SlideShare uma empresa Scribd logo
1 de 6
Baixar para ler offline
North American Society for Trenchless Technology (NASTT)
                                 NO-DIG 2006

                                      Nashville, TN
                                     March 15-20, 2007



STRIPPING OF LINERS FROM PIPES USING HDD TECHNOLOGY
Harry Baum and Kwigs Bowen2
1
  President, W.S.U. Inc.., Breckenridge, Colorado
2
  Area Manager, Team Fishel, Chandler, Arizona


ABSTRACT
Horizontal directional drilling is a non-intrusive method for installing utility lines, gas pipes, water pipes,
sewer lines or fiber-optic conduit below the ground without the need to open trench. Horizontal directional
drills “bore” a tunnel using fixed-length drill rods that are threaded together to create what’s called a drill
string. This drill string is advanced or drilled through the ground from an entrance to an exit location. This
drilled bore can be drilled to precise locations because of the drilling tool’s slanted steering plate. The
orientation of the tool and its slanted steering plate is what determines the direction the drill head
navigates. The directional path will move when pushed through the ground without rotation. A transmitter
enclosed in the drill heads housing transmits depth, digital clock rotation position, temperature and angle
to a remote receiver on the surface. Maximum depth depends upon the style of the transmitter but
normally 50 feet is average.

Because of the flexibility HDD offers, Harry Baum, owner of W.S.U. Inc. and Steve Wentworth of Earth
Tool Company LLC (manufacturer of HammerHead trenchless products) began conversations on the
concept to remotely remove linings from the inside of sewer lines. As a novel concept invention
Wentworth designed an umbrella like mechanical device which is attached to a directional drill.
Wentworth had already designed tooling for other directional drilling uses and was able to quickly offer
Baum solutions. Baum was very familiar with failed liners and the problems caused where open cut was
often the only solution for removing linings. Removal of factory installed linings using custom designed
tooling, deployed and actuated by a directional drill rig, is a new method. Having the ability to attach
different tools to the end of rigid drill pipe opens the opportunity for other remotely operated mechanical
devices. Just as a surgical tool is used to open arteries the stripping tool could open the clogged sewer
arteries without open cutting the entire section.

Ductile iron pipe with factory applied high density polyethylene (HDPE) liner has been widely used for
sanitary sewer installations where high hydrogen sulfide gas concentrations exist. Failure of the pipes
protective HDPE liner from hydrogen sulfide corrosion caused the liner to delaminate in sheets. This
created the potential for problematic system backups. It was clear that the failing liner had to be removed.
The removal was intended to simultaneously eliminate the potential for backup and produce a surface
appropriate for relining using cured in place pipe (CIPP) methods.

This paper will review a highly successful 1st attempt at using a new trenchless technology, Liner
Stripping, in cooperation with Pima County Wastewater Management, Tucson Arizona. System owner
engineers, contractor, sub-contractor and equipment manufacturer joined to make the job possible with
the custom developed technology.

The job success highlights the potential HDD drills have to service non-man entry or difficult man entry
locations with custom engineered tooling. The method of “Liner Stripping,” as with all trenchless methods,
will be less disruptive and less invasive than previously accepted methods or remedies to service a pipe’s


                                                Paper E-2-04
interior spaces. The results demonstrate that servicing the interior of buried pipes with the attributes of an
HDD drill stem is a concept that has profound potential.


INTRODUCTION

Recently, the Pima County Wastewater Management (PCWM) in Tucson, Arizona found itself with a
perplexing problem when it tried to rehabilitate one of its ductile HDPE lined sanitary sewer pipes. In
weighing possible solutions, PCWM officials permitted “Liner Stripping” of the HDPE using a horizontal
directional drill HDD rig followed by CIPP lining of the sewer main. Normally HDD is used for the
trenchless installation of new underground utilities not rehabilitation so this application is quite a novel
concept.

The Pima County wastewater conveyance system consists of nearly 3,300 miles of public separate
sanitary sewers, ranging in size from 6- to 78-in. pipe diameters with an 84-in. box culvert. The Old
Nogales Highway trunk sewer consists of more than 16,000 ft of 18-in ductile iron pipe with a
polyethylene liner. The liner has de-laminated from the host pipe to some degree on roughly one-third of
the total length of the trunk sewer line. The de-lamination on some stretches was severe enough
warranting an emergency repair to remove the liner from the flow line. Pima County surrounds the high
desert city of Tucson and land south to the Mexico border. Tucson sits on a remarkably flat plane
consisting of fine granular soil that is susceptible to erosion. Blockage backups must be avoided when
operating a pipeline or ground erosion can case sinkholes.

In the 1980’s corrosion of ductile iron pipe was avoided by using a factory installed polyethylene lining.
The liner .06 to .10” (1.524 to 2.54 mm) thick was intended to prevent hydrogen sulfide gas, from
contacting the ductile iron sealing the odiferous gas from the iron atmosphere. Hydrogen sulfide gas is a
normal byproduct of decomposition in sanitary systems.

Damage to the HDPE liner around the bell and spigot may have occurred during installation or some time
afterward allowing hydrogen sulfide to attack the ductile iron pipe. Oxidization built up between the liner
and the interior surface of the ductile iron which caused de-bonding of the liner from the pipe. This de-
bonding of the liner caused the liner to hang down inside the pipe like poorly applied wallpaper falling
from the ceiling. Sewer flow velocity between the de-lamination accelerates the sewer liner degradation.
This was evident when an inspection camera (figure 1) was used to inspect the line. The hanging liner
(figures 2-5) reduces the annular circumferential area stalling the flow of solids which had caused
backups and could continue to do so.




Figure 1 - The mobile camera inspection truck
controls the operation and recording of a robotic
camera. The camera documents real time
information which becomes a permanent record for
future use.


                                                Paper E-2-04
Figure 2 - Shown from the robotic camera, is a        Figure 3 - The arrow indicates the early stages of
separated HDPE liner folded into the flow stream.     HDPE lining separation at the ductile iron pipe joint.




Figure 4 - The circle indicates liner that has        Figure 5 - Liner failure indicated by the camera
completely pulled away from the host pipe creating    operator.
turbulence downstream. A by-product of this
turbulence is hydrogen sulfide gas which escalates
the degradation of the pipe.

Pima County has the additional stress of having the possibility of the backup inducing a sinkhole in one or
more locations. For this reason, county officials had to find a solution that would eliminate the hanging
liner and find a solution to protect the perfectly serviceable ductile iron portion of their pipe.

W.S.U. Inc., in Breckenridge, Colorado, was contracted by Pima County engineers to rehabilitate the
ductile iron sewer line using the custom stripping tool developed by Earth Tool Company, LLC, and
manufacturer of HammerHead trenchless products based out of Oconomowoc, Wisconsin. The proximity
of the line, within a railroad right of way made open-cut a daunting and undesirable method. PCWMD
engineers chose the less invasive technology HDD knowing that open cut methodologies would not be
acceptable.

After the HDPE liner was completely removed a new CIPP liner would be applied to the bare ductile iron
pipe which would produce the corrosion barrier need to make the pipe last. To insure complete removal of
the HDPE liner a sewer camera recorded instantaneous progress inspection behind the rotating lining
striping mechanism.

HDD SOLUTION

The HDD rig is setback from the intersection from the intended path end point (figure 6). This setback is
determined by HDD rig rod radius specifications and the desired depth end point. The midsize HDD rig


                                              Paper E-2-04
chosen for this application can develop 24,000 pounds of tensile and 4,000 ft. lbs. of torque. However,
only a small portion of this power is required to accomplish the stripping liner removal process. A drill rod
access point is excavated and the top section of pipe removed (figure 7) An inflatable plug was inserted
into the sewer line and the sewer flow was by-passed around the working section (figure 8).




Figure 6 - On the surface, the
directional drill operator receives
radio confirmation from the                                           Figure 8 - To prevent customer
camera operator to access                                             interruption, the working section on
                                       Figure 7 - For the             the sewer line was bypassed using a
progress in the sewer line. If a       directional drill to access
section requires further stripping,                                   pump to maintain sewer flow.
                                       the sewer main, a fifteen
the camera operator alerts the drill   (15) foot section was
operator to back up and give           removed from the top of the
additional attention that section of   pipe.
pipe.


After the trenchless bore path intersected the sewer line, the drill stem was pushed out so as to extend
into a downstream manhole where the Poly Stripper mechanism was installed (figure 9). To control the
long unsupported drill string a soft urethane radial or triangular pilot was used as a centering plug (figure
10) with marginal diametrical clearance. With rotation bearings housed at both ends of the centering plug
stabilized the rod during high speed rotation.




Figure 9 - The stripping device is lowered down         Figure 10 - The liner stripping device is assembled
hole in sections and assembled in the manhole.          above ground to instruct crew members of the
                                                        proper joint assembly connection down hole.


The Poly Stripper was attached just behind the centering plug. Using the HDD rig’s water pump pressure,
the deployment of the radial stripper arms are controlled via bias pressure within the strippers operating


                                               Paper E-2-04
piston mechanism (figure 11). Water pressure controls the stripper arms’ force when deployed against the
liner host pipe (figure 12). Some water is bypassed around the piston chamber flushing away cuttings
continuously. At the entry manhole, a screen was placed in the flow path, separating cuttings from the
flow. These chips of the liner were then vacuumed up and disposed of (figure 13).




Figure 11 - The stripping arms          Figure 12 - The robotic camera    Figure 13 - WSU used a vacuum
are deployed using water                trails the stripping device       truck to clean the entry manhole
pressure supplied by through the        showing where the pipe has        and remove the cut lining chips
drill stem by a water pump              been stripped of the HDPE         and other debris.
connected to the directional drill.     lining.
Once the arms are deployed, the
drill string is rotated and the liner
is scraped from the pipe,
preparing it for lining.

HDPE liner is scraped away from the adjacent host pipe during rotational arm deployment. Followed by
the inspection camera the Poly Strippers’ progress is monitored as rotational speed is variable to
approximately 250 rpm. Radio contact between the HDD rig operator and the camera operator was all the
direction necessary to achieve production speed of approximately 10ft/min. By inspecting with the
camera, the operator was alerted to sections that required further stripping. In addition, the camera
operator could communicate the need to retract the stripper arms to de-tangle portions of the HDPE liner
that had entangled the stripper arms.

Several attachment cutting tools were developed, a .125” (3.175 mm) thick spring steel scraper proved
superior to other designs. Each of the three stripper arms held one scraper blade which was angled
slightly away from the clock wise rotation center line. Water used to make drilling fluid is common practice
when directional drilling underground utilities so additional rig operator training is minimal. Repeatedly,
the operator turned on the water pump, waited for water pressure to rise at the rig then began rotating the
drill stripping tool. He then pulled drill pipe toward the rig until again removing drill stem and repeating the
process.

CONCLUSION

HDD machines can provide huge economic potential to service non-man entry or difficult man entry
locations with custom engineered tooling. Engineers basic working knowleadge of HDD capabilities can
solve a myriad of sewer line issues. Pima County Arizona engineers were more than satisfied with the
first successful performance of this experimental method. Coordination between engineers, contractor,
sub-contractor and equipment manufacturer was essential in providing planning through job completion.
 Information supplied by Dan Cohen of WSU, a licensee of Inliner Technologies, installed ~ 5,720 lf of
18 inch ∅, 7.4mm thick CIPP using the Pulled-In-Place method of insertion per ASTM F 1743, PCWMD
specifications and WSU, ISO protocol. Individual runs of CIPP were resin impregnated at WSU’s wetout
facility located near Fairplay, Colorado just prior to it’s scheduled installation date. The wetout tube along
with it’s corresponding calibration hose was shipped to the job site in Tucson, Arizona inside a
temperature controlled, refrigerated reefer truck. The lining tube was winched into place followed by an
air inversion of the calibration hose. The CIPP was then cured using steam for pressure and heat.


                                                 Paper E-2-04
Independent third party testing was performed by HTS, Inc. of Houston, TX for thickness (ASTM D 5813),
flexural properties (ASTM D 790) and tensile strength (ASTM D 638). Each CIPP installation exceeded
the required minimum properties in every instance.

In all, the Poly-Stripper was used to clean about 5,700 feet of pipe over a two and half month period.
Afterward, WSU went in and rehabbed the pipe using CIPP with the comfort in knowing the loose liner
was completely removed as video proved. To date the project is considered by all involved to have been
a very succuessful method for removing de-bonded liner from ductile iron pipe. Because the liner was
removed completely, the corresponding CIPP liner was installed normally without any intrusive obstacles.




                                             Paper E-2-04

Mais conteúdo relacionado

Mais procurados

26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draftJohn Grover
 
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE Akhil Prabhakar
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06John Grover
 
VDOT BMP Clearinghouse Specification 8- Infiltration
VDOT BMP Clearinghouse Specification 8- Infiltration VDOT BMP Clearinghouse Specification 8- Infiltration
VDOT BMP Clearinghouse Specification 8- Infiltration Patrick McPartland, E.I.T.
 
Groundwater Control for Construction
Groundwater Control for ConstructionGroundwater Control for Construction
Groundwater Control for ConstructionMartin Preene
 
Western Pipeway Presentation
Western Pipeway PresentationWestern Pipeway Presentation
Western Pipeway PresentationWestern Pipeway
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012Mike Vernon
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryPorts-To-Plains Blog
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020Pomcert
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyAbhinav Bisht
 
BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326Danny Flett
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisDan Arthur
 
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...Integrating Geomechanics With Operational Practices Improves Extended-Reach D...
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...Society of Petroleum Engineers
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas FieldsNeil Barnard
 
ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014Xavier MICHEL
 

Mais procurados (20)

26-grover-john-draft
26-grover-john-draft26-grover-john-draft
26-grover-john-draft
 
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
UNCONVENTIONAL GAS- DRILLING FOOTPRINT REDUCTION CHALLENGE
 
OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06OSEA J Grover 7 Dec 06
OSEA J Grover 7 Dec 06
 
Pneumatic Pipe Bursting Systems
Pneumatic Pipe Bursting SystemsPneumatic Pipe Bursting Systems
Pneumatic Pipe Bursting Systems
 
VDOT BMP Clearinghouse Specification 8- Infiltration
VDOT BMP Clearinghouse Specification 8- Infiltration VDOT BMP Clearinghouse Specification 8- Infiltration
VDOT BMP Clearinghouse Specification 8- Infiltration
 
Groundwater Control for Construction
Groundwater Control for ConstructionGroundwater Control for Construction
Groundwater Control for Construction
 
Ch 44 subsoil drainage
Ch 44   subsoil drainageCh 44   subsoil drainage
Ch 44 subsoil drainage
 
Western Pipeway Presentation
Western Pipeway PresentationWestern Pipeway Presentation
Western Pipeway Presentation
 
NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012NI_Water_Dunmurry_2012
NI_Water_Dunmurry_2012
 
Hydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the IndustryHydraulic Fracturing: Importance to the Industry
Hydraulic Fracturing: Importance to the Industry
 
Horizon 2020
Horizon 2020Horizon 2020
Horizon 2020
 
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
Acf environmental   2016 apwa fl expo - integrated infrastructure-an innovati...Acf environmental   2016 apwa fl expo - integrated infrastructure-an innovati...
Acf environmental 2016 apwa fl expo - integrated infrastructure-an innovati...
 
Exploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well TechnologyExploring Tight Gas Reservoir Using Intelligent Well Technology
Exploring Tight Gas Reservoir Using Intelligent Well Technology
 
BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326BOE+Brochure+-+Rotajet+150326
BOE+Brochure+-+Rotajet+150326
 
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative AnalysisState & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
State & Federal Regulation of Hydraulic Fracturing: A Comparative Analysis
 
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...Integrating Geomechanics With Operational Practices Improves Extended-Reach D...
Integrating Geomechanics With Operational Practices Improves Extended-Reach D...
 
Borehole treatment
Borehole treatmentBorehole treatment
Borehole treatment
 
Project_Report[2]
Project_Report[2]Project_Report[2]
Project_Report[2]
 
Development of Tight Gas Fields
Development of Tight Gas FieldsDevelopment of Tight Gas Fields
Development of Tight Gas Fields
 
ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014ADC PRS Study-Paper OGJ- June 2014
ADC PRS Study-Paper OGJ- June 2014
 

Destaque

Destaque (6)

Trenchless Technology Article copy
Trenchless Technology Article copyTrenchless Technology Article copy
Trenchless Technology Article copy
 
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LININGSEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
SEWER REHABILITATION / REPLACEMENT FOR RCC PIPES WITH INTERNAL LINING
 
Trench less Technology
Trench less Technology Trench less Technology
Trench less Technology
 
Trenchless technolgy
Trenchless technolgyTrenchless technolgy
Trenchless technolgy
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 

Semelhante a Stripping of liners from pipes using hdd technology (2007)

A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional BoringWe-Bore-It
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY MD AMANULLAH
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdfpawankumar491710
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologydinesh sharma
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15John Grover
 
soft permeable pipe
soft permeable pipesoft permeable pipe
soft permeable pipecrownswear
 
soft permeable pipe
soft permeable pipesoft permeable pipe
soft permeable pipecrownswear
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfKARTHIKGOUD64
 
Wastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsWastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsAreej Al-Azzawi
 
trenchless technology
trenchless technologytrenchless technology
trenchless technologyHemish Patel
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technologyRemya Rajeev
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.Himanshu Rao
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16Leo Youngman
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxMailapalliJayaRaju
 

Semelhante a Stripping of liners from pipes using hdd technology (2007) (20)

A Complete Guide on Directional Boring
A Complete Guide on Directional BoringA Complete Guide on Directional Boring
A Complete Guide on Directional Boring
 
PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY PPT ON TRENCHLESS TECHNOLOGY
PPT ON TRENCHLESS TECHNOLOGY
 
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdftrenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
trenchlesstechnologybymdamanullah-150920165545-lva1-app6892 (3).pdf
 
Submarine outfalls & intakes ppt
Submarine outfalls & intakes pptSubmarine outfalls & intakes ppt
Submarine outfalls & intakes ppt
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Drilling imp
Drilling impDrilling imp
Drilling imp
 
Trenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe InstallationsTrenchless Technologies for New Pipe Installations
Trenchless Technologies for New Pipe Installations
 
Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15Paper 43 - Deep Water Pipeline CT 9_2_15
Paper 43 - Deep Water Pipeline CT 9_2_15
 
Pipe Jacking
Pipe JackingPipe Jacking
Pipe Jacking
 
soft permeable pipe
soft permeable pipesoft permeable pipe
soft permeable pipe
 
soft permeable pipe
soft permeable pipesoft permeable pipe
soft permeable pipe
 
TRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdfTRENCHLESS-TECHNOLOGY.pdf
TRENCHLESS-TECHNOLOGY.pdf
 
Wastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutionsWastewater pump station_design_problems_and_solutions
Wastewater pump station_design_problems_and_solutions
 
trenchless technology
trenchless technologytrenchless technology
trenchless technology
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
transtech.pptx
transtech.pptxtranstech.pptx
transtech.pptx
 
Trenchless technology
Trenchless technologyTrenchless technology
Trenchless technology
 
Trenchless Technology for Laying Underground pipes.
Trenchless Technology for  Laying Underground pipes.Trenchless Technology for  Laying Underground pipes.
Trenchless Technology for Laying Underground pipes.
 
GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16GROUP_6_YOUNGMAN_L_ANNEX_15-16
GROUP_6_YOUNGMAN_L_ANNEX_15-16
 
Foundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptxFoundations for SPAR Platforms1.pptx
Foundations for SPAR Platforms1.pptx
 

Último

Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...noida100girls
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageMatteo Carbone
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechNewman George Leech
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Tina Ji
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMANIlamathiKannappan
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetDenis Gagné
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Roomdivyansh0kumar0
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfOrient Homes
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation SlidesKeppelCorporation
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 

Último (20)

KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)KestrelPro Flyer Japan IT Week 2024 (English)
KestrelPro Flyer Japan IT Week 2024 (English)
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...BEST ✨ Call Girls In  Indirapuram Ghaziabad  ✔️ 9871031762 ✔️ Escorts Service...
BEST ✨ Call Girls In Indirapuram Ghaziabad ✔️ 9871031762 ✔️ Escorts Service...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
Insurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usageInsurers' journeys to build a mastery in the IoT usage
Insurers' journeys to build a mastery in the IoT usage
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
Nepali Escort Girl Kakori \ 9548273370 Indian Call Girls Service Lucknow ₹,9517
 
RE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman LeechRE Capital's Visionary Leadership under Newman Leech
RE Capital's Visionary Leadership under Newman Leech
 
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
Russian Faridabad Call Girls(Badarpur) : ☎ 8168257667, @4999
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
A DAY IN THE LIFE OF A SALESMAN / WOMAN
A DAY IN THE LIFE OF A  SALESMAN / WOMANA DAY IN THE LIFE OF A  SALESMAN / WOMAN
A DAY IN THE LIFE OF A SALESMAN / WOMAN
 
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature SetCreating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
Creating Low-Code Loan Applications using the Trisotech Mortgage Feature Set
 
Forklift Operations: Safety through Cartoons
Forklift Operations: Safety through CartoonsForklift Operations: Safety through Cartoons
Forklift Operations: Safety through Cartoons
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130  Available With RoomVIP Kolkata Call Girl Howrah 👉 8250192130  Available With Room
VIP Kolkata Call Girl Howrah 👉 8250192130 Available With Room
 
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdfCatalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
Catalogue ONG NƯỚC uPVC - HDPE DE NHAT.pdf
 
Best Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting PartnershipBest Practices for Implementing an External Recruiting Partnership
Best Practices for Implementing an External Recruiting Partnership
 
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
Keppel Ltd. 1Q 2024 Business Update  Presentation SlidesKeppel Ltd. 1Q 2024 Business Update  Presentation Slides
Keppel Ltd. 1Q 2024 Business Update Presentation Slides
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 

Stripping of liners from pipes using hdd technology (2007)

  • 1. North American Society for Trenchless Technology (NASTT) NO-DIG 2006 Nashville, TN March 15-20, 2007 STRIPPING OF LINERS FROM PIPES USING HDD TECHNOLOGY Harry Baum and Kwigs Bowen2 1 President, W.S.U. Inc.., Breckenridge, Colorado 2 Area Manager, Team Fishel, Chandler, Arizona ABSTRACT Horizontal directional drilling is a non-intrusive method for installing utility lines, gas pipes, water pipes, sewer lines or fiber-optic conduit below the ground without the need to open trench. Horizontal directional drills “bore” a tunnel using fixed-length drill rods that are threaded together to create what’s called a drill string. This drill string is advanced or drilled through the ground from an entrance to an exit location. This drilled bore can be drilled to precise locations because of the drilling tool’s slanted steering plate. The orientation of the tool and its slanted steering plate is what determines the direction the drill head navigates. The directional path will move when pushed through the ground without rotation. A transmitter enclosed in the drill heads housing transmits depth, digital clock rotation position, temperature and angle to a remote receiver on the surface. Maximum depth depends upon the style of the transmitter but normally 50 feet is average. Because of the flexibility HDD offers, Harry Baum, owner of W.S.U. Inc. and Steve Wentworth of Earth Tool Company LLC (manufacturer of HammerHead trenchless products) began conversations on the concept to remotely remove linings from the inside of sewer lines. As a novel concept invention Wentworth designed an umbrella like mechanical device which is attached to a directional drill. Wentworth had already designed tooling for other directional drilling uses and was able to quickly offer Baum solutions. Baum was very familiar with failed liners and the problems caused where open cut was often the only solution for removing linings. Removal of factory installed linings using custom designed tooling, deployed and actuated by a directional drill rig, is a new method. Having the ability to attach different tools to the end of rigid drill pipe opens the opportunity for other remotely operated mechanical devices. Just as a surgical tool is used to open arteries the stripping tool could open the clogged sewer arteries without open cutting the entire section. Ductile iron pipe with factory applied high density polyethylene (HDPE) liner has been widely used for sanitary sewer installations where high hydrogen sulfide gas concentrations exist. Failure of the pipes protective HDPE liner from hydrogen sulfide corrosion caused the liner to delaminate in sheets. This created the potential for problematic system backups. It was clear that the failing liner had to be removed. The removal was intended to simultaneously eliminate the potential for backup and produce a surface appropriate for relining using cured in place pipe (CIPP) methods. This paper will review a highly successful 1st attempt at using a new trenchless technology, Liner Stripping, in cooperation with Pima County Wastewater Management, Tucson Arizona. System owner engineers, contractor, sub-contractor and equipment manufacturer joined to make the job possible with the custom developed technology. The job success highlights the potential HDD drills have to service non-man entry or difficult man entry locations with custom engineered tooling. The method of “Liner Stripping,” as with all trenchless methods, will be less disruptive and less invasive than previously accepted methods or remedies to service a pipe’s Paper E-2-04
  • 2. interior spaces. The results demonstrate that servicing the interior of buried pipes with the attributes of an HDD drill stem is a concept that has profound potential. INTRODUCTION Recently, the Pima County Wastewater Management (PCWM) in Tucson, Arizona found itself with a perplexing problem when it tried to rehabilitate one of its ductile HDPE lined sanitary sewer pipes. In weighing possible solutions, PCWM officials permitted “Liner Stripping” of the HDPE using a horizontal directional drill HDD rig followed by CIPP lining of the sewer main. Normally HDD is used for the trenchless installation of new underground utilities not rehabilitation so this application is quite a novel concept. The Pima County wastewater conveyance system consists of nearly 3,300 miles of public separate sanitary sewers, ranging in size from 6- to 78-in. pipe diameters with an 84-in. box culvert. The Old Nogales Highway trunk sewer consists of more than 16,000 ft of 18-in ductile iron pipe with a polyethylene liner. The liner has de-laminated from the host pipe to some degree on roughly one-third of the total length of the trunk sewer line. The de-lamination on some stretches was severe enough warranting an emergency repair to remove the liner from the flow line. Pima County surrounds the high desert city of Tucson and land south to the Mexico border. Tucson sits on a remarkably flat plane consisting of fine granular soil that is susceptible to erosion. Blockage backups must be avoided when operating a pipeline or ground erosion can case sinkholes. In the 1980’s corrosion of ductile iron pipe was avoided by using a factory installed polyethylene lining. The liner .06 to .10” (1.524 to 2.54 mm) thick was intended to prevent hydrogen sulfide gas, from contacting the ductile iron sealing the odiferous gas from the iron atmosphere. Hydrogen sulfide gas is a normal byproduct of decomposition in sanitary systems. Damage to the HDPE liner around the bell and spigot may have occurred during installation or some time afterward allowing hydrogen sulfide to attack the ductile iron pipe. Oxidization built up between the liner and the interior surface of the ductile iron which caused de-bonding of the liner from the pipe. This de- bonding of the liner caused the liner to hang down inside the pipe like poorly applied wallpaper falling from the ceiling. Sewer flow velocity between the de-lamination accelerates the sewer liner degradation. This was evident when an inspection camera (figure 1) was used to inspect the line. The hanging liner (figures 2-5) reduces the annular circumferential area stalling the flow of solids which had caused backups and could continue to do so. Figure 1 - The mobile camera inspection truck controls the operation and recording of a robotic camera. The camera documents real time information which becomes a permanent record for future use. Paper E-2-04
  • 3. Figure 2 - Shown from the robotic camera, is a Figure 3 - The arrow indicates the early stages of separated HDPE liner folded into the flow stream. HDPE lining separation at the ductile iron pipe joint. Figure 4 - The circle indicates liner that has Figure 5 - Liner failure indicated by the camera completely pulled away from the host pipe creating operator. turbulence downstream. A by-product of this turbulence is hydrogen sulfide gas which escalates the degradation of the pipe. Pima County has the additional stress of having the possibility of the backup inducing a sinkhole in one or more locations. For this reason, county officials had to find a solution that would eliminate the hanging liner and find a solution to protect the perfectly serviceable ductile iron portion of their pipe. W.S.U. Inc., in Breckenridge, Colorado, was contracted by Pima County engineers to rehabilitate the ductile iron sewer line using the custom stripping tool developed by Earth Tool Company, LLC, and manufacturer of HammerHead trenchless products based out of Oconomowoc, Wisconsin. The proximity of the line, within a railroad right of way made open-cut a daunting and undesirable method. PCWMD engineers chose the less invasive technology HDD knowing that open cut methodologies would not be acceptable. After the HDPE liner was completely removed a new CIPP liner would be applied to the bare ductile iron pipe which would produce the corrosion barrier need to make the pipe last. To insure complete removal of the HDPE liner a sewer camera recorded instantaneous progress inspection behind the rotating lining striping mechanism. HDD SOLUTION The HDD rig is setback from the intersection from the intended path end point (figure 6). This setback is determined by HDD rig rod radius specifications and the desired depth end point. The midsize HDD rig Paper E-2-04
  • 4. chosen for this application can develop 24,000 pounds of tensile and 4,000 ft. lbs. of torque. However, only a small portion of this power is required to accomplish the stripping liner removal process. A drill rod access point is excavated and the top section of pipe removed (figure 7) An inflatable plug was inserted into the sewer line and the sewer flow was by-passed around the working section (figure 8). Figure 6 - On the surface, the directional drill operator receives radio confirmation from the Figure 8 - To prevent customer camera operator to access interruption, the working section on Figure 7 - For the the sewer line was bypassed using a progress in the sewer line. If a directional drill to access section requires further stripping, pump to maintain sewer flow. the sewer main, a fifteen the camera operator alerts the drill (15) foot section was operator to back up and give removed from the top of the additional attention that section of pipe. pipe. After the trenchless bore path intersected the sewer line, the drill stem was pushed out so as to extend into a downstream manhole where the Poly Stripper mechanism was installed (figure 9). To control the long unsupported drill string a soft urethane radial or triangular pilot was used as a centering plug (figure 10) with marginal diametrical clearance. With rotation bearings housed at both ends of the centering plug stabilized the rod during high speed rotation. Figure 9 - The stripping device is lowered down Figure 10 - The liner stripping device is assembled hole in sections and assembled in the manhole. above ground to instruct crew members of the proper joint assembly connection down hole. The Poly Stripper was attached just behind the centering plug. Using the HDD rig’s water pump pressure, the deployment of the radial stripper arms are controlled via bias pressure within the strippers operating Paper E-2-04
  • 5. piston mechanism (figure 11). Water pressure controls the stripper arms’ force when deployed against the liner host pipe (figure 12). Some water is bypassed around the piston chamber flushing away cuttings continuously. At the entry manhole, a screen was placed in the flow path, separating cuttings from the flow. These chips of the liner were then vacuumed up and disposed of (figure 13). Figure 11 - The stripping arms Figure 12 - The robotic camera Figure 13 - WSU used a vacuum are deployed using water trails the stripping device truck to clean the entry manhole pressure supplied by through the showing where the pipe has and remove the cut lining chips drill stem by a water pump been stripped of the HDPE and other debris. connected to the directional drill. lining. Once the arms are deployed, the drill string is rotated and the liner is scraped from the pipe, preparing it for lining. HDPE liner is scraped away from the adjacent host pipe during rotational arm deployment. Followed by the inspection camera the Poly Strippers’ progress is monitored as rotational speed is variable to approximately 250 rpm. Radio contact between the HDD rig operator and the camera operator was all the direction necessary to achieve production speed of approximately 10ft/min. By inspecting with the camera, the operator was alerted to sections that required further stripping. In addition, the camera operator could communicate the need to retract the stripper arms to de-tangle portions of the HDPE liner that had entangled the stripper arms. Several attachment cutting tools were developed, a .125” (3.175 mm) thick spring steel scraper proved superior to other designs. Each of the three stripper arms held one scraper blade which was angled slightly away from the clock wise rotation center line. Water used to make drilling fluid is common practice when directional drilling underground utilities so additional rig operator training is minimal. Repeatedly, the operator turned on the water pump, waited for water pressure to rise at the rig then began rotating the drill stripping tool. He then pulled drill pipe toward the rig until again removing drill stem and repeating the process. CONCLUSION HDD machines can provide huge economic potential to service non-man entry or difficult man entry locations with custom engineered tooling. Engineers basic working knowleadge of HDD capabilities can solve a myriad of sewer line issues. Pima County Arizona engineers were more than satisfied with the first successful performance of this experimental method. Coordination between engineers, contractor, sub-contractor and equipment manufacturer was essential in providing planning through job completion. Information supplied by Dan Cohen of WSU, a licensee of Inliner Technologies, installed ~ 5,720 lf of 18 inch ∅, 7.4mm thick CIPP using the Pulled-In-Place method of insertion per ASTM F 1743, PCWMD specifications and WSU, ISO protocol. Individual runs of CIPP were resin impregnated at WSU’s wetout facility located near Fairplay, Colorado just prior to it’s scheduled installation date. The wetout tube along with it’s corresponding calibration hose was shipped to the job site in Tucson, Arizona inside a temperature controlled, refrigerated reefer truck. The lining tube was winched into place followed by an air inversion of the calibration hose. The CIPP was then cured using steam for pressure and heat. Paper E-2-04
  • 6. Independent third party testing was performed by HTS, Inc. of Houston, TX for thickness (ASTM D 5813), flexural properties (ASTM D 790) and tensile strength (ASTM D 638). Each CIPP installation exceeded the required minimum properties in every instance. In all, the Poly-Stripper was used to clean about 5,700 feet of pipe over a two and half month period. Afterward, WSU went in and rehabbed the pipe using CIPP with the comfort in knowing the loose liner was completely removed as video proved. To date the project is considered by all involved to have been a very succuessful method for removing de-bonded liner from ductile iron pipe. Because the liner was removed completely, the corresponding CIPP liner was installed normally without any intrusive obstacles. Paper E-2-04