SlideShare uma empresa Scribd logo
1 de 38
Baixar para ler offline
February 13, 2014
Bill Rose, Director of Engineering
Gary Bousquet, Engineering Manager
Special Meeting
Imported Water Committee
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
2
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
3
 BDCP Preferred Alternative: 9,000 cfs
pipeline/tunnel
 No Action Alternative
 NRDC Portfolio Concept
 Delta Vision BDCP Plus Concept
4
5
 2 – 40 feet diameter 30 mile long tunnels
between intermediate forebay and
modified Clifton Court forebay
 5 tunnel launch/retrieval shafts
 Clifton Court forebay split into 2, north
and south forebays
6
 3- 3,000 cfs intakes off Sacramento River
w/ sedimentation basins and pumping
plants
 3 – North tunnels 20/29 feet diameter,
~14 miles between pumping plants and
intermediate forebay
 1 – 40 acre intermediate forebay
connected to main conveyance tunnels
7
9
10
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
11
 Water Authority Gate Process
 Risk Management Plan
 Potential impacts on project cost
and schedule
12
Gate 1 - Risk Management Plan
Identify
Analyze
MitigateMonitor
Update Manage
Risks
During All
Project
Phases
Project Initiation and Design Phases
13
 Channel Tunnel (United Kingdom/France)
 Alaska Way Viaduct (Seattle)
 Calaveras Dam (Bay Area)
 Panama Canal Expansion
 Bay Bridge
14
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
15
Milestone Completion Date Allowable
Delay
Final EIR/EIS Complete August 29, 2014 {0}
Notice to Proceed Construction November 20, 2019 {0}
Pump Procurement Complete July 18, 2022 {681}
TBM Procurement Finished September 13, 2023 {387}
Finish Installing Permanent Power January 17, 2024 {0}
Intermediate Forebay Complete June 9, 2027 {641}
Intake Pumping Plants Finished November 1, 2027 {540}
Main Conveyance Tunnels
Complete
July 15, 2028 {382}
Main Tunnel Startup and
Commissioning Finished
December 22, 2028 {0}
16
17
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
18
 Property acquisition plan
 Condemnation considerations
 Appraisal process
 Securing rights of entry or up front work
19
 Excavated material removal
 Excavated material disposal
 Ventilation system design
 Tunnel boring machines
20
 Temporary power
◦ Locations for power delivery
◦ Power needs
◦ Electrical infrastructure design and construction
 Permanent power
◦ Assess existing transmission system for possible
system upgrades
◦ Look at system reliability
21
 Utilities
 SR-12 and SR-160 highway relocations
 Natural gas wells
22
23
 Existing work accomplished
 Ground conditions
 Groundwater
 Borings
24
 Historical Data – Collected from other Delta
area projects such as levees and highways
 2009-2012 Field Explorations – borings, cone
penetration tests, geophysical surveys, and
laboratory testing
 Identifying soils types, hardness,
groundwater elevations, cobbles …
25
26
 Design Bid Build versus Design Build
 Bonding ability
 Labor requirements
 Project labor agreements
27
 Tunnel boring machines
 Steel liners
 Borrow material
 Specialized contractors
 Technical experts
 Competing projects
28
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
29
 River Intake Structures
 Forebays & flow control structures
 Tunnels and pipelines
 Controls and communications
 Utilities and power delivery
 Contingency ~ 36 percent
30
Estimated Costs
Dual Tunnels
3,000 cfs 6,000 cfs BDCP
Proposed
9,000 cfs
15,000 cfs
Construction $9.4B $11.4B $12.4B $14.5B
Engineering,
project/construction
management
$1.4B $1.7B $1.9B
(~15%)
$2.3B
Total $10.8B $13.1B $14.3B $16.8B
Tunnel Options Construction Costs
Source: BDCP, Table 9.B-6, November 2013
Notes: 1. BDCP revised cost of single bore tunnel is $8.6B per
November 12, 2013 web post.
2. Costs are stated in 2012 dollars.
31
 Contingency @ 36 percent
 Soft Costs @ 15 percent
 Direct Construction Costs Expected
Accuracy Range +50% to -25%
◦ Results in Range of $11.2 to $20.6 billion
32
 Description of Proposed Facilities
 Review Process – Gate Process
 Construction Schedule
 Risk Areas
 Construction Estimate
 Greatest Risks and Impacts
33
 Unknown subsurface conditions
 Alternate project delivery methods
 Property acquisition
 Resource timing
34
 Add contingency and time to schedule
 Manage Risk (e.g. use risk register)
35
 Review Updated Engineering Conceptual
Design Report – Complete
 Engineering Assessment of BDCP Costs
Estimates – February 2014
 Comment Letter – April 2014
36
37
38

Mais conteúdo relacionado

Mais procurados

Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationIRJET Journal
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Fairfax County
 
Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_updateBoris Markov
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationFairfax County
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Toronto Public Consultation Unit
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016Rolando Garcia
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Fairfax County
 
Victoria Lamore. Resume 2016. pdf
Victoria Lamore. Resume 2016. pdfVictoria Lamore. Resume 2016. pdf
Victoria Lamore. Resume 2016. pdfVictoria Lamore
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014San Diego County Water Authority
 
Sample Airport / Aviation Projects (2015 - 2020)
Sample Airport / Aviation Projects (2015 - 2020)Sample Airport / Aviation Projects (2015 - 2020)
Sample Airport / Aviation Projects (2015 - 2020)Nelson Ekeh E.I.T.
 

Mais procurados (20)

Assessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer StationAssessment the Need of Al Kut City for Solid Waste Transfer Station
Assessment the Need of Al Kut City for Solid Waste Transfer Station
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation - BTC U...
 
Presentation CS_update
Presentation CS_updatePresentation CS_update
Presentation CS_update
 
CV - Ahmed Mounir
CV - Ahmed MounirCV - Ahmed Mounir
CV - Ahmed Mounir
 
Scott Smith-complete-employment-history
Scott Smith-complete-employment-historyScott Smith-complete-employment-history
Scott Smith-complete-employment-history
 
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 ImplementationDulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
Dulles Corridor Metrorail Project: Silver Line Phase 2 Implementation
 
Hossam CV-FEB2016
Hossam CV-FEB2016Hossam CV-FEB2016
Hossam CV-FEB2016
 
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
Lng use in trucking
Lng use in truckingLng use in trucking
Lng use in trucking
 
CVAQ5
CVAQ5CVAQ5
CVAQ5
 
CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016CV_Rolando M. Garcia_Feb 2016
CV_Rolando M. Garcia_Feb 2016
 
CNG & LNG for Heavy Duty Trucking
CNG & LNG forHeavy Duty TruckingCNG & LNG forHeavy Duty Trucking
CNG & LNG for Heavy Duty Trucking
 
eng.ramy
eng.ramy eng.ramy
eng.ramy
 
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
Dulles Corridor Metrorail Project: Board Transportation Committee Update- Jul...
 
Vedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas ShipsVedam Design: Engineering Solutions - Gas Ships
Vedam Design: Engineering Solutions - Gas Ships
 
Victoria Lamore. Resume 2016. pdf
Victoria Lamore. Resume 2016. pdfVictoria Lamore. Resume 2016. pdf
Victoria Lamore. Resume 2016. pdf
 
Vedam Design:- BWTS - Retrofits Services
Vedam Design:-  BWTS - Retrofits Services Vedam Design:-  BWTS - Retrofits Services
Vedam Design:- BWTS - Retrofits Services
 
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
Bay-Delta Conservation Plan -- Infrastructure Review, Jan. 9, 2014
 
Sample Airport / Aviation Projects (2015 - 2020)
Sample Airport / Aviation Projects (2015 - 2020)Sample Airport / Aviation Projects (2015 - 2020)
Sample Airport / Aviation Projects (2015 - 2020)
 

Semelhante a Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014

PPT Item # 5 - Water Main Installation HDD
PPT Item # 5 - Water Main Installation HDDPPT Item # 5 - Water Main Installation HDD
PPT Item # 5 - Water Main Installation HDDahcitycouncil
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationFairfax County
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationDamian Coetzee
 
G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptxVatsalPancholi6
 
Sea to Ski Higway Improvements Project
Sea to Ski Higway Improvements ProjectSea to Ski Higway Improvements Project
Sea to Ski Higway Improvements ProjectUrbanSystemsCanada
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentationKunal Gudwani
 
Robin dargavel consutant mechanical - facilities engineer
Robin dargavel   consutant mechanical - facilities engineerRobin dargavel   consutant mechanical - facilities engineer
Robin dargavel consutant mechanical - facilities engineerRobin Dargavel BEng (Hons)
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptxPradeepKumar504728
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptxseifelsaie2
 
Pipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringPipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringTauqueerAhmad17
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013 carsoncorporation
 
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...UrbanSystemsCanada
 
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...Environmental Protection Agency, Ireland
 
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridgesindranaths
 

Semelhante a Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014 (20)

PPT Item # 5 - Water Main Installation HDD
PPT Item # 5 - Water Main Installation HDDPPT Item # 5 - Water Main Installation HDD
PPT Item # 5 - Water Main Installation HDD
 
Stormwater Wastewater Consolidation
Stormwater Wastewater ConsolidationStormwater Wastewater Consolidation
Stormwater Wastewater Consolidation
 
Wp special master-plan[071113]
Wp special master-plan[071113]Wp special master-plan[071113]
Wp special master-plan[071113]
 
CBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins PresentationCBI-electric Renewable Cabins Presentation
CBI-electric Renewable Cabins Presentation
 
Nazmy Markos
Nazmy MarkosNazmy Markos
Nazmy Markos
 
G13 - Project Management.pptx
G13 - Project Management.pptxG13 - Project Management.pptx
G13 - Project Management.pptx
 
Sea to Ski Higway Improvements Project
Sea to Ski Higway Improvements ProjectSea to Ski Higway Improvements Project
Sea to Ski Higway Improvements Project
 
Project charter presentation
Project charter presentationProject charter presentation
Project charter presentation
 
Robin dargavel consutant mechanical - facilities engineer
Robin dargavel   consutant mechanical - facilities engineerRobin dargavel   consutant mechanical - facilities engineer
Robin dargavel consutant mechanical - facilities engineer
 
Mahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCVMahmoud Ahmed ElbadawyCV
Mahmoud Ahmed ElbadawyCV
 
Saeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer UtilitiesSaeed Ahmad Infrastucture Engineer Utilities
Saeed Ahmad Infrastucture Engineer Utilities
 
Cost estimate presentation (1).pptx
Cost estimate presentation (1).pptxCost estimate presentation (1).pptx
Cost estimate presentation (1).pptx
 
Tunnel Presentation (1).pptx
Tunnel Presentation (1).pptxTunnel Presentation (1).pptx
Tunnel Presentation (1).pptx
 
Pipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineeringPipeline - MIT.ppt for pipeline engineering
Pipeline - MIT.ppt for pipeline engineering
 
Negdc presentation december 2013
Negdc presentation   december 2013 Negdc presentation   december 2013
Negdc presentation december 2013
 
The GBHE Project Experience
The GBHE Project ExperienceThe GBHE Project Experience
The GBHE Project Experience
 
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...
Risk Analysis and the Identification of Infrastructure Renewal Needs for the ...
 
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
15. Addressing challeneges in wastewater netwroks - Michael Goss - Water Even...
 
Design manual-for-small-bridges
Design manual-for-small-bridgesDesign manual-for-small-bridges
Design manual-for-small-bridges
 
Masterplan.pptx
Masterplan.pptxMasterplan.pptx
Masterplan.pptx
 

Mais de San Diego County Water Authority

Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 San Diego County Water Authority
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...San Diego County Water Authority
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...San Diego County Water Authority
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014San Diego County Water Authority
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesSan Diego County Water Authority
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...San Diego County Water Authority
 

Mais de San Diego County Water Authority (20)

Session 2 presentation
Session 2 presentationSession 2 presentation
Session 2 presentation
 
Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015Update on Supply Conditions and Drought Response Activities - September 24, 2015
Update on Supply Conditions and Drought Response Activities - September 24, 2015
 
Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015 Update on Supply Conditions and Drought Response Activities - June 25, 2015
Update on Supply Conditions and Drought Response Activities - June 25, 2015
 
Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015Update on Supply Conditions and Drought Response Activities - October 22, 2015
Update on Supply Conditions and Drought Response Activities - October 22, 2015
 
Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015Update on Supply Conditions and Drought Response Activities - December 10, 2015
Update on Supply Conditions and Drought Response Activities - December 10, 2015
 
Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016Update on Supply Conditions and Drought Response Activities - February 25, 2016
Update on Supply Conditions and Drought Response Activities - February 25, 2016
 
Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015Update on Supply Conditions and Drought Response Activities - August 27, 2015
Update on Supply Conditions and Drought Response Activities - August 27, 2015
 
Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015 Update on Supply Conditions and Drought Response Activities - July 23, 2015
Update on Supply Conditions and Drought Response Activities - July 23, 2015
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFixBay Delta Conservation Plan/California WaterFix
Bay Delta Conservation Plan/California WaterFix
 
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
Bay Delta Conservation Plan/California WaterFix: Potential Cost Impact to the...
 
Bay-Delta Activities Update
Bay-Delta Activities UpdateBay-Delta Activities Update
Bay-Delta Activities Update
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...State Treasurer's Assessment of the Affordability and Financing Consideration...
State Treasurer's Assessment of the Affordability and Financing Consideration...
 
2015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 20152015-2016 Bay-Delta Workplan - February 26, 2015
2015-2016 Bay-Delta Workplan - February 26, 2015
 
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
Bay-Delta Conservation Plan: Supplemental Draft EIR/EIS Comment Letter - July...
 
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
Bay-Delta Conservation Plan: Economic and Financial Risk Assessment to the Wa...
 
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
Bay-Delta Conservation Plan: Draft EIR/EIS Comment Letter - March 27, 2014
 
Update on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response ActivitiesUpdate on Supply Conditions and Drought Response Activities
Update on Supply Conditions and Drought Response Activities
 
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
Approval of Shortage Management Actions in Response to MWD Supply Cutbacks an...
 

Último

Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Delhi Call girls
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdflambardar420420
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Delhi Call girls
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...anjanibaddipudi1
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceDelhi Call girls
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkobhavenpr
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Delhi Call girls
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPsychicRuben LoveSpells
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreiebhavenpr
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptxYasinAhmad20
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...Andy (Avraham) Blumenthal
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...hyt3577
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfssuser5750e1
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)Delhi Call girls
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsVoterMood
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdfFIRST INDIA
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhbhavenpr
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Developmentnarsireddynannuri1
 

Último (20)

Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 48 (Gurgaon)
 
422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf422524114-Patriarchy-Kamla-Bhasin gg.pdf
422524114-Patriarchy-Kamla-Bhasin gg.pdf
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Gurgaon Sector 46 (Gurgaon)
 
04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf04052024_First India Newspaper Jaipur.pdf
04052024_First India Newspaper Jaipur.pdf
 
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
*Navigating Electoral Terrain: TDP's Performance under N Chandrababu Naidu's ...
 
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort ServiceBusty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
Busty Desi⚡Call Girls in Vasundhara Ghaziabad >༒8448380779 Escort Service
 
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopkoEmbed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
Embed-2 (1).pdfb[k[k[[k[kkkpkdpokkdpkopko
 
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
Enjoy Night ≽ 8448380779 ≼ Call Girls In Palam Vihar (Gurgaon)
 
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost LoverPowerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
Powerful Love Spells in Phoenix, AZ (310) 882-6330 Bring Back Lost Lover
 
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreieGujarat-SEBCs.pdf pfpkoopapriorjfperjreie
Gujarat-SEBCs.pdf pfpkoopapriorjfperjreie
 
China's soft power in 21st century .pptx
China's soft power in 21st century   .pptxChina's soft power in 21st century   .pptx
China's soft power in 21st century .pptx
 
06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf06052024_First India Newspaper Jaipur.pdf
06052024_First India Newspaper Jaipur.pdf
 
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
America Is the Target; Israel Is the Front Line _ Andy Blumenthal _ The Blogs...
 
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
{Qatar{^🚀^(+971558539980**}})Abortion Pills for Sale in Dubai. .abu dhabi, sh...
 
declarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdfdeclarationleaders_sd_re_greens_theleft_5.pdf
declarationleaders_sd_re_greens_theleft_5.pdf
 
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
WhatsApp 📞 8448380779 ✅Call Girls In Chaura Sector 22 ( Noida)
 
Politician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full DetailsPolitician uddhav thackeray biography- Full Details
Politician uddhav thackeray biography- Full Details
 
05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf05052024_First India Newspaper Jaipur.pdf
05052024_First India Newspaper Jaipur.pdf
 
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdhEmbed-4.pdf lkdiinlajeklhndklheduhuekjdh
Embed-4.pdf lkdiinlajeklhndklheduhuekjdh
 
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's DevelopmentNara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
Nara Chandrababu Naidu's Visionary Policies For Andhra Pradesh's Development
 

Bay Delta Conservation Plan - Infrastructure Review - Feb. 13, 2014

  • 1. February 13, 2014 Bill Rose, Director of Engineering Gary Bousquet, Engineering Manager Special Meeting Imported Water Committee
  • 2.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 2
  • 3.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 3
  • 4.  BDCP Preferred Alternative: 9,000 cfs pipeline/tunnel  No Action Alternative  NRDC Portfolio Concept  Delta Vision BDCP Plus Concept 4
  • 5. 5
  • 6.  2 – 40 feet diameter 30 mile long tunnels between intermediate forebay and modified Clifton Court forebay  5 tunnel launch/retrieval shafts  Clifton Court forebay split into 2, north and south forebays 6
  • 7.  3- 3,000 cfs intakes off Sacramento River w/ sedimentation basins and pumping plants  3 – North tunnels 20/29 feet diameter, ~14 miles between pumping plants and intermediate forebay  1 – 40 acre intermediate forebay connected to main conveyance tunnels 7
  • 8.
  • 9. 9
  • 10. 10
  • 11.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 11
  • 12.  Water Authority Gate Process  Risk Management Plan  Potential impacts on project cost and schedule 12
  • 13. Gate 1 - Risk Management Plan Identify Analyze MitigateMonitor Update Manage Risks During All Project Phases Project Initiation and Design Phases 13
  • 14.  Channel Tunnel (United Kingdom/France)  Alaska Way Viaduct (Seattle)  Calaveras Dam (Bay Area)  Panama Canal Expansion  Bay Bridge 14
  • 15.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 15
  • 16. Milestone Completion Date Allowable Delay Final EIR/EIS Complete August 29, 2014 {0} Notice to Proceed Construction November 20, 2019 {0} Pump Procurement Complete July 18, 2022 {681} TBM Procurement Finished September 13, 2023 {387} Finish Installing Permanent Power January 17, 2024 {0} Intermediate Forebay Complete June 9, 2027 {641} Intake Pumping Plants Finished November 1, 2027 {540} Main Conveyance Tunnels Complete July 15, 2028 {382} Main Tunnel Startup and Commissioning Finished December 22, 2028 {0} 16
  • 17. 17
  • 18.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 18
  • 19.  Property acquisition plan  Condemnation considerations  Appraisal process  Securing rights of entry or up front work 19
  • 20.  Excavated material removal  Excavated material disposal  Ventilation system design  Tunnel boring machines 20
  • 21.  Temporary power ◦ Locations for power delivery ◦ Power needs ◦ Electrical infrastructure design and construction  Permanent power ◦ Assess existing transmission system for possible system upgrades ◦ Look at system reliability 21
  • 22.  Utilities  SR-12 and SR-160 highway relocations  Natural gas wells 22
  • 23. 23
  • 24.  Existing work accomplished  Ground conditions  Groundwater  Borings 24
  • 25.  Historical Data – Collected from other Delta area projects such as levees and highways  2009-2012 Field Explorations – borings, cone penetration tests, geophysical surveys, and laboratory testing  Identifying soils types, hardness, groundwater elevations, cobbles … 25
  • 26. 26
  • 27.  Design Bid Build versus Design Build  Bonding ability  Labor requirements  Project labor agreements 27
  • 28.  Tunnel boring machines  Steel liners  Borrow material  Specialized contractors  Technical experts  Competing projects 28
  • 29.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 29
  • 30.  River Intake Structures  Forebays & flow control structures  Tunnels and pipelines  Controls and communications  Utilities and power delivery  Contingency ~ 36 percent 30
  • 31. Estimated Costs Dual Tunnels 3,000 cfs 6,000 cfs BDCP Proposed 9,000 cfs 15,000 cfs Construction $9.4B $11.4B $12.4B $14.5B Engineering, project/construction management $1.4B $1.7B $1.9B (~15%) $2.3B Total $10.8B $13.1B $14.3B $16.8B Tunnel Options Construction Costs Source: BDCP, Table 9.B-6, November 2013 Notes: 1. BDCP revised cost of single bore tunnel is $8.6B per November 12, 2013 web post. 2. Costs are stated in 2012 dollars. 31
  • 32.  Contingency @ 36 percent  Soft Costs @ 15 percent  Direct Construction Costs Expected Accuracy Range +50% to -25% ◦ Results in Range of $11.2 to $20.6 billion 32
  • 33.  Description of Proposed Facilities  Review Process – Gate Process  Construction Schedule  Risk Areas  Construction Estimate  Greatest Risks and Impacts 33
  • 34.  Unknown subsurface conditions  Alternate project delivery methods  Property acquisition  Resource timing 34
  • 35.  Add contingency and time to schedule  Manage Risk (e.g. use risk register) 35
  • 36.  Review Updated Engineering Conceptual Design Report – Complete  Engineering Assessment of BDCP Costs Estimates – February 2014  Comment Letter – April 2014 36
  • 37. 37
  • 38. 38