Properly Reviewing a Schedule
         March 20, 2008

         Chris Carson, PSP
           Director, Project Controls
               Alpha Corporation
        chris.carson@alphacorporation.com
Properly Reviewing a Schedule
Goals
  Confirm that schedule is reasonable and
  attainable
  Understand Contractor’s Means & Methods
  Establish a good baseline for monitoring
  Verify durations
  Verify logic and sequencing
  Identify claims positioning issues
  Identify risks in schedule and assumptions
  Document concerns
Schedule Review
Baseline Schedule Review
 Review Scheduling Specification
 Confirm Submittal Completeness
 Gain Familiarity with Project
 Import Schedule & Verify
 Review Schedule Architecture
 Review Schedule Construction
 Review Narrative
 Review Sequencing
 Evaluate Metrics & Statistics
 Perform Analysis
 Write Report
Baseline Schedule Review
Review Scheduling Specification
 Section 01320 or 01.32.16        CPM Network requirements
 Check Related Specifications     Duration definitions & restrictions
 Sections or Special Provisions   Initial schedule submission
 Software requirements            Full detailed project schedule
 Data exchange requirements       (baseline) submission
 Master dictionaries/reports      Schedule updates
     Activity Code requirements   Delays & time extensions
     ID Coding requirements            Notification Requirements
 Preconstruction meeting          Early completion schedules
 Qualifications of scheduler      Final as-built submittal
 Required submittal contents      Cost & Resource loading
 Owner mandated milestone         Narrative Requirements
 treatment                        Prohibitions on manipulation
 Float ownership
Schedule Specification
               Use a checklist to
               capture specification
               requirements
               Identify time allowed for
               review and response
Baseline Schedule Review
Gain Familiarity with Project
    Review Plans & Specifications
    Review specialty specs like DOT Bridge & Road Manual
    Visit job site
    Review construction methodology or unusual techniques
    Bring in expertise if necessary
Baseline Schedule Review
Confirm Submittal Completeness
   Compare to schedule specification requirements
   Notify Contractor immediately if not complete
   Do not start review until submittal is complete
   Typical missing items:
      Schedule Narrative
      Electronic File
      Explanation of Calendars, Lags, Activity Codes, Constraints,
      Resources, Costs
      Milestones and Milestone definitions
   Consider two part review if costs or resources are missing
Baseline Schedule Review
Import Schedule & Verify
   Keep original submittal file, make copy to review
   Should review in original software if possible
   Recognize that there are issues with import in many software
   packages
   Develop checklist to identify potential import issues
   Example - Primavera P3 to P5 import :
       In P3, Lags are driven by Predecessor Calendar
       In P5, Lags can be driven by choice of Calendars
       Default P5 setting to drive Lags is not the Predecessor Calendar
   Must verify that imported schedule used to analyze is identical to
   original submitted schedule
Baseline Schedule Review
Develop a checklist for reviews
Baseline Schedule Review
Review Schedule Architecture
    Check Schedule Rules & Settings
    Recalculate Schedule
    Review Organizational Tools

Review Schedule Construction
    Evaluate Activities
    Review Logic
    Evaluate Critical Path
Baseline Schedule Review
Review Schedule Architecture
    Check Schedule Rules & Settings
      Retained Logic vs. Progress Override
        • Won’t affect Baseline, but could cause optimistic
          predictions during updates
      Resource and Cost rules
        • Estimate to Complete setting might allow Estimate at
          Completion to change
      Understand all settings and how they affect Earned
      Value & reports
      Identify how Critical Path is calculated
        • Longest Path

        • Total Float value
Baseline Schedule Review
Review Schedule Architecture
     Recalculate Schedule, ensure no change
     Check NTP and Completion dates
     Check all interim Milestone dates
     Review Organizational Tools
      • Review Activity Code Dictionaries

      • Review Resource Code Dictionaries

      • Review Calendars

      • Review WBS
Baseline Schedule Review
Review Schedule Construction
 Evaluate Activities
    Sort by Activity Description
       For good guidelines, see AACE publication No. 23R-02,
       Recommended Practice for Identification of Activities
       See if descriptions are consistent and unique
       Ensure all items that could delay project are represented by
       activities, such as procurement and other admin work
       Compare descriptions for reasonable and comparable Original
       Durations
       Confirm that descriptions capture full scope of work
    Sort by Original Duration
       Check for specification maximum times
       Check for reasonable ODs
Baseline Schedule Review
Review Schedule Construction
    Review Logic
      See AACE publication No. 24R-03, Recommended
      Practice for Developing Activity Logic for guidelines
      Check open-ended relationships
        • Should only be two; start and end
        • Reduces accuracy of network calculations
        • Watch for “dangling” activities: SS or FS with
          negative Lag which leave Predecessor open-ended
          upon updates
      Evaluate relationships
        • Check on all Lags
        • Filter by trade, check same-trade relationships
        • Filter by Contractor, check those relationships
Baseline Schedule Review
Review Schedule Construction
    Evaluate Critical Path
       Is it reasonable and customary?
       Does it start at beginning of project and run to completion?
       Does it have an appropriate level of detail?
       Are there manipulations driving the Critical Path?
             Float sequestering where everything is critical
         •

             Manipulation where Critical Path runs inappropriately through all
         •
             owner responsibilities
             Critical Path is the only highly detailed string of activities in the
         •
             project
             Nothing is critical due to heavy constraint use
         •

             Numerous lags, perhaps not identified, inserted in the Critical Path,
         •
             forcing it through specific activities
             Is there weather planning included in Critical Path activities or will
         •
             any adverse weather cause slippage?
Baseline Schedule Review
Review Schedule Construction
     Evaluate Near Critical Paths
        How much work is just off Critical Path?
        Check Longest Path and lowest Total Float paths
        (Recommend review of TF < ½ Reporting Period)
     Sort by Total Float
        Check reasonableness of high float items
        Is there a consistent range of TF?
        Lots of high TF activities means underdeveloped logic
        All low TF suggests inappropriate logic
     Sort by Late Start
        This is the worst case expectation of work flow
        Start at end of schedule & see if reasonable
        Organize by Late Start, Order Week Ascending, see if the
        amount of work planned each week is possible
        Check trade stacking, can they fit into spaces?
Baseline Schedule Review
Review Schedule Construction
    Sort by Early Start
       Organize by Early Start, Order Week Ascending, again
       see if the amount of work planned each week is
       reasonable
       Are there trades stacking up?
    Organize by Early Start, Sort by Late Start
       Summarize to Early Start, review overlaps between
       weeks
       Specifically review strong overlaps (points out missing
       relationships)
       Helps focus on small segments of project working
       concurrently
Baseline Schedule Review
Review Schedule Construction
   Review resources
     Check for resource “soft” logic used to control flow of
     manpower from area to area
     Schedules without reasonable soft logic will likely show
     lots of high Total Float values
     Overuse of soft logic can sequester Total Float and
     force Critical Path
     Durations should be resource-based; that is calculated
     by production rate x quantity, so resource planning
     must be taken into account
Baseline Schedule Review
Review Written Narrative
     At a minimum, Narrative should identify sequence and work
     flow
     Identify phasing
     Provide the Area Designation Plan
     Summary of the work
     Explain plan for construction
     Identify potential problems or risks
     Summarize the Critical Path; does it match the schedule?
     Identify all Milestones
     Explain schedule components:
        Activity ID Coding, Activity Coding, Resources, Lags, Constraints,
        unusual logic relationships
     Adverse weather planning
Baseline Schedule Review
Review Sequencing
   Use Narrative as guide
   Check for missing Activity Codes that may not include work in
   sequences
   Choose layout with sequencing
   Compare to specification requirements
   Summarize to sequences, then drill into each sequence
   Check reasonableness of logic
   Check overlap of sequences
   Check other layouts
Baseline Schedule Review
Generate Metrics
   Counts
      Activities by type (procurement, construction, Owner
      responsibilities)
      Activities by trade (Section number, work package)
      Activities on Longest Path
      Relationships
        • Total by types

        • Lags

      Constraints
   Verify appropriate & consistent level of detail
Baseline Schedule Review
Data retrieval from schedule
  Develop data crunching methodologies
    Master layouts with filters
    Export filters to export to Excel or Lotus
    Standard Pivot tables
    Input/output worksheet spreadsheets
    Graphical depictions for reasonableness
      • Histogram distributions

      • Tables

      • Charts
Baseline Schedule Review
Use Pivot Tables or other data
collecting & collating methodologies
Baseline Schedule Review
Generate Statistics
    Recommend use of Pivot Tables
    Use statistics to identify inconsistencies
      Ratio work/non-work activities
      Ratio trade work
      Ratio durations (helps spot partial overdevelopment)
      Ratio work in each sequence
      Percentage of activities on Longest Path and Near
      Critical Paths
No. Activities
                  H
                   am
                     m
                      oc
                        ks
                                 an
                                     d
                           A
                             sp Mile
                        C        ha            st
                         le




                                                                0
                                                                    50
                                                                         100
                                                                               150
                                                                                     200
                                                                                           250
                                                                                                 300
                                                  on
                            ar lt P                    es
                              in          la
                                 g           c
                                    an em
                                        d            en
                                           G
                                               ru t
                                                  bb
                                                       i
                                       D
                                 D        em ng
                  E
                   ro               em o
                     si                 ob litio
                       on
                                             ili n
                           &                    za
                              S
                                ed E tion
                                    im lec
                                        en tri
                                            t C ca
                                                 on l
                                                      tro
                                                            l
                                            G
                                    La ra
                                                  d
                               M nd ing
                                            sc
                                  at
                                                a
                                     er
                                       ia pin
                                                         g
                                           lD
                        M                       e
                   S
                    to aint Mo live
                                                         ry
                      rm en b
                          D an iliza
                            ra         ce          tio
                               in
                                   / S of n
                                       to Tra
                                                                                                       Distribution of Activities




                                          rm ffi




Feature of Work
                                                Se c
                                                     w
                             S                           er
                               tri So
                                  pi        un
                          S                      dw
                            ub ng
                                m / P al
                                                          l
                                  itt
                                                                                                                                            proportion detail in trade activities)




                                     al aint
                            S
                              id         / A ing
                         U ewa ppr
                           nd                      ov
                               er lk /
                                                                                                                                                                                       Baseline Schedule Review




                                                         al
                                             M
                                  gr
                                     ou ed
                                         nd ia
                                                         n
                                               U
                                                 til
                                                    iti
                                                                                                                                    Histogram of Activity Work Scope (showing out of




                                                        es
Baseline Schedule Review
Perform Analysis
    Review types of constraints
    Remove constraints, one by one
    Look at results with each removal and identify effects
    Evaluate total number of constraints
      Date constraints; should be minimum and only those
      dictated by Owner
      Don’t allow mandatory constraints which sequester float
      Logic constraints; watch for float removal constraints like
      Zero Total or Free Float
      Network should be logic driven, not constraint driven
    Constraints can cause multiple Critical Paths
      Requires analysis of each path in baseline and updates
Baseline Schedule Review
Perform Analysis
   With Cost Loading, use Earned Value
     Review S-Curve for reasonableness
     Don’t use Banana Curves, the Late Start curve
     provides a deceptive lower performance range
     Remember that this sets the baseline for
     monitoring the progress
Baseline Schedule Review
Review shape of Earned Value S-Curve (BCWS)
  Might point out front-end loading or unreasonable plan
  May show too aggressive expectations for billing
Baseline Schedule Review
Write Report
   Organize checklist to match report
   Provide Executive Summary
   Provide recommendations for Best Practices
   improvement in schedule
   Provide Deficiency List
   Require response to Deficiency List
   Do not dictate means and methods
   Keep report professional without addressing assumed
   motivation for schedule features
      Don’t say, “Use of so many constraints is clearly a devious
      attempt to pervert Critical Path”
Update Schedule Review
General process similar to Baseline
  Review Scheduling Specification
  Review Plans & Specifications
  Confirm Submittal Completeness
  Import Schedule & Verify
  Data Validation
  Review Schedule Architecture
  Review Schedule Construction
  Review Narrative
  Review Sequencing
  Evaluate Statistics
  Write Report
Update Schedule Review
 Update Schedule Review
  Same steps as Baseline Review
    Review Scheduling Specification
    Review Plans & Specifications
    Confirm Submittal Completeness
    Import Schedule & Verify
  Data Validation – must be done with each update
  Same steps as Baseline Review
    Review Schedule Architecture
    Review Schedule Construction
    Review Narrative
Update Schedule Review
Data Validation
  Field information – should have been kept on a daily
  basis
    Verify Actual Start Dates
    Verify Actual Finish Dates
    Verify Predicted Finish for any activity started but not
    finished
    Verify Percent Complete if schedule is cost loaded
    Prefer Remaining Duration, not Percent Complete, for time
    reporting
       • Superintendents generally cannot provide accurate
         Percent Complete
  Data validation is very important
Update Schedule Review
Data Validation
  Office information
    Watch status of buyout process; purchase orders &
    subcontracts – what is not bought out
    Verify Submittal & Approval status
    Verify status of administrative tasks
      • Utility paperwork status

      • Permits – site, building, right-of-way, Health Department

      • Environmental releases, etc.

    Verify status of materials fabrication and order time - “Lead
    Time” – this is an area where schedule manipulation can
    occur
Update Schedule Review
Data Validation
  Owner information
    Independently verify status of Owner controlled activities
      • Owner utility applications & progress

               Electricity
           -
               Gas service
           -
               Water & sewer
           -
               Telephone
           -
               Cable or data
           -
               Security system
           -
          Delivery dates for Owner furnished equipment
      •

          Other Owner contractual work
      •

          Verify coordination with Owner work
      •
Update Schedule Review
Calculate Schedule
  Ensure software setting is Retained Logic
  Verify Data Date is correct date
  Calculate schedule
Check for Out-of-Sequence Work
  Change setting temporarily to Progress Override
  If the completion date changes significantly, then there
  is a lot of out-of-sequence work needing correcting
  If minimal change, no significant out-of-sequence work
  Change the setting back to Retained Logic (default)
Update Schedule Review
Prepare for Schedule Analysis
  Use standard Layout with comparison to last
  update
  Check for slippage in Substantial Completion
  date or Milestones
    If no slippage, project predicts on time completion
         Perform standard analysis, use standard reports and
     •
         publish
    If slippage, will need additional analysis of slipped
    schedule
Update Schedule Review
Standard Schedule Analysis (On-Time
Completion)
  Three basic components to monitor
    Critical Path progress
     • Slippage will directly delay work

    Near Critical progress
     • Slippage could easily overtake Critical Path and delay
         work
    Non-Critical (“mass volume”) work
     • Lack of progress will cause trade stacking and over-
         crowding of work space at a later date
     • Could easily allow too much work for areas available

     • Good place to use Earned Value for monitoring

     • Can use Float Dissipation to monitor

     • Can use other methods to monitor
Update Schedule Review
Standard Schedule Analysis (On-Time
Completion)
  Two types of paths to watch
     Critical Path to end of project (Substantial Completion)
     Critical Path to Interim Milestones
  Critical Path to end of project
     Ideally use Longest Path
     Monitor minimum Total Float value Critical Path as well
  Critical Paths to Interim Milestones
     One path per each Milestone to watch
     This can be time consuming, but necessary
     Slippage in interim Milestones and achieving final Milestone
     can be basis for acceleration claims
Update Schedule Review
Standard Schedule Analysis (On-Time
Completion)
  Identify current period Critical Path (Longest Path)
  Identify current period Near-Critical activities
  Identify Milestones to review
    Owner mandated only
    Watch particularly for Milestones with Liquidated Damages
  Identify historical trends and statistics (mass volume)
    Graphics are powerful in the report
  Identify resource problems or concerns
  Identify risks, either continuing or new
Update Schedule Review
Historical Comparisons & Statistics
  Run Tipper (TPR) reports
  Run Total Float dissipation (Erosion of Float) reports
  Run Free Float dissipation reports (monitors
  disruption)
  Review Out-of-Sequence work by trade
     Which trade is causing most out-of-sequence work?
     Are they working out-of-sequence due to other trade
     failures to complete?
     Or working in open areas without regard for planning?
  Run Resource reports
     Are appropriate resources working?
     Check against Tipper reports
Update Schedule Review
      Review (TPR) Time Performance Ratio trending
       (AD/OD)

                                     Time Performance Ratio

      8.00
      7.00
      6.00
      5.00
TPR




      4.00
      3.00
      2.00
      1.00
      0.00
             31-   30- 31-     28-  31-    30-   31- 30-   31-    31-  30- 31-    30-   31-  31- 28- Total
             Oct   Nov- Jan-   Feb- Mar-   Apr- May- Jun- Jul-06 Aug- Sep- Oct-   Nov- Dec- Jan- Feb-
                    05   06     06   06     06   06   06          06   06   06     06   06   07   07

                                                     Period Ending
Update Schedule Review
 Review (TPR) Time Performance Ratio trending by
  Milestone by Responsible Contractor (AD/OD)
Update Schedule Review
  Review (TPR) Time Performance Ratio per trade
   (AD/OD)
               Time Performance Ratio

      12.0
      10.0
       8.0
TPR




       6.0
       4.0
       2.0
       0.0




                    ev s
                             ry




                              s
                             ry




                             nt
                            ws




                  El cal
                              e




                / W fing




                               l
                E q h es
                              s
                            rk
                            in




                           ca
                            g

                           or
                           al
                           et




                          nt
                         on
                          m




               Fu me
                        wo




                         in
                        do




                        ni

                        tri
                        et




                        at
                        cr




                      pe

                      oo
       Ad




                        s



                     ish
                     as




                    ha

                    ec
                     te




                     M




                     ni

                      p
                    on




                     in
                    R
                   ar




                   ui
                   Fi
                   M
                  Si




                  rn



                 ec
                 El
                  C




                 C




               M
              rs
           oo
         D




                        Type of Work
Update Schedule Review
Review (TPR) Time Performance Ratio trending by
 trade (AD/OD)
                                   Time Performance Ratio (Concrete)

      8.00
      7.00
      6.00
      5.00
TPR




      4.00
      3.00
      2.00
      1.00
      0.00
                                                 6




                                                                       07




                                                                                      7
                 6




                                                            6




                                                                                               l
                               6




                                                                                             ta
                                              -0




                                                                                   -0
                  0




                                                             0
                             -0




                                                                     n-




                                                                                          To
               p-




                                                          c-
                                            ov




                                                                                 eb
                           ct




                                                                   Ja
             Se




                                                       De
                         -O




                                          -N




                                                                               -F
                                                                    -
            -




                                                        -




                                                                 31
                      31




                                       30




                                                                            28
         30




                                                     31




                                                      Period Ending
Update Schedule Review
Trade Monitoring by Crew – no resource loading
  available, load single crew resources into activities


  AMP Terminals Yard Project
Update Schedule Review
                                  Watch erosion of float, do not let it continue
                                          Print by trade when assessing available resources
                                     •



                                                 Relative Total Float of Area Completion Milestones
                       200




                       150
Relative Total Float




                                                                                                                                                                SCAC
                                                                                                                                                                RCA
                       100
                                                                                                                                                                  WH
                                                                                                                                                                MCAC/CCAC

                                                                                                                                                                Utility Bldg

                                                                                                                                                                  NBB
                                                                                                                                                                MSGQ
                        50
                                                                                                                                                                  WBN
                                                                                                                                                                NOB

                                                                                                                                                                Subst Comp

                         0




                                                                                                                                      22
                             BL


                                    08


                                           09


                                                  10


                                                         11


                                                                12


                                                                       13


                                                                              14


                                                                                     15


                                                                                            16


                                                                                                   17


                                                                                                          18


                                                                                                                 19


                                                                                                                        20


                                                                                                                               21




                                                                                                                                             23


                                                                                                                                                    24


                                                                                                                                                           25
                                                                                                                                    SI
                                  KN


                                         KN


                                                KN


                                                       KN


                                                              KN


                                                                     KN


                                                                            KN


                                                                                   KN


                                                                                          KN


                                                                                                 KN


                                                                                                        KN


                                                                                                               KN


                                                                                                                      KN


                                                                                                                             KN




                                                                                                                                                  KN


                                                                                                                                                         KN
                                                                                                                                           SS
                       -50
Update Schedule Review
                         Earned Value Management Reporting
                                  Earned Value and Actual Costs
                             •

                                  Compared against Planned Value
                             •

                                             Ciudad Juarez Earned Value
                                          Project Update Earned Value
                 $70,000,000.00

                 $60,000,000.00

                 $50,000,000.00
B illing Value




                 $40,000,000.00
                                                                          Early Curve
                                                                          Late Curve
                 $30,000,000.00
                                                                          Actual Curve
                 $20,000,000.00

                 $10,000,000.00

                         $0.00
                             De v-0 5




                             De v-0 6




                             De -0 7
                             Fe 0 6




                              Ju 0 6




                             Fe -0 7




                              Ju 0 7




                             Fe -0 8
                             M - 06
                             A p - 06




                             A u l-06




                             M 07
                             A p - 07




                             A u l-07




                             M 08
                                      8
                             O - 05



                             J a -0 5




                             M r- 06




                             S e - 06
                             O - 06



                             J a -0 6




                             M r- 07




                             S e - 07
                             O - 07



                             Ja 07
                             J u -06




                             J u -07
                             No - 05




                             No - 06




                             No - 07




                                   -0
                                 n-




                                 n-




                                 n-
                                 b-




                                 b-
                                 c-
                                 v
                                 n




                                 n
                                ar




                                ar




                                ar
                                 b
                                 c




                                 c
                                p




                                g
                                p




                                g
                                p
                               ay




                               ay
                               ct




                               ct




                               ct
                           Se




                                                    Period Ending
Update Schedule Review
                             Earned Value Management Reporting
                                     SPI and CPI metrics
                                 •

                                     Watch trending
                                 •


                                                                       Schedule Performance Index

                 1.20

                 1.00
S PI (E V/P V)




                 0.80

                 0.60

                 0.40

                 0.20

                 0.00
                                        05




                                                                                                                                                   06
                                                        06




                                                                                                      06




                                                                                                                                                                   07
                                                                  06


                                                                           6




                                                                                                                6




                                                                                                                                                                             07
                                                                                    6
                        05




                                                05




                                                                                                                         06

                                                                                                                                   06




                                                                                                                                                           06
                                                                                               6
                                 5




                                                                                                                                            6
                                                                         -0




                                                                                                            l-0
                                                                                r- 0


                                                                                            -0
                               -0




                                                                                                                                          -0
                                      v-




                                                                                                                                                 v-
                                                      n-




                                                                                                    n-




                                                                                                                                                                 n-
                                                              b-




                                                                                                                                                                         b-
                        p-




                                              c-




                                                                                                                     g-

                                                                                                                               p-




                                                                                                                                                         c-
                                                                       ar




                                                                                        ay
                             ct




                                                                                                                                        ct
                                                                                                           Ju
                                                                               Ap
                                     No




                                                                                                                                                No
                                                     Ja




                                                                                                   Ju




                                                                                                                                                                Ja
                                                             Fe




                                                                                                                                                                        Fe
                   Se




                                             De




                                                                                                                    Au

                                                                                                                              Se




                                                                                                                                                        De
                                                                       M
                             O




                                                                                                                                        O
                                                                                        M




                                                                                        Period Ending
Update Schedule Review
Schedule Analysis – Sequencing Review
  Set up a Layout for Sequence
    Group by Phase or Location
     • Look for out-of-sequence work by trade

    Summarize to Phase
    Neck for non-work periods
    Review the sequence shown by the summary bars
  Set up a Layout for Responsibility
    Group by Responsibility
    Summarize to Responsibility
    Neck for non-work periods
    Review trade workload
Update Schedule Review
Schedule Analysis – Constructability
  Set up a Layout for weekly work
    Group by Early Start
    Order by Week
    Sort by ES, EF , TF
    Zoom in to weekly week
    Set Major Vertical Sight Lines to one week
    Expose column for Responsibility and Location
    Review work to be done weekly over the next few months
    for reasonableness
Update Schedule Review
Schedule Analysis (Slipped Completion)
  If slippage is due to the Owner, then a time extension
  is owed to the Contractor
  If slippage is due to the Contractor or his
  Subcontractors, then the Contractor owes the Owner a
  Recovery Schedule
  If the Owner causes a delay and the Sub or GC causes
  a concurrent delay, then a time extension is owed to
  the Contractor with no costs; and no recovery schedule
  required
  Understand excusable/inexcusable and
  compensable/non-compensable time
  Clean up all Owner caused delays each period
Update Schedule Review
Schedule Analysis (Slipped Completion)
  Identify previous period Critical Path (Longest Path)
  Use layout to compare against current schedule
  Identify current Critical Path & changes from previous
  Identify which activities slipped and drove progress
     Causal Activities drive progress
     Identify Start Gain or Loss
     Identify Production Gain or Loss
  Identify specific Causal Activity or Activities for delay
  Develop process for dealing with slipped completion
  before needed
Update Schedule Review
Schedule Analysis (Slipped Completion)
  Quantify start and production changes for each causal
  activity by working from the beginning of the period, using
  a standard layout with current baseline as schedule target
  Verify the totals
  Research the issues that caused the changes to the
  causal activities
     Interview Owner project admin team
     Review project documents; issue files, minutes,
     RFI/submittal logs, field reports, photographs
     This research is usually a discussion about reasonably
     current problems – quick, painless, and easy
Update Schedule Review
Schedule Analysis (Slipped Completion)
  Identify the Driving Issues that Affect the Causal Activities
  Assess Responsibility for Driving Issues
  Review Concurrency of Driving Issues– Can Be Delay and/or
  Acceleration/Mitigation
  Work Through Concurrent Driving Issues from the Beginning of
  the Period, Identifying first driving issue, establishing any
  concurrency with next driving issue
  Perform a Careful Concurrent Delay Analysis, Record in Clear
  Graphical Format
  Assign Responsibilities for All Driving Concurrent Delays
Update Schedule Review
Schedule Analysis (Slipped Completion)
  If Contractor team is responsible for any driving
  delays, or portions of Concurrent Delay, recovery
  schedule is required
    Predetermine how much slippage is allowed before
    requiring a recovery schedule
    Request recovery schedule immediately
  If Owner is Responsible for Any Driving Delays, or
  Portions of Concurrent Delay
    Discuss with Owner
    Request Time Impact Analysis from Contractor
    Collaborate and determine best approach; Owner
    Mitigation, paid Contractor Mitigation, or Time Extension
Update Schedule Review
Report should include general status summaries:
Update Schedule Review
Include Earned Value metrics in report
Update Schedule Review
Customized reports – Enterprise - myPrimavera
Update Schedule Review
Review - Standard Reporting Format
Schedule Review Comments
 Review provides claims avoidance opportunities
 Review identifies risks
 Always request recovery schedule when Contractor has
 slipped completion of any milestone
 Always resolve Owner caused delays to limit exposure to
 constructive acceleration delays
 Be reasonable, goal is to get a good schedule in place
 and update regularly
 Do not be confrontational or judgmental in report
 Watch trending of work slippage
 Owner should support report recommendations
 Provide a clear Discrepancy List necessary for
 Contractor to correct
Questions?
Properly Reviewing a Schedule
           March 20, 2008

          Chris Carson, PSP
               Project Controls Manager
                  Alpha Corporation
         chris.carson@alphacorporation.com

Mais conteúdo relacionado

Mais procurados

Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingChris Carson
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdfMy own
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfKarim Ragab
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسM Maged Hegazy, LLM, MBA, CCP, P3O
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2Chris Carson
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysisADITYA GHUMARE
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)Amr Morsy
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني M Maged Hegazy, LLM, MBA, CCP, P3O
 

Mais procurados (20)

50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only50 Planning Fundamentals V5.0 - procedures only
50 Planning Fundamentals V5.0 - procedures only
 
Delay Analysis and Concurrent Delay
Delay Analysis and Concurrent DelayDelay Analysis and Concurrent Delay
Delay Analysis and Concurrent Delay
 
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 MeetingDealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
Dealing With A Schedule That Cannot Be Approved - AACE 2012 Meeting
 
AWP-Education-Primer.pdf
AWP-Education-Primer.pdfAWP-Education-Primer.pdf
AWP-Education-Primer.pdf
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
DCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdfDCMA 14 Point Assessment by Karim Ragab.pdf
DCMA 14 Point Assessment by Karim Ragab.pdf
 
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامسأسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
أسس علم التخطيط في 50 سؤال وجواب - الاصدار الخامس
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
Eot claims hr__may2012
Eot claims hr__may2012Eot claims hr__may2012
Eot claims hr__may2012
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Baseline Schedules 2
Baseline Schedules 2Baseline Schedules 2
Baseline Schedules 2
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
International Delay Analysis Approaches
International Delay Analysis ApproachesInternational Delay Analysis Approaches
International Delay Analysis Approaches
 
CCP Course - Introduction.pdf
CCP Course - Introduction.pdfCCP Course - Introduction.pdf
CCP Course - Introduction.pdf
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Baseline schedule review and analysis
Baseline schedule review and analysisBaseline schedule review and analysis
Baseline schedule review and analysis
 
How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)How to perform time impact analysis (TIA)
How to perform time impact analysis (TIA)
 
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
خمسون سؤال في إدارة عقود التشييد أو المقاولات -الإصدار الثاني
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 

Destaque

UXSpeakeasy - How To Get A Great UX Job
UXSpeakeasy - How To Get A Great UX JobUXSpeakeasy - How To Get A Great UX Job
UXSpeakeasy - How To Get A Great UX JobPatrick Neeman
 
Introduction to Building Wireframes (with OmniGraffle)
Introduction to Building Wireframes (with OmniGraffle)Introduction to Building Wireframes (with OmniGraffle)
Introduction to Building Wireframes (with OmniGraffle)Erin 'Folletto' Casali
 
Service tax
Service taxService tax
Service taxhas10nas
 
Intro to radiography 1_2(NDT)
Intro to radiography 1_2(NDT)Intro to radiography 1_2(NDT)
Intro to radiography 1_2(NDT)Ravi Shekhar
 
Strategy Management of Ford Motor Company.
Strategy Management of Ford Motor Company.Strategy Management of Ford Motor Company.
Strategy Management of Ford Motor Company.Zahra Rezwana
 
Engaging Learners with Technology
Engaging Learners with TechnologyEngaging Learners with Technology
Engaging Learners with TechnologyDean Shareski
 
Deep Learning through Examples
Deep Learning through ExamplesDeep Learning through Examples
Deep Learning through ExamplesSri Ambati
 
What I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessWhat I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessJonathon Colman
 
Web Trends to Watch in 2014
Web Trends to Watch in 2014Web Trends to Watch in 2014
Web Trends to Watch in 2014David King
 
Fintech and Transformation of the Financial Services Industry
Fintech and Transformation of the Financial Services IndustryFintech and Transformation of the Financial Services Industry
Fintech and Transformation of the Financial Services IndustryRobin Teigland
 
Fracking The Social Web - 2014
Fracking The Social Web - 2014Fracking The Social Web - 2014
Fracking The Social Web - 2014John V Willshire
 
Mango Training for NGOs - key financial concepts and jargon
Mango Training for NGOs - key financial concepts and jargonMango Training for NGOs - key financial concepts and jargon
Mango Training for NGOs - key financial concepts and jargonTerry Lewis
 
Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Emiland
 
The NEW Way to Win Friends & Influence People (social media in events)
The NEW Way to Win Friends & Influence People (social media in events)The NEW Way to Win Friends & Influence People (social media in events)
The NEW Way to Win Friends & Influence People (social media in events)Lara McCulloch-Carter
 
Size exclusion chromatography
Size exclusion chromatographySize exclusion chromatography
Size exclusion chromatographyMandvi Shandilya
 
Sales management By Rajiv P. Kumar (Buddhist)
Sales management By Rajiv P. Kumar (Buddhist)Sales management By Rajiv P. Kumar (Buddhist)
Sales management By Rajiv P. Kumar (Buddhist)Dr. Rajiv P. Kumar
 
Operating Systems - File Management
Operating Systems -  File ManagementOperating Systems -  File Management
Operating Systems - File ManagementDamian T. Gordon
 

Destaque (20)

UXSpeakeasy - How To Get A Great UX Job
UXSpeakeasy - How To Get A Great UX JobUXSpeakeasy - How To Get A Great UX Job
UXSpeakeasy - How To Get A Great UX Job
 
Introduction to Building Wireframes (with OmniGraffle)
Introduction to Building Wireframes (with OmniGraffle)Introduction to Building Wireframes (with OmniGraffle)
Introduction to Building Wireframes (with OmniGraffle)
 
Service tax
Service taxService tax
Service tax
 
WCM (World Class Manufacturing)
WCM (World Class Manufacturing)WCM (World Class Manufacturing)
WCM (World Class Manufacturing)
 
Intro to radiography 1_2(NDT)
Intro to radiography 1_2(NDT)Intro to radiography 1_2(NDT)
Intro to radiography 1_2(NDT)
 
Strategy Management of Ford Motor Company.
Strategy Management of Ford Motor Company.Strategy Management of Ford Motor Company.
Strategy Management of Ford Motor Company.
 
Engaging Learners with Technology
Engaging Learners with TechnologyEngaging Learners with Technology
Engaging Learners with Technology
 
Mri brain anatomy Dr Muhammad Bin Zulfiqar
Mri brain anatomy Dr Muhammad Bin ZulfiqarMri brain anatomy Dr Muhammad Bin Zulfiqar
Mri brain anatomy Dr Muhammad Bin Zulfiqar
 
Deep Learning through Examples
Deep Learning through ExamplesDeep Learning through Examples
Deep Learning through Examples
 
BUSINESS QUIZ -Round 1
 BUSINESS QUIZ -Round 1 BUSINESS QUIZ -Round 1
BUSINESS QUIZ -Round 1
 
What I Carry: 10 Tools for Success
What I Carry: 10 Tools for SuccessWhat I Carry: 10 Tools for Success
What I Carry: 10 Tools for Success
 
Web Trends to Watch in 2014
Web Trends to Watch in 2014Web Trends to Watch in 2014
Web Trends to Watch in 2014
 
Fintech and Transformation of the Financial Services Industry
Fintech and Transformation of the Financial Services IndustryFintech and Transformation of the Financial Services Industry
Fintech and Transformation of the Financial Services Industry
 
Fracking The Social Web - 2014
Fracking The Social Web - 2014Fracking The Social Web - 2014
Fracking The Social Web - 2014
 
Mango Training for NGOs - key financial concepts and jargon
Mango Training for NGOs - key financial concepts and jargonMango Training for NGOs - key financial concepts and jargon
Mango Training for NGOs - key financial concepts and jargon
 
Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.Dear NSA, let me take care of your slides.
Dear NSA, let me take care of your slides.
 
The NEW Way to Win Friends & Influence People (social media in events)
The NEW Way to Win Friends & Influence People (social media in events)The NEW Way to Win Friends & Influence People (social media in events)
The NEW Way to Win Friends & Influence People (social media in events)
 
Size exclusion chromatography
Size exclusion chromatographySize exclusion chromatography
Size exclusion chromatography
 
Sales management By Rajiv P. Kumar (Buddhist)
Sales management By Rajiv P. Kumar (Buddhist)Sales management By Rajiv P. Kumar (Buddhist)
Sales management By Rajiv P. Kumar (Buddhist)
 
Operating Systems - File Management
Operating Systems -  File ManagementOperating Systems -  File Management
Operating Systems - File Management
 

Semelhante a Schedule Review

Schedule Development
Schedule DevelopmentSchedule Development
Schedule DevelopmentChris Carson
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project ManagementGoutama Bachtiar
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
IWP Timeline
IWP TimelineIWP Timeline
IWP TimelineScot Fyfe
 
Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05xtiandlr
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Managementtkrikau
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Scheduleshofiulalom
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & ControlingDarshana Viduranga
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time managementImran Jamil
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewDanielle Murphy
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls FrameworkReuben Gonzales
 
The project plan
The project planThe project plan
The project planVatsalaPG
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTSAJJAD KHUDHUR ABBAS
 
20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution
20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution
20200429 PMI NYC Meetup Agile Governance Ariel Partners for DistributionCraeg Strong
 

Semelhante a Schedule Review (20)

Schedule Development
Schedule DevelopmentSchedule Development
Schedule Development
 
Project Planning Scheduling
Project Planning SchedulingProject Planning Scheduling
Project Planning Scheduling
 
2015 Toronto Section Presentation
2015 Toronto Section Presentation2015 Toronto Section Presentation
2015 Toronto Section Presentation
 
Information Technology Project Management
Information Technology Project ManagementInformation Technology Project Management
Information Technology Project Management
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
IWP Timeline
IWP TimelineIWP Timeline
IWP Timeline
 
Remade Slides.pptx
Remade Slides.pptxRemade Slides.pptx
Remade Slides.pptx
 
Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05Sce vasg os_project_managementprocess_scw2010_05
Sce vasg os_project_managementprocess_scw2010_05
 
PMP Exam Prep - Time Management
PMP Exam Prep - Time ManagementPMP Exam Prep - Time Management
PMP Exam Prep - Time Management
 
AnAr project management overview
AnAr project management overviewAnAr project management overview
AnAr project management overview
 
Triple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & ScheduleTriple Constraints of Projects: Scope, Cost & Schedule
Triple Constraints of Projects: Scope, Cost & Schedule
 
Projrct Monitoring & Controling
Projrct   Monitoring  & ControlingProjrct   Monitoring  & Controling
Projrct Monitoring & Controling
 
A brief on project time management
A brief on project time managementA brief on project time management
A brief on project time management
 
AWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overviewAWIN presentation it's only logical-a scheduling overview
AWIN presentation it's only logical-a scheduling overview
 
Project Controls Framework
Project Controls FrameworkProject Controls Framework
Project Controls Framework
 
The project plan
The project planThe project plan
The project plan
 
Episode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENTEpisode 23 : PROJECT TIME MANAGEMENT
Episode 23 : PROJECT TIME MANAGEMENT
 
ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)ACH 216 Lecture 08 (Scheduling)
ACH 216 Lecture 08 (Scheduling)
 
20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution
20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution
20200429 PMI NYC Meetup Agile Governance Ariel Partners for Distribution
 
Project scheduling
Project schedulingProject scheduling
Project scheduling
 

Mais de Chris Carson

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIChris Carson
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop ConferenceChris Carson
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesChris Carson
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueChris Carson
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpChris Carson
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry SchedulingChris Carson
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodChris Carson
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion SchedulesChris Carson
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotChris Carson
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminChris Carson
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationChris Carson
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesChris Carson
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...Chris Carson
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesChris Carson
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful MediationChris Carson
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule RevisionsChris Carson
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex ProjectChris Carson
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesChris Carson
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - AirportChris Carson
 

Mais de Chris Carson (20)

Favorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEIFavorite Delay Analysis Methodologies Town Hall SEI
Favorite Delay Analysis Methodologies Town Hall SEI
 
Use Of Schedule Logs 2012 Pmi Scop Conference
Use Of Schedule Logs   2012 Pmi Scop ConferenceUse Of Schedule Logs   2012 Pmi Scop Conference
Use Of Schedule Logs 2012 Pmi Scop Conference
 
Pmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation SchedulesPmicos 2011 Review And Analysis Of Mitigation Schedules
Pmicos 2011 Review And Analysis Of Mitigation Schedules
 
Mitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned ValueMitigation And Performance Recovery Using Earned Value
Mitigation And Performance Recovery Using Earned Value
 
Roadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls PpRoadmap To World Class Project Controls Pp
Roadmap To World Class Project Controls Pp
 
Types Of Industry Scheduling
Types Of Industry SchedulingTypes Of Industry Scheduling
Types Of Industry Scheduling
 
Use Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis MethodUse Of A Claims Triage Workshop To Choose An Analysis Method
Use Of A Claims Triage Workshop To Choose An Analysis Method
 
Early Completion Schedules
Early Completion SchedulesEarly Completion Schedules
Early Completion Schedules
 
Can A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does NotCan A Subcontractor Have CP Delay When The Gc Does Not
Can A Subcontractor Have CP Delay When The Gc Does Not
 
Schedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract AdminSchedule-Centric View Of Contract Admin
Schedule-Centric View Of Contract Admin
 
Design &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan PresentationDesign &amp; Development Of A Schedule Management Plan Presentation
Design &amp; Development Of A Schedule Management Plan Presentation
 
Presentation Classification Of Schedule Types
Presentation Classification Of Schedule TypesPresentation Classification Of Schedule Types
Presentation Classification Of Schedule Types
 
Claims Triage
Claims TriageClaims Triage
Claims Triage
 
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...Using Symptoms To Develop Appropriate Claims Avoidance Documentation   Wpl We...
Using Symptoms To Develop Appropriate Claims Avoidance Documentation Wpl We...
 
Mitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel SchedulesMitigation Of Risks In Using Parallel Schedules
Mitigation Of Risks In Using Parallel Schedules
 
How To Structure A Successful Mediation
How To Structure A Successful MediationHow To Structure A Successful Mediation
How To Structure A Successful Mediation
 
2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions2010 AACEi Great Debate - Approval of Schedule Revisions
2010 AACEi Great Debate - Approval of Schedule Revisions
 
Planning A Complex Project
Planning A Complex ProjectPlanning A Complex Project
Planning A Complex Project
 
Mitigation of Risk in Dual Schedules
Mitigation of Risk in Dual SchedulesMitigation of Risk in Dual Schedules
Mitigation of Risk in Dual Schedules
 
Innovative Program Delivery - Airport
Innovative Program Delivery - AirportInnovative Program Delivery - Airport
Innovative Program Delivery - Airport
 

Último

Call Girls Somajiguda Sarani 7001305949 all area service COD available Any Time
Call Girls Somajiguda Sarani 7001305949 all area service COD available Any TimeCall Girls Somajiguda Sarani 7001305949 all area service COD available Any Time
Call Girls Somajiguda Sarani 7001305949 all area service COD available Any Timedelhimodelshub1
 
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...First NO1 World Amil baba in Faisalabad
 
Call Girls Sanand 7397865700 Ridhima Hire Me Full Night
Call Girls Sanand 7397865700 Ridhima Hire Me Full NightCall Girls Sanand 7397865700 Ridhima Hire Me Full Night
Call Girls Sanand 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...Amil Baba Company
 
Gripping Adult Web Series You Can't Afford to Miss
Gripping Adult Web Series You Can't Afford to MissGripping Adult Web Series You Can't Afford to Miss
Gripping Adult Web Series You Can't Afford to Missget joys
 
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...Amil baba
 
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts Service
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts ServiceVip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts Service
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts ServiceApsara Of India
 
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].pp
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].ppGRADE 7 NEW PPT ENGLISH 1 [Autosaved].pp
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].ppJasmineLinogon
 
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full Night
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full NightCall Girls Sabarmati 7397865700 Ridhima Hire Me Full Night
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170Sonam Pathan
 
Call Girls CG Road 7397865700 Independent Call Girls
Call Girls CG Road 7397865700  Independent Call GirlsCall Girls CG Road 7397865700  Independent Call Girls
Call Girls CG Road 7397865700 Independent Call Girlsssuser7cb4ff
 
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCRdollysharma2066
 
Call Girls SG Highway 7397865700 Ridhima Hire Me Full Night
Call Girls SG Highway 7397865700 Ridhima Hire Me Full NightCall Girls SG Highway 7397865700 Ridhima Hire Me Full Night
Call Girls SG Highway 7397865700 Ridhima Hire Me Full Nightssuser7cb4ff
 
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...Amil Baba Company
 
(伦敦大学毕业证学位证成绩单-PDF版)
(伦敦大学毕业证学位证成绩单-PDF版)(伦敦大学毕业证学位证成绩单-PDF版)
(伦敦大学毕业证学位证成绩单-PDF版)twfkn8xj
 
Call Girl Price Andheri WhatsApp:+91-9833363713
Call Girl Price Andheri WhatsApp:+91-9833363713Call Girl Price Andheri WhatsApp:+91-9833363713
Call Girl Price Andheri WhatsApp:+91-9833363713Sonam Pathan
 
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Service
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls ServiceCall Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Service
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Servicedollysharma2066
 
Zoom In Game for ice breaking in a training
Zoom In Game for ice breaking in a trainingZoom In Game for ice breaking in a training
Zoom In Game for ice breaking in a trainingRafik ABDI
 
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...Amil baba
 

Último (20)

Call Girls Somajiguda Sarani 7001305949 all area service COD available Any Time
Call Girls Somajiguda Sarani 7001305949 all area service COD available Any TimeCall Girls Somajiguda Sarani 7001305949 all area service COD available Any Time
Call Girls Somajiguda Sarani 7001305949 all area service COD available Any Time
 
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
Authentic No 1 Amil Baba In Pakistan Authentic No 1 Amil Baba In Karachi No 1...
 
Call Girls Sanand 7397865700 Ridhima Hire Me Full Night
Call Girls Sanand 7397865700 Ridhima Hire Me Full NightCall Girls Sanand 7397865700 Ridhima Hire Me Full Night
Call Girls Sanand 7397865700 Ridhima Hire Me Full Night
 
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...
Amil baba in Pakistan amil baba Karachi amil baba in pakistan amil baba in la...
 
Gripping Adult Web Series You Can't Afford to Miss
Gripping Adult Web Series You Can't Afford to MissGripping Adult Web Series You Can't Afford to Miss
Gripping Adult Web Series You Can't Afford to Miss
 
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...
NO1 Certified Black magic/kala jadu,manpasand shadi in lahore,karachi rawalpi...
 
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts Service
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts ServiceVip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts Service
Vip Udaipur Call Girls 9602870969 Dabok Airport Udaipur Escorts Service
 
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].pp
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].ppGRADE 7 NEW PPT ENGLISH 1 [Autosaved].pp
GRADE 7 NEW PPT ENGLISH 1 [Autosaved].pp
 
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full Night
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full NightCall Girls Sabarmati 7397865700 Ridhima Hire Me Full Night
Call Girls Sabarmati 7397865700 Ridhima Hire Me Full Night
 
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170
Call Girls Near Taurus Sarovar Portico Hotel New Delhi 9873777170
 
Call Girls CG Road 7397865700 Independent Call Girls
Call Girls CG Road 7397865700  Independent Call GirlsCall Girls CG Road 7397865700  Independent Call Girls
Call Girls CG Road 7397865700 Independent Call Girls
 
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR
8377087607 Full Enjoy @24/7 Call Girls in Patel Nagar Delhi NCR
 
Call Girls SG Highway 7397865700 Ridhima Hire Me Full Night
Call Girls SG Highway 7397865700 Ridhima Hire Me Full NightCall Girls SG Highway 7397865700 Ridhima Hire Me Full Night
Call Girls SG Highway 7397865700 Ridhima Hire Me Full Night
 
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...
Real NO1 Amil baba in Faisalabad Kala jadu in faisalabad Aamil baba Faisalaba...
 
Environment Handling Presentation by Likhon Ahmed.pptx
Environment Handling Presentation by Likhon Ahmed.pptxEnvironment Handling Presentation by Likhon Ahmed.pptx
Environment Handling Presentation by Likhon Ahmed.pptx
 
(伦敦大学毕业证学位证成绩单-PDF版)
(伦敦大学毕业证学位证成绩单-PDF版)(伦敦大学毕业证学位证成绩单-PDF版)
(伦敦大学毕业证学位证成绩单-PDF版)
 
Call Girl Price Andheri WhatsApp:+91-9833363713
Call Girl Price Andheri WhatsApp:+91-9833363713Call Girl Price Andheri WhatsApp:+91-9833363713
Call Girl Price Andheri WhatsApp:+91-9833363713
 
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Service
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls ServiceCall Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Service
Call Girls In Moti Bagh (8377877756 )-Genuine Rate Girls Service
 
Zoom In Game for ice breaking in a training
Zoom In Game for ice breaking in a trainingZoom In Game for ice breaking in a training
Zoom In Game for ice breaking in a training
 
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...
NO1 WorldWide Amil baba in pakistan Amil Baba in Karachi Black Magic Islamaba...
 

Schedule Review

  • 1. Properly Reviewing a Schedule March 20, 2008 Chris Carson, PSP Director, Project Controls Alpha Corporation chris.carson@alphacorporation.com
  • 2. Properly Reviewing a Schedule Goals Confirm that schedule is reasonable and attainable Understand Contractor’s Means & Methods Establish a good baseline for monitoring Verify durations Verify logic and sequencing Identify claims positioning issues Identify risks in schedule and assumptions Document concerns
  • 3. Schedule Review Baseline Schedule Review Review Scheduling Specification Confirm Submittal Completeness Gain Familiarity with Project Import Schedule & Verify Review Schedule Architecture Review Schedule Construction Review Narrative Review Sequencing Evaluate Metrics & Statistics Perform Analysis Write Report
  • 4. Baseline Schedule Review Review Scheduling Specification Section 01320 or 01.32.16 CPM Network requirements Check Related Specifications Duration definitions & restrictions Sections or Special Provisions Initial schedule submission Software requirements Full detailed project schedule Data exchange requirements (baseline) submission Master dictionaries/reports Schedule updates Activity Code requirements Delays & time extensions ID Coding requirements Notification Requirements Preconstruction meeting Early completion schedules Qualifications of scheduler Final as-built submittal Required submittal contents Cost & Resource loading Owner mandated milestone Narrative Requirements treatment Prohibitions on manipulation Float ownership
  • 5. Schedule Specification Use a checklist to capture specification requirements Identify time allowed for review and response
  • 6. Baseline Schedule Review Gain Familiarity with Project Review Plans & Specifications Review specialty specs like DOT Bridge & Road Manual Visit job site Review construction methodology or unusual techniques Bring in expertise if necessary
  • 7. Baseline Schedule Review Confirm Submittal Completeness Compare to schedule specification requirements Notify Contractor immediately if not complete Do not start review until submittal is complete Typical missing items: Schedule Narrative Electronic File Explanation of Calendars, Lags, Activity Codes, Constraints, Resources, Costs Milestones and Milestone definitions Consider two part review if costs or resources are missing
  • 8. Baseline Schedule Review Import Schedule & Verify Keep original submittal file, make copy to review Should review in original software if possible Recognize that there are issues with import in many software packages Develop checklist to identify potential import issues Example - Primavera P3 to P5 import : In P3, Lags are driven by Predecessor Calendar In P5, Lags can be driven by choice of Calendars Default P5 setting to drive Lags is not the Predecessor Calendar Must verify that imported schedule used to analyze is identical to original submitted schedule
  • 9. Baseline Schedule Review Develop a checklist for reviews
  • 10. Baseline Schedule Review Review Schedule Architecture Check Schedule Rules & Settings Recalculate Schedule Review Organizational Tools Review Schedule Construction Evaluate Activities Review Logic Evaluate Critical Path
  • 11. Baseline Schedule Review Review Schedule Architecture Check Schedule Rules & Settings Retained Logic vs. Progress Override • Won’t affect Baseline, but could cause optimistic predictions during updates Resource and Cost rules • Estimate to Complete setting might allow Estimate at Completion to change Understand all settings and how they affect Earned Value & reports Identify how Critical Path is calculated • Longest Path • Total Float value
  • 12. Baseline Schedule Review Review Schedule Architecture Recalculate Schedule, ensure no change Check NTP and Completion dates Check all interim Milestone dates Review Organizational Tools • Review Activity Code Dictionaries • Review Resource Code Dictionaries • Review Calendars • Review WBS
  • 13. Baseline Schedule Review Review Schedule Construction Evaluate Activities Sort by Activity Description For good guidelines, see AACE publication No. 23R-02, Recommended Practice for Identification of Activities See if descriptions are consistent and unique Ensure all items that could delay project are represented by activities, such as procurement and other admin work Compare descriptions for reasonable and comparable Original Durations Confirm that descriptions capture full scope of work Sort by Original Duration Check for specification maximum times Check for reasonable ODs
  • 14. Baseline Schedule Review Review Schedule Construction Review Logic See AACE publication No. 24R-03, Recommended Practice for Developing Activity Logic for guidelines Check open-ended relationships • Should only be two; start and end • Reduces accuracy of network calculations • Watch for “dangling” activities: SS or FS with negative Lag which leave Predecessor open-ended upon updates Evaluate relationships • Check on all Lags • Filter by trade, check same-trade relationships • Filter by Contractor, check those relationships
  • 15. Baseline Schedule Review Review Schedule Construction Evaluate Critical Path Is it reasonable and customary? Does it start at beginning of project and run to completion? Does it have an appropriate level of detail? Are there manipulations driving the Critical Path? Float sequestering where everything is critical • Manipulation where Critical Path runs inappropriately through all • owner responsibilities Critical Path is the only highly detailed string of activities in the • project Nothing is critical due to heavy constraint use • Numerous lags, perhaps not identified, inserted in the Critical Path, • forcing it through specific activities Is there weather planning included in Critical Path activities or will • any adverse weather cause slippage?
  • 16. Baseline Schedule Review Review Schedule Construction Evaluate Near Critical Paths How much work is just off Critical Path? Check Longest Path and lowest Total Float paths (Recommend review of TF < ½ Reporting Period) Sort by Total Float Check reasonableness of high float items Is there a consistent range of TF? Lots of high TF activities means underdeveloped logic All low TF suggests inappropriate logic Sort by Late Start This is the worst case expectation of work flow Start at end of schedule & see if reasonable Organize by Late Start, Order Week Ascending, see if the amount of work planned each week is possible Check trade stacking, can they fit into spaces?
  • 17. Baseline Schedule Review Review Schedule Construction Sort by Early Start Organize by Early Start, Order Week Ascending, again see if the amount of work planned each week is reasonable Are there trades stacking up? Organize by Early Start, Sort by Late Start Summarize to Early Start, review overlaps between weeks Specifically review strong overlaps (points out missing relationships) Helps focus on small segments of project working concurrently
  • 18. Baseline Schedule Review Review Schedule Construction Review resources Check for resource “soft” logic used to control flow of manpower from area to area Schedules without reasonable soft logic will likely show lots of high Total Float values Overuse of soft logic can sequester Total Float and force Critical Path Durations should be resource-based; that is calculated by production rate x quantity, so resource planning must be taken into account
  • 19. Baseline Schedule Review Review Written Narrative At a minimum, Narrative should identify sequence and work flow Identify phasing Provide the Area Designation Plan Summary of the work Explain plan for construction Identify potential problems or risks Summarize the Critical Path; does it match the schedule? Identify all Milestones Explain schedule components: Activity ID Coding, Activity Coding, Resources, Lags, Constraints, unusual logic relationships Adverse weather planning
  • 20. Baseline Schedule Review Review Sequencing Use Narrative as guide Check for missing Activity Codes that may not include work in sequences Choose layout with sequencing Compare to specification requirements Summarize to sequences, then drill into each sequence Check reasonableness of logic Check overlap of sequences Check other layouts
  • 21. Baseline Schedule Review Generate Metrics Counts Activities by type (procurement, construction, Owner responsibilities) Activities by trade (Section number, work package) Activities on Longest Path Relationships • Total by types • Lags Constraints Verify appropriate & consistent level of detail
  • 22. Baseline Schedule Review Data retrieval from schedule Develop data crunching methodologies Master layouts with filters Export filters to export to Excel or Lotus Standard Pivot tables Input/output worksheet spreadsheets Graphical depictions for reasonableness • Histogram distributions • Tables • Charts
  • 23. Baseline Schedule Review Use Pivot Tables or other data collecting & collating methodologies
  • 24. Baseline Schedule Review Generate Statistics Recommend use of Pivot Tables Use statistics to identify inconsistencies Ratio work/non-work activities Ratio trade work Ratio durations (helps spot partial overdevelopment) Ratio work in each sequence Percentage of activities on Longest Path and Near Critical Paths
  • 25. No. Activities H am m oc ks an d A sp Mile C ha st le 0 50 100 150 200 250 300 on ar lt P es in la g c an em d en G ru t bb i D D em ng E ro em o si ob litio on ili n & za S ed E tion im lec en tri t C ca on l tro l G La ra d M nd ing sc at a er ia pin g lD M e S to aint Mo live ry rm en b D an iliza ra ce tio in / S of n to Tra Distribution of Activities rm ffi Feature of Work Se c w S er tri So pi un S dw ub ng m / P al l itt proportion detail in trade activities) al aint S id / A ing U ewa ppr nd ov er lk / Baseline Schedule Review al M gr ou ed nd ia n U til iti Histogram of Activity Work Scope (showing out of es
  • 26. Baseline Schedule Review Perform Analysis Review types of constraints Remove constraints, one by one Look at results with each removal and identify effects Evaluate total number of constraints Date constraints; should be minimum and only those dictated by Owner Don’t allow mandatory constraints which sequester float Logic constraints; watch for float removal constraints like Zero Total or Free Float Network should be logic driven, not constraint driven Constraints can cause multiple Critical Paths Requires analysis of each path in baseline and updates
  • 27. Baseline Schedule Review Perform Analysis With Cost Loading, use Earned Value Review S-Curve for reasonableness Don’t use Banana Curves, the Late Start curve provides a deceptive lower performance range Remember that this sets the baseline for monitoring the progress
  • 28. Baseline Schedule Review Review shape of Earned Value S-Curve (BCWS) Might point out front-end loading or unreasonable plan May show too aggressive expectations for billing
  • 29. Baseline Schedule Review Write Report Organize checklist to match report Provide Executive Summary Provide recommendations for Best Practices improvement in schedule Provide Deficiency List Require response to Deficiency List Do not dictate means and methods Keep report professional without addressing assumed motivation for schedule features Don’t say, “Use of so many constraints is clearly a devious attempt to pervert Critical Path”
  • 30. Update Schedule Review General process similar to Baseline Review Scheduling Specification Review Plans & Specifications Confirm Submittal Completeness Import Schedule & Verify Data Validation Review Schedule Architecture Review Schedule Construction Review Narrative Review Sequencing Evaluate Statistics Write Report
  • 31. Update Schedule Review Update Schedule Review Same steps as Baseline Review Review Scheduling Specification Review Plans & Specifications Confirm Submittal Completeness Import Schedule & Verify Data Validation – must be done with each update Same steps as Baseline Review Review Schedule Architecture Review Schedule Construction Review Narrative
  • 32. Update Schedule Review Data Validation Field information – should have been kept on a daily basis Verify Actual Start Dates Verify Actual Finish Dates Verify Predicted Finish for any activity started but not finished Verify Percent Complete if schedule is cost loaded Prefer Remaining Duration, not Percent Complete, for time reporting • Superintendents generally cannot provide accurate Percent Complete Data validation is very important
  • 33. Update Schedule Review Data Validation Office information Watch status of buyout process; purchase orders & subcontracts – what is not bought out Verify Submittal & Approval status Verify status of administrative tasks • Utility paperwork status • Permits – site, building, right-of-way, Health Department • Environmental releases, etc. Verify status of materials fabrication and order time - “Lead Time” – this is an area where schedule manipulation can occur
  • 34. Update Schedule Review Data Validation Owner information Independently verify status of Owner controlled activities • Owner utility applications & progress Electricity - Gas service - Water & sewer - Telephone - Cable or data - Security system - Delivery dates for Owner furnished equipment • Other Owner contractual work • Verify coordination with Owner work •
  • 35. Update Schedule Review Calculate Schedule Ensure software setting is Retained Logic Verify Data Date is correct date Calculate schedule Check for Out-of-Sequence Work Change setting temporarily to Progress Override If the completion date changes significantly, then there is a lot of out-of-sequence work needing correcting If minimal change, no significant out-of-sequence work Change the setting back to Retained Logic (default)
  • 36. Update Schedule Review Prepare for Schedule Analysis Use standard Layout with comparison to last update Check for slippage in Substantial Completion date or Milestones If no slippage, project predicts on time completion Perform standard analysis, use standard reports and • publish If slippage, will need additional analysis of slipped schedule
  • 37. Update Schedule Review Standard Schedule Analysis (On-Time Completion) Three basic components to monitor Critical Path progress • Slippage will directly delay work Near Critical progress • Slippage could easily overtake Critical Path and delay work Non-Critical (“mass volume”) work • Lack of progress will cause trade stacking and over- crowding of work space at a later date • Could easily allow too much work for areas available • Good place to use Earned Value for monitoring • Can use Float Dissipation to monitor • Can use other methods to monitor
  • 38. Update Schedule Review Standard Schedule Analysis (On-Time Completion) Two types of paths to watch Critical Path to end of project (Substantial Completion) Critical Path to Interim Milestones Critical Path to end of project Ideally use Longest Path Monitor minimum Total Float value Critical Path as well Critical Paths to Interim Milestones One path per each Milestone to watch This can be time consuming, but necessary Slippage in interim Milestones and achieving final Milestone can be basis for acceleration claims
  • 39. Update Schedule Review Standard Schedule Analysis (On-Time Completion) Identify current period Critical Path (Longest Path) Identify current period Near-Critical activities Identify Milestones to review Owner mandated only Watch particularly for Milestones with Liquidated Damages Identify historical trends and statistics (mass volume) Graphics are powerful in the report Identify resource problems or concerns Identify risks, either continuing or new
  • 40. Update Schedule Review Historical Comparisons & Statistics Run Tipper (TPR) reports Run Total Float dissipation (Erosion of Float) reports Run Free Float dissipation reports (monitors disruption) Review Out-of-Sequence work by trade Which trade is causing most out-of-sequence work? Are they working out-of-sequence due to other trade failures to complete? Or working in open areas without regard for planning? Run Resource reports Are appropriate resources working? Check against Tipper reports
  • 41. Update Schedule Review Review (TPR) Time Performance Ratio trending (AD/OD) Time Performance Ratio 8.00 7.00 6.00 5.00 TPR 4.00 3.00 2.00 1.00 0.00 31- 30- 31- 28- 31- 30- 31- 30- 31- 31- 30- 31- 30- 31- 31- 28- Total Oct Nov- Jan- Feb- Mar- Apr- May- Jun- Jul-06 Aug- Sep- Oct- Nov- Dec- Jan- Feb- 05 06 06 06 06 06 06 06 06 06 06 06 07 07 Period Ending
  • 42. Update Schedule Review Review (TPR) Time Performance Ratio trending by Milestone by Responsible Contractor (AD/OD)
  • 43. Update Schedule Review Review (TPR) Time Performance Ratio per trade (AD/OD) Time Performance Ratio 12.0 10.0 8.0 TPR 6.0 4.0 2.0 0.0 ev s ry s ry nt ws El cal e / W fing l E q h es s rk in ca g or al et nt on m Fu me wo in do ni tri et at cr pe oo Ad s ish as ha ec te M ni p on in R ar ui Fi M Si rn ec El C C M rs oo D Type of Work
  • 44. Update Schedule Review Review (TPR) Time Performance Ratio trending by trade (AD/OD) Time Performance Ratio (Concrete) 8.00 7.00 6.00 5.00 TPR 4.00 3.00 2.00 1.00 0.00 6 07 7 6 6 l 6 ta -0 -0 0 0 -0 n- To p- c- ov eb ct Ja Se De -O -N -F - - - 31 31 30 28 30 31 Period Ending
  • 45. Update Schedule Review Trade Monitoring by Crew – no resource loading available, load single crew resources into activities AMP Terminals Yard Project
  • 46. Update Schedule Review Watch erosion of float, do not let it continue Print by trade when assessing available resources • Relative Total Float of Area Completion Milestones 200 150 Relative Total Float SCAC RCA 100 WH MCAC/CCAC Utility Bldg NBB MSGQ 50 WBN NOB Subst Comp 0 22 BL 08 09 10 11 12 13 14 15 16 17 18 19 20 21 23 24 25 SI KN KN KN KN KN KN KN KN KN KN KN KN KN KN KN KN SS -50
  • 47. Update Schedule Review Earned Value Management Reporting Earned Value and Actual Costs • Compared against Planned Value • Ciudad Juarez Earned Value Project Update Earned Value $70,000,000.00 $60,000,000.00 $50,000,000.00 B illing Value $40,000,000.00 Early Curve Late Curve $30,000,000.00 Actual Curve $20,000,000.00 $10,000,000.00 $0.00 De v-0 5 De v-0 6 De -0 7 Fe 0 6 Ju 0 6 Fe -0 7 Ju 0 7 Fe -0 8 M - 06 A p - 06 A u l-06 M 07 A p - 07 A u l-07 M 08 8 O - 05 J a -0 5 M r- 06 S e - 06 O - 06 J a -0 6 M r- 07 S e - 07 O - 07 Ja 07 J u -06 J u -07 No - 05 No - 06 No - 07 -0 n- n- n- b- b- c- v n n ar ar ar b c c p g p g p ay ay ct ct ct Se Period Ending
  • 48. Update Schedule Review Earned Value Management Reporting SPI and CPI metrics • Watch trending • Schedule Performance Index 1.20 1.00 S PI (E V/P V) 0.80 0.60 0.40 0.20 0.00 05 06 06 06 07 06 6 6 07 6 05 05 06 06 06 6 5 6 -0 l-0 r- 0 -0 -0 -0 v- v- n- n- n- b- b- p- c- g- p- c- ar ay ct ct Ju Ap No No Ja Ju Ja Fe Fe Se De Au Se De M O O M Period Ending
  • 49. Update Schedule Review Schedule Analysis – Sequencing Review Set up a Layout for Sequence Group by Phase or Location • Look for out-of-sequence work by trade Summarize to Phase Neck for non-work periods Review the sequence shown by the summary bars Set up a Layout for Responsibility Group by Responsibility Summarize to Responsibility Neck for non-work periods Review trade workload
  • 50. Update Schedule Review Schedule Analysis – Constructability Set up a Layout for weekly work Group by Early Start Order by Week Sort by ES, EF , TF Zoom in to weekly week Set Major Vertical Sight Lines to one week Expose column for Responsibility and Location Review work to be done weekly over the next few months for reasonableness
  • 51. Update Schedule Review Schedule Analysis (Slipped Completion) If slippage is due to the Owner, then a time extension is owed to the Contractor If slippage is due to the Contractor or his Subcontractors, then the Contractor owes the Owner a Recovery Schedule If the Owner causes a delay and the Sub or GC causes a concurrent delay, then a time extension is owed to the Contractor with no costs; and no recovery schedule required Understand excusable/inexcusable and compensable/non-compensable time Clean up all Owner caused delays each period
  • 52. Update Schedule Review Schedule Analysis (Slipped Completion) Identify previous period Critical Path (Longest Path) Use layout to compare against current schedule Identify current Critical Path & changes from previous Identify which activities slipped and drove progress Causal Activities drive progress Identify Start Gain or Loss Identify Production Gain or Loss Identify specific Causal Activity or Activities for delay Develop process for dealing with slipped completion before needed
  • 53. Update Schedule Review Schedule Analysis (Slipped Completion) Quantify start and production changes for each causal activity by working from the beginning of the period, using a standard layout with current baseline as schedule target Verify the totals Research the issues that caused the changes to the causal activities Interview Owner project admin team Review project documents; issue files, minutes, RFI/submittal logs, field reports, photographs This research is usually a discussion about reasonably current problems – quick, painless, and easy
  • 54. Update Schedule Review Schedule Analysis (Slipped Completion) Identify the Driving Issues that Affect the Causal Activities Assess Responsibility for Driving Issues Review Concurrency of Driving Issues– Can Be Delay and/or Acceleration/Mitigation Work Through Concurrent Driving Issues from the Beginning of the Period, Identifying first driving issue, establishing any concurrency with next driving issue Perform a Careful Concurrent Delay Analysis, Record in Clear Graphical Format Assign Responsibilities for All Driving Concurrent Delays
  • 55. Update Schedule Review Schedule Analysis (Slipped Completion) If Contractor team is responsible for any driving delays, or portions of Concurrent Delay, recovery schedule is required Predetermine how much slippage is allowed before requiring a recovery schedule Request recovery schedule immediately If Owner is Responsible for Any Driving Delays, or Portions of Concurrent Delay Discuss with Owner Request Time Impact Analysis from Contractor Collaborate and determine best approach; Owner Mitigation, paid Contractor Mitigation, or Time Extension
  • 56. Update Schedule Review Report should include general status summaries:
  • 57. Update Schedule Review Include Earned Value metrics in report
  • 58. Update Schedule Review Customized reports – Enterprise - myPrimavera
  • 59. Update Schedule Review Review - Standard Reporting Format
  • 60. Schedule Review Comments Review provides claims avoidance opportunities Review identifies risks Always request recovery schedule when Contractor has slipped completion of any milestone Always resolve Owner caused delays to limit exposure to constructive acceleration delays Be reasonable, goal is to get a good schedule in place and update regularly Do not be confrontational or judgmental in report Watch trending of work slippage Owner should support report recommendations Provide a clear Discrepancy List necessary for Contractor to correct
  • 61. Questions? Properly Reviewing a Schedule March 20, 2008 Chris Carson, PSP Project Controls Manager Alpha Corporation chris.carson@alphacorporation.com