SlideShare a Scribd company logo
1 of 73
Download to read offline
1   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi Run-of-River HPP
Presentation to Government of Lao PDR
     and other interested Stakeholders

           Monday 16 July 2012, Luang Prabang
Content of Presentation
1. General
2. Introduction of Pöyry
3. State of the art for run-of-river power plants
4. MRC Guidelines
5. Xayaburi HPP and other hydro schemes in the Mekong
6. Prior Consultation Process
7. Roles of Pöyry
8. MRC Guidelines
9. Dam safety
10.Sediments
11.Water Volume in the River
12.Fish Migration
13.Trans-boundary Effects
14.Main project changes recommended and implemented
15.Ongoing investigation works for the detailed design
16.Downstream effects of Run-of-river power plants similar to the Xayaburi Power Plant
17.Video Presentation on Project
18.Conclusions


3   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
General
• The general intention of this presentation is to inform the audience on
    – particularities of a run-of-river hydropower scheme
    – the compliance of the project with the MRC design guidelines
    – particular issues which were raised during the Prior Consultation Process
    – the concerns related to the issue of sediment transport in the lower reaches of the
      Mekong River
    – the influence the project might have on the water flow quantities in the lower
      reaches of the Mekong River
• It will also be shown what changes the project developer intends to actively
  introduce in the project to positively influence the sediment transport process
  and the other requirements stipulated in the MRC Design Guidelines.
• The Xayaburi project has been under development since 2007 and the
  following studies / reports have been completed by others and used as basis:
    – Feasibility study
    – Environmental and social impact assessments
    – EPC tender documents
    – Various Studies on this project and general information available




4   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Presenters of Pöyry

• Knut Sierotzki, Responsible Director for Hydropower Asia and
    Russia, 25 years experience in water management and hydropower
    globally, since 1991 also working in SE Asia

• René Schmidiger, Senior Project Manager and Dam Expert, 36 years
    experience in hydropower projects in all continents, since 1992 also
    working in SE Asia

• Dr. Robert Zwahlen, Senior Environmentalist and Biologist, 35 years
    experience in environmental impact assessments and management
    projects mainly in the tropics, since 1989 also working in SE Asia,
    independent expert of World Bank, ADB and other international
    organisations on environment




5    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
GLOBAL EXPERTS IN CONSULTING AND ENGINEERING

    Pöyry is a global consulting and engineering
    company dedicated to balanced sustainability and
    responsible business

    About 7 000 experts in about 50 countries
    Project experience in over 100 countries
    15 000 projects annually

    Net sales in 2011 EUR 796 million




                                                                COPYRIGHT©PÖYRY
6      Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
ENGINEERING BALANCED SUSTAINABILITY™



 • Balanced sustainability is a holistic,
   multidimensional approach to sustainability
   that we apply to everything we do.
 • It strives to achieve a balance between
   economic, environmental and social
   dimensions, as most appropriate to the
   nature of the project and where in the
   world we are working.
 • Engineering balanced sustainability™ is
   about improving resource efficiency. It
   involves finding solutions to improve
   energy, water, material and supply chain
   efficiencies while improving the overall
   return on investments.




                                                            7
   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
GROUP’S NET SALES IN 2011



                 Net sales by business group                                                        Net sales by region
                           Management
                           Consulting                                                                  Other 4 (5) %
                             11 (11) %
                                                                   Energy           South America                              Nordics
      Water &                                                      26 (25) %          18 (11) %                                29 (28) %
      Environment
       11 (12) %
                                                                               North America
                                                                                     4 (4) %
                                                                                      Asia
                                                                                      7 (7) %
Urban & Mobility
      23 (29) %

                                                              Industry
                                                              30 (23) %
                                                                                                                  38 (45) %
                                                                                                                Other Europe




  8       Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
PÖYRY – YOUR PREFERRED PARTNER
                 Global network                                                                          Tradition meets innovation


                                                                             tunnel
                                                                             engineers
                                                                                         environmental
                                                                                           specialists

                                                                 hydraulic
                                                                 engineers

                                                                                                         Foundation of Elektrobank in 1895
                                                                                          electrical &
                                                                                          mechanical
                                                                                          engineers
                                                                   Over 400 hydro
                                                       civil         specialists
                                                     engineers                                             International activity
Range of services
                                                                                                           On-going projects worldwide
    Asset valuation
    Consulting services                                                        dam
    Project development services                                             engineers
    Design & Engineering
    Construction Services
    Electromechanical &
    rehabilitation services
    Specialized Services



9      Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
...WITH 120 YEARS OF HYDRO EXPERIENCE

     • 1895: Foundation of Elektrobank in Zurich,
       Switzerland
     • 1911: Association of Finnish Steam Boiler Users
       established (later Fuel and Power Economy)
     • 1946: Elektrobank’s engineering department
       becomes Elektro-Watt
     • 1965: Elektro-Watt becomes Elektrowatt Engineering
       Services and later Electrowatt Engineering
     • 1972: Ekono Oy was established by separating the
       Consulting business from the Finnish Association.
     • 1993: Jaakko Pöyry Group acquired Ekono’s energy
       business and continued under name Ekono Energy
     • 1997: Acquisition of Electrowatt Engineering by the
       Jaakko Pöyry Group
     • 1998: Energy business group of Jaakko Pöyry Group
       operates under name Electrowatt-Ekono
     • 2004: Acquisition of Verbundplan GmbH by the
       Jaakko Pöyry Group
     • 2006: Electrowatt-Ekono and Verbundplan called
       Pöyry under the Pöyry Group’s rebranding strategy
     • 2011: Acquisition of SwedPower AB by Pöyry Group



10     Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Major Hydropower projects of Pöyry under execution in 2012

     Current Projects                                            No. of MW
     Laja I, Chile                                                   35
     Taschinas, Switzerland                                          11
     Thurfeld, Switzerland                                            2
     Deriner, Turkey                                                670
     Ermenek, Turkey                                                300
     Tuirial, India                                                  60
     Macchu Piccu II, Peru,                                         100
     Quitaracsa, Peru                                               112
     Rucatayo, Chile,                                                56
     Limberg II PSP, Austria                                        480
     Reisseck II PSP, Austria                                       430
     Uma Oya, Sri Lanka                                             150
     Siah Bishe PSP, Iran                                          1,000
     Rheinfelden, Switzerland                                       116
     Tsankov Kamak, Bulgaria                                         80
     Rudbar-Lorestan, Iran                                          450
     Lehen HPP, Austria                                              20
     Xayaburi, Lao PDR                                             1,470
     Ashta, Albania                                                  90
     Beyhani 1, Turkey                                              550
     Karlsdorf Gössendorf, Austria                                   20
     Total capacity under execution                                6,202




11      Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Nam Ngum 2 Hydroelectric Project, Lao PDR
 181 m concrete faced rockfill dam and 615 MW hydropower plant (Francis units)


                                                              Client
                                                              South East Asia Energy Ltd., Bangkok
                                                              Thailand

                                                              Project Details
                                                                Dam height 181 m
                                                                Crest length 510 m
                                                                Spillway capacity 9,000 m3
                                                                Power tunnel 1 x 675 m    3 x 210 m
                                                                Gross head 164 m
                                                                Rated discharge 422 m3/s
                                                                Powerhouse (surface) 3 x 205 MW

                                                              Scope of Services
                                                              Independent owner’s engineer - feasibility,
                                                              tender, detailed design and construction
                                                              supervision

                                                              Execution Period
                                                              2004 – 2011


12   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
FREUDENAU HYDRO POWER PLANT, AUSTRIA
     Run-of-river power plant with 6 bulb turbines of 30 MW, rated capacity 172 MW

     Client
     Österreichische Donaukraftwerke AG

     Scope of Services
     • Prefeasibility study
     • Feasibility study
     • Engineering design
     • Tendering and procurement services
     • Design of backwater area in cooperation with
       Vienna Metropolitan Administration
     • Construction and erection supervision
     • Commissioning
     Execution Period
     1992 – 1998




13      Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
BIRECIK DAM AND HYDROPOWER PLANT, TURKEY
     62.5 m high concrete gravity dam/fill dam with concrete core, 672 MW, 6 Francis turbines

     Client
     Ministry of Energy and Natural
     Resources (DSI), Turkey

     Scope of Services
     • Feasibility Study
     • Final Design
     • Construction design
     • Site Management
     • BOT development
     • Operation
     Execution Period
     1996 – 2001




14      Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
NATHPA JHAKRI HYDROPOWER SCHEME, INDIA
1500 MW run-of-river power plant in the Himalayan foothills



                                                              Client:
                                                              Nathpa Jhakri Power Corporation Ltd. (NJPC),
                                                              Shimla, India

                                                              Scope of Services (1990-2003):
                                                              • Preparation and review of technical specifications
                                                              • Review of detailed designs and civil construction
                                                                  drawings
                                                              •   Establishment of quality control procedures
                                                              •   Assistance in solving technical problems during
                                                                  construction
                                                              •   Settlement of claims
                                                              •   Advice on construction methodology and
                                                                  equipment
                                                              •   General project monitoring and management




15   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Kukule Hydropower Plant, Sri Lanka


                                                              Client:
                                                              Ceylon Electricity Board
                                                              Description:
                                                              • Implementation of a 78 MW run-of-
                                                                  river scheme

                                                              Scope of Services (1998-2003):
                                                              • Tender documents and drawings
                                                              • Assistance in pre-qualification and
                                                                  tender evaluation
                                                              •   Civil engineering drawings
                                                              •   Review of E&M design and
                                                                  documents
                                                              •   Supervision of construction, erection
                                                                  and commissioning




16   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
RHEINFELDEN POWER STATION, SWITZERLAND/GERMANY

     Client
     Kraftübertragungswerke Rheinfelden AG

     Project Details
     Replacement of power plant from 1895
     Owners engineer for design of a 116 MW run-of-
     river scheme to replace existing power plan
     with 4 bulb turbines a total discharge of
     1500 m³/s.

     Scope of Services
     • Final Design
     • Environmental impact assessment and
       investigations
     • Assistance to client for receiving the
       concession from the authorities
     • Construction Design and Supervision
     Execution Period
     1984 – 1994
     2004 – 2011



17     Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in run-of-river power plants


The technology for run-of-river power
plants is now about 120 years old. Some
of the first schemes were built along the
river Rhine between 1895 and 1905.
During the last 120 years considerable
developments have taken place in
technical fields as well as in the
sustainability of such schemes.




18   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in Run-of-river power plants

• The reservoir level has to be kept
  largely constant (head) and inflowing
  water is constantly released either
  through the turbines or the spillway
• The water is not stored (except
  impounding) and therefore the mean
  daily flow regime of the river is not
  affected
• This is in contrast to high head storage
  schemes where large volumes of water
  are stored by means of high dams
     – storing excess water during the high flow
       season and releasing water during the low
       flow season and
     – accumulating the river flow sediments in the
       reservoir



19   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in run-of-river power plants

Today the following main principles are used in the design of the run-
of-river power plant:
     – to built the weir and power structure as flexible as possible allowing the routing of
       floods, sediments and nutrients directly through the system.
     – to allow migration of fish and other aquatic animals through or around the dam
      structure
     – to have the best available equipment to avoid pollution, to allow downstream fish
      migration and best use of the energy
     – to allow for efficient navigation and to support recreation
     – to satisfy the highest safety standards according national and international norms
     – to support the general development of a region with the supply of safe, reliable
      and clean energy




20   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in run-of-river power plants

Various upstream and down stream fish migration systems e.g. fish
lock, fish ladder, natural by-pass channel, fish lift etc.
Protection of the area and ban of fishing and hunting in the vicinity of
all structures.




21   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in run-of-river power plants
Fish Friendly Turbine




22   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish Friendly Turbines:




 Mortality of fish passing through turbines


 Turbine Type                                                           Length of Fish
                                                              5-10 cm                    30-50 cm
 Francis                                                      >50%                   up to 100%
 Kaplan                                                       5-10%                      15-30%
 Fish-friendly turbines                                        <5%                        5-10%




23   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
State of the Art in run-of-river power plants

Release of Sediments
     – Most of the larger run-of-river schemes
       with dams / weirs larger than about 20m
       height are equipped with larger bottom
       outlets for sediment release.
     Examples:
     – India, CWC request from public and
       private developers the use of large
       bottom outlets is required for the
       continuous release of sediments during
       the monsoon period.
     – China, some large run-of-river dams
       have sediment outlets e.g Three
       Gorges
     – Sudan, Merowe (Nile River), large
       Sediment outlets were provided
     – France, CNR will explain in their
       presentation
24   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
MRC design guidelines

• The preliminary MRC design guidelines is one of the documents
  developed for the implementation of the 1995 Mekong Agreement to
  assure a sustainable development of the Mekong River Basin
• The guidelines deal with the following issues:
      – Navigation lock system
      – Fish passing facilities
      – Sediments
      – Water quality and aquatic ecology
      – Safety of dams
• For downstream countries the issue of sediments and nutrient is of
     particular interest for the long-term development of the lower Mekong
     Regions




25    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme and other hydro schemes in the Mekong
 Upstream Hydropower developments:
     1. Manwan HPP, 1550 MW, 132 m high dam with
        seasonal storage
     2. Jinghong HPP, 1750 MW, 108 m high dam
     3. Nouzhadu HPP, 5850 MW, 261.5 m high dam, multi-
        annual storage
     4. Xiaowan HPP, 4200 MW, 294.5 m dam, multi-annual
        storage
 The schemes under development
 (Xiaowan & Nouzhadu) are
 storage schemes and will also trap
 large amounts of sediments to secure
 the operation of the d/s power plants.
 Reference: Department of
 Sedimentation, China Institute of
 Water Resources Hydropower
 Research

 Downstream hydropower
 Developments:
     1. All d/s schemes are run-of-river
        schemes.
     2. None of this schemes have any pond
        larger then a few hours of operation
     3. Dam heights are below 30m




26     Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Overview




27   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Main Features

Country:                                Lao PDR
Location:                               Xayaburi town, Approximate 80 km south of Luang Prabang
Commercial operation:                   October 2019 (expected)
Construction cost:                      $3.8 billion
Owner(s):                               Xayaburi Power Company Limited (XPCL)
Dam and Spillways
Height:                                 32.6 m
Length:                                 820 m
Type of spillway:                       7 x radial gates, 4 low level outlets
Spillway capacity :                     47’500 m3/s
Pond Capacity :                         726 Mio m3, filling time with mean Mekong flow about 50 hours
Catchment area:                         272,000 km2
Full supply level:                      275 m a.s.l.
Power station
Hydraulic rated head:                   18 m
Turbines:                               7 x 175 MW Kaplan-type, 1 x 60 MW Kaplan-type
Maximum capacity:                       1,285 MW
Energy Production:                      7’405 GWh,
Export to Thailand                      6’985 GWh supplies electricity for 3 Mio people or 750’000 families
For Lao PDR                             420 GWh supplies electricity for 1 Mio people or 200’000 families


28   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Construction Sequences
                                                                                                 Cofferdam completion
                                                                                                 schedule

                                                                                                 May 2013

Cofferdam completion
      schedule

      May 2013




                                                          Stage 1 Intermediate
                        DOWNSTREAM                          Block completion
                                                                schedule
                                                                Jun 2014

             River diversion phase 1: construction cofferdams at the right side of the Intermediate block



 29   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Construction Sequences
                    Navigation Lock and
                    Spillway completion
                          schedule
                          Oct 2014




                       DOWNSTREAM




            River diversion phase 1: construction Navigation log and spillway



30   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Construction Sequences
                                                                                                       Cofferdam removal
                                                                                                            schedule

                                                                                                             Oct 2014

Cofferdam removal
schedule

Oct 2014




                                                                                                        Cofferdam completion
       Cofferdam completion                                                                             schedule
       schedule
                                                                                                        Jun 2015
                          DOWNSTREAM
       Jun 2015



               River diversion phase 2: construction coffer dam at the left side of the Intermediate block



  31    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Construction Sequences




                                                                                                  Main structure of
                                                                                                  Powerhouse & Fish
                                                                                                  ladder completion
                       DOWNSTREAM                                                                 schedule
                                                                                                  Mar 2018



            River diversion phase 2: construction coffer dam at the left side of the Intermediate block



32   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Xayaburi scheme, Construction Sequences




                                                                                                     Cofferdam removal
                                                                                                     schedule
       Cofferdam removal
       schedule                                                 Powerhouse                           Mar 2018
                   DOWNSTREAM
                                                                commissioning
       Mar 2018                                                 Sep 2019


            River diversion phase 2: removal coffer dam at the left side of the Intermediate block



33   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Role of Pöyry

• Contractual basis:
     – Consulting Services Agreement for Compliance Review
     – Between GOL and Pöyry Energy (5. May 2011)
• Scope of work: to report on whether
     – Xayaburi Power Company (Owner) has complied with and satisfied the
       Mekong River Commission (MRC) Design Guidelines
     – GOL and the Owner have taken into consideration the comments
       submitted by the MRC member countries during the Prior Consultation
       Process
     – GOL and Owner have complied with the terms of “Prior Consultation
       Project Review Report on Xayaburi Project”, dated 24 March 2011
     – Issues relating to development, construction and implementation of
       Xayaburi and any discrepancies, conflicts and needs for changes in
       connection with comments by the riparian countries




34   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Role of Pöyry, Compliance Study
Pöyry has performed in 2011 a Compliance Study based on the previous
documentation on the following topics.
     – Following the “Prior Consultation Process” according to the MRC guidelines, the
        MRC stakeholder countries issued comments on Xayaburi project
     – Critical comments were raised by Vietnam, Cambodia and Thailand
     – Main items of concern and potential improvements are:
           • Retention of sediment
           • Migration of fish
     – Pöyry carried out a Compliance Report with the objective to:
           • Assess comments made by stakeholders and MRC on the current design
           • Evaluate these comments against the MRC guidelines
           • Identify points where the current design does not fully follow the MRC guidelines
           • Propose measures to make the Xayaburi project fully compliant with the MRC guidelines
     – The Compliance Report was issued to the Government of Lao in August 2011.
     – Continuous assistance to the Government of Lao to address the technical queries
        raised.




35   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main issues raised in the Prior Consultation Process

• The main concerns of the riparian countries are:
     – Trans-boundary issues
     – Certain impacts not addressed in as great detail as one would like
        • Sediment trapping
        • Nutrients
        • Fishery
        • Biodiversity
        • Socio-economic aspects
• These concerns can be remedied during the construction stage by:
     – Additional investigations recommended
     – Implementation of certain design changes
         • Providing of flushing gates to allow release of sediments
         • Improvement of fish pass facilities




36   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main issues raised in the Prior Consultation Process

• Findings MRC Expert Group Safety of Dams
     – Issues will be taken into account
• Findings MRC Expert Group Navigation Lock System
     – Suggested changes will be introduced
• Findings MRC Fishery Expert Group (fish ecology and fishery)
     – Gaps are identified and recommended actions will be implemented
• Findings MRC Fishery Expert Group (fish passage facilities)
     – Recommendations are reasonable and applicable recommendations will
       be checked and taken into account




37   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main issues raised in the Prior Consultation Process

• Findings MRC Fishery Expert Group (socio-economics and rural
     livelihood aspects)
      – Baseline investigation
      – Monitoring
      – Compensation measures
• Findings MRC Sediment Expert Group on sediments
      – Sedimentation during construction
      – Adaptive management of flushing devices
         • Uncertainties considering available data
         • Uncertainties considering future development
         • Mitigation of sediment concentration peaks




38    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Dam safety
• General design principles
     – State of the art design principles and design methods are being used
       and which are in line with the size and importance of the project
• Overall project safety concept
     – The concept is being developed in which the different project parts (or
       elements) will be design according to different criteria, depending on
       their importance and damage potential. Applies to civil works and also
       all equipment.
• Flood design
     – Follows internationally accepted concepts
• Seismic design
     – ICOLD guidelines will be followed where project parts will be designed
       for OBE (operation basis earthquake, 145 yr), DBE (design basis
       earthquake, 475 yr) and checked against the SEE (safety evaluation
       earthquake, 10’000 yr), depending on their hazard potential
• Design complies with MRC design guidelines

39   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (1)

• Main concerns expressed
     – Reduction of sediment content in Mekong River downstream of Xayaburi
     – Can have detrimental effects up to Mekong delta in Vietnam
     – Leading there to costal erosion and intrusion of sea water
     – Reduction of nutrition content in Mekong River downstream of Xayaburi
     – Having detrimental effect on fish population
     – Leading to reduction of fishing yields in River downstream
     – Negatively affecting downstream population
• Current sediment transport regime
     – The main sediment transport in the river takes place during the high flow
       season
     – In the present state the yearly sediment flow in the river is in a stable
       state, although influenced by the construction of dams in China (see
       explanations of CNR)




40   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (2)

• Basic requirement for sediment transport
     – Xayaburi dam must be a transparent dam and mimic the natural
       conditions (see MRC Guidelines)
     – This means the dam must be capable not to retain and store the
       sediments, but to release them towards downstream in natural way
• Introduction of low level outlets
     – The original spillway outline design has been adapted by introducing 4
       large capacity low level outlets equipped with radial gates
     – Their dimensions are 12 m (width) and 16 m (height)
     – Their sill level is 14 m lower than the spillway sill level
     – The number of the original spillway openings has been reduced by 3
       openings and the spillway sill level has been lowered by 2m
• Purpose of the low level outlets
     – The low level outlets will allow, in combination with the spillway, to
        • route sediment loaded flood flows through the available low level and spillway
          openings and to
        • draw down the reservoir and to flush the sediments towards downstream

41   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (3)

• Cross section of low level outlet




42   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (4)

• Cross section of spillway outlets




43   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediments (5)

• Longitudinal section along spillway complex, showing both spillway
     opening and low level openings




                                                               252

                                                                      238
                                                                230




44    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (6)

• Timing of sediment release
     – Flood routing will be done during high river flows in the flood flow season
     – Reservoir flushing will be done also during the flood season primarily
       during the weekend
     – The operations will be done in each year in order to mimic close natural
       conditions
• Effect of these operations
     – These repetitive operations will prevent the excessive accumulation of
       sediments in the reservoir and which would be lacking in the downstream
• Control of sediment concentration
     – Too high sediment concentrations in the water released through the low
       level outlets would be detrimental to the river fauna
     – The sediment concentration will be controlled by combined release
       operations through the low level outlets (high concentration) and the
       spillway openings (low concentration)



45   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Sediment measures proposed by Pöyry (7)

• Control of effect of these operations
     – Potential sedimentation in the reservoir will need to be monitored by
       repetitive bathymetric surveys
     – Based on these results the flood routing and reservoir flushing operations
       can be adapted to the current needs
     – The installed release facilities offer full flexibility in this respect
     – Monitoring of sediment concentration downstream during flushing
       operation
• Coarse sediments
     – Will need to be transported by mechanical means (see CNR note)
• Conclusion
     – With the planned sediment release facilities and the intended operation
       procedures it will be possible to achieve a project facility transparent to
       sediments
     – The sediments entering the reservoir will be transferred towards
       downstream and potential negative effects of lack of sediment there can
       be reduced to a minimum.
46   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Flow Volume in Mekong River (1)

• Main concerns expressed
     – The current flow volume of the Mekong River would be affected by
       Xayaburi
     – There would be less flow in the low flow season
     – There could be higher flood flows
• Principle of run-of-river plant
     – There will be no seasonal storage of water volumes
     – The daily inflow into the reservoir corresponds to the daily outflow (see
       also CNR)
• Effect of Xayaburi on downstream river flow conditions
     – The current flow conditions in the river will therefore virtually not be
       changed
     – Minor changes are possible caused by daily variations in the power
       production (causing reservoir fluctuations up to 30 cm)




47   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Flow Volume in Mekong River (2)

     – Equally minor changes are to be expected during the weekend, when
       power production will be reduced
     – The effect of such changes in the water flow, which can cause water level
       variations limited to less than one meter, will reduce and finally equalize
       along the river the further away downstream one gets from the dam
     – The speed of the downstream water level variations can be controlled by
       operational measures. There will thus be no sudden water level rises.
• Flushing operations
     – Such operations can affect the downstream water flow for a longer river
       stretch
     – But flushing is only planned to be performed in the high flow season, when
       changes in the river flow are less felt




48   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Environmental and Social Impact Assessment (ESIA)
Carried out in 2007 - 2010
     – The studies carried out be by the EIA Consultant cover all the aspects which need
        to be covered for such a project and to comply with GoL requirements
     – The local environmental law in Lao PDR follows Worldbank/IFC guidelines
     – The total environmental cost are adequate even some of the total cost are
        accounted under other topics, e.g. cost for fishpass
The environmental studies were approved by GoL on 13 September 2010
Main findings:
     – Minor impact on local population, limited re-settlement required
     – Minor impact on fish fauna, Environmental Impact Assessment (EIA) survey only
        identified limited amount of fish species
Improvements recommended for the ESIA:
     – Additional survey of actual physical conditions, especially on fish species
     – Additional study on sedimentation




49   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Technical Paper No. 8 by MRC
The MRC published the main results of the main fish
migration systems in the Lower Mekong Basin.
There are three different migration systems:
     – The Lower Mekong Migration System (LMS)
       This migration system covers the stretch from the Khone
       Falls downstream to southern Cambodia, including the
       Tonle Sap system, and the Mekong Delta in Vietnam.
     – The Middle Mekong Migration System (MMS)
       From just above the Khone Falls and upstream to the Loei
       River, Thailand, the migration patterns are determined by
       the presence of large tributaries connecting to the Mekong
       mainstream.
     – The Upper Mekong Migration System (UMS)
       The third migration system occurs in the upper section of the
       river, approximately from the mouth of the Loei River and
       upstream towards the border between Lao PDR and China
       (probably continuing into China).
Whereas the LMS and the MMS are inter-connected to a
large degree, the UMS appears to be relatively isolated,
with little “exchange” between the UMS and the other
migration systems. These populations should be regarded
as separate biological unit.


50   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Technical Paper No. 8 by MRC
Main conclusions
1. The LMS and MMS migratory system are
     playing a crucial role in the fisheries of the
     Tonle Sap and Mekong delta.
2.   The main spawning areas are in the LMS
     and its tributaries.
3.   The UMS is not (or very limited) connected
     to the other migratory systems and has only
     significance for the local fisheries in this
     stretch of the river.
4.   The highest biodiversity of the Mekong is in
     the area downstream the Khone falls in
     Cambodia.
5.   The area between the mouth of the Loei
     River and the Chinese Border: One of the
     remarkable species in the UMS is the Giant
     Mekong Catfish (Pangasianodon gigas). It
     seems genetically to be a local subspecies
     which might be separated from the
     downstream population.

51   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish Migrations

Mainly two types:
• anadromous: adults move upstream for reproduction, young move
  downstream
• catadromous: adults move downstream (for reproduction in the sea),
  young move upstream
Other migrations, over longer or shorter distances, not necessarily
related to reproduction.




52   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
General effects of HPPs

Main impacts of dams on fish migration:
• Dams interrupt upstream fish migration
• Downstream migrations go mainly through the turbines, with a high
  risk of injury and mortality
• Fish that do not migrate for reproduction can be influenced by
  fragmentation of the populations (no genetic exchange between
  populations isolated by dams).




53   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main Measures Taken

Different measures have been developed for maintaining fish
populations and migrations, as:
• Fish ladders of different types
• Fish lifts
• Traps combined with transport
• Fish hatcheries and artificial restocking of rivers (in cases where
  migrations could not be maintained and/or other conditions led or
  contributed to the decrease in fish populations)
• Fish friendly turbines (turbines reducing risk of injuring or killing fish)




54   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish Hatcheries

• Done in cases where barriers
  (dams) are too high to be
  passed with a fish ladder
• where other conditions (mainly
  water quality) threaten fish
  populations
• usually done only for
  economically important species




55   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Limitations

• Experience gained so far mainly in North American and European
  rivers.
• Historic targets for measures were mostly Salmonids, i.e. fish which
  can cope with fast currents and rather high steps.
• Recently, fish passes were implemented which are acceptable for a
  wider range of fish species.
• Limited experience with fish passes in large tropical rivers but rapidly
  growing with the experiences in other countries e.g. Brazil




56   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (1)
• The present layout of the fish passing facilities comprises the
     following main structures
      – facility for upstream migration,
      – fish passage recording system for upstream migration and
      – facility for downstream migration
• The selected system is very
  comprehensive and employs
  a state-of-the-art technology
  and covers all operational
  conditions of the scheme
• However there are a few issues
  which need improvement
  to be in compliance with the
  MRC design guidelines.




57    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main Problems Identified

• Potentially very high amount of biomass, i.e. a very large number of
  migrating fish, during certain periods.
• High number of species with a very wide range of size.
• Therefore different migration requirements, especially concerning
  manageable flow speed and height of steps.
• Limited knowledge of fish migrations (in terms of species, numbers
  and seasonal distribution) at the project site.




58   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (2)

The following investigations are recommended:                  Area influenced by Xayaburi dam

1. During the first stage of the construction:                 Area influenced by other dams


     – develop additional baseline data on biology, ecology
       and livelihood restoration
     – improve the knowledge concerning the specific
       requirements of the aquatic fauna on the fish passage
       facilities
2. Investigations to be done independently from the
      start of the construction when sufficient data are
      available and under national or multinational
      responsibility:
     – additional investigations on trans-boundary issues on
       hydrology and baseline investigations (fauna, flora,
       habitat and socio-economy)
     – A cumulative impact assessment of the mainstream
       dams




59   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (3)

The following design adaptations are
  recommended:
• The fish passage facilities should be
  amended as follows:
     – The planned facility should be adapted as
       follows:
           • The downstream passage needs to be changed
             at the inlet and outlet structures
           • The velocity of the channels needs to be
             adapted based on the proposed investigations
           • The head difference between the pools needs
             to be adapted (too high); this will lead to a
             longer fish passing facility.
     – There should be a system provided to allow
       fish passage during construction
     – Flexibility allowing later improvements if
       required

60   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (4)
     – The MRC design guidelines require
       several independent systems:
           • The navigation lock should be adapted
             to serve as a fish lock (also during
             construction stage)
           • Space for a fish lift should be prepared




61   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (5)




62   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish passing facilities (6)

Furthermore the following additional measures are recommended:
     – Fish friendly turbines have been recommended in the feasibility study.
       The degree of fish friendliness of the turbines should be verified with the
       envisaged supplier of such turbines.
     – It is recommended to set-up and operate a fish breeding station for the
       augmentation of the existing fish
       population and re-introduction of
       locally endangered species for
       release in a suitable river stretch.




63    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Additional Recommendations

Given the lack in baseline information, the following is recommended:

• Aquatic baseline investigation concerning important habitats, spawning
     areas, feeding areas, etc. within the future reservoir area.

• Fish survey: species inventory, migration patterns, abundance, total fish
     biomass and larval drift.

• Identification of target species which represent whole groups (concerning
     size and migration patterns, economic importance, etc.); swimming ability
     and behavioural studies.




64     Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Fish Migration and Biomass Study

• A study has started which aims at providing additional information on
     migrations and biomass.
•    A suitable sampling site was chosen about 1 km d/s of the dam site.
•    Main method applied is detecting migrating fish by means of hydro
     sonar; four stations are being used (one fix on each river bank, two
     mobile ones on boats).
•    First field campaigns have been carried out end of March / April and
•    First reports were submitted.




65    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
First Results




Size of fish migrating upstream (April 2012):

 April 2012 (left)                                            May 2012 (right)
 • about 50% 0-20 cm                                          • about 50% 0-20 cm
 • about 5% > 1 m                                             • about 10% > 1 m, up to 2.2m



66   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
First Results (2)




67   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Follow-up

Ongoing activities:
• Follow-up on studies, monitoring results
• Initiation and supervision of implementation of environmental
  measures on site
• Maintaining discussion and exchange of information with relevant
  stakeholders
• Integration of new findings into design of fishway




68   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Main project changes recommended and to be implemented

• The following changes will be implemented in the project
• A) Sediment transportation
     – Provision of large capacity low level outlets
     – Allows passage of the sediments towards downstream during high flow
       season
     – The aim is a transparent dam with respect to sediments
• B) Fish passage
     – Fish passing facility in navigation lock
         • Allows fish passage also during construction period
     – Adaptation of fish ladder system (step height) depending on findings of
       baseline studies
     – Provision of a fish lift (additional) if baseline studies indicate the need for it
• C) Navigation locks
     – Improvements in upstream lock approach area (avoidance of bends)
     – Changes in lock feeding system (making operation more smooth)


69   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Recommended investigations
Investigations to be carried out specifically
for Xayaburi (i.e. by the developer) during
the construction stage:
• Fish survey and related studies for optimising
  fish pass facility
• Additional socio-economic studies on the
  effects of Xayaburi in the reservoir area and in
  the downstream proximity
• Continuous measurements of flow, water
  quality and other parameters
• Baseline study for sediment content and
  sediment composition of Mekong river in
  project area
Framework studies to be carried under national or multinational
responsibility, independent from the start of the construction:
• CIA and trans-boundary assessment of effects of all HPP developments in the
     Mekong basin (also taking into account effects of planned and operating dams in
     China).

70     Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Ongoing investigation works for the detailed design

The following main topics of investigations are on-going or have
already been completed:

                                                                   2010        2011        2012
     S/N                      Investigation Topics
                                                              Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
       1         Seismic investigation
      1.1        Geological investigations
       2         River quality measurements
       3         Hydrological measurements
      3.1        River Sedimentation sampling
       4         Meteorology measurements
       5         Additional ecological studies
      5.1        Fish survey
       6         Additional social studies




71   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
Conclusions by Pöyry
• The Compliance Study performed by Pöyry has established those
  areas where the project was not yet fully in compliance with the MRC
  preliminary design guidelines
• Proposals on actions to be taken to bring the project into full
  compliance were made
• The necessary actions have all been initiated by now and which
  consist of
     – Actual changes to the project and its future operation
     – Additional studies and investigations in areas where knowledge deficits
       were identified
• With these actions taken it can be considered that the project will not
  have unacceptable negative effects and restrictions on the population
  living downstream of the project, and therefore also not in the
  neighboring countries further south
• Following this carefully balanced approach the project fulfills the
  highest standards in accordance with the current State-of-the-Art

72   Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
THANK YOU!




73    Xayaburi HPP, Presentation 16 July 2012, Luang Prabang

More Related Content

Viewers also liked

Hydropower project
Hydropower projectHydropower project
Hydropower projectNoelle Banks
 
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMBHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMyash Natani
 
St module1 1 jan2008
St module1  1 jan2008St module1  1 jan2008
St module1 1 jan2008kjmughal
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Ryan Triadhitama
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Pratik Diyora
 
Hydraulic turbines
Hydraulic turbinesHydraulic turbines
Hydraulic turbinesDr. Ramesh B
 
Recent Trends In Power Generation
Recent Trends In Power GenerationRecent Trends In Power Generation
Recent Trends In Power GenerationGowtham MG
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plantYuri Melliza
 
Hydraulic turbine
Hydraulic  turbineHydraulic  turbine
Hydraulic turbineJay Patel
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier applicationdaudsangeenkhan
 
Hydro electric power
Hydro electric powerHydro electric power
Hydro electric powerLEE-MALAK
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSRaju D
 

Viewers also liked (17)

Hydropower
HydropowerHydropower
Hydropower
 
Hydropower project
Hydropower projectHydropower project
Hydropower project
 
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEMBHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
BHEL HARIDWAR,CONSTRUCTION OF TURBO GENERATOR AND EXCITATION SYSTEM
 
St module1 1 jan2008
St module1  1 jan2008St module1  1 jan2008
St module1 1 jan2008
 
Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)Hydroelectric Power Plant (and Pumped Storage Power Plant)
Hydroelectric Power Plant (and Pumped Storage Power Plant)
 
Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008Hydro power plant presentation project by pratik diyora 100420106008
Hydro power plant presentation project by pratik diyora 100420106008
 
Hydro power presentation
Hydro power presentationHydro power presentation
Hydro power presentation
 
Hydraulic turbines
Hydraulic turbinesHydraulic turbines
Hydraulic turbines
 
Recent Trends In Power Generation
Recent Trends In Power GenerationRecent Trends In Power Generation
Recent Trends In Power Generation
 
Hydro electric power plant
Hydro electric power plantHydro electric power plant
Hydro electric power plant
 
Hydraulic turbine
Hydraulic  turbineHydraulic  turbine
Hydraulic turbine
 
Ppt of turbine
Ppt of turbinePpt of turbine
Ppt of turbine
 
Steam turbine
Steam turbineSteam turbine
Steam turbine
 
Types of turbine & thier application
Types of turbine & thier applicationTypes of turbine & thier application
Types of turbine & thier application
 
Hydro electric power
Hydro electric powerHydro electric power
Hydro electric power
 
Steam Turbines Basics
Steam Turbines BasicsSteam Turbines Basics
Steam Turbines Basics
 
Elements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTSElements of HYDRO ELECTRIC POWER PLANTS
Elements of HYDRO ELECTRIC POWER PLANTS
 

Similar to Xiyaburi dam project poyry july_2012_v_03

1.8 project management
1.8 project management1.8 project management
1.8 project managementsomchand123
 
Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010smilerneil
 
эрчим хүчний яам
эрчим хүчний яамэрчим хүчний яам
эрчим хүчний яамBayar Tsend
 
Green Week presentation - bart fokkens
Green Week presentation - bart fokkensGreen Week presentation - bart fokkens
Green Week presentation - bart fokkensRESTORE
 
Korea business forum july4 0930-1400
Korea business forum july4 0930-1400Korea business forum july4 0930-1400
Korea business forum july4 0930-1400nautes7881
 
Green Buildings - Anna Tuominen - Poyry - April 2010
Green Buildings - Anna Tuominen - Poyry - April 2010Green Buildings - Anna Tuominen - Poyry - April 2010
Green Buildings - Anna Tuominen - Poyry - April 2010Burton Lee
 
Veolia german mongolian corp days
Veolia german mongolian corp days    Veolia german mongolian corp days
Veolia german mongolian corp days Turchino Avanti
 
Ex Stream Eng Design Group Corporate Profile
Ex Stream Eng Design Group Corporate ProfileEx Stream Eng Design Group Corporate Profile
Ex Stream Eng Design Group Corporate Profileggurudev
 
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.sEsia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.szubeditufail
 
4220 SLSC Programme Roadmap - FINAL - 161216
4220 SLSC Programme Roadmap - FINAL - 1612164220 SLSC Programme Roadmap - FINAL - 161216
4220 SLSC Programme Roadmap - FINAL - 161216Godfrey Bridger
 
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi MalaysiaISCN_Secretariat
 
Micro-hydropower’s.pptx
Micro-hydropower’s.pptxMicro-hydropower’s.pptx
Micro-hydropower’s.pptxPrakashBudha3
 
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...OECD Environment
 

Similar to Xiyaburi dam project poyry july_2012_v_03 (20)

1.8 project management
1.8 project management1.8 project management
1.8 project management
 
Richard Taylor, IHA
Richard Taylor, IHARichard Taylor, IHA
Richard Taylor, IHA
 
A common vision for water innovation - Roisin Ingles, WssTP
A common vision for water innovation - Roisin Ingles, WssTPA common vision for water innovation - Roisin Ingles, WssTP
A common vision for water innovation - Roisin Ingles, WssTP
 
Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010Rating Green Buildings - 4th March 2010
Rating Green Buildings - 4th March 2010
 
эрчим хүчний яам
эрчим хүчний яамэрчим хүчний яам
эрчим хүчний яам
 
Green Week presentation - bart fokkens
Green Week presentation - bart fokkensGreen Week presentation - bart fokkens
Green Week presentation - bart fokkens
 
Korea business forum july4 0930-1400
Korea business forum july4 0930-1400Korea business forum july4 0930-1400
Korea business forum july4 0930-1400
 
Clean Energy Forum, all slides combined
Clean Energy Forum, all slides combinedClean Energy Forum, all slides combined
Clean Energy Forum, all slides combined
 
Green Buildings - Anna Tuominen - Poyry - April 2010
Green Buildings - Anna Tuominen - Poyry - April 2010Green Buildings - Anna Tuominen - Poyry - April 2010
Green Buildings - Anna Tuominen - Poyry - April 2010
 
Veolia german mongolian corp days
Veolia german mongolian corp days    Veolia german mongolian corp days
Veolia german mongolian corp days
 
Ex Stream Eng Design Group Corporate Profile
Ex Stream Eng Design Group Corporate ProfileEx Stream Eng Design Group Corporate Profile
Ex Stream Eng Design Group Corporate Profile
 
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.sEsia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
Esia of 132 kv mehmoodabad g.s and u.g transmission line from qayumabad g.s
 
4220 SLSC Programme Roadmap - FINAL - 161216
4220 SLSC Programme Roadmap - FINAL - 1612164220 SLSC Programme Roadmap - FINAL - 161216
4220 SLSC Programme Roadmap - FINAL - 161216
 
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia
2012 ISCN Symposium Sustainable Initiatives in Universiti Teknologi Malaysia
 
NHPC Training Report
NHPC Training ReportNHPC Training Report
NHPC Training Report
 
Micro-hydropower’s.pptx
Micro-hydropower’s.pptxMicro-hydropower’s.pptx
Micro-hydropower’s.pptx
 
Design Group Corporate Profile
Design Group Corporate ProfileDesign Group Corporate Profile
Design Group Corporate Profile
 
Real Estate Sustainability
Real Estate SustainabilityReal Estate Sustainability
Real Estate Sustainability
 
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...
Experience of implementing the Joint Crediting Mechanism (JCM) and way forwar...
 
CONPOLOX-AOP PPT
CONPOLOX-AOP PPTCONPOLOX-AOP PPT
CONPOLOX-AOP PPT
 

More from Sarod Paichayonrittha

พระพุทธเจ้าทรงสั่งสอนอะไร What did the buddha teach
พระพุทธเจ้าทรงสั่งสอนอะไร  What did the buddha teachพระพุทธเจ้าทรงสั่งสอนอะไร  What did the buddha teach
พระพุทธเจ้าทรงสั่งสอนอะไร What did the buddha teachSarod Paichayonrittha
 
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุ
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุสูตรของเว่ยหลาง โดย พุทธทาสภิกขุ
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุSarod Paichayonrittha
 
อานาปานสติสูตร
อานาปานสติสูตรอานาปานสติสูตร
อานาปานสติสูตรSarod Paichayonrittha
 
Ukti marketing brief make it happens -jan2014
Ukti marketing brief  make it happens  -jan2014Ukti marketing brief  make it happens  -jan2014
Ukti marketing brief make it happens -jan2014Sarod Paichayonrittha
 
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณ
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณรำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณ
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณSarod Paichayonrittha
 
Led lighting outdoor design challenge dec2013
Led lighting outdoor design challenge dec2013Led lighting outdoor design challenge dec2013
Led lighting outdoor design challenge dec2013Sarod Paichayonrittha
 
Kwater investor presentation oct2013
Kwater investor presentation oct2013Kwater investor presentation oct2013
Kwater investor presentation oct2013Sarod Paichayonrittha
 
พระพุทธเจ้าทรงสั่งสอนอะไร พระนิพนธ์ในสมเด็จพระญาณสังวร
พระพุทธเจ้าทรงสั่งสอนอะไร  พระนิพนธ์ในสมเด็จพระญาณสังวรพระพุทธเจ้าทรงสั่งสอนอะไร  พระนิพนธ์ในสมเด็จพระญาณสังวร
พระพุทธเจ้าทรงสั่งสอนอะไร พระนิพนธ์ในสมเด็จพระญาณสังวรSarod Paichayonrittha
 
Handbook malaysian fi t feed-in-tariff renewable energy mar2011
Handbook   malaysian fi t feed-in-tariff renewable energy mar2011Handbook   malaysian fi t feed-in-tariff renewable energy mar2011
Handbook malaysian fi t feed-in-tariff renewable energy mar2011Sarod Paichayonrittha
 
รายงานประเมินผลไทยเข้มแข็ง มีค2554
รายงานประเมินผลไทยเข้มแข็ง มีค2554รายงานประเมินผลไทยเข้มแข็ง มีค2554
รายงานประเมินผลไทยเข้มแข็ง มีค2554Sarod Paichayonrittha
 
ตำราพิชัยสงครามสิบสามบท ของซุนวู
ตำราพิชัยสงครามสิบสามบท ของซุนวูตำราพิชัยสงครามสิบสามบท ของซุนวู
ตำราพิชัยสงครามสิบสามบท ของซุนวูSarod Paichayonrittha
 
The ultimatum of god nature the one straw revolution -a recapitulation-1996
The ultimatum of god nature the one straw revolution  -a recapitulation-1996The ultimatum of god nature the one straw revolution  -a recapitulation-1996
The ultimatum of god nature the one straw revolution -a recapitulation-1996Sarod Paichayonrittha
 
Led Lighting SSL Road Map US.DOE aug2012
Led Lighting SSL Road Map US.DOE aug2012 Led Lighting SSL Road Map US.DOE aug2012
Led Lighting SSL Road Map US.DOE aug2012 Sarod Paichayonrittha
 
หลักการเขียนลายเซ็น
หลักการเขียนลายเซ็นหลักการเขียนลายเซ็น
หลักการเขียนลายเซ็นSarod Paichayonrittha
 
ISA Effective Use of PID Controllers 3-7-2013
ISA Effective Use of PID Controllers 3-7-2013ISA Effective Use of PID Controllers 3-7-2013
ISA Effective Use of PID Controllers 3-7-2013Sarod Paichayonrittha
 
Feed in tariff malaysia brochure 2012
Feed in tariff malaysia brochure 2012Feed in tariff malaysia brochure 2012
Feed in tariff malaysia brochure 2012Sarod Paichayonrittha
 

More from Sarod Paichayonrittha (20)

พระพุทธเจ้าทรงสั่งสอนอะไร What did the buddha teach
พระพุทธเจ้าทรงสั่งสอนอะไร  What did the buddha teachพระพุทธเจ้าทรงสั่งสอนอะไร  What did the buddha teach
พระพุทธเจ้าทรงสั่งสอนอะไร What did the buddha teach
 
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุ
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุสูตรของเว่ยหลาง โดย พุทธทาสภิกขุ
สูตรของเว่ยหลาง โดย พุทธทาสภิกขุ
 
อานาปานสติสูตร
อานาปานสติสูตรอานาปานสติสูตร
อานาปานสติสูตร
 
Ukti marketing brief make it happens -jan2014
Ukti marketing brief  make it happens  -jan2014Ukti marketing brief  make it happens  -jan2014
Ukti marketing brief make it happens -jan2014
 
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณ
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณรำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณ
รำลึกวันวาน ปกิณกธรรม หลวงปู่มั่น_ภูริทัตโต_โดยหลวงตาทองคำ_จารุวัณโณ
 
The new scada jun2014
The new scada jun2014 The new scada jun2014
The new scada jun2014
 
Led lighting outdoor design challenge dec2013
Led lighting outdoor design challenge dec2013Led lighting outdoor design challenge dec2013
Led lighting outdoor design challenge dec2013
 
Kwater investor presentation oct2013
Kwater investor presentation oct2013Kwater investor presentation oct2013
Kwater investor presentation oct2013
 
พระพุทธเจ้าทรงสั่งสอนอะไร พระนิพนธ์ในสมเด็จพระญาณสังวร
พระพุทธเจ้าทรงสั่งสอนอะไร  พระนิพนธ์ในสมเด็จพระญาณสังวรพระพุทธเจ้าทรงสั่งสอนอะไร  พระนิพนธ์ในสมเด็จพระญาณสังวร
พระพุทธเจ้าทรงสั่งสอนอะไร พระนิพนธ์ในสมเด็จพระญาณสังวร
 
Oil and gas thailand 2011 v f
Oil and gas thailand 2011 v fOil and gas thailand 2011 v f
Oil and gas thailand 2011 v f
 
Handbook malaysian fi t feed-in-tariff renewable energy mar2011
Handbook   malaysian fi t feed-in-tariff renewable energy mar2011Handbook   malaysian fi t feed-in-tariff renewable energy mar2011
Handbook malaysian fi t feed-in-tariff renewable energy mar2011
 
รายงานประเมินผลไทยเข้มแข็ง มีค2554
รายงานประเมินผลไทยเข้มแข็ง มีค2554รายงานประเมินผลไทยเข้มแข็ง มีค2554
รายงานประเมินผลไทยเข้มแข็ง มีค2554
 
ตำราพิชัยสงครามสิบสามบท ของซุนวู
ตำราพิชัยสงครามสิบสามบท ของซุนวูตำราพิชัยสงครามสิบสามบท ของซุนวู
ตำราพิชัยสงครามสิบสามบท ของซุนวู
 
The ultimatum of god nature the one straw revolution -a recapitulation-1996
The ultimatum of god nature the one straw revolution  -a recapitulation-1996The ultimatum of god nature the one straw revolution  -a recapitulation-1996
The ultimatum of god nature the one straw revolution -a recapitulation-1996
 
ABB DC Circuit Breakers Catalog
ABB DC Circuit Breakers CatalogABB DC Circuit Breakers Catalog
ABB DC Circuit Breakers Catalog
 
Led Lighting SSL Road Map US.DOE aug2012
Led Lighting SSL Road Map US.DOE aug2012 Led Lighting SSL Road Map US.DOE aug2012
Led Lighting SSL Road Map US.DOE aug2012
 
หลักการเขียนลายเซ็น
หลักการเขียนลายเซ็นหลักการเขียนลายเซ็น
หลักการเขียนลายเซ็น
 
ISA Effective Use of PID Controllers 3-7-2013
ISA Effective Use of PID Controllers 3-7-2013ISA Effective Use of PID Controllers 3-7-2013
ISA Effective Use of PID Controllers 3-7-2013
 
China bullet train population 2013
China bullet train population 2013China bullet train population 2013
China bullet train population 2013
 
Feed in tariff malaysia brochure 2012
Feed in tariff malaysia brochure 2012Feed in tariff malaysia brochure 2012
Feed in tariff malaysia brochure 2012
 

Recently uploaded

How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?XfilesPro
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Patryk Bandurski
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountPuma Security, LLC
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxKatpro Technologies
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksSoftradix Technologies
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxOnBoard
 

Recently uploaded (20)

How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?How to Remove Document Management Hurdles with X-Docs?
How to Remove Document Management Hurdles with X-Docs?
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
Integration and Automation in Practice: CI/CD in Mule Integration and Automat...
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Breaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path MountBreaking the Kubernetes Kill Chain: Host Path Mount
Breaking the Kubernetes Kill Chain: Host Path Mount
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptxFactors to Consider When Choosing Accounts Payable Services Providers.pptx
Factors to Consider When Choosing Accounts Payable Services Providers.pptx
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Benefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other FrameworksBenefits Of Flutter Compared To Other Frameworks
Benefits Of Flutter Compared To Other Frameworks
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Maximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptxMaximizing Board Effectiveness 2024 Webinar.pptx
Maximizing Board Effectiveness 2024 Webinar.pptx
 

Xiyaburi dam project poyry july_2012_v_03

  • 1. 1 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 2. Xayaburi Run-of-River HPP Presentation to Government of Lao PDR and other interested Stakeholders Monday 16 July 2012, Luang Prabang
  • 3. Content of Presentation 1. General 2. Introduction of Pöyry 3. State of the art for run-of-river power plants 4. MRC Guidelines 5. Xayaburi HPP and other hydro schemes in the Mekong 6. Prior Consultation Process 7. Roles of Pöyry 8. MRC Guidelines 9. Dam safety 10.Sediments 11.Water Volume in the River 12.Fish Migration 13.Trans-boundary Effects 14.Main project changes recommended and implemented 15.Ongoing investigation works for the detailed design 16.Downstream effects of Run-of-river power plants similar to the Xayaburi Power Plant 17.Video Presentation on Project 18.Conclusions 3 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 4. General • The general intention of this presentation is to inform the audience on – particularities of a run-of-river hydropower scheme – the compliance of the project with the MRC design guidelines – particular issues which were raised during the Prior Consultation Process – the concerns related to the issue of sediment transport in the lower reaches of the Mekong River – the influence the project might have on the water flow quantities in the lower reaches of the Mekong River • It will also be shown what changes the project developer intends to actively introduce in the project to positively influence the sediment transport process and the other requirements stipulated in the MRC Design Guidelines. • The Xayaburi project has been under development since 2007 and the following studies / reports have been completed by others and used as basis: – Feasibility study – Environmental and social impact assessments – EPC tender documents – Various Studies on this project and general information available 4 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 5. Presenters of Pöyry • Knut Sierotzki, Responsible Director for Hydropower Asia and Russia, 25 years experience in water management and hydropower globally, since 1991 also working in SE Asia • René Schmidiger, Senior Project Manager and Dam Expert, 36 years experience in hydropower projects in all continents, since 1992 also working in SE Asia • Dr. Robert Zwahlen, Senior Environmentalist and Biologist, 35 years experience in environmental impact assessments and management projects mainly in the tropics, since 1989 also working in SE Asia, independent expert of World Bank, ADB and other international organisations on environment 5 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 6. GLOBAL EXPERTS IN CONSULTING AND ENGINEERING Pöyry is a global consulting and engineering company dedicated to balanced sustainability and responsible business About 7 000 experts in about 50 countries Project experience in over 100 countries 15 000 projects annually Net sales in 2011 EUR 796 million COPYRIGHT©PÖYRY 6 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 7. ENGINEERING BALANCED SUSTAINABILITY™ • Balanced sustainability is a holistic, multidimensional approach to sustainability that we apply to everything we do. • It strives to achieve a balance between economic, environmental and social dimensions, as most appropriate to the nature of the project and where in the world we are working. • Engineering balanced sustainability™ is about improving resource efficiency. It involves finding solutions to improve energy, water, material and supply chain efficiencies while improving the overall return on investments. 7 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 8. GROUP’S NET SALES IN 2011 Net sales by business group Net sales by region Management Consulting Other 4 (5) % 11 (11) % Energy South America Nordics Water & 26 (25) % 18 (11) % 29 (28) % Environment 11 (12) % North America 4 (4) % Asia 7 (7) % Urban & Mobility 23 (29) % Industry 30 (23) % 38 (45) % Other Europe 8 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 9. PÖYRY – YOUR PREFERRED PARTNER Global network Tradition meets innovation tunnel engineers environmental specialists hydraulic engineers Foundation of Elektrobank in 1895 electrical & mechanical engineers Over 400 hydro civil specialists engineers International activity Range of services On-going projects worldwide Asset valuation Consulting services dam Project development services engineers Design & Engineering Construction Services Electromechanical & rehabilitation services Specialized Services 9 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 10. ...WITH 120 YEARS OF HYDRO EXPERIENCE • 1895: Foundation of Elektrobank in Zurich, Switzerland • 1911: Association of Finnish Steam Boiler Users established (later Fuel and Power Economy) • 1946: Elektrobank’s engineering department becomes Elektro-Watt • 1965: Elektro-Watt becomes Elektrowatt Engineering Services and later Electrowatt Engineering • 1972: Ekono Oy was established by separating the Consulting business from the Finnish Association. • 1993: Jaakko Pöyry Group acquired Ekono’s energy business and continued under name Ekono Energy • 1997: Acquisition of Electrowatt Engineering by the Jaakko Pöyry Group • 1998: Energy business group of Jaakko Pöyry Group operates under name Electrowatt-Ekono • 2004: Acquisition of Verbundplan GmbH by the Jaakko Pöyry Group • 2006: Electrowatt-Ekono and Verbundplan called Pöyry under the Pöyry Group’s rebranding strategy • 2011: Acquisition of SwedPower AB by Pöyry Group 10 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 11. Major Hydropower projects of Pöyry under execution in 2012 Current Projects No. of MW Laja I, Chile 35 Taschinas, Switzerland 11 Thurfeld, Switzerland 2 Deriner, Turkey 670 Ermenek, Turkey 300 Tuirial, India 60 Macchu Piccu II, Peru, 100 Quitaracsa, Peru 112 Rucatayo, Chile, 56 Limberg II PSP, Austria 480 Reisseck II PSP, Austria 430 Uma Oya, Sri Lanka 150 Siah Bishe PSP, Iran 1,000 Rheinfelden, Switzerland 116 Tsankov Kamak, Bulgaria 80 Rudbar-Lorestan, Iran 450 Lehen HPP, Austria 20 Xayaburi, Lao PDR 1,470 Ashta, Albania 90 Beyhani 1, Turkey 550 Karlsdorf Gössendorf, Austria 20 Total capacity under execution 6,202 11 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 12. Nam Ngum 2 Hydroelectric Project, Lao PDR 181 m concrete faced rockfill dam and 615 MW hydropower plant (Francis units) Client South East Asia Energy Ltd., Bangkok Thailand Project Details Dam height 181 m Crest length 510 m Spillway capacity 9,000 m3 Power tunnel 1 x 675 m 3 x 210 m Gross head 164 m Rated discharge 422 m3/s Powerhouse (surface) 3 x 205 MW Scope of Services Independent owner’s engineer - feasibility, tender, detailed design and construction supervision Execution Period 2004 – 2011 12 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 13. FREUDENAU HYDRO POWER PLANT, AUSTRIA Run-of-river power plant with 6 bulb turbines of 30 MW, rated capacity 172 MW Client Österreichische Donaukraftwerke AG Scope of Services • Prefeasibility study • Feasibility study • Engineering design • Tendering and procurement services • Design of backwater area in cooperation with Vienna Metropolitan Administration • Construction and erection supervision • Commissioning Execution Period 1992 – 1998 13 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 14. BIRECIK DAM AND HYDROPOWER PLANT, TURKEY 62.5 m high concrete gravity dam/fill dam with concrete core, 672 MW, 6 Francis turbines Client Ministry of Energy and Natural Resources (DSI), Turkey Scope of Services • Feasibility Study • Final Design • Construction design • Site Management • BOT development • Operation Execution Period 1996 – 2001 14 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 15. NATHPA JHAKRI HYDROPOWER SCHEME, INDIA 1500 MW run-of-river power plant in the Himalayan foothills Client: Nathpa Jhakri Power Corporation Ltd. (NJPC), Shimla, India Scope of Services (1990-2003): • Preparation and review of technical specifications • Review of detailed designs and civil construction drawings • Establishment of quality control procedures • Assistance in solving technical problems during construction • Settlement of claims • Advice on construction methodology and equipment • General project monitoring and management 15 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 16. Kukule Hydropower Plant, Sri Lanka Client: Ceylon Electricity Board Description: • Implementation of a 78 MW run-of- river scheme Scope of Services (1998-2003): • Tender documents and drawings • Assistance in pre-qualification and tender evaluation • Civil engineering drawings • Review of E&M design and documents • Supervision of construction, erection and commissioning 16 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 17. RHEINFELDEN POWER STATION, SWITZERLAND/GERMANY Client Kraftübertragungswerke Rheinfelden AG Project Details Replacement of power plant from 1895 Owners engineer for design of a 116 MW run-of- river scheme to replace existing power plan with 4 bulb turbines a total discharge of 1500 m³/s. Scope of Services • Final Design • Environmental impact assessment and investigations • Assistance to client for receiving the concession from the authorities • Construction Design and Supervision Execution Period 1984 – 1994 2004 – 2011 17 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 18. State of the Art in run-of-river power plants The technology for run-of-river power plants is now about 120 years old. Some of the first schemes were built along the river Rhine between 1895 and 1905. During the last 120 years considerable developments have taken place in technical fields as well as in the sustainability of such schemes. 18 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 19. State of the Art in Run-of-river power plants • The reservoir level has to be kept largely constant (head) and inflowing water is constantly released either through the turbines or the spillway • The water is not stored (except impounding) and therefore the mean daily flow regime of the river is not affected • This is in contrast to high head storage schemes where large volumes of water are stored by means of high dams – storing excess water during the high flow season and releasing water during the low flow season and – accumulating the river flow sediments in the reservoir 19 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 20. State of the Art in run-of-river power plants Today the following main principles are used in the design of the run- of-river power plant: – to built the weir and power structure as flexible as possible allowing the routing of floods, sediments and nutrients directly through the system. – to allow migration of fish and other aquatic animals through or around the dam structure – to have the best available equipment to avoid pollution, to allow downstream fish migration and best use of the energy – to allow for efficient navigation and to support recreation – to satisfy the highest safety standards according national and international norms – to support the general development of a region with the supply of safe, reliable and clean energy 20 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 21. State of the Art in run-of-river power plants Various upstream and down stream fish migration systems e.g. fish lock, fish ladder, natural by-pass channel, fish lift etc. Protection of the area and ban of fishing and hunting in the vicinity of all structures. 21 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 22. State of the Art in run-of-river power plants Fish Friendly Turbine 22 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 23. Fish Friendly Turbines: Mortality of fish passing through turbines Turbine Type Length of Fish 5-10 cm 30-50 cm Francis >50% up to 100% Kaplan 5-10% 15-30% Fish-friendly turbines <5% 5-10% 23 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 24. State of the Art in run-of-river power plants Release of Sediments – Most of the larger run-of-river schemes with dams / weirs larger than about 20m height are equipped with larger bottom outlets for sediment release. Examples: – India, CWC request from public and private developers the use of large bottom outlets is required for the continuous release of sediments during the monsoon period. – China, some large run-of-river dams have sediment outlets e.g Three Gorges – Sudan, Merowe (Nile River), large Sediment outlets were provided – France, CNR will explain in their presentation 24 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 25. MRC design guidelines • The preliminary MRC design guidelines is one of the documents developed for the implementation of the 1995 Mekong Agreement to assure a sustainable development of the Mekong River Basin • The guidelines deal with the following issues: – Navigation lock system – Fish passing facilities – Sediments – Water quality and aquatic ecology – Safety of dams • For downstream countries the issue of sediments and nutrient is of particular interest for the long-term development of the lower Mekong Regions 25 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 26. Xayaburi scheme and other hydro schemes in the Mekong Upstream Hydropower developments: 1. Manwan HPP, 1550 MW, 132 m high dam with seasonal storage 2. Jinghong HPP, 1750 MW, 108 m high dam 3. Nouzhadu HPP, 5850 MW, 261.5 m high dam, multi- annual storage 4. Xiaowan HPP, 4200 MW, 294.5 m dam, multi-annual storage The schemes under development (Xiaowan & Nouzhadu) are storage schemes and will also trap large amounts of sediments to secure the operation of the d/s power plants. Reference: Department of Sedimentation, China Institute of Water Resources Hydropower Research Downstream hydropower Developments: 1. All d/s schemes are run-of-river schemes. 2. None of this schemes have any pond larger then a few hours of operation 3. Dam heights are below 30m 26 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 27. Xayaburi scheme, Overview 27 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 28. Xayaburi scheme, Main Features Country: Lao PDR Location: Xayaburi town, Approximate 80 km south of Luang Prabang Commercial operation: October 2019 (expected) Construction cost: $3.8 billion Owner(s): Xayaburi Power Company Limited (XPCL) Dam and Spillways Height: 32.6 m Length: 820 m Type of spillway: 7 x radial gates, 4 low level outlets Spillway capacity : 47’500 m3/s Pond Capacity : 726 Mio m3, filling time with mean Mekong flow about 50 hours Catchment area: 272,000 km2 Full supply level: 275 m a.s.l. Power station Hydraulic rated head: 18 m Turbines: 7 x 175 MW Kaplan-type, 1 x 60 MW Kaplan-type Maximum capacity: 1,285 MW Energy Production: 7’405 GWh, Export to Thailand 6’985 GWh supplies electricity for 3 Mio people or 750’000 families For Lao PDR 420 GWh supplies electricity for 1 Mio people or 200’000 families 28 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 29. Xayaburi scheme, Construction Sequences Cofferdam completion schedule May 2013 Cofferdam completion schedule May 2013 Stage 1 Intermediate DOWNSTREAM Block completion schedule Jun 2014 River diversion phase 1: construction cofferdams at the right side of the Intermediate block 29 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 30. Xayaburi scheme, Construction Sequences Navigation Lock and Spillway completion schedule Oct 2014 DOWNSTREAM River diversion phase 1: construction Navigation log and spillway 30 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 31. Xayaburi scheme, Construction Sequences Cofferdam removal schedule Oct 2014 Cofferdam removal schedule Oct 2014 Cofferdam completion Cofferdam completion schedule schedule Jun 2015 DOWNSTREAM Jun 2015 River diversion phase 2: construction coffer dam at the left side of the Intermediate block 31 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 32. Xayaburi scheme, Construction Sequences Main structure of Powerhouse & Fish ladder completion DOWNSTREAM schedule Mar 2018 River diversion phase 2: construction coffer dam at the left side of the Intermediate block 32 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 33. Xayaburi scheme, Construction Sequences Cofferdam removal schedule Cofferdam removal schedule Powerhouse Mar 2018 DOWNSTREAM commissioning Mar 2018 Sep 2019 River diversion phase 2: removal coffer dam at the left side of the Intermediate block 33 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 34. Role of Pöyry • Contractual basis: – Consulting Services Agreement for Compliance Review – Between GOL and Pöyry Energy (5. May 2011) • Scope of work: to report on whether – Xayaburi Power Company (Owner) has complied with and satisfied the Mekong River Commission (MRC) Design Guidelines – GOL and the Owner have taken into consideration the comments submitted by the MRC member countries during the Prior Consultation Process – GOL and Owner have complied with the terms of “Prior Consultation Project Review Report on Xayaburi Project”, dated 24 March 2011 – Issues relating to development, construction and implementation of Xayaburi and any discrepancies, conflicts and needs for changes in connection with comments by the riparian countries 34 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 35. Role of Pöyry, Compliance Study Pöyry has performed in 2011 a Compliance Study based on the previous documentation on the following topics. – Following the “Prior Consultation Process” according to the MRC guidelines, the MRC stakeholder countries issued comments on Xayaburi project – Critical comments were raised by Vietnam, Cambodia and Thailand – Main items of concern and potential improvements are: • Retention of sediment • Migration of fish – Pöyry carried out a Compliance Report with the objective to: • Assess comments made by stakeholders and MRC on the current design • Evaluate these comments against the MRC guidelines • Identify points where the current design does not fully follow the MRC guidelines • Propose measures to make the Xayaburi project fully compliant with the MRC guidelines – The Compliance Report was issued to the Government of Lao in August 2011. – Continuous assistance to the Government of Lao to address the technical queries raised. 35 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 36. Main issues raised in the Prior Consultation Process • The main concerns of the riparian countries are: – Trans-boundary issues – Certain impacts not addressed in as great detail as one would like • Sediment trapping • Nutrients • Fishery • Biodiversity • Socio-economic aspects • These concerns can be remedied during the construction stage by: – Additional investigations recommended – Implementation of certain design changes • Providing of flushing gates to allow release of sediments • Improvement of fish pass facilities 36 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 37. Main issues raised in the Prior Consultation Process • Findings MRC Expert Group Safety of Dams – Issues will be taken into account • Findings MRC Expert Group Navigation Lock System – Suggested changes will be introduced • Findings MRC Fishery Expert Group (fish ecology and fishery) – Gaps are identified and recommended actions will be implemented • Findings MRC Fishery Expert Group (fish passage facilities) – Recommendations are reasonable and applicable recommendations will be checked and taken into account 37 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 38. Main issues raised in the Prior Consultation Process • Findings MRC Fishery Expert Group (socio-economics and rural livelihood aspects) – Baseline investigation – Monitoring – Compensation measures • Findings MRC Sediment Expert Group on sediments – Sedimentation during construction – Adaptive management of flushing devices • Uncertainties considering available data • Uncertainties considering future development • Mitigation of sediment concentration peaks 38 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 39. Dam safety • General design principles – State of the art design principles and design methods are being used and which are in line with the size and importance of the project • Overall project safety concept – The concept is being developed in which the different project parts (or elements) will be design according to different criteria, depending on their importance and damage potential. Applies to civil works and also all equipment. • Flood design – Follows internationally accepted concepts • Seismic design – ICOLD guidelines will be followed where project parts will be designed for OBE (operation basis earthquake, 145 yr), DBE (design basis earthquake, 475 yr) and checked against the SEE (safety evaluation earthquake, 10’000 yr), depending on their hazard potential • Design complies with MRC design guidelines 39 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 40. Sediment measures proposed by Pöyry (1) • Main concerns expressed – Reduction of sediment content in Mekong River downstream of Xayaburi – Can have detrimental effects up to Mekong delta in Vietnam – Leading there to costal erosion and intrusion of sea water – Reduction of nutrition content in Mekong River downstream of Xayaburi – Having detrimental effect on fish population – Leading to reduction of fishing yields in River downstream – Negatively affecting downstream population • Current sediment transport regime – The main sediment transport in the river takes place during the high flow season – In the present state the yearly sediment flow in the river is in a stable state, although influenced by the construction of dams in China (see explanations of CNR) 40 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 41. Sediment measures proposed by Pöyry (2) • Basic requirement for sediment transport – Xayaburi dam must be a transparent dam and mimic the natural conditions (see MRC Guidelines) – This means the dam must be capable not to retain and store the sediments, but to release them towards downstream in natural way • Introduction of low level outlets – The original spillway outline design has been adapted by introducing 4 large capacity low level outlets equipped with radial gates – Their dimensions are 12 m (width) and 16 m (height) – Their sill level is 14 m lower than the spillway sill level – The number of the original spillway openings has been reduced by 3 openings and the spillway sill level has been lowered by 2m • Purpose of the low level outlets – The low level outlets will allow, in combination with the spillway, to • route sediment loaded flood flows through the available low level and spillway openings and to • draw down the reservoir and to flush the sediments towards downstream 41 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 42. Sediment measures proposed by Pöyry (3) • Cross section of low level outlet 42 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 43. Sediment measures proposed by Pöyry (4) • Cross section of spillway outlets 43 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 44. Sediments (5) • Longitudinal section along spillway complex, showing both spillway opening and low level openings 252 238 230 44 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 45. Sediment measures proposed by Pöyry (6) • Timing of sediment release – Flood routing will be done during high river flows in the flood flow season – Reservoir flushing will be done also during the flood season primarily during the weekend – The operations will be done in each year in order to mimic close natural conditions • Effect of these operations – These repetitive operations will prevent the excessive accumulation of sediments in the reservoir and which would be lacking in the downstream • Control of sediment concentration – Too high sediment concentrations in the water released through the low level outlets would be detrimental to the river fauna – The sediment concentration will be controlled by combined release operations through the low level outlets (high concentration) and the spillway openings (low concentration) 45 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 46. Sediment measures proposed by Pöyry (7) • Control of effect of these operations – Potential sedimentation in the reservoir will need to be monitored by repetitive bathymetric surveys – Based on these results the flood routing and reservoir flushing operations can be adapted to the current needs – The installed release facilities offer full flexibility in this respect – Monitoring of sediment concentration downstream during flushing operation • Coarse sediments – Will need to be transported by mechanical means (see CNR note) • Conclusion – With the planned sediment release facilities and the intended operation procedures it will be possible to achieve a project facility transparent to sediments – The sediments entering the reservoir will be transferred towards downstream and potential negative effects of lack of sediment there can be reduced to a minimum. 46 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 47. Flow Volume in Mekong River (1) • Main concerns expressed – The current flow volume of the Mekong River would be affected by Xayaburi – There would be less flow in the low flow season – There could be higher flood flows • Principle of run-of-river plant – There will be no seasonal storage of water volumes – The daily inflow into the reservoir corresponds to the daily outflow (see also CNR) • Effect of Xayaburi on downstream river flow conditions – The current flow conditions in the river will therefore virtually not be changed – Minor changes are possible caused by daily variations in the power production (causing reservoir fluctuations up to 30 cm) 47 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 48. Flow Volume in Mekong River (2) – Equally minor changes are to be expected during the weekend, when power production will be reduced – The effect of such changes in the water flow, which can cause water level variations limited to less than one meter, will reduce and finally equalize along the river the further away downstream one gets from the dam – The speed of the downstream water level variations can be controlled by operational measures. There will thus be no sudden water level rises. • Flushing operations – Such operations can affect the downstream water flow for a longer river stretch – But flushing is only planned to be performed in the high flow season, when changes in the river flow are less felt 48 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 49. Environmental and Social Impact Assessment (ESIA) Carried out in 2007 - 2010 – The studies carried out be by the EIA Consultant cover all the aspects which need to be covered for such a project and to comply with GoL requirements – The local environmental law in Lao PDR follows Worldbank/IFC guidelines – The total environmental cost are adequate even some of the total cost are accounted under other topics, e.g. cost for fishpass The environmental studies were approved by GoL on 13 September 2010 Main findings: – Minor impact on local population, limited re-settlement required – Minor impact on fish fauna, Environmental Impact Assessment (EIA) survey only identified limited amount of fish species Improvements recommended for the ESIA: – Additional survey of actual physical conditions, especially on fish species – Additional study on sedimentation 49 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 50. Technical Paper No. 8 by MRC The MRC published the main results of the main fish migration systems in the Lower Mekong Basin. There are three different migration systems: – The Lower Mekong Migration System (LMS) This migration system covers the stretch from the Khone Falls downstream to southern Cambodia, including the Tonle Sap system, and the Mekong Delta in Vietnam. – The Middle Mekong Migration System (MMS) From just above the Khone Falls and upstream to the Loei River, Thailand, the migration patterns are determined by the presence of large tributaries connecting to the Mekong mainstream. – The Upper Mekong Migration System (UMS) The third migration system occurs in the upper section of the river, approximately from the mouth of the Loei River and upstream towards the border between Lao PDR and China (probably continuing into China). Whereas the LMS and the MMS are inter-connected to a large degree, the UMS appears to be relatively isolated, with little “exchange” between the UMS and the other migration systems. These populations should be regarded as separate biological unit. 50 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 51. Technical Paper No. 8 by MRC Main conclusions 1. The LMS and MMS migratory system are playing a crucial role in the fisheries of the Tonle Sap and Mekong delta. 2. The main spawning areas are in the LMS and its tributaries. 3. The UMS is not (or very limited) connected to the other migratory systems and has only significance for the local fisheries in this stretch of the river. 4. The highest biodiversity of the Mekong is in the area downstream the Khone falls in Cambodia. 5. The area between the mouth of the Loei River and the Chinese Border: One of the remarkable species in the UMS is the Giant Mekong Catfish (Pangasianodon gigas). It seems genetically to be a local subspecies which might be separated from the downstream population. 51 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 52. Fish Migrations Mainly two types: • anadromous: adults move upstream for reproduction, young move downstream • catadromous: adults move downstream (for reproduction in the sea), young move upstream Other migrations, over longer or shorter distances, not necessarily related to reproduction. 52 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 53. General effects of HPPs Main impacts of dams on fish migration: • Dams interrupt upstream fish migration • Downstream migrations go mainly through the turbines, with a high risk of injury and mortality • Fish that do not migrate for reproduction can be influenced by fragmentation of the populations (no genetic exchange between populations isolated by dams). 53 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 54. Main Measures Taken Different measures have been developed for maintaining fish populations and migrations, as: • Fish ladders of different types • Fish lifts • Traps combined with transport • Fish hatcheries and artificial restocking of rivers (in cases where migrations could not be maintained and/or other conditions led or contributed to the decrease in fish populations) • Fish friendly turbines (turbines reducing risk of injuring or killing fish) 54 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 55. Fish Hatcheries • Done in cases where barriers (dams) are too high to be passed with a fish ladder • where other conditions (mainly water quality) threaten fish populations • usually done only for economically important species 55 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 56. Limitations • Experience gained so far mainly in North American and European rivers. • Historic targets for measures were mostly Salmonids, i.e. fish which can cope with fast currents and rather high steps. • Recently, fish passes were implemented which are acceptable for a wider range of fish species. • Limited experience with fish passes in large tropical rivers but rapidly growing with the experiences in other countries e.g. Brazil 56 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 57. Fish passing facilities (1) • The present layout of the fish passing facilities comprises the following main structures – facility for upstream migration, – fish passage recording system for upstream migration and – facility for downstream migration • The selected system is very comprehensive and employs a state-of-the-art technology and covers all operational conditions of the scheme • However there are a few issues which need improvement to be in compliance with the MRC design guidelines. 57 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 58. Main Problems Identified • Potentially very high amount of biomass, i.e. a very large number of migrating fish, during certain periods. • High number of species with a very wide range of size. • Therefore different migration requirements, especially concerning manageable flow speed and height of steps. • Limited knowledge of fish migrations (in terms of species, numbers and seasonal distribution) at the project site. 58 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 59. Fish passing facilities (2) The following investigations are recommended: Area influenced by Xayaburi dam 1. During the first stage of the construction: Area influenced by other dams – develop additional baseline data on biology, ecology and livelihood restoration – improve the knowledge concerning the specific requirements of the aquatic fauna on the fish passage facilities 2. Investigations to be done independently from the start of the construction when sufficient data are available and under national or multinational responsibility: – additional investigations on trans-boundary issues on hydrology and baseline investigations (fauna, flora, habitat and socio-economy) – A cumulative impact assessment of the mainstream dams 59 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 60. Fish passing facilities (3) The following design adaptations are recommended: • The fish passage facilities should be amended as follows: – The planned facility should be adapted as follows: • The downstream passage needs to be changed at the inlet and outlet structures • The velocity of the channels needs to be adapted based on the proposed investigations • The head difference between the pools needs to be adapted (too high); this will lead to a longer fish passing facility. – There should be a system provided to allow fish passage during construction – Flexibility allowing later improvements if required 60 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 61. Fish passing facilities (4) – The MRC design guidelines require several independent systems: • The navigation lock should be adapted to serve as a fish lock (also during construction stage) • Space for a fish lift should be prepared 61 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 62. Fish passing facilities (5) 62 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 63. Fish passing facilities (6) Furthermore the following additional measures are recommended: – Fish friendly turbines have been recommended in the feasibility study. The degree of fish friendliness of the turbines should be verified with the envisaged supplier of such turbines. – It is recommended to set-up and operate a fish breeding station for the augmentation of the existing fish population and re-introduction of locally endangered species for release in a suitable river stretch. 63 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 64. Additional Recommendations Given the lack in baseline information, the following is recommended: • Aquatic baseline investigation concerning important habitats, spawning areas, feeding areas, etc. within the future reservoir area. • Fish survey: species inventory, migration patterns, abundance, total fish biomass and larval drift. • Identification of target species which represent whole groups (concerning size and migration patterns, economic importance, etc.); swimming ability and behavioural studies. 64 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 65. Fish Migration and Biomass Study • A study has started which aims at providing additional information on migrations and biomass. • A suitable sampling site was chosen about 1 km d/s of the dam site. • Main method applied is detecting migrating fish by means of hydro sonar; four stations are being used (one fix on each river bank, two mobile ones on boats). • First field campaigns have been carried out end of March / April and • First reports were submitted. 65 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 66. First Results Size of fish migrating upstream (April 2012): April 2012 (left) May 2012 (right) • about 50% 0-20 cm • about 50% 0-20 cm • about 5% > 1 m • about 10% > 1 m, up to 2.2m 66 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 67. First Results (2) 67 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 68. Follow-up Ongoing activities: • Follow-up on studies, monitoring results • Initiation and supervision of implementation of environmental measures on site • Maintaining discussion and exchange of information with relevant stakeholders • Integration of new findings into design of fishway 68 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 69. Main project changes recommended and to be implemented • The following changes will be implemented in the project • A) Sediment transportation – Provision of large capacity low level outlets – Allows passage of the sediments towards downstream during high flow season – The aim is a transparent dam with respect to sediments • B) Fish passage – Fish passing facility in navigation lock • Allows fish passage also during construction period – Adaptation of fish ladder system (step height) depending on findings of baseline studies – Provision of a fish lift (additional) if baseline studies indicate the need for it • C) Navigation locks – Improvements in upstream lock approach area (avoidance of bends) – Changes in lock feeding system (making operation more smooth) 69 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 70. Recommended investigations Investigations to be carried out specifically for Xayaburi (i.e. by the developer) during the construction stage: • Fish survey and related studies for optimising fish pass facility • Additional socio-economic studies on the effects of Xayaburi in the reservoir area and in the downstream proximity • Continuous measurements of flow, water quality and other parameters • Baseline study for sediment content and sediment composition of Mekong river in project area Framework studies to be carried under national or multinational responsibility, independent from the start of the construction: • CIA and trans-boundary assessment of effects of all HPP developments in the Mekong basin (also taking into account effects of planned and operating dams in China). 70 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 71. Ongoing investigation works for the detailed design The following main topics of investigations are on-going or have already been completed: 2010 2011 2012 S/N Investigation Topics Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 1 Seismic investigation 1.1 Geological investigations 2 River quality measurements 3 Hydrological measurements 3.1 River Sedimentation sampling 4 Meteorology measurements 5 Additional ecological studies 5.1 Fish survey 6 Additional social studies 71 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 72. Conclusions by Pöyry • The Compliance Study performed by Pöyry has established those areas where the project was not yet fully in compliance with the MRC preliminary design guidelines • Proposals on actions to be taken to bring the project into full compliance were made • The necessary actions have all been initiated by now and which consist of – Actual changes to the project and its future operation – Additional studies and investigations in areas where knowledge deficits were identified • With these actions taken it can be considered that the project will not have unacceptable negative effects and restrictions on the population living downstream of the project, and therefore also not in the neighboring countries further south • Following this carefully balanced approach the project fulfills the highest standards in accordance with the current State-of-the-Art 72 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang
  • 73. THANK YOU! 73 Xayaburi HPP, Presentation 16 July 2012, Luang Prabang