SlideShare uma empresa Scribd logo
1 de 37
Baixar para ler offline
CONFIDENTIAL AND PROPRIETARY
DESTINATION BIHAR:
OPPORTUNITIES IN BIHAR STATE’S
TRANSMISSION AND DISTRIBUTION SECTOR
2
FROM A GLORIOUS PAST TO A GLORIOUS FUTURE
Ancient Bihar was a centre for:
Power – Maurya dynasty first and one of the greatest
Learning - Nalanda and Vikramshila; one of the oldest and truly
international universities of the world
Culture and religion - Buddhism started from Bihar
The state since the 70’s lagged behind other India states in economic terms
However, recently it is bouncing back with
Improved governance – better law and order situation
Greater emphasis on education
Increased investment in Infrastructure
Better health care facilities
3
A shining example of development is the Roads Sector.
Bihar State Highway Project Phase I– 9 Packages, 820 KM of State
Highways under implementation
Bihar State Highway Project Phase II– 4 Packages, SH 78 (100 KM) under
implementation
Bihar State Highway Project Phase III– 3 Packages
7 PPP Projects (NH) identified and under various stages of execution
4 Laning of Corridors
For the period 2011–2012, Bihar was also India's fastest growing State, with a
growth rate of 13.1% for the year 2011–12, which had followed a growth rate
of 14.8% for the previous year.
Bihar has managed to record 11.95% annual growth rate, the highest among all
the states, during the 11th Plan period
4
DESTINATION BIHAR:
OPPORTUNITIES IN BIHAR STATE’S TRANSMISSION AND DISTRIBUTION SECTOR
The Bihar State Power Transmission and Distribution Sectors including Rural
Electrification are set to receive, tender and execute projects to the tune of INR ~28,250
Cr
These projects are to be tendered and executed within the 12th Plan (now 2013-14 to
2016-17)
The projects are at various stages – planned, sanctioned, tendered or awarded
The projects funded under schemes such as the BRGF, RAPDRP, RGGVY , ADB and the
State Plan
The prime objective of the conference is to create an awareness, amongst
participants, of the substantial opportunity present in the State as well as the
support provided by the State to private players participating in the Sector
S.No Sector Amount (in INR Cr)
1 Transmission (including Schemes and State Plan) 8,114
2
Distribution (including Schemes and State Plan) 20,137 (includes RGGVY and
RAPDRP)
Total 28,251
5
AGENDA
1.0 SECTOR AND UTILITY PROFILE
CURRENT SCHEMES
OPPORTUNITIES IN TRANSMISSION
POTENTIAL CHALLENGES
INDEPENDENT MARKET VIEW OF THE UTILITY2.0
3.0
4.0
6.0
OPPORTUNITIES IN DISTRIBUTION5.0
6
1.0 SECTOR AND UTILITY PROFILE
7
SECTOR AND UTILITY (TRANSCO) PROFILE
Ownership
Installed Capacity in MW
Grand
TotalCoal Hydro RES*
State 210 0 66.3 276.3
Private 0 0 29.5 29.5
Central 1414.7 129.43 0 1544.1
Sub-total 1624.7 129.43 95.8 1849.9
Status of Transmission Infrastructure
S. No Voltage
No. of
Substation
Length
(Kms)
Transmiss-
ion (MVA)
1 400 kV - 75.00 -
2 220 kV 9 1147 2450
3 132 kV 76 5178 4588
85 6400
Peak Demand & Peak Demand Met in (MW) for Bihar
(Source: CEA Annual reports) Transmission circles include Patna, Bihar Sharif, Gaya,
Dehri on Sone, Muzaffarpur, Purnea and Bhagalpur
1509
1882
2192
2642
3194
3873
4472
5602
0
1000
2000
3000
4000
5000
6000
2009 2010 2011 2012 2013 2014 2015 2016
inMW
Peak Demand
8
UTILITY PROFILE (DISCOMS)
Bihar State
Power Holding
Company Ltd.
Bihar State
Power
Generation
Company
Bihar State
Power
Transmission
Company
North Bihar
Power
Distribution
Company
South Bihar
Power
Distribution
Company
Bihar State
Electricity
Board
Unbundled in 2012
as per EA ‘03
Distribution Company
Estimated
Population
*
No. of
Districts
Electricity Consumers
(approx)
Area Circles
North Bihar Power Distribution
Co Ltd
6.5 Cr 21 22 Lacs
52,925 Sq Km
(53.46% of total)
7 Electric Supply Circles: Saharsa,
Purnea, Muzaffarpur, Motihari,
Chapra, Darbhanga, Samastipur
South Bihar Power Distribution
Co Ltd
3.8 Cr 17 18 Lacs
46,070 Sq Km
(46.54% of total)
9 Electric Supply Circles: Patna,
Bhojpur (Ara), Nalanda
(Biharsharif), PESU (East), PESU
(West), Gaya, Rohtas (Sasaram),
Bhagalpur, Munger
*As per Census data 2011
9
UTILITY PROFILE (DISCOMS) CONTINUED….
-
500,000
1,000,000
1,500,000
2,000,000
2,500,000
3,000,000
3,500,000
4,000,000
4,500,000
2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12
Revenue – Cost Gap (INR/ unit) Growth in Consumer Numbers
(Source: erstwhile BERC Tariff) (Source: erstwhile BSEB Annual reports)
Demand of the state growing at a CAGR of 8 %
Industrial and Domestic consumers contribute to about 50% of the total sales
The gap between demand and supply was highest during 2009-10 - 32.9 %(720 MW)
The gap reduced to 15.5% in the year 2011-12 owing to the short and medium term purchases by erstwhile
BSEB; energy deficit in FY 2012-13 – 16.7%
Steady rise (Rs 2.25 per unit at 11.1 % CAGR) in Average Billing Rate during FY 2005-06 to FY 2011-12
Power purchase cost increased twice as fast as the increase in revenue; however, from the last two years,
revenue has been increasing at a CAGR of 18%
2.06
2.26
2.50 2.57
3.273.27 3.26 3.26 3.39
4.09
0.00
1.00
2.00
3.00
4.00
5.00
2008-09 2009-10 2010-11 2011-12 2012-13
Cost Revenue
10
POLICY IMPLEMENTATION DASHBOARD – CEA TARGETS
Policy Description Status
Rural
Electrification
Policy
56% of the villages should be electrified by 2012
At least one 33/11 kV sub-station per block and at least one distribution transformer per village
National
Electricity
Policy, 2005
Introduction of Open Access in Distribution - Open Access availability to 1MW+ consumers
Full-fledged SCADA system for distribution utilities
Energy Audits for segregating techno-commercial losses
Provision of SCADA in Transmission system with upgrades
Determination of Open Access Charges in Transmission
Electricity Act,
2003
Unbundling of State Electricity Boards and constitution of SERC
Setting up of special courts, assessing officer and appellate authority
Preparation of annual statement of accounts in consultation with C&AG
Supply of electricity by Distribution Licensee
National Tariff
Policy, 2006
Level of consumer tariff should be within (+) & (-) 20% of cost of supply
Tariff for agricultural use should be subsidized below cost of supply
Introduction of two part tariff and time differentiated tariff for large consumers (1 MW & above)
Development of tariff framework (Point of Connection mechanism) by CERC after taking into
consideration advice of CEA
Determination of technical loss benchmarks in transmission after considering advice of CEA
Development of Key performance indicators (KPI) for Transmission
Completed Ongoing Not yet startedSource: CEA
11
INDEPENDENT MARKET VIEW OF THE UTILITY2.0
12
INDEPENDENT MARKET VIEW ON DISCOMS
Observations from ‘First Annual Integrated Ratings of SDU as per
Framework Approved by MoP’ Report
by ICRA Ltd and Credit Analysis and Research Ltd
“B” Rating
1 BSPHCL
2 Northern Power Distribution Company of AP Ltd
3 Assam Power Distribution Company Ltd
4 Chamundeshwari Electricity Supply Corporation Ltd
5 Uttar Haryana Bijli Vitran Nigam Ltd
6 Tamil Nadu Generation and Distribution Corporation Ltd
7 Dakshin Haryana Bijli Vitran Nigam Ltd
8 MP Pashchim Kshetra Vidyut Vitaran Company Ltd
9 MP Poorv Kshetra Vidyut Vitaran Company Ltd
10 MP Madhya Kshetra Vidyut Vitran Company Ltd
Rating Definition – Below Average Operational and Financial Capability
13
INDEPENDENT MARKET VIEW ON DISCOMS CONTINUED….
…And Impact on Private Participants
S. No. Key Strengths Potential Impact
1
Satisfactory progress in terms of reforms and restructuring of the
sector, which includes unbundling on functional lines and
corporatization
Creation of favorable environment
for all participants
2
Timely receipt of subsidy from the State Government Funding available for the sector has
a direct impact on upcoming
projects and payment cycle
3
Effective functioning of the Bihar Electricity Regulatory Commission Timely execution of decisions
pertaining to the developer (DF,
IPTC) space
4
Regulatory clarity in place, on the back of release of multi-year tariff
order for the control period FY 2014 to FY 2016 in November 2012 and
timely filing of tariff petition/orders
Creation of favorable environment
for all participants
5
Timely availability of audited financial accounts for FY2012 Would assist private participants in
their decision making process
6
Implementation/steady progress in key reform measures such as
special courts for anti-theft measures, unbundling of utilities, setting up
of consumer grievance forums, etc
Favorable environment for all
participants especially developers
7
Fuel & Power Purchase Cost Adjustment (FPPCA) framework is
operational, allowing the increase in such uncontrollable‟ cost items to
be recovered from consumers on monthly basis
Favorable environment for all
participants especially developers
14
INDEPENDENT MARKET VIEW ON DISCOMS CONTINUED….
…And Impact on Private Participants
S. No. Key Concerns Potential Impact/Counter
1
Continuing weak financial position, with coverage of costs through
revenues at less than 80%
Potential payment issues – to be
countered by incoming funding
2
High and increasing AT&C losses Opportunity for all potential private
participants including developers,
contractors, component
manufacturers and service provider;
Initiatives in metering and collection
efficiency already underway
3
Huge unmetered consumption and deterioration in collection
efficiency
Opportunity for all potential private
participants including developers,
contractors, component
manufacturers and service provider;
Initiatives in metering and collection
efficiency already underway
4
Funding of the entire asset base has been done through debt thus
leading to an unfavorable capital structure. Further, accumulated
losses from the past have led to a negative net worth
Participation in Financial
Restructuring Plan
High amount of receivables, although the same has shown a
declining trend over the years
May have an indirect impact on
payment– to be countered by
incoming funding
In order to improve billing and collection the utility has proposed and is implementing numerous initiatives,
such as:
spot billing , drop boxes and alternative points of collections, collection through mobile vans and banking,
internet banking facility, M-commerce initiatives, collection through Gramin banks etc.
15
CURRENT SCHEMES3.0
16
CURRENT SCHEMES DASHBOARD (with Approx INR values)
Sl. NO. Scheme Description
Allocation for State
Power Sector
Timeline of
Scheme for State
1
RGGVY (Rajiv Gandhi
Grameen Vidyutikaran
Yojana)
Scheme for creating rural
electricity infrastructure and
completing rural household
electrification from 33kV and
below level
11850 Cr
Partial
Electrification - 10th,
11th
Full Electrification -
12th Plan
2
R-APDRP (Restructured
– Accelerated Power
Development and
Reforms Programme)
Part B
Renovation, modernization
and strengthening of network
of 11 kV level and below
1155 Cr
Ongoing; scheduled
to culminate in 12th
Plan
3
BRGF (Backward
Regions Grant Fund )
Phase I and II
The fund will provide financial
resources for supplementing
and converging existing
developmental inflows into
identified districts
~9000 Cr 12th Plan
4
Multilateral funding
(ADB, WB etc…)
Funding in the State is
happening through
organizations such as Asian
Development Bank
375 Cr (under
implementation)
another ~700 Cr
planned
Ongoing
5 State Plan
State funded projects and
procurement. The plan is
made annually.
Transmission - ~300 Cr
Distribution – 300-400
Cr
Annual
17
BACKWARDS REGIONS GRANT FUND (Values in INR Cr)
BRGF Total Corpus for Bihar - ~
12000 Cr
Corpus for Bihar Power Sector -
~9000 Cr
BRGF Distribution Sector –
~5932 Cr
BRGF Transmission Sector –
~2194 Cr
Phase I –
~2484 Cr
Phase II –
~3448 Cr
Phase II Ext. –
~472 Cr
Phase III Ext. –
~1721 Cr
Strengthening of Distribution System and
Removal of Constraints; Phase I funds are
sanctioned and tendered
Strengthening of Sub-Transmission and
Transmission System; Phase II ext. funds are
sanctioned and under implementation
Apart from the above - Full Scale electrification of villages of 11 districts sanctioned by MoP/REC – INR ~837 Cr
State’s
Commitment to
the Sector
Addl. INR
5000+ Cr to be
executed in 12th
Plan
18
RGGGVY – PROPOSED and SANCTIONED DPRs (To be implemented in 12th Plan)
S.No District Amount (INR ~Cr) Current Status
1 Araria 243 Sanctioned
2 Purnea 308 Sanctioned
3 Siwan 320 Sanctioned
4 Kishanganj 273.29 Sanctioned and Tendered (submission upcoming)
5 Saran 302 Proposed
6 Gopalganj 277 Proposed
7 Samastipur 531 Proposed
8 Muzaffarpur 563 Proposed
9 Katihar 477 Proposed
10 Saharsa 249 Proposed
11 Darbhanga 398 Proposed
12 Supaul 340 Proposed
13 East Champaran 474 Proposed
14 Madhubani 583 Proposed
15 Begusarai 359 Proposed
16 Khagaria 170 Proposed
17 Madhepura 252 Proposed
18 Sitamarhi 309 Proposed
19 Sheohar 71 Proposed
20 West Champaran 451 Proposed
21 Vaishali 621 Proposed
Total ~7,571
Upcoming
Projects - INR
11,000 to
12,000 Cr!
19
RGGGVY – PROPOSED and SANCTIONED DPRs (To be implemented in 12th Plan)
S.No District Amount (INR ~Cr) Current Status
1 Banka 199 Awarded
2 Gaya 498 Awarded
3 Rohtas 218 Awarded
4 Patna 420 Awarded
5 Lakhisarai 153 Proposed
6 Aurangabad 358 Proposed
7 Bhabhua 338 Proposed
8 Buxar 254 Proposed
9 Bhagalpur 216 Proposed
10 Bhojpur 169 Sanctioned
11 Nalanda 456 Sanctioned
12 Nawada 241 Sanctioned
13 Munger 154 Proposed
14 Jamui 227 Proposed
15 Arwal 111 Proposed
16 Jehanabad 175 Proposed
17 Sheikhpura 89 Proposed
4,276
Upcoming
Projects - INR
11,000 to
12,000 Cr!
20
R-APDRP PART B
R-APDRP Part B Approved - ~
~1155 Cr
North Bihar
~287 Cr
South Bihar –
~868 Cr
Covers 3 Supply Areas, 7 Circles and 29 Towns Covers 4 Supply Areas, 9 Circles and 35 Towns
Top 5 Towns in Terms of Value
S.No District Approved Value
(INR Cr)
1 Patna 505
2 Gaya 65.4
3 Bhagalpur 55.7
4 Munger 23.5
5 Sasaram 20.4
Top 5 Towns in Terms of Value
S.No District Approved Value
(INR Cr)
1 Muzaffarpur 61.7
2 Darbhanga 29.5
3 Purnea 27.8
4 Hajipur 27.3
5 Chapra 18.9
21
MULTI-LATERAL FUNDING
Ongoing ADB Sponsored Distribution
Works (86% ADB, 14% State)
Ongoing ADB Sponsored Transmission
Works (86% ADB, 14% State)
Package A – Bihar Sharif - INR 38 Cr
Package B – Motihari, Bettiah - INR 34 Cr
Pkg C – Samastipur, Begusarai - INR 56 Cr
Package D – Ara, Buxer- INR 49 Cr
Package G – S/S- INR 49 Cr
Package H – S/S- INR 47 Cr
Package I – TL - INR 58 Cr
Package J – TL - INR 42 Cr
Investment of INR ~300
Cr expected in
Distribution till 2015-16
Main works to be carried out:
• Augmentation of substation capacity
• LT and HT lines re-conductoring
• New lines
• Consumer metering
22
OPPORTUNITIES IN TRANSMISSION4.0
23
Tendered
Projects -
INR 500 Cr+
OPPORTUNITIES IN TRANSMISSION
Current Opportunities (BRGF Phase II and III ext) – Partial List
S.No Works Est. Value (INR ~Cr)
1 NIT No. 160/PR/BSPTCL/2013 – 132 KV D/C lines and line bays in GSS (3 Packages) 60
2
NIT No. 161/PR/BSPTCL/2013 - Re-conductoring of 132 KV S/C and D/C lines (4
Packages)
56
3
NIT No. 162/PR/BSPTCL/2013 - Re-conductoring of 132 KV S/C and D/C lines (4
Packages)
42
4 NIT No. 168/PR/BSPTCL/2013 - Re-conductoring of 220 KV D/C lines (2 Packages) 31.5
5
Capacity Augmentation of 220/132 KV GSS (7 GSSs) by installing one 160 MVA
Transformer at each GSS, constructing bays – Turnkey Basis
67.5
6
Capacity Augmentation of 132/33 KV GSS (6 GSSs) by installing one 50 MVA and one
20 MVA Transformer at 6 GSS (different for 50 MVA and 20 MVA) , constructing bays
etc– Turnkey Basis
58.5
7
Construction of 4 numbers 220/132 KV SS (Bhikanpura, Samastipur, Supaul and
SKMCH) and 1 number 132/33 KV SS (Sheohar) and associated Transmission Lines
1400 Cr (to be tendered)8 Capacity addition by above GSS; 220/132 KV - 1280 MVA, 132/33 KV – 600 MVA
9 Capacity augmentation of 32 Nos. old GSS (1700 MVA).
10 Stringing Of 2nd Circuit of Existing 17 No’s S/C Transmission Line.
Further details can be found on
www.eproc.bihar .gov.in
Upcoming
Projects - INR
1400 Cr
24
OPPORTUNITIES IN TRANSMISSION CONTINUED…
Upcoming Opportunities (BRGF Phase III) – To be Executed in 12th Plan
S.No Works Est. Value (INR ~Cr)
1
Construction of 03 Nos. 400/220/132 KV GSS (Bihta, Gaighat and Fatuha) and 11
Nos. 220/132/33 KV GSS (Chapra, Sonenagar, Gaya, Jakkanpur, Mithapur, Sabour,
Jamalpur, Sheikhpura, Nawada, Hathidah and Dumraon).
4600 Cr
2
(400/220 KV – 3000 MVA, 220/132 KV – 4160 MVA &
132/33 KV – 650 MVA).
3 Capacity augmentation of 09 Nos. old GSS (470 MVA).
4 2x500 MVA , 400/220 KV Pooling Station at Kajra
5 2x500 MVA, 400/220 KV I.P.P at Lakhisarai, Pirpainti & Buxar switchyard.
Current Opportunities (State Plan) – Partial List for 2013-14
S.No Works Est. Value (INR ~Cr)
1 Constraint Removal in Transmission System 49
2 Renovation of 15 GSS 9
3 2nd Circuit Stringing Activities -
Further
Execution in
12th Plan –
INR 4600 Cr
State spend on
projects and
procurement -
INR ~330 Cr PA
Total corpus planned to be executed by 2017 is INR~8000 Cr
25
OPPORTUNITIES IN TRANSMISSION CONTINUED…
Transmission Service Provider on PPP – Evacuation of Power from Buxar TPS
S.No Works Timeline
1
• Buxar TPS – Bihta 400 KV D/C
• Buxar TPS – Dumraon 220 KV D/C
• Buxar TPS – Mohania 220 KV D/C
• Buxar TPS – Dehri 220 KV D/C
• 2x500 MVA, 400/220 KV SS at Bihta
• Bihta 400/220 KV – Patna 400 KV D/C Line
• LILO of Ara – Khagaul 220 KV D/C
• Bihta 400/220 KV – Bihta 220/132 KV D/C Line
• 2x160 MVA 220/132 KV SS at Dumraon
• LILO 220 KV D/C at Dumraon
• Dumraon 220/132 KV SS
• Bihta 400/220 KV – Sipara 220/132 KV D/C Line
Planned; To be tendered
by 2015
26
OPPORTUNITIES IN DISTRIBUTION5.0
27
Upcoming
Projects -
INR 1155 Cr
OPPORTUNITIES IN DISTRIBUTION
Current Opportunities (R-APDRP Part B)
S.No Works Est. Value (INR
~Cr)
EMD
(INR ~Cr)
Completion
1
NIT No.: 177/PR/NBPDCL/2013
for 17 towns of Tirhut Electric Supply Area, Muzaffarpur
175.75 3.5 18 Months
2
NIT No.: 178/PR/NBPDCL/2013
for 2 towns of Mithila Electric Supply Area, Darbhanga
44.7 0.90 18 Months
3
NIT No. 179/PR/NBPDCL/2013
for 10 towns of Kosi Electric Supply Area, Saharsa
119 2.5 18 Months
4
NIT No.: 197/PR/SBPDCL/2013
for Package-A of PESU Area, Patna comprising of New Capital &
Kankarbagh Divisions
154 3.08 18 Months
5
NIT No.: 198/PR/SBPDCL/2013
for Package-B of PESU Area, Patna comprising of Danapur,
Patliputra, Dakbanglow & Gardanibag Divisions of PESU (West)
Circle
196.25 3.92 18 Months
6
NIT No. 199/PR/SBPDCL/2013
for Package-C of PESU Area, Patna comprising of Rajendra Nagar,
Bankipur, Gulzarbagh & Patna City Divisions of PESU (East) Circle
155.4 3.10 18 Months
7
NIT No.: 200/PR/SBPDCL/2013
for 13 towns of Magadh Electric Supply Area, Gaya
199. 3.98 18 Months
8
NIT No.: 201/PR/SBPDCL/2013
for 12 towns of Bhagalpur Electric Supply Area, Bhagalpur
156 3.12 18 Months
9
NIT No.: 202/PR/SBPDCL/2013
for 9 towns of Central Electric Supply Area, Patna
48 0.96 18 Months
Further details can be found on
www.eproc.bihar .gov.in
28
Upcoming
Projects -
INR 1087 Cr
OPPORTUNITIES IN DISTRIBUTION CONTINUED…
Current Opportunities (BRGF Phase I)
S.No Works Est. Value
(INR ~Cr)
EMD
(INR ~Cr)
Cost of
Tender Doc
1
NIT No.: 190/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Muzaffarpur, Vaishali, Sitamarhi,
Sheohar, East and West Champaran
117.5 2.36 1 Lac
2
NIT No.: 191/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Saranm, Siwan, Gopalganj
100 2.01 1 Lac
3
NIT No.: 192/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Samastipur, Begusarai
82 1.65 1 Lac
4
NIT No.: 193/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Darbhanga, Madhubani
110 2.20 1 Lac
5
NIT No.: 194/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Saharsa, Khagaria, Supaul, Madhepura,
Purnea, Araria, Katihar, Kishanganj
102 2.05 1 Lac
6
NIT No.: 196/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Gaya, Nawada, Jehanabad
92.7 1.85 1 Lac
Further details can be found on
www.eproc.bihar .gov.in
29
Upcoming
Projects -
INR 1087 Cr
OPPORTUNITIES IN DISTRIBUTION CONTINUED…
Current Opportunities (BRGF Phase I)
S.No Works Est. Value
(INR ~Cr)
EMD
(INR ~Cr)
Cost of
Tender Doc
7
NIT No.: 203/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Arwal, Aurangabad
78.7 1.57 1 Lac
8
NIT No.: 204/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Rohtas, Kaimur
82 1.64 1 Lac
9
NIT No.: 205/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Bhojpur, Buxar
53.4 1.07 1 Lac
10
NIT No.: 206/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Nalanda, Patna
104 2.09 1 Lac
11
NIT No.: 207/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Bhagalpur, Banka, Munger
99 1.98 1 Lac
12
NIT No.: 208/PR/NBPDCL/2013 – Supply and erection of 33/11
KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV
PSS, on Turnkey Basis – Jamui, Lakhisarai, Sheikpura
66.6 1.33 1 Lac
Further details can be found on
www.eproc.bihar .gov.in
30
OPPORTUNITIES IN DISTRIBUTION CONTINUED…
Other Upcoming Opportunities including State Plan
Sl.No Works
Est. Value
(INR ~Cr)
Approx.
Timeline
1
Non RAPDRP IT Works for Non RAPDRP Towns; Would include key
modules such as MBC, New Connection, MIS, MDAS, energy Audit, Web
Services, Asset and Maintenance Management (GIS not included)
35 1 Month
2
Feeder Segregation works for 37 districts in Bihar State (Under Rainbow
Revolution State Scheme)
- Upcoming
3 Civil work of DCRs (District Control Rooms) in 21 Districts 51.6 Upcoming
4 Civil work of MRT Building in 7 Districts 14.6 Upcoming
5 Redevelopment of Karbhigiya TPS as an Energy Park 28
Tendered
(Submission
Upcoming)
6
NIT No.: 157/PR/SBPDCL/2013 – Supply of 1741 numbers of 63 KVA,
11/0.433 KV Al Wound Distribution Transformers
13.9
Tendered
(Submission
Upcoming)
7 Collection Initiatives -
Tendered
(Submission
upcoming)
8 Prepaid Metering – Expression of interest - Upcoming
9 NIT of On-spot billing tender - Upcoming
10 NIT 144/PR/SBPDCL/2013ACSR Weasel Conductor (7727 KM) 16.24 Tendered
Further details can be found on
www.eproc.bihar .gov.in
31
AREAS TO COME UP FOR DISTRIBUTION FRANCHISEE (10 Twin Cities)
2
6
43
58
9
10
North Bihar
1. Bettiah – Motihari
2. Gopalganj - Siwan
3. Chapra – Hazipur
4. Darbhanga - Samastipur
5. Begusarai – Barauni
6. Purnia - Kathihar
South Bihar
7. Lakhisarai - Munger
8. Bihar Sharif - Rajgir
9. Arrah - Buxar
10. Sasaram - Dehri
32
FRANCHISEE AREA CHARACTERISTICS
Town District No. of Consumers Revenue Assessment AT&C losses
Motihari East Champaran 25363 8.99 55%-60%
Bettiah West Champaran 66661 35.53 55%-60%
Gopalganj Gopalganj 7274 10.51 55%-60%
Siwan Siwan 83054 30.56 55%-60%
Chapra Saran 47698 16.71 55%-60%
Hazipur Vaishali 35288 33.06 55%-60%
Darbhanga Darbhanga 24613 4.78 55%-60%
Samastipur Samastipur 12226 4.46 55%-60%
Begusarai Begusarai 39260 7.41 55%-60%
Barauni Begusarai 38425 4.08 55%-60%
Purniya Purnia 101678 93.38 55%-60%
Katihar Katihar 62236 46.33 55%-60%
Lakhisarai Lakhisarai 27601 18.27 65%
Munger Munger 33263 42.93 38%
Biharsharif Nalanda 55948 35.39 78%
Rajgir Nalanda 10216 12.13 76%
Aarah Bhojpur 84276 31.61 53%
Buxor Buxar 33433 18.92 60%
Sasaram Rohtas 50000-60000 15.87 62%
Dehri Rohtas 50000-60000 34.99 41%
33
SUMMARY OF KEY INITIATIVES IN T&D
Initiative Sector Status
Re-conductoring and second stringing of Transmission Lines Transmission Ongoing
Capacity augmentation by increasing transformers T&D Ongoing
New Lines, SS and Grids T&D Ongoing
R&M of SS Transmission Ongoing
Apex Metering for Bulk Power Transfer Pts Transmission Upcoming
PPP in Transmission (Transmission Service Provider) Transmission Upcoming
Regularization of Tariff Calendar and Petition T&D Upcoming
Increased Metering Activities Distribution Ongoing
Prepaid Metering – Supply, Installation and Maintenance of Single and
Three Phase Static Energy Meters
Distribution Upcoming
Modern SCADA (Patna City) Distribution Ongoing
Collection Initiatives such as POS collection, Mobile Vans, Spot Billing,
Increased Centers, M-Commerce, Internet Payment Mechanism etc
Distribution Ongoing/Upcoming
Non R-APDRP IT Works Distribution Upcoming
Feeder Segregation Programme (Pilot for 1 district underway, 37 other
districts planned)
Distribution Ongoing/Upcoming
PPP in Distribution (Franchisee Model) Distribution Ongoing/Upcoming
Heightened Response Times for O&M T&D Ongoing
34
POTENTIAL CHALLENGES6.0
35
POTENTIAL CHALLENGES
Payment Related Tendering Related
• Issuance of operational
guidelines for tendering (may
be time-bound)
• Analysis of participants
ongoing projects – addition to
QR
• Standardized schedule of
rates
Execution Related
• Appointment of PMCs for
project monitoring and
timely execution
• Formation of execution cell by
Utilities
• Clear guidelines for handing
over of works to the utility
….And Potential Solutions
• All projects are fund tied
ensuring timely payments
• Promises to pay within a
months time
• Monitoring by MDs
personally
• Re-engineering of invoice
approval and payment
processing workflow
36
END OF DECK
Contact Details of Officials
Name Designation Number eMail
Sri Sanjay Kumar Singh,
I.A.S
MD, BSPTCL
(0612)-2504442 singhsanjaypat@gmail.com
Sri Sanjay Kumar
Agarwal, I.A.S
MD, NBPDCL
(0612)-2504044 md.nbpdcl@gmail.com
Smt. Palka Sahani, I.A.S MD, SBPDCL (0612)-2504045 md.sbpdcl@gmail.com
Sri N.K.P. Sinha CE(RE), NBPDCL 9431247281 Cere.bseb@gmail.com
Sri S.K.P. Singh CE(Comm.), SBPDCL 9470001748 Cecom.sbpdcl@gmail.com
Sri Y.K. Thakur CE, (trans) BSPTCL 9470001760 Ce.trans664@gmail.com
37
END OF DECK
Division Ravi Kathpal
Associate Director
Energy Division
Vijay Dhonde
Lead Consultant
Energy Division
Sudhanshu Malhotra
Principal Consultant
Energy Division
Address Feedback Infra Private Limited
602, 6th Floor, Natraj, Western
Express Highway, Andheri
(East),
Mumbai 400 069.
Feedback Infra Private Limited
602, 6th Floor, Natraj, Western
Express Highway, Andheri
(East),
Mumbai 400 069.
Feedback Infra Private Limited
15th Floor, Tower 9B, DLF Cyber
City, Gurgaon – 122002
Haryana (INDIA)
Phone +91 22 67718816
+91 9820019591
+91 22 67718828
+91 983343447
+91 124 4169136
+91 9899382737
Fax +91 22 66713639 +91 22 66713639 +91 124 4169155
Email Ravi.kathpal@feedbackinfra.com Vijay.dhonde@feedbackinfra.com Sudhanshu.malhotra@feedbackinfr
a.com

Mais conteúdo relacionado

Mais procurados

Union budget-2010-11
Union budget-2010-11Union budget-2010-11
Union budget-2010-11
Bimal Syal
 

Mais procurados (19)

Union Budget..........Ppt..Final
Union Budget..........Ppt..FinalUnion Budget..........Ppt..Final
Union Budget..........Ppt..Final
 
Union Budget 2022-23 : Ministry of Road Transport and Highway
Union Budget 2022-23 : Ministry of Road Transport and HighwayUnion Budget 2022-23 : Ministry of Road Transport and Highway
Union Budget 2022-23 : Ministry of Road Transport and Highway
 
Union budget-2010-11
Union budget-2010-11Union budget-2010-11
Union budget-2010-11
 
Budget 2022
Budget  2022 Budget  2022
Budget 2022
 
Key features of budget 2011
Key features of budget 2011Key features of budget 2011
Key features of budget 2011
 
Comparison of Union Budget 2014-15, 15-16, 16-17, 17-18
Comparison of Union Budget 2014-15, 15-16, 16-17, 17-18Comparison of Union Budget 2014-15, 15-16, 16-17, 17-18
Comparison of Union Budget 2014-15, 15-16, 16-17, 17-18
 
DHPA budget 2022 final
DHPA budget 2022 finalDHPA budget 2022 final
DHPA budget 2022 final
 
Union budget
Union budgetUnion budget
Union budget
 
Budget proposal for rural india
Budget proposal for rural indiaBudget proposal for rural india
Budget proposal for rural india
 
India's Budget Highlights 2022- 23
   India's Budget Highlights 2022- 23   India's Budget Highlights 2022- 23
India's Budget Highlights 2022- 23
 
Exclusive report on ‪‎budget 2015‬ 16 by epic research private limited
Exclusive report on ‪‎budget 2015‬  16 by epic research private limitedExclusive report on ‪‎budget 2015‬  16 by epic research private limited
Exclusive report on ‪‎budget 2015‬ 16 by epic research private limited
 
Deloitte Survey Results: Understanding the Effect of the Union Budget 2021 on...
Deloitte Survey Results: Understanding the Effect of the Union Budget 2021 on...Deloitte Survey Results: Understanding the Effect of the Union Budget 2021 on...
Deloitte Survey Results: Understanding the Effect of the Union Budget 2021 on...
 
UNION Budget 2017-2018
UNION Budget 2017-2018UNION Budget 2017-2018
UNION Budget 2017-2018
 
Uttarakhand 13mar 2008
Uttarakhand 13mar 2008Uttarakhand 13mar 2008
Uttarakhand 13mar 2008
 
Analysis of the Union Budget 2018-19
Analysis of the Union Budget 2018-19Analysis of the Union Budget 2018-19
Analysis of the Union Budget 2018-19
 
Key features of budget 2011 2012
Key features of budget 2011 2012Key features of budget 2011 2012
Key features of budget 2011 2012
 
MTBiz July 2017
MTBiz July 2017 MTBiz July 2017
MTBiz July 2017
 
Fainal budget 2011 ppt
Fainal budget 2011 pptFainal budget 2011 ppt
Fainal budget 2011 ppt
 
New guidelines for the transportation industry
New guidelines for the transportation industryNew guidelines for the transportation industry
New guidelines for the transportation industry
 

Destaque

132kv Substation
132kv Substation132kv Substation
132kv Substation
guestecdd58
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
Prateek Agarwal
 
1phase induction motors
1phase induction motors1phase induction motors
1phase induction motors
Vijay Raskar
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
Ishank Ranjan
 

Destaque (20)

132kv Substation
132kv Substation132kv Substation
132kv Substation
 
33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)33/11 kV substation (u.p.p.c.l.)
33/11 kV substation (u.p.p.c.l.)
 
CIGRE Belgium presentation on Actively Managing Distribution Connected Genera...
CIGRE Belgium presentation on Actively Managing Distribution Connected Genera...CIGRE Belgium presentation on Actively Managing Distribution Connected Genera...
CIGRE Belgium presentation on Actively Managing Distribution Connected Genera...
 
Practical Power Distribution
Practical Power DistributionPractical Power Distribution
Practical Power Distribution
 
Substation Maintenance
Substation MaintenanceSubstation Maintenance
Substation Maintenance
 
Planning for Substation Maintenance and Reliability
Planning for Substation Maintenance and ReliabilityPlanning for Substation Maintenance and Reliability
Planning for Substation Maintenance and Reliability
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Fibre optics cable
Fibre optics cableFibre optics cable
Fibre optics cable
 
Synchronous motors
Synchronous motorsSynchronous motors
Synchronous motors
 
Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1Presentation on power distribution, operation and maintenance in comilla pbs 1
Presentation on power distribution, operation and maintenance in comilla pbs 1
 
Nuclear energy
Nuclear energyNuclear energy
Nuclear energy
 
NUCLEAR WASTE PRESENTATION
NUCLEAR WASTE PRESENTATIONNUCLEAR WASTE PRESENTATION
NUCLEAR WASTE PRESENTATION
 
1phase induction motors
1phase induction motors1phase induction motors
1phase induction motors
 
Synchronous machines
Synchronous machinesSynchronous machines
Synchronous machines
 
Synchronous motor
Synchronous motorSynchronous motor
Synchronous motor
 
Presentation on Green Energy
Presentation on Green EnergyPresentation on Green Energy
Presentation on Green Energy
 
Rural electrification
Rural electrificationRural electrification
Rural electrification
 
Green Power Presentation
Green Power PresentationGreen Power Presentation
Green Power Presentation
 
Motor starter
Motor starterMotor starter
Motor starter
 
PPt on 220 kV substation
PPt on 220 kV substationPPt on 220 kV substation
PPt on 220 kV substation
 

Semelhante a Destination Bihar : Opportunities in Bihar State’s Transmission and Distribution Sector Presentation

Market Research Report : Electric vehicle market in india 2014 - Sample
Market Research Report : Electric vehicle market in india 2014 - SampleMarket Research Report : Electric vehicle market in india 2014 - Sample
Market Research Report : Electric vehicle market in india 2014 - Sample
Netscribes, Inc.
 
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.pptSPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
ssuser8f8879
 
Nepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptxNepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptx
ssuserfbc60b
 
Re Pref Offer Presentation To Press 22 Feb04
Re Pref Offer Presentation To Press 22 Feb04Re Pref Offer Presentation To Press 22 Feb04
Re Pref Offer Presentation To Press 22 Feb04
neddy16
 

Semelhante a Destination Bihar : Opportunities in Bihar State’s Transmission and Distribution Sector Presentation (20)

Electricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forwardElectricity Act 2003, Amendments and way forward
Electricity Act 2003, Amendments and way forward
 
Market Research Report : Electric vehicle market in india 2014 - Sample
Market Research Report : Electric vehicle market in india 2014 - SampleMarket Research Report : Electric vehicle market in india 2014 - Sample
Market Research Report : Electric vehicle market in india 2014 - Sample
 
Beacon.march2014
Beacon.march2014Beacon.march2014
Beacon.march2014
 
Budget 2015
Budget 2015Budget 2015
Budget 2015
 
Final presentation on power sector t&d
Final presentation on power sector  t&dFinal presentation on power sector  t&d
Final presentation on power sector t&d
 
BHEL FINAL PROJECT.docx
BHEL FINAL PROJECT.docxBHEL FINAL PROJECT.docx
BHEL FINAL PROJECT.docx
 
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distributionDay-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
Day-3, Mr. Ramesh Narayan BYPL Ippai issues in distribution
 
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.pptSPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
SPEAKER 5- Financial Management Of SOEs in BRICS member countries.ppt
 
Nepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptxNepal_Presentation_Final.pptx
Nepal_Presentation_Final.pptx
 
India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015India - Renewables - eligible overseas capital markets candidate 2015
India - Renewables - eligible overseas capital markets candidate 2015
 
XYZ solar power Global IPO
XYZ solar power   Global IPOXYZ solar power   Global IPO
XYZ solar power Global IPO
 
India Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets CandidateIndia Renewables-Eligible Overseas Capital Markets Candidate
India Renewables-Eligible Overseas Capital Markets Candidate
 
A Review of Restructured Power Development and Reform Programme in India
A Review of Restructured Power Development and Reform Programme in IndiaA Review of Restructured Power Development and Reform Programme in India
A Review of Restructured Power Development and Reform Programme in India
 
SECOND high level commitie report ON INFRASTRUCTURE PROJECT
SECOND high level commitie report ON INFRASTRUCTURE PROJECTSECOND high level commitie report ON INFRASTRUCTURE PROJECT
SECOND high level commitie report ON INFRASTRUCTURE PROJECT
 
Equity Market Reactions based on Company’s Financial Strategies
Equity Market Reactions based on Company’s Financial StrategiesEquity Market Reactions based on Company’s Financial Strategies
Equity Market Reactions based on Company’s Financial Strategies
 
EV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPCEV Charging - Business Opportunity for NTPC
EV Charging - Business Opportunity for NTPC
 
Energy crisis in India
Energy crisis in India Energy crisis in India
Energy crisis in India
 
Energy Infrastructure in India : A Reference Book
Energy Infrastructure in India : A Reference BookEnergy Infrastructure in India : A Reference Book
Energy Infrastructure in India : A Reference Book
 
RENEWABLE POLICY
RENEWABLE POLICYRENEWABLE POLICY
RENEWABLE POLICY
 
Re Pref Offer Presentation To Press 22 Feb04
Re Pref Offer Presentation To Press 22 Feb04Re Pref Offer Presentation To Press 22 Feb04
Re Pref Offer Presentation To Press 22 Feb04
 

Mais de pManifold

pManifold Utility Customer Research Mobility Engagement Case Studies
pManifold Utility Customer Research Mobility Engagement Case StudiespManifold Utility Customer Research Mobility Engagement Case Studies
pManifold Utility Customer Research Mobility Engagement Case Studies
pManifold
 
pManifold IUKAN Summary
pManifold IUKAN SummarypManifold IUKAN Summary
pManifold IUKAN Summary
pManifold
 
pManifold Utility Practice
pManifold Utility Practice pManifold Utility Practice
pManifold Utility Practice
pManifold
 
IUKAN Conference 2013 - Event Directory
IUKAN Conference 2013 - Event DirectoryIUKAN Conference 2013 - Event Directory
IUKAN Conference 2013 - Event Directory
pManifold
 
Casestudy DF Customer Monitoring
Casestudy DF Customer MonitoringCasestudy DF Customer Monitoring
Casestudy DF Customer Monitoring
pManifold
 
EUCOPS Capability
EUCOPS CapabilityEUCOPS Capability
EUCOPS Capability
pManifold
 
Pre bid meeting Shil-Mumbra-Kalwa-20120621
Pre bid meeting Shil-Mumbra-Kalwa-20120621Pre bid meeting Shil-Mumbra-Kalwa-20120621
Pre bid meeting Shil-Mumbra-Kalwa-20120621
pManifold
 
pManifold Introduction to Research Practice
pManifold Introduction to Research PracticepManifold Introduction to Research Practice
pManifold Introduction to Research Practice
pManifold
 
pManifold Introduction to Consulting Practice
pManifold Introduction to Consulting PracticepManifold Introduction to Consulting Practice
pManifold Introduction to Consulting Practice
pManifold
 
pManifold_Introduction_Overall_20120508
pManifold_Introduction_Overall_20120508pManifold_Introduction_Overall_20120508
pManifold_Introduction_Overall_20120508
pManifold
 

Mais de pManifold (20)

pManifold Introduction Overall 2016
 pManifold Introduction Overall 2016 pManifold Introduction Overall 2016
pManifold Introduction Overall 2016
 
pManifold Utility Practice 2015
pManifold Utility Practice 2015pManifold Utility Practice 2015
pManifold Utility Practice 2015
 
pManifold Casestudy Customer research Cops Utility Waste
pManifold Casestudy Customer research Cops Utility WastepManifold Casestudy Customer research Cops Utility Waste
pManifold Casestudy Customer research Cops Utility Waste
 
pManifold fy2014-15_q1_q2_brief_update
pManifold fy2014-15_q1_q2_brief_updatepManifold fy2014-15_q1_q2_brief_update
pManifold fy2014-15_q1_q2_brief_update
 
P manifold customer_audit_feedback_monitoring_services
P manifold customer_audit_feedback_monitoring_servicesP manifold customer_audit_feedback_monitoring_services
P manifold customer_audit_feedback_monitoring_services
 
pManifold Utility Customer Research Mobility Engagement Case Studies
pManifold Utility Customer Research Mobility Engagement Case StudiespManifold Utility Customer Research Mobility Engagement Case Studies
pManifold Utility Customer Research Mobility Engagement Case Studies
 
IUKAN 2014
IUKAN 2014IUKAN 2014
IUKAN 2014
 
pManifold IUKAN Summary
pManifold IUKAN SummarypManifold IUKAN Summary
pManifold IUKAN Summary
 
pManifold Turnkey Managed Services - Customer Experience and Revenue Assurance
pManifold Turnkey Managed Services - Customer Experience and Revenue AssurancepManifold Turnkey Managed Services - Customer Experience and Revenue Assurance
pManifold Turnkey Managed Services - Customer Experience and Revenue Assurance
 
Introduction to pManifold's Health Practice
Introduction to pManifold's Health PracticeIntroduction to pManifold's Health Practice
Introduction to pManifold's Health Practice
 
pManifold Utility_Customer_Engagement_AnnualPackage
pManifold Utility_Customer_Engagement_AnnualPackagepManifold Utility_Customer_Engagement_AnnualPackage
pManifold Utility_Customer_Engagement_AnnualPackage
 
pManifold Utility Practice
pManifold Utility Practice pManifold Utility Practice
pManifold Utility Practice
 
IUKAN Conference 2013 - Event Directory
IUKAN Conference 2013 - Event DirectoryIUKAN Conference 2013 - Event Directory
IUKAN Conference 2013 - Event Directory
 
Casestudy DF Customer Monitoring
Casestudy DF Customer MonitoringCasestudy DF Customer Monitoring
Casestudy DF Customer Monitoring
 
EUCOPS Capability
EUCOPS CapabilityEUCOPS Capability
EUCOPS Capability
 
Pre bid meeting Shil-Mumbra-Kalwa-20120621
Pre bid meeting Shil-Mumbra-Kalwa-20120621Pre bid meeting Shil-Mumbra-Kalwa-20120621
Pre bid meeting Shil-Mumbra-Kalwa-20120621
 
pManifold Introduction to Research Practice
pManifold Introduction to Research PracticepManifold Introduction to Research Practice
pManifold Introduction to Research Practice
 
pManifold Introduction to Consulting Practice
pManifold Introduction to Consulting PracticepManifold Introduction to Consulting Practice
pManifold Introduction to Consulting Practice
 
pManifold_Introduction_Overall_20120508
pManifold_Introduction_Overall_20120508pManifold_Introduction_Overall_20120508
pManifold_Introduction_Overall_20120508
 
Webinar: Market, Customer and Investment Intelligence on Ujjain for Distribut...
Webinar: Market, Customer and Investment Intelligence on Ujjain for Distribut...Webinar: Market, Customer and Investment Intelligence on Ujjain for Distribut...
Webinar: Market, Customer and Investment Intelligence on Ujjain for Distribut...
 

Último

Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts PodanurTop Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
dharasingh5698
 
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
MollyBrown86
 
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
mriyagarg453
 
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
nirzagarg
 

Último (20)

The Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results PresentationThe Leonardo 1Q 2024 Results Presentation
The Leonardo 1Q 2024 Results Presentation
 
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts PodanurTop Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
Top Rated Call Girls In Podanur 📱 {7001035870} VIP Escorts Podanur
 
Teekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings PresentationTeekay Tankers Q1-24 Earnings Presentation
Teekay Tankers Q1-24 Earnings Presentation
 
Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024Osisko Development - Investor Presentation - May 2024
Osisko Development - Investor Presentation - May 2024
 
High Profile Call Girls in Pune (Adult Only) 8005736733 Escort Service 24x7 ...
High Profile Call Girls in Pune  (Adult Only) 8005736733 Escort Service 24x7 ...High Profile Call Girls in Pune  (Adult Only) 8005736733 Escort Service 24x7 ...
High Profile Call Girls in Pune (Adult Only) 8005736733 Escort Service 24x7 ...
 
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
Indapur - Virgin Call Girls Pune | Whatsapp No 8005736733 VIP Escorts Service...
 
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Panjabi Bagh, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Editing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxxEditing progress 20th march.docxxxxxxxxx
Editing progress 20th march.docxxxxxxxxx
 
Best investment platform in india-Falcon Invoice Discounting
Best investment platform in india-Falcon Invoice DiscountingBest investment platform in india-Falcon Invoice Discounting
Best investment platform in india-Falcon Invoice Discounting
 
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
Ambala Escorts Service ☎️ 6378878445 ( Sakshi Sinha ) High Profile Call Girls...
 
Vijayawada ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready F...
Vijayawada ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready F...Vijayawada ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready F...
Vijayawada ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready F...
 
Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024Teck Supplemental Information, May 2, 2024
Teck Supplemental Information, May 2, 2024
 
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
VVIP Pune Call Girls Parvati Gaon WhatSapp Number 8005736733 With Elite Staff...
 
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
Dubai Call Girls O525547&19 Calls Girls In Dubai (L0w+Charger)
 
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
VVIP Pune Call Girls Sopan Baug WhatSapp Number 8005736733 With Elite Staff A...
 
AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024AMG Quarterly Investor Presentation May 2024
AMG Quarterly Investor Presentation May 2024
 
Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024Collective Mining | Corporate Presentation - May 2024
Collective Mining | Corporate Presentation - May 2024
 
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
VVIP Pune Call Girls Handewadi WhatSapp Number 8005736733 With Elite Staff An...
 
Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024Financial Results for the Fiscal Year Ended March 2024
Financial Results for the Fiscal Year Ended March 2024
 
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
💚😋 Saharanpur Escort Service Call Girls, 9352852248 ₹5000 To 25K With AC💚😋
 

Destination Bihar : Opportunities in Bihar State’s Transmission and Distribution Sector Presentation

  • 1. CONFIDENTIAL AND PROPRIETARY DESTINATION BIHAR: OPPORTUNITIES IN BIHAR STATE’S TRANSMISSION AND DISTRIBUTION SECTOR
  • 2. 2 FROM A GLORIOUS PAST TO A GLORIOUS FUTURE Ancient Bihar was a centre for: Power – Maurya dynasty first and one of the greatest Learning - Nalanda and Vikramshila; one of the oldest and truly international universities of the world Culture and religion - Buddhism started from Bihar The state since the 70’s lagged behind other India states in economic terms However, recently it is bouncing back with Improved governance – better law and order situation Greater emphasis on education Increased investment in Infrastructure Better health care facilities
  • 3. 3 A shining example of development is the Roads Sector. Bihar State Highway Project Phase I– 9 Packages, 820 KM of State Highways under implementation Bihar State Highway Project Phase II– 4 Packages, SH 78 (100 KM) under implementation Bihar State Highway Project Phase III– 3 Packages 7 PPP Projects (NH) identified and under various stages of execution 4 Laning of Corridors For the period 2011–2012, Bihar was also India's fastest growing State, with a growth rate of 13.1% for the year 2011–12, which had followed a growth rate of 14.8% for the previous year. Bihar has managed to record 11.95% annual growth rate, the highest among all the states, during the 11th Plan period
  • 4. 4 DESTINATION BIHAR: OPPORTUNITIES IN BIHAR STATE’S TRANSMISSION AND DISTRIBUTION SECTOR The Bihar State Power Transmission and Distribution Sectors including Rural Electrification are set to receive, tender and execute projects to the tune of INR ~28,250 Cr These projects are to be tendered and executed within the 12th Plan (now 2013-14 to 2016-17) The projects are at various stages – planned, sanctioned, tendered or awarded The projects funded under schemes such as the BRGF, RAPDRP, RGGVY , ADB and the State Plan The prime objective of the conference is to create an awareness, amongst participants, of the substantial opportunity present in the State as well as the support provided by the State to private players participating in the Sector S.No Sector Amount (in INR Cr) 1 Transmission (including Schemes and State Plan) 8,114 2 Distribution (including Schemes and State Plan) 20,137 (includes RGGVY and RAPDRP) Total 28,251
  • 5. 5 AGENDA 1.0 SECTOR AND UTILITY PROFILE CURRENT SCHEMES OPPORTUNITIES IN TRANSMISSION POTENTIAL CHALLENGES INDEPENDENT MARKET VIEW OF THE UTILITY2.0 3.0 4.0 6.0 OPPORTUNITIES IN DISTRIBUTION5.0
  • 6. 6 1.0 SECTOR AND UTILITY PROFILE
  • 7. 7 SECTOR AND UTILITY (TRANSCO) PROFILE Ownership Installed Capacity in MW Grand TotalCoal Hydro RES* State 210 0 66.3 276.3 Private 0 0 29.5 29.5 Central 1414.7 129.43 0 1544.1 Sub-total 1624.7 129.43 95.8 1849.9 Status of Transmission Infrastructure S. No Voltage No. of Substation Length (Kms) Transmiss- ion (MVA) 1 400 kV - 75.00 - 2 220 kV 9 1147 2450 3 132 kV 76 5178 4588 85 6400 Peak Demand & Peak Demand Met in (MW) for Bihar (Source: CEA Annual reports) Transmission circles include Patna, Bihar Sharif, Gaya, Dehri on Sone, Muzaffarpur, Purnea and Bhagalpur 1509 1882 2192 2642 3194 3873 4472 5602 0 1000 2000 3000 4000 5000 6000 2009 2010 2011 2012 2013 2014 2015 2016 inMW Peak Demand
  • 8. 8 UTILITY PROFILE (DISCOMS) Bihar State Power Holding Company Ltd. Bihar State Power Generation Company Bihar State Power Transmission Company North Bihar Power Distribution Company South Bihar Power Distribution Company Bihar State Electricity Board Unbundled in 2012 as per EA ‘03 Distribution Company Estimated Population * No. of Districts Electricity Consumers (approx) Area Circles North Bihar Power Distribution Co Ltd 6.5 Cr 21 22 Lacs 52,925 Sq Km (53.46% of total) 7 Electric Supply Circles: Saharsa, Purnea, Muzaffarpur, Motihari, Chapra, Darbhanga, Samastipur South Bihar Power Distribution Co Ltd 3.8 Cr 17 18 Lacs 46,070 Sq Km (46.54% of total) 9 Electric Supply Circles: Patna, Bhojpur (Ara), Nalanda (Biharsharif), PESU (East), PESU (West), Gaya, Rohtas (Sasaram), Bhagalpur, Munger *As per Census data 2011
  • 9. 9 UTILITY PROFILE (DISCOMS) CONTINUED…. - 500,000 1,000,000 1,500,000 2,000,000 2,500,000 3,000,000 3,500,000 4,000,000 4,500,000 2005-06 2006-07 2007-08 2008-09 2009-10 2010-11 2011-12 Revenue – Cost Gap (INR/ unit) Growth in Consumer Numbers (Source: erstwhile BERC Tariff) (Source: erstwhile BSEB Annual reports) Demand of the state growing at a CAGR of 8 % Industrial and Domestic consumers contribute to about 50% of the total sales The gap between demand and supply was highest during 2009-10 - 32.9 %(720 MW) The gap reduced to 15.5% in the year 2011-12 owing to the short and medium term purchases by erstwhile BSEB; energy deficit in FY 2012-13 – 16.7% Steady rise (Rs 2.25 per unit at 11.1 % CAGR) in Average Billing Rate during FY 2005-06 to FY 2011-12 Power purchase cost increased twice as fast as the increase in revenue; however, from the last two years, revenue has been increasing at a CAGR of 18% 2.06 2.26 2.50 2.57 3.273.27 3.26 3.26 3.39 4.09 0.00 1.00 2.00 3.00 4.00 5.00 2008-09 2009-10 2010-11 2011-12 2012-13 Cost Revenue
  • 10. 10 POLICY IMPLEMENTATION DASHBOARD – CEA TARGETS Policy Description Status Rural Electrification Policy 56% of the villages should be electrified by 2012 At least one 33/11 kV sub-station per block and at least one distribution transformer per village National Electricity Policy, 2005 Introduction of Open Access in Distribution - Open Access availability to 1MW+ consumers Full-fledged SCADA system for distribution utilities Energy Audits for segregating techno-commercial losses Provision of SCADA in Transmission system with upgrades Determination of Open Access Charges in Transmission Electricity Act, 2003 Unbundling of State Electricity Boards and constitution of SERC Setting up of special courts, assessing officer and appellate authority Preparation of annual statement of accounts in consultation with C&AG Supply of electricity by Distribution Licensee National Tariff Policy, 2006 Level of consumer tariff should be within (+) & (-) 20% of cost of supply Tariff for agricultural use should be subsidized below cost of supply Introduction of two part tariff and time differentiated tariff for large consumers (1 MW & above) Development of tariff framework (Point of Connection mechanism) by CERC after taking into consideration advice of CEA Determination of technical loss benchmarks in transmission after considering advice of CEA Development of Key performance indicators (KPI) for Transmission Completed Ongoing Not yet startedSource: CEA
  • 11. 11 INDEPENDENT MARKET VIEW OF THE UTILITY2.0
  • 12. 12 INDEPENDENT MARKET VIEW ON DISCOMS Observations from ‘First Annual Integrated Ratings of SDU as per Framework Approved by MoP’ Report by ICRA Ltd and Credit Analysis and Research Ltd “B” Rating 1 BSPHCL 2 Northern Power Distribution Company of AP Ltd 3 Assam Power Distribution Company Ltd 4 Chamundeshwari Electricity Supply Corporation Ltd 5 Uttar Haryana Bijli Vitran Nigam Ltd 6 Tamil Nadu Generation and Distribution Corporation Ltd 7 Dakshin Haryana Bijli Vitran Nigam Ltd 8 MP Pashchim Kshetra Vidyut Vitaran Company Ltd 9 MP Poorv Kshetra Vidyut Vitaran Company Ltd 10 MP Madhya Kshetra Vidyut Vitran Company Ltd Rating Definition – Below Average Operational and Financial Capability
  • 13. 13 INDEPENDENT MARKET VIEW ON DISCOMS CONTINUED…. …And Impact on Private Participants S. No. Key Strengths Potential Impact 1 Satisfactory progress in terms of reforms and restructuring of the sector, which includes unbundling on functional lines and corporatization Creation of favorable environment for all participants 2 Timely receipt of subsidy from the State Government Funding available for the sector has a direct impact on upcoming projects and payment cycle 3 Effective functioning of the Bihar Electricity Regulatory Commission Timely execution of decisions pertaining to the developer (DF, IPTC) space 4 Regulatory clarity in place, on the back of release of multi-year tariff order for the control period FY 2014 to FY 2016 in November 2012 and timely filing of tariff petition/orders Creation of favorable environment for all participants 5 Timely availability of audited financial accounts for FY2012 Would assist private participants in their decision making process 6 Implementation/steady progress in key reform measures such as special courts for anti-theft measures, unbundling of utilities, setting up of consumer grievance forums, etc Favorable environment for all participants especially developers 7 Fuel & Power Purchase Cost Adjustment (FPPCA) framework is operational, allowing the increase in such uncontrollable‟ cost items to be recovered from consumers on monthly basis Favorable environment for all participants especially developers
  • 14. 14 INDEPENDENT MARKET VIEW ON DISCOMS CONTINUED…. …And Impact on Private Participants S. No. Key Concerns Potential Impact/Counter 1 Continuing weak financial position, with coverage of costs through revenues at less than 80% Potential payment issues – to be countered by incoming funding 2 High and increasing AT&C losses Opportunity for all potential private participants including developers, contractors, component manufacturers and service provider; Initiatives in metering and collection efficiency already underway 3 Huge unmetered consumption and deterioration in collection efficiency Opportunity for all potential private participants including developers, contractors, component manufacturers and service provider; Initiatives in metering and collection efficiency already underway 4 Funding of the entire asset base has been done through debt thus leading to an unfavorable capital structure. Further, accumulated losses from the past have led to a negative net worth Participation in Financial Restructuring Plan High amount of receivables, although the same has shown a declining trend over the years May have an indirect impact on payment– to be countered by incoming funding In order to improve billing and collection the utility has proposed and is implementing numerous initiatives, such as: spot billing , drop boxes and alternative points of collections, collection through mobile vans and banking, internet banking facility, M-commerce initiatives, collection through Gramin banks etc.
  • 16. 16 CURRENT SCHEMES DASHBOARD (with Approx INR values) Sl. NO. Scheme Description Allocation for State Power Sector Timeline of Scheme for State 1 RGGVY (Rajiv Gandhi Grameen Vidyutikaran Yojana) Scheme for creating rural electricity infrastructure and completing rural household electrification from 33kV and below level 11850 Cr Partial Electrification - 10th, 11th Full Electrification - 12th Plan 2 R-APDRP (Restructured – Accelerated Power Development and Reforms Programme) Part B Renovation, modernization and strengthening of network of 11 kV level and below 1155 Cr Ongoing; scheduled to culminate in 12th Plan 3 BRGF (Backward Regions Grant Fund ) Phase I and II The fund will provide financial resources for supplementing and converging existing developmental inflows into identified districts ~9000 Cr 12th Plan 4 Multilateral funding (ADB, WB etc…) Funding in the State is happening through organizations such as Asian Development Bank 375 Cr (under implementation) another ~700 Cr planned Ongoing 5 State Plan State funded projects and procurement. The plan is made annually. Transmission - ~300 Cr Distribution – 300-400 Cr Annual
  • 17. 17 BACKWARDS REGIONS GRANT FUND (Values in INR Cr) BRGF Total Corpus for Bihar - ~ 12000 Cr Corpus for Bihar Power Sector - ~9000 Cr BRGF Distribution Sector – ~5932 Cr BRGF Transmission Sector – ~2194 Cr Phase I – ~2484 Cr Phase II – ~3448 Cr Phase II Ext. – ~472 Cr Phase III Ext. – ~1721 Cr Strengthening of Distribution System and Removal of Constraints; Phase I funds are sanctioned and tendered Strengthening of Sub-Transmission and Transmission System; Phase II ext. funds are sanctioned and under implementation Apart from the above - Full Scale electrification of villages of 11 districts sanctioned by MoP/REC – INR ~837 Cr State’s Commitment to the Sector Addl. INR 5000+ Cr to be executed in 12th Plan
  • 18. 18 RGGGVY – PROPOSED and SANCTIONED DPRs (To be implemented in 12th Plan) S.No District Amount (INR ~Cr) Current Status 1 Araria 243 Sanctioned 2 Purnea 308 Sanctioned 3 Siwan 320 Sanctioned 4 Kishanganj 273.29 Sanctioned and Tendered (submission upcoming) 5 Saran 302 Proposed 6 Gopalganj 277 Proposed 7 Samastipur 531 Proposed 8 Muzaffarpur 563 Proposed 9 Katihar 477 Proposed 10 Saharsa 249 Proposed 11 Darbhanga 398 Proposed 12 Supaul 340 Proposed 13 East Champaran 474 Proposed 14 Madhubani 583 Proposed 15 Begusarai 359 Proposed 16 Khagaria 170 Proposed 17 Madhepura 252 Proposed 18 Sitamarhi 309 Proposed 19 Sheohar 71 Proposed 20 West Champaran 451 Proposed 21 Vaishali 621 Proposed Total ~7,571 Upcoming Projects - INR 11,000 to 12,000 Cr!
  • 19. 19 RGGGVY – PROPOSED and SANCTIONED DPRs (To be implemented in 12th Plan) S.No District Amount (INR ~Cr) Current Status 1 Banka 199 Awarded 2 Gaya 498 Awarded 3 Rohtas 218 Awarded 4 Patna 420 Awarded 5 Lakhisarai 153 Proposed 6 Aurangabad 358 Proposed 7 Bhabhua 338 Proposed 8 Buxar 254 Proposed 9 Bhagalpur 216 Proposed 10 Bhojpur 169 Sanctioned 11 Nalanda 456 Sanctioned 12 Nawada 241 Sanctioned 13 Munger 154 Proposed 14 Jamui 227 Proposed 15 Arwal 111 Proposed 16 Jehanabad 175 Proposed 17 Sheikhpura 89 Proposed 4,276 Upcoming Projects - INR 11,000 to 12,000 Cr!
  • 20. 20 R-APDRP PART B R-APDRP Part B Approved - ~ ~1155 Cr North Bihar ~287 Cr South Bihar – ~868 Cr Covers 3 Supply Areas, 7 Circles and 29 Towns Covers 4 Supply Areas, 9 Circles and 35 Towns Top 5 Towns in Terms of Value S.No District Approved Value (INR Cr) 1 Patna 505 2 Gaya 65.4 3 Bhagalpur 55.7 4 Munger 23.5 5 Sasaram 20.4 Top 5 Towns in Terms of Value S.No District Approved Value (INR Cr) 1 Muzaffarpur 61.7 2 Darbhanga 29.5 3 Purnea 27.8 4 Hajipur 27.3 5 Chapra 18.9
  • 21. 21 MULTI-LATERAL FUNDING Ongoing ADB Sponsored Distribution Works (86% ADB, 14% State) Ongoing ADB Sponsored Transmission Works (86% ADB, 14% State) Package A – Bihar Sharif - INR 38 Cr Package B – Motihari, Bettiah - INR 34 Cr Pkg C – Samastipur, Begusarai - INR 56 Cr Package D – Ara, Buxer- INR 49 Cr Package G – S/S- INR 49 Cr Package H – S/S- INR 47 Cr Package I – TL - INR 58 Cr Package J – TL - INR 42 Cr Investment of INR ~300 Cr expected in Distribution till 2015-16 Main works to be carried out: • Augmentation of substation capacity • LT and HT lines re-conductoring • New lines • Consumer metering
  • 23. 23 Tendered Projects - INR 500 Cr+ OPPORTUNITIES IN TRANSMISSION Current Opportunities (BRGF Phase II and III ext) – Partial List S.No Works Est. Value (INR ~Cr) 1 NIT No. 160/PR/BSPTCL/2013 – 132 KV D/C lines and line bays in GSS (3 Packages) 60 2 NIT No. 161/PR/BSPTCL/2013 - Re-conductoring of 132 KV S/C and D/C lines (4 Packages) 56 3 NIT No. 162/PR/BSPTCL/2013 - Re-conductoring of 132 KV S/C and D/C lines (4 Packages) 42 4 NIT No. 168/PR/BSPTCL/2013 - Re-conductoring of 220 KV D/C lines (2 Packages) 31.5 5 Capacity Augmentation of 220/132 KV GSS (7 GSSs) by installing one 160 MVA Transformer at each GSS, constructing bays – Turnkey Basis 67.5 6 Capacity Augmentation of 132/33 KV GSS (6 GSSs) by installing one 50 MVA and one 20 MVA Transformer at 6 GSS (different for 50 MVA and 20 MVA) , constructing bays etc– Turnkey Basis 58.5 7 Construction of 4 numbers 220/132 KV SS (Bhikanpura, Samastipur, Supaul and SKMCH) and 1 number 132/33 KV SS (Sheohar) and associated Transmission Lines 1400 Cr (to be tendered)8 Capacity addition by above GSS; 220/132 KV - 1280 MVA, 132/33 KV – 600 MVA 9 Capacity augmentation of 32 Nos. old GSS (1700 MVA). 10 Stringing Of 2nd Circuit of Existing 17 No’s S/C Transmission Line. Further details can be found on www.eproc.bihar .gov.in Upcoming Projects - INR 1400 Cr
  • 24. 24 OPPORTUNITIES IN TRANSMISSION CONTINUED… Upcoming Opportunities (BRGF Phase III) – To be Executed in 12th Plan S.No Works Est. Value (INR ~Cr) 1 Construction of 03 Nos. 400/220/132 KV GSS (Bihta, Gaighat and Fatuha) and 11 Nos. 220/132/33 KV GSS (Chapra, Sonenagar, Gaya, Jakkanpur, Mithapur, Sabour, Jamalpur, Sheikhpura, Nawada, Hathidah and Dumraon). 4600 Cr 2 (400/220 KV – 3000 MVA, 220/132 KV – 4160 MVA & 132/33 KV – 650 MVA). 3 Capacity augmentation of 09 Nos. old GSS (470 MVA). 4 2x500 MVA , 400/220 KV Pooling Station at Kajra 5 2x500 MVA, 400/220 KV I.P.P at Lakhisarai, Pirpainti & Buxar switchyard. Current Opportunities (State Plan) – Partial List for 2013-14 S.No Works Est. Value (INR ~Cr) 1 Constraint Removal in Transmission System 49 2 Renovation of 15 GSS 9 3 2nd Circuit Stringing Activities - Further Execution in 12th Plan – INR 4600 Cr State spend on projects and procurement - INR ~330 Cr PA Total corpus planned to be executed by 2017 is INR~8000 Cr
  • 25. 25 OPPORTUNITIES IN TRANSMISSION CONTINUED… Transmission Service Provider on PPP – Evacuation of Power from Buxar TPS S.No Works Timeline 1 • Buxar TPS – Bihta 400 KV D/C • Buxar TPS – Dumraon 220 KV D/C • Buxar TPS – Mohania 220 KV D/C • Buxar TPS – Dehri 220 KV D/C • 2x500 MVA, 400/220 KV SS at Bihta • Bihta 400/220 KV – Patna 400 KV D/C Line • LILO of Ara – Khagaul 220 KV D/C • Bihta 400/220 KV – Bihta 220/132 KV D/C Line • 2x160 MVA 220/132 KV SS at Dumraon • LILO 220 KV D/C at Dumraon • Dumraon 220/132 KV SS • Bihta 400/220 KV – Sipara 220/132 KV D/C Line Planned; To be tendered by 2015
  • 27. 27 Upcoming Projects - INR 1155 Cr OPPORTUNITIES IN DISTRIBUTION Current Opportunities (R-APDRP Part B) S.No Works Est. Value (INR ~Cr) EMD (INR ~Cr) Completion 1 NIT No.: 177/PR/NBPDCL/2013 for 17 towns of Tirhut Electric Supply Area, Muzaffarpur 175.75 3.5 18 Months 2 NIT No.: 178/PR/NBPDCL/2013 for 2 towns of Mithila Electric Supply Area, Darbhanga 44.7 0.90 18 Months 3 NIT No. 179/PR/NBPDCL/2013 for 10 towns of Kosi Electric Supply Area, Saharsa 119 2.5 18 Months 4 NIT No.: 197/PR/SBPDCL/2013 for Package-A of PESU Area, Patna comprising of New Capital & Kankarbagh Divisions 154 3.08 18 Months 5 NIT No.: 198/PR/SBPDCL/2013 for Package-B of PESU Area, Patna comprising of Danapur, Patliputra, Dakbanglow & Gardanibag Divisions of PESU (West) Circle 196.25 3.92 18 Months 6 NIT No. 199/PR/SBPDCL/2013 for Package-C of PESU Area, Patna comprising of Rajendra Nagar, Bankipur, Gulzarbagh & Patna City Divisions of PESU (East) Circle 155.4 3.10 18 Months 7 NIT No.: 200/PR/SBPDCL/2013 for 13 towns of Magadh Electric Supply Area, Gaya 199. 3.98 18 Months 8 NIT No.: 201/PR/SBPDCL/2013 for 12 towns of Bhagalpur Electric Supply Area, Bhagalpur 156 3.12 18 Months 9 NIT No.: 202/PR/SBPDCL/2013 for 9 towns of Central Electric Supply Area, Patna 48 0.96 18 Months Further details can be found on www.eproc.bihar .gov.in
  • 28. 28 Upcoming Projects - INR 1087 Cr OPPORTUNITIES IN DISTRIBUTION CONTINUED… Current Opportunities (BRGF Phase I) S.No Works Est. Value (INR ~Cr) EMD (INR ~Cr) Cost of Tender Doc 1 NIT No.: 190/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Muzaffarpur, Vaishali, Sitamarhi, Sheohar, East and West Champaran 117.5 2.36 1 Lac 2 NIT No.: 191/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Saranm, Siwan, Gopalganj 100 2.01 1 Lac 3 NIT No.: 192/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Samastipur, Begusarai 82 1.65 1 Lac 4 NIT No.: 193/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Darbhanga, Madhubani 110 2.20 1 Lac 5 NIT No.: 194/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Saharsa, Khagaria, Supaul, Madhepura, Purnea, Araria, Katihar, Kishanganj 102 2.05 1 Lac 6 NIT No.: 196/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Gaya, Nawada, Jehanabad 92.7 1.85 1 Lac Further details can be found on www.eproc.bihar .gov.in
  • 29. 29 Upcoming Projects - INR 1087 Cr OPPORTUNITIES IN DISTRIBUTION CONTINUED… Current Opportunities (BRGF Phase I) S.No Works Est. Value (INR ~Cr) EMD (INR ~Cr) Cost of Tender Doc 7 NIT No.: 203/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Arwal, Aurangabad 78.7 1.57 1 Lac 8 NIT No.: 204/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Rohtas, Kaimur 82 1.64 1 Lac 9 NIT No.: 205/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Bhojpur, Buxar 53.4 1.07 1 Lac 10 NIT No.: 206/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Nalanda, Patna 104 2.09 1 Lac 11 NIT No.: 207/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Bhagalpur, Banka, Munger 99 1.98 1 Lac 12 NIT No.: 208/PR/NBPDCL/2013 – Supply and erection of 33/11 KV PSS, 33 KV Lines, 11 KV Lines, Augmentation of 33/11 KV PSS, on Turnkey Basis – Jamui, Lakhisarai, Sheikpura 66.6 1.33 1 Lac Further details can be found on www.eproc.bihar .gov.in
  • 30. 30 OPPORTUNITIES IN DISTRIBUTION CONTINUED… Other Upcoming Opportunities including State Plan Sl.No Works Est. Value (INR ~Cr) Approx. Timeline 1 Non RAPDRP IT Works for Non RAPDRP Towns; Would include key modules such as MBC, New Connection, MIS, MDAS, energy Audit, Web Services, Asset and Maintenance Management (GIS not included) 35 1 Month 2 Feeder Segregation works for 37 districts in Bihar State (Under Rainbow Revolution State Scheme) - Upcoming 3 Civil work of DCRs (District Control Rooms) in 21 Districts 51.6 Upcoming 4 Civil work of MRT Building in 7 Districts 14.6 Upcoming 5 Redevelopment of Karbhigiya TPS as an Energy Park 28 Tendered (Submission Upcoming) 6 NIT No.: 157/PR/SBPDCL/2013 – Supply of 1741 numbers of 63 KVA, 11/0.433 KV Al Wound Distribution Transformers 13.9 Tendered (Submission Upcoming) 7 Collection Initiatives - Tendered (Submission upcoming) 8 Prepaid Metering – Expression of interest - Upcoming 9 NIT of On-spot billing tender - Upcoming 10 NIT 144/PR/SBPDCL/2013ACSR Weasel Conductor (7727 KM) 16.24 Tendered Further details can be found on www.eproc.bihar .gov.in
  • 31. 31 AREAS TO COME UP FOR DISTRIBUTION FRANCHISEE (10 Twin Cities) 2 6 43 58 9 10 North Bihar 1. Bettiah – Motihari 2. Gopalganj - Siwan 3. Chapra – Hazipur 4. Darbhanga - Samastipur 5. Begusarai – Barauni 6. Purnia - Kathihar South Bihar 7. Lakhisarai - Munger 8. Bihar Sharif - Rajgir 9. Arrah - Buxar 10. Sasaram - Dehri
  • 32. 32 FRANCHISEE AREA CHARACTERISTICS Town District No. of Consumers Revenue Assessment AT&C losses Motihari East Champaran 25363 8.99 55%-60% Bettiah West Champaran 66661 35.53 55%-60% Gopalganj Gopalganj 7274 10.51 55%-60% Siwan Siwan 83054 30.56 55%-60% Chapra Saran 47698 16.71 55%-60% Hazipur Vaishali 35288 33.06 55%-60% Darbhanga Darbhanga 24613 4.78 55%-60% Samastipur Samastipur 12226 4.46 55%-60% Begusarai Begusarai 39260 7.41 55%-60% Barauni Begusarai 38425 4.08 55%-60% Purniya Purnia 101678 93.38 55%-60% Katihar Katihar 62236 46.33 55%-60% Lakhisarai Lakhisarai 27601 18.27 65% Munger Munger 33263 42.93 38% Biharsharif Nalanda 55948 35.39 78% Rajgir Nalanda 10216 12.13 76% Aarah Bhojpur 84276 31.61 53% Buxor Buxar 33433 18.92 60% Sasaram Rohtas 50000-60000 15.87 62% Dehri Rohtas 50000-60000 34.99 41%
  • 33. 33 SUMMARY OF KEY INITIATIVES IN T&D Initiative Sector Status Re-conductoring and second stringing of Transmission Lines Transmission Ongoing Capacity augmentation by increasing transformers T&D Ongoing New Lines, SS and Grids T&D Ongoing R&M of SS Transmission Ongoing Apex Metering for Bulk Power Transfer Pts Transmission Upcoming PPP in Transmission (Transmission Service Provider) Transmission Upcoming Regularization of Tariff Calendar and Petition T&D Upcoming Increased Metering Activities Distribution Ongoing Prepaid Metering – Supply, Installation and Maintenance of Single and Three Phase Static Energy Meters Distribution Upcoming Modern SCADA (Patna City) Distribution Ongoing Collection Initiatives such as POS collection, Mobile Vans, Spot Billing, Increased Centers, M-Commerce, Internet Payment Mechanism etc Distribution Ongoing/Upcoming Non R-APDRP IT Works Distribution Upcoming Feeder Segregation Programme (Pilot for 1 district underway, 37 other districts planned) Distribution Ongoing/Upcoming PPP in Distribution (Franchisee Model) Distribution Ongoing/Upcoming Heightened Response Times for O&M T&D Ongoing
  • 35. 35 POTENTIAL CHALLENGES Payment Related Tendering Related • Issuance of operational guidelines for tendering (may be time-bound) • Analysis of participants ongoing projects – addition to QR • Standardized schedule of rates Execution Related • Appointment of PMCs for project monitoring and timely execution • Formation of execution cell by Utilities • Clear guidelines for handing over of works to the utility ….And Potential Solutions • All projects are fund tied ensuring timely payments • Promises to pay within a months time • Monitoring by MDs personally • Re-engineering of invoice approval and payment processing workflow
  • 36. 36 END OF DECK Contact Details of Officials Name Designation Number eMail Sri Sanjay Kumar Singh, I.A.S MD, BSPTCL (0612)-2504442 singhsanjaypat@gmail.com Sri Sanjay Kumar Agarwal, I.A.S MD, NBPDCL (0612)-2504044 md.nbpdcl@gmail.com Smt. Palka Sahani, I.A.S MD, SBPDCL (0612)-2504045 md.sbpdcl@gmail.com Sri N.K.P. Sinha CE(RE), NBPDCL 9431247281 Cere.bseb@gmail.com Sri S.K.P. Singh CE(Comm.), SBPDCL 9470001748 Cecom.sbpdcl@gmail.com Sri Y.K. Thakur CE, (trans) BSPTCL 9470001760 Ce.trans664@gmail.com
  • 37. 37 END OF DECK Division Ravi Kathpal Associate Director Energy Division Vijay Dhonde Lead Consultant Energy Division Sudhanshu Malhotra Principal Consultant Energy Division Address Feedback Infra Private Limited 602, 6th Floor, Natraj, Western Express Highway, Andheri (East), Mumbai 400 069. Feedback Infra Private Limited 602, 6th Floor, Natraj, Western Express Highway, Andheri (East), Mumbai 400 069. Feedback Infra Private Limited 15th Floor, Tower 9B, DLF Cyber City, Gurgaon – 122002 Haryana (INDIA) Phone +91 22 67718816 +91 9820019591 +91 22 67718828 +91 983343447 +91 124 4169136 +91 9899382737 Fax +91 22 66713639 +91 22 66713639 +91 124 4169155 Email Ravi.kathpal@feedbackinfra.com Vijay.dhonde@feedbackinfra.com Sudhanshu.malhotra@feedbackinfr a.com