The “Greening of Aiken” project is a model, “deep energy retrofit” on the University of Vermont campus. It demonstrates that renovation can out-perform new construction, while meeting a tight budget. This project sets an example for low energy-consuming design and construction, responsible use of natural resources, and healthy learning and work environments.
Booking open Available Pune Call Girls Nanded City 6297143586 Call Hot India...
A Net-Zero World and The Greening of Aiken
1.
2. Beauty in Living
Photo by John Fowler / CC-BY-2.0
Photo modified by Disenyo from photo by Paul
Kempeneers / CC-BY-SA-2.5
Photo by Martin St-Amant / CC-BY-SA-3.0
Photo by Bill Maclay
Photo
by
Pascal
Reusch
/
CC-‐BY-‐SA-‐3.0
Photo
derived
from
photo
by
Hans
Ollermann
/
CC-‐BY-‐2.0
Public
Domain
3. Evolution of Energy and Settlement
Renewable / Farms and Villages Coal / Urbanization Oil / SuburbanizationFarming/Renewable Coal Oil
Painting by Thomas James Judkin / Public Domain
Photograph by Michigan Department of Transportation / Public Domain
painting by Jan Brueghel the Elder / Public Domain-US
painting by Jean-François Millet / Public Domain-US
Photo by austrini / CC BY 2.0
Photo by Rand, McNally & Co / Public Domain-US
photo by Seattle Eng Co / Public Domain-US
Photo by Minesweeper / CC-BY-SA-3.0
Photo by David Shankbone / CC-BY-SA-3.0
Derivative by Maclay Architects from Otto Krebs 1874 / Public Domain-US
4. economy, energy, environment, equity & population
Global Challenges & Our Buildings & Community s Impacts
photo
by
Olsen
Dave,
U.S.
Fish
and
Wildlife
Service
/
Public
Domain
Photo by Ahron de Leeuw / CC-BY-2.0
Public Domain
Photo by Perpetual Tourist / CC-BY-2.0
Photo by John Hill / CC-BY-SA-3.0
19. Classrooms:
• Low ceilings
• Poor lighting and air
quality
• Inefficient cooling
and heating
Hallways:
• Dark, uninviting,
cramped,
not allowing
community
interactions
Atrium:
• Cramped with angled
glazing limiting view
and connection to
campus
Pre-Renovation Internal Conditions
20. Air Intake at Ground
Level Creates Indoor Air
Quality Problems
Biological Materials
Inside of Fresh
Air Intake
Mechanical Room
Duct Insulation
Deteriorated
Pre- Renovation Mechanical
Conditions
36. Wrap jamb with self-adhering air and moisture barrier sheet membrane, lapped over sill membrane.
37. Install backer rod and sealant from the interior side of window, to seal window frame to air barrier.
Install spray urethane foam (low-expanding type) between window frame and vinyl angle from the
outside (not shown.)
38. APPLY SPRAY AIR & MOISTURE BARRIER MEMBRANE
Apply spray air and moisture barrier (Tremco Exo-Air 120) over sheet AMB around window
perimeter, over base of masonry wall anchors and metal panel wall anchors.
39. APPLY RIGID FOAM (XPS) INSULATION
Install rigid foam tight to face of AMB, cut out around wall anchors, in two layers (3” and
2”) with joints staggered. Sealant daubs hold insulation boards temporarily, masonry wall
anchors retain the insulation permanently.
40. Seal around openings (window openings, wall anchor penetrations) and gaps with spray
foam or sealant. Gaps ¼” or greater in rigid foam are sealed with spray urethane foam,
less than ¼” sealed with flexible sealant.
45. The Construction Process
• Mock-up includes as many actual building elements as possible
• Shortened construction schedule by team working through details and
installation sequences
46. The Construction Process
• Treat the mock-up as the building
• All elements of the mock-up
reviewed
• Aiken included smoke testing the
mock-up
47. The Construction Process
Inspection, Inspection, Inspection
• Every aspect of the membrane: mock-up to caulking
inspected
• Apparent flaws identified by colored dots and initialed by
contractor when complete for re-inspection
• All inspections of each stage needed to pass prior to next
step starting
48. • Window air and water leakage testing
• Compliance Testing
Enclosure Testing During
Construction
62. TEAM MEMBERS
OWNER TEAM
University of Vermont
Robert Vaughn, Director, Capital Planning and Management
Paula Carlaccini, Director, Facilities Design and Construction
Ken Bean, University Architect
Todd Merchant, Senior Construction Administrator
Mike Stevens, Construction Project Coordinator
“Greening of Aiken Committee”
Gary Hawley, Research Associate
Carl Waite, Senior Research Analyst
Alan McIntosh, Professor
Deane Want, Associate Professor
Don DeHayes, Professor & Former Dean
Mary Watzin, Dean
Eco-Machine
Matthew Beam, Graduate Student
John Todd, Professor
Commissioning Consultant
Allan Bullis , Efficiency Innovations, LLC, Envelope
Inspection and Testing
Building Durability Consultant
Gale Associates
Construction Cost Consultant
Vermeulens Cost Consultants
DEW Construction, Inc.
Owner LEED Consultant
Linda Samter
CONSTRUCTION TEAM
PC Construction, General Contractor
Laura Clements, Project Manager
Jordan Hershman, Project Engineer
John Lavoie, Site Superintendent
Amie Hammer & Kaitlyn Evarts, Project Assistants
St. Albans Glass, Window and Metal Panel Subcontractor
Greg Swan
North Stars Masonry, Inc., Masonry Subcontractor
Larry Shelton
Dayco, Inc., Membrane Roofing Subcontractor
Dana Geno
Nicom Coatings, Corp., Wall Coatings and Membranes Subcontractor
John Larosa
DESIGN TEAM
Maclay Architects
Bill Maclay, Principal
Brian Leet & Tom Bodell, Project Managers
Lisa Sawin, Job Captain
Chris Cook, Project Assistant
Energy Consultant
Andy Shapiro, Energy Balance
Cost Consultant
DEW Construction, Inc.
Kohler Lewis, Mechanical and Plumbing Engineers
Joe Kohler
Adam Kohler
Dan Lewis
Roy Swain
Pearson and Associates, Electrical Engineer
Alan Gould
Engineering Ventures, Civil Consulting Engineer
Sarah Thyng
Engineering Ventures, Structural Engineer
Greg Sellers
Chase Engineering, Fire Protection Engineer
Matt Chase