E4014 Construction Surveying
Dam Construction
Objectives
On completion of the module you should be
capable of:
• describing the various types of dam
construction
• describing the provision of spillways and river
diversions
• planning detail surveys for damsite design
• planning dam wall monitoring surveys
• reading and understanding the plans and
drawings associated with dam construction
Introduction
The material covered in this lecture is specific
to dam construction.
It is assumed that the concept of control and
detail surveys is already known by the student
Dams
Dams are constructed for one or more of the
following purposes:
• Storage of water for urban supply
• storage of water for farm irrigation
• flood mitigation
Dams
• A watertight seal placed in a river in order to
create a lake or reservoir by impounding the
stream flow
• Must be stable under all loading conditions
• must resist
– hydrostatic pressures on its upstream face
– destructive influences of water perculation and
possible uplift due to it
Investigation for Dams
Factors to be considered include:
• Geological conditions
– effect the location and construction of the
foundations, abutments, dam itself, and spillways
• long and short term stream flow
• rainfall and storage reservoir characteristics of the
proposed dam catchment
• access road
Investigation for Dams
Factors to be considered continued:
• local availability of earth and rock materials
and their suitability for dam construction
– or as concrete aggregates
• degree of permeability of the rock formation
on which the dam is to be placed
– may affect hydrostatic uplift pressures and the
degree of grouting necessary to control it
Investigation for Dams
Factors to be considered continued:
• planning for river diversion to occur while the
dam is being constructed
– cutting a temporary channel which by-passes the
dam itself
– installation of large pipes under the dam
Investigation for Dams
Factors to be considered continued:
• provision of sites for:
– water intake structures and pumping stations for
water supply dam
– Penstocks ( inlet tower )
– power station in the case of hydro-electric
facilities
Investigation for Dams
Factors to be considered continued:
• an Environmental Impact Study
– short and long term effects of of the proposed
reservoir and the construction operations on the
region
– aesthetics, plant and animal, ecology, fish
preservation and public amenity of the reservoir
and downstream reaches
– noise and dust hazards in construction
– effects of the dam on the regional micro-climate
Types of Dams
Dams are classified by the materials of which
they are constructed:
• earth
• earth and rock
• rock
• concrete
Types of Dams
The first three can be subgrouped as
embankment dams whilst there are also
several different types of concrete dams:
• Embankment
– earth - earth and rock
– rock
• concrete
– solid gravity - concrete arch
– arch-gravity - hollow gravity
– prestressed concrete
Embankment Dams
One constructed of naturally excavated
materials
• Two sub groups
– earthfill
– rockfill
Embankment Dams - Earthfill
Dam composed
entirely of
soils
Thomson Dam, a 166 metre high earthfill and
rockfill dam
Embankment Dams - Earthfill
• Fine grained impervious material
• only moderate stability, necessitating flat
side-slopes
• protect slopes from erosion by layers of
rock rip-rap
Embankment Dams - Earthfill
• Symmetrical zoned material
• somewhat steeper slopes
• most common type
Embankment Dams - Earthfill
• Hybrid of types A and B
• large upstream impervious section
• transition zone
• downstream pervious zone
• may be used when rapid reservoir draw
Embankment Dams - Earthfill
Process of dam construction:
• All vegetable matter and organic material is cleared
from the dam site
• grout holes for the cut-off curtain are drilled to a
depth where the grout curtain will effectively seal
off the seepage of water beneath the proposed dam
Embankment Dams - Earthfill
Process of dam construction:
• The holes are filled with cement-water at
sufficient pressure to force it into rock fissures
beneath the dam foundation
Embankment Dams - Earthfill
Process of dam construction:
• When placing the embankment layers of soil
should be kept horizontal, but graded slightly
from the centre to the sides
• layers should be approx
– 150mm after compaction for impervious core
– 225mm for outer pervious zones
Embankment Dams - Earthfill
Process of dam construction:
• Protection of the embankment from
upstream wave action
– stone rip rap commonly used
• prevention of erosion on dry downstream
side
– grass, stone or concrete
• No earth dam should be overtopped from the reservoir,
spillways are provided to discharge excess water from the
reservoir
Embankment Dams - Earthfill
Crotty Dam, an 82 metre high concrete-faced
rockfill structure.
Embankment Dams -
Embankment
between the clay core and the rock fill both upstream and downstream of
the core. In foreground drilling rigs are being used to drill grout holes
in the conglomerate, sandstone and shale foundation. Grouting is used
to fill open cracks in the foundation rock so water cannot leak out of
the dam and is carried out by pumping grout (a mixture of cement and
water) under pressure into holes drilled in the foundation rock.
Windamere Dam under construction,
a 69m high, Earth and Rock Fill Dam
Brown clay core in centre of photo with light
grey andesite rock fill both upstream (left)
and downstream (right) of clay core. Note
the narrow zones of dark brown filter
material
Embankment Dams - Embankment
or Concrete
Provided suitable materials are available
embankment dams often offer a more
economical alternative to concrete
structures
The inability of the abutment materials to take the
thrust from a concrete dam may dictate the
construction of an embankment dam
however many sites are suited to concrete dams
Concrete Dams - Types
Types of concrete dams include:
– solid gravity
– concrete arch
– arch-gravity
– hollow gravity
– prestressed concrete
Concrete Dams - Solid Gravity
Straight or curved relying on its weight for
stability
• Concrete using large aggregate ( 150mm to
225mm maximum size )
• dam is made up of individual vertical blocks
with construction joints
– later grouted to prevent leakage
Concrete Dams - Solid Gravity
Warragamba Dam, 142 metre high concrete
gravity dam
Concrete Dams - Buttress
Sloping concrete slab
supported on a
number of buttresses
• Massive buttress occurs when the
buttresses touch
Concrete Dams - Arch
Upstream curvature
transmitting the
majority of its load
onto the abutments
• Base thickness < 60% of its height
• where base thickness > 60% of its height, the dam is
essentially a curved gravity dam
• suited to deep, narrow gorges of strong abutment
material
• constructed in blocks- appropriate shrinkage gaps
and construction joints
Concrete Dams - Arch
• Gordon Dam in Tasmania is a 140 metre
high concrete arch dam
Concrete Dams - Arch Gravity
Combination of gravity and arch dams
curved gravity dams
Concrete Dams - Hollow Gravity
Rely upon their weight for stability
for watertightness, an impervious reinforced
concrete membrane supported by
buttresses securely keyed into sound rock
• Include
– slab and buttress, with inclined membrane
– massive buttress, touching buttresses
– conoidal, with a plane upstream face and identical
massive buttresses
– multiple-arch, membrane is a series of arches as
distinct from a slab
Concrete Dams - Prestressed
Downstream curvature
dam subjected to compressive forces before
filling
after filling, tensile stresses resulting in the
dam are counteracted by the already
existing compressive forces
River Diversion
Before the dam can be constructed, diversion
of the river is necessary
Satisfactory handling of the stream flow during
construction is vital to the success of the work
cost of river diversion must be compared with the risk
of all or parts of the new dam in peak flood
conditions
types of diversion
tunnel, flume, concrete or steel pipeline and open channel
River Diversion
Building a
diversion
tunnel
Cofferdams act
as barriers to
the river
Construction of the dam
and power station
Closure of the
diversion tunnel
Spillways
• When dams are designed provision needs to be
made to cope with large floods. Spillways are built
to provide a path for floodwater to flow over or
around the dam
• Spillways on concrete dams are usually
constructed to allow water to flow over the
top.
• Spillways associated with embankment dams
are built to take the water around the side of
the dam and away from the downstream face.
Spillways
• Overflow Spillway
– overflows a special section of the dam itself
• Byewash Spillway
– separate open flood channel cut through a nearby
saddle and with a small weir at the upstream end
• Side-Inlet Spillway
– located on the steep side of the gorge
– direction of flow is parallel to the crest of the river
• Drop-Inlet Spillway
– water enters via a horizontal lip, drops through a vertical
or sloping shaft and discharges through a horizontal or
gently sloping culvert
Spillways
• Overflow Spillways
• Glennies Creek Dam spillway
Spillway Gates
• Allow control over the level of fill of the reservoir
• Used for three reasons:
– to reduce the cost of the dam
– to reduce the inundation of land in the reservoir area
– to reduce the downstream flood damage
• Three types
– sliding gates - shutters running grooves
– roller gates - employ rollers on the shutters
– radial gates - form an arc pivoting on a trunion bearing
Outlet
• Necessary to make provision for the discharge of
water as and when it is required for irrigation etc.
• Separate outlet required
– commonly a pipe passing under or through the
dam, with discharge controlled by valves
Damsite Surveys
• Study of existing topographic maps and aerial
photographs will indicate possible dam sites.
• An estimate of catchment area and storage
capacity can also be made
• Surveys required
– contour survey
– watershed traverse
– stability of site
– cadastral surveys
Dam Site Surveys -
Contour Survey
• Following selection of a possible site an aerial
survey should be undertaken to provide a more
detailed contour of the storage area
• Typical scale, 1 : 10000 with a 2m contour interval
• Allows more accurate computation of storage
capacity
• if the site is feasible, the survey provides a more
concise design location of the dam wall
• marks placed during the control survey for photo
control also provides control for all future surveys
Dam Site Surveys -
Watershed Traverse
• Where insufficient information exists to
accurately determine the catchment area, it may
be necessary to carry out a watershed traverse
Dam Site Surveys -
Stability of Site
• Dam must be positioned where it will be stable and
where the storage area does not have excessive
underground leakage
• Soil and rock features must be carefully examined
• Large dams require test pits, bore holes and detailed
geological survey
• small dams may require only test holes to determine
sub-surface features
• the position of each investigation must be accurately
located
Dam Site Surveys -
Cadastral Surveys
• Land to be inundated is resumed by the
constructing authority
• Cadastral surveys required to delineate the land to be resumed
• Surveys will also be required to close roads
passing through inundated land
Surveys in Dam Wall Area
• General location of dam wall has been decided
from earlier surveys
• Further surveys are required within this area to aid final design and computation of volumes of excavation and fill
- detail surveys
- definition of dam wall on plan
- location of limits of dam on ground
- by-wash
- clearing of site
- pipeline surveys
- road access
- pumping stations
Surveys in Dam Wall Area -
Detail Surveys
• More intense geological and soil surveys are
carried out
– ensure absence of geological faults
– determine required depth of stripping
• Detail and contour survey locating all topographic features, test-bores
etc.
– total stations or GPS
– scale 1 : 1000, contour interval 1m
Surveys in Dam Wall Area -
Definition of Dam Wall on Plan
• Following consideration of all factors, it is now
possible to to define the centreline of the dam wall
on the contour plan
– also, working to specified batters, the extent of the
earthworks can be plotted on the contour plan
Surveys in Dam Wall Area -
Definition of Dam Wall on Plan
• Crest RL 550m
• 5m wide pavement on top
• batters 2:1
Surveys in Dam Wall Area -
Locate Dam Limits on Ground
• Stability of dam is dependent on
– foundations,
– materials used, and
– method of construction
• Foundations
– remove all unsuitable material or unstable
material from within the limits of the dam wall
• Requires definition of the limits of the wall marked on the ground
– toe of batters require pegging
Surveys in Dam Wall Area -
Grout Curtains
• Grout is pumped down drill holes bored along the
centreline and on either side of it
• Centreline must be marked before actual construction
commences
Surveys in Dam Wall Area -
By-Wash
• The downstream face of an embankment dam will
scour if water flows over the dam crest
• an outlet or by-wash channel is necessary to allow
excess water to flow around the dam wall to be
discharged away from the dam wall
– large dams normally have a large concrete channel
• The horizontal and vertical position of the by-wash must
be defined on the ground
Surveys in Dam Area -
Clearing of Site
• Usual to clear the dam storage area of vegitation
and tree cover prior to filling of the dam
• Requires definition of the limits of the dam storage area marked on the ground
– running the contour equal to full storage level
Surveys in Dam Area -
Additional Surveys
• Pipeline alignment and sections from dam to
consumer
• pipeline easement surveys
• access roads to dam site, and
• surveys for siting and constructing pumping
stations
Surveys in Dam Area -
Stability of Dam Wall
• Monitoring surveys
– to determine if any horizontal or vertical movement
occurs after construction and in later years
– unusual movement may indicate dam failure
• Fix permanent marks along the crest of the dam
wall and over the downstream face
• regular control surveys required
– must be able to identify small movement of say
3mm in horizontal or vertical
Small Dams
• Contour survey of pondage area is undertaken by
ground survey rather than aerial survey
• only test bore-holes are used to determine sub
surface features with respect to site stability
investigations
• by-wash need only be a grass channel
Proposed Earth Dam, General Arrangement
and Detail (Sheet 1 of 6)
• Plan of Works Area
– dam centreline
– by-wash
– Drop Inlet
• Longitudinal Section
• Embankment - Type Section
• Storage Capacity Diagram
Proposed Earth Dam, General Arrangement
and Detail (Sheet 1 of 6) - Plan of Works Area
Proposed Earth Dam, Plan of Storage Area
(Sheet 2 of 6)
• Control Traverse
• horizontal control
– datum, permanent marks
• vertical control
– datum, bench marks
• full storage level
• test holes, test Pit Logs
Proposed Earth Dam, Standard 600 * 100
Drop Inlet (Sheet 5 of 6)
• Typical Abutment Plan and elevation
• By-Wash Location Plan
Proposed Earth Dam, Setting Out Survey
(Sheet 6 of 6)
• Assist with setting out batter points

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Dams 1
Dams 1Dams 1
Dams 1
 
DAM ENGINEERING
DAM ENGINEERINGDAM ENGINEERING
DAM ENGINEERING
 
Reservoir Dam Safety
Reservoir Dam SafetyReservoir Dam Safety
Reservoir Dam Safety
 
Final
FinalFinal
Final
 
Dam - Classification based on structure
Dam - Classification based on structureDam - Classification based on structure
Dam - Classification based on structure
 
Dams and reservoirs by Deepansh Jain
Dams and reservoirs  by Deepansh JainDams and reservoirs  by Deepansh Jain
Dams and reservoirs by Deepansh Jain
 
Dam and types of dam with site selection
Dam and types of dam with site selectionDam and types of dam with site selection
Dam and types of dam with site selection
 
Ranjith bsr
Ranjith bsrRanjith bsr
Ranjith bsr
 
Dams pdf
Dams pdfDams pdf
Dams pdf
 
Dams
DamsDams
Dams
 
project on dam and dam safety with application of geophysics
project on dam and dam safety with application of geophysicsproject on dam and dam safety with application of geophysics
project on dam and dam safety with application of geophysics
 
Dam
DamDam
Dam
 
Dam safety
Dam safetyDam safety
Dam safety
 
Dam presentation
Dam presentationDam presentation
Dam presentation
 
Dam
DamDam
Dam
 
Dams
DamsDams
Dams
 
Dam design
Dam designDam design
Dam design
 
DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .DAMS AND IT'S TYPES . . .
DAMS AND IT'S TYPES . . .
 
Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01Dams by Luke Camilleri, 3.01
Dams by Luke Camilleri, 3.01
 
Dams & its Construction
Dams & its ConstructionDams & its Construction
Dams & its Construction
 

Semelhante a Damconstruction 1

26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
RijuDasgupta
 
Power plant engineering unit-iii.pptx
Power plant engineering unit-iii.pptxPower plant engineering unit-iii.pptx
Power plant engineering unit-iii.pptx
SyedMujeeb22
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
abhijitsaha99
 

Semelhante a Damconstruction 1 (20)

Dams
DamsDams
Dams
 
Dams.pptx
Dams.pptxDams.pptx
Dams.pptx
 
Dams PPT
Dams PPTDams PPT
Dams PPT
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
26901321007_SAPTADEEP DASGUPTA_CE(PE)701C.pdf
 
Design of Hydraulic Structures
Design of Hydraulic StructuresDesign of Hydraulic Structures
Design of Hydraulic Structures
 
Dams.ppt
Dams.pptDams.ppt
Dams.ppt
 
Cross drainage work
Cross drainage workCross drainage work
Cross drainage work
 
Bridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptxBridge and Railway Engineering.pptx
Bridge and Railway Engineering.pptx
 
damandtypesofdamwithsiteselection-170403160723.pdf
damandtypesofdamwithsiteselection-170403160723.pdfdamandtypesofdamwithsiteselection-170403160723.pdf
damandtypesofdamwithsiteselection-170403160723.pdf
 
New geology of dams & reservoir unit v
New geology of dams & reservoir unit vNew geology of dams & reservoir unit v
New geology of dams & reservoir unit v
 
Power plant engineering unit-iii.pptx
Power plant engineering unit-iii.pptxPower plant engineering unit-iii.pptx
Power plant engineering unit-iii.pptx
 
Cofferdams
Cofferdams Cofferdams
Cofferdams
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptxdamandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
damandtypesofdamwithsiteselection-170403160723 (1) (1).pptx
 
Storage head works
Storage head worksStorage head works
Storage head works
 
WRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity damsWRE II construction of galleries in gravity dams
WRE II construction of galleries in gravity dams
 
Dams and Reserviors
Dams and ReserviorsDams and Reserviors
Dams and Reserviors
 
Diversion head work
Diversion head workDiversion head work
Diversion head work
 
Geological Considerations - Dam
Geological Considerations - DamGeological Considerations - Dam
Geological Considerations - Dam
 

Mais de soenarto soendjaja

Mais de soenarto soendjaja (20)

Mengaktifkan analysis tool pak
Mengaktifkan analysis tool pakMengaktifkan analysis tool pak
Mengaktifkan analysis tool pak
 
Analisis data statistiks dengan ms excel
Analisis data statistiks dengan ms excelAnalisis data statistiks dengan ms excel
Analisis data statistiks dengan ms excel
 
Merancang penelitian
Merancang penelitianMerancang penelitian
Merancang penelitian
 
How to-implements-of-iso-6419293
How to-implements-of-iso-6419293How to-implements-of-iso-6419293
How to-implements-of-iso-6419293
 
Hotel management-courses-6647682
Hotel management-courses-6647682Hotel management-courses-6647682
Hotel management-courses-6647682
 
Good thenewiso9001ver00 130909014428-
Good thenewiso9001ver00 130909014428-Good thenewiso9001ver00 130909014428-
Good thenewiso9001ver00 130909014428-
 
G 01 ci_seminarlajan2007williams
G 01 ci_seminarlajan2007williamsG 01 ci_seminarlajan2007williams
G 01 ci_seminarlajan2007williams
 
Ensuringquality
EnsuringqualityEnsuringquality
Ensuringquality
 
Function of-admi-nistration
Function of-admi-nistrationFunction of-admi-nistration
Function of-admi-nistration
 
Good quality translations com...apex translations, inc
Good quality translations com...apex translations, incGood quality translations com...apex translations, inc
Good quality translations com...apex translations, inc
 
Good quality control for cons..
Good quality control for cons..Good quality control for cons..
Good quality control for cons..
 
Good polb qms -jul24,2013
Good polb qms -jul24,2013Good polb qms -jul24,2013
Good polb qms -jul24,2013
 
Good foxlink group, the exper..
Good foxlink group, the exper..Good foxlink group, the exper..
Good foxlink group, the exper..
 
Good difference between softw..
Good difference between softw..Good difference between softw..
Good difference between softw..
 
Good a framework for building quality into construction projects part i
Good a framework for building quality into construction projects   part iGood a framework for building quality into construction projects   part i
Good a framework for building quality into construction projects part i
 
Pengelolaan sda dan tantangannya di era otonomi daerah dan globalisasi ekonom...
Pengelolaan sda dan tantangannya di era otonomi daerah dan globalisasi ekonom...Pengelolaan sda dan tantangannya di era otonomi daerah dan globalisasi ekonom...
Pengelolaan sda dan tantangannya di era otonomi daerah dan globalisasi ekonom...
 
7 aspek di iwrm indonesia
7 aspek di iwrm indonesia7 aspek di iwrm indonesia
7 aspek di iwrm indonesia
 
Sistem jaringan Irigasi
Sistem jaringan IrigasiSistem jaringan Irigasi
Sistem jaringan Irigasi
 
Crafting and Implementing Strategy Plan
Crafting and Implementing Strategy PlanCrafting and Implementing Strategy Plan
Crafting and Implementing Strategy Plan
 
Damsornodams97 121009001230-phpapp01
Damsornodams97 121009001230-phpapp01Damsornodams97 121009001230-phpapp01
Damsornodams97 121009001230-phpapp01
 

Último

Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
amitlee9823
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
dipikadinghjn ( Why You Choose Us? ) Escorts
 
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
dipikadinghjn ( Why You Choose Us? ) Escorts
 

Último (20)

Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbaiVasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
Vasai-Virar Fantastic Call Girls-9833754194-Call Girls MUmbai
 
(INDIRA) Call Girl Srinagar Call Now 8617697112 Srinagar Escorts 24x7
(INDIRA) Call Girl Srinagar Call Now 8617697112 Srinagar Escorts 24x7(INDIRA) Call Girl Srinagar Call Now 8617697112 Srinagar Escorts 24x7
(INDIRA) Call Girl Srinagar Call Now 8617697112 Srinagar Escorts 24x7
 
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
Call Girls Banaswadi Just Call 👗 7737669865 👗 Top Class Call Girl Service Ban...
 
WhatsApp 📞 Call : 9892124323 ✅Call Girls In Chembur ( Mumbai ) secure service
WhatsApp 📞 Call : 9892124323  ✅Call Girls In Chembur ( Mumbai ) secure serviceWhatsApp 📞 Call : 9892124323  ✅Call Girls In Chembur ( Mumbai ) secure service
WhatsApp 📞 Call : 9892124323 ✅Call Girls In Chembur ( Mumbai ) secure service
 
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
VIP Independent Call Girls in Bandra West 🌹 9920725232 ( Call Me ) Mumbai Esc...
 
Mira Road Awesome 100% Independent Call Girls NUmber-9833754194-Dahisar Inter...
Mira Road Awesome 100% Independent Call Girls NUmber-9833754194-Dahisar Inter...Mira Road Awesome 100% Independent Call Girls NUmber-9833754194-Dahisar Inter...
Mira Road Awesome 100% Independent Call Girls NUmber-9833754194-Dahisar Inter...
 
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
VIP Call Girl in Mira Road 💧 9920725232 ( Call Me ) Get A New Crush Everyday ...
 
Top Rated Pune Call Girls Sinhagad Road ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated  Pune Call Girls Sinhagad Road ⟟ 6297143586 ⟟ Call Me For Genuine S...Top Rated  Pune Call Girls Sinhagad Road ⟟ 6297143586 ⟟ Call Me For Genuine S...
Top Rated Pune Call Girls Sinhagad Road ⟟ 6297143586 ⟟ Call Me For Genuine S...
 
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
VIP Independent Call Girls in Mumbai 🌹 9920725232 ( Call Me ) Mumbai Escorts ...
 
Business Principles, Tools, and Techniques in Participating in Various Types...
Business Principles, Tools, and Techniques  in Participating in Various Types...Business Principles, Tools, and Techniques  in Participating in Various Types...
Business Principles, Tools, and Techniques in Participating in Various Types...
 
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
8377087607, Door Step Call Girls In Kalkaji (Locanto) 24/7 Available
 
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
VIP Call Girl Service Andheri West ⚡ 9920725232 What It Takes To Be The Best ...
 
Top Rated Pune Call Girls Dighi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated  Pune Call Girls Dighi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...Top Rated  Pune Call Girls Dighi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
Top Rated Pune Call Girls Dighi ⟟ 6297143586 ⟟ Call Me For Genuine Sex Servi...
 
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
Solution Manual for Financial Accounting, 11th Edition by Robert Libby, Patri...
 
Top Rated Pune Call Girls Pashan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated  Pune Call Girls Pashan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...Top Rated  Pune Call Girls Pashan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
Top Rated Pune Call Girls Pashan ⟟ 6297143586 ⟟ Call Me For Genuine Sex Serv...
 
Top Rated Pune Call Girls Lohegaon ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated  Pune Call Girls Lohegaon ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...Top Rated  Pune Call Girls Lohegaon ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
Top Rated Pune Call Girls Lohegaon ⟟ 6297143586 ⟟ Call Me For Genuine Sex Se...
 
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
Kharghar Blowjob Housewife Call Girls NUmber-9833754194-CBD Belapur Internati...
 
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...Booking open Available Pune Call Girls Talegaon Dabhade  6297143586 Call Hot ...
Booking open Available Pune Call Girls Talegaon Dabhade 6297143586 Call Hot ...
 
Indore Real Estate Market Trends Report.pdf
Indore Real Estate Market Trends Report.pdfIndore Real Estate Market Trends Report.pdf
Indore Real Estate Market Trends Report.pdf
 
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
VIP Call Girl in Mumbai 💧 9920725232 ( Call Me ) Get A New Crush Everyday Wit...
 

Damconstruction 1

  • 2. Objectives On completion of the module you should be capable of: • describing the various types of dam construction • describing the provision of spillways and river diversions • planning detail surveys for damsite design • planning dam wall monitoring surveys • reading and understanding the plans and drawings associated with dam construction
  • 3. Introduction The material covered in this lecture is specific to dam construction. It is assumed that the concept of control and detail surveys is already known by the student
  • 4. Dams Dams are constructed for one or more of the following purposes: • Storage of water for urban supply • storage of water for farm irrigation • flood mitigation
  • 5. Dams • A watertight seal placed in a river in order to create a lake or reservoir by impounding the stream flow • Must be stable under all loading conditions • must resist – hydrostatic pressures on its upstream face – destructive influences of water perculation and possible uplift due to it
  • 6. Investigation for Dams Factors to be considered include: • Geological conditions – effect the location and construction of the foundations, abutments, dam itself, and spillways • long and short term stream flow • rainfall and storage reservoir characteristics of the proposed dam catchment • access road
  • 7. Investigation for Dams Factors to be considered continued: • local availability of earth and rock materials and their suitability for dam construction – or as concrete aggregates • degree of permeability of the rock formation on which the dam is to be placed – may affect hydrostatic uplift pressures and the degree of grouting necessary to control it
  • 8. Investigation for Dams Factors to be considered continued: • planning for river diversion to occur while the dam is being constructed – cutting a temporary channel which by-passes the dam itself – installation of large pipes under the dam
  • 9. Investigation for Dams Factors to be considered continued: • provision of sites for: – water intake structures and pumping stations for water supply dam – Penstocks ( inlet tower ) – power station in the case of hydro-electric facilities
  • 10. Investigation for Dams Factors to be considered continued: • an Environmental Impact Study – short and long term effects of of the proposed reservoir and the construction operations on the region – aesthetics, plant and animal, ecology, fish preservation and public amenity of the reservoir and downstream reaches – noise and dust hazards in construction – effects of the dam on the regional micro-climate
  • 11. Types of Dams Dams are classified by the materials of which they are constructed: • earth • earth and rock • rock • concrete
  • 12. Types of Dams The first three can be subgrouped as embankment dams whilst there are also several different types of concrete dams: • Embankment – earth - earth and rock – rock • concrete – solid gravity - concrete arch – arch-gravity - hollow gravity – prestressed concrete
  • 13. Embankment Dams One constructed of naturally excavated materials • Two sub groups – earthfill – rockfill
  • 14. Embankment Dams - Earthfill Dam composed entirely of soils Thomson Dam, a 166 metre high earthfill and rockfill dam
  • 15. Embankment Dams - Earthfill • Fine grained impervious material • only moderate stability, necessitating flat side-slopes • protect slopes from erosion by layers of rock rip-rap
  • 16. Embankment Dams - Earthfill • Symmetrical zoned material • somewhat steeper slopes • most common type
  • 17. Embankment Dams - Earthfill • Hybrid of types A and B • large upstream impervious section • transition zone • downstream pervious zone • may be used when rapid reservoir draw
  • 18. Embankment Dams - Earthfill Process of dam construction: • All vegetable matter and organic material is cleared from the dam site • grout holes for the cut-off curtain are drilled to a depth where the grout curtain will effectively seal off the seepage of water beneath the proposed dam
  • 19. Embankment Dams - Earthfill Process of dam construction: • The holes are filled with cement-water at sufficient pressure to force it into rock fissures beneath the dam foundation
  • 20. Embankment Dams - Earthfill Process of dam construction: • When placing the embankment layers of soil should be kept horizontal, but graded slightly from the centre to the sides • layers should be approx – 150mm after compaction for impervious core – 225mm for outer pervious zones
  • 21. Embankment Dams - Earthfill Process of dam construction: • Protection of the embankment from upstream wave action – stone rip rap commonly used • prevention of erosion on dry downstream side – grass, stone or concrete • No earth dam should be overtopped from the reservoir, spillways are provided to discharge excess water from the reservoir
  • 22. Embankment Dams - Earthfill Crotty Dam, an 82 metre high concrete-faced rockfill structure.
  • 23. Embankment Dams - Embankment between the clay core and the rock fill both upstream and downstream of the core. In foreground drilling rigs are being used to drill grout holes in the conglomerate, sandstone and shale foundation. Grouting is used to fill open cracks in the foundation rock so water cannot leak out of the dam and is carried out by pumping grout (a mixture of cement and water) under pressure into holes drilled in the foundation rock. Windamere Dam under construction, a 69m high, Earth and Rock Fill Dam Brown clay core in centre of photo with light grey andesite rock fill both upstream (left) and downstream (right) of clay core. Note the narrow zones of dark brown filter material
  • 24. Embankment Dams - Embankment or Concrete Provided suitable materials are available embankment dams often offer a more economical alternative to concrete structures The inability of the abutment materials to take the thrust from a concrete dam may dictate the construction of an embankment dam however many sites are suited to concrete dams
  • 25. Concrete Dams - Types Types of concrete dams include: – solid gravity – concrete arch – arch-gravity – hollow gravity – prestressed concrete
  • 26. Concrete Dams - Solid Gravity Straight or curved relying on its weight for stability • Concrete using large aggregate ( 150mm to 225mm maximum size ) • dam is made up of individual vertical blocks with construction joints – later grouted to prevent leakage
  • 27. Concrete Dams - Solid Gravity Warragamba Dam, 142 metre high concrete gravity dam
  • 28. Concrete Dams - Buttress Sloping concrete slab supported on a number of buttresses • Massive buttress occurs when the buttresses touch
  • 29. Concrete Dams - Arch Upstream curvature transmitting the majority of its load onto the abutments • Base thickness < 60% of its height • where base thickness > 60% of its height, the dam is essentially a curved gravity dam • suited to deep, narrow gorges of strong abutment material • constructed in blocks- appropriate shrinkage gaps and construction joints
  • 30. Concrete Dams - Arch • Gordon Dam in Tasmania is a 140 metre high concrete arch dam
  • 31. Concrete Dams - Arch Gravity Combination of gravity and arch dams curved gravity dams
  • 32. Concrete Dams - Hollow Gravity Rely upon their weight for stability for watertightness, an impervious reinforced concrete membrane supported by buttresses securely keyed into sound rock • Include – slab and buttress, with inclined membrane – massive buttress, touching buttresses – conoidal, with a plane upstream face and identical massive buttresses – multiple-arch, membrane is a series of arches as distinct from a slab
  • 33. Concrete Dams - Prestressed Downstream curvature dam subjected to compressive forces before filling after filling, tensile stresses resulting in the dam are counteracted by the already existing compressive forces
  • 34. River Diversion Before the dam can be constructed, diversion of the river is necessary Satisfactory handling of the stream flow during construction is vital to the success of the work cost of river diversion must be compared with the risk of all or parts of the new dam in peak flood conditions types of diversion tunnel, flume, concrete or steel pipeline and open channel
  • 35. River Diversion Building a diversion tunnel Cofferdams act as barriers to the river Construction of the dam and power station Closure of the diversion tunnel
  • 36. Spillways • When dams are designed provision needs to be made to cope with large floods. Spillways are built to provide a path for floodwater to flow over or around the dam • Spillways on concrete dams are usually constructed to allow water to flow over the top. • Spillways associated with embankment dams are built to take the water around the side of the dam and away from the downstream face.
  • 37. Spillways • Overflow Spillway – overflows a special section of the dam itself • Byewash Spillway – separate open flood channel cut through a nearby saddle and with a small weir at the upstream end • Side-Inlet Spillway – located on the steep side of the gorge – direction of flow is parallel to the crest of the river • Drop-Inlet Spillway – water enters via a horizontal lip, drops through a vertical or sloping shaft and discharges through a horizontal or gently sloping culvert
  • 38. Spillways • Overflow Spillways • Glennies Creek Dam spillway
  • 39. Spillway Gates • Allow control over the level of fill of the reservoir • Used for three reasons: – to reduce the cost of the dam – to reduce the inundation of land in the reservoir area – to reduce the downstream flood damage • Three types – sliding gates - shutters running grooves – roller gates - employ rollers on the shutters – radial gates - form an arc pivoting on a trunion bearing
  • 40. Outlet • Necessary to make provision for the discharge of water as and when it is required for irrigation etc. • Separate outlet required – commonly a pipe passing under or through the dam, with discharge controlled by valves
  • 41. Damsite Surveys • Study of existing topographic maps and aerial photographs will indicate possible dam sites. • An estimate of catchment area and storage capacity can also be made • Surveys required – contour survey – watershed traverse – stability of site – cadastral surveys
  • 42. Dam Site Surveys - Contour Survey • Following selection of a possible site an aerial survey should be undertaken to provide a more detailed contour of the storage area • Typical scale, 1 : 10000 with a 2m contour interval • Allows more accurate computation of storage capacity • if the site is feasible, the survey provides a more concise design location of the dam wall • marks placed during the control survey for photo control also provides control for all future surveys
  • 43. Dam Site Surveys - Watershed Traverse • Where insufficient information exists to accurately determine the catchment area, it may be necessary to carry out a watershed traverse
  • 44. Dam Site Surveys - Stability of Site • Dam must be positioned where it will be stable and where the storage area does not have excessive underground leakage • Soil and rock features must be carefully examined • Large dams require test pits, bore holes and detailed geological survey • small dams may require only test holes to determine sub-surface features • the position of each investigation must be accurately located
  • 45. Dam Site Surveys - Cadastral Surveys • Land to be inundated is resumed by the constructing authority • Cadastral surveys required to delineate the land to be resumed • Surveys will also be required to close roads passing through inundated land
  • 46. Surveys in Dam Wall Area • General location of dam wall has been decided from earlier surveys • Further surveys are required within this area to aid final design and computation of volumes of excavation and fill - detail surveys - definition of dam wall on plan - location of limits of dam on ground - by-wash - clearing of site - pipeline surveys - road access - pumping stations
  • 47. Surveys in Dam Wall Area - Detail Surveys • More intense geological and soil surveys are carried out – ensure absence of geological faults – determine required depth of stripping • Detail and contour survey locating all topographic features, test-bores etc. – total stations or GPS – scale 1 : 1000, contour interval 1m
  • 48. Surveys in Dam Wall Area - Definition of Dam Wall on Plan • Following consideration of all factors, it is now possible to to define the centreline of the dam wall on the contour plan – also, working to specified batters, the extent of the earthworks can be plotted on the contour plan
  • 49. Surveys in Dam Wall Area - Definition of Dam Wall on Plan • Crest RL 550m • 5m wide pavement on top • batters 2:1
  • 50. Surveys in Dam Wall Area - Locate Dam Limits on Ground • Stability of dam is dependent on – foundations, – materials used, and – method of construction • Foundations – remove all unsuitable material or unstable material from within the limits of the dam wall • Requires definition of the limits of the wall marked on the ground – toe of batters require pegging
  • 51. Surveys in Dam Wall Area - Grout Curtains • Grout is pumped down drill holes bored along the centreline and on either side of it • Centreline must be marked before actual construction commences
  • 52. Surveys in Dam Wall Area - By-Wash • The downstream face of an embankment dam will scour if water flows over the dam crest • an outlet or by-wash channel is necessary to allow excess water to flow around the dam wall to be discharged away from the dam wall – large dams normally have a large concrete channel • The horizontal and vertical position of the by-wash must be defined on the ground
  • 53. Surveys in Dam Area - Clearing of Site • Usual to clear the dam storage area of vegitation and tree cover prior to filling of the dam • Requires definition of the limits of the dam storage area marked on the ground – running the contour equal to full storage level
  • 54. Surveys in Dam Area - Additional Surveys • Pipeline alignment and sections from dam to consumer • pipeline easement surveys • access roads to dam site, and • surveys for siting and constructing pumping stations
  • 55. Surveys in Dam Area - Stability of Dam Wall • Monitoring surveys – to determine if any horizontal or vertical movement occurs after construction and in later years – unusual movement may indicate dam failure • Fix permanent marks along the crest of the dam wall and over the downstream face • regular control surveys required – must be able to identify small movement of say 3mm in horizontal or vertical
  • 56. Small Dams • Contour survey of pondage area is undertaken by ground survey rather than aerial survey • only test bore-holes are used to determine sub surface features with respect to site stability investigations • by-wash need only be a grass channel
  • 57. Proposed Earth Dam, General Arrangement and Detail (Sheet 1 of 6) • Plan of Works Area – dam centreline – by-wash – Drop Inlet • Longitudinal Section • Embankment - Type Section • Storage Capacity Diagram
  • 58. Proposed Earth Dam, General Arrangement and Detail (Sheet 1 of 6) - Plan of Works Area
  • 59. Proposed Earth Dam, Plan of Storage Area (Sheet 2 of 6) • Control Traverse • horizontal control – datum, permanent marks • vertical control – datum, bench marks • full storage level • test holes, test Pit Logs
  • 60. Proposed Earth Dam, Standard 600 * 100 Drop Inlet (Sheet 5 of 6) • Typical Abutment Plan and elevation • By-Wash Location Plan
  • 61. Proposed Earth Dam, Setting Out Survey (Sheet 6 of 6) • Assist with setting out batter points