Crews will be performing construction work on the Eglinton Crosstown LRT project at Cedarvale and Forest Hill stations over the next few months. At Cedarvale Station, a 36-hour concrete pour will occur from July 31 to August 1, reducing Eglinton Avenue to one lane in each direction. Extended construction hours will also resume to complete pedestrian tunnels near Eglinton West Station. At Forest Hill Station, excavation and construction of station entrances will continue through 2020, and concrete pours are scheduled for August 14 and late August at the secondary entrance. Traffic configurations will be impacted at both stations through late summer due to this ongoing construction work.
3. CEDARVALE STATION UPDATE
3CEDARVALE –FOREST HILL CLC
Activity Location Approx. Date & Duration
Deep Excavation & Tieback Installation Station’s Main Entrance
Underway through to late-August 2020;
6:00 a.m. – 11:00 p.m.
Major Concrete Pours Throughout all station areas
Underway throughout 2020 into 2021
Starting as early as 5:00 a.m. ranging from 12-18
hours
Geotechnical Monitoring
Eastbound curb lane of Eglinton Ave between
Winnett Ave and Allen Rd N
January 2020 – September 2020
Tuesdays between 11:00 a.m. – 2:00 p.m.
Pedestrian Tunnel Construction Area surrounding Eglinton West Station
Underway through to 2021
Monday – Saturday; 6:00 a.m. – 2:00 a.m.
Eglinton West Station Support of
Excavation and Underpinning Works
Eglinton West Station
Underway through 2020
Monday – Saturday; 6:00 a.m. – 5:00 p.m.
Eglinton West Station Bus Loop Closure
for Roof Construction
Eglinton West Station Underway – late Summer 2020
Temporary Traffic Deck Removal, Roof
Construction, and Permanent Utility
Installation
Eglinton Avenue West March 29, 2020 – early 2021
4. UPCOMING CONCRETE POUR AT CEDARVALE STATION
4
From Friday July 31 – Saturday August 1, 2020 crews at Cedarvale Station will perform a
36-hour long concrete pour on the north side of Eglinton Avenue, between Allen Rd S and
Park Hill Rd.
• The concrete will form the permanent base for the track slab that the future LRT will travel on.
• Over 1200m3 of concrete will be poured.
• To ensure the integrity and continuity of the pour, work will start as early as 4:00 a.m. on Friday July
31 and continue through to 12:00 p.m. on Saturday August 1.
• To perform this work safely, Eglinton Avenue will be reduced to one lane in each direction, while
the pour takes place.
• No changes to pedestrian routes are expected.
• Access to Eglinton Avenue West Station and TTC will be maintained at all times.
• Overnight noise from construction activities can be expected, while the pour takes place.
CEDARVALE –FOREST HILL CLC
PREVIOUS CONCRETE POUR –
CEDARVALE STATION
6. CONCRETE POUR TRAFFIC CONFIGURATION
6
Friday July 31 – Saturday August 1, 2020
CEDARVALE –FOREST HILL CLC
7. UPDATE RESUMPTION OF EXTENDED CONSTRUCTION HOURS
7
• In spring 2019, crews began working extended construction hours to accelerate construction of Cedarvale Station
• In July 2020 crews will resume extended construction hours to complete construction of the pedestrian tunnels in the
area surrounding Eglinton West Station.
• The tunnels will connect TTC’s Eglinton West Subway Station to the future Cedarvale LRT Station.
• This work will take place Monday – Saturday from 6:00 a.m. – 2:00 a.m.
• Construction activities include:
• Excavation (hauling will continue to take place between 6:00 a.m. – 11:00 p.m. only)
• Support of Excavation Works
• Stockpiling of excavated materials
• Welding
• Concrete works
• Site-level mitigation measures are in place to minimize disruption.
CENTRAL WEST WORKS MONTHLY MEETING
RENDERING
CEDARVALE STATION
8. CONSTRUCTION PROGRESS PHOTOS
8CEDARVALE –FOREST HILL CLC
DECKING REMOVAL & STEEL INSTALLATION
– EAST SIDE OF THE BUS LOOP
REBAR & FORMWORK INSTALLATION
- STATION BOX
10. FOREST HILL STATION UPDATE
10CENTRAL WEST WORKS MONTHLY MEETING
Activity Location Approx. Date & Duration
Deep Excavation
Beneath the station roof from the Main
Entrance
Underway through summer 2020
Main Entrance Construction
Excavation, installation of struts, lagging
and tie-backs
Northeast corner of Bathurst St and
Eglinton Ave
Underway through 2020
Secondary Entrance Construction
Formwork, rebar, conduit installation
and beam excavation
North side of Eglinton Ave, west of
Bathurst St
Underway through fall 2020
Station Box Construction
Waterproofing, shotcrete application
and duct bank construction
Beneath Eglinton Ave Underway through 2020
Concrete Pours Secondary Entrance
• Friday August 14, 2020 at 5:00 a.m. for
approx. 12 hours
• Two pours in late August 2020 (dates
TBD)
Resumption of Extended
Construction Hours for Installation
of Structural Steel and Pre-cast
Panels
Secondary Entrance
August – October 2020