Examination paper: Six Sigma Management
IIBM Institute of Business Management 1
IIBM Institute of Business Management
Examination Paper MM.100
Six Sigma Green Belt
Section A: Objective Type (40 Marks)
• This section consists of Multiple Choice questions.
• Answer all the questions.
• Each question carries 1 mark.
Part One:
Multiple Choices:
1. The primary purpose of a control chart is to:
a. Set Specifications and tolerances
b. Compare operations.
c. Determine the stability of a process.
d. Accept or reject a lot of material
2. When a control chart is used on a new process, capability can be assessed at which of the following
times?
a. Before the chart is first started
b. After the first ten points are plotted
c. When the plotted points hug the centerline
d. After the process is shown to be in control
3. Precision is best described as:
a. A comparison to a known standard
b. The achievement of expected outgoing quality
c. The repeated consistency of results
d. The difference between an average measurement and the actual value
4. The overall ability of two or more operators to obtain consistent results repeatedly when measuring
the same set of parts and using the same measuring equipment is the definition of:
a. Repeatability
b. Precision
c. Reproducibility
d. Accuracy
5. Which of the following conditions must be met for a process to be in a state of statistical control?
a. Most of the product out by the process is in specification.
b. All subgroup averages and rang are within control limits.
c. All variation has been completely removed
d. Previously optimal process settings are used.
Examination paper: Six Sigma Management
IIBM Institute of Business Management 2
6. Which of the following measures of dispersion is equal to the sum of deviations from the mean
squared divided by the sample size?
a. Range
b. Standard deviation
c. Variance
d. Mode
7. An X and R chart is used to:
a. Indicate process variation
b. Specify design Limits
c. Interpret costs
d. Identify customer expectations
8. Which of the following is the most useful graphical tool for promoting and understanding the process
of capability?
a. A flowchart
b. A histogram
c. An affinity diagram
d. An Ishikawa diagram
9. The type of chart that presents the value of items in descending order is a:
a. Histogram
b. Pareto chart
c. U chart
d. Cusum chart
10. Measures of which of the following provide attributes data?
a. Temperature in degrees
b. Attendance at meetings
c. Weight in pounds
d. Length in metric units
11. The fraction of nonconforming products is plotted on which of the following types of control chart?
a. P chart
b. U chart
c. Np chart
d. C chart
12. A cause and effect diagram is a useful tool for doing which of the following?
a. Determining the flow of a process
b. Detecting shifts in a process
c. Developing theories based on symptoms
d. Arranging theories by defect count
13. Which of the following statistics would best describe the central tendency of a sample of data?
a. Mode
b. Mean
c. Standard deviation
d. Range
Examination paper: Six Sigma Management
IIBM Institute of Business Management 3
14. Which of the following type of tools or techniques is considered qualitative?
a. Histogram
b. Frequency distributions
c. Pareto chart
d. Process observations
15. Out of the following which technique is most useful in narrowing issues and limiting discussion?
a. Brainstorming
b. Quality function deployment
c. Cause and effect analysis
d. Mutilating
16. In statistics, an estimation error that is persistent or systematic is called:
a. Bias
b. Sensitivity
c. Random
d. Shift
17. For a normal distribution, two standard deviation on each side of the mean would include what
percentage of the total population:
a. 47%
b. 68%
c. 95%
d. 99%
18. If a distribution is normal, u=50 s=15, what percentage of data will be less than 30?
a. 59.18%
b. 40.82%
c. 9.18%
d. 1.33%
19. A company is receiving an unusually high number of returns from various customers. The first step in
investigating the problem would be to
a. Check the inspection records
b. Establish the correlation of the returns to shipments
c. Brainstorm the potential causes
d. Classify the returns by type and degree of serious
20. Which of the following is the best definition of a flow chart?
a. A diagram used to structure ideas into useful categories
b. An illustration used to analyze variation in a process
c. A picture used to separate steps of a process in sequential order
d. An analytical tool used to clarify opposing aspects of a desired change
21. Which of the following activities would NOT contribute to the effective functioning of a team?
a. Eliminating unnecessary activities
b. Development team performance measures
c. Defining process in detail
d. Monitoring each member’s performance
Examination paper: Six Sigma Management
IIBM Institute of Business Management 4
22. What is the standard deviation of the population-10, 4, 16, 12, and 8?
a. 4.00
b. 4.47
c. 16.00
d. 20.00
23. Which of the following tools would be most appropriate for collecting data to study the symptoms of
a problem?
a. Check sheet
b. Flow diagram
c. Force-field analysis
d. Activity network diagram
24. Which of the following measures is a sufficient statistic for the parameter u?
a. Median
b. Mid-range
c. Mean
d. Mode
25. Positional, cyclical, and temporal variations are most commonly analyzed in:
a. SPC charts
b. Multi-vari charts
c. Cause and effect diagram
d. Run charts
26. Which of the following describes the deming method for continuous improvement?
a. Cost of quality analysis
b. Process map
c. Tree Diagram
d. Plan-do-check-act cycle
27. In analysis of variance, which of the following distribution is the basis for determining whether the
variance estimates are all from the same population?
a. Chi square
b. Students
c. Normal
d. F
28. Which of the following statement best describes the set of value of a random variable?
a. It is finite.
b. It is an interval
c. It can be discrete or continuous.
d. It can be tracked by using control charts or scatter plots.
29. Which of the following is the best description of randomization?
a. A technique used to increase the precision of an experiment
b. A means of assuring representative sampling
c. The repetition of an observation or measurement
d. The relationship between two or more variables
Examination paper: Six Sigma Management
IIBM Institute of Business Management 5
30. When the order of items is not important, which of the following method is used to determine the
number of sets and subsets of items?
a. Combination
b. Permutation
c. Factorization
d. Simulation
31. Scatter diagrams are best described as:
a. Histograms.
b. Correlation analysis.
c. Pareto analysis.
d. Ishikawa diagrams.
32. A __________ is created to determine customers of a specific process.
a. Pareto chart
b. Flow diagram
c. Cause and effect diagram
d. Scatter diagram
33. A production line uses signs at specific points on the line to indicate when components or raw
materials need to be replenished. This practice is an example of:
a. Kanban
b. Poka-yake
c. Checkpoints
d. Hoshin
34. Which of the following is a good tool for planning cycle time reduction and concurrent operations?
a. A timeline
b. A Pareto diagram
c. An X and R chart
d. A PERT chart
35. Attribute and variable data are best described as which of the following?
a. Counted values measured values
b. Counted values visual features
c. Measured values counted values
d. Visual features counted values
36. All of the following are common ways for people to react to conflict except:
a. Competing
b. Collaborating
c. Avoiding
d. Sabotaging
37. A quality manager has chosen to survey customer satisfaction by taking samples based on the
categories of frequency of use, categories of use, and demographic. This technique is known as
a. Random sampling
b. Data collection
c. Stratification
d. Customer classification
Examination paper: Six Sigma Management
IIBM Institute of Business Management 6
38. Which of the following actions is Not used to reduce process cycle time?
a. Analyzing current processes
b. Reducing queue times
c. Setting priorities
d. Implementing activity-based costing
39. A company’s accounts payable department is trying to reduce the time between receipt and
payment of invoices and has recently completed a flowchart. Which of the following tool is the next
to be used by them?
a. Fishbone diagram
b. Scatter diagram
c. Box and whisker plat
d. Histogram
40. In a manufacturing company, the machine shop is what kind of customer in relation to the Human
Resource department?
a. Intermediate
b. Hidden
c. External
d. Internal
Section B: Short Notes (30 Marks)
• This section consists of Short Notes Questions.
• Answer all the questions.
• Each Question carries 6 marks.
1. Describe how QFD fits into the overall DFSS process.
2. What is interrelationship Digraph? Explain it with example.
3. Find the area under the standard normal curve between +1.50 standard deviations and +2.50
standard deviations.
4. Define terms related to One-Way ANOVA and interpret their results & data plots.
5. Define & describe the use of Rational Sub grouping.
END OF SECTION A
END OF SECTION B
Examination paper: Six Sigma Management
IIBM Institute of Business Management 7
Section C: Applied Theory (30 Marks)
• This section consists of Applied Theory Questions.
• Answer all the questions.
• Each question carries 15 marks.
• Detailed information should from the part of your answer (Word limit 200 to 250 words).
1. Suppose you are cooking steak for 100 people, & the current approval rating is 75% acceptable.
You want to know the affect of different methods and approaches to see how the overall approval
or “yield” is affected. By using the Full Factorial method explain how the overall approval or
“yield” is affected.
2. Interpret Control Charts? Distinguish between common & special causes using rules for
determining stastical control.
END OF SECTION C
Examination paper: Six Sigma Management
IIBM Institute of Business Management 8
IIBM Institute of Business Management
Examination Paper MM.100
Six Sigma Black Belt
Section A: Objective Type (40 Marks)
• This section consists of Multiple Choice questions.
• Answer all the questions.
• Part one questions carry 1 mark each & Part Two questions carry 2 marks each.
Part One:
Multiple Choices:
1. Calculate the estimated variance of the population from which the following values have been
randomly selected: 2.8 2.7 2.6 2.9 2.8 2.8 2.8.
a. 095
b. 009
c. 088
d. 008
2. The mean, median and mode of a distribution have the same value. What can be said about the
distribution?
a. It is exponential
b. It is normal
c. It is uniform
d. None of the above
3. Approximately what percent of the data values are smaller than the mean?
a. 25%
b. 50%
c. 75%
d. None of above
4. A normal probability plot is used to:
a. Determine whether the distribution is normal
b. Plot Z value
c. Determine process capability
d. It percent out of specification
5. Nominal Group technique is used to:
a. Help a group reach consensus
b. Generate a group on new ides
c. Provide a consistent stable group leadership
d. Provide a name for the group
Examination paper: Six Sigma Management
IIBM Institute of Business Management 9
6. An example of a project metric would be:
a. The decrease in defect occurrence
b. The decrease in product cost
c. The decrease in cycle time
d. All the above
7. A correct statement about the relationship between the terms parameter and statistic is:
a. A population statistic is more accurate than a parameter
b. A sample parameter is used to estimate a statistic
c. A sample statistic is used to estimate a population parameter
d. Standard deviation calculation requires both statistics and parameters
8. A and B are events. P(A) = 0.80 and P(B) = 0.90:
a. Events A and B are disjoint or mutually exclusive
b. Events A and B are not disjoint or mutually exclusive
c. P (A and B) = 0
d. P(A and B) = 1.7
9. In a certain sampling situation, a=0, b=0.08. the power of the sampling plan this case is:
a. 0
b. 0.08
c. 1.00
d. 0.92
10. A newspaper article describes a high positive correlation between obesity and orange juice
consumption among six-year-old children’s. Parents who restrict the use of orange juice for their
children have:
a. Made a type I error
b. Made a type II error
c. Misunderstood margin of error
d. Confused correlation with causation
11. In an experimental design context, replications refer to:
a. Duplicating experimental result at another location
b. Repeating a test with the same factor levels
c. Obtaining the same or similar result from different factors
d. Repeating an experiment but using at least one different factor level
12. Find the upper control limit for a range chart if n=4 and the average range is 2.282.
a. 2.282
b. 4.564
c. 5.208
d. 3.423
13. An x-bar control chart been established with control limits of 3.245 and 3.257, n=5. An engineer
collects the following sample and plots the average on the control chart: 3.257, 3.256, 3.258, 3.259
a. The process is out of control
b. The process is not out of control
c. The engineer misused the control chart
d. The control limits are incorrect
Examination paper: Six Sigma Management
IIBM Institute of Business Management 10
14. TEIZ is an acronym which refers to:
a. A set of problem solving tools
b. An organization of quality professionals
c. An experiment using transitional results
d. A Russian general responsible for creative thinking
15. A robust design is one which;
a. Has high reliability
b. Has low maintenance frequency
c. Is simple to manufacture’
d. Is resistant to varying environmental condition
16. A frequent cause of system sub optimization is:
a. Optimizing individual process
b. Failing to draw a system flow chart
c. Using data with outliers
d. Failing to consider the normal distribution
17. The x2
distribution is:
a. Symmetric
b. Left skewed
c. Right skewed
d. Normal
18. An advantage of using standard deviation rather than range for measuring dispersion of a large
sample is that:
a. Standard deviation has a simpler formula
b. Calculators have a standard deviation key but not a range Key
c. Standard deviation uses information from each measurement
d. Range calculation are not normally distributed
19. The team development stage characterized by expression of individual opinions and ideas often
without regard for team objectives is known as:
a. Performing
b. Norming
c. Conflicting
d. Storming
20. SMED is an acronym for activity that:
a. Involve housekeeping in the work area
b. Makes mistake of a certain type impossible
c. Emphasizes the pull of the customer
d. Reduces set up the time
21. A principle advantage of fractional factorial experimental designs is:
a. Reduced cost
b. Improved accuracy
c. Increased confounding
d. Higher confidence level
Examination paper: Six Sigma Management
IIBM Institute of Business Management 11
22. Dr. W Edwards Deming:
a. Lectured in Japan after World War II
b. Was an author of several books in the US
c. Is considered an expert in the quality field
d. All of the above
Part Two:
23. What percent of population falls below the lower specification limits?
a. 9.18%
b. 22.66%
c. 6.68%
d. 1.83%
24. Find the mean, median and mode of the following data set: 9, 11, 12, 14, 18, 18, 18, 20, and 23:
a. 15.5, 18, 18
b. 15, 14, 18
c. 15, 12, 18
d. 15.5, 16, 18
Use for problems 25-27:
A B Res.
25. Calculate the main effect of factor A:
a. 20
b. 25
c. 30
d. None of the above
26. Calculate the interaction effect:
a. 20
b. 25
c. 40
d. None of the above
27. If it is desirable to maximize the response R, the following levels should be used:
a. A+ and B+
b. A+ and B-
c. A- and B+
d. None of the above
1 - - 20
2 - + 30
3 + - 40
4 + + 50
Examination paper: Six Sigma Management
IIBM Institute of Business Management 12
Use for questions28-30:
Here is an experimental design with result:
A B C Responses
1
- - + 10 11 10
2 - + - 22 20 23
3 + + + 34 36 37
4 + - - 26 25 25
28. This experimental design is:
a. Full factorial
b. Half factorial
c. Quarter factorial
d. None of the above
29. The number of factors, levels and replications:
a. 3, 3, 3
b. 3, 2, 2
c. 3, 2, 3
d. None of the above
30. An indication of the experimental error is available because the design has:
a. Multiple replications
b. Multiple levels
c. Multiple factors
d. None of the above
31. The average number of defects is 21.6. Find the upper control limit for the C-chart.
a. 26.4
b. 24.6
c. 26.2
d. None of the above
Section B: Short Notes (30 Marks)
• This section consists of Short Notes Questions.
• Answer all the questions.
• Each Question carries 6 marks.
1. Briefly define Affinity Diagram with an example.
2. By using imaginary figures draw a Run Chart.
END OF SECTION A
Examination paper: Six Sigma Management
IIBM Institute of Business Management 13
3. Consider the following data & develop a normal probability graph paper & normal probability
plot:
7.9, 9.7, 10.6, 12.7, 12.8, 18.1, 21.2, 33.0, 43.5, 51.1, 81.4, 93.1
4. A painting process produces coatings with a thickness of 0.0005 & a standard deviation of
0.00002. What should the tolerance limits be for this process? Briefly explain Tolerance design?
5. What is Pugh matrix? State the steps which are used in Pugh matrix.
Section C: Applied Theory (30 Marks)
• This section consists of Applied Theory Questions.
• Answer all the questions.
• Each question carries 15 marks.
• Detailed information should from the part of your answer (Word limit 200 to 250 words).
1. Define & describe the purpose of root cause analysis? Recognize the issues involved in
identifying a root cause analysis and list various tools for resolving chronic problem?
2. Describe the purpose & elements of FMEA including risk priority number (RPN), and evaluate
FMEA results for processes, products, & services. Distinguish between design FMEA (DFMEA)
& process FMEA (PFMEA) and interpret results from each.
-
S-2-210311
END OF SECTION B
END OF SECTION C

Mais conteúdo relacionado

Mais procurados

Six Sigma Green Belt - Find the area under the standard normal curve between ...
Six Sigma Green Belt - Find the area under the standard normal curve between ...Six Sigma Green Belt - Find the area under the standard normal curve between ...
Six Sigma Green Belt - Find the area under the standard normal curve between ...Suma Kamadod
 
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...Suma Kamadod
 
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...Suma Kamadod
 
Six Sigma Green Belt - Which of the following measures is a sufficient statis...
Six Sigma Green Belt - Which of the following measures is a sufficient statis...Six Sigma Green Belt - Which of the following measures is a sufficient statis...
Six Sigma Green Belt - Which of the following measures is a sufficient statis...Suma Kamadod
 
Six Sigma Green Belt - The type of chart that presents the value of items in ...
Six Sigma Green Belt - The type of chart that presents the value of items in ...Six Sigma Green Belt - The type of chart that presents the value of items in ...
Six Sigma Green Belt - The type of chart that presents the value of items in ...Suma Kamadod
 
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...Six Sigma Green Belt - In statistics, an estimation error that is persistent ...
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...Suma Kamadod
 
Six Sigma Green Belt - Which of the following describes the deming method for...
Six Sigma Green Belt - Which of the following describes the deming method for...Six Sigma Green Belt - Which of the following describes the deming method for...
Six Sigma Green Belt - Which of the following describes the deming method for...Suma Kamadod
 
Six Sigma Green Belt - In analysis of variance, which of the following distri...
Six Sigma Green Belt - In analysis of variance, which of the following distri...Six Sigma Green Belt - In analysis of variance, which of the following distri...
Six Sigma Green Belt - In analysis of variance, which of the following distri...Suma Kamadod
 
Six Sigma Green Belt - Which of the following statistics would best describe ...
Six Sigma Green Belt - Which of the following statistics would best describe ...Six Sigma Green Belt - Which of the following statistics would best describe ...
Six Sigma Green Belt - Which of the following statistics would best describe ...Suma Kamadod
 
Six Sigma Green Belt - A production line uses signs at specific points on the...
Six Sigma Green Belt - A production line uses signs at specific points on the...Six Sigma Green Belt - A production line uses signs at specific points on the...
Six Sigma Green Belt - A production line uses signs at specific points on the...Suma Kamadod
 
Six Sigma Green Belt - A company is receiving an unusually high number of ret...
Six Sigma Green Belt - A company is receiving an unusually high number of ret...Six Sigma Green Belt - A company is receiving an unusually high number of ret...
Six Sigma Green Belt - A company is receiving an unusually high number of ret...Suma Kamadod
 
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...Suma Kamadod
 
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...Suma Kamadod
 
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...Suma Kamadod
 
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...Suma Kamadod
 
Six Sigma Green Belt - Define terms related to one way anova and interpret th...
Six Sigma Green Belt - Define terms related to one way anova and interpret th...Six Sigma Green Belt - Define terms related to one way anova and interpret th...
Six Sigma Green Belt - Define terms related to one way anova and interpret th...Suma Kamadod
 
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...Six Sigma Green Belt - Which of the following is a good tool for planning cyc...
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...Suma Kamadod
 
Six Sigma Green Belt - Interpret control charts distinguish between common &a...
Six Sigma Green Belt - Interpret control charts distinguish between common &a...Six Sigma Green Belt - Interpret control charts distinguish between common &a...
Six Sigma Green Belt - Interpret control charts distinguish between common &a...Suma Kamadod
 
Six Sigma Green Belt - Which of the following actions is not used to reduce p...
Six Sigma Green Belt - Which of the following actions is not used to reduce p...Six Sigma Green Belt - Which of the following actions is not used to reduce p...
Six Sigma Green Belt - Which of the following actions is not used to reduce p...Suma Kamadod
 
Six Sigma Green Belt - Which of the following activities would not contribute...
Six Sigma Green Belt - Which of the following activities would not contribute...Six Sigma Green Belt - Which of the following activities would not contribute...
Six Sigma Green Belt - Which of the following activities would not contribute...Suma Kamadod
 

Mais procurados (20)

Six Sigma Green Belt - Find the area under the standard normal curve between ...
Six Sigma Green Belt - Find the area under the standard normal curve between ...Six Sigma Green Belt - Find the area under the standard normal curve between ...
Six Sigma Green Belt - Find the area under the standard normal curve between ...
 
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...
Six Sigma Green Belt - The fraction of nonconforming products is plotted on w...
 
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...
Six Sigma Green Belt - A cause and effect diagram is a useful tool for doing ...
 
Six Sigma Green Belt - Which of the following measures is a sufficient statis...
Six Sigma Green Belt - Which of the following measures is a sufficient statis...Six Sigma Green Belt - Which of the following measures is a sufficient statis...
Six Sigma Green Belt - Which of the following measures is a sufficient statis...
 
Six Sigma Green Belt - The type of chart that presents the value of items in ...
Six Sigma Green Belt - The type of chart that presents the value of items in ...Six Sigma Green Belt - The type of chart that presents the value of items in ...
Six Sigma Green Belt - The type of chart that presents the value of items in ...
 
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...Six Sigma Green Belt - In statistics, an estimation error that is persistent ...
Six Sigma Green Belt - In statistics, an estimation error that is persistent ...
 
Six Sigma Green Belt - Which of the following describes the deming method for...
Six Sigma Green Belt - Which of the following describes the deming method for...Six Sigma Green Belt - Which of the following describes the deming method for...
Six Sigma Green Belt - Which of the following describes the deming method for...
 
Six Sigma Green Belt - In analysis of variance, which of the following distri...
Six Sigma Green Belt - In analysis of variance, which of the following distri...Six Sigma Green Belt - In analysis of variance, which of the following distri...
Six Sigma Green Belt - In analysis of variance, which of the following distri...
 
Six Sigma Green Belt - Which of the following statistics would best describe ...
Six Sigma Green Belt - Which of the following statistics would best describe ...Six Sigma Green Belt - Which of the following statistics would best describe ...
Six Sigma Green Belt - Which of the following statistics would best describe ...
 
Six Sigma Green Belt - A production line uses signs at specific points on the...
Six Sigma Green Belt - A production line uses signs at specific points on the...Six Sigma Green Belt - A production line uses signs at specific points on the...
Six Sigma Green Belt - A production line uses signs at specific points on the...
 
Six Sigma Green Belt - A company is receiving an unusually high number of ret...
Six Sigma Green Belt - A company is receiving an unusually high number of ret...Six Sigma Green Belt - A company is receiving an unusually high number of ret...
Six Sigma Green Belt - A company is receiving an unusually high number of ret...
 
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...
Six Sigma Green Belt - The primary purpose of a control chart is to a. set sp...
 
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...
Six Sigma Green Belt - Positional, cyclical, and temporal variations are most...
 
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...
Six Sigma Green Belt - An x and r chart is used to a. indicate process variat...
 
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...
Six Sigma Green Belt - A quality manager has chosen to survey customer satisf...
 
Six Sigma Green Belt - Define terms related to one way anova and interpret th...
Six Sigma Green Belt - Define terms related to one way anova and interpret th...Six Sigma Green Belt - Define terms related to one way anova and interpret th...
Six Sigma Green Belt - Define terms related to one way anova and interpret th...
 
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...Six Sigma Green Belt - Which of the following is a good tool for planning cyc...
Six Sigma Green Belt - Which of the following is a good tool for planning cyc...
 
Six Sigma Green Belt - Interpret control charts distinguish between common &a...
Six Sigma Green Belt - Interpret control charts distinguish between common &a...Six Sigma Green Belt - Interpret control charts distinguish between common &a...
Six Sigma Green Belt - Interpret control charts distinguish between common &a...
 
Six Sigma Green Belt - Which of the following actions is not used to reduce p...
Six Sigma Green Belt - Which of the following actions is not used to reduce p...Six Sigma Green Belt - Which of the following actions is not used to reduce p...
Six Sigma Green Belt - Which of the following actions is not used to reduce p...
 
Six Sigma Green Belt - Which of the following activities would not contribute...
Six Sigma Green Belt - Which of the following activities would not contribute...Six Sigma Green Belt - Which of the following activities would not contribute...
Six Sigma Green Belt - Which of the following activities would not contribute...
 

Destaque

Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project managementNMIMS ASSIGNMENTS HELP
 
Mba isbm case study answers & solutions 3
Mba isbm case study answers & solutions 3Mba isbm case study answers & solutions 3
Mba isbm case study answers & solutions 3NMIMS ASSIGNMENTS HELP
 
Emba iibm case study solutions & multiple answers 1
Emba iibm case study solutions & multiple answers 1Emba iibm case study solutions & multiple answers 1
Emba iibm case study solutions & multiple answers 1NMIMS ASSIGNMENTS HELP
 
Dbm ksbm case study answers & solutions
Dbm ksbm case study answers & solutionsDbm ksbm case study answers & solutions
Dbm ksbm case study answers & solutionsNMIMS ASSIGNMENTS HELP
 
Best practices in business
Best practices in businessBest practices in business
Best practices in businessadelliott
 
Find A List of Local Non denominational churches in South Africa
Find A List of Local Non denominational churches in South AfricaFind A List of Local Non denominational churches in South Africa
Find A List of Local Non denominational churches in South AfricaIFellowship.co
 
Examination paper international business management & globall marketing mana...
Examination paper  international business management & globall marketing mana...Examination paper  international business management & globall marketing mana...
Examination paper international business management & globall marketing mana...NMIMS ASSIGNMENTS HELP
 
Gdm iibms case study answers & solutions
Gdm iibms case study answers & solutionsGdm iibms case study answers & solutions
Gdm iibms case study answers & solutionsNMIMS ASSIGNMENTS HELP
 
Materials management & inventory management
Materials management & inventory managementMaterials management & inventory management
Materials management & inventory managementNMIMS ASSIGNMENTS HELP
 
Cross browser web development
Cross browser web developmentCross browser web development
Cross browser web developmentIlya Starostin
 

Destaque (20)

Examination paper of project management
Examination paper of project managementExamination paper of project management
Examination paper of project management
 
Mba isbm case study answers & solutions 3
Mba isbm case study answers & solutions 3Mba isbm case study answers & solutions 3
Mba isbm case study answers & solutions 3
 
Emba iibm case study solutions & multiple answers 1
Emba iibm case study solutions & multiple answers 1Emba iibm case study solutions & multiple answers 1
Emba iibm case study solutions & multiple answers 1
 
Banking management
Banking managementBanking management
Banking management
 
Risk management
Risk managementRisk management
Risk management
 
Dbm ksbm case study answers & solutions
Dbm ksbm case study answers & solutionsDbm ksbm case study answers & solutions
Dbm ksbm case study answers & solutions
 
Best practices in business
Best practices in businessBest practices in business
Best practices in business
 
Human resource management (3)
Human resource management (3)Human resource management (3)
Human resource management (3)
 
Find A List of Local Non denominational churches in South Africa
Find A List of Local Non denominational churches in South AfricaFind A List of Local Non denominational churches in South Africa
Find A List of Local Non denominational churches in South Africa
 
Financial management 250613
Financial management 250613Financial management 250613
Financial management 250613
 
Managerial economics
Managerial economicsManagerial economics
Managerial economics
 
Exam paper organizational_behaviour
Exam paper organizational_behaviourExam paper organizational_behaviour
Exam paper organizational_behaviour
 
Examination paper international business management & globall marketing mana...
Examination paper  international business management & globall marketing mana...Examination paper  international business management & globall marketing mana...
Examination paper international business management & globall marketing mana...
 
Managerial economics 250613
Managerial economics 250613Managerial economics 250613
Managerial economics 250613
 
Gdm iibms case study answers & solutions
Gdm iibms case study answers & solutionsGdm iibms case study answers & solutions
Gdm iibms case study answers & solutions
 
Materials management & inventory management
Materials management & inventory managementMaterials management & inventory management
Materials management & inventory management
 
應變手冊
應變手冊應變手冊
應變手冊
 
Fol
FolFol
Fol
 
Cross browser web development
Cross browser web developmentCross browser web development
Cross browser web development
 
Organizational behavior
Organizational behaviorOrganizational behavior
Organizational behavior
 

Semelhante a Examination paper six sigma green belt & six sigma black belt

Mba iibm case study solutions & multiple answers 1
Mba iibm case study solutions & multiple answers 1Mba iibm case study solutions & multiple answers 1
Mba iibm case study solutions & multiple answers 1NMIMS ASSIGNMENTS HELP
 
Six sigma iibm case study solutions & multiple answers 1
Six sigma iibm case study solutions & multiple answers 1Six sigma iibm case study solutions & multiple answers 1
Six sigma iibm case study solutions & multiple answers 1NMIMS ASSIGNMENTS HELP
 
Dbm iibm case study solutions & multiple answers 1
Dbm iibm case study solutions & multiple answers 1Dbm iibm case study solutions & multiple answers 1
Dbm iibm case study solutions & multiple answers 1NMIMS ASSIGNMENTS HELP
 
Six Sigma Green Belt - Measures of which of the following provide attributes ...
Six Sigma Green Belt - Measures of which of the following provide attributes ...Six Sigma Green Belt - Measures of which of the following provide attributes ...
Six Sigma Green Belt - Measures of which of the following provide attributes ...Suma Kamadod
 
Six Sigma Green Belt - Which of the following is the most useful graphical to...
Six Sigma Green Belt - Which of the following is the most useful graphical to...Six Sigma Green Belt - Which of the following is the most useful graphical to...
Six Sigma Green Belt - Which of the following is the most useful graphical to...Suma Kamadod
 
Six Sigma Green Belt - Which of the following measures of dispersion is equal...
Six Sigma Green Belt - Which of the following measures of dispersion is equal...Six Sigma Green Belt - Which of the following measures of dispersion is equal...
Six Sigma Green Belt - Which of the following measures of dispersion is equal...Suma Kamadod
 
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...Suma Kamadod
 
Six Sigma Green Belt - All of the following are common ways for people to re...
Six Sigma Green Belt -  All of the following are common ways for people to re...Six Sigma Green Belt -  All of the following are common ways for people to re...
Six Sigma Green Belt - All of the following are common ways for people to re...Suma Kamadod
 
Six Sigma Green Belt - A company’s accounts payable department is trying to r...
Six Sigma Green Belt - A company’s accounts payable department is trying to r...Six Sigma Green Belt - A company’s accounts payable department is trying to r...
Six Sigma Green Belt - A company’s accounts payable department is trying to r...Suma Kamadod
 
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...Six Sigma Green Belt - For a normal distribution, two standard deviation on e...
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...Suma Kamadod
 
Six Sigma Green Belt - Which of the following type of tools or techniques is ...
Six Sigma Green Belt - Which of the following type of tools or techniques is ...Six Sigma Green Belt - Which of the following type of tools or techniques is ...
Six Sigma Green Belt - Which of the following type of tools or techniques is ...Suma Kamadod
 
Six Sigma Green Belt - Attribute and variable data are best described as whic...
Six Sigma Green Belt - Attribute and variable data are best described as whic...Six Sigma Green Belt - Attribute and variable data are best described as whic...
Six Sigma Green Belt - Attribute and variable data are best described as whic...Suma Kamadod
 
Six Sigma Green Belt - Which of the following is the best definition of a flo...
Six Sigma Green Belt - Which of the following is the best definition of a flo...Six Sigma Green Belt - Which of the following is the best definition of a flo...
Six Sigma Green Belt - Which of the following is the best definition of a flo...Suma Kamadod
 

Semelhante a Examination paper six sigma green belt & six sigma black belt (13)

Mba iibm case study solutions & multiple answers 1
Mba iibm case study solutions & multiple answers 1Mba iibm case study solutions & multiple answers 1
Mba iibm case study solutions & multiple answers 1
 
Six sigma iibm case study solutions & multiple answers 1
Six sigma iibm case study solutions & multiple answers 1Six sigma iibm case study solutions & multiple answers 1
Six sigma iibm case study solutions & multiple answers 1
 
Dbm iibm case study solutions & multiple answers 1
Dbm iibm case study solutions & multiple answers 1Dbm iibm case study solutions & multiple answers 1
Dbm iibm case study solutions & multiple answers 1
 
Six Sigma Green Belt - Measures of which of the following provide attributes ...
Six Sigma Green Belt - Measures of which of the following provide attributes ...Six Sigma Green Belt - Measures of which of the following provide attributes ...
Six Sigma Green Belt - Measures of which of the following provide attributes ...
 
Six Sigma Green Belt - Which of the following is the most useful graphical to...
Six Sigma Green Belt - Which of the following is the most useful graphical to...Six Sigma Green Belt - Which of the following is the most useful graphical to...
Six Sigma Green Belt - Which of the following is the most useful graphical to...
 
Six Sigma Green Belt - Which of the following measures of dispersion is equal...
Six Sigma Green Belt - Which of the following measures of dispersion is equal...Six Sigma Green Belt - Which of the following measures of dispersion is equal...
Six Sigma Green Belt - Which of the following measures of dispersion is equal...
 
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...
Six Sigma Green Belt - If a distribution is normal, u=50 s=15, what percentag...
 
Six Sigma Green Belt - All of the following are common ways for people to re...
Six Sigma Green Belt -  All of the following are common ways for people to re...Six Sigma Green Belt -  All of the following are common ways for people to re...
Six Sigma Green Belt - All of the following are common ways for people to re...
 
Six Sigma Green Belt - A company’s accounts payable department is trying to r...
Six Sigma Green Belt - A company’s accounts payable department is trying to r...Six Sigma Green Belt - A company’s accounts payable department is trying to r...
Six Sigma Green Belt - A company’s accounts payable department is trying to r...
 
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...Six Sigma Green Belt - For a normal distribution, two standard deviation on e...
Six Sigma Green Belt - For a normal distribution, two standard deviation on e...
 
Six Sigma Green Belt - Which of the following type of tools or techniques is ...
Six Sigma Green Belt - Which of the following type of tools or techniques is ...Six Sigma Green Belt - Which of the following type of tools or techniques is ...
Six Sigma Green Belt - Which of the following type of tools or techniques is ...
 
Six Sigma Green Belt - Attribute and variable data are best described as whic...
Six Sigma Green Belt - Attribute and variable data are best described as whic...Six Sigma Green Belt - Attribute and variable data are best described as whic...
Six Sigma Green Belt - Attribute and variable data are best described as whic...
 
Six Sigma Green Belt - Which of the following is the best definition of a flo...
Six Sigma Green Belt - Which of the following is the best definition of a flo...Six Sigma Green Belt - Which of the following is the best definition of a flo...
Six Sigma Green Belt - Which of the following is the best definition of a flo...
 

Último

How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17Celine George
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...Nguyen Thanh Tu Collection
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsTechSoup
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...Nguyen Thanh Tu Collection
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxEsquimalt MFRC
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...pradhanghanshyam7136
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - Englishneillewis46
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxmarlenawright1
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfAdmir Softic
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxDenish Jangid
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptxMaritesTamaniVerdade
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Jisc
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxJisc
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseAnaAcapella
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfDr Vijay Vishwakarma
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...ZurliaSoop
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsMebane Rash
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentationcamerronhm
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxAreebaZafar22
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxRamakrishna Reddy Bijjam
 

Último (20)

How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
80 ĐỀ THI THỬ TUYỂN SINH TIẾNG ANH VÀO 10 SỞ GD – ĐT THÀNH PHỐ HỒ CHÍ MINH NĂ...
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptxHMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
HMCS Vancouver Pre-Deployment Brief - May 2024 (Web Version).pptx
 
Key note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdfKey note speaker Neum_Admir Softic_ENG.pdf
Key note speaker Neum_Admir Softic_ENG.pdf
 
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptxBasic Civil Engineering first year Notes- Chapter 4 Building.pptx
Basic Civil Engineering first year Notes- Chapter 4 Building.pptx
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)Accessible Digital Futures project (20/03/2024)
Accessible Digital Futures project (20/03/2024)
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
Spellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please PractiseSpellings Wk 3 English CAPS CARES Please Practise
Spellings Wk 3 English CAPS CARES Please Practise
 
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdfUnit 3 Emotional Intelligence and Spiritual Intelligence.pdf
Unit 3 Emotional Intelligence and Spiritual Intelligence.pdf
 
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
Jual Obat Aborsi Hongkong ( Asli No.1 ) 085657271886 Obat Penggugur Kandungan...
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
ICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptxICT Role in 21st Century Education & its Challenges.pptx
ICT Role in 21st Century Education & its Challenges.pptx
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 

Examination paper six sigma green belt & six sigma black belt

  • 1. Examination paper: Six Sigma Management IIBM Institute of Business Management 1 IIBM Institute of Business Management Examination Paper MM.100 Six Sigma Green Belt Section A: Objective Type (40 Marks) • This section consists of Multiple Choice questions. • Answer all the questions. • Each question carries 1 mark. Part One: Multiple Choices: 1. The primary purpose of a control chart is to: a. Set Specifications and tolerances b. Compare operations. c. Determine the stability of a process. d. Accept or reject a lot of material 2. When a control chart is used on a new process, capability can be assessed at which of the following times? a. Before the chart is first started b. After the first ten points are plotted c. When the plotted points hug the centerline d. After the process is shown to be in control 3. Precision is best described as: a. A comparison to a known standard b. The achievement of expected outgoing quality c. The repeated consistency of results d. The difference between an average measurement and the actual value 4. The overall ability of two or more operators to obtain consistent results repeatedly when measuring the same set of parts and using the same measuring equipment is the definition of: a. Repeatability b. Precision c. Reproducibility d. Accuracy 5. Which of the following conditions must be met for a process to be in a state of statistical control? a. Most of the product out by the process is in specification. b. All subgroup averages and rang are within control limits. c. All variation has been completely removed d. Previously optimal process settings are used.
  • 2. Examination paper: Six Sigma Management IIBM Institute of Business Management 2 6. Which of the following measures of dispersion is equal to the sum of deviations from the mean squared divided by the sample size? a. Range b. Standard deviation c. Variance d. Mode 7. An X and R chart is used to: a. Indicate process variation b. Specify design Limits c. Interpret costs d. Identify customer expectations 8. Which of the following is the most useful graphical tool for promoting and understanding the process of capability? a. A flowchart b. A histogram c. An affinity diagram d. An Ishikawa diagram 9. The type of chart that presents the value of items in descending order is a: a. Histogram b. Pareto chart c. U chart d. Cusum chart 10. Measures of which of the following provide attributes data? a. Temperature in degrees b. Attendance at meetings c. Weight in pounds d. Length in metric units 11. The fraction of nonconforming products is plotted on which of the following types of control chart? a. P chart b. U chart c. Np chart d. C chart 12. A cause and effect diagram is a useful tool for doing which of the following? a. Determining the flow of a process b. Detecting shifts in a process c. Developing theories based on symptoms d. Arranging theories by defect count 13. Which of the following statistics would best describe the central tendency of a sample of data? a. Mode b. Mean c. Standard deviation d. Range
  • 3. Examination paper: Six Sigma Management IIBM Institute of Business Management 3 14. Which of the following type of tools or techniques is considered qualitative? a. Histogram b. Frequency distributions c. Pareto chart d. Process observations 15. Out of the following which technique is most useful in narrowing issues and limiting discussion? a. Brainstorming b. Quality function deployment c. Cause and effect analysis d. Mutilating 16. In statistics, an estimation error that is persistent or systematic is called: a. Bias b. Sensitivity c. Random d. Shift 17. For a normal distribution, two standard deviation on each side of the mean would include what percentage of the total population: a. 47% b. 68% c. 95% d. 99% 18. If a distribution is normal, u=50 s=15, what percentage of data will be less than 30? a. 59.18% b. 40.82% c. 9.18% d. 1.33% 19. A company is receiving an unusually high number of returns from various customers. The first step in investigating the problem would be to a. Check the inspection records b. Establish the correlation of the returns to shipments c. Brainstorm the potential causes d. Classify the returns by type and degree of serious 20. Which of the following is the best definition of a flow chart? a. A diagram used to structure ideas into useful categories b. An illustration used to analyze variation in a process c. A picture used to separate steps of a process in sequential order d. An analytical tool used to clarify opposing aspects of a desired change 21. Which of the following activities would NOT contribute to the effective functioning of a team? a. Eliminating unnecessary activities b. Development team performance measures c. Defining process in detail d. Monitoring each member’s performance
  • 4. Examination paper: Six Sigma Management IIBM Institute of Business Management 4 22. What is the standard deviation of the population-10, 4, 16, 12, and 8? a. 4.00 b. 4.47 c. 16.00 d. 20.00 23. Which of the following tools would be most appropriate for collecting data to study the symptoms of a problem? a. Check sheet b. Flow diagram c. Force-field analysis d. Activity network diagram 24. Which of the following measures is a sufficient statistic for the parameter u? a. Median b. Mid-range c. Mean d. Mode 25. Positional, cyclical, and temporal variations are most commonly analyzed in: a. SPC charts b. Multi-vari charts c. Cause and effect diagram d. Run charts 26. Which of the following describes the deming method for continuous improvement? a. Cost of quality analysis b. Process map c. Tree Diagram d. Plan-do-check-act cycle 27. In analysis of variance, which of the following distribution is the basis for determining whether the variance estimates are all from the same population? a. Chi square b. Students c. Normal d. F 28. Which of the following statement best describes the set of value of a random variable? a. It is finite. b. It is an interval c. It can be discrete or continuous. d. It can be tracked by using control charts or scatter plots. 29. Which of the following is the best description of randomization? a. A technique used to increase the precision of an experiment b. A means of assuring representative sampling c. The repetition of an observation or measurement d. The relationship between two or more variables
  • 5. Examination paper: Six Sigma Management IIBM Institute of Business Management 5 30. When the order of items is not important, which of the following method is used to determine the number of sets and subsets of items? a. Combination b. Permutation c. Factorization d. Simulation 31. Scatter diagrams are best described as: a. Histograms. b. Correlation analysis. c. Pareto analysis. d. Ishikawa diagrams. 32. A __________ is created to determine customers of a specific process. a. Pareto chart b. Flow diagram c. Cause and effect diagram d. Scatter diagram 33. A production line uses signs at specific points on the line to indicate when components or raw materials need to be replenished. This practice is an example of: a. Kanban b. Poka-yake c. Checkpoints d. Hoshin 34. Which of the following is a good tool for planning cycle time reduction and concurrent operations? a. A timeline b. A Pareto diagram c. An X and R chart d. A PERT chart 35. Attribute and variable data are best described as which of the following? a. Counted values measured values b. Counted values visual features c. Measured values counted values d. Visual features counted values 36. All of the following are common ways for people to react to conflict except: a. Competing b. Collaborating c. Avoiding d. Sabotaging 37. A quality manager has chosen to survey customer satisfaction by taking samples based on the categories of frequency of use, categories of use, and demographic. This technique is known as a. Random sampling b. Data collection c. Stratification d. Customer classification
  • 6. Examination paper: Six Sigma Management IIBM Institute of Business Management 6 38. Which of the following actions is Not used to reduce process cycle time? a. Analyzing current processes b. Reducing queue times c. Setting priorities d. Implementing activity-based costing 39. A company’s accounts payable department is trying to reduce the time between receipt and payment of invoices and has recently completed a flowchart. Which of the following tool is the next to be used by them? a. Fishbone diagram b. Scatter diagram c. Box and whisker plat d. Histogram 40. In a manufacturing company, the machine shop is what kind of customer in relation to the Human Resource department? a. Intermediate b. Hidden c. External d. Internal Section B: Short Notes (30 Marks) • This section consists of Short Notes Questions. • Answer all the questions. • Each Question carries 6 marks. 1. Describe how QFD fits into the overall DFSS process. 2. What is interrelationship Digraph? Explain it with example. 3. Find the area under the standard normal curve between +1.50 standard deviations and +2.50 standard deviations. 4. Define terms related to One-Way ANOVA and interpret their results & data plots. 5. Define & describe the use of Rational Sub grouping. END OF SECTION A END OF SECTION B
  • 7. Examination paper: Six Sigma Management IIBM Institute of Business Management 7 Section C: Applied Theory (30 Marks) • This section consists of Applied Theory Questions. • Answer all the questions. • Each question carries 15 marks. • Detailed information should from the part of your answer (Word limit 200 to 250 words). 1. Suppose you are cooking steak for 100 people, & the current approval rating is 75% acceptable. You want to know the affect of different methods and approaches to see how the overall approval or “yield” is affected. By using the Full Factorial method explain how the overall approval or “yield” is affected. 2. Interpret Control Charts? Distinguish between common & special causes using rules for determining stastical control. END OF SECTION C
  • 8. Examination paper: Six Sigma Management IIBM Institute of Business Management 8 IIBM Institute of Business Management Examination Paper MM.100 Six Sigma Black Belt Section A: Objective Type (40 Marks) • This section consists of Multiple Choice questions. • Answer all the questions. • Part one questions carry 1 mark each & Part Two questions carry 2 marks each. Part One: Multiple Choices: 1. Calculate the estimated variance of the population from which the following values have been randomly selected: 2.8 2.7 2.6 2.9 2.8 2.8 2.8. a. 095 b. 009 c. 088 d. 008 2. The mean, median and mode of a distribution have the same value. What can be said about the distribution? a. It is exponential b. It is normal c. It is uniform d. None of the above 3. Approximately what percent of the data values are smaller than the mean? a. 25% b. 50% c. 75% d. None of above 4. A normal probability plot is used to: a. Determine whether the distribution is normal b. Plot Z value c. Determine process capability d. It percent out of specification 5. Nominal Group technique is used to: a. Help a group reach consensus b. Generate a group on new ides c. Provide a consistent stable group leadership d. Provide a name for the group
  • 9. Examination paper: Six Sigma Management IIBM Institute of Business Management 9 6. An example of a project metric would be: a. The decrease in defect occurrence b. The decrease in product cost c. The decrease in cycle time d. All the above 7. A correct statement about the relationship between the terms parameter and statistic is: a. A population statistic is more accurate than a parameter b. A sample parameter is used to estimate a statistic c. A sample statistic is used to estimate a population parameter d. Standard deviation calculation requires both statistics and parameters 8. A and B are events. P(A) = 0.80 and P(B) = 0.90: a. Events A and B are disjoint or mutually exclusive b. Events A and B are not disjoint or mutually exclusive c. P (A and B) = 0 d. P(A and B) = 1.7 9. In a certain sampling situation, a=0, b=0.08. the power of the sampling plan this case is: a. 0 b. 0.08 c. 1.00 d. 0.92 10. A newspaper article describes a high positive correlation between obesity and orange juice consumption among six-year-old children’s. Parents who restrict the use of orange juice for their children have: a. Made a type I error b. Made a type II error c. Misunderstood margin of error d. Confused correlation with causation 11. In an experimental design context, replications refer to: a. Duplicating experimental result at another location b. Repeating a test with the same factor levels c. Obtaining the same or similar result from different factors d. Repeating an experiment but using at least one different factor level 12. Find the upper control limit for a range chart if n=4 and the average range is 2.282. a. 2.282 b. 4.564 c. 5.208 d. 3.423 13. An x-bar control chart been established with control limits of 3.245 and 3.257, n=5. An engineer collects the following sample and plots the average on the control chart: 3.257, 3.256, 3.258, 3.259 a. The process is out of control b. The process is not out of control c. The engineer misused the control chart d. The control limits are incorrect
  • 10. Examination paper: Six Sigma Management IIBM Institute of Business Management 10 14. TEIZ is an acronym which refers to: a. A set of problem solving tools b. An organization of quality professionals c. An experiment using transitional results d. A Russian general responsible for creative thinking 15. A robust design is one which; a. Has high reliability b. Has low maintenance frequency c. Is simple to manufacture’ d. Is resistant to varying environmental condition 16. A frequent cause of system sub optimization is: a. Optimizing individual process b. Failing to draw a system flow chart c. Using data with outliers d. Failing to consider the normal distribution 17. The x2 distribution is: a. Symmetric b. Left skewed c. Right skewed d. Normal 18. An advantage of using standard deviation rather than range for measuring dispersion of a large sample is that: a. Standard deviation has a simpler formula b. Calculators have a standard deviation key but not a range Key c. Standard deviation uses information from each measurement d. Range calculation are not normally distributed 19. The team development stage characterized by expression of individual opinions and ideas often without regard for team objectives is known as: a. Performing b. Norming c. Conflicting d. Storming 20. SMED is an acronym for activity that: a. Involve housekeeping in the work area b. Makes mistake of a certain type impossible c. Emphasizes the pull of the customer d. Reduces set up the time 21. A principle advantage of fractional factorial experimental designs is: a. Reduced cost b. Improved accuracy c. Increased confounding d. Higher confidence level
  • 11. Examination paper: Six Sigma Management IIBM Institute of Business Management 11 22. Dr. W Edwards Deming: a. Lectured in Japan after World War II b. Was an author of several books in the US c. Is considered an expert in the quality field d. All of the above Part Two: 23. What percent of population falls below the lower specification limits? a. 9.18% b. 22.66% c. 6.68% d. 1.83% 24. Find the mean, median and mode of the following data set: 9, 11, 12, 14, 18, 18, 18, 20, and 23: a. 15.5, 18, 18 b. 15, 14, 18 c. 15, 12, 18 d. 15.5, 16, 18 Use for problems 25-27: A B Res. 25. Calculate the main effect of factor A: a. 20 b. 25 c. 30 d. None of the above 26. Calculate the interaction effect: a. 20 b. 25 c. 40 d. None of the above 27. If it is desirable to maximize the response R, the following levels should be used: a. A+ and B+ b. A+ and B- c. A- and B+ d. None of the above 1 - - 20 2 - + 30 3 + - 40 4 + + 50
  • 12. Examination paper: Six Sigma Management IIBM Institute of Business Management 12 Use for questions28-30: Here is an experimental design with result: A B C Responses 1 - - + 10 11 10 2 - + - 22 20 23 3 + + + 34 36 37 4 + - - 26 25 25 28. This experimental design is: a. Full factorial b. Half factorial c. Quarter factorial d. None of the above 29. The number of factors, levels and replications: a. 3, 3, 3 b. 3, 2, 2 c. 3, 2, 3 d. None of the above 30. An indication of the experimental error is available because the design has: a. Multiple replications b. Multiple levels c. Multiple factors d. None of the above 31. The average number of defects is 21.6. Find the upper control limit for the C-chart. a. 26.4 b. 24.6 c. 26.2 d. None of the above Section B: Short Notes (30 Marks) • This section consists of Short Notes Questions. • Answer all the questions. • Each Question carries 6 marks. 1. Briefly define Affinity Diagram with an example. 2. By using imaginary figures draw a Run Chart. END OF SECTION A
  • 13. Examination paper: Six Sigma Management IIBM Institute of Business Management 13 3. Consider the following data & develop a normal probability graph paper & normal probability plot: 7.9, 9.7, 10.6, 12.7, 12.8, 18.1, 21.2, 33.0, 43.5, 51.1, 81.4, 93.1 4. A painting process produces coatings with a thickness of 0.0005 & a standard deviation of 0.00002. What should the tolerance limits be for this process? Briefly explain Tolerance design? 5. What is Pugh matrix? State the steps which are used in Pugh matrix. Section C: Applied Theory (30 Marks) • This section consists of Applied Theory Questions. • Answer all the questions. • Each question carries 15 marks. • Detailed information should from the part of your answer (Word limit 200 to 250 words). 1. Define & describe the purpose of root cause analysis? Recognize the issues involved in identifying a root cause analysis and list various tools for resolving chronic problem? 2. Describe the purpose & elements of FMEA including risk priority number (RPN), and evaluate FMEA results for processes, products, & services. Distinguish between design FMEA (DFMEA) & process FMEA (PFMEA) and interpret results from each. - S-2-210311 END OF SECTION B END OF SECTION C