The document outlines the methodology for upgrading a Maximo system using PRINCE2 project processes. It describes the 7 PRINCE2 processes: starting up a project, directing a project, initiating a project, controlling a stage, managing product delivery, managing stage boundary, and closing a project. Each process includes activities and management products. The methodology then applies these processes to the phases of the Maximo upgrade project: initiation, gap analysis, design, build, data migration, testing, training, and closing.
2. Project Process in PRINCE2
1) Starting Up a Project
2) Directing a Project
3) Initiating a Project
4) Controlling a Stage
5) Managing Product Delivery
6) Managing Stage Boundary
7) Closing a Project
A) Project Mandate
4. 1) Starting Up a Project
1.A)Activities Involved
1.A.1)Appoint the Executive and
Project Manager
1.A.2) Capture previous lessons
1.A.3) Design and appoint the project
management team
1.A.4) Prepare the outline Business
Case
1.A.5) Select the project approach and
assemble the Project Brief
1.A.6) Plan the initiation stage
1.B)Management
Products
1.B.1)Daily Log created
1.B.2)Lessons Log created
1.B.3)Outline Business Case
created
1.B.4)Project Product Description
created
1.B.5)Project Brief created
1.B.6)Initiation Stage Plan created
DP1
5. 2) Directing a Project
Authorize Initiation
Authorize Project
Authorize Stage Plan or Exception Plan
Give Adhoc Direction
Authorize Project Closure
1.C)Activities Involved
DP1
DP2
DP3
DP4
DP5
Project Board Activities (Senior User + Senior
Supplier + Executive)
6. 3) Initiating a Project
1.D)Activities Involved
1.D.1) Prepare the Risk Management
Strategy
1.D.2) Prepare Configuration
Management Strategy
1.D.3) Prepare Quality Management
Strategy
1.D.4) Prepare Communication
Management Strategy
1.D.5) Set up Project Controls
1.D.6) Create the project Plan
1.D.7) Refine the Business Case
1.D.8) Assemble the Project Initiation
Documentation
1.E)Management
Products
1.E.1) Risk Management Strategy
Created
1.E.2) Configuration Management
Strategy Created
1.E.3) Communication
Management Strategy Created
1.E.4) Project Plan Created
1.E.5) (Detailed) Business Case
Created
1.E.6) Risk Register created
1.E.7) Configuration Items Records
Created
1.E.8) Issue Register Created
1.E.9) Quality Register Created
1.E.10) Benefits Review Plan
Created
1.F)Themes : Plan
1.F.1) Product Breakdown Structure
Created
1.F.2) Product Descriptions Created
1.F.3) Product Flow Diagram Created
DP2 DP4
7. 4) Controlling a Stage
1.G)Activities Involved
1.G.1)Authorize a Work package
1.G.2)Review Work Package status
1.G.3)Receive completed Work
Packages
1.G.4)Review the stage status
1.G.5)Report Highlights
1.G.6)Capture and examine issues
and risks
1.G.7)Escalate issues and risks
1.G.8)Take corrective action
1.H)Management
Products
1.H.1) Work Packages created
1.H.2) Highlight Report(s) created
1.H.3) Issue Report(s) created
1.H.4) Exception Report(s)
created
1.H.5) Stage Plan updated
1.H.6) Configuration Item
Records updated
1.H.7) Risk Register updated
1.H.8) Issue Register updated
1.H.9) Quality Register updated
1.H.10) Work Package(s)
updated
1.H.11) Lessons log updated
1.H.12) Issue Report updated
1.H.13) Daily Log updated
DP4
8. 5) Managing Product Delivery
1.I)Activities Involved
1.1.1) Accept a Work Package
1.1.2) Execute a Work Package
1.1.3) Deliver a Work Package
1.J)Management
Products
1.J.1) Quality Register updated
1.J.2) Configuration Item Records
updated
1.J.3) Team Plan created
1.J.4) Checkpoint Reports created
9. 6) Managing Stage Boundary
1.K)Activities Involved
1.K.1) Plan the next stage
1.K.2) Update the Project Plan
1.K.3) Update the Business Case
1.K.4) Report stage end
1.K.5) Produce an Exception Plan
1.L)Management
Products
1.L.1) Project Initiation
Documentation updated
1.L.2) Configuration Item
Records updated
1.L.3) Risk Register updated
1.L.4) Issue Register updated
1.L.5) Quality Register updated
1.L.6) Project Plan updated
1.L.7) Business Case updated
1.L.8) Benefits Review Plan
updated
1.L.9) Stage or Exception Plan
created
1.L.10) Product Descriptions
(next stage) created
1.L.11) End Stage Report created
1.L.12) Lessons Report created
DP3 DP4
10. 7) Closing a Project
1.M)Activities Involved
1.M.1) Prepare planned closure
1.M.2) Prepare premature closure
1.M.3) Hand over products
1.M.4) Evaluate the project
1.M.5) Recommend project closure
1.N)Management
Products
1.N.1) Follow-on action
recommendations created
1.N.2) Lessons Report created
1.N.3) Project Initiation
Documentation updated
1.N.4) Project Plan updated
1.N.5) Issue Register updated
1.N.6) Configuration Item
Records updated
1.N.7) Benefits Review Plan
updated
1.N.8) Risk Register closed
1.N.9) Issue Register closed
1.N.10) Quality Register closed
1.N.11) Daily Log closed
1.N.12) Lessons Log closed
DP5
11. Maximo Upgrade using PRINCE2 Project Process
Starting Up a Project
1.1) Appoint Executive and Project Manager
1.2) Capture Previous Lessons
1.3) Design and Appoint Project Management Team
1.4) Prepare Outline Business Case
1.5) Select Project Approach and Assemble the Project Brief
1.6) Plan the Initiation Stage
DP1
A.1)Project Mandate Input to Project
Startup produced by Corporate or Program
Management
12. Directing a Project
2.2) Authorize Project
2.3) Authorize Stage or Exception Plan
2.4) Give Adhoc Direction
2.5) Authorize Closure
2.1) Authorize Initiation DP1
DP2
DP3
DP4
DP5
Project Board Activities (Senior User + Senior Supplier +
Executive)
13. Initiating a Project
DP2 DP4
3.2) Core Team Assembly
3.3) Product Orientation
3.4) Training Strategy
3.5) Cutover Strategy
3.1) Kickoff Meeting
3.D.1) Prepare the Risk Management
Strategy
3.D.2) Prepare Configuration
Management Strategy
3.D.3) Prepare Quality Management
Strategy
3.D.4) Prepare Communication
Management Strategy
3.D.5) Set up Project Controls
3.D.6) Create the project Plan
3.D.7) Refine the Business Case
3.D.8) Assemble the Project Initiation
Documentation
14. Controlling a Stage- Gap Analysis
4.1) Business Process Review
4.2) Fit Gap Analysis
4.3)Data Source Review
4.4) Initial Data Mapping
4.5) New Requirements
Carry Out Managing Stage Boundary Process
DP3 DP4
15. Controlling a Stage – Design
5.1) Design CRP(Conference Room Pilots)
5.2) Workflow Analysis and Design
5.3) SOP Development
5.4) Data Mapping
Carry Out Managing Stage Boundary Process
DP3 DP4
16. Controlling a Stage- Build
6.1) Server Infrastructure Build
6.2) Maximo Install 7.x
6.3) Maximo Configuration
6.4) Customization
6.5) Reports / KPI’s
6.6) Security
6.7) Workflow Development
Carry Out Managing Stage Boundary Process
DP3 DP4
17. Controlling a Stage – Data Migration
7.1) Legacy Data Migration
7.2) Integration Framework
7.3) Data Load Development
7.4) Data Testing
Carry Out Managing Stage Boundary Process
DP3 DP4
18. Controlling a Stage - Testing
8.1) System Integration Testing
8.2) Data Migration Testing
8.3) Performance Testing
8.4) User Acceptance Testing
8.5) Cutover to Production Testing
DP3 DP4
Carry Out Managing Stage Boundary Process
19. Controlling a Stage - Training
9.1) End User Training
9.2) Systems Administrator Training
9.3) Reports Developer Training
DP3 DP4
Carry Out Closing a Project Process
20. Closing a Project
10.1) Execute Cutover Plan
10.2) Data Migration
10.3) Go Live
10.4) Stabilization
10.5) Post Implementation Review
DP5