SlideShare uma empresa Scribd logo
1 de 17
Baixar para ler offline
Contractual and Organizational
            Approaches
• The main objective of Project organization
  is to establish the relationship among:
     – the work to be done
     – the people doing the work
     – the work place(s)




Spring            Contractual and Organizational Approaches   1
2008,        Ki              Dr. Khalid Al-Gahtani
Defining the organization:
1. within the firm
     •      involves internal organization of personnel.
2. With other firms:
     •      number of organizations involved
     •      relationship between the organizations
     •      when each organization be involved in the
            project.


Spring 2008,           Contractual and Organizational Approaches   2
King Saud University              Dr. Khalid Al-Gahtani
A Project-Oriented Organization




Spring 2008,           Contractual and Organizational Approaches   3
King Saud University              Dr. Khalid Al-Gahtani
A Matrix Organization




Spring         Contractual and Organizational Approaches   4
2008,     Ki              Dr. Khalid Al-Gahtani
Main participants of a project are:
• the Owner:
     – construction manager
• the Contractor:
     – general and subcontractors,
     – material and equipment supplier
• the designer:
     – consultant and architecture engineering A/E


Spring 2008,           Contractual and Organizational Approaches   5
King Saud University              Dr. Khalid Al-Gahtani
Organizational Types
• Four principal structures of contractual
  relationship between the project
  participants:
     1.Traditional
     2.Owner-Builder
     3.Turnkey
     4.Professional Construction Manager


Spring           Contractual and Organizational Approaches   6
2008,       Ki              Dr. Khalid Al-Gahtani
Spring        Contractual and Organizational Approaches   7
2008,    Ki              Dr. Khalid Al-Gahtani
1. Traditional
• Advantages:
     1.Widely accepted and historically supported.
     2.Using lump-sum the overall cost can be
       determined before awarding the contract.
     3.Minimal involvement of the owner during
       construction.
     4.Design-construct time can be reduced using
       phased construction.


Spring 2008,           Contractual and Organizational Approaches   8
King Saud University              Dr. Khalid Al-Gahtani
1. Traditional
• Disadvantages:
     1.Design may not benefit from construction
       expertise.
     2.Overall design-construct time is usually the
       longest.
     3.The owner and the designer are usually in an
       adversary position with general contractor
       (maximum vs. minimum quality).
     4.Change orders will often end in disputes and
       may drive-up costs.
Spring 2008,           Contractual and Organizational Approaches   9
King Saud University              Dr. Khalid Al-Gahtani
Spring        Contractual and Organizational Approaches   10
2008,    Ki              Dr. Khalid Al-Gahtani
2. The Owner-Builder.
• Advantages:
     1. Justified when the volume of work is
        relatively large and relatively constant over a
        period of time.
     2. Justified where the project management can
        be separated from operational management.
     3. The owner-builder can employ all techniques
        of the design-constructor, the professional
        construction manager, and the traditional
        approach.

Spring            Contractual and Organizational Approaches   11
2008,        Ki              Dr. Khalid Al-Gahtani
Spring 2008,           Contractual and Organizational Approaches   12
King Saud University              Dr. Khalid Al-Gahtani
3. Turnkey
•     Advantages:
     1. Only one contract for the owner. Design,
        construction, and know-how are furnished by a
        single organization.
     2. Minimal owner coordination -dealing with a single
        organization.
     3. Appropriate for unknowledgeable owner.
     4. Design-construct time can be reduced through using
        phased construction.
     5. Construction expertise can be utilized during design
        phased construction.
     6. Change orders are easy to handle.

Spring 2008,           Contractual and Organizational Approaches   13
King Saud University              Dr. Khalid Al-Gahtani
3. Turnkey
• Disadvantages
     1.Usually cost cannot be determined before
       construction.
     2.If the project cost is fixed price, the overall
       quality and performance may be affected to
       ensure profit.
     3.The owner may not be informed if there is a
       design or construction problems that may
       affect the schedule or the cost.

Spring            Contractual and Organizational Approaches   14
2008,        Ki              Dr. Khalid Al-Gahtani
Spring        Contractual and Organizational Approaches   15
2008,    Ki              Dr. Khalid Al-Gahtani
4. Professional Construction Manager
• Advantages:
     1. Special construction skills may be utilized at all
        stages of the project with no conflicts of interest
        between the owner and the designer.
     2. Independent evaluation of costs, schedules, and
        overall construction performance, including similar
        evaluation for changes or modifications helps assure
        decisions in the best interest of the owner.
     3. Full-time coordination between design and the
        construction contractors is available.


Spring 2008,           Contractual and Organizational Approaches   16
King Saud University              Dr. Khalid Al-Gahtani
4. Professional Construction Manager
•     Advantages (Continue) :
     4. Minimum design-construction time can be achieved
        through use of phased construction.
     5. The professional construction manager approach
        allows price competition from local contractors akin
        to the traditional lump-sum or unit-price methods.
     6. Significant opportunities are provided for value
        engineering in the design, bidding, and award
        phases.



Spring 2008,           Contractual and Organizational Approaches   17
King Saud University              Dr. Khalid Al-Gahtani

Mais conteúdo relacionado

Mais procurados

Pmi la sponsorship
Pmi la sponsorshipPmi la sponsorship
Pmi la sponsorshipjbowdoin
 
Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficultiesNahid0521
 
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...Lviv Startup Club
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of constructionSANJEEV Wazir
 

Mais procurados (6)

Pmi la sponsorship
Pmi la sponsorshipPmi la sponsorship
Pmi la sponsorship
 
Pm chapter 7
Pm chapter 7Pm chapter 7
Pm chapter 7
 
Construction difficulties
Construction difficultiesConstruction difficulties
Construction difficulties
 
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...
Кшиштоф Малус “Communication and collaboration aspects in Agile Project Manag...
 
Unit 1 basics of construction
Unit 1 basics of constructionUnit 1 basics of construction
Unit 1 basics of construction
 
Complex project management
Complex project managementComplex project management
Complex project management
 

Destaque

Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentationTimun Loh
 
Automotive Use Cases for LTE-based V2X Study Item
Automotive Use Cases for LTE-based V2X Study ItemAutomotive Use Cases for LTE-based V2X Study Item
Automotive Use Cases for LTE-based V2X Study ItemYi-Hsueh Tsai
 
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyond
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyondCommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyond
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyondAntonio Capone
 
Limiting Risk in Construction Project Contractual Arrangements
Limiting Risk in Construction Project Contractual ArrangementsLimiting Risk in Construction Project Contractual Arrangements
Limiting Risk in Construction Project Contractual ArrangementsBradford Jacob (Virginia)
 
Contracting and subcontracting
Contracting and subcontractingContracting and subcontracting
Contracting and subcontractingRoi Xcel
 
Client consultant relationship
Client consultant relationshipClient consultant relationship
Client consultant relationshipsnehag227
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projectsCraig Brown
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational StructureMary Ann Adiong
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedSlideShare
 

Destaque (20)

Professional practice-1-presentation
Professional practice-1-presentationProfessional practice-1-presentation
Professional practice-1-presentation
 
DESIGN & BUILD
DESIGN & BUILDDESIGN & BUILD
DESIGN & BUILD
 
Project Delivery Method Selection Tool
Project Delivery Method Selection ToolProject Delivery Method Selection Tool
Project Delivery Method Selection Tool
 
Lte By Aziz
Lte By AzizLte By Aziz
Lte By Aziz
 
Automotive Use Cases for LTE-based V2X Study Item
Automotive Use Cases for LTE-based V2X Study ItemAutomotive Use Cases for LTE-based V2X Study Item
Automotive Use Cases for LTE-based V2X Study Item
 
Planning for a Connected and Autonomous Future
Planning for a Connected and Autonomous FuturePlanning for a Connected and Autonomous Future
Planning for a Connected and Autonomous Future
 
Evoluton to LTE an overview June 2010
Evoluton to LTE an overview June 2010Evoluton to LTE an overview June 2010
Evoluton to LTE an overview June 2010
 
Session b3. jen duthie data
Session b3. jen duthie dataSession b3. jen duthie data
Session b3. jen duthie data
 
Data Analytics: Challenges and the Internet of Moving Things
Data Analytics: Challenges and the Internet of Moving ThingsData Analytics: Challenges and the Internet of Moving Things
Data Analytics: Challenges and the Internet of Moving Things
 
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyond
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyondCommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyond
CommTech Talks: Vehicle-to-Vehicle Communications in LTE and beyond
 
V2X, V2I, and the Cellular Infrastructure
V2X, V2I, and the Cellular InfrastructureV2X, V2I, and the Cellular Infrastructure
V2X, V2I, and the Cellular Infrastructure
 
Limiting Risk in Construction Project Contractual Arrangements
Limiting Risk in Construction Project Contractual ArrangementsLimiting Risk in Construction Project Contractual Arrangements
Limiting Risk in Construction Project Contractual Arrangements
 
Connected and Automated Vehicles (CAVs): Implications for Travel and Infrastr...
Connected and Automated Vehicles (CAVs): Implications for Travel and Infrastr...Connected and Automated Vehicles (CAVs): Implications for Travel and Infrastr...
Connected and Automated Vehicles (CAVs): Implications for Travel and Infrastr...
 
Connected and Autonomous Vehicles: The Enabling Technologies
Connected and Autonomous Vehicles: The Enabling TechnologiesConnected and Autonomous Vehicles: The Enabling Technologies
Connected and Autonomous Vehicles: The Enabling Technologies
 
Contracting and subcontracting
Contracting and subcontractingContracting and subcontracting
Contracting and subcontracting
 
Client consultant relationship
Client consultant relationshipClient consultant relationship
Client consultant relationship
 
The Project Management Process - Week 10 Global Issues in IT projects
The Project Management Process - Week 10   Global Issues in IT projectsThe Project Management Process - Week 10   Global Issues in IT projects
The Project Management Process - Week 10 Global Issues in IT projects
 
Assimilating Self-Driving Cars Into Society: Travel Impacts & Transport Polic...
Assimilating Self-Driving Cars Into Society: Travel Impacts & Transport Polic...Assimilating Self-Driving Cars Into Society: Travel Impacts & Transport Polic...
Assimilating Self-Driving Cars Into Society: Travel Impacts & Transport Polic...
 
Organizational Structure
Organizational StructureOrganizational Structure
Organizational Structure
 
LinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-PresentedLinkedIn SlideShare: Knowledge, Well-Presented
LinkedIn SlideShare: Knowledge, Well-Presented
 

Semelhante a Organization

PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.lucaschinsheng
 
Topic 1 project management dcc40132 politeknik
Topic 1 project management dcc40132 politeknikTopic 1 project management dcc40132 politeknik
Topic 1 project management dcc40132 politeknikpqzjhty78j
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessIRJET Journal
 
Project initiation topic 2.2_project charters
Project initiation topic 2.2_project chartersProject initiation topic 2.2_project charters
Project initiation topic 2.2_project chartersRudreshSamant
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTSAJJAD KHUDHUR ABBAS
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Gregoire Lesecq
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides Pang Khai Shuen
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryMECandPMV
 
MPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification AMPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification ADebelaTekabe
 
Integrated project delivery case studies
Integrated project delivery   case studiesIntegrated project delivery   case studies
Integrated project delivery case studiesrosaangelicaportalat1
 
Chapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxChapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxteshome eshetu
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptxAlkaPandya5
 

Semelhante a Organization (20)

PP1 presentation slide.
PP1 presentation slide.PP1 presentation slide.
PP1 presentation slide.
 
Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)Time cost trade off with primavera (real case)
Time cost trade off with primavera (real case)
 
Topic 1 project management dcc40132 politeknik
Topic 1 project management dcc40132 politeknikTopic 1 project management dcc40132 politeknik
Topic 1 project management dcc40132 politeknik
 
Introduction risk management
Introduction risk managementIntroduction risk management
Introduction risk management
 
The Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project SuccessThe Impact of Project Management Practices on Project Success
The Impact of Project Management Practices on Project Success
 
Project initiation topic 2.2_project charters
Project initiation topic 2.2_project chartersProject initiation topic 2.2_project charters
Project initiation topic 2.2_project charters
 
Episode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXTEpisode 20 :PROJECT MANAGEMENT CONTEXT
Episode 20 :PROJECT MANAGEMENT CONTEXT
 
Project management for the supply management professional rev. 5 13-13
Project management for the supply management professional rev. 5 13-13Project management for the supply management professional rev. 5 13-13
Project management for the supply management professional rev. 5 13-13
 
Master's project viva zam
Master's project viva   zamMaster's project viva   zam
Master's project viva zam
 
Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016Project management in practice - world cement magazine nov 2016
Project management in practice - world cement magazine nov 2016
 
Project governance
Project governanceProject governance
Project governance
 
PP1 - Presentation Slides
PP1 - Presentation Slides PP1 - Presentation Slides
PP1 - Presentation Slides
 
Project managment
Project managmentProject managment
Project managment
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
PROJECT MANAGEMENT
PROJECT MANAGEMENTPROJECT MANAGEMENT
PROJECT MANAGEMENT
 
MPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification AMPM621Ch12.pptx project identification A
MPM621Ch12.pptx project identification A
 
Project Management
Project ManagementProject Management
Project Management
 
Integrated project delivery case studies
Integrated project delivery   case studiesIntegrated project delivery   case studies
Integrated project delivery case studies
 
Chapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptxChapter 1-Project and Construction project.pptx
Chapter 1-Project and Construction project.pptx
 
Project Management.pptx
Project Management.pptxProject Management.pptx
Project Management.pptx
 

Mais de Tu Nguyen, PMP®,PMI-RMP®

Mais de Tu Nguyen, PMP®,PMI-RMP® (20)

4.contracting
4.contracting4.contracting
4.contracting
 
3.estimating
3.estimating3.estimating
3.estimating
 
2.tendering
2.tendering2.tendering
2.tendering
 
1.introduction
1.introduction1.introduction
1.introduction
 
Session 8 gdas pmp study group presentation
Session 8   gdas pmp study group presentationSession 8   gdas pmp study group presentation
Session 8 gdas pmp study group presentation
 
Session 7 gdas pmp study group presentation
Session 7   gdas pmp study group presentationSession 7   gdas pmp study group presentation
Session 7 gdas pmp study group presentation
 
Session 6 gdas pmp study group presentation
Session 6   gdas pmp study group presentationSession 6   gdas pmp study group presentation
Session 6 gdas pmp study group presentation
 
Session 5 gdas pmp study group presentation
Session 5   gdas pmp study group presentationSession 5   gdas pmp study group presentation
Session 5 gdas pmp study group presentation
 
Session 4 gdas pmp study group presentation
Session 4   gdas pmp study group presentationSession 4   gdas pmp study group presentation
Session 4 gdas pmp study group presentation
 
Session 10 gdas pmp study group presentation
Session 10   gdas pmp study group presentationSession 10   gdas pmp study group presentation
Session 10 gdas pmp study group presentation
 
Session 3 gdas pmp study group presentation
Session 3   gdas pmp study group presentationSession 3   gdas pmp study group presentation
Session 3 gdas pmp study group presentation
 
Session 2 gdas pmp study group presentation
Session 2   gdas pmp study group presentationSession 2   gdas pmp study group presentation
Session 2 gdas pmp study group presentation
 
Node
NodeNode
Node
 
Contract
ContractContract
Contract
 
Cash flow
Cash flowCash flow
Cash flow
 
Bar chart
Bar chartBar chart
Bar chart
 
Arrow computation
Arrow computationArrow computation
Arrow computation
 
Arrow
ArrowArrow
Arrow
 
Administration
AdministrationAdministration
Administration
 
Time cost-trade-off
Time cost-trade-offTime cost-trade-off
Time cost-trade-off
 

Organization

  • 1. Contractual and Organizational Approaches • The main objective of Project organization is to establish the relationship among: – the work to be done – the people doing the work – the work place(s) Spring Contractual and Organizational Approaches 1 2008, Ki Dr. Khalid Al-Gahtani
  • 2. Defining the organization: 1. within the firm • involves internal organization of personnel. 2. With other firms: • number of organizations involved • relationship between the organizations • when each organization be involved in the project. Spring 2008, Contractual and Organizational Approaches 2 King Saud University Dr. Khalid Al-Gahtani
  • 3. A Project-Oriented Organization Spring 2008, Contractual and Organizational Approaches 3 King Saud University Dr. Khalid Al-Gahtani
  • 4. A Matrix Organization Spring Contractual and Organizational Approaches 4 2008, Ki Dr. Khalid Al-Gahtani
  • 5. Main participants of a project are: • the Owner: – construction manager • the Contractor: – general and subcontractors, – material and equipment supplier • the designer: – consultant and architecture engineering A/E Spring 2008, Contractual and Organizational Approaches 5 King Saud University Dr. Khalid Al-Gahtani
  • 6. Organizational Types • Four principal structures of contractual relationship between the project participants: 1.Traditional 2.Owner-Builder 3.Turnkey 4.Professional Construction Manager Spring Contractual and Organizational Approaches 6 2008, Ki Dr. Khalid Al-Gahtani
  • 7. Spring Contractual and Organizational Approaches 7 2008, Ki Dr. Khalid Al-Gahtani
  • 8. 1. Traditional • Advantages: 1.Widely accepted and historically supported. 2.Using lump-sum the overall cost can be determined before awarding the contract. 3.Minimal involvement of the owner during construction. 4.Design-construct time can be reduced using phased construction. Spring 2008, Contractual and Organizational Approaches 8 King Saud University Dr. Khalid Al-Gahtani
  • 9. 1. Traditional • Disadvantages: 1.Design may not benefit from construction expertise. 2.Overall design-construct time is usually the longest. 3.The owner and the designer are usually in an adversary position with general contractor (maximum vs. minimum quality). 4.Change orders will often end in disputes and may drive-up costs. Spring 2008, Contractual and Organizational Approaches 9 King Saud University Dr. Khalid Al-Gahtani
  • 10. Spring Contractual and Organizational Approaches 10 2008, Ki Dr. Khalid Al-Gahtani
  • 11. 2. The Owner-Builder. • Advantages: 1. Justified when the volume of work is relatively large and relatively constant over a period of time. 2. Justified where the project management can be separated from operational management. 3. The owner-builder can employ all techniques of the design-constructor, the professional construction manager, and the traditional approach. Spring Contractual and Organizational Approaches 11 2008, Ki Dr. Khalid Al-Gahtani
  • 12. Spring 2008, Contractual and Organizational Approaches 12 King Saud University Dr. Khalid Al-Gahtani
  • 13. 3. Turnkey • Advantages: 1. Only one contract for the owner. Design, construction, and know-how are furnished by a single organization. 2. Minimal owner coordination -dealing with a single organization. 3. Appropriate for unknowledgeable owner. 4. Design-construct time can be reduced through using phased construction. 5. Construction expertise can be utilized during design phased construction. 6. Change orders are easy to handle. Spring 2008, Contractual and Organizational Approaches 13 King Saud University Dr. Khalid Al-Gahtani
  • 14. 3. Turnkey • Disadvantages 1.Usually cost cannot be determined before construction. 2.If the project cost is fixed price, the overall quality and performance may be affected to ensure profit. 3.The owner may not be informed if there is a design or construction problems that may affect the schedule or the cost. Spring Contractual and Organizational Approaches 14 2008, Ki Dr. Khalid Al-Gahtani
  • 15. Spring Contractual and Organizational Approaches 15 2008, Ki Dr. Khalid Al-Gahtani
  • 16. 4. Professional Construction Manager • Advantages: 1. Special construction skills may be utilized at all stages of the project with no conflicts of interest between the owner and the designer. 2. Independent evaluation of costs, schedules, and overall construction performance, including similar evaluation for changes or modifications helps assure decisions in the best interest of the owner. 3. Full-time coordination between design and the construction contractors is available. Spring 2008, Contractual and Organizational Approaches 16 King Saud University Dr. Khalid Al-Gahtani
  • 17. 4. Professional Construction Manager • Advantages (Continue) : 4. Minimum design-construction time can be achieved through use of phased construction. 5. The professional construction manager approach allows price competition from local contractors akin to the traditional lump-sum or unit-price methods. 6. Significant opportunities are provided for value engineering in the design, bidding, and award phases. Spring 2008, Contractual and Organizational Approaches 17 King Saud University Dr. Khalid Al-Gahtani