MAG-ASAWANG TUBIG
 MULTI-PURPOSE PROJECT
                  o    Flood Control
                  o    Hydro-Energy Power
                  o    Irrigation
                  o    Water Resource


          Presented by:
HON. RODOLFO G. VALENCIA
           Representative,
  First District, Oriental Mindoro

                                            Research and Study by:
                                     K4 Oriental Mindoro Council, Inc.
                                            NICO P. VALENCIA
                                                   President
. . . AND WE ARE THE CAUSE
. . .WE POLLUTE THE AIR
. . .WE FILL THE LAND WITH WASTE
WE CUT THE TREES ….
WE DID NOT PROTECT AND PRESERVE
OUR ENVIRONMENT
AND WHAT ARE THE
CONSEQUENCES?

OUR CITIES ARE FLOODING
OUR LAKES ARE DRYING UP
MANY SPECIES ARE FACING THE
  THREAT OF EXTINCTION
TYPHOONS
AND OTHER
CALAMITIES ARE
INTENSIFYING




   TIDAL WAVE IN INDONESIA   EARTHQUAKE IN HAITI
TSUNAMI IN JAPAN
IN THE PHILIPPINES. . .
   WE FACE THE SAME ENVIRONMENTAL PROBLEMS
     CAUSED BY NATURAL DISASTERS. . .




          . . . TYPHOONS
Typhoon “Milenyo” was the strongest typhoon that hit
Metro Manila and Bicol in September 29, 2006.
Typhoon “Reming” devastated Albay in November 2006.
Typhoon “Ondoy” was a Disaster to Metro Manila.
September 26, 2009
Typhoon “Peping” was the caused of landslide in Baguio.
Floods in Northern Luzon. September 30, 2009
Typhoon “Pedring” submerged Roxas Boulevard.
September 27, 2011.
Typhoon “Sendong” was a Disaster to Cagayan de Oro.
December 19, 2011
Typhoon “Sendong” was earlier forecasted to hit
Oriental Mindoro. By God’s grace, Mindoro was spared
Damage Caused:
      Massive tragedy to Cagayan de Oro, Iligan City
      Death Toll reached 2000.
ORIENTAL MINDORO
     IS NOT EXEMPTED TO
           NATURAL DISASTERS. . .




             TYPHOONS. . .
               . . . FLOODS
1993
1994
DISASTER
Oriental Mindoro among 10 most
flood-prone areas in RP, says DENR
January 26, 2010
Top ten flood prone
Provinces:

1. Pampanga
2. Nueva Ecija
3. Pangasinan
4. Tarlac
5. Maguindanao
6. Bulacan
7. Metro Manila
8. North Cotabato
9. Oriental Mindoro
10. Ilocos Norte
Three Floods Hit Oriental Mindoro in December, 2005
   December 7, 17, and 27
Floods leave trail of devastation in Naujan
January 19, 2010




14,000
affected by
floods
in Naujan
December 13, 2010
MINDORO POSTS
Deluge: The Sinking Philippines – Floods
Submerge Oriental Mindoro and Parts of Visayas
Intermittent         rains
triggered flooding in
Oriental Mindoro and
several       areas     in
Visayas, forcing at least
395 individuals to flee
their      homes       on
Tuesday, the National
Disaster Risk Reduction
and          Management
Council (NDRRMC) said
Wednesday.       Southern
Luzon and portions of
the Visayas experienced
rains over the past two
days due to the presence
of an active low pressure
area       (LPA)     near
Palawan, and another
one east of southern
Mindanao –
ABS-CBN
100 Katutubong Mangyan, nagsilikas dahil
sa banta ng baha.
GMA News
Low-lying Calapan City, two other towns in
Or. Mindoro to sink in flood 10-yr. time
                              CALAPAN CITY – In about ten
                              years time, this capital city of
                              Oriental Mindoro and two of its
                              neighboring low-lying towns will
                              submerge in three to seven-
                              meter deep water should a
                              rainfall in a magnitude of what
                              Typhoon “Ondoy” brought to
                              Metro Manila occurs, unless
                              “engineering interventions” be
                              done by the government.
                              This alarming scenario was
                              brought to open by Oriental
                              Mindoro          First       District
                              Congressman          Rodolfo      G.
                              Valencia in a press conference
                              here last March 26 as he detailed
                              the recent findings of Norwegian
                              Agency       for       Development
                              Cooperation (NORAD) regarding
                              the present topographic situation
                              of the province.
OVERFLOWING OF MAG-ASAWANG TUBIG RIVER CAUSED MOST OF THE
FLOODING IN THE AREAS OF CALAPAN CITY, NAUJAN, VICTORIA , AND
PARTIALLY BACO.
SERIES OF STUDIES, CONSULTATION AND COORDINATIVE MEETINGS WERE
UNDERTAKEN IN THE PAST 30 YEARS -   NO POSITIVE RESULT




             GABION DIKES ARE TEMPORARY SOLUTIONS.
              NOT EFFECTIVE IN MOST AREAS.
RECHANNELING SOLUTIONS:
  BUCAYAO RIVER RECHANNELING,
  A PROJECT OF CONG. RGV THRU DPWH
  (P20 MILLION)
  COMPLETED 2006.
RESULT: A PARTIAL SOLUTION TO
THE FLOODING OF CALAPAN CITY.
DREDGING AND REHABILITATION
Oriental Mindoro starts anti-flood plan
The Philippine Star, March 30, 2008

CALAPAN CITY – Rep. Rodolfo Valencia of Oriental Mindoro’s 1st
District was able to secure latest model of dredging equipment
from Finland worth P70 Million. DPWH Sec. H. Ebdane approved
the award to First District of Oriental Mindoro.

RESULT:
A PARTIAL SOLUTION.
CLEARING OF
CALAPAN RIVER
AND OTHER
WATERWAYS IN THE
FIRST DISTRICT.
WHY DO WE HAVE
FLOODS
IN THE FIRST DISTRICT OF
ORIENTAL MINDORO?
THIS IS THE ISLAND OF MINDORO . . .




     TOPOGRAPHY
THE FLOW OF WATERS DIVIDES THE ISLAND OF MINDORO . . .




 A RAINFALL IN OCCIDENTAL MINDORO DRAINS TO THE LEFT.
 A RAINFALL IN ORIENTAL MINDORO DRAINS TO THE RIGHT.
BODIES OF WATER IS FORMED IN THE UPLAND OVER TIME

    Satellite
 Image from
   October,
       1999



      Aerial
Photography
        from
 2009, same
         area
ANOTHER UPLAND AREA
    Satellite
 Image from
   October,
       1999




      Aerial
Photography
        from
 2009, same
         area
THESE WATERS FLOW TO THE LOWLAND BY FALLS, RIVERS
MOST RIVERS ARE IN THE WATERSHED AREAS OF THE ISLAND

  And most
Watersheds
                               1508 km2
  are in the                    (14.26 %)
 North East                                 355 km2
   Mindoro                                  (3.36%)

       Area


It comprises               8709 km2
                            (82.37 %)
   17.62% of
  the area of
   the whole
     island of
    Mindoro.
THERE ARE FEW BIG RIVERS IN THE WATERSHED AREAS

   Blue lines
   show the
major water
flows in the
    Mindoro
Watersheds.
                  BUCAYAO
Waters from       RIVER
  the upland
    area flow
 through the
major rivers:
Mag-asawng
  Tubig River                      MAG-ASAWANG
and Bucayao                        TUBIG RIVER
       River.
RIVERS CHANGE FLOW OVER TIME . . .
    1. River migrate,
       meander and
     shortcut bends.

      2. Earthquakes,
          rainfalls, and
  typhoons can cause
    rivers to suddenly
        change course.

3. Landslides and soil
    erosion can cause
   sudden build-up of
        sediment and
     debris, and block
        existing water
             channels.
CHANGES IN RIVER FLOW IS THE CAUSE OF FLOODING

      The route
     shows the
  river flow 10
     years ago.

    The route
shows the river
       flow at
      present.

  The encircled
route changes
 the volume of
waters flowing
           in it.



                         10 YEARS AGO
                       PRESENT ROUTE
“ONE LARGE DELTA”, CATCH BASIN OF FLOOD
       Part of Baco,
    Calapan,Naujan
     comprises One      Baco
      Large Delta in             Calapan
         North East
          Mindoro.

                                           Naujan
   Water overflow in
Mag-asawangTubig
  and Bucayao River
is the cause of flood
   in the Delta Area.
FLOOD PROGRESS IN
   THE DELTA AREA

          CALAPAN
     CITY, NAUJAN,
   & PART OF BACO

      Legend:
      (Flood Depth in meters)
            0.00   - 0.25
            0.26   - 1.00
            1.00   - 5.00
            5.01   - 10.00




                                MAXIMUM12 HOURS
                                    CURRENT EXTENT
                                         FLOOD
                                   AFTER 96 TIME
FLOOD SUSCEPTABILITY MAP
(BACO, CALAPAN, NAUJAN, V
         ICTORIA)
WE HAVE A BEAUTIFUL AND PRODUCTIVE PROVINCE. . .
BUT BECAUSE OF FLOODS CAUSED BY MAG-ASAWANG TUBIG
RIVER, SOME OF OUR RICEFIELDS HAVE TRANSFORMED INTO THIS . .
.
LOST OF LIVES, PROPERTIES AND LIVELIHOOD . . .
WE MUST ACT NOW . . . BEFORE IT’S TOO LATE. . .




                                                  ...
BUT THE BIG QUESTION IS . . .


       HOW DO WE DO IT?

            . . . NATIONAL AND
           PROVINCIAL LEADERS
          AND ALL MINDOREÑOS
        MUST WORK HAND IN HAND
        TO SOLVE THIS PROBLEM . . .
LET US ALL DO IT . . .
    THE TIME IS   NOW!
LET US ALL DO IT . . .
    THE TIME IS   NOW!
The PROPOSED SOLUTION:
MAG-ASAWANG TUBIG
MULTI-PURPOSE PROJECT
                       o      Flood Control
                       o      Hydro-Energy Power
                       o      Irrigation
                       o      Water Resource

              Initiated by:
   HON. RODOLFO G. VALENCIA
              Representative,
     First District, Oriental Mindoro

                                                 Research and Study by:
                                           K4 Oriental Mindoro Council, Inc.
                                                  NICO P. VALENCIA
                                                        President
HOUSE BILL 4899
 AN ACT PROVIDING THE CONSTRUCTION OF
MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT

 Hon. RGV filed the Bill on 05 July 2011

 It will serve as flood control, irrigation system,
  power and energy, among others.

 approximate length of 49 kilometers from Mt.
  Halcon down to the Calapan Bay and Tablas
  Strait

 The Bill is now pending with the Committee on
  Public Works and Highways since August 2011.
RELATED INITIATIVES UNDERTAKEN THRU
THE OFFICE OF CONG. VALENCIA
AND K4

      An Orthophoto Map
     (Satellite Digital) of the
        Mag-asawang Tubig,
      costing about PhP 25
           Million, has been
                    obtained.

   Its contour mapping will
              be the basis of
    appropriate engineering
       design and the proper
                     costing.
 Hon. RGV sought the support
  of local Chief Executives.

 On 30 April 2012, the
  Sangguniang
  Panlalawigan, the Municipal
  Mayors and the Sangguniang
  Bayan of the seven (7)
  municipalities in the first
  district have endorsed the
  approval of the Mag-
  asawang Tubig Multi-purpose
  Bill.
 The City Government of Calapan has not responded despite the fact that
  Calapan City is the first hard-hit by flashfloods and the biggest beneficiary of
  the project.
 Memorandum of Understanding (MOU) entered into with DCCD
  Engineering Corporation, a prominent and credible engineering firm, to
  undertake preliminary review of the project.
 A Memorandum of Agreement (MOA) was executed among RGV, Gov. A.
  V. Umali, K4 President Nico P. Valencia and Mr. Armando de Rossi of CMC-
  Asia, Inc. The primary objective to obtain from the European Community
  at least US$200,000.00 to partly finance the cost of the technical study.
 A consultative meeting organized by Hon RGV and the K4 was held last
  May 17, 2012 at RGV Executive Lounge, Makati City.
 Attendees were Gov. Umali, District and Regional Office of the
  DPWH, Office of Foreign Assisted Projects, DPWH, among others.




                HON. RGV TALKING BEFORE THE PARTICIPATNS
Dr. ARMANDO DE ROSSI, President, CMC-Asia
           NICO VALENCIA, BELLEZA, center,
             Dir. HULLIO B. K4 Chairman,
Donor/SolicitorCONG. RGV 2nd from THE PARTICIPATNSStudy
   GOV. with ofTALKING and GOV.left,for Technical
      Dir. ROGELIO ANG, BEFORE UMALI DPWH
         UMALI initial US$200,000.00 OF
CONSULTATIVE MEETINGPARTICIPANTS
MAG-ASAWANG TUBIG MULTI-PURPOSE PROPECT
CONSULTATIVE MEETING
MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT
              May 17, 2012
             RGV Executive Lounge, 8th Floor, RGV Bldg, Makati City




           Initiated by:                           Research and Study by:
HON. RODOLFO G. VALENCIA                     K4 Oriental Mindoro Council, Inc.
           Representative,                          NICO P. VALENCIA
  First District, Oriental Mindoro                        President
REFERENCE PROJECT No. 1:
     THE PAMPANGA
         MEGADIKE,
     A MULTI-BILLION
            PROJECT
OF THE GOVERNMENT
   NOW PROTECTING
      THE PEOPLE OF
     PAMPANGA AND
     OTHER PARTS OF
   NORTHERN LUZON.
REFERENCE PROJECT No. 2:

      THE JALAUR RIVER MULTI-PURPOSE PROJECT II,
                    Barangay Agcala, Calinog, Ilo-ilo.

Components:                DAMS, HIGHLINE CANALS, IRRIGATION
Budget                     P11.2 Billion
Fund Sources               60% of Funds from Korean export-import bank
                           40% Counterpart from Philippine Government
Launching                  May 30, 2012
Target Completion          2016
OPERATIONAL PLAN

I. OBJECTIVE
      The principal objective is to solicit the support of
         H.E. President Benigno S. Aquino III and to certify
         House Bill No. 4899 as a priority,

     Ensure its approval by both the House of Representative and the
      Philippine Senate.

II. DURATION

    This Oplan shall officially commence in May 2012 until the closing of
    the 15th Congress on 30 June 2013.
III. KEY AREAS OF CONCERN

    o   PLANNING & STUDIES
    o   FINANCE SOURCING FOR PROJECT STUDY
    o   ENGINEERING AND COST ESTIMATES
    o   FORMAL PROJECT STUDY
    o   LEGISLATIVE-EXECUTIVE ACTION
IV. PROJECT ADVANTAGES & BENEFITS

    1. Flood Control
    2. Hydro Electric Power, 10-MW capacity
    3. Irrigation System
    4. Water Supply Resource
    5. Restoration of vast agricultural lands
    6. Development of Eco-Tourism
    7. Enhancement of Agricultural Productivity
    8. Reforestation and Ecological Balance
V. IMPLEMENTATION STRATEGY

   1. Pursue sourcing of US $ 200,000.00 study grant from the European
      Community.
   2. Completion of Preliminary Project Evaluation.
   3. Undertake Preliminary Engineering Designs and Cost Estimates, in
      coordination with DPWH.
   4. Coordinate with the Committtee Secretary to calendar H.B. 4899 for
      consideration/deliberation by the Committee on Public Works and
      Highways.
   5. Obtain support of Committee Members for the approval of the Bill and
      endorsement to the Committee on Appropriations.
   6. Obtain support of Members of the Committee on Appropriations.
   7. Follow-up Committee Report of the Committee on Public Works and
      Highways endorsing the approval of H.B. 4899.
   8. Audience with H.E. President Benigno S. Aquino II.
OTHER PROJECTS
        from the
PROPOSED MAG-ASAWANG
 MULTI-PURPOSE PROJECT
PROJECT No. 1: HYDROPOWER PROJECT
PROJECT No. 2: IRRIGATION PROJECT
PROJECT No. 3: REFORESTATION




    Trees Alongside the Megadike
PROJECT No. 4: TOURISM PROJECT




    Infinity Pool
PROJECT No. 5:
        TRANSFORMATION OF IDLE LANDS TO AGRICULTURAL LAND
PROJECT No. 6: POTABLE WATER RESOURCE
LET’S ALL DO IT . . .
                        ...      NOW!

                   Research and Study by:
             K4 Oriental Mindoro Council, Inc.
                    NICO P. VALENCIA
                          President
Initiated by:
HON. RODOLFO G. VALENCIA
           Representative,
  First District, Oriental Mindoro
Compiled and Arranged by:




                     Oriental Mindoro
                       Council, Inc.

NICO P. VALENCIA
   President

Mais conteúdo relacionado

Mais procurados

253370873 water-resource-management
253370873 water-resource-management253370873 water-resource-management
253370873 water-resource-managementRamil Artates
 
Case studies flood in britain & bangladesh
Case studies flood in britain & bangladeshCase studies flood in britain & bangladesh
Case studies flood in britain & bangladeshMs Geoflake
 
Introduction to Civil Engineering Design
Introduction to Civil Engineering DesignIntroduction to Civil Engineering Design
Introduction to Civil Engineering DesignVED Engineers Sdn. Bhd.
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Provinceharoldtaylor1113
 
UNEP presentation on water and lakes
UNEP presentation on water and lakesUNEP presentation on water and lakes
UNEP presentation on water and lakesIwl Pcu
 
Flood Hazards: A Case Study of the Floods in Bangladesh, Asia
Flood Hazards: A Case Study of the Floods in Bangladesh, AsiaFlood Hazards: A Case Study of the Floods in Bangladesh, Asia
Flood Hazards: A Case Study of the Floods in Bangladesh, AsiaUniversität Salzburg
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manilaharoldtaylor1113
 
Bangladesh Flooding
Bangladesh FloodingBangladesh Flooding
Bangladesh Floodingsamuel valko
 
L9 Bangladesh Gcse Aqa A
L9 Bangladesh Gcse Aqa AL9 Bangladesh Gcse Aqa A
L9 Bangladesh Gcse Aqa Atudorgeog
 
December 2009 Desert Report, CNCC Desert Committee
December 2009 Desert Report, CNCC Desert CommitteeDecember 2009 Desert Report, CNCC Desert Committee
December 2009 Desert Report, CNCC Desert CommitteeCNCC Desert Committee
 

Mais procurados (12)

Lecture 2 flood
Lecture 2 floodLecture 2 flood
Lecture 2 flood
 
253370873 water-resource-management
253370873 water-resource-management253370873 water-resource-management
253370873 water-resource-management
 
The Shifting Sands of Noosa
The Shifting Sands of Noosa The Shifting Sands of Noosa
The Shifting Sands of Noosa
 
Case studies flood in britain & bangladesh
Case studies flood in britain & bangladeshCase studies flood in britain & bangladesh
Case studies flood in britain & bangladesh
 
Introduction to Civil Engineering Design
Introduction to Civil Engineering DesignIntroduction to Civil Engineering Design
Introduction to Civil Engineering Design
 
Case Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite ProvinceCase Study No. 1-Groundwater Supply of Cavite Province
Case Study No. 1-Groundwater Supply of Cavite Province
 
UNEP presentation on water and lakes
UNEP presentation on water and lakesUNEP presentation on water and lakes
UNEP presentation on water and lakes
 
Flood Hazards: A Case Study of the Floods in Bangladesh, Asia
Flood Hazards: A Case Study of the Floods in Bangladesh, AsiaFlood Hazards: A Case Study of the Floods in Bangladesh, Asia
Flood Hazards: A Case Study of the Floods in Bangladesh, Asia
 
Case Study No. 8-Managing Floods in Metro Manila
Case  Study No. 8-Managing Floods in Metro ManilaCase  Study No. 8-Managing Floods in Metro Manila
Case Study No. 8-Managing Floods in Metro Manila
 
Bangladesh Flooding
Bangladesh FloodingBangladesh Flooding
Bangladesh Flooding
 
L9 Bangladesh Gcse Aqa A
L9 Bangladesh Gcse Aqa AL9 Bangladesh Gcse Aqa A
L9 Bangladesh Gcse Aqa A
 
December 2009 Desert Report, CNCC Desert Committee
December 2009 Desert Report, CNCC Desert CommitteeDecember 2009 Desert Report, CNCC Desert Committee
December 2009 Desert Report, CNCC Desert Committee
 

Semelhante a Mag asawng tubig multi-purpose project

2010 liongson-flood mitigation in metro manila-phil engg journal article
2010 liongson-flood mitigation in metro manila-phil engg journal article2010 liongson-flood mitigation in metro manila-phil engg journal article
2010 liongson-flood mitigation in metro manila-phil engg journal articleleony1948
 
Lake lanao an ancient lake in distress
Lake lanao   an ancient lake in distressLake lanao   an ancient lake in distress
Lake lanao an ancient lake in distressPip Naga
 
presentation on amphan
presentation on amphan presentation on amphan
presentation on amphan CS SUMAN KUMAR
 
Gully and flooding in anambra state the way forward
Gully and flooding in anambra state  the way forwardGully and flooding in anambra state  the way forward
Gully and flooding in anambra state the way forwardAlexander Decker
 
48 mw wind power
48 mw wind power48 mw wind power
48 mw wind powerrhoan_co
 
UPLB SEARCA 2009 Sept07
UPLB SEARCA 2009 Sept07UPLB SEARCA 2009 Sept07
UPLB SEARCA 2009 Sept07leony1948
 
MAKA KALIKASAN-1.pptx
MAKA KALIKASAN-1.pptxMAKA KALIKASAN-1.pptx
MAKA KALIKASAN-1.pptxBTSTaekook2
 
Disaster management of floods..
Disaster management of floods..Disaster management of floods..
Disaster management of floods..Surabhi Vasudev
 
Disaster management
Disaster managementDisaster management
Disaster managementjbkathiriya
 
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...IAEME Publication
 
Geohazard in Disaster Risk Reduction Management.
Geohazard in Disaster Risk Reduction Management.Geohazard in Disaster Risk Reduction Management.
Geohazard in Disaster Risk Reduction Management.MayGraceRegalado1
 
Disaster management
Disaster managementDisaster management
Disaster managementSenthil Er
 

Semelhante a Mag asawng tubig multi-purpose project (20)

2010 liongson-flood mitigation in metro manila-phil engg journal article
2010 liongson-flood mitigation in metro manila-phil engg journal article2010 liongson-flood mitigation in metro manila-phil engg journal article
2010 liongson-flood mitigation in metro manila-phil engg journal article
 
Lake lanao an ancient lake in distress
Lake lanao   an ancient lake in distressLake lanao   an ancient lake in distress
Lake lanao an ancient lake in distress
 
Essay On Floods
Essay On FloodsEssay On Floods
Essay On Floods
 
presentation on amphan
presentation on amphan presentation on amphan
presentation on amphan
 
De asaster
De asasterDe asaster
De asaster
 
Gully and flooding in anambra state the way forward
Gully and flooding in anambra state  the way forwardGully and flooding in anambra state  the way forward
Gully and flooding in anambra state the way forward
 
48 mw wind power
48 mw wind power48 mw wind power
48 mw wind power
 
Technical paper on ulysses flooding
Technical paper on ulysses floodingTechnical paper on ulysses flooding
Technical paper on ulysses flooding
 
Essay On Floods In Pakistan
Essay On Floods In PakistanEssay On Floods In Pakistan
Essay On Floods In Pakistan
 
Flood and Flash Flood
Flood and Flash FloodFlood and Flash Flood
Flood and Flash Flood
 
Floods in India
Floods in IndiaFloods in India
Floods in India
 
UPLB SEARCA 2009 Sept07
UPLB SEARCA 2009 Sept07UPLB SEARCA 2009 Sept07
UPLB SEARCA 2009 Sept07
 
MAKA KALIKASAN-1.pptx
MAKA KALIKASAN-1.pptxMAKA KALIKASAN-1.pptx
MAKA KALIKASAN-1.pptx
 
Disaster management of floods..
Disaster management of floods..Disaster management of floods..
Disaster management of floods..
 
Disaster management
Disaster managementDisaster management
Disaster management
 
Akosombo Dam (1).pptx
Akosombo Dam (1).pptxAkosombo Dam (1).pptx
Akosombo Dam (1).pptx
 
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...
EFFECTS OF INCREASED LAND USE CHANGES ON RUNOFF AND SEDIMENT YIELD IN THE UPP...
 
Geohazard in Disaster Risk Reduction Management.
Geohazard in Disaster Risk Reduction Management.Geohazard in Disaster Risk Reduction Management.
Geohazard in Disaster Risk Reduction Management.
 
T sunami
T sunamiT sunami
T sunami
 
Disaster management
Disaster managementDisaster management
Disaster management
 

Último

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024Rafal Los
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoffsammart93
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CVKhem
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUK Journal
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...DianaGray10
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century educationjfdjdjcjdnsjd
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptxHampshireHUG
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationSafe Software
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...apidays
 

Último (20)

Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024Tata AIG General Insurance Company - Insurer Innovation Award 2024
Tata AIG General Insurance Company - Insurer Innovation Award 2024
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024The 7 Things I Know About Cyber Security After 25 Years | April 2024
The 7 Things I Know About Cyber Security After 25 Years | April 2024
 
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot TakeoffStrategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
Strategize a Smooth Tenant-to-tenant Migration and Copilot Takeoff
 
Real Time Object Detection Using Open CV
Real Time Object Detection Using Open CVReal Time Object Detection Using Open CV
Real Time Object Detection Using Open CV
 
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
+971581248768>> SAFE AND ORIGINAL ABORTION PILLS FOR SALE IN DUBAI AND ABUDHA...
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdfUnderstanding Discord NSFW Servers A Guide for Responsible Users.pdf
Understanding Discord NSFW Servers A Guide for Responsible Users.pdf
 
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
Connector Corner: Accelerate revenue generation using UiPath API-centric busi...
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
presentation ICT roal in 21st century education
presentation ICT roal in 21st century educationpresentation ICT roal in 21st century education
presentation ICT roal in 21st century education
 
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
04-2024-HHUG-Sales-and-Marketing-Alignment.pptx
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time AutomationFrom Event to Action: Accelerate Your Decision Making with Real-Time Automation
From Event to Action: Accelerate Your Decision Making with Real-Time Automation
 
Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...Apidays New York 2024 - The value of a flexible API Management solution for O...
Apidays New York 2024 - The value of a flexible API Management solution for O...
 

Mag asawng tubig multi-purpose project

  • 1. MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT o Flood Control o Hydro-Energy Power o Irrigation o Water Resource Presented by: HON. RODOLFO G. VALENCIA Representative, First District, Oriental Mindoro Research and Study by: K4 Oriental Mindoro Council, Inc. NICO P. VALENCIA President
  • 2.
  • 3.
  • 4. . . . AND WE ARE THE CAUSE
  • 5. . . .WE POLLUTE THE AIR
  • 6. . . .WE FILL THE LAND WITH WASTE
  • 7. WE CUT THE TREES …. WE DID NOT PROTECT AND PRESERVE OUR ENVIRONMENT
  • 8. AND WHAT ARE THE CONSEQUENCES? OUR CITIES ARE FLOODING
  • 9. OUR LAKES ARE DRYING UP
  • 10. MANY SPECIES ARE FACING THE THREAT OF EXTINCTION
  • 11. TYPHOONS AND OTHER CALAMITIES ARE INTENSIFYING TIDAL WAVE IN INDONESIA EARTHQUAKE IN HAITI
  • 13. IN THE PHILIPPINES. . . WE FACE THE SAME ENVIRONMENTAL PROBLEMS CAUSED BY NATURAL DISASTERS. . . . . . TYPHOONS
  • 14. Typhoon “Milenyo” was the strongest typhoon that hit Metro Manila and Bicol in September 29, 2006.
  • 15. Typhoon “Reming” devastated Albay in November 2006.
  • 16. Typhoon “Ondoy” was a Disaster to Metro Manila. September 26, 2009
  • 17. Typhoon “Peping” was the caused of landslide in Baguio. Floods in Northern Luzon. September 30, 2009
  • 18. Typhoon “Pedring” submerged Roxas Boulevard. September 27, 2011.
  • 19. Typhoon “Sendong” was a Disaster to Cagayan de Oro. December 19, 2011
  • 20. Typhoon “Sendong” was earlier forecasted to hit Oriental Mindoro. By God’s grace, Mindoro was spared Damage Caused: Massive tragedy to Cagayan de Oro, Iligan City Death Toll reached 2000.
  • 21. ORIENTAL MINDORO IS NOT EXEMPTED TO NATURAL DISASTERS. . . TYPHOONS. . . . . . FLOODS
  • 23. Oriental Mindoro among 10 most flood-prone areas in RP, says DENR January 26, 2010 Top ten flood prone Provinces: 1. Pampanga 2. Nueva Ecija 3. Pangasinan 4. Tarlac 5. Maguindanao 6. Bulacan 7. Metro Manila 8. North Cotabato 9. Oriental Mindoro 10. Ilocos Norte
  • 24. Three Floods Hit Oriental Mindoro in December, 2005 December 7, 17, and 27
  • 25. Floods leave trail of devastation in Naujan January 19, 2010 14,000 affected by floods in Naujan December 13, 2010 MINDORO POSTS
  • 26. Deluge: The Sinking Philippines – Floods Submerge Oriental Mindoro and Parts of Visayas Intermittent rains triggered flooding in Oriental Mindoro and several areas in Visayas, forcing at least 395 individuals to flee their homes on Tuesday, the National Disaster Risk Reduction and Management Council (NDRRMC) said Wednesday. Southern Luzon and portions of the Visayas experienced rains over the past two days due to the presence of an active low pressure area (LPA) near Palawan, and another one east of southern Mindanao – ABS-CBN
  • 27. 100 Katutubong Mangyan, nagsilikas dahil sa banta ng baha. GMA News
  • 28. Low-lying Calapan City, two other towns in Or. Mindoro to sink in flood 10-yr. time CALAPAN CITY – In about ten years time, this capital city of Oriental Mindoro and two of its neighboring low-lying towns will submerge in three to seven- meter deep water should a rainfall in a magnitude of what Typhoon “Ondoy” brought to Metro Manila occurs, unless “engineering interventions” be done by the government. This alarming scenario was brought to open by Oriental Mindoro First District Congressman Rodolfo G. Valencia in a press conference here last March 26 as he detailed the recent findings of Norwegian Agency for Development Cooperation (NORAD) regarding the present topographic situation of the province.
  • 29. OVERFLOWING OF MAG-ASAWANG TUBIG RIVER CAUSED MOST OF THE FLOODING IN THE AREAS OF CALAPAN CITY, NAUJAN, VICTORIA , AND PARTIALLY BACO.
  • 30. SERIES OF STUDIES, CONSULTATION AND COORDINATIVE MEETINGS WERE UNDERTAKEN IN THE PAST 30 YEARS - NO POSITIVE RESULT GABION DIKES ARE TEMPORARY SOLUTIONS. NOT EFFECTIVE IN MOST AREAS.
  • 31. RECHANNELING SOLUTIONS: BUCAYAO RIVER RECHANNELING, A PROJECT OF CONG. RGV THRU DPWH (P20 MILLION) COMPLETED 2006. RESULT: A PARTIAL SOLUTION TO THE FLOODING OF CALAPAN CITY.
  • 32. DREDGING AND REHABILITATION Oriental Mindoro starts anti-flood plan The Philippine Star, March 30, 2008 CALAPAN CITY – Rep. Rodolfo Valencia of Oriental Mindoro’s 1st District was able to secure latest model of dredging equipment from Finland worth P70 Million. DPWH Sec. H. Ebdane approved the award to First District of Oriental Mindoro. RESULT: A PARTIAL SOLUTION. CLEARING OF CALAPAN RIVER AND OTHER WATERWAYS IN THE FIRST DISTRICT.
  • 33. WHY DO WE HAVE FLOODS IN THE FIRST DISTRICT OF ORIENTAL MINDORO?
  • 34. THIS IS THE ISLAND OF MINDORO . . . TOPOGRAPHY
  • 35. THE FLOW OF WATERS DIVIDES THE ISLAND OF MINDORO . . . A RAINFALL IN OCCIDENTAL MINDORO DRAINS TO THE LEFT. A RAINFALL IN ORIENTAL MINDORO DRAINS TO THE RIGHT.
  • 36. BODIES OF WATER IS FORMED IN THE UPLAND OVER TIME Satellite Image from October, 1999 Aerial Photography from 2009, same area
  • 37. ANOTHER UPLAND AREA Satellite Image from October, 1999 Aerial Photography from 2009, same area
  • 38. THESE WATERS FLOW TO THE LOWLAND BY FALLS, RIVERS
  • 39. MOST RIVERS ARE IN THE WATERSHED AREAS OF THE ISLAND And most Watersheds 1508 km2 are in the (14.26 %) North East 355 km2 Mindoro (3.36%) Area It comprises 8709 km2 (82.37 %) 17.62% of the area of the whole island of Mindoro.
  • 40. THERE ARE FEW BIG RIVERS IN THE WATERSHED AREAS Blue lines show the major water flows in the Mindoro Watersheds. BUCAYAO Waters from RIVER the upland area flow through the major rivers: Mag-asawng Tubig River MAG-ASAWANG and Bucayao TUBIG RIVER River.
  • 41. RIVERS CHANGE FLOW OVER TIME . . . 1. River migrate, meander and shortcut bends. 2. Earthquakes, rainfalls, and typhoons can cause rivers to suddenly change course. 3. Landslides and soil erosion can cause sudden build-up of sediment and debris, and block existing water channels.
  • 42. CHANGES IN RIVER FLOW IS THE CAUSE OF FLOODING The route shows the river flow 10 years ago. The route shows the river flow at present. The encircled route changes the volume of waters flowing in it. 10 YEARS AGO PRESENT ROUTE
  • 43. “ONE LARGE DELTA”, CATCH BASIN OF FLOOD Part of Baco, Calapan,Naujan comprises One Baco Large Delta in Calapan North East Mindoro. Naujan Water overflow in Mag-asawangTubig and Bucayao River is the cause of flood in the Delta Area.
  • 44. FLOOD PROGRESS IN THE DELTA AREA CALAPAN CITY, NAUJAN, & PART OF BACO Legend: (Flood Depth in meters) 0.00 - 0.25 0.26 - 1.00 1.00 - 5.00 5.01 - 10.00 MAXIMUM12 HOURS CURRENT EXTENT FLOOD AFTER 96 TIME
  • 45. FLOOD SUSCEPTABILITY MAP (BACO, CALAPAN, NAUJAN, V ICTORIA)
  • 46. WE HAVE A BEAUTIFUL AND PRODUCTIVE PROVINCE. . .
  • 47. BUT BECAUSE OF FLOODS CAUSED BY MAG-ASAWANG TUBIG RIVER, SOME OF OUR RICEFIELDS HAVE TRANSFORMED INTO THIS . . .
  • 48. LOST OF LIVES, PROPERTIES AND LIVELIHOOD . . .
  • 49. WE MUST ACT NOW . . . BEFORE IT’S TOO LATE. . . ...
  • 50. BUT THE BIG QUESTION IS . . . HOW DO WE DO IT? . . . NATIONAL AND PROVINCIAL LEADERS AND ALL MINDOREÑOS MUST WORK HAND IN HAND TO SOLVE THIS PROBLEM . . .
  • 51. LET US ALL DO IT . . . THE TIME IS NOW!
  • 52. LET US ALL DO IT . . . THE TIME IS NOW!
  • 53. The PROPOSED SOLUTION: MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT o Flood Control o Hydro-Energy Power o Irrigation o Water Resource Initiated by: HON. RODOLFO G. VALENCIA Representative, First District, Oriental Mindoro Research and Study by: K4 Oriental Mindoro Council, Inc. NICO P. VALENCIA President
  • 54. HOUSE BILL 4899 AN ACT PROVIDING THE CONSTRUCTION OF MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT Hon. RGV filed the Bill on 05 July 2011 It will serve as flood control, irrigation system, power and energy, among others. approximate length of 49 kilometers from Mt. Halcon down to the Calapan Bay and Tablas Strait The Bill is now pending with the Committee on Public Works and Highways since August 2011.
  • 55.
  • 56. RELATED INITIATIVES UNDERTAKEN THRU THE OFFICE OF CONG. VALENCIA AND K4  An Orthophoto Map (Satellite Digital) of the Mag-asawang Tubig, costing about PhP 25 Million, has been obtained.  Its contour mapping will be the basis of appropriate engineering design and the proper costing.
  • 57.  Hon. RGV sought the support of local Chief Executives.  On 30 April 2012, the Sangguniang Panlalawigan, the Municipal Mayors and the Sangguniang Bayan of the seven (7) municipalities in the first district have endorsed the approval of the Mag- asawang Tubig Multi-purpose Bill.  The City Government of Calapan has not responded despite the fact that Calapan City is the first hard-hit by flashfloods and the biggest beneficiary of the project.
  • 58.  Memorandum of Understanding (MOU) entered into with DCCD Engineering Corporation, a prominent and credible engineering firm, to undertake preliminary review of the project.
  • 59.  A Memorandum of Agreement (MOA) was executed among RGV, Gov. A. V. Umali, K4 President Nico P. Valencia and Mr. Armando de Rossi of CMC- Asia, Inc. The primary objective to obtain from the European Community at least US$200,000.00 to partly finance the cost of the technical study.
  • 60.  A consultative meeting organized by Hon RGV and the K4 was held last May 17, 2012 at RGV Executive Lounge, Makati City.  Attendees were Gov. Umali, District and Regional Office of the DPWH, Office of Foreign Assisted Projects, DPWH, among others. HON. RGV TALKING BEFORE THE PARTICIPATNS
  • 61. Dr. ARMANDO DE ROSSI, President, CMC-Asia NICO VALENCIA, BELLEZA, center, Dir. HULLIO B. K4 Chairman, Donor/SolicitorCONG. RGV 2nd from THE PARTICIPATNSStudy GOV. with ofTALKING and GOV.left,for Technical Dir. ROGELIO ANG, BEFORE UMALI DPWH UMALI initial US$200,000.00 OF
  • 63. CONSULTATIVE MEETING MAG-ASAWANG TUBIG MULTI-PURPOSE PROJECT May 17, 2012 RGV Executive Lounge, 8th Floor, RGV Bldg, Makati City Initiated by: Research and Study by: HON. RODOLFO G. VALENCIA K4 Oriental Mindoro Council, Inc. Representative, NICO P. VALENCIA First District, Oriental Mindoro President
  • 64. REFERENCE PROJECT No. 1: THE PAMPANGA MEGADIKE, A MULTI-BILLION PROJECT OF THE GOVERNMENT NOW PROTECTING THE PEOPLE OF PAMPANGA AND OTHER PARTS OF NORTHERN LUZON.
  • 65. REFERENCE PROJECT No. 2: THE JALAUR RIVER MULTI-PURPOSE PROJECT II, Barangay Agcala, Calinog, Ilo-ilo. Components: DAMS, HIGHLINE CANALS, IRRIGATION Budget P11.2 Billion Fund Sources 60% of Funds from Korean export-import bank 40% Counterpart from Philippine Government Launching May 30, 2012 Target Completion 2016
  • 66. OPERATIONAL PLAN I. OBJECTIVE  The principal objective is to solicit the support of H.E. President Benigno S. Aquino III and to certify House Bill No. 4899 as a priority,  Ensure its approval by both the House of Representative and the Philippine Senate. II. DURATION This Oplan shall officially commence in May 2012 until the closing of the 15th Congress on 30 June 2013.
  • 67. III. KEY AREAS OF CONCERN o PLANNING & STUDIES o FINANCE SOURCING FOR PROJECT STUDY o ENGINEERING AND COST ESTIMATES o FORMAL PROJECT STUDY o LEGISLATIVE-EXECUTIVE ACTION
  • 68. IV. PROJECT ADVANTAGES & BENEFITS 1. Flood Control 2. Hydro Electric Power, 10-MW capacity 3. Irrigation System 4. Water Supply Resource 5. Restoration of vast agricultural lands 6. Development of Eco-Tourism 7. Enhancement of Agricultural Productivity 8. Reforestation and Ecological Balance
  • 69. V. IMPLEMENTATION STRATEGY 1. Pursue sourcing of US $ 200,000.00 study grant from the European Community. 2. Completion of Preliminary Project Evaluation. 3. Undertake Preliminary Engineering Designs and Cost Estimates, in coordination with DPWH. 4. Coordinate with the Committtee Secretary to calendar H.B. 4899 for consideration/deliberation by the Committee on Public Works and Highways. 5. Obtain support of Committee Members for the approval of the Bill and endorsement to the Committee on Appropriations. 6. Obtain support of Members of the Committee on Appropriations. 7. Follow-up Committee Report of the Committee on Public Works and Highways endorsing the approval of H.B. 4899. 8. Audience with H.E. President Benigno S. Aquino II.
  • 70. OTHER PROJECTS from the PROPOSED MAG-ASAWANG MULTI-PURPOSE PROJECT
  • 71. PROJECT No. 1: HYDROPOWER PROJECT
  • 72. PROJECT No. 2: IRRIGATION PROJECT
  • 73. PROJECT No. 3: REFORESTATION Trees Alongside the Megadike
  • 74. PROJECT No. 4: TOURISM PROJECT Infinity Pool
  • 75. PROJECT No. 5: TRANSFORMATION OF IDLE LANDS TO AGRICULTURAL LAND
  • 76. PROJECT No. 6: POTABLE WATER RESOURCE
  • 77. LET’S ALL DO IT . . . ... NOW! Research and Study by: K4 Oriental Mindoro Council, Inc. NICO P. VALENCIA President
  • 78. Initiated by: HON. RODOLFO G. VALENCIA Representative, First District, Oriental Mindoro
  • 79. Compiled and Arranged by: Oriental Mindoro Council, Inc. NICO P. VALENCIA President