HOW TO PREPARE
THE RECOVERY /
REVISED
SCHEDULE
Rev.2
By. Engr. Abdulhay Mohamed Ghanem
Sr. Planning Engineer at Abdullah A. Alkodari Co.
Purpose of this document :
Purpose of this document is to explain
recovery/revised schedule properly by using
Who should read this document
This document is for who is concern about
schedulers, projects controllers and projects managers
The guys who will read and utilize
Primavera software like global changes, export
effect on schedule updating and this equation
BL Start). i.e A%C = (DD – BLST) / (
this document.
Let us start with preparation of
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
schedule is a new baseline schedule to rectify any occurred delay to the
whether by using crashing technique or fast track technique.
My example in this document, I am
schedule you have to make sure of the following:
1- No activities are out of sequence.
2- No activities with unsatisfied relation.
3- Remaining early start of all in progress activities is one day after data date
Regarding point no. 3, I will explain why we should fulfill
which will be applied.
4- Detach the baseline and separate the
If the updated schedule has an assigned baseline you shall remove that baseline.
is to explain and help how to use Primavera software to create a
recovery/revised schedule properly by using Primavera tools.
document:
who is concern about Primavera and project management such planners,
projects controllers and projects managers.
utilize this document should be conversant the following tools and options in
global changes, export and import in excel format, percent
effect on schedule updating and this equation Activity % complete = (Data date –
BLST) / (BLF – BLST), Which will be used to conclude the used
Let us start with preparation of recovery schedule.
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
schedule is a new baseline schedule to rectify any occurred delay to the project to meet contractual end
whether by using crashing technique or fast track technique.
example in this document, I am using percent complete type physical, before prepare your recovery
have to make sure of the following:
are out of sequence.
satisfied relation.
Remaining early start of all in progress activities is one day after data date
Regarding point no. 3, I will explain why we should fulfill this condition during explain the global changes
and separate the current progress.
If the updated schedule has an assigned baseline you shall remove that baseline.
Data Date is 31.May.15
rimavera software to create a
rimavera and project management such planners,
should be conversant the following tools and options in
percent complete type and its
BL start) / (BL finish –
Which will be used to conclude the used equation in
schedule.
Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery
project to meet contractual end
prepare your recovery
Remaining early start of all in progress activities is one day after data date not more.
lain the global changes
If the updated schedule has an assigned baseline you shall remove that baseline.
Data Date is 31.May.15
Tip: If this message appeared to you.
It means you have to release the old baseline from assigning to the current project.
assign baselines and change to current pro
If this message appeared to you.
means you have to release the old baseline from assigning to the current project.
and change to current project in mentioned tow positions, and then you can delete.
means you have to release the old baseline from assigning to the current project. From project –
ject in mentioned tow positions, and then you can delete.
5- Delete finish constraint of the project.
In projects layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
6- Press F9 to run scheduling–
scheduling options).
Delete finish constraint of the project.
layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
– Using retained logic option before scheduling progressed activities (From
layout, select dates label then remove date in cell of must finish by.(highlight it then press delete)
option before scheduling progressed activities (From
Now you can adjust the remaining duration
in progress activities and the relations of not started activities to prepare a proper recovery schedule
accordance with view of PM & CM and site
Tip: If you are using duration type fix duration and units,
you are using duration type fix duration and unit/time you will find your budgeted
planned in your baseline schedule before creating the recovery sc
end of this document how to solve.
Now we will apply the following global change to the current project as follow
a- Original duration of
b- Planned start date and planned finish date to be equal actual date for completed
activities.
Now you can adjust the remaining duration (remember I am using physical type for percent complete type)
in progress activities and the relations of not started activities to prepare a proper recovery schedule
accordance with view of PM & CM and site requirement to close the project on contractual end
ion type fix duration and units, you will find your budgeted total cost still the same. If
you are using duration type fix duration and unit/time you will find your budgeted total cost is more than you
planned in your baseline schedule before creating the recovery schedule. To solve this issue I will explain at the
is document how to solve.
Now we will apply the following global change to the current project as following:
nal duration of completed activities. (Original should = actual)
Planned start date and planned finish date to be equal actual date for completed
(remember I am using physical type for percent complete type) of
in progress activities and the relations of not started activities to prepare a proper recovery schedule in
requirement to close the project on contractual end.
you will find your budgeted total cost still the same. If
total cost is more than you
solve this issue I will explain at the
. (Original should = actual)
Planned start date and planned finish date to be equal actual date for completed
C- Original duration of in progress activities. (
d - Planned start date to be equal actual date for in progress activities.
After complete all steps. Did you asked yourself why
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
67,528,929.48 SAR in my example?
you glanced to the snapshot below
Original duration of in progress activities. (Original = actual + remaining ).
Planned start date to be equal actual date for in progress activities.
After complete all steps. Did you asked yourself why EV at Data date
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
SAR in my example?(remember I am using percent complete type physical)
you glanced to the snapshot below
actual + remaining ).
Planned start date to be equal actual date for in progress activities.
date (31.May.15) not equal
PV of the new recovery baseline? And how we can adjust it to make EV = PV =
(remember I am using percent complete type physical). If
In our example I used budgeted values
to the others two options it will not affect on the result as shown in previous snapshot.
From - admin - admin preferences
In our example I used budgeted values with current dates (Default option) even you change it
to the others two options it will not affect on the result as shown in previous snapshot.
admin preferences
(Default option) even you change it
to the others two options it will not affect on the result as shown in previous snapshot.
What if you are using
bingeing in your baseline schedule before
previous global changes
default to at completion values with current dates
1- EV = PV but not equal
2- The activities percent complete will be changed as well to values more than the actual
activities % complete
Note: in this example,
same data date is 68,876,923.16
Snapshot No.1
What if you are using percent complete type duration?. if you are using this type from
bingeing in your baseline schedule before creating the recovery baseline,
previous global changes then you changed the option of earned value calculation from
default to at completion values with current dates you will find the following:
EV = PV but not equal 68,876,923.16 SAR
The activities percent complete will be changed as well to values more than the actual
activities % complete at site. Please compare between snapshot No.1 and No.2.
in this example, we are using percent complete type duration the earned value at the
68,876,923.16 SAR
using this type from
creating the recovery baseline, then you applied all
then you changed the option of earned value calculation from
will find the following:
The activities percent complete will be changed as well to values more than the actual
at site. Please compare between snapshot No.1 and No.2.
we are using percent complete type duration the earned value at the
Note: The variance between PL and EV in snapshot No. 2
available.
With return to previous example (Physical), and the familiar equation of
– BL start) / (BL finish – BL start)
deferent formula. (Ghanem Equation
Let us see how I concluded this equation
A%C = (DD – BLST) / (BLF
Also OD = ED + RD
Where OD = Original duration of the activity.
ED = Elapsed duration of in progress activity.
RD = Remaining duration of in progress activity.
Then A%C = (DD – BLST) / (ED + RD)
A%C = ED / (ED + RD)
Where ED = DD – BLST for in progress activity.
A%C X ED + A%C X R
A%C X RD = ED – A%C X ED
RD = (ED / A%C) – ED
RD = ED ((1 / A%C)
While ED = DD –
Then DD – BLST = RD / ((1 / A%C)
Then BLST = DD
Snapshot No.2
The variance between PL and EV in snapshot No. 2 due to condition No.3 in page No.
example (Physical), and the familiar equation of Activity % complete = (Data date
BL start) which I will use it to adjust EV = PL = 67,528,929.48
Ghanem Equation)
BLST = DD – (RD / ((1 / A%C) – 1)))
Let us see how I concluded this equation
BLST) / (BLF-BLST) whereas BLF – BLST = OD
Where OD = Original duration of the activity.
ED = Elapsed duration of in progress activity.
RD = Remaining duration of in progress activity.
BLST) / (ED + RD)
A%C = ED / (ED + RD)
BLST for in progress activity.
A%C X ED + A%C X RD = ED
A%C X ED
ED
RD = ED ((1 / A%C) – 1)
– BLST and ED = RD / ((1 / A%C) – 1)
BLST = RD / ((1 / A%C) – 1)
BLST = DD – (RD / ((1 / A%C) – 1)))
due to condition No.3 in page No. 2 is not
Activity % complete = (Data date
67,528,929.48 SAR but in
1)))
BLST = OD
Note: DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
schedule.
If you filtered the completed a
problem will arise (EV not equal PV).
issue.
Export an excel sheet contain the following to work out
from Enterprise menu
DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
If you filtered the completed activities you will find EV = PV. while in progress activities,
problem will arise (EV not equal PV). therefore we will use the previous formula to solve this
Export an excel sheet contain the following to work out the formula. Before exporting, create
from Enterprise menu – user defined fields tow new fields as shown.
DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline
V. while in progress activities, the
previous formula to solve this
. Before exporting, create
With reference to third
condition not available the new original duration
vise is correct. So, this availability of this condition is very important to work out formula
third condition in page No.2, if you look to the following you will find
condition not available the new original duration will be less than the actual + remaining while
this availability of this condition is very important to work out formula
Condition is not
available so 67+30
not equal 103
In Primavera Actual
Duration of in progress
activity is the elapsed
duration (ED)
condition in page No.2, if you look to the following you will find if the
will be less than the actual + remaining while
this availability of this condition is very important to work out formula.
In Primavera Actual
Duration of in progress
activity is the elapsed
Let us complete exporting operationLet us complete exporting operation
Condition is available
so 67+30 = 97
Only in progress
activity
n progress
Then add comma from option DataThen add comma from option Data – Text to columns
Copy – Past values
Apply this global change to calculate the new actual start date.Apply this global change to calculate the new actual start date.
Data Date
Delete operation area then
save then import to
Priamvera
Delete operation area then
Then apply this global change to make actual start equal to New Act st.
The result will be as shown below.
Reuse global change No. C & D
Then apply this global change to make actual start equal to New Act st.
The result will be as shown below.
to adjust the original duration, the result will be as the following:
Note
Then apply this global change to make actual start equal to New Act st.
result will be as the following:
Now EV = PV with variance 122,608
Put the contractual end (Must finish by)
Wait for Rev.3
In rev.3 I will talk exhaustively about revised schedule,
schedule and how to use excel sheet
apply some changes on that base line schedule
type of the activities.
122,608 SAR (variance = 0.18% of earned value can be neglected)
(Must finish by), maintain, assign your new created recovery
about revised schedule, How to save actual dates to
and how to use excel sheet to transfer data from updated schedule to ba
apply some changes on that base line schedule as mentioned in page No. 5 about
0.18% of earned value can be neglected)
your new created recovery, enjoy.
How to save actual dates to submit as built
to transfer data from updated schedule to baseline schedule after
as mentioned in page No. 5 about modifying duration
My contacts informaiton
Skype account : en_ghanem
Email : Abdelhay.Ghanem@gmail.com
Mobile Phone : +966-546810855 , +966-593068907

Mais conteúdo relacionado

Mais procurados

Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery SchedulingChris Carson
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3Matiwos Tsegaye
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlM Maged Hegazy, LLM, MBA, CCP, P3O
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesThe Vertex Companies, LLC
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةM Maged Hegazy, LLM, MBA, CCP, P3O
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Tim Lloyd
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact AnalysisChris Carson
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement ignitetribes
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Charlie Jackson
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueChris Carson
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - TutorialRajeev Sharma
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of schedulingjmd2011
 

Mais procurados (20)

Recovery Scheduling
Recovery SchedulingRecovery Scheduling
Recovery Scheduling
 
Delay - EOT claims
Delay - EOT claimsDelay - EOT claims
Delay - EOT claims
 
Primavera p6 18.8 planning and scheduling guide r3
Primavera p6 18.8 planning and  scheduling guide r3Primavera p6 18.8 planning and  scheduling guide r3
Primavera p6 18.8 planning and scheduling guide r3
 
Earned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project ControlEarned Value Management - Leading & Misleading in Project Control
Earned Value Management - Leading & Misleading in Project Control
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 
VERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule AnalysesVERTEX Construction Delays and Forensic Schedule Analyses
VERTEX Construction Delays and Forensic Schedule Analyses
 
Pmp Final Review - M Maged
Pmp Final Review - M MagedPmp Final Review - M Maged
Pmp Final Review - M Maged
 
مقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافيةمقدمة عن إدارة التكاليف والشهادات الاحترافية
مقدمة عن إدارة التكاليف والشهادات الاحترافية
 
Delay analysis ... wise after the event.
Delay analysis ... wise after the event.Delay analysis ... wise after the event.
Delay analysis ... wise after the event.
 
Top10 planning fundamentals...
Top10 planning fundamentals...Top10 planning fundamentals...
Top10 planning fundamentals...
 
Time Impact Analysis
Time Impact AnalysisTime Impact Analysis
Time Impact Analysis
 
Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement Promo_Epc project rule of credit and progress measurement
Promo_Epc project rule of credit and progress measurement
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™Lessons Learned - Schedule Updating And Maintenance Using Primavera™
Lessons Learned - Schedule Updating And Maintenance Using Primavera™
 
Schedule Recovery Using Earned Value
Schedule Recovery Using Earned ValueSchedule Recovery Using Earned Value
Schedule Recovery Using Earned Value
 
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation SlidesExtension of Time (EOT) & Related Costs in Construction - Presentation Slides
Extension of Time (EOT) & Related Costs in Construction - Presentation Slides
 
Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
Project Scheduling & Controls
Project Scheduling & ControlsProject Scheduling & Controls
Project Scheduling & Controls
 
Primavera - Tutorial
Primavera - TutorialPrimavera - Tutorial
Primavera - Tutorial
 
Fundamentals of scheduling
Fundamentals of schedulingFundamentals of scheduling
Fundamentals of scheduling
 

Destaque

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysiskatrin enders
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time AnalysisFarhan Moosa
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractProject Controls Expo
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dateskrunalplanning
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorialKetut Swandana
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruptionDr Ezzat Mansour
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Comparative Study of ACH and ECH
Comparative Study of ACH and ECHComparative Study of ACH and ECH
Comparative Study of ACH and ECHKamran Akram
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2danieljohn810
 
WASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final VersionWASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final VersionIshmael Yamson
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowAbdullah Ahmed, PMP, RMP
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMIChris Carson
 
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студииTHE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студииFaculty of Economics Ljubljana in Skopje
 
Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)Syafil Kahfi
 

Destaque (20)

Methods of delay analysis
Methods of delay analysisMethods of delay analysis
Methods of delay analysis
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of ContractSession W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
Session W2 - Delay Claims and Analysis Based on FIDIC Forms of Contract
 
Understanding p6 dates
Understanding p6 datesUnderstanding p6 dates
Understanding p6 dates
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Pdf primavera tutorial
Pdf primavera tutorialPdf primavera tutorial
Pdf primavera tutorial
 
The analysis and valuation of disruption
The analysis and valuation of disruptionThe analysis and valuation of disruption
The analysis and valuation of disruption
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
Comparative Study of ACH and ECH
Comparative Study of ACH and ECHComparative Study of ACH and ECH
Comparative Study of ACH and ECH
 
Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2Understanding Constraints and Relationships in Primavera P6 8.2
Understanding Constraints and Relationships in Primavera P6 8.2
 
WASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final VersionWASPAG Presentation on ICH - Final Version
WASPAG Presentation on ICH - Final Version
 
Strategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should knowStrategic Planning first entry - that everybody should know
Strategic Planning first entry - that everybody should know
 
Claims
ClaimsClaims
Claims
 
Activity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in PrimaveraActivity Duration Types Explained with example in Primavera
Activity Duration Types Explained with example in Primavera
 
Schedule Review PMI
Schedule Review PMISchedule Review PMI
Schedule Review PMI
 
What's New in Primavera P6 16.2
What's New in Primavera P6 16.2What's New in Primavera P6 16.2
What's New in Primavera P6 16.2
 
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
Difference between versions of primavera 6,7,R8.1,R8.2,R8.3
 
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студииTHE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
THE IMPORTANCE OF FDI IN THE MACEDONIAN ECONOMY - MBA магистерски студии
 
Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)Chapter 1 (overview of derivatives)
Chapter 1 (overview of derivatives)
 
7. curriculum vitae
7. curriculum vitae7. curriculum vitae
7. curriculum vitae
 

Semelhante a HOW TO PREPARE A RECOVERY SCHEDULE

Project Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docxProject Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docxbriancrawford30935
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingSHAZEBALIKHAN1
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxmaoanderton
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment DetailsSoe Naing Win
 
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docxGanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docxbudbarber38650
 
Pm0011 – project planning
Pm0011 – project planningPm0011 – project planning
Pm0011 – project planningsmumbahelp
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET Journal
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance ManagementCraig Brown
 
6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docxalinainglis
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handoutZenawi Mehari
 

Semelhante a HOW TO PREPARE A RECOVERY SCHEDULE (20)

Project Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docxProject Scope and Business Objective WorksheetA. General Informa.docx
Project Scope and Business Objective WorksheetA. General Informa.docx
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Construction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential BuildingConstruction Project Schedule Template- Residential Building
Construction Project Schedule Template- Residential Building
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
LibrePlan Audiovisual documentation
LibrePlan Audiovisual documentationLibrePlan Audiovisual documentation
LibrePlan Audiovisual documentation
 
MS Project 2010 Training
MS Project 2010 TrainingMS Project 2010 Training
MS Project 2010 Training
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docxSheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
Sheet1HCM3002 Economics of HealthcareChoose a Health Plan (Part 2).docx
 
MS Project Guide.pdf
MS Project Guide.pdfMS Project Guide.pdf
MS Project Guide.pdf
 
09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details09 Fine-tuning Assignment Details
09 Fine-tuning Assignment Details
 
Earned Effort Analysis
Earned Effort AnalysisEarned Effort Analysis
Earned Effort Analysis
 
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docxGanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
GanttChartGantt ChartVersion 1.7.3© 2006-2014 Vertex42 LLCVert.docx
 
Pm0011 – project planning
Pm0011 – project planningPm0011 – project planning
Pm0011 – project planning
 
IRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project ScheduleIRJET- Quality Matrices of Project Schedule
IRJET- Quality Matrices of Project Schedule
 
Software Project Management Spm1176
Software Project Management Spm1176Software Project Management Spm1176
Software Project Management Spm1176
 
7 cost PMBOK
7 cost PMBOK7 cost PMBOK
7 cost PMBOK
 
The Project Management Process - Week 9 Performance Management
The Project Management Process - Week 9   Performance ManagementThe Project Management Process - Week 9   Performance Management
The Project Management Process - Week 9 Performance Management
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx6 I need the overall earned value analysis.  (That is, overall i.docx
6 I need the overall earned value analysis.  (That is, overall i.docx
 
Project 2007 full handout
Project 2007 full handoutProject 2007 full handout
Project 2007 full handout
 

Último

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfROCENODodongVILLACER
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfAsst.prof M.Gokilavani
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptSAURABHKUMAR892774
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...Chandu841456
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringJuanCarlosMorales19600
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the weldingMuhammadUzairLiaqat
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleAlluxio, Inc.
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgsaravananr517913
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncssuser2ae721
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxk795866
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catcherssdickerson1
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - GuideGOPINATHS437943
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Último (20)

Risk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdfRisk Assessment For Installation of Drainage Pipes.pdf
Risk Assessment For Installation of Drainage Pipes.pdf
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdfCCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
CCS355 Neural Networks & Deep Learning Unit 1 PDF notes with Question bank .pdf
 
Arduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.pptArduino_CSE ece ppt for working and principal of arduino.ppt
Arduino_CSE ece ppt for working and principal of arduino.ppt
 
An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...An experimental study in using natural admixture as an alternative for chemic...
An experimental study in using natural admixture as an alternative for chemic...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Piping Basic stress analysis by engineering
Piping Basic stress analysis by engineeringPiping Basic stress analysis by engineering
Piping Basic stress analysis by engineering
 
welding defects observed during the welding
welding defects observed during the weldingwelding defects observed during the welding
welding defects observed during the welding
 
Correctly Loading Incremental Data at Scale
Correctly Loading Incremental Data at ScaleCorrectly Loading Incremental Data at Scale
Correctly Loading Incremental Data at Scale
 
young call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Serviceyoung call girls in Green Park🔝 9953056974 🔝 escort Service
young call girls in Green Park🔝 9953056974 🔝 escort Service
 
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfgUnit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
Unit7-DC_Motors nkkjnsdkfnfcdfknfdgfggfg
 
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsyncWhy does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
Why does (not) Kafka need fsync: Eliminating tail latency spikes caused by fsync
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Introduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptxIntroduction-To-Agricultural-Surveillance-Rover.pptx
Introduction-To-Agricultural-Surveillance-Rover.pptx
 
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor CatchersTechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
TechTAC® CFD Report Summary: A Comparison of Two Types of Tubing Anchor Catchers
 
Transport layer issues and challenges - Guide
Transport layer issues and challenges - GuideTransport layer issues and challenges - Guide
Transport layer issues and challenges - Guide
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

HOW TO PREPARE A RECOVERY SCHEDULE

  • 1. HOW TO PREPARE THE RECOVERY / REVISED SCHEDULE Rev.2 By. Engr. Abdulhay Mohamed Ghanem Sr. Planning Engineer at Abdullah A. Alkodari Co.
  • 2. Purpose of this document : Purpose of this document is to explain recovery/revised schedule properly by using Who should read this document This document is for who is concern about schedulers, projects controllers and projects managers The guys who will read and utilize Primavera software like global changes, export effect on schedule updating and this equation BL Start). i.e A%C = (DD – BLST) / ( this document. Let us start with preparation of Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery schedule is a new baseline schedule to rectify any occurred delay to the whether by using crashing technique or fast track technique. My example in this document, I am schedule you have to make sure of the following: 1- No activities are out of sequence. 2- No activities with unsatisfied relation. 3- Remaining early start of all in progress activities is one day after data date Regarding point no. 3, I will explain why we should fulfill which will be applied. 4- Detach the baseline and separate the If the updated schedule has an assigned baseline you shall remove that baseline. is to explain and help how to use Primavera software to create a recovery/revised schedule properly by using Primavera tools. document: who is concern about Primavera and project management such planners, projects controllers and projects managers. utilize this document should be conversant the following tools and options in global changes, export and import in excel format, percent effect on schedule updating and this equation Activity % complete = (Data date – BLST) / (BLF – BLST), Which will be used to conclude the used Let us start with preparation of recovery schedule. Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery schedule is a new baseline schedule to rectify any occurred delay to the project to meet contractual end whether by using crashing technique or fast track technique. example in this document, I am using percent complete type physical, before prepare your recovery have to make sure of the following: are out of sequence. satisfied relation. Remaining early start of all in progress activities is one day after data date Regarding point no. 3, I will explain why we should fulfill this condition during explain the global changes and separate the current progress. If the updated schedule has an assigned baseline you shall remove that baseline. Data Date is 31.May.15 rimavera software to create a rimavera and project management such planners, should be conversant the following tools and options in percent complete type and its BL start) / (BL finish – Which will be used to conclude the used equation in schedule. Firstly we have to know what is the meaning of recovery schedule? . We can simply say that the recovery project to meet contractual end prepare your recovery Remaining early start of all in progress activities is one day after data date not more. lain the global changes If the updated schedule has an assigned baseline you shall remove that baseline. Data Date is 31.May.15
  • 3. Tip: If this message appeared to you. It means you have to release the old baseline from assigning to the current project. assign baselines and change to current pro If this message appeared to you. means you have to release the old baseline from assigning to the current project. and change to current project in mentioned tow positions, and then you can delete. means you have to release the old baseline from assigning to the current project. From project – ject in mentioned tow positions, and then you can delete.
  • 4. 5- Delete finish constraint of the project. In projects layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) 6- Press F9 to run scheduling– scheduling options). Delete finish constraint of the project. layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) – Using retained logic option before scheduling progressed activities (From layout, select dates label then remove date in cell of must finish by.(highlight it then press delete) option before scheduling progressed activities (From
  • 5. Now you can adjust the remaining duration in progress activities and the relations of not started activities to prepare a proper recovery schedule accordance with view of PM & CM and site Tip: If you are using duration type fix duration and units, you are using duration type fix duration and unit/time you will find your budgeted planned in your baseline schedule before creating the recovery sc end of this document how to solve. Now we will apply the following global change to the current project as follow a- Original duration of b- Planned start date and planned finish date to be equal actual date for completed activities. Now you can adjust the remaining duration (remember I am using physical type for percent complete type) in progress activities and the relations of not started activities to prepare a proper recovery schedule accordance with view of PM & CM and site requirement to close the project on contractual end ion type fix duration and units, you will find your budgeted total cost still the same. If you are using duration type fix duration and unit/time you will find your budgeted total cost is more than you planned in your baseline schedule before creating the recovery schedule. To solve this issue I will explain at the is document how to solve. Now we will apply the following global change to the current project as following: nal duration of completed activities. (Original should = actual) Planned start date and planned finish date to be equal actual date for completed (remember I am using physical type for percent complete type) of in progress activities and the relations of not started activities to prepare a proper recovery schedule in requirement to close the project on contractual end. you will find your budgeted total cost still the same. If total cost is more than you solve this issue I will explain at the . (Original should = actual) Planned start date and planned finish date to be equal actual date for completed
  • 6. C- Original duration of in progress activities. ( d - Planned start date to be equal actual date for in progress activities. After complete all steps. Did you asked yourself why PV of the new recovery baseline? And how we can adjust it to make EV = PV = 67,528,929.48 SAR in my example? you glanced to the snapshot below Original duration of in progress activities. (Original = actual + remaining ). Planned start date to be equal actual date for in progress activities. After complete all steps. Did you asked yourself why EV at Data date PV of the new recovery baseline? And how we can adjust it to make EV = PV = SAR in my example?(remember I am using percent complete type physical) you glanced to the snapshot below actual + remaining ). Planned start date to be equal actual date for in progress activities. date (31.May.15) not equal PV of the new recovery baseline? And how we can adjust it to make EV = PV = (remember I am using percent complete type physical). If
  • 7. In our example I used budgeted values to the others two options it will not affect on the result as shown in previous snapshot. From - admin - admin preferences In our example I used budgeted values with current dates (Default option) even you change it to the others two options it will not affect on the result as shown in previous snapshot. admin preferences (Default option) even you change it to the others two options it will not affect on the result as shown in previous snapshot.
  • 8. What if you are using bingeing in your baseline schedule before previous global changes default to at completion values with current dates 1- EV = PV but not equal 2- The activities percent complete will be changed as well to values more than the actual activities % complete Note: in this example, same data date is 68,876,923.16 Snapshot No.1 What if you are using percent complete type duration?. if you are using this type from bingeing in your baseline schedule before creating the recovery baseline, previous global changes then you changed the option of earned value calculation from default to at completion values with current dates you will find the following: EV = PV but not equal 68,876,923.16 SAR The activities percent complete will be changed as well to values more than the actual activities % complete at site. Please compare between snapshot No.1 and No.2. in this example, we are using percent complete type duration the earned value at the 68,876,923.16 SAR using this type from creating the recovery baseline, then you applied all then you changed the option of earned value calculation from will find the following: The activities percent complete will be changed as well to values more than the actual at site. Please compare between snapshot No.1 and No.2. we are using percent complete type duration the earned value at the
  • 9. Note: The variance between PL and EV in snapshot No. 2 available. With return to previous example (Physical), and the familiar equation of – BL start) / (BL finish – BL start) deferent formula. (Ghanem Equation Let us see how I concluded this equation A%C = (DD – BLST) / (BLF Also OD = ED + RD Where OD = Original duration of the activity. ED = Elapsed duration of in progress activity. RD = Remaining duration of in progress activity. Then A%C = (DD – BLST) / (ED + RD) A%C = ED / (ED + RD) Where ED = DD – BLST for in progress activity. A%C X ED + A%C X R A%C X RD = ED – A%C X ED RD = (ED / A%C) – ED RD = ED ((1 / A%C) While ED = DD – Then DD – BLST = RD / ((1 / A%C) Then BLST = DD Snapshot No.2 The variance between PL and EV in snapshot No. 2 due to condition No.3 in page No. example (Physical), and the familiar equation of Activity % complete = (Data date BL start) which I will use it to adjust EV = PL = 67,528,929.48 Ghanem Equation) BLST = DD – (RD / ((1 / A%C) – 1))) Let us see how I concluded this equation BLST) / (BLF-BLST) whereas BLF – BLST = OD Where OD = Original duration of the activity. ED = Elapsed duration of in progress activity. RD = Remaining duration of in progress activity. BLST) / (ED + RD) A%C = ED / (ED + RD) BLST for in progress activity. A%C X ED + A%C X RD = ED A%C X ED ED RD = ED ((1 / A%C) – 1) – BLST and ED = RD / ((1 / A%C) – 1) BLST = RD / ((1 / A%C) – 1) BLST = DD – (RD / ((1 / A%C) – 1))) due to condition No.3 in page No. 2 is not Activity % complete = (Data date 67,528,929.48 SAR but in 1))) BLST = OD
  • 10. Note: DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline schedule. If you filtered the completed a problem will arise (EV not equal PV). issue. Export an excel sheet contain the following to work out from Enterprise menu DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline If you filtered the completed activities you will find EV = PV. while in progress activities, problem will arise (EV not equal PV). therefore we will use the previous formula to solve this Export an excel sheet contain the following to work out the formula. Before exporting, create from Enterprise menu – user defined fields tow new fields as shown. DD, A%C and RD are fixed to fulfill the requirement of a proper recovery baseline V. while in progress activities, the previous formula to solve this . Before exporting, create
  • 11. With reference to third condition not available the new original duration vise is correct. So, this availability of this condition is very important to work out formula third condition in page No.2, if you look to the following you will find condition not available the new original duration will be less than the actual + remaining while this availability of this condition is very important to work out formula Condition is not available so 67+30 not equal 103 In Primavera Actual Duration of in progress activity is the elapsed duration (ED) condition in page No.2, if you look to the following you will find if the will be less than the actual + remaining while this availability of this condition is very important to work out formula. In Primavera Actual Duration of in progress activity is the elapsed
  • 12. Let us complete exporting operationLet us complete exporting operation Condition is available so 67+30 = 97 Only in progress activity n progress
  • 13. Then add comma from option DataThen add comma from option Data – Text to columns Copy – Past values
  • 14.
  • 15. Apply this global change to calculate the new actual start date.Apply this global change to calculate the new actual start date. Data Date Delete operation area then save then import to Priamvera Delete operation area then
  • 16. Then apply this global change to make actual start equal to New Act st. The result will be as shown below. Reuse global change No. C & D Then apply this global change to make actual start equal to New Act st. The result will be as shown below. to adjust the original duration, the result will be as the following: Note Then apply this global change to make actual start equal to New Act st. result will be as the following:
  • 17. Now EV = PV with variance 122,608 Put the contractual end (Must finish by) Wait for Rev.3 In rev.3 I will talk exhaustively about revised schedule, schedule and how to use excel sheet apply some changes on that base line schedule type of the activities. 122,608 SAR (variance = 0.18% of earned value can be neglected) (Must finish by), maintain, assign your new created recovery about revised schedule, How to save actual dates to and how to use excel sheet to transfer data from updated schedule to ba apply some changes on that base line schedule as mentioned in page No. 5 about 0.18% of earned value can be neglected) your new created recovery, enjoy. How to save actual dates to submit as built to transfer data from updated schedule to baseline schedule after as mentioned in page No. 5 about modifying duration
  • 18. My contacts informaiton Skype account : en_ghanem Email : Abdelhay.Ghanem@gmail.com Mobile Phone : +966-546810855 , +966-593068907