IRRIGATION ENGINEERING
TOPIC NAME: CROSS SECTION OF THE CANAL,
BALANCING DEPTH, AND CANAL F.S.L.
SUBJECT CODE: 2I70609
BRANCH: CIVIL ENGG,. 7TH SEM
PREPARED BY:
GUIDED BY: PROF. MAMTA PATEL
SR NO. NAME ENROLL. NO.
1. PATEL PRASHANT S. 141100106078
2. PATEL TWINKAL D. 141100106092
3. MISTRY ADITYA P. 151103106009
4. PATEL KAJAL M. 151103106011
5. RATNANI MANISHA N. 151103106016
CONTENT
 Cross section of an irrigation channel
- In cutting
- In filling
- In partial cutting and filling
 Balancing depth
 Canal F.S.L.
CROSS SECTION OF AN IRRIGATION CHANNEL
An irrigation channel section may be either,
1) In cutting
2) In filling
3) In partial cutting and filling
Cross section of canal in cutting
Cross section of canal in filling
Cross section of canal in partial cutting and filling
The main components of the canal cross- section are:
1. Side slope
2. Berm
3. Free board
4. Banks
5. Dowla
6. Inspection road
7. Borrow pits
8. Spoil bank
9. Lang width
10. Counter berm
1. SIDE SLOPES
 The side slope of channel depend on the nature of the soil.
 In average loam soil the side slopes are usually kept 1 : 1 in
cutting and 1.5 : 1in filling.
 In sandy soil say 1.5 : 1 in cutting and 2 : 1 in filling to be used.
2. BERM
 Berm is the horizontal distance left at ground level
between the toe of the bank and top edge of cutting.
 Berm is provided additional strength to bank and help in
safe guarding them against breaches.
 It is also provided for future widening of channel.
3.FREE BOARD
Free board is defined as the vertical distance between the designed full
supply level ( F.S.L.) in the canal and top level of canal banks.
It is provided to allow for wave action and floating debris.
 free board is consideration of
- canal capacity
- soil characteristics
- hydraulic gradient
4. BANKS
The purpose of the bank is to retain water so long as the berm is
not formed. They thus have to with stand full pressure of water above
the ground level.
5. INSPECTION ROAD
 An inspection road is usually provided on one or both bank of the
canal for the purpose of inspection, repair and maintenance of the
roads.
6.DOWEL
As the measure of safety for the vehicles, a raised projection of
soil, called dowel, is provided on the channel side of the inspection
road.
The top width of dowel is 0.5m, height above road level is 0.5m
and side slope is 1.5 : 1.
7. BORROW PITS
Borrow pits are small
pits which are dug to
obtain the extra earth for
making banks if the soil
obtained from cutting is
not sufficient.
The borrow pits are
usually located at distance
of 4D to 6D away from
outer toe of the bank.
The borrow pits may be
located either inside or
outside the channel.
8. SPOIL BANK
When the quantity of earth obtained from excavation or cutting of
the channel section is in excess of the quantity required for forming
the bank and service road then extra earth is usually deposited in the
form of spoil bank.
9. LAND WIDTH
The total land required for the construction of channel is divided in to two
parts. Permanent land and temporary land.
The permanent land is the land which will be required permanently during
and after construction of channel.
During construction period of the canal, some extra land is required for
storage of materials and machineries nearer the site of construction.
10.COUNTER BERM
Even after providing the usual embankment section of a bank,
saturation gradient may cut the downstream side of the bank .
In such case the saturation line should always be covered by 0.3
to 0.6 m of earth.
BALANCING DEPTH
The channel section is entirely in cutting, the extra soil has to be
deposited in spoil bank.
For the channel section entirely in filling the soil has to be obtained
from borrow pits. In both case required double handling and increased
cost of earth work.
If for a channel section the depth of cutting is such that the quantity
of excavation or cutting is equal to the earth filling required for making
the banks, then depth of cutting is known as balancing depth or most
economical depth of cutting.
The normal maximum operating water level of a water storage
when not affected by floods.
 This water level corresponds to 100% capacity.
CANAL F.S.L.
THANK YOU

Mais conteúdo relacionado

Mais procurados (20)

Chapter 4 seepage theories
Chapter 4 seepage theoriesChapter 4 seepage theories
Chapter 4 seepage theories
 
Chapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipatorsChapter 7 spillway and energy dissipators
Chapter 7 spillway and energy dissipators
 
Losses IN Canals
Losses IN CanalsLosses IN Canals
Losses IN Canals
 
Lacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation EngineeringLacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation Engineering
 
Dams and spillways
Dams and spillwaysDams and spillways
Dams and spillways
 
Canal outlets
Canal outletsCanal outlets
Canal outlets
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
Gravity Dam
Gravity DamGravity Dam
Gravity Dam
 
Canal
CanalCanal
Canal
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
energy dissipator in hydraulic structure
energy dissipator  in  hydraulic structure energy dissipator  in  hydraulic structure
energy dissipator in hydraulic structure
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Design of a channel Reach
Design of a channel ReachDesign of a channel Reach
Design of a channel Reach
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Weirs
WeirsWeirs
Weirs
 
Earthen Dam
Earthen DamEarthen Dam
Earthen Dam
 
Diversion head works
Diversion head worksDiversion head works
Diversion head works
 
Canal Regulation Work
Canal Regulation WorkCanal Regulation Work
Canal Regulation Work
 
economic channel section
economic channel sectioneconomic channel section
economic channel section
 
Canal irrigation
Canal irrigationCanal irrigation
Canal irrigation
 

Semelhante a Cross section of the canal, balancing depth and canal fsl

WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemMitaliShelke
 
08. Classification of Canals.pdf
08. Classification of Canals.pdf08. Classification of Canals.pdf
08. Classification of Canals.pdfMuhammadAjmal326519
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canalsaibabu48
 
Geological factor for canal alignment
Geological factor for canal alignmentGeological factor for canal alignment
Geological factor for canal alignmentPramoda Raj
 
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...Denish Jangid
 
Module 03 Distribution Works.pptx
Module 03 Distribution Works.pptxModule 03 Distribution Works.pptx
Module 03 Distribution Works.pptxSilasChaudhari
 
Canal of design
Canal of designCanal of design
Canal of designPREMKUMAR
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdfRoshani Shahi
 
Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...Denish Jangid
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis Smith
 
Lined or non erodible design channel study
Lined or non erodible design channel studyLined or non erodible design channel study
Lined or non erodible design channel studyroidghozi
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantagesabdqadeer
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxMaloth3
 
CHAPTER 5- Water Conveynance and Control-1.pptx
CHAPTER  5- Water Conveynance and Control-1.pptxCHAPTER  5- Water Conveynance and Control-1.pptx
CHAPTER 5- Water Conveynance and Control-1.pptxMamushLeta
 
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptxTejas279783
 

Semelhante a Cross section of the canal, balancing depth and canal fsl (20)

WREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution systemWREII Canals Head Works and Distribution system
WREII Canals Head Works and Distribution system
 
Canal Irrigation
Canal IrrigationCanal Irrigation
Canal Irrigation
 
08. Classification of Canals.pdf
08. Classification of Canals.pdf08. Classification of Canals.pdf
08. Classification of Canals.pdf
 
Unit 4-canal
Unit 4-canalUnit 4-canal
Unit 4-canal
 
Geological factor for canal alignment
Geological factor for canal alignmentGeological factor for canal alignment
Geological factor for canal alignment
 
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...Canal & canal types with design of channels by dj sir covered kennedy lacey t...
Canal & canal types with design of channels by dj sir covered kennedy lacey t...
 
Module 03 Distribution Works.pptx
Module 03 Distribution Works.pptxModule 03 Distribution Works.pptx
Module 03 Distribution Works.pptx
 
Canal of design
Canal of designCanal of design
Canal of design
 
Canals
CanalsCanals
Canals
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdf
 
3. Highway Drainage.pdf
3. Highway Drainage.pdf3. Highway Drainage.pdf
3. Highway Drainage.pdf
 
Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...Water Resources Engineering types of wells with figures Denish Jangid Open we...
Water Resources Engineering types of wells with figures Denish Jangid Open we...
 
Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016Travis_Smith_Work_Term_Report_F2016
Travis_Smith_Work_Term_Report_F2016
 
Lined or non erodible design channel study
Lined or non erodible design channel studyLined or non erodible design channel study
Lined or non erodible design channel study
 
Module-5.pptx
Module-5.pptxModule-5.pptx
Module-5.pptx
 
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
• Sediment Transport • The Earthen Canal Section • Lined Canals & Its Advantages
 
presentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptxpresentation of industrial training irrigation (2).pptx
presentation of industrial training irrigation (2).pptx
 
CHAPTER 5- Water Conveynance and Control-1.pptx
CHAPTER  5- Water Conveynance and Control-1.pptxCHAPTER  5- Water Conveynance and Control-1.pptx
CHAPTER 5- Water Conveynance and Control-1.pptx
 
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx
479112516-KT-BANDHARA-REDESIGN-3-1-pptx.pptx
 

Mais de Aditya Mistry

Earthquake design example
Earthquake design example Earthquake design example
Earthquake design example Aditya Mistry
 
Urban transportation system
Urban transportation systemUrban transportation system
Urban transportation systemAditya Mistry
 
Water and Waste Water Engineering
Water and Waste Water EngineeringWater and Waste Water Engineering
Water and Waste Water EngineeringAditya Mistry
 
Railway Bridge and Tunnel Engineering
Railway Bridge and Tunnel EngineeringRailway Bridge and Tunnel Engineering
Railway Bridge and Tunnel EngineeringAditya Mistry
 
Applied Fluid Mechanics
Applied Fluid MechanicsApplied Fluid Mechanics
Applied Fluid MechanicsAditya Mistry
 
Advance Construction & Equipment
Advance Construction & EquipmentAdvance Construction & Equipment
Advance Construction & EquipmentAditya Mistry
 
Traffic control devices
Traffic control devicesTraffic control devices
Traffic control devicesAditya Mistry
 
Shear strength of soil
Shear strength of soilShear strength of soil
Shear strength of soilAditya Mistry
 
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATIONAPPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATIONAditya Mistry
 
Special concrete and concreting method
Special concrete and concreting methodSpecial concrete and concreting method
Special concrete and concreting methodAditya Mistry
 
Modern surveying instruments
Modern surveying instrumentsModern surveying instruments
Modern surveying instrumentsAditya Mistry
 
Earthquake resistant building
Earthquake resistant buildingEarthquake resistant building
Earthquake resistant buildingAditya Mistry
 
Direct and bending stress
Direct and bending stressDirect and bending stress
Direct and bending stressAditya Mistry
 

Mais de Aditya Mistry (20)

Valuation
ValuationValuation
Valuation
 
Traffic studies
Traffic studiesTraffic studies
Traffic studies
 
Earthquake design example
Earthquake design example Earthquake design example
Earthquake design example
 
Urban transportation system
Urban transportation systemUrban transportation system
Urban transportation system
 
Water and Waste Water Engineering
Water and Waste Water EngineeringWater and Waste Water Engineering
Water and Waste Water Engineering
 
Railway Bridge and Tunnel Engineering
Railway Bridge and Tunnel EngineeringRailway Bridge and Tunnel Engineering
Railway Bridge and Tunnel Engineering
 
Applied Fluid Mechanics
Applied Fluid MechanicsApplied Fluid Mechanics
Applied Fluid Mechanics
 
Advance Construction & Equipment
Advance Construction & EquipmentAdvance Construction & Equipment
Advance Construction & Equipment
 
Traffic control devices
Traffic control devicesTraffic control devices
Traffic control devices
 
Shear strength of soil
Shear strength of soilShear strength of soil
Shear strength of soil
 
Stiffness Matrix
Stiffness MatrixStiffness Matrix
Stiffness Matrix
 
Flood Management
Flood ManagementFlood Management
Flood Management
 
Air Pollution
Air PollutionAir Pollution
Air Pollution
 
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATIONAPPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
APPLICATION OF SCIENCE AND TECHNOLOGY FOR DISASTER MANAGEMENT & MITIGATION
 
Special concrete and concreting method
Special concrete and concreting methodSpecial concrete and concreting method
Special concrete and concreting method
 
Modern surveying instruments
Modern surveying instrumentsModern surveying instruments
Modern surveying instruments
 
Earthquake resistant building
Earthquake resistant buildingEarthquake resistant building
Earthquake resistant building
 
Direct and bending stress
Direct and bending stressDirect and bending stress
Direct and bending stress
 
Temporary works
Temporary worksTemporary works
Temporary works
 
Notches and weir
Notches and weirNotches and weir
Notches and weir
 

Último

Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Romil Mishra
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONjhunlian
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxsiddharthjain2303
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书rnrncn29
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsResearcher Researcher
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionMebane Rash
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTSneha Padhiar
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.elesangwon
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingBootNeck1
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solidnamansinghjarodiya
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfNainaShrivastava14
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating SystemRashmi Bhat
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxStephen Sitton
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfalene1
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptJohnWilliam111370
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdfCaalaaAbdulkerim
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosVictor Morales
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSsandhya757531
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewsandhya757531
 

Último (20)

Designing pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptxDesigning pile caps according to ACI 318-19.pptx
Designing pile caps according to ACI 318-19.pptx
 
Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________Gravity concentration_MI20612MI_________
Gravity concentration_MI20612MI_________
 
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTIONTHE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
THE SENDAI FRAMEWORK FOR DISASTER RISK REDUCTION
 
Energy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptxEnergy Awareness training ppt for manufacturing process.pptx
Energy Awareness training ppt for manufacturing process.pptx
 
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
『澳洲文凭』买麦考瑞大学毕业证书成绩单办理澳洲Macquarie文凭学位证书
 
Novel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending ActuatorsNovel 3D-Printed Soft Linear and Bending Actuators
Novel 3D-Printed Soft Linear and Bending Actuators
 
US Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of ActionUS Department of Education FAFSA Week of Action
US Department of Education FAFSA Week of Action
 
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENTFUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
FUNCTIONAL AND NON FUNCTIONAL REQUIREMENT
 
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
2022 AWS DNA Hackathon 장애 대응 솔루션 jarvis.
 
System Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event SchedulingSystem Simulation and Modelling with types and Event Scheduling
System Simulation and Modelling with types and Event Scheduling
 
Engineering Drawing section of solid
Engineering Drawing     section of solidEngineering Drawing     section of solid
Engineering Drawing section of solid
 
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdfPaper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
Paper Tube : Shigeru Ban projects and Case Study of Cardboard Cathedral .pdf
 
Input Output Management in Operating System
Input Output Management in Operating SystemInput Output Management in Operating System
Input Output Management in Operating System
 
Turn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptxTurn leadership mistakes into a better future.pptx
Turn leadership mistakes into a better future.pptx
 
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdfComprehensive energy systems.pdf Comprehensive energy systems.pdf
Comprehensive energy systems.pdf Comprehensive energy systems.pdf
 
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.pptROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
ROBOETHICS-CCS345 ETHICS AND ARTIFICIAL INTELLIGENCE.ppt
 
Research Methodology for Engineering pdf
Research Methodology for Engineering pdfResearch Methodology for Engineering pdf
Research Methodology for Engineering pdf
 
KCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitosKCD Costa Rica 2024 - Nephio para parvulitos
KCD Costa Rica 2024 - Nephio para parvulitos
 
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMSHigh Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
High Voltage Engineering- OVER VOLTAGES IN ELECTRICAL POWER SYSTEMS
 
Artificial Intelligence in Power System overview
Artificial Intelligence in Power System overviewArtificial Intelligence in Power System overview
Artificial Intelligence in Power System overview
 

Cross section of the canal, balancing depth and canal fsl

  • 2. TOPIC NAME: CROSS SECTION OF THE CANAL, BALANCING DEPTH, AND CANAL F.S.L. SUBJECT CODE: 2I70609 BRANCH: CIVIL ENGG,. 7TH SEM PREPARED BY: GUIDED BY: PROF. MAMTA PATEL SR NO. NAME ENROLL. NO. 1. PATEL PRASHANT S. 141100106078 2. PATEL TWINKAL D. 141100106092 3. MISTRY ADITYA P. 151103106009 4. PATEL KAJAL M. 151103106011 5. RATNANI MANISHA N. 151103106016
  • 3. CONTENT  Cross section of an irrigation channel - In cutting - In filling - In partial cutting and filling  Balancing depth  Canal F.S.L.
  • 4. CROSS SECTION OF AN IRRIGATION CHANNEL An irrigation channel section may be either, 1) In cutting 2) In filling 3) In partial cutting and filling Cross section of canal in cutting
  • 5. Cross section of canal in filling Cross section of canal in partial cutting and filling
  • 6. The main components of the canal cross- section are: 1. Side slope 2. Berm 3. Free board 4. Banks 5. Dowla 6. Inspection road 7. Borrow pits 8. Spoil bank 9. Lang width 10. Counter berm
  • 7. 1. SIDE SLOPES  The side slope of channel depend on the nature of the soil.  In average loam soil the side slopes are usually kept 1 : 1 in cutting and 1.5 : 1in filling.  In sandy soil say 1.5 : 1 in cutting and 2 : 1 in filling to be used.
  • 8. 2. BERM  Berm is the horizontal distance left at ground level between the toe of the bank and top edge of cutting.  Berm is provided additional strength to bank and help in safe guarding them against breaches.  It is also provided for future widening of channel.
  • 9. 3.FREE BOARD Free board is defined as the vertical distance between the designed full supply level ( F.S.L.) in the canal and top level of canal banks. It is provided to allow for wave action and floating debris.  free board is consideration of - canal capacity - soil characteristics - hydraulic gradient
  • 10. 4. BANKS The purpose of the bank is to retain water so long as the berm is not formed. They thus have to with stand full pressure of water above the ground level. 5. INSPECTION ROAD  An inspection road is usually provided on one or both bank of the canal for the purpose of inspection, repair and maintenance of the roads.
  • 11. 6.DOWEL As the measure of safety for the vehicles, a raised projection of soil, called dowel, is provided on the channel side of the inspection road. The top width of dowel is 0.5m, height above road level is 0.5m and side slope is 1.5 : 1.
  • 12. 7. BORROW PITS Borrow pits are small pits which are dug to obtain the extra earth for making banks if the soil obtained from cutting is not sufficient. The borrow pits are usually located at distance of 4D to 6D away from outer toe of the bank. The borrow pits may be located either inside or outside the channel.
  • 13. 8. SPOIL BANK When the quantity of earth obtained from excavation or cutting of the channel section is in excess of the quantity required for forming the bank and service road then extra earth is usually deposited in the form of spoil bank.
  • 14. 9. LAND WIDTH The total land required for the construction of channel is divided in to two parts. Permanent land and temporary land. The permanent land is the land which will be required permanently during and after construction of channel. During construction period of the canal, some extra land is required for storage of materials and machineries nearer the site of construction.
  • 15. 10.COUNTER BERM Even after providing the usual embankment section of a bank, saturation gradient may cut the downstream side of the bank . In such case the saturation line should always be covered by 0.3 to 0.6 m of earth.
  • 16. BALANCING DEPTH The channel section is entirely in cutting, the extra soil has to be deposited in spoil bank. For the channel section entirely in filling the soil has to be obtained from borrow pits. In both case required double handling and increased cost of earth work. If for a channel section the depth of cutting is such that the quantity of excavation or cutting is equal to the earth filling required for making the banks, then depth of cutting is known as balancing depth or most economical depth of cutting.
  • 17. The normal maximum operating water level of a water storage when not affected by floods.  This water level corresponds to 100% capacity. CANAL F.S.L.