SlideShare uma empresa Scribd logo
1 de 20
Baixar para ler offline
PM World Journal                        Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                               by Bob Prieto
www.pmworldjournal.net                                                         Featured Paper


           Program Tetrahedron – Further Developing the Concept
                                     By Bob Prieto

                                           Fluor
In my earlier paper entitled, “The “Program Tetrahedron”: A Changed Baseline Control
Basis under Strategic Program Management” (Ref. 1), I made the case that the
traditional control of project dynamics described by the project management triangle
(Figure 1) is inadequate when we consider longer project durations such as those
associated with a facility’s complete life cycle.




In addition, while the traditional project triangle shows the need to balance the
competing forces of cost, quality and time, these change significantly in context in large,
complex, multi-project programs. Control bases which traditionally included estimate,
schedules and various definitions of fit for purpose or quality expand to include new
control bases that not only encompass the full facility life cycle but also similar
performance along each of the three bottom lines encompassing the triple bottom line
associated with true sustainability.



© 2013 Bob Prieto                   www.pmworldlibrary.net                        Page 1 of 20
PM World Journal                         Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                by Bob Prieto
www.pmworldjournal.net                                                          Featured Paper


These added control bases were shown to create a program tetrahedron as reflected in
Figure 2.




In this paper I will further develop this thinking, looking closer at some of the
relationships these new control bases create.

Let’s begin by looking at a simplified construct of the proposed tetrahedron in a singular
project context. This is shown in Figure 3 and for simplicity deals with just the first of the
“Triple Bottom Lines”. A project may be defined as being bounded by an initial project
delivery framework encompassing scope, cost, schedule, quality, risk and associated
terms & conditions. In effect, the project framework which we have created represents a
six dimensional space, within which a number of potential project solutions may exist.
Selection of an optimum project “point” or project “space” is discussed later in this paper
and is associated with the relative tightness of constraints along each of the six axis and
the uncertainties associated with project execution methodologies.




© 2013 Bob Prieto                    www.pmworldlibrary.net                         Page 2 of 20
PM World Journal                        Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                               by Bob Prieto
www.pmworldjournal.net                                                         Featured Paper




                                          Figure 3

                                    Project Tetrahedron



One of the comments received on my earlier paper appropriately called attention to the
fact that the equilateral triangle contained in Figure 1 suggested equal weighting along
each of the three dimensions of cost, time and quality. This does not necessarily have
to be the case since it is possible to constrain project execution solutions by imposing
limits along any of the axis contained in this figure or Figure 2. None-the-less the point
is well taken that all control bases do not rise to equal importance in execution of a
project and as such conveying the relative importance or relationships between the
various control bases does add value. Simply put, all project framework elements do not
need to carry equal weighting.

Figure 4 provides a simple illustration of the relationship between control bases. In this
example less cost is associated with a longer schedule and more risk. Seeking to
reduce all three, narrows the range of project execution options potentially available
(enclosed volume is reduced if quality, scope, terms& conditions are held constant) as
we will see shortly.



© 2013 Bob Prieto                   www.pmworldlibrary.net                        Page 3 of 20
PM World Journal                           Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                  by Bob Prieto
www.pmworldjournal.net                                                            Featured Paper




                                             Figure 4

                               Relationship between Control Bases



Figure 5 illustrates what a range of potential project execution solutions might look like
within a “balanced” set of control bases (which I will use for the balance of this paper for
simplicity). A range of project execution approaches exist that will result in initial delivery
of a project within the established project framework. The spherical “boundary” of this
solution set may be thought of as being associated with a confidence level that the
desired set of outputs will be achieved. If this “boundary” limit is associated with say an
80% confidence level we should expect that 80% of the time the resultant project will lie
fully within the boundary conditions associated with each of our control bases.




© 2013 Bob Prieto                      www.pmworldlibrary.net                        Page 4 of 20
PM World Journal                           Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                  by Bob Prieto
www.pmworldjournal.net                                                            Featured Paper




                                             Figure 5

                              Potential Project Execution Solutions

If, however, we seek higher confidence levels or conversely there are execution
parameters with higher levels of uncertainty than what is reflected in Figure 5, we may
find that our universe of project execution solutions run the risk of “leaking” outside our
initial project framework as seen in Figure 6. In many projects full consideration of
uncertainties is often not undertaken and as a result unrealistic expectations meet the
realities that uncertainty often brings.

This is particularly evident in projects who have fallen victim to the so-called “planning
fallacy” and even more commonly in situations where owners have planned and
budgeted on a P50 basis (50% probability of achieving a certain level of cost or
schedule performance) but established performance criteria and measures based on
P80 performance. Disappointment is almost assured.




© 2013 Bob Prieto                      www.pmworldlibrary.net                        Page 5 of 20
PM World Journal                        Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                               by Bob Prieto
www.pmworldjournal.net                                                         Featured Paper




                                          Figure 6

              Potential Project Leakage beyond established Project Framework



Alternately, extremely tight control on project outputs will limit the range of execution
solutions that may exist (within a broader “acceptable” range). Achieving very tight
project outputs, shown in Figure 7 as maximum scope, average quality and least cost,
schedule and risk has a smaller probability of being achieved. The radius of the
contained project execution set relates to the probability of achieving results in the
bounded space.
.




© 2013 Bob Prieto                   www.pmworldlibrary.net                        Page 6 of 20
PM World Journal                          Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                 by Bob Prieto
www.pmworldjournal.net                                                           Featured Paper




                                            Figure 7

                Tight Output Control has a lower Probability of being Achieved

As we move our thinking from a project context to a program context we shift from
control of an initial set of project level outputs typically associated with first delivery of a
project to a set of program level outcomes more traditionally associated with a facility or
capital assets full life cycle. Our project tetrahedron is now replaced by a program
tetrahedron as shown in Figure 8 that incorporates control bases appropriate for this
broadened and lengthened endeavor.

Capital Assets are about more than just first delivery of the project. They are about life
cycle performance. The life cycle framework encompasses achievement of the
organization’s Strategic Business Objectives from a Fit for Purpose Facility within a
defined Business Framework. System performance characteristics include resiliency
and future flexibility. Costs include both CAPEX and OPEX and time represents the
lifetimes achievable by the asset under a range of scenarios.

Table 1 shows how control bases shift as we move from a project to program context.




© 2013 Bob Prieto                     www.pmworldlibrary.net                          Page 7 of 20
PM World Journal                             Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                    by Bob Prieto
www.pmworldjournal.net                                                              Featured Paper




                                             Table 1
                         Shift in Control Bases from Project to Program

Context                             Project                         Program
Framework                           Project Framework (initial      Life Cycle Framework
                                    project delivery)
Tetrahedron                         Project Tetrahedron             Program Tetrahedron

                                            Control Bases
                                    Quality                         Fit for Purpose
                                    Scope                           Strategic Business Objectives
                                    Terms & Conditions              Business framework
                                    Cost                            Life Cycle Cost (CAPEX;
                                                                    OPEX; Other)
                                    Schedule                        Time/Lifetime
                                    Risk                            System Performance




                                               Figure 8

                                       Program Tetrahedron



© 2013 Bob Prieto                        www.pmworldlibrary.net                        Page 8 of 20
PM World Journal                         Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                by Bob Prieto
www.pmworldjournal.net                                                          Featured Paper


Programs bound the individual projects that comprise them. Initial project delivery in an
integral part of achieving overall life cycle objectives and performance. This is shown in
Figure 9. We may alternately consider the Program Tetrahedron as encompassing the
life cycle of a singular project or a collection of projects all contributing to an overall
program outcome. In Figure 10 we see that the relative importance of initial capital
asset delivery and life cycle characteristics will vary. Here, initial delivery is a smaller
part of overall lifecycle performance.




                                           Figure 9

                       Programs Bound the Projects that Comprise them




© 2013 Bob Prieto                    www.pmworldlibrary.net                        Page 9 of 20
PM World Journal                         Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                by Bob Prieto
www.pmworldjournal.net                                                          Featured Paper




                                          Figure 10

     Relative Importance of Initial Project Delivery to Life Cycle Performance Will Vary



Faces of the Tetrahedron
The project and program tetrahedrons each include four “faces” defined by three of the
six dimensions bounding the project or program space. These faces include:

       Project
           o Quality – Scope – Terms & Conditions (Boundary Conditions Face)
           o Cost – Scope – Risk (Cost Face)
           o Schedule – Terms & Conditions – Risk (Time Face)
           o Quality – Cost – Schedule (Performance Face)
       Program
           o Fit for Purpose – Strategic Business Objectives – Business Framework
               (Boundary Conditions Face)
           o Costs – Strategic Business Objectives – System Performance (Investment
               Face)
           o Time – Business Framework – System Performance (Lifetime Face)

© 2013 Bob Prieto                    www.pmworldlibrary.net                       Page 10 of 20
PM World Journal                           Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                  by Bob Prieto
www.pmworldjournal.net                                                            Featured Paper


            o Fit for Purpose – Costs – Time (Performance Face)
Let’s consider each of these four faces in turn.




                                            Figure 11

                                Faces of the Program Tetrahedron

Boundary Conditions Face

The Boundary Conditions Face is defined by the dimensions of quality, scope and terms
& conditions in the case of a project and by analogous dimensions (fit-for-purpose;
strategic business objectives; business framework) in the case of a program
encompassing all aspects and all dimensions of a complete cradle-to-grave life cycle.
In many ways the Boundary Conditions Face defines the nature of the facility asset, its
intended purpose and use, and the business context within which it is intended to
operate. Of all the faces of the Program Tetrahedron it is the one for which the greatest
certainty is required in order to provide the opportunity for efficient project execution and
program performance.
We know from experience that when sufficient clarity does not exist with respect to fit-
for-purpose attributes we can often end up with a BMW 7 Series when a Chevrolet
Spark would suffice.
Similarly, changes in scope and lack of clarity around strategic business objectives to
be accomplished are among the principle drivers of cost and schedule overruns on
projects.



© 2013 Bob Prieto                      www.pmworldlibrary.net                       Page 11 of 20
PM World Journal                         Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                by Bob Prieto
www.pmworldjournal.net                                                          Featured Paper


Finally, a well defined commercial framework is essential for any business enterprise or
project to succeed. It must define the rules of the road, clarify and document
requirements, clearly spell out obligations and responsibilities and identify those factors
which are outside the bounds of the commitments made and therefore subject to further
change or adjustment. These frameworks must be well developed and well applied and
must bind the entirety of the respective organizations.
When the Boundary Conditions Face is sufficiently well developed we find that three of
the critical practices identified by IPA for megaproject success are addressed:

       Clear objectives for the team
       All key owner functions involved in development
       Complete front-end loading (FEL) prior to sanction
Cost or Investment Face

The Cost or Investment Face is defined by the dimensions of cost, scope and risk in the
case of a project and by qualitatively similar dimensions of costs, Strategic Business
Objectives and system performance in the case of a program. The linkage between
scope and cost is easy to understand. Similarly we can see costs (both CAPEX and
OPEX as well as others) are associated with how extensive we define our strategic
business objectives to be. For example capturing 1% of market is likely less costly on a
lifecycle basis than capturing 10%.
As we seek to deliver our chosen scope or achieve our Strategic Business Objectives
we make decisions on the risks that we are willing to undertake. Will the confidence
levels in achieving those SBOs be high enough within the cost or system performance
expectations we have established for ourselves?
Our considerations of system performance must go beyond performance requirements
we might expect to see embedded in or derived from our Strategic Business Objectives
and consider things such as:

       Total system risks including potential “Black Swan” type impacts
       Overall capital asset resiliency
       Asset flexibility to adapt to changed fundamental drivers along the other five
        dimensions
Time or Lifetime Face

The Time or Lifetime Face is defined by the dimensions of schedule, terms & conditions
and risk in the case of a project and by time, business framework and system
performance in the case of a program’s full life cycle performance. The interaction
between time and risk or system performance is the key factor under normal
circumstances on this face.



© 2013 Bob Prieto                    www.pmworldlibrary.net                       Page 12 of 20
PM World Journal                        Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                               by Bob Prieto
www.pmworldjournal.net                                                         Featured Paper


As we execute a project, our remaining risks hopefully decrease over time but our
perceptions of their potential consequences may be favorably or unfavorably changed
as well as our perceptions of our ability to manage them. That static risk “S” curve we
developed at the outset of the project is no longer static (Figure 12). Similarly, from a
programmatic perspective, system performance levels will change over the assets
lifetime in either a planned or unplanned way.




                                         Figure 12

                                    Dynamic “S” Curve

Changed business frameworks, whether internally or externally driven will also modify
our program’s performance over the balance of its lifetime and anticipating, measuring
and managing such shifts are one the key dimensions of any successful asset
management program.
Performance Face

The final face of the Program Tetrahedron is the Performance Face. The Performance
Face is in effect the more familiar Project Management Triangle (Figure 1). It is
bounded by the three dimensions of quality, cost and schedule within the normal project
context and by fit for purpose, costs and time in a life cycle program context. The
tradeoffs considered between these three dimensions are well discussed elsewhere and
in effect go a long way towards determining the return on equity (ROE) for a given
facility investment.


© 2013 Bob Prieto                   www.pmworldlibrary.net                       Page 13 of 20
PM World Journal                        Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                               by Bob Prieto
www.pmworldjournal.net                                                         Featured Paper


I have previously made the point that optimization and at a later stage, management, of
program outcomes requires adequate visibility of key parameters along each of the six
dimensions defining the program tetrahedron but also meaningful measurement that
supports decision making and management action. This means that measurements
along each of the six dimensions are not sufficient. Importantly we must measure the
performance within each face of the Program Tetrahedron. We may think of this
performance within a given face as being related to the projection of the range of
possible project outcomes onto a given face as shown in Figure 13.
                                                                         Universe of Potential Program Outcomes




Program Tetrahedron Face




                                         Projection onto a Program Tetrahedron Face

                                         Figure 13

         Projection of Potential Project Outcomes onto a Program Tetrahedron Face



Performance Measures for Tetrahedron Faces

In the prior sections we looked at six dimensions that allow us to construct a life cycle
focused Program Tetrahedron consisting of four faces. The importance of measuring
factors along each of the six defining dimensions and how decisions, in one or more
dimensions, act to define potential program outcomes and limit or enhance our ability to
achieve them has been discussed. Together these six dimensions define the four
Program Tetrahedron faces:

        Boundary Conditions Face
        Cost or Investment Face
        Time or Lifetime Face

© 2013 Bob Prieto                   www.pmworldlibrary.net                                      Page 14 of 20
PM World Journal                              Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                     by Bob Prieto
www.pmworldjournal.net                                                               Featured Paper


       Performance Face

For each Program Tetrahedron Face it is desirable to define a composite management
level measure to facilitate optimization across multiple dimensions. Table 2 suggests
four such management level measures, three of which are likely to be familiar to the
reader while the fourth is offered for consideration.


                                          Table 2
                      Program Tetrahedron Management Level Measures
Program              Project/        Management      Project Level                      Program Level
Tetrahedron          Program         Level Measure   Interpretation                     Interpretation
Face                 Dimensions

Boundary             Project - Quality,    Return on               For the assets       For the assets
Conditions           Scope, T&C            Assets (ROA)            employed, the        employed, the
Face                 Program - Fit for                             return generated     life cycle return
                     Purpose, SBOs,                                by delivery of a     generated from
                     Business                                      well defined         the optimal
                     Framework                                     project. Poor        matching of
                                                                   scope definition     SBOs, definition
                                                                   acts to degrade      of fit for purpose
                                                                   ROA.                 and anticipated
                                                                                        business
                                                                                        framework.
Cost or              Project – Cost,       Return on               Risk adjusted        Life cycle returns
Investment           Scope, Risk           Investment              return on total      on initial invested
Face                 Program –             (ROI)                   project capital      capital
                     Costs, SBOs,                                  invested (equity     considering all
                     System                                        plus debt).          revenues and
                     Performance                                   Growth in risks      costs (CAPEX,
                                                                   realized, scope      OPEX, other).
                                                                   or project costs     ROI is influenced
                                                                   all act to degrade   not just by
                                                                   ROI.                 effective cost
                                                                                        control but also
                                                                                        appropriate initial
                                                                                        selection of
                                                                                        SBOs and
                                                                                        sustained system
                                                                                        performance
                                                                                        which includes
                                                                                        considerations
                                                                                        related to
                                                                                        resiliency and
                                                                                        flexibility in
                                                                                        addition to more
                                                                                        traditional

© 2013 Bob Prieto                         www.pmworldlibrary.net                              Page 15 of 20
PM World Journal                             Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                    by Bob Prieto
www.pmworldjournal.net                                                              Featured Paper


                                                                                        system
                                                                                        performance
                                                                                        criteria.
Time or              Project –            Return on Time          This is a             In a life cycle
Lifetime Face        Schedule, T&C,       (ROT)                   measure of the        context, return
                     Risk                 (Suggested new          effectiveness of      on time relates to
                     Program –            management              reducing              achieving an
                     Time, Business       level                   controllable risks    appropriate
                     Framework,           measurement)            associated with       facility lifetime.
                     System                                       initial delivery of   This
                     Performance                                  a project. Many       determination of
                                                                  risks are linked      lifetime is related
                                                                  to “exposure          to many factors
                                                                  time” such as         but a key driver
                                                                  weather,              is the ability to
                                                                  escalation and        sustain adequate
                                                                  so forth.             performance
                                                                  Conversely,           levels over time.
                                                                  imprudent
                                                                  schedule
                                                                  compression can
                                                                  create new risks
                                                                  or amplify
                                                                  existing ones.
Performance          Project –            Return on               In the traditional    In a program
Face                 Quality, Cost,       Equity (ROE)            Project Triangle,     context the
                     Schedule                                     ROE reflects          tradeoffs are
                     Program - Fit for                            delivery of           similar to the
                     Purpose, Costs,                              “appropriate”         project context
                     Time                                         (that is, as          but here fit for
                                                                  contracted for)       purpose takes on
                                                                  quality levels        a deeper and
                                                                  while getting the     more important
                                                                  balance of cost       role while time is
                                                                  and schedule          more
                                                                  right to maximize     representative of
                                                                  return on equity      the productive
                                                                  investments.          and profitable
                                                                  ROE recognizes        lifetime of the
                                                                  that extended         capital facility
                                                                  schedules carry       asset. The longer
                                                                  a financing and       the assets
                                                                  escalation cost       profitable period
                                                                  while schedules       of operation, the
                                                                  too short may         greater the ROE
                                                                  carry quality         we should
                                                                  risks and             expect.
                                                                  premium costs.


© 2013 Bob Prieto                        www.pmworldlibrary.net                               Page 16 of 20
PM World Journal                          Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                 by Bob Prieto
www.pmworldjournal.net                                                           Featured Paper


Holistic Application

While the discussion to this point has been focused very much around economic
performance of a program through its cradle to grave life cycle, the application of the
program tetrahedron is much broader. In an earlier paper, “Application of Life Cycle
Analysis in the Capital Assets Industry”, published in this publications predecessor, I
stress the importance of considering not only an assets complete life cycle but also its
performance across each of the three bottom lines encompassing the Triple Bottom
Line. The Program Tetrahedron model, further developed here, lends itself to such an
extension as can be seen in Figure 14.




                                           Figure 14

                            Triple Bottom Line Program Tetrahedron




© 2013 Bob Prieto                     www.pmworldlibrary.net                       Page 17 of 20
PM World Journal                          Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                 by Bob Prieto
www.pmworldjournal.net                                                           Featured Paper


Table 3 shows how management measures are expanded when a Triple Bottom Line
perspective is applied utilizing the Program Tetrahedron model.


                                             Table 3
                            Triple Bottom Line Management Measures
                                              Management Level Measure
Program                    Economic Bottom       Environmental       Social Bottom Line
Tetrahedron Face           Line                  Bottom Line

Boundary                   Return on Assets       Environmental Quality   Social Responsibility
Conditions Face            (ROA)
Cost or Investment         Return on              Return on Mitigation    Return on Effort
Face                       Investment (ROI)
Time or Lifetime           Return on Time         Return on Time          Return on Time
Face                       (ROT)
                           (Suggested new
                           management level
                           measurement)
Performance Face           Return on Equity       Return on               Societal Performance
                           (ROE)                  Environment             (Productivity, Quality
                                                                          of Life, Standard of
                                                                          Living)


Conclusion

The earlier paper on the Program Tetrahedron broadened the discussion of program
performance from:

       Delivery to a cradle to grave life cycle
       Life cycle costing to whole life costing where revenue, all life cycle direct costs
        and all indirect costs are considered
       Economic performance to performance against all three of the bottom lines
        comprising the Triple Bottom Line
The range of dimensions in which we must optimize was expanded and the notion of
project solution sets being associated with confidence levels introduced.
This paper further develops each of these concepts and extends consideration of the
Program Tetrahedron to a focus on the meaning of the faces created. Finally
performance measures along each of these three Bottom lines are suggested and the
reader encouraged to comment since this is still very much a work in progress.




© 2013 Bob Prieto                     www.pmworldlibrary.net                         Page 18 of 20
PM World Journal                         Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                by Bob Prieto
www.pmworldjournal.net                                                          Featured Paper


References
1. The “Program Tetrahedron”: A Changed Baseline Control Basis under Strategic Program
   Management; PM World Journal; November 2012

2. Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March
   2012

3. Stakeholder Management in Large Engineering & Construction Programs; PM World Today;
   October 2011

4. Sustainability on Large, Complex Engineering & Construction Programs Utilizing a Program
   Management Approach; PM World Today; July 2011

5. Project Selection in Large Engineering Construction Programs; PM World Today; June 2011




© 2013 Bob Prieto                    www.pmworldlibrary.net                        Page 19 of 20
PM World Journal                           Program Tetrahedron – Further Developing the Concept
Vol. II, Issue II – February 2013                                                  by Bob Prieto
www.pmworldjournal.net                                                            Featured Paper


About the Author



                               Bob Prieto
                               Senior Vice President

                               Fluor




                              Bob Prieto is a senior vice president of Fluor, one of the largest,
publicly traded engineering and construction companies in the world. He is responsible for
strategy for the firm’s Industrial & Infrastructure group which focuses on the development and
delivery of large, complex projects worldwide. The group encompasses three major business
lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and
Manufacturing and Life Sciences. Bob consults with owner’s of large engineering & construction
capital construction programs across all market sectors in the development of programmatic
delivery strategies encompassing planning, engineering, procurement, construction and
financing. He is author of “Strategic Program Management” and “The Giga Factor: Program
Management in the Engineering and Construction Industry” published by the Construction
Management Association of America (CMAA) and “Topics in Strategic Program Management”
as well as over 400 other papers and presentations.

Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and
a Fellow of the Construction Management Association of America. Bob served until 2006 as one
of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC)
Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to
shape the framework for trade and economic growth and had previously served as both as
Chairman of the Engineering and Construction Governors of the World Economic Forum and
co-chair of the infrastructure task force formed after September 11th by the New York City
Chamber of Commerce.

Previously, he established a 20-year record of building and sustaining global revenue and
earnings growth as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading
engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com.




© 2013 Bob Prieto                      www.pmworldlibrary.net                        Page 20 of 20

Mais conteúdo relacionado

Semelhante a Program tetrahedron further development

Program Tetrahedron
Program TetrahedronProgram Tetrahedron
Program TetrahedronBob Prieto
 
Managing the planning fallacy
Managing the planning fallacyManaging the planning fallacy
Managing the planning fallacyBob Prieto
 
Complexity in large engineering & construction programs
Complexity in large engineering & construction programsComplexity in large engineering & construction programs
Complexity in large engineering & construction programsBob Prieto
 
Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value BehaviorBob Prieto
 
The gigaprogram challenge
The gigaprogram challengeThe gigaprogram challenge
The gigaprogram challengeBob Prieto
 
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET Journal
 
Is it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryIs it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryBob Prieto
 
Project categorization and assessment
Project categorization and assessmentProject categorization and assessment
Project categorization and assessmentBob Prieto
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxtoltonkendal
 
A Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningA Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningJohn Goodpasture
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty ParadoxHKA
 
Coursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalCoursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalTimothy Adrian Lam
 
Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Bob Prieto
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Abdulrahman Ismail
 
Project SizingNo two projects are the same. Projects vary va.docx
Project SizingNo two projects are the same. Projects vary va.docxProject SizingNo two projects are the same. Projects vary va.docx
Project SizingNo two projects are the same. Projects vary va.docxwoodruffeloisa
 

Semelhante a Program tetrahedron further development (20)

Program Tetrahedron
Program TetrahedronProgram Tetrahedron
Program Tetrahedron
 
Managing the planning fallacy
Managing the planning fallacyManaging the planning fallacy
Managing the planning fallacy
 
Complexity in large engineering & construction programs
Complexity in large engineering & construction programsComplexity in large engineering & construction programs
Complexity in large engineering & construction programs
 
P070 a simple_view_of_complexity
P070 a simple_view_of_complexityP070 a simple_view_of_complexity
P070 a simple_view_of_complexity
 
Generalized Analysis Value Behavior
Generalized Analysis Value BehaviorGeneralized Analysis Value Behavior
Generalized Analysis Value Behavior
 
The gigaprogram challenge
The gigaprogram challengeThe gigaprogram challenge
The gigaprogram challenge
 
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A ReviewIRJET- Fuzzy Logic in Construction Project Scheduling: A Review
IRJET- Fuzzy Logic in Construction Project Scheduling: A Review
 
Is it time to rethink project managemnt theory
Is it time to rethink project managemnt theoryIs it time to rethink project managemnt theory
Is it time to rethink project managemnt theory
 
Project categorization and assessment
Project categorization and assessmentProject categorization and assessment
Project categorization and assessment
 
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docxRUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
RUNNING HEAD PROJECT SCHEDULE1PROJECT SCHEDULE5Instr.docx
 
A Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave PlanningA Risk Perspective -- Rolling Wave Planning
A Risk Perspective -- Rolling Wave Planning
 
The Programme Certainty Paradox
The Programme Certainty ParadoxThe Programme Certainty Paradox
The Programme Certainty Paradox
 
Project Management
Project ManagementProject Management
Project Management
 
Coursework 5 - IS Project Management Final
Coursework 5 - IS Project Management FinalCoursework 5 - IS Project Management Final
Coursework 5 - IS Project Management Final
 
Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...Application of system life cycle processes to large complex engineering and c...
Application of system life cycle processes to large complex engineering and c...
 
Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3Theory of Management of Large Complex Projects - Chapter 3
Theory of Management of Large Complex Projects - Chapter 3
 
Pm in noisy environments
Pm in noisy environmentsPm in noisy environments
Pm in noisy environments
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014Estimate costs in fragile and transitional contexts - July - 2014
Estimate costs in fragile and transitional contexts - July - 2014
 
Project SizingNo two projects are the same. Projects vary va.docx
Project SizingNo two projects are the same. Projects vary va.docxProject SizingNo two projects are the same. Projects vary va.docx
Project SizingNo two projects are the same. Projects vary va.docx
 

Mais de Bob Prieto

Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startupBob Prieto
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projectsBob Prieto
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projectsBob Prieto
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programsBob Prieto
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryBob Prieto
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface ManagementBob Prieto
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsBob Prieto
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global WarmingBob Prieto
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project successBob Prieto
 
Large complex project success
Large complex project successLarge complex project success
Large complex project successBob Prieto
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Bob Prieto
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under UncertaintyBob Prieto
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasBob Prieto
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentBob Prieto
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Bob Prieto
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Bob Prieto
 

Mais de Bob Prieto (20)

Engineering and construction project startup
Engineering and construction project startupEngineering and construction project startup
Engineering and construction project startup
 
Deeper look at the physics of projects
Deeper look at the physics of projectsDeeper look at the physics of projects
Deeper look at the physics of projects
 
Systems nature of large complex projects
Systems nature of large complex projectsSystems nature of large complex projects
Systems nature of large complex projects
 
Governance of mega and giga programs
Governance of mega and giga programsGovernance of mega and giga programs
Governance of mega and giga programs
 
Strengthen outcome based capital project delivery
Strengthen outcome based capital project deliveryStrengthen outcome based capital project delivery
Strengthen outcome based capital project delivery
 
Rethinking Interface Management
Rethinking Interface ManagementRethinking Interface Management
Rethinking Interface Management
 
Rework in Engineering & Construction Projects
Rework in Engineering & Construction ProjectsRework in Engineering & Construction Projects
Rework in Engineering & Construction Projects
 
Reversing Global Warming
Reversing Global WarmingReversing Global Warming
Reversing Global Warming
 
Improving infrastructure project success
Improving infrastructure project successImproving infrastructure project success
Improving infrastructure project success
 
Large complex project success
Large complex project successLarge complex project success
Large complex project success
 
Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects Impact of correlation on risks in programs and projects
Impact of correlation on risks in programs and projects
 
Decision Making Under Uncertainty
Decision Making Under UncertaintyDecision Making Under Uncertainty
Decision Making Under Uncertainty
 
Post Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the BahamasPost Dorian Engineering & Construction in the Bahamas
Post Dorian Engineering & Construction in the Bahamas
 
Debating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environmentDebating project decisions in an ai enabled environment
Debating project decisions in an ai enabled environment
 
Chapters 11 12 13
Chapters 11  12  13Chapters 11  12  13
Chapters 11 12 13
 
Chapter 10
Chapter 10Chapter 10
Chapter 10
 
Chapter 9
Chapter 9Chapter 9
Chapter 9
 
Chapter 8
Chapter 8Chapter 8
Chapter 8
 
Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7Theory of Management of Large Complex Projects - Chapter 7
Theory of Management of Large Complex Projects - Chapter 7
 
Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6Theory of Management of Large Complex Projects - Chapter 6
Theory of Management of Large Complex Projects - Chapter 6
 

Último

Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...Operational Excellence Consulting
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOne Monitar
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxShruti Mittal
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifeBhavana Pujan Kendra
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024Adnet Communications
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsGOKUL JS
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfDanny Diep To
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Associazione Digital Days
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environmentelijahj01012
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesDoe Paoro
 

Último (20)

Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
The McKinsey 7S Framework: A Holistic Approach to Harmonizing All Parts of th...
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring CapabilitiesOnemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
Onemonitar Android Spy App Features: Explore Advanced Monitoring Capabilities
 
business environment micro environment macro environment.pptx
business environment micro environment macro environment.pptxbusiness environment micro environment macro environment.pptx
business environment micro environment macro environment.pptx
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 
Planetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in LifePlanetary and Vedic Yagyas Bring Positive Impacts in Life
Planetary and Vedic Yagyas Bring Positive Impacts in Life
 
TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024TriStar Gold Corporate Presentation - April 2024
TriStar Gold Corporate Presentation - April 2024
 
Supercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebsSupercharge Your eCommerce Stores-acowebs
Supercharge Your eCommerce Stores-acowebs
 
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdfGUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
GUIDELINES ON USEFUL FORMS IN FREIGHT FORWARDING (F) Danny Diep Toh MBA.pdf
 
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
Lucia Ferretti, Lead Business Designer; Matteo Meschini, Business Designer @T...
 
Cyber Security Training in Office Environment
Cyber Security Training in Office EnvironmentCyber Security Training in Office Environment
Cyber Security Training in Office Environment
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
Unveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic ExperiencesUnveiling the Soundscape Music for Psychedelic Experiences
Unveiling the Soundscape Music for Psychedelic Experiences
 

Program tetrahedron further development

  • 1. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Program Tetrahedron – Further Developing the Concept By Bob Prieto Fluor In my earlier paper entitled, “The “Program Tetrahedron”: A Changed Baseline Control Basis under Strategic Program Management” (Ref. 1), I made the case that the traditional control of project dynamics described by the project management triangle (Figure 1) is inadequate when we consider longer project durations such as those associated with a facility’s complete life cycle. In addition, while the traditional project triangle shows the need to balance the competing forces of cost, quality and time, these change significantly in context in large, complex, multi-project programs. Control bases which traditionally included estimate, schedules and various definitions of fit for purpose or quality expand to include new control bases that not only encompass the full facility life cycle but also similar performance along each of the three bottom lines encompassing the triple bottom line associated with true sustainability. © 2013 Bob Prieto www.pmworldlibrary.net Page 1 of 20
  • 2. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper These added control bases were shown to create a program tetrahedron as reflected in Figure 2. In this paper I will further develop this thinking, looking closer at some of the relationships these new control bases create. Let’s begin by looking at a simplified construct of the proposed tetrahedron in a singular project context. This is shown in Figure 3 and for simplicity deals with just the first of the “Triple Bottom Lines”. A project may be defined as being bounded by an initial project delivery framework encompassing scope, cost, schedule, quality, risk and associated terms & conditions. In effect, the project framework which we have created represents a six dimensional space, within which a number of potential project solutions may exist. Selection of an optimum project “point” or project “space” is discussed later in this paper and is associated with the relative tightness of constraints along each of the six axis and the uncertainties associated with project execution methodologies. © 2013 Bob Prieto www.pmworldlibrary.net Page 2 of 20
  • 3. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 3 Project Tetrahedron One of the comments received on my earlier paper appropriately called attention to the fact that the equilateral triangle contained in Figure 1 suggested equal weighting along each of the three dimensions of cost, time and quality. This does not necessarily have to be the case since it is possible to constrain project execution solutions by imposing limits along any of the axis contained in this figure or Figure 2. None-the-less the point is well taken that all control bases do not rise to equal importance in execution of a project and as such conveying the relative importance or relationships between the various control bases does add value. Simply put, all project framework elements do not need to carry equal weighting. Figure 4 provides a simple illustration of the relationship between control bases. In this example less cost is associated with a longer schedule and more risk. Seeking to reduce all three, narrows the range of project execution options potentially available (enclosed volume is reduced if quality, scope, terms& conditions are held constant) as we will see shortly. © 2013 Bob Prieto www.pmworldlibrary.net Page 3 of 20
  • 4. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 4 Relationship between Control Bases Figure 5 illustrates what a range of potential project execution solutions might look like within a “balanced” set of control bases (which I will use for the balance of this paper for simplicity). A range of project execution approaches exist that will result in initial delivery of a project within the established project framework. The spherical “boundary” of this solution set may be thought of as being associated with a confidence level that the desired set of outputs will be achieved. If this “boundary” limit is associated with say an 80% confidence level we should expect that 80% of the time the resultant project will lie fully within the boundary conditions associated with each of our control bases. © 2013 Bob Prieto www.pmworldlibrary.net Page 4 of 20
  • 5. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 5 Potential Project Execution Solutions If, however, we seek higher confidence levels or conversely there are execution parameters with higher levels of uncertainty than what is reflected in Figure 5, we may find that our universe of project execution solutions run the risk of “leaking” outside our initial project framework as seen in Figure 6. In many projects full consideration of uncertainties is often not undertaken and as a result unrealistic expectations meet the realities that uncertainty often brings. This is particularly evident in projects who have fallen victim to the so-called “planning fallacy” and even more commonly in situations where owners have planned and budgeted on a P50 basis (50% probability of achieving a certain level of cost or schedule performance) but established performance criteria and measures based on P80 performance. Disappointment is almost assured. © 2013 Bob Prieto www.pmworldlibrary.net Page 5 of 20
  • 6. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 6 Potential Project Leakage beyond established Project Framework Alternately, extremely tight control on project outputs will limit the range of execution solutions that may exist (within a broader “acceptable” range). Achieving very tight project outputs, shown in Figure 7 as maximum scope, average quality and least cost, schedule and risk has a smaller probability of being achieved. The radius of the contained project execution set relates to the probability of achieving results in the bounded space. . © 2013 Bob Prieto www.pmworldlibrary.net Page 6 of 20
  • 7. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 7 Tight Output Control has a lower Probability of being Achieved As we move our thinking from a project context to a program context we shift from control of an initial set of project level outputs typically associated with first delivery of a project to a set of program level outcomes more traditionally associated with a facility or capital assets full life cycle. Our project tetrahedron is now replaced by a program tetrahedron as shown in Figure 8 that incorporates control bases appropriate for this broadened and lengthened endeavor. Capital Assets are about more than just first delivery of the project. They are about life cycle performance. The life cycle framework encompasses achievement of the organization’s Strategic Business Objectives from a Fit for Purpose Facility within a defined Business Framework. System performance characteristics include resiliency and future flexibility. Costs include both CAPEX and OPEX and time represents the lifetimes achievable by the asset under a range of scenarios. Table 1 shows how control bases shift as we move from a project to program context. © 2013 Bob Prieto www.pmworldlibrary.net Page 7 of 20
  • 8. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Table 1 Shift in Control Bases from Project to Program Context Project Program Framework Project Framework (initial Life Cycle Framework project delivery) Tetrahedron Project Tetrahedron Program Tetrahedron Control Bases Quality Fit for Purpose Scope Strategic Business Objectives Terms & Conditions Business framework Cost Life Cycle Cost (CAPEX; OPEX; Other) Schedule Time/Lifetime Risk System Performance Figure 8 Program Tetrahedron © 2013 Bob Prieto www.pmworldlibrary.net Page 8 of 20
  • 9. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Programs bound the individual projects that comprise them. Initial project delivery in an integral part of achieving overall life cycle objectives and performance. This is shown in Figure 9. We may alternately consider the Program Tetrahedron as encompassing the life cycle of a singular project or a collection of projects all contributing to an overall program outcome. In Figure 10 we see that the relative importance of initial capital asset delivery and life cycle characteristics will vary. Here, initial delivery is a smaller part of overall lifecycle performance. Figure 9 Programs Bound the Projects that Comprise them © 2013 Bob Prieto www.pmworldlibrary.net Page 9 of 20
  • 10. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Figure 10 Relative Importance of Initial Project Delivery to Life Cycle Performance Will Vary Faces of the Tetrahedron The project and program tetrahedrons each include four “faces” defined by three of the six dimensions bounding the project or program space. These faces include:  Project o Quality – Scope – Terms & Conditions (Boundary Conditions Face) o Cost – Scope – Risk (Cost Face) o Schedule – Terms & Conditions – Risk (Time Face) o Quality – Cost – Schedule (Performance Face)  Program o Fit for Purpose – Strategic Business Objectives – Business Framework (Boundary Conditions Face) o Costs – Strategic Business Objectives – System Performance (Investment Face) o Time – Business Framework – System Performance (Lifetime Face) © 2013 Bob Prieto www.pmworldlibrary.net Page 10 of 20
  • 11. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper o Fit for Purpose – Costs – Time (Performance Face) Let’s consider each of these four faces in turn. Figure 11 Faces of the Program Tetrahedron Boundary Conditions Face The Boundary Conditions Face is defined by the dimensions of quality, scope and terms & conditions in the case of a project and by analogous dimensions (fit-for-purpose; strategic business objectives; business framework) in the case of a program encompassing all aspects and all dimensions of a complete cradle-to-grave life cycle. In many ways the Boundary Conditions Face defines the nature of the facility asset, its intended purpose and use, and the business context within which it is intended to operate. Of all the faces of the Program Tetrahedron it is the one for which the greatest certainty is required in order to provide the opportunity for efficient project execution and program performance. We know from experience that when sufficient clarity does not exist with respect to fit- for-purpose attributes we can often end up with a BMW 7 Series when a Chevrolet Spark would suffice. Similarly, changes in scope and lack of clarity around strategic business objectives to be accomplished are among the principle drivers of cost and schedule overruns on projects. © 2013 Bob Prieto www.pmworldlibrary.net Page 11 of 20
  • 12. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Finally, a well defined commercial framework is essential for any business enterprise or project to succeed. It must define the rules of the road, clarify and document requirements, clearly spell out obligations and responsibilities and identify those factors which are outside the bounds of the commitments made and therefore subject to further change or adjustment. These frameworks must be well developed and well applied and must bind the entirety of the respective organizations. When the Boundary Conditions Face is sufficiently well developed we find that three of the critical practices identified by IPA for megaproject success are addressed:  Clear objectives for the team  All key owner functions involved in development  Complete front-end loading (FEL) prior to sanction Cost or Investment Face The Cost or Investment Face is defined by the dimensions of cost, scope and risk in the case of a project and by qualitatively similar dimensions of costs, Strategic Business Objectives and system performance in the case of a program. The linkage between scope and cost is easy to understand. Similarly we can see costs (both CAPEX and OPEX as well as others) are associated with how extensive we define our strategic business objectives to be. For example capturing 1% of market is likely less costly on a lifecycle basis than capturing 10%. As we seek to deliver our chosen scope or achieve our Strategic Business Objectives we make decisions on the risks that we are willing to undertake. Will the confidence levels in achieving those SBOs be high enough within the cost or system performance expectations we have established for ourselves? Our considerations of system performance must go beyond performance requirements we might expect to see embedded in or derived from our Strategic Business Objectives and consider things such as:  Total system risks including potential “Black Swan” type impacts  Overall capital asset resiliency  Asset flexibility to adapt to changed fundamental drivers along the other five dimensions Time or Lifetime Face The Time or Lifetime Face is defined by the dimensions of schedule, terms & conditions and risk in the case of a project and by time, business framework and system performance in the case of a program’s full life cycle performance. The interaction between time and risk or system performance is the key factor under normal circumstances on this face. © 2013 Bob Prieto www.pmworldlibrary.net Page 12 of 20
  • 13. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper As we execute a project, our remaining risks hopefully decrease over time but our perceptions of their potential consequences may be favorably or unfavorably changed as well as our perceptions of our ability to manage them. That static risk “S” curve we developed at the outset of the project is no longer static (Figure 12). Similarly, from a programmatic perspective, system performance levels will change over the assets lifetime in either a planned or unplanned way. Figure 12 Dynamic “S” Curve Changed business frameworks, whether internally or externally driven will also modify our program’s performance over the balance of its lifetime and anticipating, measuring and managing such shifts are one the key dimensions of any successful asset management program. Performance Face The final face of the Program Tetrahedron is the Performance Face. The Performance Face is in effect the more familiar Project Management Triangle (Figure 1). It is bounded by the three dimensions of quality, cost and schedule within the normal project context and by fit for purpose, costs and time in a life cycle program context. The tradeoffs considered between these three dimensions are well discussed elsewhere and in effect go a long way towards determining the return on equity (ROE) for a given facility investment. © 2013 Bob Prieto www.pmworldlibrary.net Page 13 of 20
  • 14. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper I have previously made the point that optimization and at a later stage, management, of program outcomes requires adequate visibility of key parameters along each of the six dimensions defining the program tetrahedron but also meaningful measurement that supports decision making and management action. This means that measurements along each of the six dimensions are not sufficient. Importantly we must measure the performance within each face of the Program Tetrahedron. We may think of this performance within a given face as being related to the projection of the range of possible project outcomes onto a given face as shown in Figure 13. Universe of Potential Program Outcomes Program Tetrahedron Face Projection onto a Program Tetrahedron Face Figure 13 Projection of Potential Project Outcomes onto a Program Tetrahedron Face Performance Measures for Tetrahedron Faces In the prior sections we looked at six dimensions that allow us to construct a life cycle focused Program Tetrahedron consisting of four faces. The importance of measuring factors along each of the six defining dimensions and how decisions, in one or more dimensions, act to define potential program outcomes and limit or enhance our ability to achieve them has been discussed. Together these six dimensions define the four Program Tetrahedron faces:  Boundary Conditions Face  Cost or Investment Face  Time or Lifetime Face © 2013 Bob Prieto www.pmworldlibrary.net Page 14 of 20
  • 15. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper  Performance Face For each Program Tetrahedron Face it is desirable to define a composite management level measure to facilitate optimization across multiple dimensions. Table 2 suggests four such management level measures, three of which are likely to be familiar to the reader while the fourth is offered for consideration. Table 2 Program Tetrahedron Management Level Measures Program Project/ Management Project Level Program Level Tetrahedron Program Level Measure Interpretation Interpretation Face Dimensions Boundary Project - Quality, Return on For the assets For the assets Conditions Scope, T&C Assets (ROA) employed, the employed, the Face Program - Fit for return generated life cycle return Purpose, SBOs, by delivery of a generated from Business well defined the optimal Framework project. Poor matching of scope definition SBOs, definition acts to degrade of fit for purpose ROA. and anticipated business framework. Cost or Project – Cost, Return on Risk adjusted Life cycle returns Investment Scope, Risk Investment return on total on initial invested Face Program – (ROI) project capital capital Costs, SBOs, invested (equity considering all System plus debt). revenues and Performance Growth in risks costs (CAPEX, realized, scope OPEX, other). or project costs ROI is influenced all act to degrade not just by ROI. effective cost control but also appropriate initial selection of SBOs and sustained system performance which includes considerations related to resiliency and flexibility in addition to more traditional © 2013 Bob Prieto www.pmworldlibrary.net Page 15 of 20
  • 16. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper system performance criteria. Time or Project – Return on Time This is a In a life cycle Lifetime Face Schedule, T&C, (ROT) measure of the context, return Risk (Suggested new effectiveness of on time relates to Program – management reducing achieving an Time, Business level controllable risks appropriate Framework, measurement) associated with facility lifetime. System initial delivery of This Performance a project. Many determination of risks are linked lifetime is related to “exposure to many factors time” such as but a key driver weather, is the ability to escalation and sustain adequate so forth. performance Conversely, levels over time. imprudent schedule compression can create new risks or amplify existing ones. Performance Project – Return on In the traditional In a program Face Quality, Cost, Equity (ROE) Project Triangle, context the Schedule ROE reflects tradeoffs are Program - Fit for delivery of similar to the Purpose, Costs, “appropriate” project context Time (that is, as but here fit for contracted for) purpose takes on quality levels a deeper and while getting the more important balance of cost role while time is and schedule more right to maximize representative of return on equity the productive investments. and profitable ROE recognizes lifetime of the that extended capital facility schedules carry asset. The longer a financing and the assets escalation cost profitable period while schedules of operation, the too short may greater the ROE carry quality we should risks and expect. premium costs. © 2013 Bob Prieto www.pmworldlibrary.net Page 16 of 20
  • 17. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Holistic Application While the discussion to this point has been focused very much around economic performance of a program through its cradle to grave life cycle, the application of the program tetrahedron is much broader. In an earlier paper, “Application of Life Cycle Analysis in the Capital Assets Industry”, published in this publications predecessor, I stress the importance of considering not only an assets complete life cycle but also its performance across each of the three bottom lines encompassing the Triple Bottom Line. The Program Tetrahedron model, further developed here, lends itself to such an extension as can be seen in Figure 14. Figure 14 Triple Bottom Line Program Tetrahedron © 2013 Bob Prieto www.pmworldlibrary.net Page 17 of 20
  • 18. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper Table 3 shows how management measures are expanded when a Triple Bottom Line perspective is applied utilizing the Program Tetrahedron model. Table 3 Triple Bottom Line Management Measures Management Level Measure Program Economic Bottom Environmental Social Bottom Line Tetrahedron Face Line Bottom Line Boundary Return on Assets Environmental Quality Social Responsibility Conditions Face (ROA) Cost or Investment Return on Return on Mitigation Return on Effort Face Investment (ROI) Time or Lifetime Return on Time Return on Time Return on Time Face (ROT) (Suggested new management level measurement) Performance Face Return on Equity Return on Societal Performance (ROE) Environment (Productivity, Quality of Life, Standard of Living) Conclusion The earlier paper on the Program Tetrahedron broadened the discussion of program performance from:  Delivery to a cradle to grave life cycle  Life cycle costing to whole life costing where revenue, all life cycle direct costs and all indirect costs are considered  Economic performance to performance against all three of the bottom lines comprising the Triple Bottom Line The range of dimensions in which we must optimize was expanded and the notion of project solution sets being associated with confidence levels introduced. This paper further develops each of these concepts and extends consideration of the Program Tetrahedron to a focus on the meaning of the faces created. Finally performance measures along each of these three Bottom lines are suggested and the reader encouraged to comment since this is still very much a work in progress. © 2013 Bob Prieto www.pmworldlibrary.net Page 18 of 20
  • 19. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper References 1. The “Program Tetrahedron”: A Changed Baseline Control Basis under Strategic Program Management; PM World Journal; November 2012 2. Application of Life Cycle Analysis in the Capital Assets Industry; PM World Today; March 2012 3. Stakeholder Management in Large Engineering & Construction Programs; PM World Today; October 2011 4. Sustainability on Large, Complex Engineering & Construction Programs Utilizing a Program Management Approach; PM World Today; July 2011 5. Project Selection in Large Engineering Construction Programs; PM World Today; June 2011 © 2013 Bob Prieto www.pmworldlibrary.net Page 19 of 20
  • 20. PM World Journal Program Tetrahedron – Further Developing the Concept Vol. II, Issue II – February 2013 by Bob Prieto www.pmworldjournal.net Featured Paper About the Author Bob Prieto Senior Vice President Fluor Bob Prieto is a senior vice president of Fluor, one of the largest, publicly traded engineering and construction companies in the world. He is responsible for strategy for the firm’s Industrial & Infrastructure group which focuses on the development and delivery of large, complex projects worldwide. The group encompasses three major business lines including Infrastructure, with an emphasis on Public Private Partnerships; Mining; and Manufacturing and Life Sciences. Bob consults with owner’s of large engineering & construction capital construction programs across all market sectors in the development of programmatic delivery strategies encompassing planning, engineering, procurement, construction and financing. He is author of “Strategic Program Management” and “The Giga Factor: Program Management in the Engineering and Construction Industry” published by the Construction Management Association of America (CMAA) and “Topics in Strategic Program Management” as well as over 400 other papers and presentations. Bob is a member of the ASCE Industry Leaders Council, National Academy of Construction and a Fellow of the Construction Management Association of America. Bob served until 2006 as one of three U.S. presidential appointees to the Asia Pacific Economic Cooperation (APEC) Business Advisory Council (ABAC), working with U.S. and Asia-Pacific business leaders to shape the framework for trade and economic growth and had previously served as both as Chairman of the Engineering and Construction Governors of the World Economic Forum and co-chair of the infrastructure task force formed after September 11th by the New York City Chamber of Commerce. Previously, he established a 20-year record of building and sustaining global revenue and earnings growth as Chairman at Parsons Brinckerhoff (PB), one of the world’s leading engineering companies. Bob Prieto can be contacted at Bob.Prieto@fluor.com. © 2013 Bob Prieto www.pmworldlibrary.net Page 20 of 20