Fairbank & Oakwood Construction Updates Deck - November 2020

1.182 visualizações

Publicada em

Construction updates for Fairbank & Oakwood stations, as of November 3, 2020.

Publicada em: Governo e ONGs
  • Seja o primeiro a comentar

  • Seja a primeira pessoa a gostar disto

Fairbank & Oakwood Construction Updates Deck - November 2020

  1. 1. November 2020 Fairbank Station & Oakwood Station Station Update
  2. 2. Fairbank Station
  3. 3. FAIRBANK STATION UPDATE 3CENTRAL WEST WORKS MONTHLY MEETING Activity Location Approx. Date & Duration Traffic Flip Dufferin St Completed October 2020 Final Concourse Slab Pour Station Box November 2020 Concrete Works (rebar, formwork, concrete pours) Station Box Underway through 2020 Waterproofing Installation Station Box Underway through 2020 Dewatering Well Monitoring West side of Dufferin Street b/w Ramsden Rd and Eglinton Ave W Underway on Wednesdays through 2020 Masonry Works Main Entrance and Concourse Level Underway through 2020 Electrical & Mechanical Installation Station Box Underway through 2020
  4. 4. CURRENT TRAFFIC CONFIGURATION 4 October 2020 – January 2021 CENTRAL WEST WORKS MONTHLY MEETING
  5. 5. CONSTRUCTION PROGRESS PHOTOS 5CENTRAL WEST WORKS MONTHLY MEETING STATION BOX CONCOURSE SLAB 3 REBAR COMPLETED SECONDARY ENTRANCE WEST WALL REBAR
  6. 6. Oakwood Station
  7. 7. OAKWOOD STATION UPDATE 7INSERT FOOTER Activity Location Approx. Date & Duration Station Box Construction Concrete pours, formwork installations, masonry works. Beneath Eglinton Avenue West between Times Rd and Oakwood Ave Underway through late 2020. Overhead Gantry Crane Removal Main Entrance Site Underway for approximately two (2) weeks Track Installations Progressing from west to east Station Box Beginning in early-November 2020 for approximately two (2) months Main Entrance Shaft Construction Waterproofing, structural steel, conduit, formwork installation and concrete pours North side of Eglinton Avenue at Oakwood Avenue with material staging on Times Road Underway through early 2021 Times Road will remain closed through January 2021 Secondary Entrance Building Construction Installation of structural steel, masonry walls, tiles, pre-cast panels, roof construction and glazing. Southside of Eglinton Avenue, west of Oakwood Avenue Underway through early 2021 Dewatering well maintenance Perimeter of the station Ongoing until the end of the year
  8. 8. CURRENT TRAFFIC CONFIGURATION 8 Expected to remain in place through late January 2021
  9. 9. UPCOMING TRAFFIC CONFIGURATION 9 Late January 2021– September 2021 INSERT FOOTER
  10. 10. CONSTRUCTION PROGRESS PHOTOS 10INSERT FOOTER ESCALATOR INSTALLATION – STATION BOX MASONRY BLOCK INSTALLATION – SECONDARY ENTRANCE

×