Attached is the Project Status Update on Technology-Related Projects for the week ending 4/9/09. Please feel free to forward the Project Status Update to any members of your implementation team.
1. Project Office Status Tool
In an effort to enhance communication concerning the Technology-Related Portfolio
of Projects, the Project Office will be providing a high-level status to project team
members, project champions and Technology Steering Committee members twice a
month.
On Project
Minor to Major Issues
Track Jeopardy
The purpose of this tool is to give project team members and the key decision
makers adequate time to plan and adjust for any issues or challenges that may
arise during implementation. This will ensure that established milestones are met
“on time” and “on budget” as defined in the project plan.
As a Project Office recommendation, each team should investigate changes in their
status especially for those teams that are within 60 days of a Go-Live date.
1
Member, Texas Tech University System
2. Technology Project Portfolio
Week of April 6, 2009
Module/Project Project
On
Jeopardy
Minor to Major Issues
Track
HR Time Tracking & Reporting
Phase I (Students)
Go-Live 9/1/08-6/1/09
Microsoft Office 2007 & Exchange
Go-Live 9/1/08-5/1/09
Conversion of Tuition & Fees
Accounts Receivable Database Go-Live missed due to competing priorities.
Phase II Go-Live 4/15/09 New Go-live will occur 4/15.
Dashboards Phase I
(Operational Data Store)
Go-Live 6/15/09 – 10/27/09 45 days until Go-Live
Online Budget Transfer
Go-Live 5/31/09
37 days until Go-Live
2
3. Technology Project Portfolio
Week of April 6, 2009
Module/Project Project
On
Jeopardy
Minor to Major Issues
Track
Finance Miscellaneous Charges
posted on Student Account Phase I
Go Live 6/1/09 38 days until Go-Live
Online Purchase Requisition
Go-Live 8/31/09
Online Leave Reporting
Phase I Go-Live 8/31/09
Online Personnel Action Forms
Go-Live 8/31/09
Blackboard
Phase II
Go-Live 9/1/09 - 12/31/09
3
4. Technology Project Portfolio
Week of April 6, 2009
Module/Project Project
On
Minor to Major Issues Jeopardy
Track
HR Time Tracking & Reporting
Start Date 5/1/09
Phase II (Employee)
Go-Live 12/31/09
Dashboards Phase II Start Date 8/1/09
(Enterprise Data Warehouse)
4
5. Technology Project Portfolio
Week of March 27, 2009
Module/Project Project
On
Jeopardy
Minor to Major Issues
Track
HR Time Tracking & Reporting
Phase I (Students)
Go-Live 9/1/08-6/1/09
Microsoft Office 2007 & Exchange
Go-Live 9/1/08-5/1/09
One Card CS Gold Upgrade LIVE !!
Go-Live 3/20/09
Document Management for SACS
Accreditation LIVE !!
Go-Live 3/25/09
Conversion of Tuition & Fees
Accounts Receivable Database
Phase II Go-Live 4/1/09 3 days until Go-Live
5
6. Technology Project Portfolio
Week of March 27, 2009
Module/Project Project
On
Jeopardy
Minor to Major Issues
Track
Dashboards Phase I
(Operational Data Store)
16 days until Go-Live
Go-Live 4/20/09
Online Budget Transfer
Go-Live 5/1/09
25 days until Go-Live
Finance Miscellaneous Charges
Proximity Parking Project may Influence Timeline
posted on Student Account Phase I
Go Live 6/1/09 46 days until Go-Live
Online Purchase Requisition
Go-Live 8/31/09
Online Leave Reporting
Phase I Go-Live 8/31/09
6
7. Technology Project Portfolio
Week of March 27, 2009
Module/Project Project
On
Minor to Major Issues Jeopardy
Track
Online Personnel Action Forms
Go-Live 8/31/09
HR Time Tracking & Reporting
Phase II (Employee)
Go-Live 12/31/09
Blackboard
Phase II
Go-Live 9/1/09 - 12/31/09
Dashboards Phase II
Start Date 8/1/09
(Enterprise Data Warehouse)
7