Chapter13 specialdecisionsituations

CHAPTER 13
SPECIAL DECISION SITUATIONS
OUTLINE
• Choice between mutually exclusive projects of unequal life
• Optimal timing decision
• Determination of economic life
• Interrelationship between investment and financing aspects
• Inflation and capital budgeting
• International capital budgeting
• Investment in capabilities
Choice between Mutually Exclusive Projects
of Unequal Life
For a proper comparison of the two alternatives, that have different lives,
we have to convert the present value of costs into a uniform annual
equivalent (UAE) figure – this is also called an equivalent annual cost
(EAC) figure. The UAE is a function of the present value of cost, the life
of the asset, and the discount rate. The UAE is simply:
PV Cost
PVIFAr,n
Uniform Annual Equivalent
PV of costs of machine A :
12,000 12,000 12,000 12,000 12,000
75,000 + + + + + = 118,260
(1.12) (1.12)2 (1.12)3 (1.12)4 (1.12)5
PV costs of machine B :
15,000 15,000 15,000
50,000 + + + = 86,030
(1.12) (1.12)2 (1.12)3
Machine A: UAE = 118,260 118,260
PVIFA12%,5 3.605
Machine B: UAE = 86,030 86,030
PVIFA12%,3 2.402
= 32,804
= 35,816
=
=
Optimal Timing
In real life, an investment is rarely a “now or never” proposition.
Typically, it can be undertaken now or at some point of time in future.
Given this option, the issue of optimal timing assumes significance.
Under conditions of certainty, the optimal timing may be
determined by using the following procedure.
1. Examine alternative dates (t) when the investment can be made.
2. Estimate the net future value as of each alternative date and
convert the same to its current value.
3. Choose the timing that has the highest current value
Determination of Economic Life
The economic life of an asset is conceptually defined as the period
after which the asset should be replaced to minimise the sum of
operating and maintenance costs and capital costs expressed on an
annual basis. Put differently, it is the replacement cycle that
minimises the uniform annual equivalent total cost, UAE (TC) of
operating and owning the asset. The UAE (TC) is simply the sum of
the uniform annual equivalent operating and maintenance cost, UAE
(OM), and the uniform annual equivalent capital cost, UAE (CC).
That is,
UAE (TC) = UAE (OM) + UAE (CC) (13.1)
S
UAE (CC)
Replacement
Period (in years)
Annualised Cost
Costs over the Life of a Machine
Interrelationship between the Investment and
Financing Aspects
• WACC is the right discount rate for a project that is a carbon copy
of the firm’s existing business.
• A project may have financing effects that differ from those of the
existing investments of the firm. It may have a different debt
capacity or be entitled to certain subsidies or have some special
financial features. In such cases the recommended method is to
calculate the adjusted NPV (or APV for short).
Adjusted Present Value (APV)
APV is calculated by first estimating the base-case NPV and then
adjusting it to reflect the financing side effects of the project.
The base-case NPV is the NPV of the project under the following
assumptions:
• The project is financed entirely by equity.
• There is no financing side effect like issue cost or subsidy
The present value of financing side effects is equal to:
• Present value of positive financing side effects like tax shield on
debt and availability of subsidies.
• Present value of negative financing side effects like issue costs and
financial distress costs associated with excessive leverage.
Illustration
Investment : Rs. 5 million
Net cash inflow : Rs.1 million per year for 8
years
Opportunity cost of capital : 15 percent
Issue cost of equity : 5 percent
Debt available : Rs.2.4 million at 14 percent
Repayment of debt : 8 equal annual instalments.
First instalment will be paid at
the end of first year
Tax rate : 40 percent
Illustration
Base – case NPV:
8 1,000,000
-5,000,000 +  = -512,700
t=1 (1.15)t
The base-case NPV has to be adjusted for two factors: (i) issue cost, and
(ii) tax-shield associated with debt.
Illustration
Out of the total financing requirement of the project Rs.2,600,000
will come from the equity sources and Rs.2,400,000 will come in
the form of debt finance. As the net equity finance required by the
project is Rs.2,600,000 and the issue costs would absorb 5 per cent
of the gross proceeds of the issue, the firm will have to issue
Rs.2,736,842 (Rs.2,600,000 / 0.95) of equity stock in order to
realise a net amount of Rs.2,600,000. The difference of Rs.136,842
is the cost of underwriting, brokerage, printing, and other issue
related expenses. The APV after adjustment for issue cost is :
APV = Base-case NPV – Issue cost
= -Rs.512,700 – Rs.136,842
= -Rs.649,542
Illustration
Now we consider the adjustment for the tax shield associated with debt
finance. The present value of tax shield associated with Rs.2,400,000 of
debt finance is calculated. From this we find that the debt finance
associated with the project brings a stream of tax shields which has a
present value of Rs.403,385. If we make adjustment for this also, we get
:
APV = Base case NPV – Issue cost + Present
value of tax shield
= -Rs.512,700 – Rs.136,842 + Rs.403,385
= -Rs.246,157
Year Debt outstanding Interest Tax shield Present value of
at the beginning tax shield
(at 14% discount rate)
1 2,400,000 336,000 134,400 117,869
2 2,100,000 294,000 117,600 90,552
3 1,800,000 252,000 100,800 68,040
4 1,500,000 210,000 84,000 49,728
5 1,200,000 168,000 67,200 34,877
6 900,000 126,000 50,400 22,982
7 600,000 84,000 33,600 13,440
8 300,000 42,000 16,800 5,897
Total Rs.403,385
Calculation of the Present Value of Tax Shield
The principle underlying APV is to divide and conquer. APV does not
reflect the side effects of financing in a single calculation. Instead, it
captures them in a series of calculations. This makes it more
illuminating. You not only know what the APV is but also where it is
coming from. This is helpful in reformulating the project.
Merits of APV
APV makes more sense for projects that have a capital structure
that is different from the rest of the firm or which have a capital structure
that changes significantly over time or which enjoy special concessions,
incentives, and subsidies. For example, APV is eminently suitable for
leveraged buyouts(LBOs) or infrastructure projects.
Adjusted Cost of Capital
D E
V V
rD (1- Tc) + rE (13.4)
Though conceptually sound, APV is not very popular because (i) it
requires some sophistication to assess the financing side effects, and (ii)
it involves a series of adjustments which may be cumbersome.
That is why WACC, which is the cost of capital adjusted for
financing effects, is more commonly used in practice. Recall that WACC
is:
There are some other formulae also of adjusted cost of capital.
Two of them are :
Modigliani and Miller formula : r* = r (1-TL) (13.5)
1+r
Miles and Ezzell formula : r* = r – L rD T (13.6)
1+ rD
where r* = adjusted cost of capital
r = opportunity cost of capital assuming 100 per cent
equity financing
T = tax rate applicable to the firm
L = marginal contribution of the project to the firm’s
debt capacity
rD = cost of debt
Adjusted Cost of Capital
Adjusted Cost of Capital
Example 1 A firm is considering a project for setting up a captive power
plant for which the following information has been gathered.
Investment outlay : Rs. 50 million
Annual post-tax savings : Rs. 5 million
Life of the project : Perpetual
Debt capacity of the project : Rs. 25 million
Interest rate of debt : 10 percent
Nature of debt : Perpetual
Tax rate of the firm : 40 percent
Opportunity cost of capital : 12 percent
The adjusted cost of capital as per Modigliani-Miller formula is :
r* = r (1-TL) = 0.12 (1- 0.4 x 0.5 ) = 0.096 or 9.6%
The adjusted cost of capital as per Miles and Ezzell formula is :
1+r 1.12
r* = r – L rD T = 0.12 –0.5 x 0.10 x 0.4 x = 0.100 or 10.0%
1+ rD 1.10
Inflation and Capital Budgeting
Inflation has been a persistent feature of the Indian economy. Hence, it
should be properly considered in capital investment appraisal. Since the
cost of capital, the discount rate, is typically expressed in nominal terms,
all the cash flows should also be expressed in nominal terms. This means
that (a) projected revenues and costs must reflect the inflation rates
expected in future and (b) salvage values, too, must be expressed in
future nominal amounts.
International Capital Budgeting
There are two equivalent ways of calculating the NPV of a foreign
project.
Home Currency Approach
• Convert all the foreign currency cash flows into rupees (use fore-
casted exchange rates)
• Calculate the NPV in rupees ( use the rupee discount rate)
Foreign Currency Approach
• Calculate the NPV in foreign currency (use the foreign currency
discount rate)
• Convert the foreign currency NPV into rupees (use the spot ex-
change rate)
Investment in Capabilities
Empirical evidence suggests that companies that perform well have
organisational capabilities that enable them to exploit opportunities.
What are these organisational capabilities? As Baldwin and Clark say: “
Organisational capabilities are combinations of human skills,
organisational procedures and routines, physical assets, and the systems
of information and incentives that improve performance along particular
dimensions. Such capabilities are indeed organisational assets.”
Capabilities
Baldwin and Clark mention five specific capabilities:
External Integration Capability The ability of the firm to link its
understanding of customers with engineering design to develop improved
products.
Internal Integration Capability Internal integration makes a company faster
and more efficient in performing various functions like new product
development, prototyping, facilities engineering, and capacity expansion
Flexibility The ability of a firm to do a variety of things and to respond
quickly to changes.
Capacity to Experiment The capacity to experiment depends on the
investments a firm makes in developing knowledge, disseminating
knowledge, and adopting the same in practice
Capacity to Cannibalise Cannibalisation involves introducing a new
product that cuts into the sales of the existing products.
Characteristics of Capabilities – Building
Investments
Investments required to build capabilities have certain special
characteristics. These are:
 Many of the outlays required are on things like common language
and communication, human training and skill development, and
support services. These are not ordinarily regarded as capital
expenditure in many firms.
 Investments required to build a capability range widely in scale
and scope.
 While costs of building capabilities are visible and appear on
someone’s budget, the benefits are derived by the company as a
whole and occur only after a time lag.
Allocating Resources to Build Capabilities
The challenge for a company lies in developing a capital allocation
system that accommodates investment in capabilities without sacrificing
the benefits of a formal financial analysis. Towards this end, the
following actions are required.
• Identify the capabilities that the firm should develop and ensure that
there is a firm organisational commitment to them.
• Develop a capital budget for capabilities and a proper system of
authorisation and accounting for expenditures relating to
capabilities.
• Translate the desired capabilities into appropriate goals and rewards
that are clearly understood and used by people throughout the
organisation.
• Link compensation of managers to improvements in speed, quality,
and flexibility, which are the outcomes of capabilities.
SUMMARY
 For a proper comparison of two mutually exclusive alternatives, that have
different lives, we have to convert the present value of costs into a uniform
annual equivalent (UAE) figure.
The UAE is simply:
PV (Cost)/PVIFA r,n
 In real life, an investment can typically be undertaken now or at some point of
time in future. The timing that has the highest current value represents the
optimal timing.
 The economic life of an asset is conceptually defined as the period after which
the asset should be replaced to minimise the sum of operating and
maintenance costs and capital costs expressed on an annual basis.
 Strictly speaking, WACC is the right discount rate for a project that is a carbon
copy of the firm’s existing business.
 A project may have financing effects that differ from those of the existing
investments of the firm. It may have different debt capacity or be entitled to
certain subsidies or have some special financial features. In such cases the
recommended method is to calculate the adjusted NPV (or APV for short).
 APV is calculated by first estimating the base-case NPV and then adjusting it
to reflect the financing impact of the project.
APV = Base-case NPV + Present value of the financing side effects of the
project
 The base-case NPV is the NPV of the project under the following assumptions
: (a) The project is financed entirely by equity. (b) There is no financing effect
like issue cost or subsidy.
 The present value of financing side effects is equal to : Present value of
positive financing side effects like tax subsidies – Present value of negative
financing side effects like issue costs.
 Though conceptually sound, APV is not very popular because (i) it requires
some sophistication to assess the financing side effects, and (ii) it involves a
series of adjustments which may be cumbersome. That is why WACC, which
is the cost of capital adjusted for financing effects, is more commonly used in
practice.
 WACC is equal to :
D E
rD (1- Tc) + rE
V V
 There are some other formulae also for calculating the adjusted cost of capital.
Two of them are:
Modigliani and Miller formula : r* = r (1-TL)
1+r
Miles and Ezzell formula : r* = r – L rD T
1+ rD
 The adjustment for inflation should be done properly in practice.
 There are two ways of evaluating an international capital budgeting proposal:
the home currency approach and the foreign currency approach. Correctly
applied both the approaches yield the same result.
 Empirical evidence suggest that companies that perform well have
organisational capabilities that enable them to exploit opportunities.
1 de 27

Recomendados

Cost  of capitalCost  of capital
Cost of capitalAaryendr
72.9K visualizações22 slides
Payback period by harikrishnananPayback period by harikrishnanan
Payback period by harikrishnananHari krishna
3.2K visualizações12 slides
CAPMCAPM
CAPMTixy Mariam Roy
80.2K visualizações10 slides
The capital budgeting processThe capital budgeting process
The capital budgeting processAileen Mae Doroja
10.8K visualizações77 slides

Mais conteúdo relacionado

Mais procurados

Dividend policyDividend policy
Dividend policyPooja Narwani
94.4K visualizações45 slides
Cost Of CapitalCost Of Capital
Cost Of Capitalelvieentero
47.1K visualizações41 slides
   capm theory   capm theory
capm theoryDivyathilakan
30.8K visualizações11 slides
Strategic control & its typesStrategic control & its types
Strategic control & its typesDeepak Singh
10.3K visualizações9 slides
Cost of capital pptCost of capital ppt
Cost of capital pptRICHA BHUSHAN
13.2K visualizações15 slides

Mais procurados(20)

Dividend policyDividend policy
Dividend policy
Pooja Narwani94.4K visualizações
Cost Of CapitalCost Of Capital
Cost Of Capital
elvieentero47.1K visualizações
   capm theory   capm theory
capm theory
Divyathilakan30.8K visualizações
Strategic control & its typesStrategic control & its types
Strategic control & its types
Deepak Singh10.3K visualizações
Investment decisions / capital BudgetingInvestment decisions / capital Budgeting
Investment decisions / capital Budgeting
Raghav Jha9.5K visualizações
Cost of capital pptCost of capital ppt
Cost of capital ppt
RICHA BHUSHAN13.2K visualizações
Dividend decision theoriesDividend decision theories
Dividend decision theories
Ayush Jain12.3K visualizações
Market value addedMarket value added
Market value added
SowmyR13.1K visualizações
Capital structure decisionsCapital structure decisions
Capital structure decisions
iqballalani16.4K visualizações
Capital BudgetingCapital Budgeting
Capital Budgeting
Dayasagar S194.9K visualizações
Cost of capitalCost of capital
Cost of capital
Nirmal PR71.2K visualizações
Dividend DecisionsDividend Decisions
Dividend Decisions
Kaushik Deb11.8K visualizações
Internal rate of returnInternal rate of return
Internal rate of return
N A M COLLEGE KALLIKKANDY4.4K visualizações
Chapter 5   cost of capital sml 401 btechChapter 5   cost of capital sml 401 btech
Chapter 5 cost of capital sml 401 btech
Mvs Krishna1.5K visualizações
Process of strategic choiceProcess of strategic choice
Process of strategic choice
Pranav Kumar Ojha96.4K visualizações
Country risk analysisCountry risk analysis
Country risk analysis
SHASHANK CHOUDHARY25.2K visualizações
Capital structureCapital structure
Capital structure
Bhawna Pandwar25.9K visualizações
Internal Rate of ReturnInternal Rate of Return
Internal Rate of Return
Hamza saeed Khan14K visualizações
RISK ANALYSIS IN CAPITAL BUDGETINGRISK ANALYSIS IN CAPITAL BUDGETING
RISK ANALYSIS IN CAPITAL BUDGETING
PANKAJ PANDEY38.8K visualizações
Chapter 2.Time Value of Money pptChapter 2.Time Value of Money ppt
Chapter 2.Time Value of Money ppt
ZahraMirzayeva12.5K visualizações

Similar a Chapter13 specialdecisionsituations

PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptxShyam273559
3 visualizações27 slides
Ch14sol cash flow estimationCh14sol cash flow estimation
Ch14sol cash flow estimationHassan Zada
266 visualizações20 slides
Capital BudgetingCapital Budgeting
Capital Budgetingyashpal01
3.1K visualizações26 slides
Project Valuation LectureProject Valuation Lecture
Project Valuation Lecturebradhapa
4.3K visualizações20 slides

Similar a Chapter13 specialdecisionsituations(20)

PPAM-AK PPT.pptxPPAM-AK PPT.pptx
PPAM-AK PPT.pptx
Shyam2735593 visualizações
Ch14sol cash flow estimationCh14sol cash flow estimation
Ch14sol cash flow estimation
Hassan Zada266 visualizações
Capital BudgetingCapital Budgeting
Capital Budgeting
yashpal013.1K visualizações
Project Valuation LectureProject Valuation Lecture
Project Valuation Lecture
bradhapa4.3K visualizações
Chapter 10.The Cost of Capital(WACC)Chapter 10.The Cost of Capital(WACC)
Chapter 10.The Cost of Capital(WACC)
ZahraMirzayeva4.6K visualizações
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
Bsgr Planmin533 visualizações
Lecture cash flow evaluation newLecture cash flow evaluation new
Lecture cash flow evaluation new
Bsgr Planmin1K visualizações
Capital budgetingCapital budgeting
Capital budgeting
bindu sreevatsava74 visualizações
Chapter 8Cost of CapitalAssociated PressLearning O.docxChapter 8Cost of CapitalAssociated PressLearning O.docx
Chapter 8Cost of CapitalAssociated PressLearning O.docx
mccormicknadine863 visualizações
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
hass63 visualizações
Adl 13-financial-managementAdl 13-financial-management
Adl 13-financial-management
Himanshu Jindal8.3K visualizações
Capital budgetingCapital budgeting
Capital budgeting
DR.MAHESH KUMAR K.R.2.7K visualizações
Capital budgeting cash flow estimationCapital budgeting cash flow estimation
Capital budgeting cash flow estimation
Prafulla Tekriwal12.3K visualizações
present worth analysis.pptpresent worth analysis.ppt
present worth analysis.ppt
ashwinigupta3831 visualizações
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
venkataramanan Thiru735 visualizações
The Discounted Cash Flow Valuation.pptxThe Discounted Cash Flow Valuation.pptx
The Discounted Cash Flow Valuation.pptx
asde131K visualizações
PriyankabbaPriyankabba
Priyankabba
PriyankaSachdeva35100 visualizações

Mais de AKSHAYA0000

SwocSwoc
SwocAKSHAYA0000
200 visualizações1 slide
Pm Pm
Pm AKSHAYA0000
83 visualizações7 slides
NpaNpa
NpaAKSHAYA0000
26 visualizações2 slides
Chapter21 projectmanagementChapter21 projectmanagement
Chapter21 projectmanagementAKSHAYA0000
92 visualizações28 slides

Mais de AKSHAYA0000(20)

SwocSwoc
Swoc
AKSHAYA0000200 visualizações
Pm Pm
Pm
AKSHAYA000083 visualizações
NpaNpa
Npa
AKSHAYA000026 visualizações
Chapter23 projectreviewandadministrativeaspectsChapter23 projectreviewandadministrativeaspects
Chapter23 projectreviewandadministrativeaspects
AKSHAYA00002.3K visualizações
Chapter22 networktechniquesforprojectmanagementChapter22 networktechniquesforprojectmanagement
Chapter22 networktechniquesforprojectmanagement
AKSHAYA00001.4K visualizações
Chapter21 projectmanagementChapter21 projectmanagement
Chapter21 projectmanagement
AKSHAYA000092 visualizações
Chapter20 venturecapitalandprivateequityChapter20 venturecapitalandprivateequity
Chapter20 venturecapitalandprivateequity
AKSHAYA000055 visualizações
Chapter19 financinginfrastructureprojectsChapter19 financinginfrastructureprojects
Chapter19 financinginfrastructureprojects
AKSHAYA0000111 visualizações
Chapter18 financingofprojectsChapter18 financingofprojects
Chapter18 financingofprojects
AKSHAYA0000536 visualizações
Chapter17 judgmentalbehaviouralChapter17 judgmentalbehavioural
Chapter17 judgmentalbehavioural
AKSHAYA0000118 visualizações
Chapter16 valuationofrealoptionsChapter16 valuationofrealoptions
Chapter16 valuationofrealoptions
AKSHAYA000077 visualizações
Chapter15 multipleprojectsandconstraintsChapter15 multipleprojectsandconstraints
Chapter15 multipleprojectsandconstraints
AKSHAYA0000473 visualizações
Chapter14 socialcostbenefitanalysisChapter14 socialcostbenefitanalysis
Chapter14 socialcostbenefitanalysis
AKSHAYA0000211 visualizações
Chapter12 projectrateofreturnChapter12 projectrateofreturn
Chapter12 projectrateofreturn
AKSHAYA000064 visualizações
Chapter11 projectriskanalysisChapter11 projectriskanalysis
Chapter11 projectriskanalysis
AKSHAYA0000490 visualizações
Chapter10 thecostofcapitalChapter10 thecostofcapital
Chapter10 thecostofcapital
AKSHAYA0000660 visualizações
Chapter9 projectcashflowsChapter9 projectcashflows
Chapter9 projectcashflows
AKSHAYA0000671 visualizações
Chapter8 investmentcriteriaChapter8 investmentcriteria
Chapter8 investmentcriteria
AKSHAYA00002.1K visualizações
Chapter7 thetimevalueofmoneyChapter7 thetimevalueofmoney
Chapter7 thetimevalueofmoney
AKSHAYA00002.1K visualizações
Chapter6 financialestimatesandprojectionsChapter6 financialestimatesandprojections
Chapter6 financialestimatesandprojections
AKSHAYA000075 visualizações

Último(20)

BYSC infopack.pdfBYSC infopack.pdf
BYSC infopack.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego160 visualizações
Nico Baumbach IMR Media ComponentNico Baumbach IMR Media Component
Nico Baumbach IMR Media Component
InMediaRes1368 visualizações
Chemistry of sex hormones.pptxChemistry of sex hormones.pptx
Chemistry of sex hormones.pptx
RAJ K. MAURYA107 visualizações
231112 (WR) v1  ChatGPT OEB 2023.pdf231112 (WR) v1  ChatGPT OEB 2023.pdf
231112 (WR) v1 ChatGPT OEB 2023.pdf
WilfredRubens.com118 visualizações
Azure DevOps Pipeline setup for Mule APIs #36Azure DevOps Pipeline setup for Mule APIs #36
Azure DevOps Pipeline setup for Mule APIs #36
MysoreMuleSoftMeetup84 visualizações
DU Oral Examination Toni SantamariaDU Oral Examination Toni Santamaria
DU Oral Examination Toni Santamaria
MIPLM128 visualizações
discussion post.pdfdiscussion post.pdf
discussion post.pdf
jessemercerail85 visualizações
Lecture: Open InnovationLecture: Open Innovation
Lecture: Open Innovation
Michal Hron94 visualizações
GSoC 2024GSoC 2024
GSoC 2024
DeveloperStudentClub1056 visualizações
CWP_23995_2013_17_11_2023_FINAL_ORDER.pdfCWP_23995_2013_17_11_2023_FINAL_ORDER.pdf
CWP_23995_2013_17_11_2023_FINAL_ORDER.pdf
SukhwinderSingh895865480 visualizações
Psychology KS5Psychology KS5
Psychology KS5
WestHatch56 visualizações
UWP OA Week Presentation (1).pptxUWP OA Week Presentation (1).pptx
UWP OA Week Presentation (1).pptx
Jisc65 visualizações
Material del tarjetero LEES Travesías.docxMaterial del tarjetero LEES Travesías.docx
Material del tarjetero LEES Travesías.docx
Norberto Millán Muñoz60 visualizações
STYP infopack.pdfSTYP infopack.pdf
STYP infopack.pdf
Fundacja Rozwoju Społeczeństwa Przedsiębiorczego159 visualizações
Narration lesson plan.docxNarration lesson plan.docx
Narration lesson plan.docx
TARIQ KHAN92 visualizações
ICANNICANN
ICANN
RajaulKarim2061 visualizações

Chapter13 specialdecisionsituations

  • 2. OUTLINE • Choice between mutually exclusive projects of unequal life • Optimal timing decision • Determination of economic life • Interrelationship between investment and financing aspects • Inflation and capital budgeting • International capital budgeting • Investment in capabilities
  • 3. Choice between Mutually Exclusive Projects of Unequal Life For a proper comparison of the two alternatives, that have different lives, we have to convert the present value of costs into a uniform annual equivalent (UAE) figure – this is also called an equivalent annual cost (EAC) figure. The UAE is a function of the present value of cost, the life of the asset, and the discount rate. The UAE is simply: PV Cost PVIFAr,n
  • 4. Uniform Annual Equivalent PV of costs of machine A : 12,000 12,000 12,000 12,000 12,000 75,000 + + + + + = 118,260 (1.12) (1.12)2 (1.12)3 (1.12)4 (1.12)5 PV costs of machine B : 15,000 15,000 15,000 50,000 + + + = 86,030 (1.12) (1.12)2 (1.12)3 Machine A: UAE = 118,260 118,260 PVIFA12%,5 3.605 Machine B: UAE = 86,030 86,030 PVIFA12%,3 2.402 = 32,804 = 35,816 = =
  • 5. Optimal Timing In real life, an investment is rarely a “now or never” proposition. Typically, it can be undertaken now or at some point of time in future. Given this option, the issue of optimal timing assumes significance. Under conditions of certainty, the optimal timing may be determined by using the following procedure. 1. Examine alternative dates (t) when the investment can be made. 2. Estimate the net future value as of each alternative date and convert the same to its current value. 3. Choose the timing that has the highest current value
  • 6. Determination of Economic Life The economic life of an asset is conceptually defined as the period after which the asset should be replaced to minimise the sum of operating and maintenance costs and capital costs expressed on an annual basis. Put differently, it is the replacement cycle that minimises the uniform annual equivalent total cost, UAE (TC) of operating and owning the asset. The UAE (TC) is simply the sum of the uniform annual equivalent operating and maintenance cost, UAE (OM), and the uniform annual equivalent capital cost, UAE (CC). That is, UAE (TC) = UAE (OM) + UAE (CC) (13.1)
  • 7. S UAE (CC) Replacement Period (in years) Annualised Cost Costs over the Life of a Machine
  • 8. Interrelationship between the Investment and Financing Aspects • WACC is the right discount rate for a project that is a carbon copy of the firm’s existing business. • A project may have financing effects that differ from those of the existing investments of the firm. It may have a different debt capacity or be entitled to certain subsidies or have some special financial features. In such cases the recommended method is to calculate the adjusted NPV (or APV for short).
  • 9. Adjusted Present Value (APV) APV is calculated by first estimating the base-case NPV and then adjusting it to reflect the financing side effects of the project. The base-case NPV is the NPV of the project under the following assumptions: • The project is financed entirely by equity. • There is no financing side effect like issue cost or subsidy The present value of financing side effects is equal to: • Present value of positive financing side effects like tax shield on debt and availability of subsidies. • Present value of negative financing side effects like issue costs and financial distress costs associated with excessive leverage.
  • 10. Illustration Investment : Rs. 5 million Net cash inflow : Rs.1 million per year for 8 years Opportunity cost of capital : 15 percent Issue cost of equity : 5 percent Debt available : Rs.2.4 million at 14 percent Repayment of debt : 8 equal annual instalments. First instalment will be paid at the end of first year Tax rate : 40 percent
  • 11. Illustration Base – case NPV: 8 1,000,000 -5,000,000 +  = -512,700 t=1 (1.15)t The base-case NPV has to be adjusted for two factors: (i) issue cost, and (ii) tax-shield associated with debt.
  • 12. Illustration Out of the total financing requirement of the project Rs.2,600,000 will come from the equity sources and Rs.2,400,000 will come in the form of debt finance. As the net equity finance required by the project is Rs.2,600,000 and the issue costs would absorb 5 per cent of the gross proceeds of the issue, the firm will have to issue Rs.2,736,842 (Rs.2,600,000 / 0.95) of equity stock in order to realise a net amount of Rs.2,600,000. The difference of Rs.136,842 is the cost of underwriting, brokerage, printing, and other issue related expenses. The APV after adjustment for issue cost is : APV = Base-case NPV – Issue cost = -Rs.512,700 – Rs.136,842 = -Rs.649,542
  • 13. Illustration Now we consider the adjustment for the tax shield associated with debt finance. The present value of tax shield associated with Rs.2,400,000 of debt finance is calculated. From this we find that the debt finance associated with the project brings a stream of tax shields which has a present value of Rs.403,385. If we make adjustment for this also, we get : APV = Base case NPV – Issue cost + Present value of tax shield = -Rs.512,700 – Rs.136,842 + Rs.403,385 = -Rs.246,157
  • 14. Year Debt outstanding Interest Tax shield Present value of at the beginning tax shield (at 14% discount rate) 1 2,400,000 336,000 134,400 117,869 2 2,100,000 294,000 117,600 90,552 3 1,800,000 252,000 100,800 68,040 4 1,500,000 210,000 84,000 49,728 5 1,200,000 168,000 67,200 34,877 6 900,000 126,000 50,400 22,982 7 600,000 84,000 33,600 13,440 8 300,000 42,000 16,800 5,897 Total Rs.403,385 Calculation of the Present Value of Tax Shield
  • 15. The principle underlying APV is to divide and conquer. APV does not reflect the side effects of financing in a single calculation. Instead, it captures them in a series of calculations. This makes it more illuminating. You not only know what the APV is but also where it is coming from. This is helpful in reformulating the project. Merits of APV APV makes more sense for projects that have a capital structure that is different from the rest of the firm or which have a capital structure that changes significantly over time or which enjoy special concessions, incentives, and subsidies. For example, APV is eminently suitable for leveraged buyouts(LBOs) or infrastructure projects.
  • 16. Adjusted Cost of Capital D E V V rD (1- Tc) + rE (13.4) Though conceptually sound, APV is not very popular because (i) it requires some sophistication to assess the financing side effects, and (ii) it involves a series of adjustments which may be cumbersome. That is why WACC, which is the cost of capital adjusted for financing effects, is more commonly used in practice. Recall that WACC is:
  • 17. There are some other formulae also of adjusted cost of capital. Two of them are : Modigliani and Miller formula : r* = r (1-TL) (13.5) 1+r Miles and Ezzell formula : r* = r – L rD T (13.6) 1+ rD where r* = adjusted cost of capital r = opportunity cost of capital assuming 100 per cent equity financing T = tax rate applicable to the firm L = marginal contribution of the project to the firm’s debt capacity rD = cost of debt Adjusted Cost of Capital
  • 18. Adjusted Cost of Capital Example 1 A firm is considering a project for setting up a captive power plant for which the following information has been gathered. Investment outlay : Rs. 50 million Annual post-tax savings : Rs. 5 million Life of the project : Perpetual Debt capacity of the project : Rs. 25 million Interest rate of debt : 10 percent Nature of debt : Perpetual Tax rate of the firm : 40 percent Opportunity cost of capital : 12 percent The adjusted cost of capital as per Modigliani-Miller formula is : r* = r (1-TL) = 0.12 (1- 0.4 x 0.5 ) = 0.096 or 9.6% The adjusted cost of capital as per Miles and Ezzell formula is : 1+r 1.12 r* = r – L rD T = 0.12 –0.5 x 0.10 x 0.4 x = 0.100 or 10.0% 1+ rD 1.10
  • 19. Inflation and Capital Budgeting Inflation has been a persistent feature of the Indian economy. Hence, it should be properly considered in capital investment appraisal. Since the cost of capital, the discount rate, is typically expressed in nominal terms, all the cash flows should also be expressed in nominal terms. This means that (a) projected revenues and costs must reflect the inflation rates expected in future and (b) salvage values, too, must be expressed in future nominal amounts.
  • 20. International Capital Budgeting There are two equivalent ways of calculating the NPV of a foreign project. Home Currency Approach • Convert all the foreign currency cash flows into rupees (use fore- casted exchange rates) • Calculate the NPV in rupees ( use the rupee discount rate) Foreign Currency Approach • Calculate the NPV in foreign currency (use the foreign currency discount rate) • Convert the foreign currency NPV into rupees (use the spot ex- change rate)
  • 21. Investment in Capabilities Empirical evidence suggests that companies that perform well have organisational capabilities that enable them to exploit opportunities. What are these organisational capabilities? As Baldwin and Clark say: “ Organisational capabilities are combinations of human skills, organisational procedures and routines, physical assets, and the systems of information and incentives that improve performance along particular dimensions. Such capabilities are indeed organisational assets.”
  • 22. Capabilities Baldwin and Clark mention five specific capabilities: External Integration Capability The ability of the firm to link its understanding of customers with engineering design to develop improved products. Internal Integration Capability Internal integration makes a company faster and more efficient in performing various functions like new product development, prototyping, facilities engineering, and capacity expansion Flexibility The ability of a firm to do a variety of things and to respond quickly to changes. Capacity to Experiment The capacity to experiment depends on the investments a firm makes in developing knowledge, disseminating knowledge, and adopting the same in practice Capacity to Cannibalise Cannibalisation involves introducing a new product that cuts into the sales of the existing products.
  • 23. Characteristics of Capabilities – Building Investments Investments required to build capabilities have certain special characteristics. These are:  Many of the outlays required are on things like common language and communication, human training and skill development, and support services. These are not ordinarily regarded as capital expenditure in many firms.  Investments required to build a capability range widely in scale and scope.  While costs of building capabilities are visible and appear on someone’s budget, the benefits are derived by the company as a whole and occur only after a time lag.
  • 24. Allocating Resources to Build Capabilities The challenge for a company lies in developing a capital allocation system that accommodates investment in capabilities without sacrificing the benefits of a formal financial analysis. Towards this end, the following actions are required. • Identify the capabilities that the firm should develop and ensure that there is a firm organisational commitment to them. • Develop a capital budget for capabilities and a proper system of authorisation and accounting for expenditures relating to capabilities. • Translate the desired capabilities into appropriate goals and rewards that are clearly understood and used by people throughout the organisation. • Link compensation of managers to improvements in speed, quality, and flexibility, which are the outcomes of capabilities.
  • 25. SUMMARY  For a proper comparison of two mutually exclusive alternatives, that have different lives, we have to convert the present value of costs into a uniform annual equivalent (UAE) figure. The UAE is simply: PV (Cost)/PVIFA r,n  In real life, an investment can typically be undertaken now or at some point of time in future. The timing that has the highest current value represents the optimal timing.  The economic life of an asset is conceptually defined as the period after which the asset should be replaced to minimise the sum of operating and maintenance costs and capital costs expressed on an annual basis.  Strictly speaking, WACC is the right discount rate for a project that is a carbon copy of the firm’s existing business.  A project may have financing effects that differ from those of the existing investments of the firm. It may have different debt capacity or be entitled to certain subsidies or have some special financial features. In such cases the recommended method is to calculate the adjusted NPV (or APV for short).
  • 26.  APV is calculated by first estimating the base-case NPV and then adjusting it to reflect the financing impact of the project. APV = Base-case NPV + Present value of the financing side effects of the project  The base-case NPV is the NPV of the project under the following assumptions : (a) The project is financed entirely by equity. (b) There is no financing effect like issue cost or subsidy.  The present value of financing side effects is equal to : Present value of positive financing side effects like tax subsidies – Present value of negative financing side effects like issue costs.  Though conceptually sound, APV is not very popular because (i) it requires some sophistication to assess the financing side effects, and (ii) it involves a series of adjustments which may be cumbersome. That is why WACC, which is the cost of capital adjusted for financing effects, is more commonly used in practice.  WACC is equal to : D E rD (1- Tc) + rE V V
  • 27.  There are some other formulae also for calculating the adjusted cost of capital. Two of them are: Modigliani and Miller formula : r* = r (1-TL) 1+r Miles and Ezzell formula : r* = r – L rD T 1+ rD  The adjustment for inflation should be done properly in practice.  There are two ways of evaluating an international capital budgeting proposal: the home currency approach and the foreign currency approach. Correctly applied both the approaches yield the same result.  Empirical evidence suggest that companies that perform well have organisational capabilities that enable them to exploit opportunities.