1. SoberIT
Software Business and Engineering Institute
T-76.5612 Software Project Management
Spring 2010
6: Distributed Software Projects
Tuomas Niinimäki
Department of Computer Science and Engineering
Helsinki University of Technology
HELSINKI UNIVERSITY OF TECHNOLOGY
2. SoberIT
Software Business and Engineering Institute
Why distribute a software project?
HELSINKI UNIVERSITY OF TECHNOLOGY
3. SoberIT
Software Business and Engineering Institute
Goals of distribution
Cost reduction
Access to competent labor force
Presence in new markets
Around-the-clock / Follow-the-sun development
Focusing on core competencies
(Carmel 1999)
HELSINKI UNIVERSITY OF TECHNOLOGY
4. SoberIT
Software Business and Engineering Institute
Distributed Software Development
Project can be distributed by
Geographical location (~ offshoring)
Organizational boundaries (~ outsourcing)
HELSINKI UNIVERSITY OF TECHNOLOGY
5. SoberIT
Software Business and Engineering Institute
Distributed Project Types
Organizational
distance
Locally
2 or more Collocated distributed Global
organizations
inter- inter- inter-
organizational organizational organizational
Locally
Traditional distributed Global
1 organization
intra- intra- intra-
organizational organizational organizational
Geographical
Same Same Different distance
location country countries
(Paasivaara 2005)
HELSINKI UNIVERSITY OF TECHNOLOGY
6. SoberIT
Software Business and Engineering Institute
Geographical distance Organizational distance
Cultural distance
HELSINKI UNIVERSITY OF TECHNOLOGY
7. SoberIT
Software Business and Engineering Institute
Benefits
Geographical distance Organizational distance
Cost-reduction Focus on core competencies
Access to new markets Access to competent labor
Access to competent labor Cost-reduction
Follow the sun –
development
Cultural distance
Access to new markets
Access to competent labor
HELSINKI UNIVERSITY OF TECHNOLOGY
8. SoberIT
Software Business and Engineering Institute
Challenges
Geographical distance Organizational distance
Location Command & Control
Time zones Practices
Cultural distance
Conventions
Assumptions
Language
HELSINKI UNIVERSITY OF TECHNOLOGY
9. SoberIT
Software Business and Engineering Institute
Geographical distance – near/offshore
Offshoring
Globally distributed software development projects
E.g. in different continents, across multiple time-zones
Higher potential to leverage cost differences
Nearshoring
Not going too far, e.g. in the same continent / time-zone
Reducing risk by having
similar culture
business conventions
legal system
less geographical distance between sites
HELSINKI UNIVERSITY OF TECHNOLOGY
11. SoberIT
Software Business and Engineering Institute
Allen curve (Allen 1978)
Probability of Communication at least once a week
30%
10%
Distance
30 m
HELSINKI UNIVERSITY OF TECHNOLOGY
12. SoberIT
Software Business and Engineering Institute
Geographical distance - summary
Goals: Risks:
Cost-reduction Communication delays
Access to new markets Lack of awareness,
Access to competent labor visibility
Follow the sun – Division of work
development Language problems and
cultural conflicts
Different business
conventions, legislation, …
Low risk = less benefits High risk = more benefits
Collocated Distributed in Nearshoring Offshoring
one country
HELSINKI UNIVERSITY OF TECHNOLOGY
13. SoberIT
Software Business and Engineering Institute
Organizational distribution
Goals: Risks:
Focus on core Differences in practices,
competencies conventions
Access to competent labor Division of tasks
Lower cost Command & control
Lack of visibility
Contracts
Conflicts of interest,
competition
HELSINKI UNIVERSITY OF TECHNOLOGY
14. SoberIT
Software Business and Engineering Institute
Organizational distance
Broadness
of the task Broad
Transparent
Box Black
box
Independent
subcontractor
Resources teams
Small- managed by
scale the customer
Project
management
resposibility
Customer Subcontractor
Subcontractor uses Collaboration practices The subcontractor
customer’s process need to be defined uses its own process
HELSINKI UNIVERSITY OF TECHNOLOGY
15. SoberIT
Software Business and Engineering Institute
Challenges of Distribution (1/4)
Coordination breakdown
Difficult to divide tasks
Geographical distance
Limits informal communication and face-to-face meetings
Traveling is expensive and time-consuming
Time-zone differences
Around-the-clock development?
Limits face-to-face meetings and synchronous
communication
Problem solving, integration and testing is hard and slow
HELSINKI UNIVERSITY OF TECHNOLOGY
16. SoberIT
Software Business and Engineering Institute
Challenges of Distribution (2/4)
Communication breakdown
Lack of communication richness
Cultural differences
Language barrier
Differences in terms used
HELSINKI UNIVERSITY OF TECHNOLOGY
17. SoberIT
Software Business and Engineering Institute
Challenges of Distribution (3/4)
Loss of “teamness”
Lack of motivation/incentive to communicate
Lack of feedback
Lack of transparency
Lack of trust
Fear, uncertainty, doubt
Company/Organization borders restrict information flow
HELSINKI UNIVERSITY OF TECHNOLOGY
18. SoberIT
Software Business and Engineering Institute
Challenges of Distribution (4/4)
Organizational borders
Roles and responsibilities?
Differing processes, tools and working practices
Lack of visibility
Context of work unclear
Information needs unclear
Forgetting or disregarding the informing of distant sites or
partners
Lack of contacts
HELSINKI UNIVERSITY OF TECHNOLOGY
19. SoberIT
Software Business and Engineering Institute
How to reduce risk in
distributed software projects?
HELSINKI UNIVERSITY OF TECHNOLOGY
20. SoberIT
Software Business and Engineering Institute
Risk from geographical distance
Reduce risks from geographical distance
Travel enough
especially when problems
in the beginning of the project
in testing and integration phases
Face-to-face communication essential for
Grounding of terms and concepts (= shared
understanding)
Informal communication
Teamness (= trust, togetherness)
HELSINKI UNIVERSITY OF TECHNOLOGY
21. SoberIT
Software Business and Engineering Institute
Reducing risk from time zone difference
Reduce risk from temporal distance
Working across time-zones reduces possibilities for
communication
Choose sites and partners preferably within same time-zone, if
frequent communication is needed
Use asynchronous communication
configuration management
testing tools
bug repository…
HELSINKI UNIVERSITY OF TECHNOLOGY
22. SoberIT
Software Business and Engineering Institute
Reducing risks from cultural differences
Reduce cultural distance
Bridgehead:
e.g. 25% of personnel onshore close to customer and
75% offshore
Cultural liaison:
e.g. a native of India settled in Finland
serving as a cultural liaison with the offshore team in
India
Rotate management across locations to create awareness for
cultural diversity and how to cope with it
HELSINKI UNIVERSITY OF TECHNOLOGY
23. SoberIT
Software Business and Engineering Institute
Practices for managing
distributed software project
HELSINKI UNIVERSITY OF TECHNOLOGY
24. SoberIT
Software Business and Engineering Institute
Visiting Engineer
Visits the collaboration partner (customer, subcontractor,
subsidiary)
Stays and works there for a longer period of time
1 week – several months
Main task is to facilitate communication between sites
Passing information and knowledge
Facilitates grounding (common concepts)
Creates contacts
Helps to solve problems (both technical and organizational)
Is available for face-to-face discussions
HELSINKI UNIVERSITY OF TECHNOLOGY
25. SoberIT
Software Business and Engineering Institute
Frequent Deliveries
Especially beneficial in distributed projects
E.g., weekly deliveries
Integration
Feedback from remote site, from customer
Benefits
Creates transparency
Ensures understanding of requirements
Brings real check points
Avoids “big bang integration”
Gives instant feedback
Improves developer motivation
HELSINKI UNIVERSITY OF TECHNOLOGY
26. SoberIT
Software Business and Engineering Institute
Frequent Deliveries
Delivery / Release cycles should be synchronized
The same cycle length should be used by all sites
Schedule for deliveries should be planned
Processes and practices for incoming deliveries
Resource allocation for evaluating the delivery
Too frequent deliveries increase overhead
But may still be beneficial for e.g. risk management, quality
HELSINKI UNIVERSITY OF TECHNOLOGY
27. SoberIT
Software Business and Engineering Institute
Example:
Different Delivery Cycles
Company Alpha let their North American site deliver to us once
every two months. We were required to deliver once a week.
When we noticed that something was missing, we had to wait for
two months.
We complained about that, and finally they changed to this same
once-a-week delivery cycle, but it took all too long to do this
change.
Two month delivery cycle was one of the biggest mistakes made in
this project. Our bug fixing average times were somewhere
between two and three months before the change.
Our scheduling was ruined. We got all the complaints because we
were subcontractors.
HELSINKI UNIVERSITY OF TECHNOLOGY
28. SoberIT
Software Business and Engineering Institute
Peer-to-Peer Links
Establishment of peer-to-peer links between organizations at
several levels
Improves communication
Enhances teamness
Links can be created between named roles
Management level: Subcontracting
Project level: Project managers
Team level: Domain / Technology experts
Proper and updated organization chart easily available
E.g. photos, roles and contact information at project’s web-
site
HELSINKI UNIVERSITY OF TECHNOLOGY
29. SoberIT
Software Business and Engineering Institute
Example: Team level links
“As a project manager my task is to create the right contacts
between the developers, so that I don’t slow down the work
and communication.
Instead, as soon as possible, the right persons will discuss
directly, and I just follow that it is working and there isn’t
problems.
When I meet the customer’s project manager and he introduces
me to somebody [from the customer company]. When I find
out that he works with certain module and that we have one
person working with another [related] module, we arrange a
meeting either through email, phone, or face-to-face. Then
they can solve common problems together.”
HELSINKI UNIVERSITY OF TECHNOLOGY
30. SoberIT
Software Business and Engineering Institute
Problem solving practices
Problem solving communication is even more important in
distributed projects than in collocated projects
Often neglected in the project planning phase
Includes discussion related to
Requirements
Design
interfaces
technical environment
project context
Lack of answers delays the project
Barrier to ask / motivation to answer?
HELSINKI UNIVERSITY OF TECHNOLOGY
31. SoberIT
Software Business and Engineering Institute
Problem solving practices
The lack of answers delays the project
Barrier to ask questions <-> motivation to answer?
Consumes time and resources!
Solutions:
Problem solving responsible
Discussion forums
Direct contacts between developers (e.g., chat)
Workshops, camps
Face-to-face problem solving
E.g. collocated integration and testing
Building trust between teams and individuals
HELSINKI UNIVERSITY OF TECHNOLOGY
32. SoberIT
Software Business and Engineering Institute
Sharing information
In a distributed project people get only the information you give
them
Formal communication:
Make sure important decisions and other information is
shared efficiently
Make sure all sites have the access to relevant sources of
information
Make sure they know they have the access to information
Tacit knowledge: “There is a lot of information at the corridors”
Do not expect anyone to know anything
Make sure they know!
Context information helps to understand other messages
HELSINKI UNIVERSITY OF TECHNOLOGY
33. SoberIT
Software Business and Engineering Institute
Sharing information
Practices:
Inform in the beginning
Give reasons and background information
Regular meetings
Weekly meetings, e.g. teleconference
Issue trackers, task trackers, repositories
Various systems for managing changes and bugs
Can your subcontractor access?
Peer-to-peer links in all levels of organization
Informal communication
Sharing project context
HELSINKI UNIVERSITY OF TECHNOLOGY
34. SoberIT
Software Business and Engineering Institute
Monitoring and Giving Transparency
Visualize and communicate project status
Follow-up in both directions
From the subcontractor to the customer
About project progress to the subcontractor
Transparency is important
Team members at all distributed sites need progress
information -> a motivating factor
One site only managing and controlling the other can be
really annoying and demotivating
Open communication about problems and challenges both
ways!
HELSINKI UNIVERSITY OF TECHNOLOGY
35. SoberIT
Software Business and Engineering Institute
Monitoring and Giving Transparency
Practices:
Regular meetings
Who should attend which meeting?
Managerial & technical meetings?
Progress reports
E.g., tasks done, open questions, problems, future
estimates
Frequent deliveries and integration
Peer-to-peer communication
HELSINKI UNIVERSITY OF TECHNOLOGY
36. SoberIT
Software Business and Engineering Institute
Feedback
Subcontractors appreciate all feedback - also positive!
A motivating factor
What kind of indirect feedback are you giving?
Do you listen to the subcontractor’s ideas?
Practices:
Design and code walkthroughs
Lessons learned
Frequent deliveries
HELSINKI UNIVERSITY OF TECHNOLOGY
37. SoberIT
Software Business and Engineering Institute
Example: Give Feedback
"Sometimes I feel that this is like a black hole, we make [code],
and send it somewhere. (...) If you haven't got any feedback for
your work during the last half year, then you just start to wonder
whether it is ok or not. Of course it is not, because when they
start to test after that half a year, then you get the mistakes. It
is difficult because you have already forgotten what you did a
half year ago."
HELSINKI UNIVERSITY OF TECHNOLOGY
38. SoberIT
Software Business and Engineering Institute
Building relationships
All communication affects relationship building
Especially meetings in the beginning are important
You cannot have too many face-to-face meetings
Travel!!
Use “visiting engineer” practice
Make visits from all sites possible
Arrange a common kick-off
Whole project team, or for each sub-project
Both formal and informal agenda
Make it possible for people to interact and get to know each
other
Maintain relationships with subsequent team events
HELSINKI UNIVERSITY OF TECHNOLOGY
39. SoberIT
Software Business and Engineering Institute
Building relationships
Alternatively other possibilities to meet, e.g.
Steering group meetings at different sites
Provide context from all sites
Trainings
hands-on training!
Pair programming
Workshops, camps, planning and problem solving meetings
Practices:
Give Faces
Kick-off
Trust building based on professional skill
Organization Chart
HELSINKI UNIVERSITY OF TECHNOLOGY
40. SoberIT
Software Business and Engineering Institute
Example: Relationship Building
We had difficulties to get our acceptance testing people to
understand that we are in the same boat [with our
subcontractors] and it is no use to be enemies.
The reasons behind might be that when these developers get a
delivery and it is not functioning perfectly well, and they know
that it is not made by their friends here, but by someone living in
Turkey and trying to do it as cheap as possible.
And that was the reason why testing was delayed here, because it
was not motivating.
In this project we learned a lot about communication and how much
it actually helps to see those subcontractor’s faces. It was
difficult to believe it beforehand!
HELSINKI UNIVERSITY OF TECHNOLOGY
42. SoberIT
Software Business and Engineering Institute
Geographical distance Organizational distance
Cultural distance
HELSINKI UNIVERSITY OF TECHNOLOGY
43. SoberIT
Software Business and Engineering Institute
Lessons learned
Distributing a software project does not make it easier to
manage
If you don’t know how to do the software yourself, it’s
probably not worth it distributing the work
It takes time
to reach the goals: e.g. cost savings, building up
competencies
It takes more time
Communication delays and overhead
Sharing knowledge and competence
Motivational issues
Communication is the essential key to success!
HELSINKI UNIVERSITY OF TECHNOLOGY
44. SoberIT
Software Business and Engineering Institute
Thank you.