SlideShare uma empresa Scribd logo
1 de 13
Baixar para ler offline
JACK-UP RIG FOUNDATION DESIGN
            APPLYING 3D FE STRUCTURE - SOIL -
            INTERACTION MODELLING

            L KELLEZI
            GEO - Danish Geotechnical Institute
            1 Maglebjergvej, DK 2800 Kgs. Lyngby, Denmark

            G KUDSK
            Maersk Contractors
            Esplanaden 50, DK 1098 Copenhagen K, Denmark

            H HOFSTEDE
            Marine Structure Consultants (MSC)
            Karel Doormanweg 66, 3100 AR Schiedam, Netherlands




       SUMMARY: The foundation engineering assessment for the world’s largest
       jack-up rig installed offshore Norway is carried out. Based on the site survey
       and soil investigation data the soil conditions vary accross the site and consist
       of bedrock overlied by very soft silt / clay and a shallow layer of seabed sand.
       From the conventional and finite element analyses an engineering solution
       comprizing construction of sand banks was proposed. The final geometry of
       the banks is determined based on the three – dimensional (3D) finite element
       (FE) integrated jack-up structure – skirted spudcan – soil – interaction
       modellings documenting that during the rig installation / preloading and
       storm loading the structural forces fall within the accepted limits. The rig was
       suceessfully installed and upgraded verifying the engineering predictions.


                                           INTRODUCTION

In the design and installation of different offshore structures an important aspect is the
investigation of the seabed conditions considering features such as slopes, depressions,
boulders, seabed inclination etc. Particularly for a jack-up drilling rig, which is supported
by three independents legs at an approximate distance of (50 – 60) m from each other, this
is a very important issue.
       In addition to seabed features the variation of the soil conditions in depth and
horizontal directions, at the three footing locations plays also a decisive role in the structure
and foundation solution.
       A geotechnical engineering assessment for the world's largest jack-up rig is given in

L Kellezi, G Kudsk, H Hofstede, Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling
Proceedings of the BGA International Conference on Foundations, Dundee, Scotland,24 – 27 June 2008. IHS BRE
Press, 2008.
Kellezi, Kudsk, Hofstede




this paper. The rig was temporarily installed next to a quay of a Norwegian yard in order to
be upgraded for further production work in the North Sea.
       The preliminary site survey indicated that the seabed in the considered area of
location was rock outcrop, undulating across the site creating slopes and depressions.
       As the current rig’s footings are skirted spudcans with areas exceeding the plan
dimensions of the seabed features and the skirts cannot penetrate through the rock, seabed
modification was necessary. The idea of creating flat areas at the footing’s locations,
through construction of shallow gravel / sand banks to a height slightly larger than the skirt
heights, was initially proposed.
       After the preliminary site survey a detailed geotechnical investigation was carried out
to verify the soil conditions. From the investigation a sediment layer of varying thickness
overlying the undulating bedrock was identified.
       Preliminary conventional and numerical skirted spudcan penetration analyses, with
originally low and lately rather increased elevations of the sand banks, indicated
non-uniform penetration, sliding and rotation of the free skirted spudcans under preloading
conditions. For a more realistic evaluation, jack-up structure - foundation interaction effects
were accounted for in the analyses.
       The full 3D FE jack-up structure – skirted spudcans – sand bank – soil - interaction
models were applied for varying heights of the sand banks, investigating the non-uniform
footings penetrations, rotations and sliding and how they effect the structure. After an
extensive amount of analyses, the final heights of the sand banks are proposed.


          JACK-UP STRUCTURE – SKIRTED SPUDCAN - SOIL SYSTEM

The current jack-up drilling rig, the world’s largest, is type independent leg cantilever and
is shown in Fig. 1 in comparison to other world known structures. It operates in water
depths up to 150 m and it has leg lengths of about 205 m.

300 m




200 m




100 m




             Eiffel Tower      Tower Bridge      Maersk     London Eye   Great Belt East
                                                 Inspirer                 Bridge Pylon

Fig. 1. The jack-up rig in comparison to other structures

Structure elements and stiffness
In the 3D FE jack-up - foundation - interaction model only the main structure elements such
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




as the three legs and the hull were included. The legs were simplified to 3D beam elements,
and the hull to plate or floor elements with the equivalent thickness. The rig designer
provided the geometry data for the legs and the hull.

Skirted spudcan geometry
The considered jack-up footings have a diameter D = 22 m and are fitted with outer and
internal skirts, which divide the spudcan into 6 compartments. Fig. 2 shows photo views of
the spudcan inside and a 3D model.




Fig. 2. Jack-up skirted spudcan

      The vertical geometry of the spudcan structure is mainly given by: Distance from
spudcan base to tip of outer skirts 2.3 m; Distance from spudcan base to tip of internal skirts
1.1 m; The spudcan itself is almost a flat rigid plate. The transverse stiffnesses of the skirts
are derived from the structural FE model of the spudcan. These thicknesses are applied in
the 3D FE analyses employing wall structural elements, respectively.

Interpretation of the soil conditions
Except the preliminary site survey, to identify the seabed and the soil conditions at the
considered spudcan locations a new site survey, seismic, (sparker and pinger) and
bathymetry was carried out. Sediments of varying thickness overlaying the bedrock were
interpreted. The largest sediment thicknesses were seen at the largest water depth. Gravity
vibrocore samples taken from seabed could not reach the bedrock and showed mostly
sediments of clayey, gravely sand. At the shallow water depths the bedrock outcrops the
seabed.
       After the interpretation of the seismic survey geotechnical investigation including 5
piezo-cone penetration tests (PCPTs) and one vibrocore for each spudcan location were
carried out. Discrepancies were though recognized at some PCPT locations. Considering
the limitations of the sparker survey, a pinger survey was carried out. With a less
penetrating, but a smaller opening angle seismic source, the pinger survey was applied to
better identify the slope of the bedrock and supplement the previous investigations in the
area. Based on the pinger data combined with the existing and new soil information, a
re-interpreted model of the sediment and bedrock surface was produced.
       Several originally proposed locations were studied finally focusing on one of them.
At each leg position four vertical cross sections such as north - south, west - east, northwest
- southeast, northeast - southwest were interpreted showing the seabed depth and the depth
of the top bedrock from the centre of the spudcans out to a distance of 50 m.
Kellezi, Kudsk, Hofstede




      To estimate the variation in thickness of the soil layers between the bedrock and the
seabed and the soil parameters applicable to the design of the foundations at the final
location a new geotechnical investigation consisting of 5 boreholes, about 70 PCPTs and
laboratory tests, classification and simple and advanced strength tests were carried out.
      From the engineering interpretation of the gathered soil data it was assessed that the
soil conditions consist of overall quaternary marine sediments, mainly deposits consisting
of a seabed layer of sand overlying clayey, sandy silt with variable thickness (0 - 9) m
overlying crystalline bedrock.

Water depth variation
The water depth at the centre of the three chosen spudcan locations are as seen from Fig. 3,
approximately –23 m at spudcan S1, -19 m at S2 and –26.5 m at S3. So the location of S2 is
shallowest, becoming deeper at S1 and even deeper at S3.




                                                   




           









                                        



Fig. 3. Bathymetry at the considered rig location

Design soil profiles and parameters
On the basis of the seismic surveys, PCPTs / boreholes and laboratory test results
(classification and triaxial, unconsolidated undrained (UU) and consolidated isotropic
drained (CID)) the soil profiles and soil parameters applicable to the engineering
assessment of the jack-up at the considered location are derived.
       A good correlation with the PCPT data was investigated for the depths where soil
samples were taken and laboratory tests performed. However, at the depths where lower
cone strength as shown in Fig. 4 and Fig. 5 were recorded no soil sample could be extracted
and no correlation was available. Under these circumstances the cone factor N = qnet / cu =
(15 – 20) was used. When applying such a correlation on the PCPT data undrained shear
strength for the silt cu = (15 – 25) kPa were assessed.
       Based on the test results and the engineering judgement initially cu = 25 kPa for the
silt and a friction angle = 35 for the seabed sand were applied.
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




Fig. 4. PCPT profile at S1 location                          Fig. 5. PCPT profile at S3 location

       The soil parameters for the bedrock are evaluated based on the engineering
experience. An undrained shear strength cu = (1000 – 1500) kPa was assigned.
       ‘As it was’ soil profile at the three spudcan location can be given by Table 1. There
are three soil layers throughout the site. However, the thickness and the elevations of the
layers strongly vary not only between the spudcan locations but also within the spudcan
areas.

Table 1. ‘As it was´ soil profile at the considered jack- up footings locations

                                                      Angle of
                        Depth of                                         Undrained          Deformation
                                      Unit weight internal friction
  Soil description       layer                                         shear strength        Modulus
                                       ' (kN/m3)    and dilation
                         h (m)                                           cu (kN/m2)         E (kN / m2)
                                                    ()         ()
  SAND, dense            Variable         10.0      35         5              -                35000
SILT / CLAY, very
                         Variable         9.0          -        -          25 / 15            100 * cu
    soft to soft
   BEDROCK               Variable        12.0          -        -       1500 / 1000           200 * cu


     The material of the sand bank constructed over the seabed at the spudcan locations is
modelled applying a unit weight ' = 11 kN/m3, a friction angle = (40 – 45) and a dilation
angle = (10 – 15) . The deformation parameters E = 100000 kPa was assigned.
     The variation of the soil conditions with depth through the considered jack-up area is
shown in the next sections showing different cross sections where the final sand banks
Kellezi, Kudsk, Hofstede




proposed for stabilizing the foundations are included.


                    CONVENTIONAL AND NUMERICAL ANALYSES

Skirted spudcan capacities / stabilities under preloading conditions are investigated
applying different methods of foundation analyses consisting of conventional and 2D / 3D
FE modelling. The common conventional skirted spudcan penetration analyses are not
directly applicable in this case as the thickness of the soil layers vary within the spudcan
area and a uniform soil profile can not be assumed.
       The results from the 2D FE analyses of the free-skirted spudcans – soil interaction
considering shallow sand banks, were found conservative as well. Therefore, 3D FE
modelling was performed assigning boreholes at the location where soil profile changes.
       The preliminary analyses applying cu = 25 kPa for the silt layer showed large
rotations and horizontal movement for the free skirted spudcans S1 and S3 where the
thickness of the silt layer is considerable and variable. Spudcan S2 is found more stable as
the silt layer is almost negligible and the height of the sand bank is conditioned from the
skirt depth.
       An attempt to include some structural stabilizing loads considering leg-spudcan
rigidity while preloading the spudcans was made. The iterative procedure was found
cumbersome and therefore cancelled.
       The issue of structure – foundation - soil interaction was raised at this time. The idea
of a full 3D model consisting of jack-up structure – skirted spudcans founded in the sand
banks constructed over the underlying soil was explored. The height of the gravel banks
were then to be determined based on the limited structural forces evaluated from the rig
designer. The structure – foundation system was investigated under preloading and storm
loading conditions.

Conventional skirted spudcan differential penetration
Before building the full 3D structure foundation model, which is complicated and requires
time for calculation, an investigation on the effect of the sand bank heights on the skirted
spudca bearing capacity and differential penetration at the locations S1 and S2 is carried out.
The minimum height at S2 is already defined.
       Two extreme soil profiles within the spudcan area are chosen, which are expected to
give maximum and minimum penetrations. The differences in penetrations are interpreted
as differential penetrations of the free-skirted spudcan. The method is not considered
accurate for the final design but serves as preliminary evaluation.
       To conventionally define footing penetration depth versus load, calculation of the
static bearing capacity of the spudcan and the skirt elements at various depths, is carried out.
When the spudcan reaches full base contact the assumption for an embedded footing is
applied. This analytical calculation method is previously verified from the FE modelling of
the skirted spudcan resting on different soil conditions.
       The spudcan bearing capacity is calculated conventionally based on SNAME 1 and
Hansen’s theory 2 and a program developed from the experience with spudcan penetration
predictions. The spudcan is simplified to a circular footing having a flat bottom. However,
the effect of the actual spudcan shape is taken into account.
       When frictional soil overlies firm to stiff clay, punching failure is investigated using
a load spread factor 1:3, assumption applied in connection with the skirt effect. This is
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




verified from previous FE analysis of the spudcan penetration in sand-clay soil profiles. In
addition, squeezing of the clay soil below the spudcan skirt is taken into account as well.
       The penetration resistance of the skirt elements is calculated as the sum of the end
resistance and skin resistance. The calculated bearing areas and the skin friction areas are
applied, respectively. Danish Code of Practice for the pile theory is used.
       To see the effect of the sand bank height in the differential penetration at spudcan S1
the elevation of the bank is moved up from -21 m to -19 m to -14 m. No punch through risk
was expected for any of the scenarios. The results for sand bank at elevation –21 m and –19
m are given for illustration in Fig. 6. The maximum preload 145 MN / leg is calculated.
       The conventional analyses for the soil profiles giving maximum penetrations are also
compared with some FE axisymmetric analyses of the spudcan penetration as shown in Fig.
6. Such analyses are previously carried out by Kellezi & Stromann 3, Kellezi et al. 4,,5 etc.

                                        
























Fig. 6, Conventional skirted spudcan differential penetration analysis assuming extreme soil conditions at
S1: a) Sand bank at –21 m; b) Sand bank at –19 m;

       For spudcan S2 the height of the sand bank is equal to the length of the skirt /
chord, plus some tolerance. The top of the bank was assumed at -13.5 m and small
differential penetrations were predicted.
       For spudcan S3 two extreme soil profiles are chosen as well expected to give
maximum and minimum penetrations. The elevation of the gravel bank is moved up from
-25 m to -23 m to -21 m to -18 m to -16 m. No punch through risk is expected.
         To make the location applicable for the rig installation, high sand banks were
necessary based on the conventional and FE axisymmetric results applying the soil
mechanic principle of load spreading. Higher banks increase the bearing capacity of the
silt layer as a result of increasing ‘fictive’ bearing area.
Kellezi, Kudsk, Hofstede




3D FE jack-up – skirted spudcan – sand banks - interaction modelling
The full 3D model is shown in Fig. 7 and 8. Different models with slightly different heights
of the gravel banks were investigated.

         




                      Boreholes




Fig. 7. 3D FE structure-foundation model, 2D build-up, horizontal plane at Hull Level +4.0 m





             S3 Elevation
                –15.8 m                                                     S1 Elevation
                                                                             –14.5 m









            S2 Elevation
              –13.5 m





Fig. 8. 3D FE structure-foundation model, final sand banks
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




      The scenario with sand bank elevations at –14.5 m, (height about 8.5 m), -13.5 m,
(height about 5.5 m), -15.8 m, (height about 10.7 m) for S1, S2 and S3 locations,
respectively was finally proposed.
      The skirted spudcans are simplified by octahedrons. The spudcan is flat and in full
contact with the sand bank from the start of the preloading. The 3 chords are not included.
The tip of the outer skirts is from the start of the analyses at elevation calculated from bank
elevation minus 2.3 m (the skirt length).
      The jack-up structure is modelled as shown in Fig. 8. The leg elements can change
length due to applied axial force. The leg beams and the spudcan plates at the connection
points can simulate the 6 degrees of freedoms.
      The soil conditions, (soil profiles derived from the seismic, PCPT / borehole data at
different cross sections), are modelled by implementing boreholes, as seen from the
horizontal planes in Fig. 7. Some of the cross sections showing the soil profiles / sections
with final gravel banks are given in Fig. 9.


                                     S1 North West-South East

                                                 Sand bank
                Seabed sand




                                                                               S2 North-South




      Silt




             S3 North West-South East


                                                                                      Bedrock




Fig. 9. Cross section profile through the model and the skirted spudcan locations
Kellezi, Kudsk, Hofstede




       The calculation procedure consists of 3 load stages, which are: Preloading to max
vertical load V =145 MN / leg; Unload to vertical V = 112 MN / leg, V = 100 MN / leg, V
= 115 MN / leg for S1, S2, S3, respectively; Storm loading, horizontal H = 6.4 MN, moment
M = 345.6 MNm at the most critical plane for wind speed 33 m/s. The storm load comes
from any direction so different analyses were needed to define the critical one.
        The loads for preloading are applied as vertical forces at each leg. The horizontal
force is applied at the hull plate pointing towards the critical leg. The moment is
implemented as a set of two vertical loads, applied downward at the critical leg-hull
connection and upwards at a point in the hull between the other two legs as shown in Fig.
8. An initial phase is calculated consisting of the construction of the sand banks.
        The limited combined loads at the structure, one single leg, are calculated from
the rig designer as: Horizontal shear force Q = 18 MN / leg; Bending moment at hull M
= 325 MNm / leg;
        The soil strength for the silt layer cu = 25 kPa, initially applied based on the
engineering judgement was not considered a lower bound assessment based on the PCPT
data and usual North Sea (qnet - cu) correlation. After reviewing the available soil data, to
increase to some level safety concerning the soil parameters following DNV 6 it was
decided to reduce the shear strength for the silt layer from cu = 25 kPa to cu = 15 kPa. This
strength is considered a lower bound design value, when taking into account the
consolidation during construction of the banks.
        The FE analyses are carried out with Plaxis programs 7, 8 . The sand bank material
was specified to correspond to the soil strength applied in the analyses. The total volume
of the sand material was about 60000 m3.

Results from the 3D FE structure – foundation model
The results for the initial phase, including the construction of the sand banks indicated
vertical non-uniform settlements of about 30 cm, taken into account in the calculation of the
total sand volume.
       The structural reaction forces for different models and preloading phase are given in
Table 2.
Table 2. Results from 3D FE model, different gravel bank elevation scenarios

          3D models               Silt Undrained Shear      Structure Reaction,   Structure Reaction,
    Sand Bank Elevation (m)         Strength cu (kPa)        Bending Moment           Shear Force
        S1     S2     S3                                        M (MNm)                Q (MN)
       –20.0, -13.5, -24.0               cu = 25                Over Limit            Over Limit
       –16.8, -13.5, -19.1               cu = 25                   295.0                 17.7

       –15.8, -13.5, -18.1               cu = 25                  224.7                  14.4

                                         cu = 20                Over Limit            Over Limit
       –15.8, -13.5, -18.1
                                         cu = 15                Over Limit            Over Limit
       –14.5, -13.5, -16.8
                                         cu = 15                  229.8                  16.1
       –14.0, -13.5, -16.3

       -14.5, -13.5, -15.8               cu = 15                  211.0                  15.1


      The structure and spudcan vertical and maximum horizontal displacements are given
in Fig. 10. The maximum calculated reaction forces are M = 211.04 MNm, shear force Qmax
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




= 15.13 MN, differential penetration at S1 about 20 cm, sliding of S1 about 12 cm. The
calculations for the unloading and storm loading analyses show only slight changes in the
deformations and structure reaction forces.






























Fig. 10. Preloading phase, structure displacements (only plate elements shown):
a) Vertical displacements b) Horizontal displacement

Kellezi, Kudsk, Hofstede




       The mechanism of non-uniform penetration or rotation for S1 an S3 can be explained
with the varying thickness of the total sand material and the underlying silt layer, within the
spudcan area. The outward rotation of S1 is for example expected due to thinner friction
material in the north-northwest.
       The final bank elevations seem to be the optimum ones. Reducing the bank heights at
one location, for example at S3 if elevation is reduced at –16.8 m, this have a strong effect
in the structure reaction forces as seen from the results in Table 2.
       No punch through or rapid penetration was predicted and the spudcans will penetrate
to about full base contact. Some differential spudcan penetrations, rotation and horizontal
movement could though occur during preloading, believed not to be critical for the jack-up
structure. However, from the load displacement curves the inward horizontal movement of
S1 is in the plastic phase and could further develop. Failure figure at for example S1 is given
in Fig. 11. Stability analysis showed safety factor slightly over 1.0.




                           S1 - Critical Section



Fig.









Fig. 11. Critical failure figure at S1, total displacement increments



                                           CONCLUSIONS

3D FE structure - foundation interaction analyses are carried out for the installation of the
world’s largest jack-up rig, offshore, Norway, where seabed features like slopes and
depressions and non-uniform soil conditions were the concern.
  Banks of sands were designed at the skirted spudcan locations with different heights,
ensuring that the structure reaction forces developed during preloading, causing footings
rotation / sliding, did not exceed the calculated limits.
  The jack-up rig was successfully installed at the location and spudcan penetrations /
displacements similar to the predicted values were recorded.
Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling




                               ACKNOWLEDGEMENT

The authors are grateful to Maersk Contractors, Copenhagen for supporting this project.


                                      REFERENCES

1. SNAME, T&R Bulletin 5-5A January 2002. Site Specific Assessment of Mobile
    Jack-Up Units. The Society of Naval Architects and Marine Engineers.
2. Hansen J B. A revised and extended formula for bearing capacity,. Bulletin No. 28,
    1970, The Danish Geotechnical Institute, pp. 5-11.
3. Kellezi, L., and Stromann H., 2003, FEM analysis of jack-up spudcan penetration for
    multi-layered critical soil conditions. Proc. of BGA Intern. Conf. on Foundations,
    ICOF2003, Dundee, Scotland, pp. 410-420.
4. Kellezi L, Hofstede H and Hansen P B. Jack-up footing penetration and fixity analyses,
    Proc. ISFOG 2005, Sept., Perth, Australia, pp. 559 – 565.
5. Kellezi L, H Denver, G Kudsk, H Stadsgaard. FE skirted footings analyses for
    combined loads and layered soil profile, ECSMGE 2007, Proc. pp. 341-346.
6. DNV (Det Norske Veritas) Foundations classification notes No. 30.4. February 1992
7. Plaxis 2002, Version 8.4. User Manual 2D, Delft University of Techn. and Plaxis b.v
8 Plaxis 3D 2006, Foundation Module Version 1.6, Delft Univ. of Techn and Plaxis b.v.

Mais conteúdo relacionado

Mais procurados

Phases of soil investigation
Phases of soil investigationPhases of soil investigation
Phases of soil investigationMachenLink
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecturegefyra-rion
 
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...bhupendra kumar verma
 
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMN
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMNA STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMN
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMNIAEME Publication
 
General Geotechnical Presentation
General Geotechnical PresentationGeneral Geotechnical Presentation
General Geotechnical Presentationandroid9999
 
Ground Improvement by Vibro Stone Columns
Ground Improvement by Vibro Stone ColumnsGround Improvement by Vibro Stone Columns
Ground Improvement by Vibro Stone ColumnsDesh Sonyok
 
soil_mechanics_lecture_slides
soil_mechanics_lecture_slidessoil_mechanics_lecture_slides
soil_mechanics_lecture_slidesMahendra Gattu
 
Somnath soni (iit ism) dhanbad presentation vphep
Somnath soni (iit ism) dhanbad presentation vphepSomnath soni (iit ism) dhanbad presentation vphep
Somnath soni (iit ism) dhanbad presentation vphepSomnath Soni
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 peckergefyra-rion
 
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...Egyptian Engineers Association
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentIJERD Editor
 
The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigationAngelo Indelicato
 
site investigation
site investigationsite investigation
site investigationolvive1208
 
IRJET- Investigations of Granular Pile Anchors in Granulated Soil Subject...
IRJET-  	  Investigations of Granular Pile Anchors in Granulated Soil Subject...IRJET-  	  Investigations of Granular Pile Anchors in Granulated Soil Subject...
IRJET- Investigations of Granular Pile Anchors in Granulated Soil Subject...IRJET Journal
 
Introduction to Geotechnical Engineering SU - Fall 2015
Introduction to Geotechnical Engineering   SU - Fall 2015Introduction to Geotechnical Engineering   SU - Fall 2015
Introduction to Geotechnical Engineering SU - Fall 2015bhaladog
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005gefyra-rion
 

Mais procurados (20)

Phases of soil investigation
Phases of soil investigationPhases of soil investigation
Phases of soil investigation
 
4th athenian lecture
4th athenian lecture4th athenian lecture
4th athenian lecture
 
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...
Comparitive study-of-pile-foundations-with-foundations-on-stone-column-treate...
 
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMN
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMNA STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMN
A STUDY ON EFFECTS OF GEOSYNTHETIC ENCASEMENT ON FLOATING STONE COLUMN
 
General Geotechnical Presentation
General Geotechnical PresentationGeneral Geotechnical Presentation
General Geotechnical Presentation
 
Dfi2005 pecker
Dfi2005 peckerDfi2005 pecker
Dfi2005 pecker
 
Engineering geology of dam
Engineering geology of damEngineering geology of dam
Engineering geology of dam
 
Ground Improvement by Vibro Stone Columns
Ground Improvement by Vibro Stone ColumnsGround Improvement by Vibro Stone Columns
Ground Improvement by Vibro Stone Columns
 
Presentation geotechnical investigation
Presentation  geotechnical investigationPresentation  geotechnical investigation
Presentation geotechnical investigation
 
soil_mechanics_lecture_slides
soil_mechanics_lecture_slidessoil_mechanics_lecture_slides
soil_mechanics_lecture_slides
 
Somnath soni (iit ism) dhanbad presentation vphep
Somnath soni (iit ism) dhanbad presentation vphepSomnath soni (iit ism) dhanbad presentation vphep
Somnath soni (iit ism) dhanbad presentation vphep
 
Geo trans2004 pecker
Geo trans2004 peckerGeo trans2004 pecker
Geo trans2004 pecker
 
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
124 مبادرة #تواصل_تطوير -المركبات البوليمرية الجيوتقنية و تطبيقاتها في الهندس...
 
International Journal of Engineering Research and Development
International Journal of Engineering Research and DevelopmentInternational Journal of Engineering Research and Development
International Journal of Engineering Research and Development
 
The role of site investigation
The role of site investigationThe role of site investigation
The role of site investigation
 
site investigation
site investigationsite investigation
site investigation
 
Dam, reservoir & tunnels
Dam, reservoir & tunnelsDam, reservoir & tunnels
Dam, reservoir & tunnels
 
IRJET- Investigations of Granular Pile Anchors in Granulated Soil Subject...
IRJET-  	  Investigations of Granular Pile Anchors in Granulated Soil Subject...IRJET-  	  Investigations of Granular Pile Anchors in Granulated Soil Subject...
IRJET- Investigations of Granular Pile Anchors in Granulated Soil Subject...
 
Introduction to Geotechnical Engineering SU - Fall 2015
Introduction to Geotechnical Engineering   SU - Fall 2015Introduction to Geotechnical Engineering   SU - Fall 2015
Introduction to Geotechnical Engineering SU - Fall 2015
 
Athens pecker 2005
Athens pecker 2005Athens pecker 2005
Athens pecker 2005
 

Destaque

Construction of marine and offshore structures b. gerwick (second edition)
Construction of marine and offshore structures   b. gerwick (second edition)Construction of marine and offshore structures   b. gerwick (second edition)
Construction of marine and offshore structures b. gerwick (second edition)OFFSHORE VN
 
Bao cao thuc tap tot ngiep
Bao cao thuc tap tot ngiepBao cao thuc tap tot ngiep
Bao cao thuc tap tot ngiepOFFSHORE VN
 
Ly thuyet do tin cay
Ly thuyet do tin cayLy thuyet do tin cay
Ly thuyet do tin cayOFFSHORE VN
 
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lan
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lanTính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lan
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lanOFFSHORE VN
 
Tính toán dđr inplace
Tính toán dđr  inplaceTính toán dđr  inplace
Tính toán dđr inplaceOFFSHORE VN
 
Guidelines for marine lifting operation noble denton
Guidelines for marine lifting operation noble dentonGuidelines for marine lifting operation noble denton
Guidelines for marine lifting operation noble dentonOFFSHORE VN
 
Dinh chim kcd bang sa lan
Dinh chim kcd bang sa lanDinh chim kcd bang sa lan
Dinh chim kcd bang sa lanOFFSHORE VN
 
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGE
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGEFINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGE
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGEOFFSHORE VN
 
19100309 offshore-platform-design
19100309 offshore-platform-design19100309 offshore-platform-design
19100309 offshore-platform-designOFFSHORE VN
 
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.net
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.netQui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.net
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.netOFFSHORE VN
 

Destaque (20)

Download here
Download hereDownload here
Download here
 
Construction of marine and offshore structures b. gerwick (second edition)
Construction of marine and offshore structures   b. gerwick (second edition)Construction of marine and offshore structures   b. gerwick (second edition)
Construction of marine and offshore structures b. gerwick (second edition)
 
Bao cao thuc tap tot ngiep
Bao cao thuc tap tot ngiepBao cao thuc tap tot ngiep
Bao cao thuc tap tot ngiep
 
Download here
Download hereDownload here
Download here
 
Ly thuyet do tin cay
Ly thuyet do tin cayLy thuyet do tin cay
Ly thuyet do tin cay
 
7485 pdf c01
7485 pdf c017485 pdf c01
7485 pdf c01
 
Download
DownloadDownload
Download
 
Download
DownloadDownload
Download
 
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lan
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lanTính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lan
Tính toán thiết kế vận chuyển khối chân đế trên biển bằng sà lan
 
Download
DownloadDownload
Download
 
Download
DownloadDownload
Download
 
Download
DownloadDownload
Download
 
Tính toán dđr inplace
Tính toán dđr  inplaceTính toán dđr  inplace
Tính toán dđr inplace
 
Guidelines for marine lifting operation noble denton
Guidelines for marine lifting operation noble dentonGuidelines for marine lifting operation noble denton
Guidelines for marine lifting operation noble denton
 
Dinh chim kcd bang sa lan
Dinh chim kcd bang sa lanDinh chim kcd bang sa lan
Dinh chim kcd bang sa lan
 
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGE
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGEFINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGE
FINITE ELEMENT MODELING AND JACKET LAUCH ANALYSIS USING A BARGE
 
19100309 offshore-platform-design
19100309 offshore-platform-design19100309 offshore-platform-design
19100309 offshore-platform-design
 
Download
DownloadDownload
Download
 
Sap
SapSap
Sap
 
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.net
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.netQui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.net
Qui dinh kt_khai_thac_cau_cang-2003___cong_trinhbien.net
 

Semelhante a Download

302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundationsJunaida Wally
 
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction""Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"Remedy Geotechnics Ltd
 
Conference paper subgrade reaction
Conference paper subgrade reactionConference paper subgrade reaction
Conference paper subgrade reactionabdulhakim mawas
 
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...IRJET Journal
 
Bearing capacity of sand overlying clay strip footing - paxis 3 d
Bearing capacity of sand overlying clay   strip footing - paxis 3 dBearing capacity of sand overlying clay   strip footing - paxis 3 d
Bearing capacity of sand overlying clay strip footing - paxis 3 dGonzalo Nureña Zegarra
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006gefyra-rion
 
High-Resolution 3D Seismic: Coal Mines Fields
High-Resolution 3D Seismic: Coal Mines FieldsHigh-Resolution 3D Seismic: Coal Mines Fields
High-Resolution 3D Seismic: Coal Mines FieldsAli Osman Öncel
 
Performance of square footing resting on laterally confined sand
Performance of square footing resting on laterally confined sandPerformance of square footing resting on laterally confined sand
Performance of square footing resting on laterally confined sandeSAT Publishing House
 
SUBSOIL EXPLORATION 35.pptx
SUBSOIL EXPLORATION 35.pptxSUBSOIL EXPLORATION 35.pptx
SUBSOIL EXPLORATION 35.pptxKamalineeNayak
 
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless Soil
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless SoilEccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless Soil
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless SoilIJERA Editor
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation supportJim McMullan
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewR K DHIMAN
 
Geostatistical approach to the estimation of the uncertainty and spatial vari...
Geostatistical approach to the estimation of the uncertainty and spatial vari...Geostatistical approach to the estimation of the uncertainty and spatial vari...
Geostatistical approach to the estimation of the uncertainty and spatial vari...IOSR Journals
 
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxHORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxSamirsinh Parmar
 
INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxCarolTumaneng
 
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined LoadBehaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined LoadIJERA Editor
 
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load IJERA Editor
 

Semelhante a Download (20)

302 settlement of piled foundations
302 settlement of piled foundations302 settlement of piled foundations
302 settlement of piled foundations
 
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction""Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
"Challenges Faced in 3-D Finite Element Modelling of Stone Column Construction"
 
Conference paper subgrade reaction
Conference paper subgrade reactionConference paper subgrade reaction
Conference paper subgrade reaction
 
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
PERFORMANCE EVALUATION OF DEEP EXCAVATION UNDER STATIC AND SEISMIC LOAD CONDI...
 
Bearing capacity of sand overlying clay strip footing - paxis 3 d
Bearing capacity of sand overlying clay   strip footing - paxis 3 dBearing capacity of sand overlying clay   strip footing - paxis 3 d
Bearing capacity of sand overlying clay strip footing - paxis 3 d
 
Mokpo symposium pecker 2006
Mokpo symposium pecker 2006Mokpo symposium pecker 2006
Mokpo symposium pecker 2006
 
High-Resolution 3D Seismic: Coal Mines Fields
High-Resolution 3D Seismic: Coal Mines FieldsHigh-Resolution 3D Seismic: Coal Mines Fields
High-Resolution 3D Seismic: Coal Mines Fields
 
Ijciet 10 02_061
Ijciet 10 02_061Ijciet 10 02_061
Ijciet 10 02_061
 
Performance of square footing resting on laterally confined sand
Performance of square footing resting on laterally confined sandPerformance of square footing resting on laterally confined sand
Performance of square footing resting on laterally confined sand
 
SUBSOIL EXPLORATION 35.pptx
SUBSOIL EXPLORATION 35.pptxSUBSOIL EXPLORATION 35.pptx
SUBSOIL EXPLORATION 35.pptx
 
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless Soil
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless SoilEccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless Soil
Eccentrically Loaded Small Scale Ring Footing on Resting on Cohesionless Soil
 
Soil cement walls for excavation support
Soil cement walls for excavation supportSoil cement walls for excavation support
Soil cement walls for excavation support
 
Deep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over viewDeep foundation construction in bouldery bed an over view
Deep foundation construction in bouldery bed an over view
 
Ijciet 06 10_008
Ijciet 06 10_008Ijciet 06 10_008
Ijciet 06 10_008
 
Geostatistical approach to the estimation of the uncertainty and spatial vari...
Geostatistical approach to the estimation of the uncertainty and spatial vari...Geostatistical approach to the estimation of the uncertainty and spatial vari...
Geostatistical approach to the estimation of the uncertainty and spatial vari...
 
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptxHORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
HORIZONTAL ANCHOR IN REINFORCED EARTH.pptx
 
INTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptxINTRODUCTION_AND_geotechnical_activities(2).pptx
INTRODUCTION_AND_geotechnical_activities(2).pptx
 
Auckland
AucklandAuckland
Auckland
 
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined LoadBehaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
 
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
Behaviour of Single Pile in Reinforced Slope Subjected to Inclined Load
 

Último

Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024The Digital Insurer
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfsudhanshuwaghmare1
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfhans926745
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?Igalia
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024The Digital Insurer
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)Gabriella Davis
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdflior mazor
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerThousandEyes
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsJoaquim Jorge
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesBoston Institute of Analytics
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024The Digital Insurer
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 

Último (20)

Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law DevelopmentsTrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
TrustArc Webinar - Stay Ahead of US State Data Privacy Law Developments
 
Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024Axa Assurance Maroc - Insurer Innovation Award 2024
Axa Assurance Maroc - Insurer Innovation Award 2024
 
Boost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdfBoost Fertility New Invention Ups Success Rates.pdf
Boost Fertility New Invention Ups Success Rates.pdf
 
Tech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdfTech Trends Report 2024 Future Today Institute.pdf
Tech Trends Report 2024 Future Today Institute.pdf
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?A Year of the Servo Reboot: Where Are We Now?
A Year of the Servo Reboot: Where Are We Now?
 
Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024Partners Life - Insurer Innovation Award 2024
Partners Life - Insurer Innovation Award 2024
 
A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)A Domino Admins Adventures (Engage 2024)
A Domino Admins Adventures (Engage 2024)
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
GenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdfGenAI Risks & Security Meetup 01052024.pdf
GenAI Risks & Security Meetup 01052024.pdf
 
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
How to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected WorkerHow to Troubleshoot Apps for the Modern Connected Worker
How to Troubleshoot Apps for the Modern Connected Worker
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
Artificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and MythsArtificial Intelligence: Facts and Myths
Artificial Intelligence: Facts and Myths
 
HTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation StrategiesHTML Injection Attacks: Impact and Mitigation Strategies
HTML Injection Attacks: Impact and Mitigation Strategies
 
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
Bajaj Allianz Life Insurance Company - Insurer Innovation Award 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 

Download

  • 1. JACK-UP RIG FOUNDATION DESIGN APPLYING 3D FE STRUCTURE - SOIL - INTERACTION MODELLING L KELLEZI GEO - Danish Geotechnical Institute 1 Maglebjergvej, DK 2800 Kgs. Lyngby, Denmark G KUDSK Maersk Contractors Esplanaden 50, DK 1098 Copenhagen K, Denmark H HOFSTEDE Marine Structure Consultants (MSC) Karel Doormanweg 66, 3100 AR Schiedam, Netherlands SUMMARY: The foundation engineering assessment for the world’s largest jack-up rig installed offshore Norway is carried out. Based on the site survey and soil investigation data the soil conditions vary accross the site and consist of bedrock overlied by very soft silt / clay and a shallow layer of seabed sand. From the conventional and finite element analyses an engineering solution comprizing construction of sand banks was proposed. The final geometry of the banks is determined based on the three – dimensional (3D) finite element (FE) integrated jack-up structure – skirted spudcan – soil – interaction modellings documenting that during the rig installation / preloading and storm loading the structural forces fall within the accepted limits. The rig was suceessfully installed and upgraded verifying the engineering predictions. INTRODUCTION In the design and installation of different offshore structures an important aspect is the investigation of the seabed conditions considering features such as slopes, depressions, boulders, seabed inclination etc. Particularly for a jack-up drilling rig, which is supported by three independents legs at an approximate distance of (50 – 60) m from each other, this is a very important issue. In addition to seabed features the variation of the soil conditions in depth and horizontal directions, at the three footing locations plays also a decisive role in the structure and foundation solution. A geotechnical engineering assessment for the world's largest jack-up rig is given in L Kellezi, G Kudsk, H Hofstede, Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling Proceedings of the BGA International Conference on Foundations, Dundee, Scotland,24 – 27 June 2008. IHS BRE Press, 2008.
  • 2. Kellezi, Kudsk, Hofstede this paper. The rig was temporarily installed next to a quay of a Norwegian yard in order to be upgraded for further production work in the North Sea. The preliminary site survey indicated that the seabed in the considered area of location was rock outcrop, undulating across the site creating slopes and depressions. As the current rig’s footings are skirted spudcans with areas exceeding the plan dimensions of the seabed features and the skirts cannot penetrate through the rock, seabed modification was necessary. The idea of creating flat areas at the footing’s locations, through construction of shallow gravel / sand banks to a height slightly larger than the skirt heights, was initially proposed. After the preliminary site survey a detailed geotechnical investigation was carried out to verify the soil conditions. From the investigation a sediment layer of varying thickness overlying the undulating bedrock was identified. Preliminary conventional and numerical skirted spudcan penetration analyses, with originally low and lately rather increased elevations of the sand banks, indicated non-uniform penetration, sliding and rotation of the free skirted spudcans under preloading conditions. For a more realistic evaluation, jack-up structure - foundation interaction effects were accounted for in the analyses. The full 3D FE jack-up structure – skirted spudcans – sand bank – soil - interaction models were applied for varying heights of the sand banks, investigating the non-uniform footings penetrations, rotations and sliding and how they effect the structure. After an extensive amount of analyses, the final heights of the sand banks are proposed. JACK-UP STRUCTURE – SKIRTED SPUDCAN - SOIL SYSTEM The current jack-up drilling rig, the world’s largest, is type independent leg cantilever and is shown in Fig. 1 in comparison to other world known structures. It operates in water depths up to 150 m and it has leg lengths of about 205 m. 300 m 200 m 100 m Eiffel Tower Tower Bridge Maersk London Eye Great Belt East Inspirer Bridge Pylon Fig. 1. The jack-up rig in comparison to other structures Structure elements and stiffness In the 3D FE jack-up - foundation - interaction model only the main structure elements such
  • 3. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling as the three legs and the hull were included. The legs were simplified to 3D beam elements, and the hull to plate or floor elements with the equivalent thickness. The rig designer provided the geometry data for the legs and the hull. Skirted spudcan geometry The considered jack-up footings have a diameter D = 22 m and are fitted with outer and internal skirts, which divide the spudcan into 6 compartments. Fig. 2 shows photo views of the spudcan inside and a 3D model. Fig. 2. Jack-up skirted spudcan The vertical geometry of the spudcan structure is mainly given by: Distance from spudcan base to tip of outer skirts 2.3 m; Distance from spudcan base to tip of internal skirts 1.1 m; The spudcan itself is almost a flat rigid plate. The transverse stiffnesses of the skirts are derived from the structural FE model of the spudcan. These thicknesses are applied in the 3D FE analyses employing wall structural elements, respectively. Interpretation of the soil conditions Except the preliminary site survey, to identify the seabed and the soil conditions at the considered spudcan locations a new site survey, seismic, (sparker and pinger) and bathymetry was carried out. Sediments of varying thickness overlaying the bedrock were interpreted. The largest sediment thicknesses were seen at the largest water depth. Gravity vibrocore samples taken from seabed could not reach the bedrock and showed mostly sediments of clayey, gravely sand. At the shallow water depths the bedrock outcrops the seabed. After the interpretation of the seismic survey geotechnical investigation including 5 piezo-cone penetration tests (PCPTs) and one vibrocore for each spudcan location were carried out. Discrepancies were though recognized at some PCPT locations. Considering the limitations of the sparker survey, a pinger survey was carried out. With a less penetrating, but a smaller opening angle seismic source, the pinger survey was applied to better identify the slope of the bedrock and supplement the previous investigations in the area. Based on the pinger data combined with the existing and new soil information, a re-interpreted model of the sediment and bedrock surface was produced. Several originally proposed locations were studied finally focusing on one of them. At each leg position four vertical cross sections such as north - south, west - east, northwest - southeast, northeast - southwest were interpreted showing the seabed depth and the depth of the top bedrock from the centre of the spudcans out to a distance of 50 m.
  • 4. Kellezi, Kudsk, Hofstede To estimate the variation in thickness of the soil layers between the bedrock and the seabed and the soil parameters applicable to the design of the foundations at the final location a new geotechnical investigation consisting of 5 boreholes, about 70 PCPTs and laboratory tests, classification and simple and advanced strength tests were carried out. From the engineering interpretation of the gathered soil data it was assessed that the soil conditions consist of overall quaternary marine sediments, mainly deposits consisting of a seabed layer of sand overlying clayey, sandy silt with variable thickness (0 - 9) m overlying crystalline bedrock. Water depth variation The water depth at the centre of the three chosen spudcan locations are as seen from Fig. 3, approximately –23 m at spudcan S1, -19 m at S2 and –26.5 m at S3. So the location of S2 is shallowest, becoming deeper at S1 and even deeper at S3.                  Fig. 3. Bathymetry at the considered rig location Design soil profiles and parameters On the basis of the seismic surveys, PCPTs / boreholes and laboratory test results (classification and triaxial, unconsolidated undrained (UU) and consolidated isotropic drained (CID)) the soil profiles and soil parameters applicable to the engineering assessment of the jack-up at the considered location are derived. A good correlation with the PCPT data was investigated for the depths where soil samples were taken and laboratory tests performed. However, at the depths where lower cone strength as shown in Fig. 4 and Fig. 5 were recorded no soil sample could be extracted and no correlation was available. Under these circumstances the cone factor N = qnet / cu = (15 – 20) was used. When applying such a correlation on the PCPT data undrained shear strength for the silt cu = (15 – 25) kPa were assessed. Based on the test results and the engineering judgement initially cu = 25 kPa for the silt and a friction angle = 35 for the seabed sand were applied.
  • 5. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling Fig. 4. PCPT profile at S1 location Fig. 5. PCPT profile at S3 location The soil parameters for the bedrock are evaluated based on the engineering experience. An undrained shear strength cu = (1000 – 1500) kPa was assigned. ‘As it was’ soil profile at the three spudcan location can be given by Table 1. There are three soil layers throughout the site. However, the thickness and the elevations of the layers strongly vary not only between the spudcan locations but also within the spudcan areas. Table 1. ‘As it was´ soil profile at the considered jack- up footings locations Angle of Depth of Undrained Deformation Unit weight internal friction Soil description layer shear strength Modulus ' (kN/m3) and dilation h (m) cu (kN/m2) E (kN / m2) () () SAND, dense Variable 10.0 35 5 - 35000 SILT / CLAY, very Variable 9.0 - - 25 / 15 100 * cu soft to soft BEDROCK Variable 12.0 - - 1500 / 1000 200 * cu The material of the sand bank constructed over the seabed at the spudcan locations is modelled applying a unit weight ' = 11 kN/m3, a friction angle = (40 – 45) and a dilation angle = (10 – 15) . The deformation parameters E = 100000 kPa was assigned. The variation of the soil conditions with depth through the considered jack-up area is shown in the next sections showing different cross sections where the final sand banks
  • 6. Kellezi, Kudsk, Hofstede proposed for stabilizing the foundations are included. CONVENTIONAL AND NUMERICAL ANALYSES Skirted spudcan capacities / stabilities under preloading conditions are investigated applying different methods of foundation analyses consisting of conventional and 2D / 3D FE modelling. The common conventional skirted spudcan penetration analyses are not directly applicable in this case as the thickness of the soil layers vary within the spudcan area and a uniform soil profile can not be assumed. The results from the 2D FE analyses of the free-skirted spudcans – soil interaction considering shallow sand banks, were found conservative as well. Therefore, 3D FE modelling was performed assigning boreholes at the location where soil profile changes. The preliminary analyses applying cu = 25 kPa for the silt layer showed large rotations and horizontal movement for the free skirted spudcans S1 and S3 where the thickness of the silt layer is considerable and variable. Spudcan S2 is found more stable as the silt layer is almost negligible and the height of the sand bank is conditioned from the skirt depth. An attempt to include some structural stabilizing loads considering leg-spudcan rigidity while preloading the spudcans was made. The iterative procedure was found cumbersome and therefore cancelled. The issue of structure – foundation - soil interaction was raised at this time. The idea of a full 3D model consisting of jack-up structure – skirted spudcans founded in the sand banks constructed over the underlying soil was explored. The height of the gravel banks were then to be determined based on the limited structural forces evaluated from the rig designer. The structure – foundation system was investigated under preloading and storm loading conditions. Conventional skirted spudcan differential penetration Before building the full 3D structure foundation model, which is complicated and requires time for calculation, an investigation on the effect of the sand bank heights on the skirted spudca bearing capacity and differential penetration at the locations S1 and S2 is carried out. The minimum height at S2 is already defined. Two extreme soil profiles within the spudcan area are chosen, which are expected to give maximum and minimum penetrations. The differences in penetrations are interpreted as differential penetrations of the free-skirted spudcan. The method is not considered accurate for the final design but serves as preliminary evaluation. To conventionally define footing penetration depth versus load, calculation of the static bearing capacity of the spudcan and the skirt elements at various depths, is carried out. When the spudcan reaches full base contact the assumption for an embedded footing is applied. This analytical calculation method is previously verified from the FE modelling of the skirted spudcan resting on different soil conditions. The spudcan bearing capacity is calculated conventionally based on SNAME 1 and Hansen’s theory 2 and a program developed from the experience with spudcan penetration predictions. The spudcan is simplified to a circular footing having a flat bottom. However, the effect of the actual spudcan shape is taken into account. When frictional soil overlies firm to stiff clay, punching failure is investigated using a load spread factor 1:3, assumption applied in connection with the skirt effect. This is
  • 7. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling verified from previous FE analysis of the spudcan penetration in sand-clay soil profiles. In addition, squeezing of the clay soil below the spudcan skirt is taken into account as well. The penetration resistance of the skirt elements is calculated as the sum of the end resistance and skin resistance. The calculated bearing areas and the skin friction areas are applied, respectively. Danish Code of Practice for the pile theory is used. To see the effect of the sand bank height in the differential penetration at spudcan S1 the elevation of the bank is moved up from -21 m to -19 m to -14 m. No punch through risk was expected for any of the scenarios. The results for sand bank at elevation –21 m and –19 m are given for illustration in Fig. 6. The maximum preload 145 MN / leg is calculated. The conventional analyses for the soil profiles giving maximum penetrations are also compared with some FE axisymmetric analyses of the spudcan penetration as shown in Fig. 6. Such analyses are previously carried out by Kellezi & Stromann 3, Kellezi et al. 4,,5 etc.                              Fig. 6, Conventional skirted spudcan differential penetration analysis assuming extreme soil conditions at S1: a) Sand bank at –21 m; b) Sand bank at –19 m; For spudcan S2 the height of the sand bank is equal to the length of the skirt / chord, plus some tolerance. The top of the bank was assumed at -13.5 m and small differential penetrations were predicted. For spudcan S3 two extreme soil profiles are chosen as well expected to give maximum and minimum penetrations. The elevation of the gravel bank is moved up from -25 m to -23 m to -21 m to -18 m to -16 m. No punch through risk is expected. To make the location applicable for the rig installation, high sand banks were necessary based on the conventional and FE axisymmetric results applying the soil mechanic principle of load spreading. Higher banks increase the bearing capacity of the silt layer as a result of increasing ‘fictive’ bearing area.
  • 8. Kellezi, Kudsk, Hofstede 3D FE jack-up – skirted spudcan – sand banks - interaction modelling The full 3D model is shown in Fig. 7 and 8. Different models with slightly different heights of the gravel banks were investigated.  Boreholes Fig. 7. 3D FE structure-foundation model, 2D build-up, horizontal plane at Hull Level +4.0 m      S3 Elevation –15.8 m S1 Elevation  –14.5 m           S2 Elevation  –13.5 m  Fig. 8. 3D FE structure-foundation model, final sand banks
  • 9. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling The scenario with sand bank elevations at –14.5 m, (height about 8.5 m), -13.5 m, (height about 5.5 m), -15.8 m, (height about 10.7 m) for S1, S2 and S3 locations, respectively was finally proposed. The skirted spudcans are simplified by octahedrons. The spudcan is flat and in full contact with the sand bank from the start of the preloading. The 3 chords are not included. The tip of the outer skirts is from the start of the analyses at elevation calculated from bank elevation minus 2.3 m (the skirt length). The jack-up structure is modelled as shown in Fig. 8. The leg elements can change length due to applied axial force. The leg beams and the spudcan plates at the connection points can simulate the 6 degrees of freedoms. The soil conditions, (soil profiles derived from the seismic, PCPT / borehole data at different cross sections), are modelled by implementing boreholes, as seen from the horizontal planes in Fig. 7. Some of the cross sections showing the soil profiles / sections with final gravel banks are given in Fig. 9. S1 North West-South East Sand bank Seabed sand S2 North-South Silt S3 North West-South East Bedrock Fig. 9. Cross section profile through the model and the skirted spudcan locations
  • 10. Kellezi, Kudsk, Hofstede The calculation procedure consists of 3 load stages, which are: Preloading to max vertical load V =145 MN / leg; Unload to vertical V = 112 MN / leg, V = 100 MN / leg, V = 115 MN / leg for S1, S2, S3, respectively; Storm loading, horizontal H = 6.4 MN, moment M = 345.6 MNm at the most critical plane for wind speed 33 m/s. The storm load comes from any direction so different analyses were needed to define the critical one. The loads for preloading are applied as vertical forces at each leg. The horizontal force is applied at the hull plate pointing towards the critical leg. The moment is implemented as a set of two vertical loads, applied downward at the critical leg-hull connection and upwards at a point in the hull between the other two legs as shown in Fig. 8. An initial phase is calculated consisting of the construction of the sand banks. The limited combined loads at the structure, one single leg, are calculated from the rig designer as: Horizontal shear force Q = 18 MN / leg; Bending moment at hull M = 325 MNm / leg; The soil strength for the silt layer cu = 25 kPa, initially applied based on the engineering judgement was not considered a lower bound assessment based on the PCPT data and usual North Sea (qnet - cu) correlation. After reviewing the available soil data, to increase to some level safety concerning the soil parameters following DNV 6 it was decided to reduce the shear strength for the silt layer from cu = 25 kPa to cu = 15 kPa. This strength is considered a lower bound design value, when taking into account the consolidation during construction of the banks. The FE analyses are carried out with Plaxis programs 7, 8 . The sand bank material was specified to correspond to the soil strength applied in the analyses. The total volume of the sand material was about 60000 m3. Results from the 3D FE structure – foundation model The results for the initial phase, including the construction of the sand banks indicated vertical non-uniform settlements of about 30 cm, taken into account in the calculation of the total sand volume. The structural reaction forces for different models and preloading phase are given in Table 2. Table 2. Results from 3D FE model, different gravel bank elevation scenarios  3D models Silt Undrained Shear Structure Reaction, Structure Reaction, Sand Bank Elevation (m) Strength cu (kPa) Bending Moment Shear Force S1 S2 S3 M (MNm) Q (MN) –20.0, -13.5, -24.0 cu = 25 Over Limit Over Limit –16.8, -13.5, -19.1 cu = 25 295.0 17.7 –15.8, -13.5, -18.1 cu = 25 224.7 14.4 cu = 20 Over Limit Over Limit –15.8, -13.5, -18.1 cu = 15 Over Limit Over Limit –14.5, -13.5, -16.8 cu = 15 229.8 16.1 –14.0, -13.5, -16.3 -14.5, -13.5, -15.8 cu = 15 211.0 15.1  The structure and spudcan vertical and maximum horizontal displacements are given in Fig. 10. The maximum calculated reaction forces are M = 211.04 MNm, shear force Qmax
  • 11. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling = 15.13 MN, differential penetration at S1 about 20 cm, sliding of S1 about 12 cm. The calculations for the unloading and storm loading analyses show only slight changes in the deformations and structure reaction forces.                        Fig. 10. Preloading phase, structure displacements (only plate elements shown): a) Vertical displacements b) Horizontal displacement 
  • 12. Kellezi, Kudsk, Hofstede The mechanism of non-uniform penetration or rotation for S1 an S3 can be explained with the varying thickness of the total sand material and the underlying silt layer, within the spudcan area. The outward rotation of S1 is for example expected due to thinner friction material in the north-northwest. The final bank elevations seem to be the optimum ones. Reducing the bank heights at one location, for example at S3 if elevation is reduced at –16.8 m, this have a strong effect in the structure reaction forces as seen from the results in Table 2. No punch through or rapid penetration was predicted and the spudcans will penetrate to about full base contact. Some differential spudcan penetrations, rotation and horizontal movement could though occur during preloading, believed not to be critical for the jack-up structure. However, from the load displacement curves the inward horizontal movement of S1 is in the plastic phase and could further develop. Failure figure at for example S1 is given in Fig. 11. Stability analysis showed safety factor slightly over 1.0.      S1 - Critical Section    Fig.      Fig. 11. Critical failure figure at S1, total displacement increments CONCLUSIONS 3D FE structure - foundation interaction analyses are carried out for the installation of the world’s largest jack-up rig, offshore, Norway, where seabed features like slopes and depressions and non-uniform soil conditions were the concern. Banks of sands were designed at the skirted spudcan locations with different heights, ensuring that the structure reaction forces developed during preloading, causing footings rotation / sliding, did not exceed the calculated limits. The jack-up rig was successfully installed at the location and spudcan penetrations / displacements similar to the predicted values were recorded.
  • 13. Jack-up Rig Foundation Design Applying 3D FE Structure-Soil-Interaction Modeling ACKNOWLEDGEMENT The authors are grateful to Maersk Contractors, Copenhagen for supporting this project.  REFERENCES 1. SNAME, T&R Bulletin 5-5A January 2002. Site Specific Assessment of Mobile Jack-Up Units. The Society of Naval Architects and Marine Engineers. 2. Hansen J B. A revised and extended formula for bearing capacity,. Bulletin No. 28, 1970, The Danish Geotechnical Institute, pp. 5-11. 3. Kellezi, L., and Stromann H., 2003, FEM analysis of jack-up spudcan penetration for multi-layered critical soil conditions. Proc. of BGA Intern. Conf. on Foundations, ICOF2003, Dundee, Scotland, pp. 410-420. 4. Kellezi L, Hofstede H and Hansen P B. Jack-up footing penetration and fixity analyses, Proc. ISFOG 2005, Sept., Perth, Australia, pp. 559 – 565. 5. Kellezi L, H Denver, G Kudsk, H Stadsgaard. FE skirted footings analyses for combined loads and layered soil profile, ECSMGE 2007, Proc. pp. 341-346. 6. DNV (Det Norske Veritas) Foundations classification notes No. 30.4. February 1992 7. Plaxis 2002, Version 8.4. User Manual 2D, Delft University of Techn. and Plaxis b.v 8 Plaxis 3D 2006, Foundation Module Version 1.6, Delft Univ. of Techn and Plaxis b.v.