SlideShare uma empresa Scribd logo
1 de 32
Earned Value Management
Drexel University, Goodwin College CT431-120 Project Management
R. Gottardi, Instructor/Author                                    May 31, 2009
Some Definitions
• Planned Value, PV (BCWS): the portion
  of the approved total cost estimate during
  a given period
• Actual Cost, AC: the total of the direct &
  indirect costs incurred in accomplishing
  work on a task or project during a given
  period
                                               2
Project Tracking without Earned Value
                                         Project Performance

                                                      BCWS      Actual Cost


              200
              180
              160
              140
              120
$000




              100
              80
              60
              40
              20
               0
                     1    2    3    4         5        6            7         8     9     10    11    12
       BCWS          10   20   25   40        62       80           98        125   137   149   160   175
       Actual Cost   30   48   52   55        60       65           70        72
                                                            Weeks


       Conclusion: It looks like we are under budget. What’s missing?
                                                                                                            3
What’s Missing
• Any measure of how much work has been
  accomplished
• Earned Value: an estimate of the value of
  the physical work actually completed
• Can be
  – currency, e.g., $
  – Quantities, e.g., tons, yds3, SF, etc.
  – Any agreed upon value for the tasks
                                             4
How Can We Measure Progress?
• % complete of the tasks’ durations
• Rate of performance (RP): % complete actual/%
  compete planned
• Physical quantities (works for some tasks but not
  others)
   –   Tons of earth moved
   –   Cubic yards of cement poured
   –   Floors completed
   –   Sq ft completed
• Let’s use RP because it is common to many tasks &
  gives us a schedule related measure
                                                      5
Establish Earning Rules
Rule         Credit at Start         Credit at End

0/100                          0%                    100%

50/50                          50%                   50%

25/75                          25%                   75%

20/80                          20%                   80%

  Credit means the budgeted cost of work
    performed is included in the earned value
    calculation to the extent of the % indicated.
                                                            6
Earned Value Vs. Planned Value
                                      Project Performance

                                      PV(BCWS)   EV(BCWP)


           200
           180
           160
           140
           120
$000




                                                                            Schedule Variance
           100
                                                                            Behind Schedule
            80
            60
            40
            20
             0
                  1    2    3    4          5       6            7    8        9        10      11    12
       PV(BCWS)   10   20   25   40        62       80           98   125     137      149      160   175
       EV(BCWP)   28   60   62   70        72       80           82   92
                                                         Weeks


                                                                                                            7
Earned Value vs. Actual Cost
                                         Project Performance

                                                    Actual Cost     EV(BCWP)


             100
              90
                                                                                    Cost Variance ($)
              80                                                                    Under Budget
              70
              60
$000




              50
              40
              30
              20
              10
               0
                     1    2    3    4         5        6            7          8    9         10        11   12
       Actual Cost   30   48   52   55        60       65           70         72
       EV(BCWP)      28   60   62   70        72       80           82         92
                                                            Weeks

                                                                                                              8
Combine All Variables
                                            Project Performance

                                            PV(BCWS)        AC(Actual Cost)        EV(BCWP)


                  200
                  180
                  160
                                                                                                          PV
                  140
                  120
$000




                  100
                                                                                               EV
                  80
                  60                                                                AC
                  40
                  20
                   0
                         1    2    3    4              5          6           7           8         9          10    11    12

       PV(BCWS)          10   20   25   40             62        80           98         125        137        149   160   175
       AC(Actual Cost)   30   48   52   55             60        65           70          72
       EV(BCWP)          28   60   62   70             72        80           82          92
                                                                      Weeks
                                                                                                                                9
Variance Computations
•   Cost Variance (CV)=EV-AC
•   Schedule Variance (SV)=EV-PV
•   Negative values are unfavorable
•   Positive values are favorable



                                      10
Performance Indices
• Cost Performance Index (CPI)=EV/AC
• Schedule Performance Index
  (SPI)=EV/PV
• <1= unfavorable
• >1=favorable


                                       11
Earned Value
• Integrates schedule & cost data
• Explains causes of variances
• Encourages objective measurement of
  progress
• Measures performance


                                        12
Problem
• Given:
  • EV = $5,000
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                   13
Problem
• Given:
  • EV = $5,000 = Earned Value
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI
                                 14
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        15
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                        16
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         17
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV =
  •   SV =
  •   CPI =
  •   SPI =
                                         18
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC
  •   SV =
  •   CPI =
  •   SPI =
                                         19
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000
  •   SV =
  •   CPI =
  •   SPI =
                                         20
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV =
  •   CPI =
  •   SPI =
                                            21
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV
  •   CPI =
  •   SPI =
                                            22
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000
  •   CPI =
  •   SPI =
                                            23
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI =
  •   SPI =
                                            24
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC
  •   SPI =
                                            25
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000
  •   SPI =
                                            26
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI =
                                            27
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV
                                            28
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BSWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000
                                            29
Problem
• Given:
  • EV = $5,000 = Earned Value = BCWP
  • PV = $10,000 = Planned Value =BCWS
  • AC = $15,000 = Actual Cost
• Solve:
  •   CV = EV-AC = 5,000-15,000 = -10,000
  •   SV = EV-PV = 5,000-10,000 = -5,000
  •   CPI = EV/AC = 5,000/15,000 = .33
  •   SPI = EV/PV = 5,000/10,000 = .5
                                            30
Other Terms & Computations
• BAC: Budget at Completion: The
  original total budget for a project
• EAC: Estimate at Completion =
  BAC/CPI (CPI = Cost Performance Index)
• ETC: Estimate to Complete: EAC-AC
• Variance at Completion: BAC-EAC

                                       31
Earned Value
•   Title: Earned Value Management
•   Filename: Earned Value Management Lecture 2009eMY31
•   Author: Ron Gottardi
•   Author Affiliation: Drexel University, Goodwin College of
    Professional Studies
•   Course: CT431-120 Project management
•   Date: May 31, 2009
•   Copyright 2009 Ron Gottardi




                                                                32

Mais conteúdo relacionado

Destaque

AmyandSusan
AmyandSusanAmyandSusan
AmyandSusansgrobins
 
Question 3 – what have you learnt from
Question 3 – what have you learnt fromQuestion 3 – what have you learnt from
Question 3 – what have you learnt fromnushy1993
 
Focusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the VulnerabilitiesFocusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the VulnerabilitiesRoger Johnston
 
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"PerformanceIN
 
01 introduction E-Commerce
01 introduction E-Commerce01 introduction E-Commerce
01 introduction E-CommerceNirbhay Singh
 
Google Ground Kiajánló
Google Ground KiajánlóGoogle Ground Kiajánló
Google Ground Kiajánlópontrendezveny
 
XING Q3 report 2012 english version
XING Q3 report 2012 english versionXING Q3 report 2012 english version
XING Q3 report 2012 english versionXING SE
 
205180 cm with jde
205180 cm with jde205180 cm with jde
205180 cm with jdep6academy
 

Destaque (19)

Wxig points update
Wxig points updateWxig points update
Wxig points update
 
AmyandSusan
AmyandSusanAmyandSusan
AmyandSusan
 
Hugps138
Hugps138Hugps138
Hugps138
 
Question 3 – what have you learnt from
Question 3 – what have you learnt fromQuestion 3 – what have you learnt from
Question 3 – what have you learnt from
 
No tlp Polisi
No tlp PolisiNo tlp Polisi
No tlp Polisi
 
SGGSWU Prospectus 2016-17
SGGSWU Prospectus 2016-17SGGSWU Prospectus 2016-17
SGGSWU Prospectus 2016-17
 
VW Santana Vista - Brochure
VW Santana Vista - BrochureVW Santana Vista - Brochure
VW Santana Vista - Brochure
 
33559
3355933559
33559
 
Focusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the VulnerabilitiesFocusing on the Threats to the Detriment of the Vulnerabilities
Focusing on the Threats to the Detriment of the Vulnerabilities
 
Freefixer log
Freefixer logFreefixer log
Freefixer log
 
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
Create - Day 2 - 11:15 - "Six Secrets to Overcoming Social Marketing Hurdles"
 
Oppa (13)
Oppa (13)Oppa (13)
Oppa (13)
 
The Anatomy Of The Idea
The Anatomy Of The IdeaThe Anatomy Of The Idea
The Anatomy Of The Idea
 
01 introduction E-Commerce
01 introduction E-Commerce01 introduction E-Commerce
01 introduction E-Commerce
 
Jft 13-desktop-optical-power-meter-jfopt
Jft 13-desktop-optical-power-meter-jfoptJft 13-desktop-optical-power-meter-jfopt
Jft 13-desktop-optical-power-meter-jfopt
 
Google Ground Kiajánló
Google Ground KiajánlóGoogle Ground Kiajánló
Google Ground Kiajánló
 
Unit 1 the universe
Unit 1 the universeUnit 1 the universe
Unit 1 the universe
 
XING Q3 report 2012 english version
XING Q3 report 2012 english versionXING Q3 report 2012 english version
XING Q3 report 2012 english version
 
205180 cm with jde
205180 cm with jde205180 cm with jde
205180 cm with jde
 

Semelhante a Earned value management lecture 2009e my31

SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARKSPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARKSPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARKSPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARKTsuyoshi Horigome
 
Free SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARKFree SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARKSPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARKSPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARKSPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARKSPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARKTsuyoshi Horigome
 
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARKTsuyoshi Horigome
 
Schedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateSchedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateGlen Alleman
 
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARKSPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARKTsuyoshi Horigome
 

Semelhante a Earned value management lecture 2009e my31 (20)

SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8004-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8117 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARKSPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
SPICE MODEL of TPC8A02-H (Professional+ZDSP Model) in SPICE PARK
 
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPCA8014 (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPCM8002-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARKSPICE MODEL of RN1417 in SPICE PARK
SPICE MODEL of RN1417 in SPICE PARK
 
SPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARKSPICE MODEL of RN1114FT in SPICE PARK
SPICE MODEL of RN1114FT in SPICE PARK
 
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARKSPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Professional+BDP Model) in SPICE PARK
 
Free SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARKFree SPICE Model of S3K60 in SPICE PARK
Free SPICE Model of S3K60 in SPICE PARK
 
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARKSPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of 2SK3906 (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARKSPICE MODEL of RN1107FS in SPICE PARK
SPICE MODEL of RN1107FS in SPICE PARK
 
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8032-H (Standard+BDS Model) in SPICE PARK
 
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARKSPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
SPICE MODEL of 2SK3435 (Professional+BDP Model) in SPICE PARK
 
SPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARKSPICE MODEL of DTC123JM in SPICE PARK
SPICE MODEL of DTC123JM in SPICE PARK
 
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARKSPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
SPICE MODEL of TPC8110 (Standard+BDS Model) in SPICE PARK
 
Schedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year lateSchedule variance = 0 and we’re a year late
Schedule variance = 0 and we’re a year late
 
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARKSPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
SPICE MODEL of TPCA8014-H (Professional+BDSP Model) in SPICE PARK
 

Último

NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFChandresh Chudasama
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...ssuserf63bd7
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCRashishs7044
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...ictsugar
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchirictsugar
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxsaniyaimamuddin
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessSeta Wicaksana
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africaictsugar
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Riya Pathan
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfShashank Mehta
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfJos Voskuil
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditNhtLNguyn9
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Americas Got Grants
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 

Último (20)

NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Guide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDFGuide Complete Set of Residential Architectural Drawings PDF
Guide Complete Set of Residential Architectural Drawings PDF
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...International Business Environments and Operations 16th Global Edition test b...
International Business Environments and Operations 16th Global Edition test b...
 
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
8447779800, Low rate Call girls in Uttam Nagar Delhi NCR
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...Global Scenario On Sustainable  and Resilient Coconut Industry by Dr. Jelfina...
Global Scenario On Sustainable and Resilient Coconut Industry by Dr. Jelfina...
 
Marketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent ChirchirMarketplace and Quality Assurance Presentation - Vincent Chirchir
Marketplace and Quality Assurance Presentation - Vincent Chirchir
 
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptxFinancial-Statement-Analysis-of-Coca-cola-Company.pptx
Financial-Statement-Analysis-of-Coca-cola-Company.pptx
 
Organizational Structure Running A Successful Business
Organizational Structure Running A Successful BusinessOrganizational Structure Running A Successful Business
Organizational Structure Running A Successful Business
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Kenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby AfricaKenya’s Coconut Value Chain by Gatsby Africa
Kenya’s Coconut Value Chain by Gatsby Africa
 
Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737Independent Call Girls Andheri Nightlaila 9967584737
Independent Call Girls Andheri Nightlaila 9967584737
 
Darshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdfDarshan Hiranandani [News About Next CEO].pdf
Darshan Hiranandani [News About Next CEO].pdf
 
Digital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdfDigital Transformation in the PLM domain - distrib.pdf
Digital Transformation in the PLM domain - distrib.pdf
 
Chapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal auditChapter 9 PPT 4th edition.pdf internal audit
Chapter 9 PPT 4th edition.pdf internal audit
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...Church Building Grants To Assist With New Construction, Additions, And Restor...
Church Building Grants To Assist With New Construction, Additions, And Restor...
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 

Earned value management lecture 2009e my31

  • 1. Earned Value Management Drexel University, Goodwin College CT431-120 Project Management R. Gottardi, Instructor/Author May 31, 2009
  • 2. Some Definitions • Planned Value, PV (BCWS): the portion of the approved total cost estimate during a given period • Actual Cost, AC: the total of the direct & indirect costs incurred in accomplishing work on a task or project during a given period 2
  • 3. Project Tracking without Earned Value Project Performance BCWS Actual Cost 200 180 160 140 120 $000 100 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 BCWS 10 20 25 40 62 80 98 125 137 149 160 175 Actual Cost 30 48 52 55 60 65 70 72 Weeks Conclusion: It looks like we are under budget. What’s missing? 3
  • 4. What’s Missing • Any measure of how much work has been accomplished • Earned Value: an estimate of the value of the physical work actually completed • Can be – currency, e.g., $ – Quantities, e.g., tons, yds3, SF, etc. – Any agreed upon value for the tasks 4
  • 5. How Can We Measure Progress? • % complete of the tasks’ durations • Rate of performance (RP): % complete actual/% compete planned • Physical quantities (works for some tasks but not others) – Tons of earth moved – Cubic yards of cement poured – Floors completed – Sq ft completed • Let’s use RP because it is common to many tasks & gives us a schedule related measure 5
  • 6. Establish Earning Rules Rule Credit at Start Credit at End 0/100 0% 100% 50/50 50% 50% 25/75 25% 75% 20/80 20% 80% Credit means the budgeted cost of work performed is included in the earned value calculation to the extent of the % indicated. 6
  • 7. Earned Value Vs. Planned Value Project Performance PV(BCWS) EV(BCWP) 200 180 160 140 120 $000 Schedule Variance 100 Behind Schedule 80 60 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 7
  • 8. Earned Value vs. Actual Cost Project Performance Actual Cost EV(BCWP) 100 90 Cost Variance ($) 80 Under Budget 70 60 $000 50 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 Actual Cost 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 8
  • 9. Combine All Variables Project Performance PV(BCWS) AC(Actual Cost) EV(BCWP) 200 180 160 PV 140 120 $000 100 EV 80 60 AC 40 20 0 1 2 3 4 5 6 7 8 9 10 11 12 PV(BCWS) 10 20 25 40 62 80 98 125 137 149 160 175 AC(Actual Cost) 30 48 52 55 60 65 70 72 EV(BCWP) 28 60 62 70 72 80 82 92 Weeks 9
  • 10. Variance Computations • Cost Variance (CV)=EV-AC • Schedule Variance (SV)=EV-PV • Negative values are unfavorable • Positive values are favorable 10
  • 11. Performance Indices • Cost Performance Index (CPI)=EV/AC • Schedule Performance Index (SPI)=EV/PV • <1= unfavorable • >1=favorable 11
  • 12. Earned Value • Integrates schedule & cost data • Explains causes of variances • Encourages objective measurement of progress • Measures performance 12
  • 13. Problem • Given: • EV = $5,000 • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 13
  • 14. Problem • Given: • EV = $5,000 = Earned Value • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI 14
  • 15. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 15
  • 16. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 16
  • 17. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 • Solve: • CV = • SV = • CPI = • SPI = 17
  • 18. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = • SV = • CPI = • SPI = 18
  • 19. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC • SV = • CPI = • SPI = 19
  • 20. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 • SV = • CPI = • SPI = 20
  • 21. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = • CPI = • SPI = 21
  • 22. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV • CPI = • SPI = 22
  • 23. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 • CPI = • SPI = 23
  • 24. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = • SPI = 24
  • 25. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC • SPI = 25
  • 26. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 • SPI = 26
  • 27. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = 27
  • 28. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV 28
  • 29. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BSWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 29
  • 30. Problem • Given: • EV = $5,000 = Earned Value = BCWP • PV = $10,000 = Planned Value =BCWS • AC = $15,000 = Actual Cost • Solve: • CV = EV-AC = 5,000-15,000 = -10,000 • SV = EV-PV = 5,000-10,000 = -5,000 • CPI = EV/AC = 5,000/15,000 = .33 • SPI = EV/PV = 5,000/10,000 = .5 30
  • 31. Other Terms & Computations • BAC: Budget at Completion: The original total budget for a project • EAC: Estimate at Completion = BAC/CPI (CPI = Cost Performance Index) • ETC: Estimate to Complete: EAC-AC • Variance at Completion: BAC-EAC 31
  • 32. Earned Value • Title: Earned Value Management • Filename: Earned Value Management Lecture 2009eMY31 • Author: Ron Gottardi • Author Affiliation: Drexel University, Goodwin College of Professional Studies • Course: CT431-120 Project management • Date: May 31, 2009 • Copyright 2009 Ron Gottardi 32