Eglinton-Mt Pleasant Construction Liaison Committee - November 202011 2020

  1. 1. November 11, 2020 Eglinton Crosstown LRT Eglinton – Mt Pleasant CLC
  2. 2. Eglinton Station
  3. 3. EGLINTON STATION UPDATE 3CENTRAL WEST WORKS MONTHLY MEETING Activity Location Approx. Date & Duration Extended Hours for Station Box Construction Excavation, rebar, conduit and micropile installation Beneath the TTC box Underway through 2020 Monday – Friday, 24 hours Berwick Portal Construction/TTC Eglinton Station Works Delivery of escalator truss and north platform relocation preparatory works Eglinton TTC Station Periodically through 2020; subject to TTC approval Next scheduled closure(s): • November 14-15, 2020 Tunnel Ventilation Shaft Construction Center of Yonge St between Eglinton Ave and Roehampton Ave Underway through December 2020 Elevator Construction 2200 Yonge St (former Smoke’s Poutinerie) Underway through December 2020 Structural Steel Deliveries Northeast corner of Yonge St and Eglinton Ave As early as 6:00 a.m. Monday – Sunday for two (2) weeks
  4. 4. CURRENT TRAFFIC CONFIGURATION 4CENTRAL WEST WORKS MONTHLY MEETING Through 2020
  5. 5. CONSTRUCTION PROGRESS PHOTOS 5CENTRAL WEST WORKS MONTHLY MEETING REBAR INSTALLATIONS – BERWICK PORTAL WATERPROOFING
  6. 6. Mount Pleasant Station
  7. 7. MOUNT PLEASANT STATION UPDATE 7INSERT FOOTER Activity Location Approx. Date & Duration Tunnel Segment Demolition and Removal Station Box and Entrances Complete! Deep Excavation and Chipping Underneath the Station Roof Underway for approximately two (2) weeks Utility Reinstatement Works North and South sides of Eglinton Avenue Underway through 2021 Waterproofing, rebar, steel and conduit installations Secondary Entrance and Station Box Underway through 2021 Concrete Works Secondary Entrance and Station Box Underway through 2021 Above Ground Construction of the Secondary Entrance • Structural Steel Installations North side of Eglinton Avenue, east of Mount Pleasant Road Expected to start late Winter 2020 and continue through to 2021
  8. 8. CURRENT TRAFFIC CONFIGURATION 8 Until early Winter 2020
  9. 9. SNOW CLEARING ROUTES 9 Winter 2019 - 2020
  10. 10. RECORD BREAKING ACHIEVEMENT: MT PLEASANT STATION COMPLETES THE LARGEST CONCRETE POUR ON THE PROJECT! 10INSERT FOOTER Last Saturday, Mt Pleasant Station completed the largest concrete pour on the project to-date. The team poured 1700 m3 of concrete in 11 hours, forming two of the station inverts and track beds.
  11. 11. CONSTRUCTION PROGRESS PHOTOS 11INSERT FOOTER Tunnel demolition and removal complete.

×