INTERNSHIP PRESENTATION ON
BRIGADE Lake Front, BANGALORE
CHELINATH B
AH15019
PGP ACM 29 (2015-17)
NICMAR, HYDERABAD
Project Details
• Name of the Project : Brigade Lakefront (Project Code: 2895)
• Scope of wok : Construction of sub-structure & super
Structure work of proposed Residential
towers A,B,C,D,E,F and G
(AMBER BLOCK) & H,I,J,K,L,M and N
(BLUEBLOCK)
• Location : Whitefield, Bangalore
• Client : Brigade Enterprises Ltd.
• Contractor : Simplex Infrastructures Ltd.
• Architect : RSP Design Consultants(India) Pvt Ltd.
• Structural Consultant : Vintech Consultants
• Type of contract : Item Rate Contract
• Free Issue Materials : RMC, Cement, Reinforcement steel, S-
form
• Defect liability Period :12 months from completion of project
Contract Details
• LOI issued Date : 06-Sept-2013(Amber block)
13-Mar-2014(Blue Block)
• Contractual Commencement : 16-Sept-2013(Amber Block)
15-Mar-2014(Blue Block)
• Actual Commencement : 01-Oct-2013(Amber Block)
15-Mar-2014(Blue Block)
• Contract Value : Rs.38.22 Cr(Amber Block)
Rs.48.20 Cr(Blue Block)
• Contract Period : 19 months + 2 months (Amber Block)
21 months + 2 months (Blue Block )
• Mobilization Advance : 278 Lakhs (Amber Block)
351 Lakhs (Blue Block)
• Retention Money : 2.5% of total value of work done from
each RA Bill
• RA Bill Payments : 50% of bill value as within 15
days from the date of submission of
Bill & Balance 50% after Verification of
Bills in next 15 days.
Plan & Facilities
Type of Residence
•2, 3 & 4 Bedroom Luxury Apartments
(2 Bedroom: 107 - 134 sqm; 3 Bedroom: 154
- 259 sqm; 4 Bedroom: 312 sqm)
Budget Range
•Rs. 77 Lakh Onwards (Inclusive of car-park
and exclusive of statutory expenses)
Facilities
•2787 sqm Clubhouse with rooftop
swimming pool
•Basketball, Tennis and Cricket Pitch
•Large open green spaces
•Children's play area and Senior Citizens
court
Note: 1 square metre = 10.764 square feet
Project Execution Details
Phase I: North & Central parcel (Amber & Blue block)
19 months structural work + 2 months finishing works for North Parcel
21 months structural work + 2 months finishing works for Central Parcel
•North parcel: 2B+G+14 - 7 towers (A-G)
o Towers A-F constructed using MIVAN formwork
o Tower G constructed fully using conventional formwork
•Central parcel: 2B+G+14 - 7 towers (H-N)
oConventional formwork is used in all towers up to Ground floor
oS- formwork is used in floors from 1-14.
Phase II: South parcel (Crimson block)
•2B+G+14 – 6 Towers (O-T)
•23 months for 2 towers, 25 months for 2 towers & 28 months for 2 towers
•Additional 2 months for finishing works.
Activities done & Learnings during training
 Planning Department
• Concrete Pour Delay Analysis : PUMP (1405D) Tower-K 7th floor -
150m3
Pump Capacity 55m3 per hour
Total time for completion of 150m3: 17 hours
Total operating time: 514mins or 8.57 hours
Total delay time: 8.43 hours
Overall Efficiency of the process: 33.96%
Reasons for delay : Delay in pumping due to
lack of RMC trucks
Delay in vibration
Delay in shifting pipes
Delay in loading
Delay by the driver
Pump failure
Concrete Placement @ F Wing 14th floor by Crane and Bucket
• The concreting process with the help of tower crane was also observed in detail.
• The activity with highest Coefficient of Variation should be taken care to
reduce
the delay in concreting process.
Average 08:33 29:30 37:10 17:30 44:10 12:40 28:00 02:40 41:00
SD 01:01 09:55 21:03 06:21 25:36 18:25 09:52 00:31 17:39
CV% 12 33.7 56.7 36.3 15.6 145.4 35.3 19.4 35.2
Cycle
Duration
RMC
Delay
Bucket
Filling
Crane
Delay @
RMC
RMC to
14F
Placeme
nt Delay
Place
ment
Crane Delay
@14F
14F to
RMC
Pump efficiency
• There were 4 pumps available on site for placement of concrete.
• The cost per cubic meter of each pump was calculated separately.
• The pump with more cost per cum was removed from site as it was nearing its
salvage value.
Cost per Cum(from April, 16 to June, 16)
Equipm
ent
Concre
te Qty
Deployement
/ Hire Charges
Diesel &
Mobil
Cost
Operator &
Helper
Salary
Other
Costs
Repairing
Cost
Total Cost
Cost/cu
m
1407 6592 350000 213817 60000 7549 35794 667160 101.21
1405 5914 300000 160047 60000 27090 42796 589933 99.75
350 644 150000 44914 60000 29995 129164 414074 642.47
Sany 1849 125000 89323 60000 61415 103720 439458 237.67
350000
300000
150000
125000
213817
160047
44914
89323
60000
60000
60000
60000
7549
27090
29995
61415
35794
42796
129164
103720
667160
589933
414074
439458
101.21
99.75
642.47
237.67
CONCR ET E PUMP 1407 CONCR ET E PUMP 1405 CONCR ET E PUMP 350 CONCR E T E PUMP SANY
CONCRETE PUMPS COSTS
Deployment/hire charges Diesel Cost Operator Salary
Other Costs Repairing Cost Total Cost
Cost/cum
Quantity Surveying Department
Estimation of quantities for Tower K
Shuttering & Concrete quantities for one wing was calculated and they are as follows :
Description
From
estimate(m2/
cu.m)
Used on
site(m2/cu.m)
Wall 10.11 11.76
Beam 10.29 9.62
Slab 7.13 6.76
Overall 9.28 10.1
SI.
No
Description No
Quantit
y
Un
it
Final
I 2# 3 BHK
A Shuttering 2 734.36 m2
1469
B Concrete 2 68.34 m2
136.7
II 2# 2 BHK
A Shuttering 2 421.00 m3
842
B Concrete 2 56.7 m3
113.4
III 3 BHK Staircase
Shuttering 78.01 m2
67.11
Concrete 10.21 m3
8.033
2 BHK Staircase
Shuttering 58.91 m2
58.91
Concrete 8.55 m3
8.55
Passageway
Shuttering 160.06 m2
160.06
Concrete 12.76 m3
12.76
Stores & Purchase Department
 Material Purchase Methodology
– Purchase Indent received from site – to be approved by Project-in-charge
– Checking for status of required material in store
– Request for Quotations (RFQ) – 2 to 3 vendors
– Preparation of comparative statements and should be approved by PM
– Negotiation and fixing of final rates and T&C
– Preparing of Purchase Order
– Terms & Conditions in a purchase order (PO) includes payment terms (45-60 days),
validity of quotation, unloading, VAT 14.5%, Entry tax 5% (for out-side India
procurements) etc.,
Quality Control Department (QA & QC)
The quality department keeps a check on materials received on site as well as
existing materials and also methodology of construction.
CONCRETE
•Cube test
•Compression test
•Tension test
•Slump test (Workability)
– For s – form concrete: Flow test is done (450 – 500mm)
– For conventional form concrete: Slump test is done (100 – 150mm +/- 20mm)
•All other necessary test and checks are for materials that arrive on site by the department.
CEMENT
– Fineness
– Consistency
– Initial Setting Time (IST)
– Final Setting Time (FST)
– Soundness test
– Specific gravity
– Compression test etc.
VDF (Vacuum Dewatered Flooring)
VDF is a special type of flooring technique it is used to achieve
•High Strength
•Longer Life
•Better Finish
•Faster Work
•It is suitable for high abrasion & heavy traffic movement.
VDF concreting for BLUE block basement was observed and the
productivity was also calculated considering various activities involved
during concreting.
•Total duration: 2:35:00
•Total pump operation time: 21:00
•Pumped 19.25 cum out of 142 cum
•Therefore, a productivity of 13.56 was achieved in the process.
VDF pavement construction
• A pavement was constructed from the West entrance of the site to AMBER
block for fire & safety department clearance, as per the requirements.
• A total concrete quantity of 64 m3
was poured for a length of 8m x 38m (M20 –
150mm thick).
• HDPE sheets were laid below to prevent moisture entry and Saltax boards were
used to fill the joints.
• Panelized concreting was done in order to prevent crack development.
IPS Flooring (Indian Patent Stone flooring)
• IPS flooring is a basic type of flooring which provides good wearing properties.
• It is generally used for all types of floors and mix of concrete used for IPS
flooring specification is 1:1.5:3.
• As per the nature of use the flooring thickness of concrete is decided from 25
mm to 50 mm. It is laid over the concrete base (1:4:8), which is almost 3 to 4
inches thick plain cement concrete (PCC) base.
• The whole area is divided into 2m x 2m panels with the help of glass strips in
order to avoid spreading of cracks from one panel to another in case of repair or
damage.
SAFETY Department
List of personal protective equipment’s at
site:
•Safety helmet (White, Yellow, Blue, Green,
Red)
•Safety shoes
•Safety belts
•Hand gloves (Cotton, Rubber, Leather)
•Ear plug
•Nose mask
•Eye goggles
•Face shield
•Life line rope
•Safety net
•Fire buckets
•Safety jacket
•Shoulder pad
Safety inspection:
•Daily inspection of plant and equipment’s by the operator
•Weekly Inspection of scaffold by scaffolding supervisor.
•Monthly Inspection of electrical hand tools
•Quarterly Inspection of temporary electrical systems.
•Yearly inspection of lifting machinery and equipment.
Record keeping:
•The safety officer is responsible for submitting a monthly safety report.
•The record of all health and safety related training, meeting, inspection and
audit will be kept in specified formats.
Project safety signs:
The size of safety sign boards was minimum 60x30 cm.
The safety sign boards included:
•Wear Proper PPE
•Wear Safety Helmet
•Wear Safety shoes and gloves
•First Aid Locations
To convey project safety statistics, a board was kept displaying at the entrance of
project site which included:
•Number of man- hours worked safely
•Lost time injuries
•Recordable incidents
•Trained employees etc.
Skilled Training Center
• This is a special initiative taken up by the SIMPLEX Infrastructures Ltd. in order to train
the labors in an effective way.
• The labors are trained in bar bending, masonry and shuttering i.e. both Conventional and
S-form shuttering.
• During the course of training, the labors are also taught the importance of safety when
working on site.
• For un-skilled workers, a training period of 45 days is fixed whereas for skilled workers,
the training period is 3 months.
Batching plants at Site
o The software used for the system is IDS software.
o Mix proportions have been saved as per the Client’s requirements.
o The silo’s capacity is 100MT – one truck of cement is 35 – 40MT.
o A truck of 6m3
is filled within 10-11 minutes time.
o The approximate cost of the plant is INR 50,00,000.
o An average hourly production of 30m3
is obtained from BP-2.
o Water content can be adjusted in the system with varying requirements.
PHYSICAL CONDITIONS AT SITE THAT CAN BE
RESOLVED
• After removal of the props,
workers haven’t stored the props
and steel stirrups properly, which
caused rusting and deterioration.
• Reinforcement at slab bottom
portion after removal of
shuttering.
• It is due to improper placement of
cover block and concrete pour.
• Scrap accumulation at site
• It was generated from the bar bending
workshop.
• It can be minimized by proper understanding,
execution of BBS and by providing proper
provisions to dispose the scrap materials.
• Land sliding happened near the skilled
training workshop.
• It was due to heavy rain, as well as
huge quantity of water that got
accumulated due to debris.
• Concrete was being transferred from plant to truck.
• In that process some quantity of concrete was falling down from
truck due to the carelessness of the operator and driver, by
leaving the channel open.
Amber Block Blue Block
Crimson
Block
Project Current Status
THANK YOU

Mais conteúdo relacionado

Mais procurados

Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paintMinh Bui Si
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDeltares
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CVAli Khidr
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010Minh Bui Si
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairingPham Dinh Thac
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plantNihar Routray
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture worksMohd Nizam Mohd Zan
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02Minh Bui Si
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodologyELSAYED DIAB
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilatorMinh Bui Si
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsSHAJI GEORGE
 
Resume shyamal kr sahu-
Resume shyamal kr sahu-Resume shyamal kr sahu-
Resume shyamal kr sahu-Shyamal Sahu
 
Company portfolio
Company portfolioCompany portfolio
Company portfolioDave Kelly
 

Mais procurados (20)

Method painting works emulsion paint
Method painting works   emulsion paintMethod painting works   emulsion paint
Method painting works emulsion paint
 
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipeDSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
DSD-NL 2014 - Geo Klantendag - 1. leidinginstallatie met direct pipe
 
Ali Khidr CV
Ali Khidr CVAli Khidr CV
Ali Khidr CV
 
Excavation method rectified 13-11-2010
Excavation method   rectified 13-11-2010Excavation method   rectified 13-11-2010
Excavation method rectified 13-11-2010
 
Ms for concrete repairing
Ms for concrete repairingMs for concrete repairing
Ms for concrete repairing
 
Project mgmt set up of cement plant
Project mgmt set up of cement plantProject mgmt set up of cement plant
Project mgmt set up of cement plant
 
Method of Statement - Road furniture works
Method of Statement - Road furniture worksMethod of Statement - Road furniture works
Method of Statement - Road furniture works
 
Concrete method rev02
Concrete method rev02Concrete method rev02
Concrete method rev02
 
3rd stage ppt black book
3rd stage ppt   black book3rd stage ppt   black book
3rd stage ppt black book
 
Bridge construction methodology
Bridge construction methodologyBridge construction methodology
Bridge construction methodology
 
INTERNSHIPS TRAINING IN A PILING SITE
INTERNSHIPS TRAINING IN A PILING SITEINTERNSHIPS TRAINING IN A PILING SITE
INTERNSHIPS TRAINING IN A PILING SITE
 
Column & beam
Column & beamColumn & beam
Column & beam
 
2 cm-ms-bld-012 - roof fan & natural ventilator
2   cm-ms-bld-012 - roof fan & natural ventilator2   cm-ms-bld-012 - roof fan & natural ventilator
2 cm-ms-bld-012 - roof fan & natural ventilator
 
Quick trench program
Quick trench programQuick trench program
Quick trench program
 
T.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy tsT.Shaji George - Copy - Copy ts
T.Shaji George - Copy - Copy ts
 
Resume shyamal kr sahu-
Resume shyamal kr sahu-Resume shyamal kr sahu-
Resume shyamal kr sahu-
 
Tushar resume
Tushar resumeTushar resume
Tushar resume
 
Company portfolio
Company portfolioCompany portfolio
Company portfolio
 
Michael CV.
Michael CV.Michael CV.
Michael CV.
 
Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION Episode 22 : PROJECT EXECUTION
Episode 22 : PROJECT EXECUTION
 

Semelhante a AH15019

Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Shubham Arora
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Abhimanyu Saraswat
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road constructionSatish Kambaliya
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptxssuser2ec079
 
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1Er Naveen Kumar
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...DougDos
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdSk Md Nayar
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnakishore1192
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah
 
CURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCCURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCAnil Singh
 
Construction Engineer Piping ,Tower crane - Anoop
Construction Engineer Piping ,Tower crane - AnoopConstruction Engineer Piping ,Tower crane - Anoop
Construction Engineer Piping ,Tower crane - AnoopAnoop Ramachandran
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportDivyesh Mungara
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphbhlksd
 

Semelhante a AH15019 (20)

Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
 
Summer Internship in Jaypee Group
Summer Internship in Jaypee Group Summer Internship in Jaypee Group
Summer Internship in Jaypee Group
 
Summer training report
Summer training reportSummer training report
Summer training report
 
Case study bridge construction upto pier and road construction
Case study   bridge construction upto pier and road constructionCase study   bridge construction upto pier and road construction
Case study bridge construction upto pier and road construction
 
Monthly Progress Report - September 2014
Monthly Progress Report - September 2014Monthly Progress Report - September 2014
Monthly Progress Report - September 2014
 
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
11. KGA, MALL - Execution Plan - R- 06.03.2023.pptx
 
Industrial Training Report1
Industrial Training Report1Industrial Training Report1
Industrial Training Report1
 
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
PROPOSED 4BEDROOM DUPLEX & A ONE BEDROOM SEMI-DETACHED RESIDENTIAL DEVELOMENT...
 
Industrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures LtdIndustrial Training On Construction At Simplex Infrastructures Ltd
Industrial Training On Construction At Simplex Infrastructures Ltd
 
Project Review Presentation (2)
Project Review Presentation (2)Project Review Presentation (2)
Project Review Presentation (2)
 
Abhishek presentation.pptx
Abhishek presentation.pptxAbhishek presentation.pptx
Abhishek presentation.pptx
 
summer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patnasummer Internship report L&T_ Bihar museum_Patna
summer Internship report L&T_ Bihar museum_Patna
 
Mohamed Salah Ibrahim
Mohamed Salah IbrahimMohamed Salah Ibrahim
Mohamed Salah Ibrahim
 
CURRICULAM_VITAE_QC
CURRICULAM_VITAE_QCCURRICULAM_VITAE_QC
CURRICULAM_VITAE_QC
 
Construction Engineer Piping ,Tower crane - Anoop
Construction Engineer Piping ,Tower crane - AnoopConstruction Engineer Piping ,Tower crane - Anoop
Construction Engineer Piping ,Tower crane - Anoop
 
Constructionmethodologyandprojectmanagementreport
ConstructionmethodologyandprojectmanagementreportConstructionmethodologyandprojectmanagementreport
Constructionmethodologyandprojectmanagementreport
 
Construction practices aphb
Construction practices aphbConstruction practices aphb
Construction practices aphb
 
Allwyn Leo CV
Allwyn Leo CVAllwyn Leo CV
Allwyn Leo CV
 
Allwyn-PE-CV
Allwyn-PE-CVAllwyn-PE-CV
Allwyn-PE-CV
 
wsa
wsawsa
wsa
 

AH15019

  • 1. INTERNSHIP PRESENTATION ON BRIGADE Lake Front, BANGALORE CHELINATH B AH15019 PGP ACM 29 (2015-17) NICMAR, HYDERABAD
  • 2. Project Details • Name of the Project : Brigade Lakefront (Project Code: 2895) • Scope of wok : Construction of sub-structure & super Structure work of proposed Residential towers A,B,C,D,E,F and G (AMBER BLOCK) & H,I,J,K,L,M and N (BLUEBLOCK) • Location : Whitefield, Bangalore • Client : Brigade Enterprises Ltd. • Contractor : Simplex Infrastructures Ltd. • Architect : RSP Design Consultants(India) Pvt Ltd. • Structural Consultant : Vintech Consultants • Type of contract : Item Rate Contract • Free Issue Materials : RMC, Cement, Reinforcement steel, S- form • Defect liability Period :12 months from completion of project
  • 3. Contract Details • LOI issued Date : 06-Sept-2013(Amber block) 13-Mar-2014(Blue Block) • Contractual Commencement : 16-Sept-2013(Amber Block) 15-Mar-2014(Blue Block) • Actual Commencement : 01-Oct-2013(Amber Block) 15-Mar-2014(Blue Block) • Contract Value : Rs.38.22 Cr(Amber Block) Rs.48.20 Cr(Blue Block) • Contract Period : 19 months + 2 months (Amber Block) 21 months + 2 months (Blue Block ) • Mobilization Advance : 278 Lakhs (Amber Block) 351 Lakhs (Blue Block) • Retention Money : 2.5% of total value of work done from each RA Bill • RA Bill Payments : 50% of bill value as within 15 days from the date of submission of Bill & Balance 50% after Verification of Bills in next 15 days.
  • 4. Plan & Facilities Type of Residence •2, 3 & 4 Bedroom Luxury Apartments (2 Bedroom: 107 - 134 sqm; 3 Bedroom: 154 - 259 sqm; 4 Bedroom: 312 sqm) Budget Range •Rs. 77 Lakh Onwards (Inclusive of car-park and exclusive of statutory expenses) Facilities •2787 sqm Clubhouse with rooftop swimming pool •Basketball, Tennis and Cricket Pitch •Large open green spaces •Children's play area and Senior Citizens court Note: 1 square metre = 10.764 square feet
  • 5. Project Execution Details Phase I: North & Central parcel (Amber & Blue block) 19 months structural work + 2 months finishing works for North Parcel 21 months structural work + 2 months finishing works for Central Parcel •North parcel: 2B+G+14 - 7 towers (A-G) o Towers A-F constructed using MIVAN formwork o Tower G constructed fully using conventional formwork •Central parcel: 2B+G+14 - 7 towers (H-N) oConventional formwork is used in all towers up to Ground floor oS- formwork is used in floors from 1-14. Phase II: South parcel (Crimson block) •2B+G+14 – 6 Towers (O-T) •23 months for 2 towers, 25 months for 2 towers & 28 months for 2 towers •Additional 2 months for finishing works.
  • 6. Activities done & Learnings during training  Planning Department • Concrete Pour Delay Analysis : PUMP (1405D) Tower-K 7th floor - 150m3 Pump Capacity 55m3 per hour Total time for completion of 150m3: 17 hours Total operating time: 514mins or 8.57 hours Total delay time: 8.43 hours Overall Efficiency of the process: 33.96% Reasons for delay : Delay in pumping due to lack of RMC trucks Delay in vibration Delay in shifting pipes Delay in loading Delay by the driver Pump failure
  • 7. Concrete Placement @ F Wing 14th floor by Crane and Bucket • The concreting process with the help of tower crane was also observed in detail. • The activity with highest Coefficient of Variation should be taken care to reduce the delay in concreting process. Average 08:33 29:30 37:10 17:30 44:10 12:40 28:00 02:40 41:00 SD 01:01 09:55 21:03 06:21 25:36 18:25 09:52 00:31 17:39 CV% 12 33.7 56.7 36.3 15.6 145.4 35.3 19.4 35.2 Cycle Duration RMC Delay Bucket Filling Crane Delay @ RMC RMC to 14F Placeme nt Delay Place ment Crane Delay @14F 14F to RMC
  • 8. Pump efficiency • There were 4 pumps available on site for placement of concrete. • The cost per cubic meter of each pump was calculated separately. • The pump with more cost per cum was removed from site as it was nearing its salvage value. Cost per Cum(from April, 16 to June, 16) Equipm ent Concre te Qty Deployement / Hire Charges Diesel & Mobil Cost Operator & Helper Salary Other Costs Repairing Cost Total Cost Cost/cu m 1407 6592 350000 213817 60000 7549 35794 667160 101.21 1405 5914 300000 160047 60000 27090 42796 589933 99.75 350 644 150000 44914 60000 29995 129164 414074 642.47 Sany 1849 125000 89323 60000 61415 103720 439458 237.67
  • 9. 350000 300000 150000 125000 213817 160047 44914 89323 60000 60000 60000 60000 7549 27090 29995 61415 35794 42796 129164 103720 667160 589933 414074 439458 101.21 99.75 642.47 237.67 CONCR ET E PUMP 1407 CONCR ET E PUMP 1405 CONCR ET E PUMP 350 CONCR E T E PUMP SANY CONCRETE PUMPS COSTS Deployment/hire charges Diesel Cost Operator Salary Other Costs Repairing Cost Total Cost Cost/cum
  • 10. Quantity Surveying Department Estimation of quantities for Tower K Shuttering & Concrete quantities for one wing was calculated and they are as follows : Description From estimate(m2/ cu.m) Used on site(m2/cu.m) Wall 10.11 11.76 Beam 10.29 9.62 Slab 7.13 6.76 Overall 9.28 10.1 SI. No Description No Quantit y Un it Final I 2# 3 BHK A Shuttering 2 734.36 m2 1469 B Concrete 2 68.34 m2 136.7 II 2# 2 BHK A Shuttering 2 421.00 m3 842 B Concrete 2 56.7 m3 113.4 III 3 BHK Staircase Shuttering 78.01 m2 67.11 Concrete 10.21 m3 8.033 2 BHK Staircase Shuttering 58.91 m2 58.91 Concrete 8.55 m3 8.55 Passageway Shuttering 160.06 m2 160.06 Concrete 12.76 m3 12.76
  • 11. Stores & Purchase Department  Material Purchase Methodology – Purchase Indent received from site – to be approved by Project-in-charge – Checking for status of required material in store – Request for Quotations (RFQ) – 2 to 3 vendors – Preparation of comparative statements and should be approved by PM – Negotiation and fixing of final rates and T&C – Preparing of Purchase Order – Terms & Conditions in a purchase order (PO) includes payment terms (45-60 days), validity of quotation, unloading, VAT 14.5%, Entry tax 5% (for out-side India procurements) etc.,
  • 12. Quality Control Department (QA & QC) The quality department keeps a check on materials received on site as well as existing materials and also methodology of construction. CONCRETE •Cube test •Compression test •Tension test •Slump test (Workability) – For s – form concrete: Flow test is done (450 – 500mm) – For conventional form concrete: Slump test is done (100 – 150mm +/- 20mm) •All other necessary test and checks are for materials that arrive on site by the department. CEMENT – Fineness – Consistency – Initial Setting Time (IST) – Final Setting Time (FST) – Soundness test – Specific gravity – Compression test etc.
  • 13.
  • 14. VDF (Vacuum Dewatered Flooring) VDF is a special type of flooring technique it is used to achieve •High Strength •Longer Life •Better Finish •Faster Work •It is suitable for high abrasion & heavy traffic movement. VDF concreting for BLUE block basement was observed and the productivity was also calculated considering various activities involved during concreting. •Total duration: 2:35:00 •Total pump operation time: 21:00 •Pumped 19.25 cum out of 142 cum •Therefore, a productivity of 13.56 was achieved in the process.
  • 15. VDF pavement construction • A pavement was constructed from the West entrance of the site to AMBER block for fire & safety department clearance, as per the requirements. • A total concrete quantity of 64 m3 was poured for a length of 8m x 38m (M20 – 150mm thick). • HDPE sheets were laid below to prevent moisture entry and Saltax boards were used to fill the joints. • Panelized concreting was done in order to prevent crack development.
  • 16. IPS Flooring (Indian Patent Stone flooring) • IPS flooring is a basic type of flooring which provides good wearing properties. • It is generally used for all types of floors and mix of concrete used for IPS flooring specification is 1:1.5:3. • As per the nature of use the flooring thickness of concrete is decided from 25 mm to 50 mm. It is laid over the concrete base (1:4:8), which is almost 3 to 4 inches thick plain cement concrete (PCC) base. • The whole area is divided into 2m x 2m panels with the help of glass strips in order to avoid spreading of cracks from one panel to another in case of repair or damage.
  • 17. SAFETY Department List of personal protective equipment’s at site: •Safety helmet (White, Yellow, Blue, Green, Red) •Safety shoes •Safety belts •Hand gloves (Cotton, Rubber, Leather) •Ear plug •Nose mask •Eye goggles •Face shield •Life line rope •Safety net •Fire buckets •Safety jacket •Shoulder pad
  • 18. Safety inspection: •Daily inspection of plant and equipment’s by the operator •Weekly Inspection of scaffold by scaffolding supervisor. •Monthly Inspection of electrical hand tools •Quarterly Inspection of temporary electrical systems. •Yearly inspection of lifting machinery and equipment. Record keeping: •The safety officer is responsible for submitting a monthly safety report. •The record of all health and safety related training, meeting, inspection and audit will be kept in specified formats.
  • 19. Project safety signs: The size of safety sign boards was minimum 60x30 cm. The safety sign boards included: •Wear Proper PPE •Wear Safety Helmet •Wear Safety shoes and gloves •First Aid Locations To convey project safety statistics, a board was kept displaying at the entrance of project site which included: •Number of man- hours worked safely •Lost time injuries •Recordable incidents •Trained employees etc.
  • 20. Skilled Training Center • This is a special initiative taken up by the SIMPLEX Infrastructures Ltd. in order to train the labors in an effective way. • The labors are trained in bar bending, masonry and shuttering i.e. both Conventional and S-form shuttering. • During the course of training, the labors are also taught the importance of safety when working on site. • For un-skilled workers, a training period of 45 days is fixed whereas for skilled workers, the training period is 3 months.
  • 21. Batching plants at Site o The software used for the system is IDS software. o Mix proportions have been saved as per the Client’s requirements. o The silo’s capacity is 100MT – one truck of cement is 35 – 40MT. o A truck of 6m3 is filled within 10-11 minutes time. o The approximate cost of the plant is INR 50,00,000. o An average hourly production of 30m3 is obtained from BP-2. o Water content can be adjusted in the system with varying requirements.
  • 22. PHYSICAL CONDITIONS AT SITE THAT CAN BE RESOLVED • After removal of the props, workers haven’t stored the props and steel stirrups properly, which caused rusting and deterioration. • Reinforcement at slab bottom portion after removal of shuttering. • It is due to improper placement of cover block and concrete pour.
  • 23. • Scrap accumulation at site • It was generated from the bar bending workshop. • It can be minimized by proper understanding, execution of BBS and by providing proper provisions to dispose the scrap materials. • Land sliding happened near the skilled training workshop. • It was due to heavy rain, as well as huge quantity of water that got accumulated due to debris.
  • 24. • Concrete was being transferred from plant to truck. • In that process some quantity of concrete was falling down from truck due to the carelessness of the operator and driver, by leaving the channel open.
  • 25. Amber Block Blue Block Crimson Block Project Current Status