SlideShare uma empresa Scribd logo
1 de 29
CONSTRUCTION CLAIMS
Claims in Construction Contracts are Inevitable
Reasons of Claims The employer and his professional representative who prepare the contract in haste leaving many short comings in their documents and also commit defaults in fulfilling their obligations try to defend their document/action though they very well know that some aspects are indefensible.
How to Tackle Claims To tackle the problem of claims effectively it is necessary for both sides to have a better understanding of the basis and principles of contract and therefore of the rights and obligations of the two parties.
Understanding It is necessary for professional representatives of both sides to have an understanding of business side of industry so as to appreciate the circumstances in which the contractor conducts the risks in which he can properly and contractually be expected to undertake and the financial consequences if things go wrong.
If things go wrong by reason of any default on the part of contractor, it must remain his concern; however, if the default lies with the employer or his management team, then the employer must face the financial consequences and settle the claims without any loss of time to avoid any adverse effect on progress of work.
Different Types of Claims ,[object Object],[object Object],[object Object],[object Object],[object Object]
Contractual Claims These are the claims which arise out of the express provision of the particular contract i.e., for extra cost, expense and direct loss specifically provided as a remedy in the contract for breach of contract on the part of the party concerned.
Extra Contractual Claims These claims are also known as common law claims.  These claims are for damages for breach of contract at common law.
Quantum Merit Claims Provide remedy for a person who has carried out work under the instruction of the owner but no price has been agreed or where original contract has been replaced by a new one and payment is claimed for work done under the substituted contract.
Ex-Gratia Claims Ex-gratia claim is one where no legal remedy is available to the contractor but arise out of hardship.  On the ground of equity or favour the authority concerned may in certain circumstances consider that hardship calls for mercy and moral liability.  These claims are also called sympathy claims.  Wherever such claims are to be given it will be better if these are given during the currency of the contract so that the money paid helps in improving progress of work.
Counter Claims The claims raised by the opposite party to counter the claims of the claimant is called as counter claims.
Potential Heads of Claims ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
All participants to make a list of problems at site which have or may lead to claims.
Preparation and Presentation of Claims ,[object Object],[object Object],[object Object],[object Object]
Preparation and Presentation of Claims ,[object Object],[object Object],[object Object],[object Object]
Burden of Proof Where the claim situation arise the party attempting to demonstrate that it was prevented from performing or performed in excess of, or that the other side performed contract to contract requirement has the responsibility of proving such a conduct. The accused party need not usually defend itself against the allegation until some evidence is presented by the party raising claim showing wrongful exercise of lawful authority on the part of the party against whom the claim is raised.
When the party establishes evidence in his favour which is sufficiently strong and would be enough to render a favourble decision unless contradicted and overcome by the other party, the party against whom the claim is raised, either has to come forward with a concrete counter fact to demolish the claim or will have to consider the claim.  Therefore the party must bring out concrete evidence while raising the claim which will not be easily demolished by the other party.
Basis of Claim ,[object Object],[object Object],[object Object]
Importance of Facts  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
The contractor who raised the claim bear the burden of proof for establishing a claim by providing concrete evidence of cost impact that is effective enough to demonstrate that the claimed cost were incurred as a result of extra work, changes or defaults of owner etc.  The proof of expenditure is a pre-requisite for complete claim analysis by the owner.
Claims – Supporting Evidence ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
In a situation where a claim is lost for direct loss and /or expense in respect of a variation it will be necessary that it is supported by the following: ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
DRAFTING OF CLAIM ,[object Object],[object Object],[object Object],[object Object]
INTRODUCTON ,[object Object],[object Object],[object Object]
Ground of Claim ,[object Object]
Substantiation of Claim ,[object Object],In order to prove the fact of delay on the part of the employer use of planning technique such as CPM, should also be made.
Providing Damages ,[object Object],[object Object],[object Object]
Negotiating Settlement  ,[object Object],[object Object],[object Object],[object Object]

Mais conteúdo relacionado

Mais procurados

Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Tahir B Mirza
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedMichael Pink
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management Rajat Nainwal
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008AYM1979
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Divyanshu Dayal
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationVimal Daluwatta
 
Contract Conditions
Contract ConditionsContract Conditions
Contract ConditionsDr K M SONI
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts fritzlejarso
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.Aszahari Aie
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationAyush Joshi
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16Arvind Solanki
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qumes manandhar
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Managementjohnkirth1898
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)mohamed Ismail
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentationelliotfus
 

Mais procurados (20)

Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)Contracts & Claims Management Workshop (Session-1)
Contracts & Claims Management Workshop (Session-1)
 
Construction Delay Analysis, Simplified
Construction Delay Analysis, SimplifiedConstruction Delay Analysis, Simplified
Construction Delay Analysis, Simplified
 
Construction Project Management
Construction Project Management Construction Project Management
Construction Project Management
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
Clause 14.1 The Contract Price- Understanding Clauses in FIDIC ‘Conditions of...
 
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
Clause 4.2 Performance Security-Understanding Clauses in FIDIC ‘Conditions of...
 
EOT Related Cost Compensation Determination
EOT Related Cost Compensation DeterminationEOT Related Cost Compensation Determination
EOT Related Cost Compensation Determination
 
FIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshopFIDIC variation, claim & dispute - CYLFEx workshop
FIDIC variation, claim & dispute - CYLFEx workshop
 
Contract Conditions
Contract ConditionsContract Conditions
Contract Conditions
 
Fidic contracts management introduction
Fidic contracts management introductionFidic contracts management introduction
Fidic contracts management introduction
 
Types and forms of contracts
Types and forms of contracts Types and forms of contracts
Types and forms of contracts
 
Types of contract
Types of contractTypes of contract
Types of contract
 
Lecture 1 introduction to construction procurement process.
Lecture 1   introduction to construction procurement process.Lecture 1   introduction to construction procurement process.
Lecture 1 introduction to construction procurement process.
 
Extension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentationExtension of Time (EoT) in Construction Project presentation
Extension of Time (EoT) in Construction Project presentation
 
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16CONTRACT ADMINISTRATION- Presentation dated 22.11.16
CONTRACT ADMINISTRATION- Presentation dated 22.11.16
 
Cp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post qCp 2 selection of contractor - pq and post q
Cp 2 selection of contractor - pq and post q
 
Construction Project Management
Construction Project ManagementConstruction Project Management
Construction Project Management
 
Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)Time management in fidic red book 2017(prmg080 project)
Time management in fidic red book 2017(prmg080 project)
 
Claims
ClaimsClaims
Claims
 
Construction Law Presentation
Construction Law PresentationConstruction Law Presentation
Construction Law Presentation
 

Destaque (6)

Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]Chapter 2 [compatibility mode]
Chapter 2 [compatibility mode]
 
"Types and Causes of Construction Claims"
"Types and Causes of Construction Claims""Types and Causes of Construction Claims"
"Types and Causes of Construction Claims"
 
Final Presentation
Final Presentation Final Presentation
Final Presentation
 
Claim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINALClaim Presentation Rev 03 FINAL
Claim Presentation Rev 03 FINAL
 
Extension of time Analysis
Extension of time AnalysisExtension of time Analysis
Extension of time Analysis
 
Extension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed IbarhimExtension of time (E.O.T) By Ahmed Ibarhim
Extension of time (E.O.T) By Ahmed Ibarhim
 

Semelhante a Construction Claims

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closuresrinivas2036
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7ashleyyeap
 
Wc intercompany arbitration
Wc intercompany arbitrationWc intercompany arbitration
Wc intercompany arbitrationcplacitella
 
Home Inspector's Insurance & Risk Management - July 19, 2013
Home Inspector's Insurance & Risk Management - July 19, 2013Home Inspector's Insurance & Risk Management - July 19, 2013
Home Inspector's Insurance & Risk Management - July 19, 2013Gerald Brunker
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your TimesharePotomacLegalGroup
 
RETS Presentation - Home Inspector's Insurance & Risk Management
RETS Presentation - Home Inspector's Insurance & Risk ManagementRETS Presentation - Home Inspector's Insurance & Risk Management
RETS Presentation - Home Inspector's Insurance & Risk ManagementGerald Brunker
 
Contract Basics for Credit Unions
Contract Basics for Credit UnionsContract Basics for Credit Unions
Contract Basics for Credit Unionslspasser
 
The Importance of Tendering Your Defense to an Insurer
The Importance of Tendering Your Defense to an InsurerThe Importance of Tendering Your Defense to an Insurer
The Importance of Tendering Your Defense to an InsurerAndrewCaulfield5
 
common business dispute legal claims by business lawyer David Steinfeld.pdf
common business dispute legal claims by business lawyer David Steinfeld.pdfcommon business dispute legal claims by business lawyer David Steinfeld.pdf
common business dispute legal claims by business lawyer David Steinfeld.pdfDavid Steinfeld, Esq.
 
Claims Final (2)
Claims Final (2)Claims Final (2)
Claims Final (2)vijay popat
 
Negotiating vendor contracts
Negotiating vendor contractsNegotiating vendor contracts
Negotiating vendor contractsbobweil
 
Employee or Independent Contractor?
Employee or Independent Contractor? Employee or Independent Contractor?
Employee or Independent Contractor? bodo-con
 
Remedies of Contract Law | Main Principles
Remedies of Contract Law | Main PrinciplesRemedies of Contract Law | Main Principles
Remedies of Contract Law | Main Principlessahansathsarawegiriy1
 
Essentials Of Contracting
Essentials Of ContractingEssentials Of Contracting
Essentials Of Contractingmkroland
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Pierrette Khoury BComm/B Laws, GDLP
 

Semelhante a Construction Claims (20)

Construction claims, disputes and project closure
Construction claims, disputes and project closureConstruction claims, disputes and project closure
Construction claims, disputes and project closure
 
Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7Professional Practice 1 Tutorial 7
Professional Practice 1 Tutorial 7
 
Wc intercompany arbitration
Wc intercompany arbitrationWc intercompany arbitration
Wc intercompany arbitration
 
Fifty Ways to Leave Your Debtor
Fifty Ways to Leave Your DebtorFifty Ways to Leave Your Debtor
Fifty Ways to Leave Your Debtor
 
Home Inspector's Insurance & Risk Management - July 19, 2013
Home Inspector's Insurance & Risk Management - July 19, 2013Home Inspector's Insurance & Risk Management - July 19, 2013
Home Inspector's Insurance & Risk Management - July 19, 2013
 
How to Get Out of Your Timeshare
How to Get Out of Your TimeshareHow to Get Out of Your Timeshare
How to Get Out of Your Timeshare
 
RETS Presentation - Home Inspector's Insurance & Risk Management
RETS Presentation - Home Inspector's Insurance & Risk ManagementRETS Presentation - Home Inspector's Insurance & Risk Management
RETS Presentation - Home Inspector's Insurance & Risk Management
 
Contract Basics for Credit Unions
Contract Basics for Credit UnionsContract Basics for Credit Unions
Contract Basics for Credit Unions
 
Business laws
Business lawsBusiness laws
Business laws
 
The Importance of Tendering Your Defense to an Insurer
The Importance of Tendering Your Defense to an InsurerThe Importance of Tendering Your Defense to an Insurer
The Importance of Tendering Your Defense to an Insurer
 
Hurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community AssociationHurricane Recovery Compilation for Community Association
Hurricane Recovery Compilation for Community Association
 
common business dispute legal claims by business lawyer David Steinfeld.pdf
common business dispute legal claims by business lawyer David Steinfeld.pdfcommon business dispute legal claims by business lawyer David Steinfeld.pdf
common business dispute legal claims by business lawyer David Steinfeld.pdf
 
Claims Final (2)
Claims Final (2)Claims Final (2)
Claims Final (2)
 
The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..The pathway to documenting successful contract claims..
The pathway to documenting successful contract claims..
 
Negotiating vendor contracts
Negotiating vendor contractsNegotiating vendor contracts
Negotiating vendor contracts
 
Employee or Independent Contractor?
Employee or Independent Contractor? Employee or Independent Contractor?
Employee or Independent Contractor?
 
UK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletterUK Adjudicators March 2018 newsletter
UK Adjudicators March 2018 newsletter
 
Remedies of Contract Law | Main Principles
Remedies of Contract Law | Main PrinciplesRemedies of Contract Law | Main Principles
Remedies of Contract Law | Main Principles
 
Essentials Of Contracting
Essentials Of ContractingEssentials Of Contracting
Essentials Of Contracting
 
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
Turnbull Bowles Lawyers - Security of Payment Act Guide - www.turnbullbowles....
 

Construction Claims

  • 2. Claims in Construction Contracts are Inevitable
  • 3. Reasons of Claims The employer and his professional representative who prepare the contract in haste leaving many short comings in their documents and also commit defaults in fulfilling their obligations try to defend their document/action though they very well know that some aspects are indefensible.
  • 4. How to Tackle Claims To tackle the problem of claims effectively it is necessary for both sides to have a better understanding of the basis and principles of contract and therefore of the rights and obligations of the two parties.
  • 5. Understanding It is necessary for professional representatives of both sides to have an understanding of business side of industry so as to appreciate the circumstances in which the contractor conducts the risks in which he can properly and contractually be expected to undertake and the financial consequences if things go wrong.
  • 6. If things go wrong by reason of any default on the part of contractor, it must remain his concern; however, if the default lies with the employer or his management team, then the employer must face the financial consequences and settle the claims without any loss of time to avoid any adverse effect on progress of work.
  • 7.
  • 8. Contractual Claims These are the claims which arise out of the express provision of the particular contract i.e., for extra cost, expense and direct loss specifically provided as a remedy in the contract for breach of contract on the part of the party concerned.
  • 9. Extra Contractual Claims These claims are also known as common law claims. These claims are for damages for breach of contract at common law.
  • 10. Quantum Merit Claims Provide remedy for a person who has carried out work under the instruction of the owner but no price has been agreed or where original contract has been replaced by a new one and payment is claimed for work done under the substituted contract.
  • 11. Ex-Gratia Claims Ex-gratia claim is one where no legal remedy is available to the contractor but arise out of hardship. On the ground of equity or favour the authority concerned may in certain circumstances consider that hardship calls for mercy and moral liability. These claims are also called sympathy claims. Wherever such claims are to be given it will be better if these are given during the currency of the contract so that the money paid helps in improving progress of work.
  • 12. Counter Claims The claims raised by the opposite party to counter the claims of the claimant is called as counter claims.
  • 13.
  • 14. All participants to make a list of problems at site which have or may lead to claims.
  • 15.
  • 16.
  • 17. Burden of Proof Where the claim situation arise the party attempting to demonstrate that it was prevented from performing or performed in excess of, or that the other side performed contract to contract requirement has the responsibility of proving such a conduct. The accused party need not usually defend itself against the allegation until some evidence is presented by the party raising claim showing wrongful exercise of lawful authority on the part of the party against whom the claim is raised.
  • 18. When the party establishes evidence in his favour which is sufficiently strong and would be enough to render a favourble decision unless contradicted and overcome by the other party, the party against whom the claim is raised, either has to come forward with a concrete counter fact to demolish the claim or will have to consider the claim. Therefore the party must bring out concrete evidence while raising the claim which will not be easily demolished by the other party.
  • 19.
  • 20.
  • 21. The contractor who raised the claim bear the burden of proof for establishing a claim by providing concrete evidence of cost impact that is effective enough to demonstrate that the claimed cost were incurred as a result of extra work, changes or defaults of owner etc. The proof of expenditure is a pre-requisite for complete claim analysis by the owner.
  • 22.
  • 23.
  • 24.
  • 25.
  • 26.
  • 27.
  • 28.
  • 29.