SlideShare uma empresa Scribd logo
1 de 35
Baixar para ler offline
The Panama Canal
Expansion Program




                      José Barrios Ng
                  Deputy Administrator
                Panama Canal Authority
                            April 2010
Program Components                                                                             15.8 M m3


        $5.25 billion investment
Atlantic Ocean


Post-Panamax Locks -                                   Increasing Gatun Lake’s
     Atlantic Side                                    Maximum Operational Level                         Deepening and
                                                                                                        Widening of the
                                                                                                       Atlantic Entrance

                                                                                                Post-Panamax
                                                                                              Locks – Pacific Side
                                                                   26.7 m       27.1 m



                  Deepening and Widening of
                 Gatun Lake’s and Gaillard Cut’s
                     Navigational Channels




                                                                                                                                     8.7 M m3

                                        Access Channel to Post-Panamax Locks - Pacific Side
                                                                                                                           Deepening and
                                                                                                                           Widening of the
                                                            49 M m3                                                        Pacific Entrance



                                                                                                    Pacific Ocean
Locks and vessels sizes
Existing locks' maximum vessel size: 4,400 TEU
                                                    33.5 m (110’)




                                  32.3 m (106’)

    12.4 m
    (39.5’)                                                                  55 m (180’)




              12.8 m (42’)
                                                  49 m (160’)




                              18.3 m (60’)
                                                                    15.2 m
                                                                     (50’)




              New locks' maximum vessel size: 12,600 TEU
Pacific Access Channel - Phase 1

Programmed                                   100%
     Actual                                  100%
          0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%   Contract Scope: 7.4 Mm3, cleaning 146 hectares of
                                                        MEC and relocation of a 3.6 km stretch of Borinquen
  Excavated 7.3 M m3                                    road

  July 15, 2009                                         Awarded: 17 July, 2007
                         136 m                          Amount Awarded: B/.41,094,000.00
                                                        Amount Paid: B/. 40,431,196.00

                                 46 m
                                                • Contractor passed final inspection –
                                                  project is completed
   Original
                                                • Administrative closure in process
  Original 2009
   July 15,                                                                                         MEC 1
                                                                                                    146 Has
                                                                                                    cleaned


                                                        Borinquen
                                                          Road




                                                                                                     4
Pacific Access Channel - Phase 2                 Programmed                                  99.9%
                                                 Actual                                      99.6%
  7.4 M m3 excavated                        0     10      20   30   40   50   60   70   80       90   100


                          Excavation                                COMPLETED
                                                    Contract scope : 7.5 Mm3 - excavation,
                                                    relocation of a 1.3 Km. stretch of Borinquen
                                                    road, diversion of a 3.5 Km. stretch of Cocoli
                                                    River.

                                                    Contract Awarded to the consortium Cilsa-
                                                    Minera María for B/. 25,489,200.30.

                                                    Award date: November 27, 2007.

                                                       •Contractor passed final inspection –
                                                       project is completed
                                                       •Administrative closure in process



                                       Carretera
                                       Borinquen



             Río Cocolí


                                       PAC - 2
                                                                                             5
Projects Under Execution                                                                                      Awarded: 16-DEC-2008
                                                                                                                      Company: Constructora MECO, S.A.
        Pacific Access Channel - Phase 3                                                                              Excavation: 8.0M m3
                                                                                                                      Cleaning remaining 190 has in T6 area
    Programmed                                       51%
                  Actual                                      63%                                             4.47 M m3 excavated
                       0    10      20      30   40     50     60     70      80   90   100
                                                                                                              190 hectares cleared

                                                                                                                                              PAC 3



                                                                                                                MEC
                                                                                                               190 Ha




            140                                                                                                                                                  140
ELEVATION




            110                                                                                                                                                  110

             80                                                                                                                       PAC-1                       80

             50                                                                                                                                                   50
                                                              PAC-2                                                                     PAC 3
             20
                                                                              PAC-4                                                                               20
              9                                                                                                                                                   9




                    6+480   6+160   5+840    5+520    5+200   4+880   4+560   4+240   3+920   3+600   3+280   2+960   2+640   2+320   2+000   1+680   1+360   1+040
Pacific Access Channel – Phase 4
                                                 26 M m3 of dry excavation
                                                                                                • Bid announcement: July 31, 2009
                                                                                                • Proposals receipt: 22-DEC-09
                                                                                                • Awarded: 6-JAN-10
Programmed                    9%                                                                • Awarded to: FCC-ICA-MECO Consortium
                  Actual      9%                                                                • Order to proceed: 22-JAN-10
                                                                                                • Expected works startup date: 27-APR-10
                       0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
                                                                                                • Estimated completion date: 2-AUG-13 (1,288 days)



                                                                                                                                      PAC 3
                                                                                                                      PAC 4


                                                                                              PAC 2




                                                                                                                                       PAC 1
                                                               Borinquen Dam


            140                                                                                                                                                140
ELEVATION




            110                                                                                                                                                110

             80                                                                                                                     PAC-1                       80

             50                                                                                                                                                 50
                                                            PAC-2                                                                     PAC 3
             20
                                                                            PAC-4                                                                               20
              9                                                                                                                                                 9




                    6+480   6+160   5+840   5+520   5+200   4+880   4+560   4+240   3+920   3+600   3+280   2+960   2+640   2+320   2+000   1+680   1+360   1+040
Borinquen Dam




Pacific Access Channel
                                         Rocks
                                                 Miraflores Lake




                             Clay core
Projects Under Execution
Dredging areas in Gatun Lake and Gaillard Cut
                              Programmed        28%

     Gatun Lake                    Actual      27%
                                        0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%


                                            6.8 M m3 dredged




                  Barro Colorado




                                                                     Gamboa
Projects Under Execution
Gatun Lake’s critical dredging areas




 New prism line
 once the island is
 removed
Projects Under Execution
Pacific Entrance Deepening and Widening (8.7 M m3)
                                                                                       4.88 M m3 dredged
Programmed contractual                      47%
                Actual                        52%
                     0%   10%   20%   30%   40%   50%   60%   70%   80%   90% 100%




                                                                             Awarded: April 1, 2008
                                                                             Company: Dredging International
                                                                             Amount: B/. 177,500,676.78
                                                                             Dredged volume: 8.7 M m3
Atlantic Side Dredging
Atlantic Entrance Dredging
Reforestation Projects Under Execution
                       PAC-1/ Camino de Cruces National Park (Panama)                                       70%
                       PAC-2 /Campana National Park (Western Panama)                                        70%
                     PAC-3/ ANAM Center for Forestry Reearch (Chiriqui)                           52%

                     PAC-3/ Gral. Omar Torrijos (Piedras Gordas – Cocle)                             52%
PAC-2/ Parque Nal. Gral. Omar TorrijosNational Park (Bajo Grande/Ojo de                         48%
                                                            Agua–Cocle)

              Dreding of the Lake / Baru Volcano National Park (Chiriqui)                       47%

               PAC-3/ Chagres National Park (Panama-Quebrada Oscura)                              52%

    PAC-2 /Gral. Omar Torrijos National Park (La Rica/Caño Sucio–Cocle)
                                                                                          38%                        Rev. March-2010

                                                                            0   10   20   30    40    50   60   70     80     90   100

                                                                                               Chagres
                       Baru                                Campana                              40 Ha
                      Volcano                               30 Ha
                       30 Ha



                                                                                Camino de Cruces
                                                                                     115 ha
                       Cenetr for Forestry
                        Research 50 Ha
                                                       Gral. Omar Torrijos
                                                              180 Ha
Locks Design and Construction
         Programmed 2.78%
              Actual 1.57%
                   0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Analyzed components
          Mathematical model


                               Basins intake


Intake


                               Trifurcation



                           Flow divider


         Connection to Ports              Central connection
         secondary
         culvert
Physical Model in Lyon, France
Pacific Locks
New Atlantic Locks
Bid Price Behaviour of Principal Expansion Program Projects
                         B/. 388M below Budget
                                 BUDGET                                 $ 302,374,000

    Pacific Access Channel - 4
                                 FCC-ICA-MECO               $ 267,798,795.99              - 11%

                                 BUDGET                                 $ 105,821,000

    Atlantic Entrance Dredging
                                 JAN DE NUL, NV                 $ 89,617,317              - 15%

                                 BUDGET                              $ 3,481,0000,000

    Locks
                                 GUPC                            $ 3,221,631,384           - 7%

                                 BUDGET                                  $ 68,067,623

    Pacific Access Channel - 3
                                 Constructora MECO, S.A.                $ 36,659,852.28   - 46%

                                 BUDGET                                 $ 181,096,000

    Pacific Entrance Dredging
                                 Dredging International          $ 177,500,676.78          - 2%

                                 BUDGET                                  $ 48,459,296

    Pacific Access Channel - 2
                                 CILSA - MINERA MARÍA                 $ 25,489,200.30     - 47%

                                 BUDGET                                  $ 61,208,966

    Pacific Access Channel - 1
                                 Constructora Urbana S.A.               $ 41,094,000      - 33%
                                        25%          50%          75%              100%
Summary Schedule of Main Projects with Baseline and Contingency
                 as of March 31, 2010*


                                                                        %        06        2007              2008                2009                2010                2011            2012                    2013                2014
                 Activity                                             Progress   4T   1T   2T   3T   4T 1T   2T   3T   4T   1T   2T   3T   4T   1T   2T   3T   4T   1T   2T   3T   4T   1T   2T   3T   4T   1T   2T   3T   4T   1T   2T   3T   4T




                 Specifications and Locks Models                      100%
Locks




                 Design & Build Post-Panamax Locks                      2%

                 Excavation Contract 1                                100%
Access Channel




                 Excavation Contract 2                                100%
                 Excavation Contract 3                                 63%
                 Excavation Contract 4 and Dams                         9%

                 Dredging of the Pacific Entrance                      52%
Dredging




                 Deepening and Widening of Gatun Lake and
                                                                       27%
                 Deepening of Gaillard Cut
                 Dredging of the Atlantic Entrance                      5%

                 Increase Operating Level of Gatún Lake                <1%

                 Expanded Canal Begins Operations




                       Specifications and Design           Bidding and Contracting                           Execution                          Contingency                              Beginning of operations
                       Baseline*                           Baseline                                          Baseline                           against baseline


* Baseline from December 31, 2006 including contingency.
Some business opportunities linked to
                   the Canal Expansion
   Aggregates                                                    Heavy equipment B/.400M


Sand B/.13M

              Rock B/.19M


           Cement
           B/.95M                                                            Forms
                                                                             B/.68M
                                          Goods and
Concrete                              services required
B/.700M                               for the Expansion
                                            Project
                                                                             Diesel
                                                                             B/.176M


                            Steel
                            B/.300M


                                                    Excavation
                                                    B/.420M
Potential Impact of the
Panama Canal Expansion
WORLD MAIN LOGISTICS HUBS


                                                         ROTTERDAM

                                       NY/NJ                         HAMBURG
SHANGHAI     BUSAN                 HAMPTON
                          LA/LB      RDS.
SHENZHEN                                     SAVANNAH    ALGECIRAS
                                              FREEPORT
     HONG KONG                                KINGSTON                         DUBAI

                                    PANAMÁ
 SINGAPORE




Panama is the main logistical, transportation and transshipment
hub of the Americas.
U.S. East and Gulf Coast Ports
Port Authorities Expansion Projects
             Location                                                   Project              Estimated
                                                                                            Completion
 Georgia Ports Authority                    Deepening of the Savannah River Channel        2014
                                            from 42’ to 48’.
 Port of Miami                              Deepening draft from 42’ to 50’ and the        2014
                                            construction of Port of Miami Tunnel
                                            Project to expedite delivery of goods.
 Philadelphia Regional                      Dredging the main shipping channel of the      Within 5 – 7
 Port Authority                             Delaware River from 40’ to 45’.                years
 Port Authority of New                      Harbor deepening project to 50’; $10           Harbor
 York & New Jersey                          million approved to analyze alternatives for   deepening to be
                                            Bayonne Bridge (height: 151’).                 completed in
                                                                                           phases from
                                                                                           2010 to 2014.
 Port of Houston                            The Bayport Container & Cruise Terminal        All phases
 Authority                                  project (Phase 1 is completed); future         completed in
                                            capacity of 2.3M TEU.                          15-20 years
 Broward County’s Port                      Inauguration of Cruise Terminal 18 for         Nov. 2009
 Everglades Department                      megaships.
Source: MERC with information provided by port Authorities, January 2010.
Port Authorities Expansion Projects


              Location                                                  Project               Estimated
                                                                                             Completion
  Port of Palm Beach                        Development of logistics center for
                                            storage and distribution of cargo to the
                                            South Florida region.
  Jacksonville Port                         Development of container terminals by           2011 - 2012
  Authority                                 MOL (already in use) and Hanjin with total
                                            additional capacity of 1.5M TEU


  Maryland Port                             Construction of the new 50-foot berth at        2012
  Administration                            Baltimore’s Seagirt Marine Terminal.
  Manatee County Port                       The 788 acre Logistics Port Manatee (LPM)       2011
  Authority                                 multimodal logistic park (Port Manatee’s
                                            first container terminal); directly served by
                                            CSX railroad.




Source: MERC with information provided by port Authorities, January 2010.
PORT OF SAVANNAH:
      DC Activity Translates into Long-Term Carrier Options

   Largest concentration of Retail Import DC’s along the East Coast
        20+ DC’s within 100 miles (161 km), including Walmart, Kmart, Lowes,
         The Home Depot, IKEA, Dollar Tree, Pier 1, and Target to name a few
        Over 200 additional Georgia DC’s from wholesale suppliers to
         retailers within a 5-hour drive with names like Toys “R” Us
         Bass Pro Shop and Academy Sports.
                                                                Atlantic    Ocean Downtown Savannah
        Available land and building
         within 5 miles (8 km) of                                    A
                                                    Garden City Terminal
         the port.                             C      B          D
                                                                     E
                                                                 F
                                                          G              H
A   Electrolux       G    Heineken                                                 I
B   Target           H    The Home Depot                                               J
C   IKEA             II   Lowes                                                            K
D   Whirlpool        J
                     J    Dollar Tree
E   Icon H&F         K    Pier 1 Imports
F
F   Wal-Mart
GEORGIA IMPORTERS:
               20+ Savannah-area Import DCs, 200+ more within 5 Hours

                                                       Savannah-area Import DC’s
                                                                               Sq. Ft.    Sq. M.
                                                 Academy Sports             1,000,000     92,903
                                                 Advance Auto Parts           380,000     35,303
                                                 Bass Pro Shops               600,000     55,742
                                                 Best Buy                     748,000     69,491
                                                 Citi Trends Fashion          155,000     14,400
                                                 Dollar Tree                  800,000     74,322
                                                 Farmer’s Furniture           250,000     23,226
                                                 Fred’s                       600,000     55,742
                                                 Hugo Boss                    165,000     15,329
                                                 Icon H & F                   600,000     55,742
                                                 IKEA                       1,700,000    157,935
                                                 Kmart-Sears                2,200,000    204,387
                                                 Kohl’s                       600,000     55,742
                                                 Lowe’s                     1,250,000    116,129
                                                 Midwest Air Technologies     150,000     13,935
                                                 Noritake                     105,000      9,754
                                                 Oneida                       500,000     46,452
                                                 Paper Tigers                 115,000     10,684
                                                 Pier 1 Imports               783,000     72,743
                                                 Target                     2,100,000    195,096
     Note: This list is not intended to be
                                                 The Home Depot             1,400,000    130,064
definitive of Georgia’s extensive list of port
                                                 Tire Rack                    250,000     23,226
dependent DCs.
                                                 Wal-Mart (2)               3,300,000    306,580
Importance of the Savannah Harbor
          deepening project
• Designed to deepen the Savannah River from 42 to 48
  feet.
• To be completed in 2014, in time with Canal expansion
• Post Panamax vessels transiting the expanded Canal will
  be able make calls at the Port of Savannah.
• 72 percent of total trade moving through Georgia’s ports
  transits the Panama Canal.
• Out of the 30 liner services that transit the Panama
  Canal, 15 call at the Port of Savannah.
• ACP expects rapid deployment of 8,000 TEUs vessels
  once the Canal expansion is completed.
GPA-ACP Strategic Alliance




• Initially subscribed in 2003 to generate new business by promoting
  the all-water route from Asia to the USEC via the Panama Canal.
• Renewed in 2008 for three additional years
• Allows for joint marketing activities; exchange of market studies and
  information on modernization and improvement programs;
  technological interchange and cross training activities.
Governor Purdue/GPA visit to Panama Canal – Sept 09
International Ports Connected through the Panama
                       Canal every Week


                                                                                                                        Rotterdam
                                                                                                   Bremerhaven
                                                                                             Tilbury
                                                                                           Felixstowe
                 Osaka                                                                                                  Hamburg
                 Nagoya                                                                     Thamesport                       Dunkerque
                                                                               Halifax
           Shanghai                               Seattle                                                               Zeebrugge
  Kwangyang                                                                   NJ/NY Boston
Qingdao                                                               Wilmington                                    Le Havre
       Pusan                  Tokyo                               Newport News                                   Antwerp
       Keelung                Shimizu           Oakland              Charleston          Baltimore                            Port Said
      Yantian             Yokohama          Los Angeles                 . Miami        Savannah
      Hong Kong         Kobe                 Long Beach            New Orleans          Everglades Marseilles
    Colombo                                                                             Colon
                   Hakata                      Manzanillo (Mx)       VeracruzKingston     Manzanillo
Chabang                                                                                                     La Spezia
                         Kaohsiung                                                          Cartagena
                                                           Puerto Limón                        Maracaibo
                                                                    Balboa                     La Guaira
                       Tanjung Priok                                                               Guanta
                                                               Buenaventura                          Puerto Cabello
                                   Doniambo                           Manta
Singapore                                                         Guayaquil
                                                                      Callao
                                                                      Arica                             Santos
                                                        Tahiti                                         Paranagua
                                                                       Iquique
                Brisbane                                             Coquimbo                        Itajai
                    Sydney                                          Antofagasta
                                                                     Valparaíso
                                                                   San Antonio
                                                Auckland            San Vicente                       Transit the       Canal
                  Melbourne
                                                                                                 Feeder services
Source: ACP and ComPairData, 2007
Routes, ports and betweenness centralities in the GCSN




  Routes, ports and betweenness centralities in the GCSN. (a) The trajectories of all cargo ships bigger than 10 000 GT
  during 2007. The colour scale indicates the number of journeys along each route. Ships are assumed to travel along
  the shortest (geodesic) paths on water. (b) A map of the 50 ports of highest betweenness centrality and a ranked list of
  the 20 most central ports.

  Kaluza P et al. J. R. Soc. Interface
  doi:10.1098/rsif.2009.0495

©2010 by The Royal Society
Panama Canal Expansion

Mais conteúdo relacionado

Mais procurados

Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptxssusercbae26
 
Breakwaters ports and harbors report
Breakwaters ports and harbors reportBreakwaters ports and harbors report
Breakwaters ports and harbors reportErnel Gonzaga
 
Titanic engineering aspects
Titanic engineering aspectsTitanic engineering aspects
Titanic engineering aspectsMohamedSamarin
 
28-3 Powerpoint: US Economic Imperialism in Latin America
28-3 Powerpoint: US Economic Imperialism in Latin America28-3 Powerpoint: US Economic Imperialism in Latin America
28-3 Powerpoint: US Economic Imperialism in Latin Americatmeyer1026
 
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptx
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptxSaurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptx
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptxTribhuwan University
 
Angrepet På Pearl Harbor
Angrepet På Pearl HarborAngrepet På Pearl Harbor
Angrepet På Pearl Harbortarzanol
 
Determination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil EngineeringDetermination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil EngineeringAbdullah Hayat Khan
 
Breakwaters day 1 - introduction
Breakwaters   day 1 - introductionBreakwaters   day 1 - introduction
Breakwaters day 1 - introductionRuwan Madhushanka
 
Ism curso conocimientos generales 1 introducción
Ism curso conocimientos generales 1 introducciónIsm curso conocimientos generales 1 introducción
Ism curso conocimientos generales 1 introducciónAlejandro Díez Fernández
 
Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...Professor Kabir Sadeghi
 
The Space Race
The Space RaceThe Space Race
The Space RaceRCSDIT
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminarPrashant Ojha
 

Mais procurados (20)

Excavation and Ground water control1.pptx
Excavation and Ground water control1.pptxExcavation and Ground water control1.pptx
Excavation and Ground water control1.pptx
 
Breakwaters ports and harbors report
Breakwaters ports and harbors reportBreakwaters ports and harbors report
Breakwaters ports and harbors report
 
Titanic engineering aspects
Titanic engineering aspectsTitanic engineering aspects
Titanic engineering aspects
 
28-3 Powerpoint: US Economic Imperialism in Latin America
28-3 Powerpoint: US Economic Imperialism in Latin America28-3 Powerpoint: US Economic Imperialism in Latin America
28-3 Powerpoint: US Economic Imperialism in Latin America
 
Heavy weather lrg
Heavy weather lrgHeavy weather lrg
Heavy weather lrg
 
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptx
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptxSaurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptx
Saurav_BEARING CAPACITY OF BED ROCK AND SOIL DEPOSITS.pptx
 
Lecture 4
Lecture 4Lecture 4
Lecture 4
 
Angrepet På Pearl Harbor
Angrepet På Pearl HarborAngrepet På Pearl Harbor
Angrepet På Pearl Harbor
 
Cofferdam
CofferdamCofferdam
Cofferdam
 
Determination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil EngineeringDetermination of Liquid Limit of Soil : Civil Engineering
Determination of Liquid Limit of Soil : Civil Engineering
 
Tunnelling methods
Tunnelling methodsTunnelling methods
Tunnelling methods
 
Breakwaters day 1 - introduction
Breakwaters   day 1 - introductionBreakwaters   day 1 - introduction
Breakwaters day 1 - introduction
 
Ism curso conocimientos generales 1 introducción
Ism curso conocimientos generales 1 introducciónIsm curso conocimientos generales 1 introducción
Ism curso conocimientos generales 1 introducción
 
Halsema Highway
Halsema HighwayHalsema Highway
Halsema Highway
 
Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...Significant Guidance for Design and Construction of Marine and Offshore Struc...
Significant Guidance for Design and Construction of Marine and Offshore Struc...
 
Panama canal
Panama canalPanama canal
Panama canal
 
The Space Race
The Space RaceThe Space Race
The Space Race
 
Submerged tunnel technical seminar
Submerged tunnel technical seminarSubmerged tunnel technical seminar
Submerged tunnel technical seminar
 
Break waters
Break watersBreak waters
Break waters
 
Curing of concrete
Curing of concreteCuring of concrete
Curing of concrete
 

Mais de Ports-To-Plains Blog

2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference Handouts2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference HandoutsPorts-To-Plains Blog
 
Energy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation InfrastructureEnergy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation InfrastructurePorts-To-Plains Blog
 
Wind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. ManufacturingWind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. ManufacturingPorts-To-Plains Blog
 
Compressed Air Wind Energy Storage
Compressed Air Wind Energy StorageCompressed Air Wind Energy Storage
Compressed Air Wind Energy StoragePorts-To-Plains Blog
 
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...Ports-To-Plains Blog
 
Ports-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of StatePorts-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of StatePorts-To-Plains Blog
 
News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813Ports-To-Plains Blog
 
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...Ports-To-Plains Blog
 
2013 Energy Conference Save the Date
2013 Energy Conference Save the Date2013 Energy Conference Save the Date
2013 Energy Conference Save the DatePorts-To-Plains Blog
 
February 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains AllianceFebruary 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains AlliancePorts-To-Plains Blog
 
Draft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL ProjectDraft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL ProjectPorts-To-Plains Blog
 
PTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline DecisionPTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline DecisionPorts-To-Plains Blog
 
News Release PTP Keystone XL Nebraska
News Release PTP Keystone XL NebraskaNews Release PTP Keystone XL Nebraska
News Release PTP Keystone XL NebraskaPorts-To-Plains Blog
 
Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012Ports-To-Plains Blog
 
Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011Ports-To-Plains Blog
 
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...Ports-To-Plains Blog
 
Interim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory CommitteesInterim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory CommitteesPorts-To-Plains Blog
 
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012Ports-To-Plains Blog
 

Mais de Ports-To-Plains Blog (20)

Canada and U.S. Trade Overview
Canada and U.S. Trade Overview Canada and U.S. Trade Overview
Canada and U.S. Trade Overview
 
2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference Handouts2013 Ports-to-Plains Alliance Energy Conference Handouts
2013 Ports-to-Plains Alliance Energy Conference Handouts
 
Energy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation InfrastructureEnergy Development Impact on Transportation Infrastructure
Energy Development Impact on Transportation Infrastructure
 
Wind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. ManufacturingWind Energy's Future and the Impact on U.S. Manufacturing
Wind Energy's Future and the Impact on U.S. Manufacturing
 
Compressed Air Wind Energy Storage
Compressed Air Wind Energy StorageCompressed Air Wind Energy Storage
Compressed Air Wind Energy Storage
 
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
Fuels Policy, Ethanol and RFS Reform Political and Policy Implications on Gas...
 
Ports-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of StatePorts-to-Plains Letter Submitted to Department of State
Ports-to-Plains Letter Submitted to Department of State
 
News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813News Release Keystone XL Supporting SEIS Finding 041813
News Release Keystone XL Supporting SEIS Finding 041813
 
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
Ports-to-Plains: The Importance of a Statewide Transportation to Colorado's E...
 
2013 Energy Conference Save the Date
2013 Energy Conference Save the Date2013 Energy Conference Save the Date
2013 Energy Conference Save the Date
 
February 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains AllianceFebruary 2013 Update from the Ports-to-Plains Alliance
February 2013 Update from the Ports-to-Plains Alliance
 
Draft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL ProjectDraft Supplemental EIS for the Keystone XL Project
Draft Supplemental EIS for the Keystone XL Project
 
PTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline DecisionPTP supports Heineman Keystone XL Pipeline Decision
PTP supports Heineman Keystone XL Pipeline Decision
 
Keystone XL Letter Dec 2012 NEDEQ
Keystone XL Letter Dec 2012 NEDEQKeystone XL Letter Dec 2012 NEDEQ
Keystone XL Letter Dec 2012 NEDEQ
 
News Release PTP Keystone XL Nebraska
News Release PTP Keystone XL NebraskaNews Release PTP Keystone XL Nebraska
News Release PTP Keystone XL Nebraska
 
Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012Ports-to-Plains Alliance Webinar 113012
Ports-to-Plains Alliance Webinar 113012
 
Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011Nebraska Trade Relationships 2004 – 2011
Nebraska Trade Relationships 2004 – 2011
 
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
Comments on Interim Guidance on State Freight Plans and State Advisory Commit...
 
Interim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory CommitteesInterim Guidance on State Freight Plans and State Freight Advisory Committees
Interim Guidance on State Freight Plans and State Freight Advisory Committees
 
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
Ports-to-Plains Alliance Northern Working Group Strategic Plan October 2012
 

Último

trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdfMintel Group
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckHajeJanKamps
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsIndiaMART InterMESH Limited
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Anamaria Contreras
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...Hector Del Castillo, CPM, CPMM
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in PhilippinesDavidSamuel525586
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxappkodes
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxRakhi Bazaar
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamArik Fletcher
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSendBig4
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreNZSG
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers referencessuser2c065e
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingrajputmeenakshi733
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersPeter Horsten
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Peter Ward
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMVoces Mineras
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsKnowledgeSeed
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterJamesConcepcion7
 

Último (20)

trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdftrending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
trending-flavors-and-ingredients-in-salty-snacks-us-2024_Redacted-V2.pdf
 
Pitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deckPitch Deck Teardown: Xpanceo's $40M Seed deck
Pitch Deck Teardown: Xpanceo's $40M Seed deck
 
Welding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan DynamicsWelding Electrode Making Machine By Deccan Dynamics
Welding Electrode Making Machine By Deccan Dynamics
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.Traction part 2 - EOS Model JAX Bridges.
Traction part 2 - EOS Model JAX Bridges.
 
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
How Generative AI Is Transforming Your Business | Byond Growth Insights | Apr...
 
WAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdfWAM Corporate Presentation April 12 2024.pdf
WAM Corporate Presentation April 12 2024.pdf
 
Entrepreneurship lessons in Philippines
Entrepreneurship lessons in  PhilippinesEntrepreneurship lessons in  Philippines
Entrepreneurship lessons in Philippines
 
Appkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptxAppkodes Tinder Clone Script with Customisable Solutions.pptx
Appkodes Tinder Clone Script with Customisable Solutions.pptx
 
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptxGo for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
Go for Rakhi Bazaar and Pick the Latest Bhaiya Bhabhi Rakhi.pptx
 
Technical Leaders - Working with the Management Team
Technical Leaders - Working with the Management TeamTechnical Leaders - Working with the Management Team
Technical Leaders - Working with the Management Team
 
Send Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.comSend Files | Sendbig.com
Send Files | Sendbig.comSend Files | Sendbig.com
 
Jewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource CentreJewish Resources in the Family Resource Centre
Jewish Resources in the Family Resource Centre
 
Excvation Safety for safety officers reference
Excvation Safety for safety officers referenceExcvation Safety for safety officers reference
Excvation Safety for safety officers reference
 
digital marketing , introduction of digital marketing
digital marketing , introduction of digital marketingdigital marketing , introduction of digital marketing
digital marketing , introduction of digital marketing
 
EUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exportersEUDR Info Meeting Ethiopian coffee exporters
EUDR Info Meeting Ethiopian coffee exporters
 
Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...Fordham -How effective decision-making is within the IT department - Analysis...
Fordham -How effective decision-making is within the IT department - Analysis...
 
Memorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQMMemorándum de Entendimiento (MoU) entre Codelco y SQM
Memorándum de Entendimiento (MoU) entre Codelco y SQM
 
Introducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applicationsIntroducing the Analogic framework for business planning applications
Introducing the Analogic framework for business planning applications
 
Healthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare NewsletterHealthcare Feb. & Mar. Healthcare Newsletter
Healthcare Feb. & Mar. Healthcare Newsletter
 

Panama Canal Expansion

  • 1. The Panama Canal Expansion Program José Barrios Ng Deputy Administrator Panama Canal Authority April 2010
  • 2. Program Components 15.8 M m3 $5.25 billion investment Atlantic Ocean Post-Panamax Locks - Increasing Gatun Lake’s Atlantic Side Maximum Operational Level Deepening and Widening of the Atlantic Entrance Post-Panamax Locks – Pacific Side 26.7 m 27.1 m Deepening and Widening of Gatun Lake’s and Gaillard Cut’s Navigational Channels 8.7 M m3 Access Channel to Post-Panamax Locks - Pacific Side Deepening and Widening of the 49 M m3 Pacific Entrance Pacific Ocean
  • 3. Locks and vessels sizes Existing locks' maximum vessel size: 4,400 TEU 33.5 m (110’) 32.3 m (106’) 12.4 m (39.5’) 55 m (180’) 12.8 m (42’) 49 m (160’) 18.3 m (60’) 15.2 m (50’) New locks' maximum vessel size: 12,600 TEU
  • 4. Pacific Access Channel - Phase 1 Programmed 100% Actual 100% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Contract Scope: 7.4 Mm3, cleaning 146 hectares of MEC and relocation of a 3.6 km stretch of Borinquen Excavated 7.3 M m3 road July 15, 2009 Awarded: 17 July, 2007 136 m Amount Awarded: B/.41,094,000.00 Amount Paid: B/. 40,431,196.00 46 m • Contractor passed final inspection – project is completed Original • Administrative closure in process Original 2009 July 15, MEC 1 146 Has cleaned Borinquen Road 4
  • 5. Pacific Access Channel - Phase 2 Programmed 99.9% Actual 99.6% 7.4 M m3 excavated 0 10 20 30 40 50 60 70 80 90 100 Excavation COMPLETED Contract scope : 7.5 Mm3 - excavation, relocation of a 1.3 Km. stretch of Borinquen road, diversion of a 3.5 Km. stretch of Cocoli River. Contract Awarded to the consortium Cilsa- Minera María for B/. 25,489,200.30. Award date: November 27, 2007. •Contractor passed final inspection – project is completed •Administrative closure in process Carretera Borinquen Río Cocolí PAC - 2 5
  • 6. Projects Under Execution Awarded: 16-DEC-2008 Company: Constructora MECO, S.A. Pacific Access Channel - Phase 3 Excavation: 8.0M m3 Cleaning remaining 190 has in T6 area Programmed 51% Actual 63% 4.47 M m3 excavated 0 10 20 30 40 50 60 70 80 90 100 190 hectares cleared PAC 3 MEC 190 Ha 140 140 ELEVATION 110 110 80 PAC-1 80 50 50 PAC-2 PAC 3 20 PAC-4 20 9 9 6+480 6+160 5+840 5+520 5+200 4+880 4+560 4+240 3+920 3+600 3+280 2+960 2+640 2+320 2+000 1+680 1+360 1+040
  • 7. Pacific Access Channel – Phase 4 26 M m3 of dry excavation • Bid announcement: July 31, 2009 • Proposals receipt: 22-DEC-09 • Awarded: 6-JAN-10 Programmed 9% • Awarded to: FCC-ICA-MECO Consortium Actual 9% • Order to proceed: 22-JAN-10 • Expected works startup date: 27-APR-10 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% • Estimated completion date: 2-AUG-13 (1,288 days) PAC 3 PAC 4 PAC 2 PAC 1 Borinquen Dam 140 140 ELEVATION 110 110 80 PAC-1 80 50 50 PAC-2 PAC 3 20 PAC-4 20 9 9 6+480 6+160 5+840 5+520 5+200 4+880 4+560 4+240 3+920 3+600 3+280 2+960 2+640 2+320 2+000 1+680 1+360 1+040
  • 8. Borinquen Dam Pacific Access Channel Rocks Miraflores Lake Clay core
  • 9. Projects Under Execution Dredging areas in Gatun Lake and Gaillard Cut Programmed 28% Gatun Lake Actual 27% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% 6.8 M m3 dredged Barro Colorado Gamboa
  • 10. Projects Under Execution Gatun Lake’s critical dredging areas New prism line once the island is removed
  • 11. Projects Under Execution Pacific Entrance Deepening and Widening (8.7 M m3) 4.88 M m3 dredged Programmed contractual 47% Actual 52% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Awarded: April 1, 2008 Company: Dredging International Amount: B/. 177,500,676.78 Dredged volume: 8.7 M m3
  • 14. Reforestation Projects Under Execution PAC-1/ Camino de Cruces National Park (Panama) 70% PAC-2 /Campana National Park (Western Panama) 70% PAC-3/ ANAM Center for Forestry Reearch (Chiriqui) 52% PAC-3/ Gral. Omar Torrijos (Piedras Gordas – Cocle) 52% PAC-2/ Parque Nal. Gral. Omar TorrijosNational Park (Bajo Grande/Ojo de 48% Agua–Cocle) Dreding of the Lake / Baru Volcano National Park (Chiriqui) 47% PAC-3/ Chagres National Park (Panama-Quebrada Oscura) 52% PAC-2 /Gral. Omar Torrijos National Park (La Rica/Caño Sucio–Cocle) 38% Rev. March-2010 0 10 20 30 40 50 60 70 80 90 100 Chagres Baru Campana 40 Ha Volcano 30 Ha 30 Ha Camino de Cruces 115 ha Cenetr for Forestry Research 50 Ha Gral. Omar Torrijos 180 Ha
  • 15. Locks Design and Construction Programmed 2.78% Actual 1.57% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
  • 16. Analyzed components Mathematical model Basins intake Intake Trifurcation Flow divider Connection to Ports Central connection secondary culvert
  • 17. Physical Model in Lyon, France
  • 20. Bid Price Behaviour of Principal Expansion Program Projects B/. 388M below Budget BUDGET $ 302,374,000 Pacific Access Channel - 4 FCC-ICA-MECO $ 267,798,795.99 - 11% BUDGET $ 105,821,000 Atlantic Entrance Dredging JAN DE NUL, NV $ 89,617,317 - 15% BUDGET $ 3,481,0000,000 Locks GUPC $ 3,221,631,384 - 7% BUDGET $ 68,067,623 Pacific Access Channel - 3 Constructora MECO, S.A. $ 36,659,852.28 - 46% BUDGET $ 181,096,000 Pacific Entrance Dredging Dredging International $ 177,500,676.78 - 2% BUDGET $ 48,459,296 Pacific Access Channel - 2 CILSA - MINERA MARÍA $ 25,489,200.30 - 47% BUDGET $ 61,208,966 Pacific Access Channel - 1 Constructora Urbana S.A. $ 41,094,000 - 33% 25% 50% 75% 100%
  • 21. Summary Schedule of Main Projects with Baseline and Contingency as of March 31, 2010* % 06 2007 2008 2009 2010 2011 2012 2013 2014 Activity Progress 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T 1T 2T 3T 4T Specifications and Locks Models 100% Locks Design & Build Post-Panamax Locks 2% Excavation Contract 1 100% Access Channel Excavation Contract 2 100% Excavation Contract 3 63% Excavation Contract 4 and Dams 9% Dredging of the Pacific Entrance 52% Dredging Deepening and Widening of Gatun Lake and 27% Deepening of Gaillard Cut Dredging of the Atlantic Entrance 5% Increase Operating Level of Gatún Lake <1% Expanded Canal Begins Operations Specifications and Design Bidding and Contracting Execution Contingency Beginning of operations Baseline* Baseline Baseline against baseline * Baseline from December 31, 2006 including contingency.
  • 22. Some business opportunities linked to the Canal Expansion Aggregates Heavy equipment B/.400M Sand B/.13M Rock B/.19M Cement B/.95M Forms B/.68M Goods and Concrete services required B/.700M for the Expansion Project Diesel B/.176M Steel B/.300M Excavation B/.420M
  • 23. Potential Impact of the Panama Canal Expansion
  • 24. WORLD MAIN LOGISTICS HUBS ROTTERDAM NY/NJ HAMBURG SHANGHAI BUSAN HAMPTON LA/LB RDS. SHENZHEN SAVANNAH ALGECIRAS FREEPORT HONG KONG KINGSTON DUBAI PANAMÁ SINGAPORE Panama is the main logistical, transportation and transshipment hub of the Americas.
  • 25. U.S. East and Gulf Coast Ports
  • 26. Port Authorities Expansion Projects Location Project Estimated Completion Georgia Ports Authority Deepening of the Savannah River Channel 2014 from 42’ to 48’. Port of Miami Deepening draft from 42’ to 50’ and the 2014 construction of Port of Miami Tunnel Project to expedite delivery of goods. Philadelphia Regional Dredging the main shipping channel of the Within 5 – 7 Port Authority Delaware River from 40’ to 45’. years Port Authority of New Harbor deepening project to 50’; $10 Harbor York & New Jersey million approved to analyze alternatives for deepening to be Bayonne Bridge (height: 151’). completed in phases from 2010 to 2014. Port of Houston The Bayport Container & Cruise Terminal All phases Authority project (Phase 1 is completed); future completed in capacity of 2.3M TEU. 15-20 years Broward County’s Port Inauguration of Cruise Terminal 18 for Nov. 2009 Everglades Department megaships. Source: MERC with information provided by port Authorities, January 2010.
  • 27. Port Authorities Expansion Projects Location Project Estimated Completion Port of Palm Beach Development of logistics center for storage and distribution of cargo to the South Florida region. Jacksonville Port Development of container terminals by 2011 - 2012 Authority MOL (already in use) and Hanjin with total additional capacity of 1.5M TEU Maryland Port Construction of the new 50-foot berth at 2012 Administration Baltimore’s Seagirt Marine Terminal. Manatee County Port The 788 acre Logistics Port Manatee (LPM) 2011 Authority multimodal logistic park (Port Manatee’s first container terminal); directly served by CSX railroad. Source: MERC with information provided by port Authorities, January 2010.
  • 28. PORT OF SAVANNAH: DC Activity Translates into Long-Term Carrier Options  Largest concentration of Retail Import DC’s along the East Coast  20+ DC’s within 100 miles (161 km), including Walmart, Kmart, Lowes, The Home Depot, IKEA, Dollar Tree, Pier 1, and Target to name a few  Over 200 additional Georgia DC’s from wholesale suppliers to retailers within a 5-hour drive with names like Toys “R” Us Bass Pro Shop and Academy Sports. Atlantic Ocean Downtown Savannah  Available land and building within 5 miles (8 km) of A Garden City Terminal the port. C B D E F G H A Electrolux G Heineken I B Target H The Home Depot J C IKEA II Lowes K D Whirlpool J J Dollar Tree E Icon H&F K Pier 1 Imports F F Wal-Mart
  • 29. GEORGIA IMPORTERS: 20+ Savannah-area Import DCs, 200+ more within 5 Hours Savannah-area Import DC’s Sq. Ft. Sq. M. Academy Sports 1,000,000 92,903 Advance Auto Parts 380,000 35,303 Bass Pro Shops 600,000 55,742 Best Buy 748,000 69,491 Citi Trends Fashion 155,000 14,400 Dollar Tree 800,000 74,322 Farmer’s Furniture 250,000 23,226 Fred’s 600,000 55,742 Hugo Boss 165,000 15,329 Icon H & F 600,000 55,742 IKEA 1,700,000 157,935 Kmart-Sears 2,200,000 204,387 Kohl’s 600,000 55,742 Lowe’s 1,250,000 116,129 Midwest Air Technologies 150,000 13,935 Noritake 105,000 9,754 Oneida 500,000 46,452 Paper Tigers 115,000 10,684 Pier 1 Imports 783,000 72,743 Target 2,100,000 195,096 Note: This list is not intended to be The Home Depot 1,400,000 130,064 definitive of Georgia’s extensive list of port Tire Rack 250,000 23,226 dependent DCs. Wal-Mart (2) 3,300,000 306,580
  • 30. Importance of the Savannah Harbor deepening project • Designed to deepen the Savannah River from 42 to 48 feet. • To be completed in 2014, in time with Canal expansion • Post Panamax vessels transiting the expanded Canal will be able make calls at the Port of Savannah. • 72 percent of total trade moving through Georgia’s ports transits the Panama Canal. • Out of the 30 liner services that transit the Panama Canal, 15 call at the Port of Savannah. • ACP expects rapid deployment of 8,000 TEUs vessels once the Canal expansion is completed.
  • 31. GPA-ACP Strategic Alliance • Initially subscribed in 2003 to generate new business by promoting the all-water route from Asia to the USEC via the Panama Canal. • Renewed in 2008 for three additional years • Allows for joint marketing activities; exchange of market studies and information on modernization and improvement programs; technological interchange and cross training activities.
  • 32. Governor Purdue/GPA visit to Panama Canal – Sept 09
  • 33. International Ports Connected through the Panama Canal every Week Rotterdam Bremerhaven Tilbury Felixstowe Osaka Hamburg Nagoya Thamesport Dunkerque Halifax Shanghai Seattle Zeebrugge Kwangyang NJ/NY Boston Qingdao Wilmington Le Havre Pusan Tokyo Newport News Antwerp Keelung Shimizu Oakland Charleston Baltimore Port Said Yantian Yokohama Los Angeles . Miami Savannah Hong Kong Kobe Long Beach New Orleans Everglades Marseilles Colombo Colon Hakata Manzanillo (Mx) VeracruzKingston Manzanillo Chabang La Spezia Kaohsiung Cartagena Puerto Limón Maracaibo Balboa La Guaira Tanjung Priok Guanta Buenaventura Puerto Cabello Doniambo Manta Singapore Guayaquil Callao Arica Santos Tahiti Paranagua Iquique Brisbane Coquimbo Itajai Sydney Antofagasta Valparaíso San Antonio Auckland San Vicente Transit the Canal Melbourne Feeder services Source: ACP and ComPairData, 2007
  • 34. Routes, ports and betweenness centralities in the GCSN Routes, ports and betweenness centralities in the GCSN. (a) The trajectories of all cargo ships bigger than 10 000 GT during 2007. The colour scale indicates the number of journeys along each route. Ships are assumed to travel along the shortest (geodesic) paths on water. (b) A map of the 50 ports of highest betweenness centrality and a ranked list of the 20 most central ports. Kaluza P et al. J. R. Soc. Interface doi:10.1098/rsif.2009.0495 ©2010 by The Royal Society