Seven Basic Steps to
Build Realistic Schedule
    in Project 2010

         B Sai Prasad
  PMP, PMI-SP, MCTS Project 2007,
        MCTS Project 2010
        www.sainivas.com
“Microsoft Project is the enhanced
   version of Microsoft Excel”
               Anonymous




          Seven Steps To Success - Microsoft Project   2
Takeaways
• Forecast scheduling with Project 2010
  1. Realistic
  2. Dynamic
  3. Presentable




                   Seven Steps To Success - Microsoft Project   3
Seven Steps To Success
1.   Enter project information
2.   Create work breakdown structure
3.   Sequence tasks
4.   Estimate resources
5.   Optimize schedule
6.   Baseline schedule
7.   Record Progress

                 Seven Steps To Success - Microsoft Project   4
Step 1: Enter Project Information
Set the project start date
   Don’t: Type project start date in Gantt Chart view.
   Do: Set Project Information in Project ribbon
Set working time, holidays
   Don’t: Change Calendar settings in Options dialog
   Do: Use Change Working time in Project ribbon




                  Seven Steps To Success - Microsoft Project   5
Step 2: Create work breakdown
                structure
 Display project objective and estimates
   Don’t: Insert summary task in Gantt Chart
   Do: Show Project Summary task using Format ribbon
 Add deliverables and detail tasks
   Don’t: Auto schedule tasks, combine tasks into one
   Do: Manually schedule tasks, insert tasks using Task
    ribbon
 Check WBS granularity
   Don’t: Expand/collapse the summary tasks
   Do: Use Outline button in View ribbon
                  Seven Steps To Success - Microsoft Project   6
Step 3: Sequence tasks
 Set dependencies
   Don’t: Enter the task dates, drag the task bar
   Do: Set dependencies using Task forms
 Validate network
   Don’t: Use Gantt Chart view
   Do: Use Task forms, Network diagram in Task ribbon
 Compare top-down and bottom-up estimates
   Don’t: Set constraints on low-level tasks
   Do: Manually schedule summary tasks, auto schedule
    detail tasks
                   Seven Steps To Success - Microsoft Project   7
Step 4: Estimate resources
 Add resource details
   Don’t: Type resource name in Gantt Chart
   Do: Use Resource Sheet in Resource ribbon
 Assign resources
   Don’t: Select resource name in Gantt Chart
   Do: Use Assign Resources, Team planner in Resource
    ribbon
 Fix task duration or work or resource assignment
   Don’t: Change the work or duration
   Do: Use the task type to control the behavior
                  Seven Steps To Success - Microsoft Project   8
Step 5: Optimize schedule
Identify critical path
   Don’t: Have broken critical path
   Do: Check slack, critical path using Format ribbon
Level resources
   Don’t: Use Gantt chart view
   Do: Use Resource Usage, Team planner in
    Resource ribbon



                 Seven Steps To Success - Microsoft Project   9
Step 6: Baseline schedule
Set baseline
   Don’t: Copy the file (or) fields to custom fields
   Do: Set Baseline using Project ribbon
View baseline
   Don’t: Insert columns in view
   Do: Use Baseline table, Show baseline bar using
    Format ribbon



                  Seven Steps To Success - Microsoft Project   10
Step 7: Record progress
 Record actual
   Don’t: Use the Entry table for recording actual
   Do: Use the Tracking table with % complete in Task
    ribbon
 Slippage
   Don’t: Write formula to calculate variance
   Do: Use Slippage of Format ribbon, Variance table
 Report progress
   Don’t: Use the standard reports, copy picture
   Do: Print views, copy timeline view
                  Seven Steps To Success - Microsoft Project   11
Seven Steps To Success
1.   Enter Project Information
2.   Create Work breakdown structure
3.   Sequence tasks
4.   Estimate resources
5.   Optimize schedule
6.   Baseline schedule
7.   Record Progress

                 Seven Steps To Success - Microsoft Project   12
Thank you

Email: sai@sainivas.com
Web: www.sainivas.com



    Seven Steps To Success - Microsoft Project   13

Mais conteúdo relacionado

Mais procurados

Task Tracking in SharePoint
Task Tracking in SharePointTask Tracking in SharePoint
Task Tracking in SharePointBrightWork
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Startedmsprojectpros
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALVismay Shah
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overviewMaher Almohamad
 
MS Project 2016
MS Project 2016MS Project 2016
MS Project 2016Tuan Yang
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training pptglobalp7
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010Ong-Art Sanpinit
 
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraWww.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraYasser Nassr
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMPAndy Pham, PMP
 
Ms project management
Ms  project managementMs  project management
Ms project managementchinunki4
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentationFarrukh Raja
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calenderMaheep Gupta
 
Initialization microsoft project 2010
Initialization microsoft project  2010Initialization microsoft project  2010
Initialization microsoft project 2010Wipro
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project WorkshopEder Alves
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineRaphael Santos
 

Mais procurados (20)

Microsot project basics
Microsot project basicsMicrosot project basics
Microsot project basics
 
Task Tracking in SharePoint
Task Tracking in SharePointTask Tracking in SharePoint
Task Tracking in SharePoint
 
MS Project 2010 Getting Started
MS Project 2010 Getting StartedMS Project 2010 Getting Started
MS Project 2010 Getting Started
 
SharePoint - Stay on Track
SharePoint - Stay on TrackSharePoint - Stay on Track
SharePoint - Stay on Track
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
MICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIALMICROSOFT PROJECT TUTORIAL
MICROSOFT PROJECT TUTORIAL
 
Ms project 2016 overview
Ms project 2016 overviewMs project 2016 overview
Ms project 2016 overview
 
MS Project 2016
MS Project 2016MS Project 2016
MS Project 2016
 
Ms project training ppt
Ms project training pptMs project training ppt
Ms project training ppt
 
How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010How to Create S-Curve by MS Project 2010
How to Create S-Curve by MS Project 2010
 
Ms Project 2010
Ms Project 2010Ms Project 2010
Ms Project 2010
 
Www.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primaveraWww.7aramy kotob.tk-planning.scheduling.using.primavera
Www.7aramy kotob.tk-planning.scheduling.using.primavera
 
4 - Updating Task Progress
4 - Updating Task Progress4 - Updating Task Progress
4 - Updating Task Progress
 
Ms Project 2010 Application For PMP
Ms Project 2010 Application For PMPMs Project 2010 Application For PMP
Ms Project 2010 Application For PMP
 
Ms project management
Ms  project managementMs  project management
Ms project management
 
44259126 ms-project-presentation
44259126 ms-project-presentation44259126 ms-project-presentation
44259126 ms-project-presentation
 
Microsoft project calender
Microsoft project calenderMicrosoft project calender
Microsoft project calender
 
Initialization microsoft project 2010
Initialization microsoft project  2010Initialization microsoft project  2010
Initialization microsoft project 2010
 
Ms Project Workshop
Ms Project WorkshopMs Project Workshop
Ms Project Workshop
 
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project OnlineMPUG Webinar - Creating a Portfolio KPI Report in Project Online
MPUG Webinar - Creating a Portfolio KPI Report in Project Online
 

Semelhante a Seven Basic Steps to Build Realistic Schedule in Project 2010

Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxadampcarr67227
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxhenrymartin15260
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxGracePentinio1
 
5927 ms office project 2007 - managing projects
5927   ms office project 2007 - managing projects5927   ms office project 2007 - managing projects
5927 ms office project 2007 - managing projectsbestip
 
Tableau Course Content.docx
Tableau Course Content.docxTableau Course Content.docx
Tableau Course Content.docxLeotrainings
 
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectQuick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectDeepak Alse
 
Lecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementLecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementSayed Ahmed
 
Project management
Project managementProject management
Project managementnethisip13
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides SlideTeam
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.comWilliamsTaylor33
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioCtatum
 
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Project Partners LLC
 
TaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxTaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxerlindaw
 
Web design process client presentation
Web design process client presentationWeb design process client presentation
Web design process client presentationTroy Philis
 
Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Nguyen Huy Toan
 
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfJoewelDRamirez
 

Semelhante a Seven Basic Steps to Build Realistic Schedule in Project 2010 (20)

Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docxHomework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
Homework 8.docxHomework 8 (50 Points)AssignmentWrite .docx
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docx
 
PRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptxPRIMAVERA P6 manual.pptx
PRIMAVERA P6 manual.pptx
 
5927 ms office project 2007 - managing projects
5927   ms office project 2007 - managing projects5927   ms office project 2007 - managing projects
5927 ms office project 2007 - managing projects
 
WBS PROJECT
WBS PROJECTWBS PROJECT
WBS PROJECT
 
Tableau Course Content.docx
Tableau Course Content.docxTableau Course Content.docx
Tableau Course Content.docx
 
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft ProjectQuick and Easy Guide to Planning & Scheduling with Microsoft Project
Quick and Easy Guide to Planning & Scheduling with Microsoft Project
 
Lecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_managementLecture 05 project_time_and_schedule_management
Lecture 05 project_time_and_schedule_management
 
Project management
Project managementProject management
Project management
 
Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides Initial Project Meeting Agenda PowerPoint Presentation Slides
Initial Project Meeting Agenda PowerPoint Presentation Slides
 
Mgt 402 Success Begins / snaptutorial.com
Mgt 402  Success Begins / snaptutorial.comMgt 402  Success Begins / snaptutorial.com
Mgt 402 Success Begins / snaptutorial.com
 
Ga 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum PortfolioGa 09 G2 Charles Tatum Portfolio
Ga 09 G2 Charles Tatum Portfolio
 
Activity7
Activity7Activity7
Activity7
 
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
Easily Create your Project WBS in MS-Excel with Simple Forward Scheduling usi...
 
TaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docxTaskYou are required to prepare for this Assessment Item by.docx
TaskYou are required to prepare for this Assessment Item by.docx
 
Web design process client presentation
Web design process client presentationWeb design process client presentation
Web design process client presentation
 
9505 (1).doc
9505 (1).doc9505 (1).doc
9505 (1).doc
 
Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1Using the-one-page-project-manager-1233449659402110-1
Using the-one-page-project-manager-1233449659402110-1
 
Using The One Page Project Manager
Using The One Page Project ManagerUsing The One Page Project Manager
Using The One Page Project Manager
 
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdfASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
ASAP_Business_One___Project_Kickoff_Presentation.ppt.pdf
 

Último

"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr BaganFwdays
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embeddingZilliz
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsSergiu Bodiu
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024BookNet Canada
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsMiki Katsuragi
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyAlfredo García Lavilla
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Mark Simos
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clashcharlottematthew16
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek SchlawackFwdays
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubKalema Edgar
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxhariprasad279825
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 

Último (20)

"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan"ML in Production",Oleksandr Bagan
"ML in Production",Oleksandr Bagan
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptxE-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
E-Vehicle_Hacking_by_Parul Sharma_null_owasp.pptx
 
Training state-of-the-art general text embedding
Training state-of-the-art general text embeddingTraining state-of-the-art general text embedding
Training state-of-the-art general text embedding
 
DevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platformsDevEX - reference for building teams, processes, and platforms
DevEX - reference for building teams, processes, and platforms
 
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
New from BookNet Canada for 2024: BNC CataList - Tech Forum 2024
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
Vertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering TipsVertex AI Gemini Prompt Engineering Tips
Vertex AI Gemini Prompt Engineering Tips
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
Commit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easyCommit 2024 - Secret Management made easy
Commit 2024 - Secret Management made easy
 
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
Tampa BSides - Chef's Tour of Microsoft Security Adoption Framework (SAF)
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Powerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time ClashPowerpoint exploring the locations used in television show Time Clash
Powerpoint exploring the locations used in television show Time Clash
 
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
"Subclassing and Composition – A Pythonic Tour of Trade-Offs", Hynek Schlawack
 
Unleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding ClubUnleash Your Potential - Namagunga Girls Coding Club
Unleash Your Potential - Namagunga Girls Coding Club
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Artificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptxArtificial intelligence in cctv survelliance.pptx
Artificial intelligence in cctv survelliance.pptx
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 

Seven Basic Steps to Build Realistic Schedule in Project 2010

  • 1. Seven Basic Steps to Build Realistic Schedule in Project 2010 B Sai Prasad PMP, PMI-SP, MCTS Project 2007, MCTS Project 2010 www.sainivas.com
  • 2. “Microsoft Project is the enhanced version of Microsoft Excel” Anonymous Seven Steps To Success - Microsoft Project 2
  • 3. Takeaways • Forecast scheduling with Project 2010 1. Realistic 2. Dynamic 3. Presentable Seven Steps To Success - Microsoft Project 3
  • 4. Seven Steps To Success 1. Enter project information 2. Create work breakdown structure 3. Sequence tasks 4. Estimate resources 5. Optimize schedule 6. Baseline schedule 7. Record Progress Seven Steps To Success - Microsoft Project 4
  • 5. Step 1: Enter Project Information Set the project start date  Don’t: Type project start date in Gantt Chart view.  Do: Set Project Information in Project ribbon Set working time, holidays  Don’t: Change Calendar settings in Options dialog  Do: Use Change Working time in Project ribbon Seven Steps To Success - Microsoft Project 5
  • 6. Step 2: Create work breakdown structure  Display project objective and estimates  Don’t: Insert summary task in Gantt Chart  Do: Show Project Summary task using Format ribbon  Add deliverables and detail tasks  Don’t: Auto schedule tasks, combine tasks into one  Do: Manually schedule tasks, insert tasks using Task ribbon  Check WBS granularity  Don’t: Expand/collapse the summary tasks  Do: Use Outline button in View ribbon Seven Steps To Success - Microsoft Project 6
  • 7. Step 3: Sequence tasks  Set dependencies  Don’t: Enter the task dates, drag the task bar  Do: Set dependencies using Task forms  Validate network  Don’t: Use Gantt Chart view  Do: Use Task forms, Network diagram in Task ribbon  Compare top-down and bottom-up estimates  Don’t: Set constraints on low-level tasks  Do: Manually schedule summary tasks, auto schedule detail tasks Seven Steps To Success - Microsoft Project 7
  • 8. Step 4: Estimate resources  Add resource details  Don’t: Type resource name in Gantt Chart  Do: Use Resource Sheet in Resource ribbon  Assign resources  Don’t: Select resource name in Gantt Chart  Do: Use Assign Resources, Team planner in Resource ribbon  Fix task duration or work or resource assignment  Don’t: Change the work or duration  Do: Use the task type to control the behavior Seven Steps To Success - Microsoft Project 8
  • 9. Step 5: Optimize schedule Identify critical path  Don’t: Have broken critical path  Do: Check slack, critical path using Format ribbon Level resources  Don’t: Use Gantt chart view  Do: Use Resource Usage, Team planner in Resource ribbon Seven Steps To Success - Microsoft Project 9
  • 10. Step 6: Baseline schedule Set baseline  Don’t: Copy the file (or) fields to custom fields  Do: Set Baseline using Project ribbon View baseline  Don’t: Insert columns in view  Do: Use Baseline table, Show baseline bar using Format ribbon Seven Steps To Success - Microsoft Project 10
  • 11. Step 7: Record progress  Record actual  Don’t: Use the Entry table for recording actual  Do: Use the Tracking table with % complete in Task ribbon  Slippage  Don’t: Write formula to calculate variance  Do: Use Slippage of Format ribbon, Variance table  Report progress  Don’t: Use the standard reports, copy picture  Do: Print views, copy timeline view Seven Steps To Success - Microsoft Project 11
  • 12. Seven Steps To Success 1. Enter Project Information 2. Create Work breakdown structure 3. Sequence tasks 4. Estimate resources 5. Optimize schedule 6. Baseline schedule 7. Record Progress Seven Steps To Success - Microsoft Project 12
  • 13. Thank you Email: sai@sainivas.com Web: www.sainivas.com Seven Steps To Success - Microsoft Project 13