Project Management
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
Dr. Mahmoud Ab...
(AOA) and (AON) Network Construction and
Critical Path Calculations
(Using Four Methods)
EXAMPLE:
Construct the (AOA) and ...
Solution (1):
(AOA) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Y...
Solution (2):
(AOA) network (calculations in node)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A...
Solution (3):
(AOA) network (calculations on arrow)
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
...
Solution (4):
(AON) network
Activity
Path
(i - j)
Duration
(days)
ES EF LS LF
TF
(Slack)
Critical
A (1 – 2) 2 0 2 0 2 0* Y...
Próximos SlideShares
Carregando em…5
×

(AOA) and (AON) Network construction and critical path calculations (using four methods)

5.042 visualizações

Publicada em

Project Management: Network construction and critical path calculations (using four methods)

Publicada em: Engenharia

(AOA) and (AON) Network construction and critical path calculations (using four methods)

  1. 1. Project Management (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) Dr. Mahmoud Abbas Mahmoud Assistant Professor
  2. 2. (AOA) and (AON) Network Construction and Critical Path Calculations (Using Four Methods) EXAMPLE: Construct the (AOA) and (AON) networks for the project whose activities, their durations and their precedence relationships are as given in the table, also find: i) [ES, EF, LS, LF, Slack] for all activities. ii) Critical path(s). iii) Project completion time. Activity Predecessor Activity Duration (days) A - 2 B A 8 C A 10 D B 6 E B 3 F C 3 G C 7 H D, F 5 I E 2 J G 8
  3. 3. Solution (1): (AOA) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  4. 4. Solution (2): (AOA) network (calculations in node) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Note: (LC = LF) & (EC = EF) Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  5. 5. Solution (3): (AOA) network (calculations on arrow) Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days
  6. 6. Solution (4): (AON) network Activity Path (i - j) Duration (days) ES EF LS LF TF (Slack) Critical A (1 – 2) 2 0 2 0 2 0* Yes B (2 – 3) 8 2 10 8 16 6 No C (2 – 4) 10 2 12 2 12 0* Yes D (3 – 5) 6 10 16 16 22 6 No E (3 – 6) 3 10 13 22 25 12 No F (4 – 5) 3 12 15 19 22 7 No G (4 – 7) 7 12 19 12 19 0* Yes H (5 – 8) 5 16 21 22 27 6 No I (6 – 8) 2 13 15 25 27 12 No J (7 – 8) 8 19 27 19 27 0* Yes Therefore: Critical path: A --- C --- G --- J Project completion time = 27 days

×