Blue mountains cascade dam- Horizontal direction drill

Priority Sewerage Program

Upper Blue Mountains Sewerage Scheme

Horizontal Directional Drilling
Author: Dean Garratt
GOALS & BACKGROUND
PSP Alliance
Environmentally sensitive
engineering
• PSP alliance aims to improve public health and
protect the environment especially local
waterways and catchments
• Upper Blue Mountains project introduces
reticulated sewerage to replace poorly
performing septic tanks
Major Sydney Water catchment area
World Heritage Area (We are boring under Cascade Creek pictured in the
background)
PROJECT SCOPE & ISSUES
• Connect the new sewerage network to the Winmalee sewerage treatment plant.
• Use Horizontal Directional Drilling to bore from Meadow Bath to the existing North Katoomba sewer
through Sandstone, Claystone and minor seams of Ironstone.
• Perform geological survey and detailed design analysis to minimise risk and maximise design life
• Use trenchless technology (HDD) to minimise the impact on the environment.
– This is particularly important due to the World heritage status and tourism of the region.
– HDD allows precise control of the grade so pumping stations
aren’t needed, eliminating capital, running and maintenance costs.
• Install 2 pipelines: 2366m @ DN450mm and 2358m @ DN225mm.
• The smaller pipe will be used as backup in case of blockage or overload.
• Use Heavy Duty Polyethylene (HDPE) pipe to maximise design life
and ease of installation.
HOME
Technical Specification
CostsPlans Productivity
End Show
The HDD Process
Achievements
HOME PAGE
Site Layout
Pipe Welding
Pipe Installation
Schedule
HomeThe geographical layout showing location of
pipes and Cascade Dam
Section DN225 Section DN450
PLANS – Plan View
Home
Home
PLANS – DN225 Section
Plan View Section DN450
Home
PLANS – DN450 Section
Plan View Section DN225
Home
• The HDD for the DN255 was carried out first
• The rig was then moved to the DN450 location & 225mm
pilot hole was drilled
• The hole was then forward reamed to 450mm diameter
• After drilling was complete, the pipes were installed into the bores
• The pipes were welded in parallel with the drilling so that they
could be installed into their bores as soon as drilling was complete
Summary Schedule
Site Layout
Home
• A detailed geotechnical survey helps make the right
choice of drilling rig, fluid composition, tools and
techniques
• Drill path is engineered using computer-aided design
and sophisticated mechanical and stress engineering
software
• With the rig accurately aligned to the drill path, drilling
fluid (bentonite & water) is pumped down the drill pipes.
This provides high pressure fluid to jet nozzles for drilling
the softer materials, or power to a down hole motor
which drives a roller-cone bit in rock.
• The fluid provides drilling power, consolidates the walls
of the drillhole, acts as a lubricant and carries spoil out
of the hole
• As the cuttings laden fluid travels back up the drillhole, it
is captured, the cuttings removed and recycled, so the
fluid can be pumped back around the drilling loop
• The downhole drilling assembly is guided by electronic
steering instrumentation that transmits data in real time
to a surface-based computer that allows the driller to
precisely locate the drilling assembly and guide it along
the pre-determined drill path
• The drilling assembly is replaced with a reamer which is
pulled back or pushed forward to enlarge the pilot hole
to the size needed for the product pipe
HDD Process Home
Technical
Spec
The American Augers DD-1100: DD1100 Spec. link
Home
Engine Type:
2 x Caterpillar 3412E DITTA diesel engines.
Rating:
2 x 760 HP @ 2100 RPM = 1520 total HP
Pumps:
Each engine drives 4 hydrostatic drive pumps – 2 for rotary
torque and 2 for thrust/pullback
Rotary System:
Four pinion drives
100,000 ft-lbs rotary torque @ 0-40 RPM (at max torque)
44,000 ft-lbs rotary torque @ 0-90 RPM (at max speed)
Carriage System:
Six pinion drive, each with a planetary gearbox and two
speed radial motor. Two 3” mud hoses in a hose carrier.
Carriage Thrust/Pullback:
500 tonnes @ 6.9m/min
372 tonnes @ 9.2m/min
241 tonnes @ 13.8m/min
114 tonnes @ 32.5 m/min
Operators Control Console Description:
Electric over hydraulic controls, pulse with modulation,
Diagnostic warning lights for all filters & fluid levels. Full
digital and analogue instrumentation.
Other Features:
Wire-line steering system, 3785 LPM flow capacity, Wiggle
steer
Home
• The pipeline was joined using industry
standard butt fusion welding
• Due to access restrictions, the pipeline was
welded & debeaded in 800m lengths. Each
length of pipe was 12m.
• The welding machine used was a McElroy
TracStar No. 618 Fusion welder
• Welding the DN225 pipe achieved
approximately 5-7 joints/day
• Welding the DN450 pipe achieved
approximately 3-5 joints /day
• To see an animation of the butt fusion welding
process, click on the link below
Fusion welding animation
HDPE Pipe welding
Home
•The pilot hole was drilled short of tunnel. The bentonite in the borehole
was cleaned via flocculation. Once the drilling mud is cleaned the last
section of the borehole will be drilled with clean water and punch into the
tunnel
•The pipes were pushed/floated in from entry side (rig site, Medlow Bath)
towards the exit side (Katoomba)
•A 30 tonne excavator was used straddle the entry point and feed the
pipe directly into the hole with additional excavators used to help manage
the bends in the pipe string
•The pipe was fed into the bore open ended to allow fluid remaining in the
belly of the bore to flow into the pipe thus insuring the pipe is not too
buoyant which would jam the pipe against the top of the hole
• The designers generated 31 variations of what installation loads may be
seen when installing the pipe, they took into account the following criteria;
-Mud Weight
-Viscosity
-Helical Buckling
-Sinusoidal Buckling
-Asbuilt profile of the bore.
-Properties of the HDPE pipe
HDPE Pipe Installation
Production & Productivity - Overview
Home
• Productivity was increased by using
parallel processes
• Drilling operations were carried out 24/7 to
decrease the overall duration thus
minimising overhead costs
• On average approximately 10-15 men
were used during the peak day operating
period & 6-8 men used during the night shift
to save on cost
• The plant and equipment chosen was
advanced enough to complete the work with
a high factor of safety.
DN225 Pilot hole for DN450 pipe
DN225 Drilling
Production & Productivity – DN225 Drilling
Average production = 2.2 manhours / metre
Home
Overview DN225 Pilot hole for DN450 pipe
Average productivity = 76 metres / day
Production & Productivity – DN225 Pilot hole Drilling for DN450 pipe
Overview DN225 Drilling
Average production = 2.0 manhours / metre
Home
Average productivity = 126 metres / day
• Total Cost incl indirects = $14.4 million
• Total Cost directs only = $10.3 million
• Total length of 2 bores = 4724m
• Rate incl indirects = $3050/metre
• Rate directs only = $2180/metre
Cost
Home
Technical feats and 

achievements
At 2.4km length, this is the world's
longest HDD sewer installation,
overtaking the record set by AJ Lucas
with the Wollongong sewer pipeline
installed in 2004.
Home
End of presentation
1 de 19

Recomendados

InterMoor Installation of Subsea Pile and Manifold at AC24 por
InterMoor Installation of Subsea Pile and Manifold at AC24InterMoor Installation of Subsea Pile and Manifold at AC24
InterMoor Installation of Subsea Pile and Manifold at AC24jonathonmiller2008
2K visualizações24 slides
Mining Operations Optimize Dewatering Processes por
Mining Operations Optimize Dewatering ProcessesMining Operations Optimize Dewatering Processes
Mining Operations Optimize Dewatering ProcessesInstrument Specialties, Inc.
662 visualizações3 slides
Global Perspective on the Future of Subsea Technology por
Global Perspective on the Future of Subsea TechnologyGlobal Perspective on the Future of Subsea Technology
Global Perspective on the Future of Subsea TechnologyConference_Presentations
3.4K visualizações29 slides
Subsea Separation presentation por
Subsea Separation presentationSubsea Separation presentation
Subsea Separation presentationSunday Kanshio, PhD
9.4K visualizações18 slides
Statoil innovate subsea_technology_v5 por
Statoil innovate subsea_technology_v5Statoil innovate subsea_technology_v5
Statoil innovate subsea_technology_v5Statoil
1.9K visualizações16 slides
Dariush.resume por
Dariush.resumeDariush.resume
Dariush.resumeDariush yaghmai
319 visualizações13 slides

Mais conteúdo relacionado

Mais procurados

Trenchless Technologies for New Pipe Installations por
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsLoay Ghazaleh MBA, BSc Civil Eng.
993 visualizações49 slides
Gadsen Drive Emergency Gravity Sewer Repairs por
Gadsen Drive Emergency Gravity Sewer RepairsGadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer RepairsFairfax County
150 visualizações11 slides
MAN CV ud 1.3.16 por
MAN CV ud 1.3.16MAN CV ud 1.3.16
MAN CV ud 1.3.16MOHAMMED ABDUL NAYEEM
197 visualizações10 slides
Fish Market Drainage At Abu Hamour por
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu HamourMohamed ElSirsy
929 visualizações17 slides
Cv english por
Cv englishCv english
Cv englishJerson Rodriguez Aular
167 visualizações6 slides
Longer, deeper, colder - Technology to cross energy frontiers por
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiersStatoil
919 visualizações6 slides

Mais procurados(20)

Gadsen Drive Emergency Gravity Sewer Repairs por Fairfax County
Gadsen Drive Emergency Gravity Sewer RepairsGadsen Drive Emergency Gravity Sewer Repairs
Gadsen Drive Emergency Gravity Sewer Repairs
Fairfax County150 visualizações
Fish Market Drainage At Abu Hamour por Mohamed ElSirsy
Fish Market Drainage At Abu HamourFish Market Drainage At Abu Hamour
Fish Market Drainage At Abu Hamour
Mohamed ElSirsy929 visualizações
Longer, deeper, colder - Technology to cross energy frontiers por Statoil
Longer, deeper, colder - Technology to cross energy frontiersLonger, deeper, colder - Technology to cross energy frontiers
Longer, deeper, colder - Technology to cross energy frontiers
Statoil919 visualizações
Water transportation to drilling sites por Martin Preene
Water transportation to drilling sitesWater transportation to drilling sites
Water transportation to drilling sites
Martin Preene1.6K visualizações
What subsea control systems low res por Tomásio Leite
What   subsea control systems low resWhat   subsea control systems low res
What subsea control systems low res
Tomásio Leite3.7K visualizações
RV Thuwal - Refit project overview by Maritime Survey Australia por MichaelUberti
RV Thuwal - Refit project overview by Maritime Survey AustraliaRV Thuwal - Refit project overview by Maritime Survey Australia
RV Thuwal - Refit project overview by Maritime Survey Australia
MichaelUberti386 visualizações
J Ray Firsts por MyLast1
J Ray FirstsJ Ray Firsts
J Ray Firsts
MyLast11.7K visualizações
My latest cv 1 por Pratik Parmar
My latest cv 1My latest cv 1
My latest cv 1
Pratik Parmar49 visualizações
03 drilling recent development ui 17 sep 2007 por yudi05
03 drilling recent development   ui 17 sep 200703 drilling recent development   ui 17 sep 2007
03 drilling recent development ui 17 sep 2007
yudi05906 visualizações
Keep it clean! – An Introduction to Stormwater Treatment por Communications Branding
Keep it clean! – An Introduction to Stormwater TreatmentKeep it clean! – An Introduction to Stormwater Treatment
Keep it clean! – An Introduction to Stormwater Treatment
Communications Branding916 visualizações
MCS Presentation por ArranEwan
MCS PresentationMCS Presentation
MCS Presentation
ArranEwan16.3K visualizações
CV.- Sayed Asghar Mosavi VA Version! por Sayed Mosawi
CV.- Sayed Asghar Mosavi VA Version!CV.- Sayed Asghar Mosavi VA Version!
CV.- Sayed Asghar Mosavi VA Version!
Sayed Mosawi266 visualizações
New Wave Energy Services Ltd. Presentation 2016 US por Kristopher Vardell
New Wave Energy Services Ltd. Presentation 2016 USNew Wave Energy Services Ltd. Presentation 2016 US
New Wave Energy Services Ltd. Presentation 2016 US
Kristopher Vardell647 visualizações
Facilities Engineering Presentation por Hudbay Minerals Inc.
Facilities Engineering PresentationFacilities Engineering Presentation
Facilities Engineering Presentation
Hudbay Minerals Inc.1.1K visualizações
Development of Tight Gas Fields por Neil Barnard
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
Neil Barnard209 visualizações

Similar a Blue mountains cascade dam- Horizontal direction drill

Mine dewatering techniques por
Mine dewatering techniquesMine dewatering techniques
Mine dewatering techniquesGroundwater Engineering Ltd
14.5K visualizações25 slides
Demzy's Presentation on HDD por
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDDDemzy George
4.2K visualizações42 slides
Barangaroo South District Cooling Plant (DCP) Fact Sheet por
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact SheetDeanDallwitz
968 visualizações5 slides
Summer Training Presentation por
Summer Training PresentationSummer Training Presentation
Summer Training PresentationNilesh Singh Bundela
808 visualizações22 slides
4th yer ppt por
4th yer  ppt4th yer  ppt
4th yer pptYogesh Thakur
1.1K visualizações22 slides
Disinfection System por
Disinfection SystemDisinfection System
Disinfection SystemToronto Public Consultation Unit
716 visualizações23 slides

Similar a Blue mountains cascade dam- Horizontal direction drill(20)

Demzy's Presentation on HDD por Demzy George
Demzy's Presentation on HDDDemzy's Presentation on HDD
Demzy's Presentation on HDD
Demzy George4.2K visualizações
Barangaroo South District Cooling Plant (DCP) Fact Sheet por DeanDallwitz
Barangaroo South District Cooling Plant (DCP) Fact SheetBarangaroo South District Cooling Plant (DCP) Fact Sheet
Barangaroo South District Cooling Plant (DCP) Fact Sheet
DeanDallwitz968 visualizações
Summer Training Presentation por Nilesh Singh Bundela
Summer Training PresentationSummer Training Presentation
Summer Training Presentation
Nilesh Singh Bundela808 visualizações
4th yer ppt por Yogesh Thakur
4th yer  ppt4th yer  ppt
4th yer ppt
Yogesh Thakur1.1K visualizações
Dewatering for open pit mines and quarries por Martin Preene
Dewatering for open pit mines and quarriesDewatering for open pit mines and quarries
Dewatering for open pit mines and quarries
Martin Preene7.6K visualizações
Treatment of wastewater por Arpit Budania
Treatment of wastewaterTreatment of wastewater
Treatment of wastewater
Arpit Budania2.3K visualizações
Trenchless technolgy por Bhalchandra Tankkar
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
Bhalchandra Tankkar1.8K visualizações
Exploring Tight Gas Reservoir Using Intelligent Well Technology por Abhinav Bisht
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Abhinav Bisht2.1K visualizações
Pipe Jacking por Himanshu Gupta
Pipe JackingPipe Jacking
Pipe Jacking
Himanshu Gupta17.2K visualizações
Trenchless technology por Aglaia Connect
Trenchless technologyTrenchless technology
Trenchless technology
Aglaia Connect1.2K visualizações
What is the Future for Magnetite Projects in Australia por Midas Engineering Group
What is the Future for Magnetite Projects in AustraliaWhat is the Future for Magnetite Projects in Australia
What is the Future for Magnetite Projects in Australia
Midas Engineering Group940 visualizações
Petroleum Cycle.pdf por ALANMARTIN95
Petroleum Cycle.pdfPetroleum Cycle.pdf
Petroleum Cycle.pdf
ALANMARTIN9549 visualizações
Basics of Hydro power plant por Prasad Vejendla
Basics of  Hydro power plant Basics of  Hydro power plant
Basics of Hydro power plant
Prasad Vejendla67.8K visualizações
GROUP A - POSTER PRESENTATION - M02MAM por tolani adeleke
GROUP A - POSTER PRESENTATION - M02MAMGROUP A - POSTER PRESENTATION - M02MAM
GROUP A - POSTER PRESENTATION - M02MAM
tolani adeleke172 visualizações
Final year project por MohammadHasif
Final year projectFinal year project
Final year project
MohammadHasif82 visualizações
Pipe bursting and Pre-chlorination_effectiveness on large scale projects por HammerHead Trenchless Equipment
Pipe bursting and Pre-chlorination_effectiveness on large scale projectsPipe bursting and Pre-chlorination_effectiveness on large scale projects
Pipe bursting and Pre-chlorination_effectiveness on large scale projects
HammerHead Trenchless Equipment1.1K visualizações
Ground Investigation by Horizontal Directional Drilling por Tim Leung
Ground Investigation by Horizontal Directional DrillingGround Investigation by Horizontal Directional Drilling
Ground Investigation by Horizontal Directional Drilling
Tim Leung2.3K visualizações
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline... por John Grover
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
Offshore - Coiled Tubing Offers Pre-Commissioning Tool for Deepwater Pipeline...
John Grover384 visualizações

Último

Pull down shoulder press final report docx (1).pdf por
Pull down shoulder press final report docx (1).pdfPull down shoulder press final report docx (1).pdf
Pull down shoulder press final report docx (1).pdfComsat Universal Islamabad Wah Campus
17 visualizações25 slides
DevOps-ITverse-2023-IIT-DU.pptx por
DevOps-ITverse-2023-IIT-DU.pptxDevOps-ITverse-2023-IIT-DU.pptx
DevOps-ITverse-2023-IIT-DU.pptxAnowar Hossain
12 visualizações45 slides
Design of machine elements-UNIT 3.pptx por
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptxgopinathcreddy
32 visualizações31 slides
Control Systems Feedback.pdf por
Control Systems Feedback.pdfControl Systems Feedback.pdf
Control Systems Feedback.pdfLGGaming5
6 visualizações39 slides
SPICE PARK DEC2023 (6,625 SPICE Models) por
SPICE PARK DEC2023 (6,625 SPICE Models) SPICE PARK DEC2023 (6,625 SPICE Models)
SPICE PARK DEC2023 (6,625 SPICE Models) Tsuyoshi Horigome
28 visualizações218 slides
MK__Cert.pdf por
MK__Cert.pdfMK__Cert.pdf
MK__Cert.pdfHassan Khan
11 visualizações1 slide

Último(20)

DevOps-ITverse-2023-IIT-DU.pptx por Anowar Hossain
DevOps-ITverse-2023-IIT-DU.pptxDevOps-ITverse-2023-IIT-DU.pptx
DevOps-ITverse-2023-IIT-DU.pptx
Anowar Hossain12 visualizações
Design of machine elements-UNIT 3.pptx por gopinathcreddy
Design of machine elements-UNIT 3.pptxDesign of machine elements-UNIT 3.pptx
Design of machine elements-UNIT 3.pptx
gopinathcreddy32 visualizações
Control Systems Feedback.pdf por LGGaming5
Control Systems Feedback.pdfControl Systems Feedback.pdf
Control Systems Feedback.pdf
LGGaming56 visualizações
SPICE PARK DEC2023 (6,625 SPICE Models) por Tsuyoshi Horigome
SPICE PARK DEC2023 (6,625 SPICE Models) SPICE PARK DEC2023 (6,625 SPICE Models)
SPICE PARK DEC2023 (6,625 SPICE Models)
Tsuyoshi Horigome28 visualizações
MK__Cert.pdf por Hassan Khan
MK__Cert.pdfMK__Cert.pdf
MK__Cert.pdf
Hassan Khan11 visualizações
Investigation of Physicochemical Changes of Soft Clay around Deep Geopolymer ... por AltinKaradagli
Investigation of Physicochemical Changes of Soft Clay around Deep Geopolymer ...Investigation of Physicochemical Changes of Soft Clay around Deep Geopolymer ...
Investigation of Physicochemical Changes of Soft Clay around Deep Geopolymer ...
AltinKaradagli12 visualizações
MSA Website Slideshow (16).pdf por msaucla
MSA Website Slideshow (16).pdfMSA Website Slideshow (16).pdf
MSA Website Slideshow (16).pdf
msaucla76 visualizações
Introduction to CAD-CAM.pptx por suyogpatil49
Introduction to CAD-CAM.pptxIntroduction to CAD-CAM.pptx
Introduction to CAD-CAM.pptx
suyogpatil495 visualizações
Searching in Data Structure por raghavbirla63
Searching in Data StructureSearching in Data Structure
Searching in Data Structure
raghavbirla637 visualizações
GDSC Mikroskil Members Onboarding 2023.pdf por gdscmikroskil
GDSC Mikroskil Members Onboarding 2023.pdfGDSC Mikroskil Members Onboarding 2023.pdf
GDSC Mikroskil Members Onboarding 2023.pdf
gdscmikroskil53 visualizações
K8S Roadmap.pdf por MaryamTavakkoli2
K8S Roadmap.pdfK8S Roadmap.pdf
K8S Roadmap.pdf
MaryamTavakkoli28 visualizações
Design_Discover_Develop_Campaign.pptx por ShivanshSeth6
Design_Discover_Develop_Campaign.pptxDesign_Discover_Develop_Campaign.pptx
Design_Discover_Develop_Campaign.pptx
ShivanshSeth632 visualizações
What is Unit Testing por Sadaaki Emura
What is Unit TestingWhat is Unit Testing
What is Unit Testing
Sadaaki Emura24 visualizações
Investor Presentation por eser sevinç
Investor PresentationInvestor Presentation
Investor Presentation
eser sevinç25 visualizações
SUMIT SQL PROJECT SUPERSTORE 1.pptx por Sumit Jadhav
SUMIT SQL PROJECT SUPERSTORE 1.pptxSUMIT SQL PROJECT SUPERSTORE 1.pptx
SUMIT SQL PROJECT SUPERSTORE 1.pptx
Sumit Jadhav 15 visualizações
fakenews_DBDA_Mar23.pptx por deepmitra8
fakenews_DBDA_Mar23.pptxfakenews_DBDA_Mar23.pptx
fakenews_DBDA_Mar23.pptx
deepmitra815 visualizações
Effect of deep chemical mixing columns on properties of surrounding soft clay... por AltinKaradagli
Effect of deep chemical mixing columns on properties of surrounding soft clay...Effect of deep chemical mixing columns on properties of surrounding soft clay...
Effect of deep chemical mixing columns on properties of surrounding soft clay...
AltinKaradagli9 visualizações
Codes and Conventions.pptx por IsabellaGraceAnkers
Codes and Conventions.pptxCodes and Conventions.pptx
Codes and Conventions.pptx
IsabellaGraceAnkers9 visualizações

Blue mountains cascade dam- Horizontal direction drill

  • 1. Priority Sewerage Program
 Upper Blue Mountains Sewerage Scheme
 Horizontal Directional Drilling Author: Dean Garratt
  • 2. GOALS & BACKGROUND PSP Alliance Environmentally sensitive engineering • PSP alliance aims to improve public health and protect the environment especially local waterways and catchments • Upper Blue Mountains project introduces reticulated sewerage to replace poorly performing septic tanks Major Sydney Water catchment area World Heritage Area (We are boring under Cascade Creek pictured in the background)
  • 3. PROJECT SCOPE & ISSUES • Connect the new sewerage network to the Winmalee sewerage treatment plant. • Use Horizontal Directional Drilling to bore from Meadow Bath to the existing North Katoomba sewer through Sandstone, Claystone and minor seams of Ironstone. • Perform geological survey and detailed design analysis to minimise risk and maximise design life • Use trenchless technology (HDD) to minimise the impact on the environment. – This is particularly important due to the World heritage status and tourism of the region. – HDD allows precise control of the grade so pumping stations aren’t needed, eliminating capital, running and maintenance costs. • Install 2 pipelines: 2366m @ DN450mm and 2358m @ DN225mm. • The smaller pipe will be used as backup in case of blockage or overload. • Use Heavy Duty Polyethylene (HDPE) pipe to maximise design life and ease of installation.
  • 4. HOME Technical Specification CostsPlans Productivity End Show The HDD Process Achievements HOME PAGE Site Layout Pipe Welding Pipe Installation Schedule
  • 5. HomeThe geographical layout showing location of pipes and Cascade Dam Section DN225 Section DN450 PLANS – Plan View
  • 6. Home Home PLANS – DN225 Section Plan View Section DN450
  • 7. Home PLANS – DN450 Section Plan View Section DN225
  • 8. Home • The HDD for the DN255 was carried out first • The rig was then moved to the DN450 location & 225mm pilot hole was drilled • The hole was then forward reamed to 450mm diameter • After drilling was complete, the pipes were installed into the bores • The pipes were welded in parallel with the drilling so that they could be installed into their bores as soon as drilling was complete Summary Schedule
  • 10. • A detailed geotechnical survey helps make the right choice of drilling rig, fluid composition, tools and techniques • Drill path is engineered using computer-aided design and sophisticated mechanical and stress engineering software • With the rig accurately aligned to the drill path, drilling fluid (bentonite & water) is pumped down the drill pipes. This provides high pressure fluid to jet nozzles for drilling the softer materials, or power to a down hole motor which drives a roller-cone bit in rock. • The fluid provides drilling power, consolidates the walls of the drillhole, acts as a lubricant and carries spoil out of the hole • As the cuttings laden fluid travels back up the drillhole, it is captured, the cuttings removed and recycled, so the fluid can be pumped back around the drilling loop • The downhole drilling assembly is guided by electronic steering instrumentation that transmits data in real time to a surface-based computer that allows the driller to precisely locate the drilling assembly and guide it along the pre-determined drill path • The drilling assembly is replaced with a reamer which is pulled back or pushed forward to enlarge the pilot hole to the size needed for the product pipe HDD Process Home
  • 11. Technical Spec The American Augers DD-1100: DD1100 Spec. link Home Engine Type: 2 x Caterpillar 3412E DITTA diesel engines. Rating: 2 x 760 HP @ 2100 RPM = 1520 total HP Pumps: Each engine drives 4 hydrostatic drive pumps – 2 for rotary torque and 2 for thrust/pullback Rotary System: Four pinion drives 100,000 ft-lbs rotary torque @ 0-40 RPM (at max torque) 44,000 ft-lbs rotary torque @ 0-90 RPM (at max speed) Carriage System: Six pinion drive, each with a planetary gearbox and two speed radial motor. Two 3” mud hoses in a hose carrier. Carriage Thrust/Pullback: 500 tonnes @ 6.9m/min 372 tonnes @ 9.2m/min 241 tonnes @ 13.8m/min 114 tonnes @ 32.5 m/min Operators Control Console Description: Electric over hydraulic controls, pulse with modulation, Diagnostic warning lights for all filters & fluid levels. Full digital and analogue instrumentation. Other Features: Wire-line steering system, 3785 LPM flow capacity, Wiggle steer
  • 12. Home • The pipeline was joined using industry standard butt fusion welding • Due to access restrictions, the pipeline was welded & debeaded in 800m lengths. Each length of pipe was 12m. • The welding machine used was a McElroy TracStar No. 618 Fusion welder • Welding the DN225 pipe achieved approximately 5-7 joints/day • Welding the DN450 pipe achieved approximately 3-5 joints /day • To see an animation of the butt fusion welding process, click on the link below Fusion welding animation HDPE Pipe welding
  • 13. Home •The pilot hole was drilled short of tunnel. The bentonite in the borehole was cleaned via flocculation. Once the drilling mud is cleaned the last section of the borehole will be drilled with clean water and punch into the tunnel •The pipes were pushed/floated in from entry side (rig site, Medlow Bath) towards the exit side (Katoomba) •A 30 tonne excavator was used straddle the entry point and feed the pipe directly into the hole with additional excavators used to help manage the bends in the pipe string •The pipe was fed into the bore open ended to allow fluid remaining in the belly of the bore to flow into the pipe thus insuring the pipe is not too buoyant which would jam the pipe against the top of the hole • The designers generated 31 variations of what installation loads may be seen when installing the pipe, they took into account the following criteria; -Mud Weight -Viscosity -Helical Buckling -Sinusoidal Buckling -Asbuilt profile of the bore. -Properties of the HDPE pipe HDPE Pipe Installation
  • 14. Production & Productivity - Overview Home • Productivity was increased by using parallel processes • Drilling operations were carried out 24/7 to decrease the overall duration thus minimising overhead costs • On average approximately 10-15 men were used during the peak day operating period & 6-8 men used during the night shift to save on cost • The plant and equipment chosen was advanced enough to complete the work with a high factor of safety. DN225 Pilot hole for DN450 pipe DN225 Drilling
  • 15. Production & Productivity – DN225 Drilling Average production = 2.2 manhours / metre Home Overview DN225 Pilot hole for DN450 pipe Average productivity = 76 metres / day
  • 16. Production & Productivity – DN225 Pilot hole Drilling for DN450 pipe Overview DN225 Drilling Average production = 2.0 manhours / metre Home Average productivity = 126 metres / day
  • 17. • Total Cost incl indirects = $14.4 million • Total Cost directs only = $10.3 million • Total length of 2 bores = 4724m • Rate incl indirects = $3050/metre • Rate directs only = $2180/metre Cost Home
  • 18. Technical feats and 
 achievements At 2.4km length, this is the world's longest HDD sewer installation, overtaking the record set by AJ Lucas with the Wollongong sewer pipeline installed in 2004. Home