmoud Abbas Mahmoud G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 How to find the Critical Activities and the Critical Path ???
  46. 46. Dr. Mahmoud Abbas Mahmoud Remember that only a critical activity can have a Zero Total Float (TF)
  47. 47. Dr. Mahmoud Abbas Mahmoud Therefore, we will calculate the Total Floats for all activities and each activity has a ZERO Total Float (TF) will be a critical activity.
  48. 48. Total Float (TF) calculations Dr. Mahmoud Abbas Mahmoud TFij = (LC)j – (ES)i – Dij A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36
  49. 49. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity A B C D E F G Dummy
  50. 50. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy For activity A (1, 2) TF = 10 – 0 – 10 = 0*
  51. 51. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A B C D E F G Dummy
  52. 52. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy For activity B (1, 3) TF = 15 – 0 – 7 = 8
  53. 53. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B C D E F G Dummy
  54. 54. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy For activity C (2, 3) TF = 15 – 10 – 5 = 0*
  55. 55. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C D E F G Dummy
  56. 56. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy For activity D (3, 4) TF = 24 – 10 – 6 = 8
  57. 57. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D E F G Dummy
  58. 58. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy For activity E (3, 5) TF = 24 – 15 – 9 = 0*
  59. 59. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E F G Dummy
  60. 60. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy For activity F (4, 6) TF = 36 – 16 – 8 = 12
  61. 61. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F G Dummy
  62. 62. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy For activity G (5, 6) TF = 36 – 24 – 12 = 0*
  63. 63. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G Dummy
  64. 64. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy For Dummy activity (4, 5) TF = 24 – 16 – 0 = 8
  65. 65. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy
  66. 66. Dr. Mahmoud Abbas Mahmoud A= 10 B= 7 1 2 3 C= 5 D= 6 E= 9 4 5 6Dummy F= 8 G= 12 0 0 0 10 10 15 15 24 16 24 24 36 36 CriticalTotal FloatActivity Yes0A No8B Yes0C No8D Yes0E No12F Yes0G No8Dummy The Critical Activities are: (A, C, E, G) Critical Path is: (A C E G) Project completion time is: 36 weeks
  67. 67. Dr. Mahmoud Al-Naimi

×