Off-site and On-Site Extrusion Decommissioning Scheduling Plan
1. Off-site and On-Site Extrusion Decommissioning
Scheduling/Plan
Presented by: Arleen Pena, 10Dec2014
Dot Color Definition
Green Dot BSC Off-siteCalibrations
Yellow Dot BSC On-siteCalibrations
Red Dot Failed Calibration = NCEP
Blue Dot Retired Status for Calibration
Calibration will usea colored dot systemto identify retired instruments.
The purposeis to mitigate the potential risk of instruments migrating to
non-decommissioned areas. Instrumentswith completed exit calibration
will be labeled, per procedureand receive an additional Blue colored dot to
indicate retirement
Off-Site Calibrations:
Green Dot placed on instruments on 12Dec2014
Start Exit Calibrations week of 15Dec to 19Dec2014
3 stages to be sent-out (see Checklist/B1 Toolroom/Grey Cabinets)
SCHEDULING: 15Dec2014, 17Dec2014and 19Dec2014
- Need items by 10:00amin Cal Lab in order to ship-outby noon
On-Site Calibrations:
Yellow Dot placed on instruments on 24Dec2014
Preparation Walk-through Inspection Meeting on 5Jan2015
SCHEDULING:
DATE ON-SITE LINE #
1/6/2015 Line 1 Extruder
1/7/2015 Line 2 andLine 6 Extruder
1/9/2015 Line 3 Killion¾”ExtruderKL-075
1/12/2015 Line 5
1/12/2015 Line 9
1/14/2015 Line 10
2/9/2015 Line 7
2. Off-site and On-Site Extrusion Decommissioning
Scheduling/Plan
Presented by: Arleen Pena, 10Dec2014
Off-Site andOn-Site Calibrations Internal Processing:
Check-off list created fromIM&Tspreadsheet
- Date-out/Date-in Check-off List/Comments
Review Calibration Certificates and update CalMan
If it “Passes,” placea Blue Dot atop the Green/Yellow Dot
- Indicates “Retired” Status
If it “Fails,” place a Red Dot atop the Green/Yellow Dot; initiate NCEP
After NCEP completion, place a Blue Dot atop the Red Dot
- Indicates“Retired” Status
Process status of any incoming Calibration Certificates/update CalMan
Process any related OOT/NCEPs
Instruments to be disposition by Owner and stored in segregated area
Status: Retired