SlideShare uma empresa Scribd logo
1 de 12
Baixar para ler offline
Sustainable School Projects: Rain Garden Page 1 of 12 
Rain Garden 
A simple, yet effective method to control stormwater is through the 
use of rain gardens. The design of a rain garden involves, among other 
things, the hydrologic cycle, nonpoint pollutant treatment, resource 
conservation, habitat creation, nutrient cycles, soil chemistry, 
horticulture, landscape architecture, and ecology. Beyond its use for 
stormwater control, the rain garden provides attractive landscaping 
and a natural habitat for birds and butterflies, while encouraging 
environmental stewardship and community pride. 
To continue choose a step from the list below: 
Step 1 - Let's Begin 
Step 2 - Goals/Objectives & Budget 
Step 3 - Gather Information 
Step 4 - Location & Size of Rain Garden 
Step 5 - Designing Your Rain Garden 
Step 6 - Selecting Plants for Your Rain Garden 
Step 7 - Design Review & Obtaining Permission 
Step 8 - Construction 
Step 9 - Maintenance 
Step 10 - Advertise 
Step 11 - Develop Timeline 
Step 12 - Preliminary Plans for Construction Day 
Step 13 - Construction Day 
Step 14 - Write Summary Report 
Step 15 - Keep it going! 
Step 1 - Let's Begin 
● Identify project participants (students and teachers) 
- Assign group leaders to communicate with maintenance 
staff 
● Begin securing partnership involvement 
● Get written agreement from school administration and 
maintenance staff 
- Clarify roles and responsibilities 
- Each school may allow a different amount of landscape 
changes 
- Ensure that there will be open communication throughout 
the project
Sustainable School Projects: Rain Garden Page 2 of 12 
Step 2 - Goals/Objectives and Budget 
● Outline project goals and objectives 
● Estimate amount you intend to spend [Budget] 
● Establish link between current school curriculum and 
environmental enhancement project. 
Cost 
Planning - $25 
Design - $100 
Materials - $varies 
Plants - $varies 
Soil - $varies 
Other - $varies 
Construction - $950 
Labor - $0 (volunteers) 
TOTAL ESTIMATED COST: $1,075 
Cost Spreadsheet 
Residential rain gardens average about $3 to $4 per square foot, 
depending on soil conditions and the density and types of plants 
used. Commercial, industrial and institutional site costs can 
range between $10 to $40 per square foot, based on the need 
for control structures, curbing, storm drains and underdrains. 
In any bioretention cell design, the cost of plants varies 
substantially and can account for a significant portion of the 
facility's expenditures. While these cost estimates are slightly 
greater than those of typical landscaping treatment (due to the 
increased number of plantings, additional soil excavation, backfill 
material, use of underdrains etc.), those landscaping expenses 
that would be required regardless of the bioretention installation 
should be subtracted when determining the net cost. 
Step 3 - Gather Information 
● Obtain a schematic of the school including wetlands, power 
lines, fire lanes, future building plans, etc. 
● Walk around and survey the school grounds to identify 
potential areas for project implementation 
(i.e. areas where water ponds during/after storms, areas where 
there is a lot of erosion, landscaping doesn’t get enough water)
Sustainable School Projects: Rain Garden Page 3 of 12 
● Identify gutters/downspouts 
● Request assistance from landscape architect, ecologist, and 
maintenance staff 
● Investigate permit requirements 
● Make list of problem areas 
● Take pictures of problem areas 
● Conduct informal survey of school community (including 
students, staff, parents, and maintenance staff) to determine 
their satisfaction with the current state of the school 
environment. 
Step 4 - Location and Size of Rain Garden 
Now that you have walked the campus, gathered all of the maps 
and materials you need, talked to the facilities manager, 
surveyed your fellow students and teachers, and listed the 
problem areas or potential areas for your rain garden, here are 
things to consider when locating and sizing your rain garden. 
Make sure you do not plan your rain garden in a riparian buffer, 
too close to the foundation, and other factors listed below in the 
“Location” section. Also, be sure to design a manageable rain 
garden – make sure it is a size that can be maintained well by 
your class. Check out the maintenance requirements in Step 9. 
● Two primary factors to consider when designing a rain garden 
are: 
● Planning the location of your rain garden 
● How to determine the size of your rain garden 
**NOTE: Now is an excellent time to call your local Cooperative Extension 
Office to have them test the soil. They will do this free of charge. A good soil 
mix for a rain garden is 50% sand, 20% topsoil, and 30% compost. If the soil 
onsite contains less than 10% clay, then it can be used in place of imported 
topsoil in the mix. It is possible you may be able to use the existing soil, but 
if it is not in good condition, you may have to spend some money on new soil 
and/or amendments such as lime, gypsum and specific nutrients.
Sustainable School Projects: Rain Garden Page 4 of 12 
How to find an appropriate location for a rain garden 
Take a walk around the school grounds during the next 
rainstorm. Make a note of where puddles are forming, which 
areas are not draining well, and where runoff is flowing. 
Finding a good location for a rain garden involves balancing a 
number of different factors: 
The rain garden should be located in a place where it will receive 
runoff. Check to make sure runoff flows to your site, or could 
flow with minor modifications, such as cutting a space out of a 
curb. 
The rain garden must be located far enough from the building to 
avoid damage to the foundation. If your school has a basement, 
the rain garden should be located at least 25’ from the building. 
If there is no basement, the rain garden should be at least 5’ 
from the building. 
Find out where underground utilities are buried. Common 
utilities will include: water, sewer, electricity, natural gas, 
telephone, cable, and possibly a separate storm sewer (some 
older areas have combined sewers, where the stormwater drains 
directly into the sanitary sewer system). It is often difficult and 
time consuming to find out exactly where all of the utilities are 
buried on your site, so start early. Write letters to each of the 
utilities, requesting plans showing the locations of underground 
utilities on your property. Have your maintenance staff show you 
where the utilities enter the building, and try to avoid using this 
area for rain gardens. Before construction, you can call Miss 
Utility, who will come to your site and mark the locations of 
utilities with spray paint, so you can be certain of avoiding them. 
Stay at least five feet horizontally and one foot vertically from 
any utilities. 
Check your soil. Since a lot of earth was moved during the 
construction of your school and school grounds, it is likely that 
your soils will be highly compacted, and will not drain well. In 
order to compensate for this, you should use a special soil mix 
within the rain garden. You should also install an underdrain at 
the bottom of the rain garden.
Sustainable School Projects: Rain Garden Page 5 of 12 
The underdrain should be a perforated PVC pipe that runs from 
the bottom of the rain garden out to some discharge point. This 
could be a grassy area, a wooded area, a stream, or even a 
parking lot. 
Also consider what will happen to runoff during very large 
storms. The rain garden is designed for small storms. When 
there is a great deal of rain, the rain garden will fill and 
eventually overflow. Be aware of where water will go when it 
overflows the rain garden. Minimize the impact that this overflow 
will have by directing it toward grassy areas, wooded areas, or 
existing storm drains. 
Avoid trees. Soils near trees tend to have the best drainage, and 
should not be disturbed. 
Avoid areas where there will be heavy foot traffic. Heavy foot 
traffic will pack down the soil in the rain garden, which will 
degrade its ability to infiltrate runoff. Place the rain garden 
somewhere out of the way, where the soil will not be compacted, 
and the vegetation will not be trampled. 
Be sensitive to how other people use of the site. For example, 
avoid building your rain garden on a favorite picnic spot. 
How to determine the size of a rain garden 
When full, the ponded area should have a maximum depth of six 
inches. The planting soil usually has a minimum depth of 2.5 
feet, but this depth may be constrained by the maximum depth 
of the underdrain at your site. The underdrain must discharge 
down gradient from the rain garden. Depending on your site 
topography, the bottom of the rain garden may need to be 
shallower than three feet below the ground surface. 
When rain gardens are designed for new sites, their sizes are 
matched to their drainage areas. When a site is being retrofit, 
the size of the rain garden is often limited by the availability of 
suitable space. Even in this case, it is important to estimate how 
effectively your proposed rain garden will capture, treat and 
infiltrate runoff from your site. This can be accomplished using 
the sizing tool.
Sustainable School Projects: Rain Garden Page 6 of 12 
Step 5 - Designing Your Rain Garden 
Now that you have determined the location and size of your rain 
garden you can begin to design it: 
● Copy and increase the size of the school plan so that every 
inch equal 10 feet (1” = 10’) 
● Draw a schematic drawing of the rain garden on a copy of the 
school plan 
● Show where the water source comes into the rain garden 
(bioswale, rain barrel hose, or where water sheets off of 
sidewalk or parking lot) 
● Determine the size of the rain garden (in square feet) 
Step 6 - Selecting Plants for Your Rain Garden 
Now that you have selected the location and determined the size 
of your rain garden take a few days to analyze the site you have 
selected. The success of your rain garden depends on this 
important information. Take notes and track what is happening 
at the site in the rain and on sunny days. Write down how much 
sun it gets – how many hours of afternoon sun? morning sun? Is 
there a reflection off of an adjacent building that provides more 
light or seems to make the heat more severe? Figure out if there 
are any unusual ‘microclimates’ at the site and then begin 
researching the plants that like these conditions. 
Plant your rain garden with plants that thrive in that 
environment. Whether in the sun or shade, rain gardens can be 
planted with shrubs and flowers that are beautiful and low 
maintenance – as long as you select the plants that love those 
conditions. Native plants – or plants that grow naturally in this 
climate or region -- can thrive without a lot of care, extra water, 
or extra fertilizer. 
This is an opportunity to learn more about the types of plants 
that love the sun, love the shade, love to have their ‘feet wet’ for 
a day or two, or don’t mind being dry for days on end. It is like a 
puzzle. See if you can pick out plants that are different heights, 
have different leaf color, and bloom different colors throughout 
the spring, summer, and fall seasons. Remember that even in 
the winter, plants without leaves can provide berries for birds
Sustainable School Projects: Rain Garden Page 7 of 12 
and have an unusual structure that can be accentuated in the 
snow. 
Designing with Plants: 
● Use a circle template (or ruler) to place plants in your rain 
garden 
● Select several 4-6’ shrubs, a lot of perennials (flowers that 
come back every year), and depending on the size of the rain 
garden a medium-sized tree or two [15-20’ at full growth]) 
Refer to the sample drawing to help you. 
Consider these things when selecting plants: 
● Choose native plants when possible 
● Avoid planting non-native invasive plants 
● Choose fragrant or edible plants when possible 
● Avoid toxic/poisonous plants 
● Avoid plants that produce excessive pollen 
Sample plant list to use as a guide: 
Prince George's County, MD Plant List 
Additional plant information: 
Useful Links 
Step 7 - Design Review and Obtaining Permission 
Once you have a schematic design of your rain garden, schedule 
a meeting with your principal and facilities/maintenance 
manager. This is an information gathering meeting and be 
prepared to make revisions based on the discussion at the 
meeting. 
Be prepared to discuss the construction and maintenance issues 
with the principal and maintenance staff. 
[Read the following steps (Step 8 – Construction and Step 9 – 
Maintenance) to understand the materials, material delivery, and 
site and soil preparation procedures.] 
During the meeting: 
● Review the draft design 
● Discuss the construction of the rain garden
Sustainable School Projects: Rain Garden Page 8 of 12 
● Find out about school regulations about delivery and storage of 
materials and equipment that will be used for construction of the 
rain garden. 
● Discuss the maintenance issues (roles and responsibilities) 
Step 8 - Construction 
Construction techniques are extremely critical in ensuring the 
success of a rain garden. Various construction guidelines and 
inspection points are given below, as well as a general 
construction schedule adapted from the Prince George's County 
Bioretention Manual. Local or regional rain garden/bioretention 
cell guides may also have useful information. 
Sequence of Construction 
1/2 day - Install sediment control devices. (These are for larger 
projects. Check with your local building permit office. It’s a good 
idea to surround the down gradient part of the site with straw 
bales or silt fence. It’s readily available and inexpensive.) 
1 day - Grade site to elevations shown on plan. If applicable, 
construct curb openings and/or remove and replace existing 
concrete. Curb openings should be blocked or other measures 
taken to prohibit drainage from entering construction area. 
(Equipment such as a backhoe may be rented for this. Make sure 
any Miss Utility is notified before any digging. Safety fence 
should be used around any construction area or excavation.) 
1/2 day - Stabilize grading within Limit of Disturbance except for 
the bioretention area, which will be planted. (Surrounding the 
cell with a biolog, straw bales, or compost berm to keep 
sediment out of the bioretention cell.) 
1/2 day - Excavate bioretention area to proposed invert depth 
and scarify the existing soil surfaces, taking care not to compact 
the in-situ materials. (A contractor may be hired to dig the hole. 
Make sure that there are no open areas or pits open at the end 
of the day and no excavation over local jurisdiction or OSHA 
limits. Generally bioretention cells are less than 3 feet deep.)
Sustainable School Projects: Rain Garden Page 9 of 12 
1/2 day - Install underdrain system and observation wells, if 
specified. (Use perforated 4” HDPE pipe and surround the pipe 
with about 2” of gravel) 
1/4 day - Backfill bioretention area with planting soil. (Fill the 
cell with 8” lifts of soil. Saturate each lift and let it drain and 
then place the next lift. Be careful not to compact the soil with 
equipment and saturate it.) 
1/4 day - Plant vegetation. 
1/4 day - Mulch and install erosion protection at entrance points. 
Remove sediment control practices or entrance blocks with 
inspector authorization if this project requires a permit. (It is 
recommended to leave perimeter biodegradable controls to 
reduce sediment loads to cell) 
Total Estimated Construction Time: 5.5 Days 
Step 9 - Maintenance 
A routine maintenance schedule can be followed. An example is 
presented here, as adapted from the Prince George's County 
Bioretention Manual. Experience has shown that the economic 
incentive of maintaining property values ensures that most 
homeowners will maintain their LID landscape. 
Maintenance Schedule 
Soil 
● Visually inspect and repair erosion monthly. Use small stones 
to stabilize erosion along drainage paths. 
● Check the pH once or twice a year. Apply an alkaline product, 
such as limestone, if needed. 
Mulch 
● Re-mulch any void areas by hand as needed. 
● Every 6 months, in the spring and fall, add a fresh mulch layer. 
● Once every 2 to 3 years, in the spring, remove old mulch layer 
before applying new one. 
Plants
Sustainable School Projects: Rain Garden Page 10 of 12 
● Immediately after the completion of cell construction, water 
plant material for 14 consecutive days unless there is sufficient 
natural rainfall. 
● When trees have taken root, or at least by 6 months, remove 
stakes and wires. 
● Once a month (more frequently in the summer), visually 
inspect vegetation for disease or pest problems. 
● If treatment is warranted, use the least toxic approach. 
● Twice a year, from March 15th to April 30th and October 1st to 
November 30th, remove and replace all dead and diseased 
vegetation considered beyond treatment. 
● During times of extended drought, look for physical features of 
stress (unrevived wilting, yellow, spotted or brown leaves, loss 
of leaves, etc.). Water in the early morning as needed. 
● Weed regularly, if needed. 
● Prune excess growth annually or more often, if desired. 
Trimmed materials may be recycled back in with replenished 
mulch or land filled if there is a concern of heavy metals 
accumulation. 
General 
● After rainstorms, inspect the cell and make sure that drainage 
paths are clear and that ponding water dissipates over 4-6 
hours. (Water may pond for longer times during the winter and 
early spring.) 
**NOTE: Keep in mind, the rain garden is not a pond. It should not provide a 
breeding ground for mosquitoes. Mosquitoes need at least 4 days of standing 
water to develop as larva. 
Step 10 - Advertise 
● Spread the word!!! 
● Develop a website 
● Provide an outline of goals and objectives 
● Post pictures 
● Advertise URL through school newspaper, public television 
● Update often 
Step 11 - Create Timeline 
● Order supplies 
● Arrange for material delivery
Sustainable School Projects: Rain Garden Page 11 of 12 
● Advertise work days on web and in school newspaper 
- Ask for volunteers 
● Create timeline for project completion 
Step 12 - Preliminary Plans for Construction Day 
Some final preparations need to be made to make your 
construction day a success. 
Be sure to: 
1. Notify your school administrators and maintenance staff that 
the construction will begin 
2. Call key volunteers (Ask them to arrive early and be Team 
Leaders) 
3. Ask volunteers to bring gloves, shovels, and water bottles 
(make sure their tools are labeled with their names) 
4. Create a Task List 
5. Delegate responsibility so that you can be free to coordinate 
on construction day 
6. Print out and copy the Construction Sequence page 
7. Get an Emergency Kit and set up an Emergency Plan 
8. Make sure building door(s) are open so that volunteers can 
use bathroom facilities 
9. Make sure you have access to water hose 
10. Provide refreshments and snacks (if possible) – at least 
provide water 
11. Contact local newspaper, or designate a student volunteer or 
parent to take photos and write about the event 
12. Bring camera 
Step 13 - Construction Day 
Now that all of your materials have been ordered and volunteers 
have been scheduled it is time to construct your rain garden. 
Prior to construction: 
1. Arrive early 
2. Take “Before” photo 
3. Organize the construction site: 
● Position plants and materials 
● Label tools
Sustainable School Projects: Rain Garden Page 12 of 12 
● Place tools that are not being used in a central location 
● Put Emergency Kit on hand in the central location 
4. Greet and organize volunteers 
● Have volunteers sign in 
● Delegate responsibilities 
● Announce the schedule and breaks 
● Provide info on emergency plan, bathroom locations, and 
refreshments 
● Distribute the Construction Sequence information 
● Take photo of all volunteers 
During Construction: 
1. Take photos of all the construction phases, emphasizing the 
volunteers 
2. Interview the volunteers 
Post-Construction: 
1. Water the rain garden 
2. Take “After” photo 
3. Step back and appreciate 
Remember to: 
● Continuously monitor safety 
● Have fun! 
Step 14 - Write Summary Report 
● Write final report 
- Use input from all students involved 
● Post names of volunteers on web and in school newspaper 
● Take follow-up survey of school community 
● Review budget 
● Plan long-term maintenance 
● Determine future learning outcomes 
Step 15 - Keep It Going 
● Where do we go from here?!!! 
The End!!

Mais conteúdo relacionado

Mais procurados

Sustainability in interior design, Architecture
Sustainability in interior design, ArchitectureSustainability in interior design, Architecture
Sustainability in interior design, Architecturemahmood Albrifkany
 
American parks Landscape design Central park new york case study
American parks Landscape design Central park new york case studyAmerican parks Landscape design Central park new york case study
American parks Landscape design Central park new york case studyAr.Farooqh A
 
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBIN
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBINCULTURAL CENTER OF THE PHILIPPINES BY RG GARBIN
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBINRG Trinity
 
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)Ashraf Danish
 
Types of Low E Glass Coatings
Types of Low E Glass CoatingsTypes of Low E Glass Coatings
Types of Low E Glass CoatingsPPG IdeaScapes
 
Literature review exhibtion center
Literature review exhibtion centerLiterature review exhibtion center
Literature review exhibtion centerkaleabsenay
 
Green Urban Design for Brgy Lapaz, Makati City, Philippines
Green Urban Design for Brgy Lapaz, Makati City, PhilippinesGreen Urban Design for Brgy Lapaz, Makati City, Philippines
Green Urban Design for Brgy Lapaz, Makati City, PhilippinesArch. Ma. Elena E. Lamasan
 
LANDSCAPE CASE STUDY
LANDSCAPE CASE STUDYLANDSCAPE CASE STUDY
LANDSCAPE CASE STUDYAmit Majumdar
 
GreenStudio - Chapter 4 2 7 Shading Devices
GreenStudio - Chapter 4 2 7 Shading DevicesGreenStudio - Chapter 4 2 7 Shading Devices
GreenStudio - Chapter 4 2 7 Shading DevicesGalala University
 
Passive Design Strategies, Teksing BambooWood School, Kavre, Nepal
Passive Design Strategies, Teksing BambooWood School, Kavre, NepalPassive Design Strategies, Teksing BambooWood School, Kavre, Nepal
Passive Design Strategies, Teksing BambooWood School, Kavre, NepalNaman Sharma
 
Report on tesla solar roof
Report on tesla solar roofReport on tesla solar roof
Report on tesla solar roofAniket Gupta
 
Detailing : Interior Wall Assemblies
Detailing : Interior Wall AssembliesDetailing : Interior Wall Assemblies
Detailing : Interior Wall AssembliesTodd Wyatt
 
2012 13 mat 3 lect 2 lightwt fac met clad
2012 13 mat 3 lect 2 lightwt fac met clad2012 13 mat 3 lect 2 lightwt fac met clad
2012 13 mat 3 lect 2 lightwt fac met cladC_W_X
 
California academy of Science: Case study
California academy of Science: Case studyCalifornia academy of Science: Case study
California academy of Science: Case studySatya Rachakonda
 
Raghuleela mall, Vashi
Raghuleela mall, VashiRaghuleela mall, Vashi
Raghuleela mall, Vashiamupatil13
 
MASTER PLAN OF GGSIPU Shrikant
MASTER PLAN OF GGSIPU  ShrikantMASTER PLAN OF GGSIPU  Shrikant
MASTER PLAN OF GGSIPU ShrikantShriKant49
 

Mais procurados (20)

Sustainability in interior design, Architecture
Sustainability in interior design, ArchitectureSustainability in interior design, Architecture
Sustainability in interior design, Architecture
 
American parks Landscape design Central park new york case study
American parks Landscape design Central park new york case studyAmerican parks Landscape design Central park new york case study
American parks Landscape design Central park new york case study
 
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBIN
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBINCULTURAL CENTER OF THE PHILIPPINES BY RG GARBIN
CULTURAL CENTER OF THE PHILIPPINES BY RG GARBIN
 
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)
BUILDING A SHOPPING COMPLEX FOR THE GENERATION X (GEN X)
 
School Design
School Design School Design
School Design
 
Primary school (1)
Primary school (1)Primary school (1)
Primary school (1)
 
Types of Low E Glass Coatings
Types of Low E Glass CoatingsTypes of Low E Glass Coatings
Types of Low E Glass Coatings
 
Literature review exhibtion center
Literature review exhibtion centerLiterature review exhibtion center
Literature review exhibtion center
 
Minimum standard
Minimum standardMinimum standard
Minimum standard
 
Green Urban Design for Brgy Lapaz, Makati City, Philippines
Green Urban Design for Brgy Lapaz, Makati City, PhilippinesGreen Urban Design for Brgy Lapaz, Makati City, Philippines
Green Urban Design for Brgy Lapaz, Makati City, Philippines
 
LANDSCAPE CASE STUDY
LANDSCAPE CASE STUDYLANDSCAPE CASE STUDY
LANDSCAPE CASE STUDY
 
GreenStudio - Chapter 4 2 7 Shading Devices
GreenStudio - Chapter 4 2 7 Shading DevicesGreenStudio - Chapter 4 2 7 Shading Devices
GreenStudio - Chapter 4 2 7 Shading Devices
 
Passive Design Strategies, Teksing BambooWood School, Kavre, Nepal
Passive Design Strategies, Teksing BambooWood School, Kavre, NepalPassive Design Strategies, Teksing BambooWood School, Kavre, Nepal
Passive Design Strategies, Teksing BambooWood School, Kavre, Nepal
 
Report on tesla solar roof
Report on tesla solar roofReport on tesla solar roof
Report on tesla solar roof
 
Detailing : Interior Wall Assemblies
Detailing : Interior Wall AssembliesDetailing : Interior Wall Assemblies
Detailing : Interior Wall Assemblies
 
2012 13 mat 3 lect 2 lightwt fac met clad
2012 13 mat 3 lect 2 lightwt fac met clad2012 13 mat 3 lect 2 lightwt fac met clad
2012 13 mat 3 lect 2 lightwt fac met clad
 
Landscape Architecture
Landscape ArchitectureLandscape Architecture
Landscape Architecture
 
California academy of Science: Case study
California academy of Science: Case studyCalifornia academy of Science: Case study
California academy of Science: Case study
 
Raghuleela mall, Vashi
Raghuleela mall, VashiRaghuleela mall, Vashi
Raghuleela mall, Vashi
 
MASTER PLAN OF GGSIPU Shrikant
MASTER PLAN OF GGSIPU  ShrikantMASTER PLAN OF GGSIPU  Shrikant
MASTER PLAN OF GGSIPU Shrikant
 

Semelhante a Sustainable School Projects: Rain Garden

Sustainable School Projects: Rain Garden
Sustainable School Projects: Rain GardenSustainable School Projects: Rain Garden
Sustainable School Projects: Rain GardenSotirakou964
 
Bs finallll (1)
Bs finallll (1)Bs finallll (1)
Bs finallll (1)Lam Yu
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)kohwenqi
 
Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)Doreen Yeo
 
Kansas Rain Garden Manual
Kansas Rain Garden ManualKansas Rain Garden Manual
Kansas Rain Garden ManualSotirakou964
 
Create a Rain garden
Create a Rain gardenCreate a Rain garden
Create a Rain gardenalind tiwari
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvestingalind tiwari
 
Delaware Rain Gardens Manual
Delaware Rain Gardens ManualDelaware Rain Gardens Manual
Delaware Rain Gardens ManualSotirakou964
 

Semelhante a Sustainable School Projects: Rain Garden (20)

Sustainable School Projects: Rain Garden
Sustainable School Projects: Rain GardenSustainable School Projects: Rain Garden
Sustainable School Projects: Rain Garden
 
Bs finallll (1)
Bs finallll (1)Bs finallll (1)
Bs finallll (1)
 
Wisconsin Rain Gardens: A How to Manual for Homeowners
Wisconsin Rain Gardens: A How to Manual for HomeownersWisconsin Rain Gardens: A How to Manual for Homeowners
Wisconsin Rain Gardens: A How to Manual for Homeowners
 
West Michigan: Rain Gardens
West Michigan: Rain GardensWest Michigan: Rain Gardens
West Michigan: Rain Gardens
 
Rain garden
Rain gardenRain garden
Rain garden
 
Group 5 sustainable stormwater management(building services1)
Group 5   sustainable stormwater management(building services1)Group 5   sustainable stormwater management(building services1)
Group 5 sustainable stormwater management(building services1)
 
Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)Sustainable stormwater management(building services1)
Sustainable stormwater management(building services1)
 
Oklahoma Farm to School: Rain Gardens
Oklahoma Farm to School: Rain GardensOklahoma Farm to School: Rain Gardens
Oklahoma Farm to School: Rain Gardens
 
Kansas Rain Garden Manual
Kansas Rain Garden ManualKansas Rain Garden Manual
Kansas Rain Garden Manual
 
Rain Gardens - Helping the Environment While Enhancing the Beauty of Your Yard
Rain Gardens - Helping the Environment While Enhancing the Beauty of Your YardRain Gardens - Helping the Environment While Enhancing the Beauty of Your Yard
Rain Gardens - Helping the Environment While Enhancing the Beauty of Your Yard
 
Test
TestTest
Test
 
Rain Garden
Rain GardenRain Garden
Rain Garden
 
Create a Rain garden
Create a Rain gardenCreate a Rain garden
Create a Rain garden
 
Rain garden
Rain gardenRain garden
Rain garden
 
Rain water harvesting
Rain water harvestingRain water harvesting
Rain water harvesting
 
Delaware Rain Gardens Manual
Delaware Rain Gardens ManualDelaware Rain Gardens Manual
Delaware Rain Gardens Manual
 
Delaware Rain Gardens Manual
Delaware Rain Gardens ManualDelaware Rain Gardens Manual
Delaware Rain Gardens Manual
 
North Carolina, Asheville - Rain Gardens
North Carolina, Asheville - Rain Gardens North Carolina, Asheville - Rain Gardens
North Carolina, Asheville - Rain Gardens
 
Kansas Rain Garden Design and Implementation Manual ~ Kansas State University
Kansas Rain Garden Design and Implementation Manual ~ Kansas State UniversityKansas Rain Garden Design and Implementation Manual ~ Kansas State University
Kansas Rain Garden Design and Implementation Manual ~ Kansas State University
 
Western Washington Rain Garden Handbook
Western Washington Rain Garden HandbookWestern Washington Rain Garden Handbook
Western Washington Rain Garden Handbook
 

Mais de School Vegetable Gardening - Victory Gardens

Mais de School Vegetable Gardening - Victory Gardens (20)

Behind Enemy Lines - Marthe Cohn - One Woman against Nazi Germany
Behind Enemy Lines - Marthe Cohn - One Woman against Nazi GermanyBehind Enemy Lines - Marthe Cohn - One Woman against Nazi Germany
Behind Enemy Lines - Marthe Cohn - One Woman against Nazi Germany
 
Classical Art School Gardening Posters
Classical Art School Gardening PostersClassical Art School Gardening Posters
Classical Art School Gardening Posters
 
One Teacher Saves her School & her Students
One Teacher Saves her School & her StudentsOne Teacher Saves her School & her Students
One Teacher Saves her School & her Students
 
Coconut Oil helps Heal Children's ADHD - ADD Disease, Autism & Alzheimer Disease
Coconut Oil helps Heal Children's ADHD - ADD Disease, Autism & Alzheimer DiseaseCoconut Oil helps Heal Children's ADHD - ADD Disease, Autism & Alzheimer Disease
Coconut Oil helps Heal Children's ADHD - ADD Disease, Autism & Alzheimer Disease
 
One Teacher Makes Students into Champions
One Teacher Makes Students into ChampionsOne Teacher Makes Students into Champions
One Teacher Makes Students into Champions
 
Good Books help Students Excel in Life & School
Good Books help Students Excel in Life & SchoolGood Books help Students Excel in Life & School
Good Books help Students Excel in Life & School
 
Greening & Restoring the Sahara Desert with the Groasis Waterboxx
Greening & Restoring the Sahara Desert with the Groasis WaterboxxGreening & Restoring the Sahara Desert with the Groasis Waterboxx
Greening & Restoring the Sahara Desert with the Groasis Waterboxx
 
Groasis Waterboxx Lets Trees Grow Up in Unfriendly Places
Groasis Waterboxx Lets Trees Grow Up in Unfriendly PlacesGroasis Waterboxx Lets Trees Grow Up in Unfriendly Places
Groasis Waterboxx Lets Trees Grow Up in Unfriendly Places
 
Explanation of the Groasis Technology for Growing Food in Desert Regions
Explanation of the Groasis Technology for Growing Food in Desert RegionsExplanation of the Groasis Technology for Growing Food in Desert Regions
Explanation of the Groasis Technology for Growing Food in Desert Regions
 
Groasis Waterboxx & the Agua, Vida Naturaleza Project for Growing Food in Des...
Groasis Waterboxx & the Agua, Vida Naturaleza Project for Growing Food in Des...Groasis Waterboxx & the Agua, Vida Naturaleza Project for Growing Food in Des...
Groasis Waterboxx & the Agua, Vida Naturaleza Project for Growing Food in Des...
 
Groasis Waterboxx Handbook on Planting Instructions for Trees & Crops in Dese...
Groasis Waterboxx Handbook on Planting Instructions for Trees & Crops in Dese...Groasis Waterboxx Handbook on Planting Instructions for Trees & Crops in Dese...
Groasis Waterboxx Handbook on Planting Instructions for Trees & Crops in Dese...
 
Groasis Waterboxx Manual for Growing Vegetables in Arid Lands
Groasis Waterboxx Manual for Growing Vegetables in Arid LandsGroasis Waterboxx Manual for Growing Vegetables in Arid Lands
Groasis Waterboxx Manual for Growing Vegetables in Arid Lands
 
Water Saving Measures of Using the Groasis Waterboxx in Organic Gardening in ...
Water Saving Measures of Using the Groasis Waterboxx in Organic Gardening in ...Water Saving Measures of Using the Groasis Waterboxx in Organic Gardening in ...
Water Saving Measures of Using the Groasis Waterboxx in Organic Gardening in ...
 
Making a Week’s Worth of Rain Last the Whole Year
Making a Week’s Worth of Rain Last the Whole YearMaking a Week’s Worth of Rain Last the Whole Year
Making a Week’s Worth of Rain Last the Whole Year
 
Using the Groasis Waterboxx to Plant New Trees in Desert Regions
Using the Groasis Waterboxx to Plant New Trees in Desert RegionsUsing the Groasis Waterboxx to Plant New Trees in Desert Regions
Using the Groasis Waterboxx to Plant New Trees in Desert Regions
 
Greening the World - Desert Restoration, Reduce CO2, Feed the People & Create...
Greening the World - Desert Restoration, Reduce CO2, Feed the People & Create...Greening the World - Desert Restoration, Reduce CO2, Feed the People & Create...
Greening the World - Desert Restoration, Reduce CO2, Feed the People & Create...
 
Groasis Technology Compared to Drip Irrigation
Groasis Technology Compared to Drip IrrigationGroasis Technology Compared to Drip Irrigation
Groasis Technology Compared to Drip Irrigation
 
Groasis Waterboxx - Palm Springs Students Test New Planter Designed to Fight ...
Groasis Waterboxx - Palm Springs Students Test New Planter Designed to Fight ...Groasis Waterboxx - Palm Springs Students Test New Planter Designed to Fight ...
Groasis Waterboxx - Palm Springs Students Test New Planter Designed to Fight ...
 
Groasis Waterboxx Handbook for Planting Methods & Sample of Crop Test Results...
Groasis Waterboxx Handbook for Planting Methods & Sample of Crop Test Results...Groasis Waterboxx Handbook for Planting Methods & Sample of Crop Test Results...
Groasis Waterboxx Handbook for Planting Methods & Sample of Crop Test Results...
 
Groasis Waterboxx Technology Offers Possible Cure for the Deserts
Groasis Waterboxx Technology Offers Possible Cure for the DesertsGroasis Waterboxx Technology Offers Possible Cure for the Deserts
Groasis Waterboxx Technology Offers Possible Cure for the Deserts
 

Último

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactPECB
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactdawncurless
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxiammrhaywood
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformChameera Dedduwage
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDThiyagu K
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Celine George
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingTechSoup
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxShobhayan Kirtania
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104misteraugie
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfchloefrazer622
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...anjaliyadav012327
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdfSoniaTolstoy
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxGaneshChakor2
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpinRaunakKeshri1
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docxPoojaSen20
 

Último (20)

Beyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global ImpactBeyond the EU: DORA and NIS 2 Directive's Global Impact
Beyond the EU: DORA and NIS 2 Directive's Global Impact
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
Accessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impactAccessible design: Minimum effort, maximum impact
Accessible design: Minimum effort, maximum impact
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptxSOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
SOCIAL AND HISTORICAL CONTEXT - LFTVD.pptx
 
A Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy ReformA Critique of the Proposed National Education Policy Reform
A Critique of the Proposed National Education Policy Reform
 
Measures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SDMeasures of Dispersion and Variability: Range, QD, AD and SD
Measures of Dispersion and Variability: Range, QD, AD and SD
 
Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17Advanced Views - Calendar View in Odoo 17
Advanced Views - Calendar View in Odoo 17
 
Grant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy ConsultingGrant Readiness 101 TechSoup and Remy Consulting
Grant Readiness 101 TechSoup and Remy Consulting
 
The byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptxThe byproduct of sericulture in different industries.pptx
The byproduct of sericulture in different industries.pptx
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104Nutritional Needs Presentation - HLTH 104
Nutritional Needs Presentation - HLTH 104
 
Disha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdfDisha NEET Physics Guide for classes 11 and 12.pdf
Disha NEET Physics Guide for classes 11 and 12.pdf
 
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
JAPAN: ORGANISATION OF PMDA, PHARMACEUTICAL LAWS & REGULATIONS, TYPES OF REGI...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdfBASLIQ CURRENT LOOKBOOK  LOOKBOOK(1) (1).pdf
BASLIQ CURRENT LOOKBOOK LOOKBOOK(1) (1).pdf
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
CARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptxCARE OF CHILD IN INCUBATOR..........pptx
CARE OF CHILD IN INCUBATOR..........pptx
 
Student login on Anyboli platform.helpin
Student login on Anyboli platform.helpinStudent login on Anyboli platform.helpin
Student login on Anyboli platform.helpin
 
mini mental status format.docx
mini    mental       status     format.docxmini    mental       status     format.docx
mini mental status format.docx
 

Sustainable School Projects: Rain Garden

  • 1. Sustainable School Projects: Rain Garden Page 1 of 12 Rain Garden A simple, yet effective method to control stormwater is through the use of rain gardens. The design of a rain garden involves, among other things, the hydrologic cycle, nonpoint pollutant treatment, resource conservation, habitat creation, nutrient cycles, soil chemistry, horticulture, landscape architecture, and ecology. Beyond its use for stormwater control, the rain garden provides attractive landscaping and a natural habitat for birds and butterflies, while encouraging environmental stewardship and community pride. To continue choose a step from the list below: Step 1 - Let's Begin Step 2 - Goals/Objectives & Budget Step 3 - Gather Information Step 4 - Location & Size of Rain Garden Step 5 - Designing Your Rain Garden Step 6 - Selecting Plants for Your Rain Garden Step 7 - Design Review & Obtaining Permission Step 8 - Construction Step 9 - Maintenance Step 10 - Advertise Step 11 - Develop Timeline Step 12 - Preliminary Plans for Construction Day Step 13 - Construction Day Step 14 - Write Summary Report Step 15 - Keep it going! Step 1 - Let's Begin ● Identify project participants (students and teachers) - Assign group leaders to communicate with maintenance staff ● Begin securing partnership involvement ● Get written agreement from school administration and maintenance staff - Clarify roles and responsibilities - Each school may allow a different amount of landscape changes - Ensure that there will be open communication throughout the project
  • 2. Sustainable School Projects: Rain Garden Page 2 of 12 Step 2 - Goals/Objectives and Budget ● Outline project goals and objectives ● Estimate amount you intend to spend [Budget] ● Establish link between current school curriculum and environmental enhancement project. Cost Planning - $25 Design - $100 Materials - $varies Plants - $varies Soil - $varies Other - $varies Construction - $950 Labor - $0 (volunteers) TOTAL ESTIMATED COST: $1,075 Cost Spreadsheet Residential rain gardens average about $3 to $4 per square foot, depending on soil conditions and the density and types of plants used. Commercial, industrial and institutional site costs can range between $10 to $40 per square foot, based on the need for control structures, curbing, storm drains and underdrains. In any bioretention cell design, the cost of plants varies substantially and can account for a significant portion of the facility's expenditures. While these cost estimates are slightly greater than those of typical landscaping treatment (due to the increased number of plantings, additional soil excavation, backfill material, use of underdrains etc.), those landscaping expenses that would be required regardless of the bioretention installation should be subtracted when determining the net cost. Step 3 - Gather Information ● Obtain a schematic of the school including wetlands, power lines, fire lanes, future building plans, etc. ● Walk around and survey the school grounds to identify potential areas for project implementation (i.e. areas where water ponds during/after storms, areas where there is a lot of erosion, landscaping doesn’t get enough water)
  • 3. Sustainable School Projects: Rain Garden Page 3 of 12 ● Identify gutters/downspouts ● Request assistance from landscape architect, ecologist, and maintenance staff ● Investigate permit requirements ● Make list of problem areas ● Take pictures of problem areas ● Conduct informal survey of school community (including students, staff, parents, and maintenance staff) to determine their satisfaction with the current state of the school environment. Step 4 - Location and Size of Rain Garden Now that you have walked the campus, gathered all of the maps and materials you need, talked to the facilities manager, surveyed your fellow students and teachers, and listed the problem areas or potential areas for your rain garden, here are things to consider when locating and sizing your rain garden. Make sure you do not plan your rain garden in a riparian buffer, too close to the foundation, and other factors listed below in the “Location” section. Also, be sure to design a manageable rain garden – make sure it is a size that can be maintained well by your class. Check out the maintenance requirements in Step 9. ● Two primary factors to consider when designing a rain garden are: ● Planning the location of your rain garden ● How to determine the size of your rain garden **NOTE: Now is an excellent time to call your local Cooperative Extension Office to have them test the soil. They will do this free of charge. A good soil mix for a rain garden is 50% sand, 20% topsoil, and 30% compost. If the soil onsite contains less than 10% clay, then it can be used in place of imported topsoil in the mix. It is possible you may be able to use the existing soil, but if it is not in good condition, you may have to spend some money on new soil and/or amendments such as lime, gypsum and specific nutrients.
  • 4. Sustainable School Projects: Rain Garden Page 4 of 12 How to find an appropriate location for a rain garden Take a walk around the school grounds during the next rainstorm. Make a note of where puddles are forming, which areas are not draining well, and where runoff is flowing. Finding a good location for a rain garden involves balancing a number of different factors: The rain garden should be located in a place where it will receive runoff. Check to make sure runoff flows to your site, or could flow with minor modifications, such as cutting a space out of a curb. The rain garden must be located far enough from the building to avoid damage to the foundation. If your school has a basement, the rain garden should be located at least 25’ from the building. If there is no basement, the rain garden should be at least 5’ from the building. Find out where underground utilities are buried. Common utilities will include: water, sewer, electricity, natural gas, telephone, cable, and possibly a separate storm sewer (some older areas have combined sewers, where the stormwater drains directly into the sanitary sewer system). It is often difficult and time consuming to find out exactly where all of the utilities are buried on your site, so start early. Write letters to each of the utilities, requesting plans showing the locations of underground utilities on your property. Have your maintenance staff show you where the utilities enter the building, and try to avoid using this area for rain gardens. Before construction, you can call Miss Utility, who will come to your site and mark the locations of utilities with spray paint, so you can be certain of avoiding them. Stay at least five feet horizontally and one foot vertically from any utilities. Check your soil. Since a lot of earth was moved during the construction of your school and school grounds, it is likely that your soils will be highly compacted, and will not drain well. In order to compensate for this, you should use a special soil mix within the rain garden. You should also install an underdrain at the bottom of the rain garden.
  • 5. Sustainable School Projects: Rain Garden Page 5 of 12 The underdrain should be a perforated PVC pipe that runs from the bottom of the rain garden out to some discharge point. This could be a grassy area, a wooded area, a stream, or even a parking lot. Also consider what will happen to runoff during very large storms. The rain garden is designed for small storms. When there is a great deal of rain, the rain garden will fill and eventually overflow. Be aware of where water will go when it overflows the rain garden. Minimize the impact that this overflow will have by directing it toward grassy areas, wooded areas, or existing storm drains. Avoid trees. Soils near trees tend to have the best drainage, and should not be disturbed. Avoid areas where there will be heavy foot traffic. Heavy foot traffic will pack down the soil in the rain garden, which will degrade its ability to infiltrate runoff. Place the rain garden somewhere out of the way, where the soil will not be compacted, and the vegetation will not be trampled. Be sensitive to how other people use of the site. For example, avoid building your rain garden on a favorite picnic spot. How to determine the size of a rain garden When full, the ponded area should have a maximum depth of six inches. The planting soil usually has a minimum depth of 2.5 feet, but this depth may be constrained by the maximum depth of the underdrain at your site. The underdrain must discharge down gradient from the rain garden. Depending on your site topography, the bottom of the rain garden may need to be shallower than three feet below the ground surface. When rain gardens are designed for new sites, their sizes are matched to their drainage areas. When a site is being retrofit, the size of the rain garden is often limited by the availability of suitable space. Even in this case, it is important to estimate how effectively your proposed rain garden will capture, treat and infiltrate runoff from your site. This can be accomplished using the sizing tool.
  • 6. Sustainable School Projects: Rain Garden Page 6 of 12 Step 5 - Designing Your Rain Garden Now that you have determined the location and size of your rain garden you can begin to design it: ● Copy and increase the size of the school plan so that every inch equal 10 feet (1” = 10’) ● Draw a schematic drawing of the rain garden on a copy of the school plan ● Show where the water source comes into the rain garden (bioswale, rain barrel hose, or where water sheets off of sidewalk or parking lot) ● Determine the size of the rain garden (in square feet) Step 6 - Selecting Plants for Your Rain Garden Now that you have selected the location and determined the size of your rain garden take a few days to analyze the site you have selected. The success of your rain garden depends on this important information. Take notes and track what is happening at the site in the rain and on sunny days. Write down how much sun it gets – how many hours of afternoon sun? morning sun? Is there a reflection off of an adjacent building that provides more light or seems to make the heat more severe? Figure out if there are any unusual ‘microclimates’ at the site and then begin researching the plants that like these conditions. Plant your rain garden with plants that thrive in that environment. Whether in the sun or shade, rain gardens can be planted with shrubs and flowers that are beautiful and low maintenance – as long as you select the plants that love those conditions. Native plants – or plants that grow naturally in this climate or region -- can thrive without a lot of care, extra water, or extra fertilizer. This is an opportunity to learn more about the types of plants that love the sun, love the shade, love to have their ‘feet wet’ for a day or two, or don’t mind being dry for days on end. It is like a puzzle. See if you can pick out plants that are different heights, have different leaf color, and bloom different colors throughout the spring, summer, and fall seasons. Remember that even in the winter, plants without leaves can provide berries for birds
  • 7. Sustainable School Projects: Rain Garden Page 7 of 12 and have an unusual structure that can be accentuated in the snow. Designing with Plants: ● Use a circle template (or ruler) to place plants in your rain garden ● Select several 4-6’ shrubs, a lot of perennials (flowers that come back every year), and depending on the size of the rain garden a medium-sized tree or two [15-20’ at full growth]) Refer to the sample drawing to help you. Consider these things when selecting plants: ● Choose native plants when possible ● Avoid planting non-native invasive plants ● Choose fragrant or edible plants when possible ● Avoid toxic/poisonous plants ● Avoid plants that produce excessive pollen Sample plant list to use as a guide: Prince George's County, MD Plant List Additional plant information: Useful Links Step 7 - Design Review and Obtaining Permission Once you have a schematic design of your rain garden, schedule a meeting with your principal and facilities/maintenance manager. This is an information gathering meeting and be prepared to make revisions based on the discussion at the meeting. Be prepared to discuss the construction and maintenance issues with the principal and maintenance staff. [Read the following steps (Step 8 – Construction and Step 9 – Maintenance) to understand the materials, material delivery, and site and soil preparation procedures.] During the meeting: ● Review the draft design ● Discuss the construction of the rain garden
  • 8. Sustainable School Projects: Rain Garden Page 8 of 12 ● Find out about school regulations about delivery and storage of materials and equipment that will be used for construction of the rain garden. ● Discuss the maintenance issues (roles and responsibilities) Step 8 - Construction Construction techniques are extremely critical in ensuring the success of a rain garden. Various construction guidelines and inspection points are given below, as well as a general construction schedule adapted from the Prince George's County Bioretention Manual. Local or regional rain garden/bioretention cell guides may also have useful information. Sequence of Construction 1/2 day - Install sediment control devices. (These are for larger projects. Check with your local building permit office. It’s a good idea to surround the down gradient part of the site with straw bales or silt fence. It’s readily available and inexpensive.) 1 day - Grade site to elevations shown on plan. If applicable, construct curb openings and/or remove and replace existing concrete. Curb openings should be blocked or other measures taken to prohibit drainage from entering construction area. (Equipment such as a backhoe may be rented for this. Make sure any Miss Utility is notified before any digging. Safety fence should be used around any construction area or excavation.) 1/2 day - Stabilize grading within Limit of Disturbance except for the bioretention area, which will be planted. (Surrounding the cell with a biolog, straw bales, or compost berm to keep sediment out of the bioretention cell.) 1/2 day - Excavate bioretention area to proposed invert depth and scarify the existing soil surfaces, taking care not to compact the in-situ materials. (A contractor may be hired to dig the hole. Make sure that there are no open areas or pits open at the end of the day and no excavation over local jurisdiction or OSHA limits. Generally bioretention cells are less than 3 feet deep.)
  • 9. Sustainable School Projects: Rain Garden Page 9 of 12 1/2 day - Install underdrain system and observation wells, if specified. (Use perforated 4” HDPE pipe and surround the pipe with about 2” of gravel) 1/4 day - Backfill bioretention area with planting soil. (Fill the cell with 8” lifts of soil. Saturate each lift and let it drain and then place the next lift. Be careful not to compact the soil with equipment and saturate it.) 1/4 day - Plant vegetation. 1/4 day - Mulch and install erosion protection at entrance points. Remove sediment control practices or entrance blocks with inspector authorization if this project requires a permit. (It is recommended to leave perimeter biodegradable controls to reduce sediment loads to cell) Total Estimated Construction Time: 5.5 Days Step 9 - Maintenance A routine maintenance schedule can be followed. An example is presented here, as adapted from the Prince George's County Bioretention Manual. Experience has shown that the economic incentive of maintaining property values ensures that most homeowners will maintain their LID landscape. Maintenance Schedule Soil ● Visually inspect and repair erosion monthly. Use small stones to stabilize erosion along drainage paths. ● Check the pH once or twice a year. Apply an alkaline product, such as limestone, if needed. Mulch ● Re-mulch any void areas by hand as needed. ● Every 6 months, in the spring and fall, add a fresh mulch layer. ● Once every 2 to 3 years, in the spring, remove old mulch layer before applying new one. Plants
  • 10. Sustainable School Projects: Rain Garden Page 10 of 12 ● Immediately after the completion of cell construction, water plant material for 14 consecutive days unless there is sufficient natural rainfall. ● When trees have taken root, or at least by 6 months, remove stakes and wires. ● Once a month (more frequently in the summer), visually inspect vegetation for disease or pest problems. ● If treatment is warranted, use the least toxic approach. ● Twice a year, from March 15th to April 30th and October 1st to November 30th, remove and replace all dead and diseased vegetation considered beyond treatment. ● During times of extended drought, look for physical features of stress (unrevived wilting, yellow, spotted or brown leaves, loss of leaves, etc.). Water in the early morning as needed. ● Weed regularly, if needed. ● Prune excess growth annually or more often, if desired. Trimmed materials may be recycled back in with replenished mulch or land filled if there is a concern of heavy metals accumulation. General ● After rainstorms, inspect the cell and make sure that drainage paths are clear and that ponding water dissipates over 4-6 hours. (Water may pond for longer times during the winter and early spring.) **NOTE: Keep in mind, the rain garden is not a pond. It should not provide a breeding ground for mosquitoes. Mosquitoes need at least 4 days of standing water to develop as larva. Step 10 - Advertise ● Spread the word!!! ● Develop a website ● Provide an outline of goals and objectives ● Post pictures ● Advertise URL through school newspaper, public television ● Update often Step 11 - Create Timeline ● Order supplies ● Arrange for material delivery
  • 11. Sustainable School Projects: Rain Garden Page 11 of 12 ● Advertise work days on web and in school newspaper - Ask for volunteers ● Create timeline for project completion Step 12 - Preliminary Plans for Construction Day Some final preparations need to be made to make your construction day a success. Be sure to: 1. Notify your school administrators and maintenance staff that the construction will begin 2. Call key volunteers (Ask them to arrive early and be Team Leaders) 3. Ask volunteers to bring gloves, shovels, and water bottles (make sure their tools are labeled with their names) 4. Create a Task List 5. Delegate responsibility so that you can be free to coordinate on construction day 6. Print out and copy the Construction Sequence page 7. Get an Emergency Kit and set up an Emergency Plan 8. Make sure building door(s) are open so that volunteers can use bathroom facilities 9. Make sure you have access to water hose 10. Provide refreshments and snacks (if possible) – at least provide water 11. Contact local newspaper, or designate a student volunteer or parent to take photos and write about the event 12. Bring camera Step 13 - Construction Day Now that all of your materials have been ordered and volunteers have been scheduled it is time to construct your rain garden. Prior to construction: 1. Arrive early 2. Take “Before” photo 3. Organize the construction site: ● Position plants and materials ● Label tools
  • 12. Sustainable School Projects: Rain Garden Page 12 of 12 ● Place tools that are not being used in a central location ● Put Emergency Kit on hand in the central location 4. Greet and organize volunteers ● Have volunteers sign in ● Delegate responsibilities ● Announce the schedule and breaks ● Provide info on emergency plan, bathroom locations, and refreshments ● Distribute the Construction Sequence information ● Take photo of all volunteers During Construction: 1. Take photos of all the construction phases, emphasizing the volunteers 2. Interview the volunteers Post-Construction: 1. Water the rain garden 2. Take “After” photo 3. Step back and appreciate Remember to: ● Continuously monitor safety ● Have fun! Step 14 - Write Summary Report ● Write final report - Use input from all students involved ● Post names of volunteers on web and in school newspaper ● Take follow-up survey of school community ● Review budget ● Plan long-term maintenance ● Determine future learning outcomes Step 15 - Keep It Going ● Where do we go from here?!!! The End!!