SlideShare uma empresa Scribd logo
1 de 42
Network Scheduling with Limited Resources
Introduction  ,[object Object],[object Object],[object Object],[object Object],[object Object]
Schedule  Graph  , Unlimited  Resources Labor available Project completion time  18 10 12 6 6 1
Let assume following constraint 10 labor available on any one day  Schedule  Graph , Resource  Limit  Of  10  Men  Cont.. 10 10 10 10 6 6 1
Complexity Of Project Scheduling With Limited Resource ,[object Object],[object Object],[object Object]
Heuristic Programs  ,[object Object],[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
Heuristic method for Resource Leveling of Project Schedule ,[object Object],[object Object],[object Object],[object Object]
Early start schedule  graph Manpower loading chart  Maximum slack 7 days so postpone activity 9  Peak requirement 24 Number  over  activity indicates the activity number as well  as  resource.
Schedule  Graph  Manpower loading  chart . Peak requirement reduce to 15  Cont..
Schedule  Graph  Manpower  Loading Chart  Activity 8 is delay by full slack of 2 days Peak requirement occur at days 1, 2  Cont..
Schedule  Graph  Manpower  Loading Chart. Best result obtain by delaying activity 3 by 2 days  Smoothen  histogram Cont..
Smoothing   Peak Resource Requirement
Heuristic Method for Resource Allocation in Project Scheduling ,[object Object],[object Object],[object Object],[object Object]
Day 1  - only one job 7 is available to start in this period and there  are  sufficient  men  to  schedule it. Schedule job 7 , 3 men remain available Only 10 men are available for the project on any day. Resource Day
Day 2-  Job 1,3,4,5 can be started on day 2 , but there are not enough men to schedule them Then second heuristic is applied for scheduling  the jobs with least slack first Schedule job 3( slack=0); 7 men remain Schedule job 4( slack=0); 3 men remain Schedule job 1( slack=3); 2 men remain Job 5 must be delayed , as there are just [2=10-(4+3+1)] men unassigned Postponed the job 5 ( slack =4) Cont..
Day 3-  continue job 3(slack =0); 7 men remain continue job 4(slack =0); 3men remain continue job 1(slack =3); 2men remain Postpone  job 5 (slack =3) Cont..
Day 4 Continue job 4 (slack =0); 6 men remain  Continue job 1 (slack =3); 5 men remain  Job 6  has no slack and hence  is critical , but only 5 men are  still unassigned  Then 3 rd   heuristic is  applied – job 1 could be postponed without  delaying  the project  Reschedule  job 1 ; 6 men remain  Schedule job 6 (slack =0); 0 men remain  Postpone Job 5 (slack =2) Cont..
Cont.. Day Manpower/ resource requirement
Day 5 Continue job 6 (slack=0); 4 men remain  Schedule Job 2 (slack =0); 2 men remain Schedule Job 1 ( slack = 0); 1 men remain  Postpone  job 5 (slack =1) Day 6  Continue Job 6 (slack =0); 4 Men remain . Continue Job 2 (slack =0); 2 Men remain . Continue Job 1 (slack =0); 1 Men remain . Postpone  job 5 (slack =0) Now job 5 is critical but no active job can be postponed without delaying project Cont..
Cont.. Day Manpower
Day 7  Continue Job 1 (slack =1); 9 Men remain  Schedule Job 5 ( slack =0); 4 Men remain  Postpone job 9 ( slack =1) Day 8 Continue Job 5 (slack =0); 5 men remain  Postpone job 9 (slack =0);  No noncritical job can be rescheduled Postpone  Job 8 (Slack =2) Day Manpower
Day 9–  Schedule job 9 ( slack =0); 1 man remain .  Postpone job 8 (slack =2) Day 10 –  Schedule job 10 ( slack =0);  no man remain. Postpone  Job 8 (slack =1) Day 11 – Continue  job 10 (slack =0); no men remain . Postpone Job 8 (slack =0)
Day 12— Continue job 10 (slack =1); no men remain  Postpone Job 8( slack =0) Day 13— Schedule  job 8 ( slack =0); 2 men remain Day 14 –  Continue job 8 ( slack = 0); 2 men remain  Cont.. Manpower Day Final schedule limited resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 7 7 7 10 9 9 6 6 9 10 10 10 8 8
Other Heuristic Approaches ,[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],Cont..
[object Object],[object Object],[object Object],[object Object],Cont..
Conceptual Problem of Critical Path Analysis When Resource Are Limited
Early start schedule Late Start schedule  Cont.. Day Resource Day Resource 1 2 3 4 5 18 10 10 8 7 1 2 3 4 5 4 4 5 18 22
If resources are limited up to 10 men then optimal early start schedule  and Late start schedule is as follows Early start schedule Day Resource 1 2 3 4 5 6 10  10 10 9 7 7
Late Start schedule  Day Resource 1 2 3 4 5 6 10 10 8 10 7 8
[object Object],[object Object],[object Object],[object Object],[object Object]
Conclusion ,[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],[object Object],Cont..
[object Object],[object Object],[object Object],[object Object],Cont..
Integer Programming Formulation – Project scheduling with limited Resource ,[object Object],[object Object],[object Object],[object Object],[object Object]
[object Object],[object Object],where k is some number such  that
[object Object],[object Object],[object Object],[object Object],[object Object],[object Object]
2 .  Job will be performed : 3. Capacity of shop will not be exceeded  4.No job will be started before its predecessors  are completed  d = 1,……,z  AND  j= 1,….,n  except  beginning job
5 .  No jobs will be split  :
 
 
 

Mais conteúdo relacionado

Mais procurados

Planning and scheduling
Planning and schedulingPlanning and scheduling
Planning and schedulingAbhishek Kumar
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesYousef Abugosh, PMP, MA
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Akaresh Jose Kaviyil JY
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpasyamputra
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSZulfiquer Ahmed Amin
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)anjalatchi
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance AnalysisAcumen
 
PMBOK Planning Process Group
PMBOK Planning Process GroupPMBOK Planning Process Group
PMBOK Planning Process GroupCurtis Tsang
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchartlearnt
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectMeryem Yıldız
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsSHAZEBALIKHAN1
 

Mais procurados (20)

Project management - CPM & PERT
Project management   - CPM & PERTProject management   - CPM & PERT
Project management - CPM & PERT
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
Resource management
Resource managementResource management
Resource management
 
Planning and scheduling
Planning and schedulingPlanning and scheduling
Planning and scheduling
 
ABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning SlidesABCs Of Project Time Management Planning Slides
ABCs Of Project Time Management Planning Slides
 
Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )Project Management Techniques ( CPM & PERT Techniques )
Project Management Techniques ( CPM & PERT Techniques )
 
Project management cpm-pert
Project management   cpm-pertProject management   cpm-pert
Project management cpm-pert
 
EpM
EpMEpM
EpM
 
FINAL REPORT
FINAL REPORTFINAL REPORT
FINAL REPORT
 
Syam critical path cpa
Syam critical path cpaSyam critical path cpa
Syam critical path cpa
 
PERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLSPERT-CPM : PROJECT MANAGEMENT TOOLS
PERT-CPM : PROJECT MANAGEMENT TOOLS
 
Unit v mha project evaluation review technique (pert)
Unit  v  mha project evaluation review technique (pert)Unit  v  mha project evaluation review technique (pert)
Unit v mha project evaluation review technique (pert)
 
Baseline Compliance Analysis
Baseline Compliance AnalysisBaseline Compliance Analysis
Baseline Compliance Analysis
 
CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6CAPM Week 2 Chapter 6
CAPM Week 2 Chapter 6
 
PMBOK Planning Process Group
PMBOK Planning Process GroupPMBOK Planning Process Group
PMBOK Planning Process Group
 
6.3 sequence activities
6.3 sequence activities6.3 sequence activities
6.3 sequence activities
 
PertGanttchart
PertGanttchartPertGanttchart
PertGanttchart
 
Project Management focused on Scheduling of a Project
Project Management focused on Scheduling of a ProjectProject Management focused on Scheduling of a Project
Project Management focused on Scheduling of a Project
 
How Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling FactorsHow Does MS Project Works 6- Task Controlling Factors
How Does MS Project Works 6- Task Controlling Factors
 
Project Scheduling
Project SchedulingProject Scheduling
Project Scheduling
 

Destaque (6)

Bar chart
Bar chartBar chart
Bar chart
 
Network scheduling
Network schedulingNetwork scheduling
Network scheduling
 
Pert
PertPert
Pert
 
Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)
Program Evaluation and Review Technique (PERT)
 
Jollibee food corporation
Jollibee food corporationJollibee food corporation
Jollibee food corporation
 
P E R T
P E R TP E R T
P E R T
 

Semelhante a Network scheduling with limited_resources- revised1

Resource Planning
Resource PlanningResource Planning
Resource PlanningWajahat Ali
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joeNASAPMC
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joeNASAPMC
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.pptTecnicoItca
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxstilliegeorgiana
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxannettsparrow
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxmamtabisht10
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?SHAZEBALIKHAN1
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcKhalid Noor Mohammed
 
Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time schedulingKamal Acharya
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagementDhamo daran
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling Nicola2903
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-seminiMaya
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentationNithin Dev
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)Dinesh Singh
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxrosemarybdodson23141
 

Semelhante a Network scheduling with limited_resources- revised1 (20)

Resource Planning
Resource PlanningResource Planning
Resource Planning
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Lukas.joe
Lukas.joeLukas.joe
Lukas.joe
 
Resource-Allocation.ppt
Resource-Allocation.pptResource-Allocation.ppt
Resource-Allocation.ppt
 
PMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docxPMGT 510Principles of Project ManagementGroup Assign.docx
PMGT 510Principles of Project ManagementGroup Assign.docx
 
Critical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docxCritical Path MethodIntroductionOnce you have the network diag.docx
Critical Path MethodIntroductionOnce you have the network diag.docx
 
Program_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptxProgram_Evaluation_and_Review_Technique.pptx
Program_Evaluation_and_Review_Technique.pptx
 
How to change working days and time in MS Project?
How to change working days and time in MS Project?How to change working days and time in MS Project?
How to change working days and time in MS Project?
 
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etcUnderstanding Microsoft Project 'Calendars' ‘Working Time’, etc
Understanding Microsoft Project 'Calendars' ‘Working Time’, etc
 
Approaches to real time scheduling
Approaches to real time schedulingApproaches to real time scheduling
Approaches to real time scheduling
 
06 projecttimemanagement
06 projecttimemanagement06 projecttimemanagement
06 projecttimemanagement
 
Resource Scheduling
Resource Scheduling  Resource Scheduling
Resource Scheduling
 
Pert Cpm Nis
Pert   Cpm NisPert   Cpm Nis
Pert Cpm Nis
 
Om chapter 14
Om chapter 14Om chapter 14
Om chapter 14
 
Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-Time --updated 60b084af4f5af-
Time --updated 60b084af4f5af-
 
Primavera presentation
Primavera presentationPrimavera presentation
Primavera presentation
 
Seminar on pert
Seminar on pertSeminar on pert
Seminar on pert
 
Ms Project 2007(Basic)
Ms Project 2007(Basic)Ms Project 2007(Basic)
Ms Project 2007(Basic)
 
Module :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levellingModule :-5 project scheduling and resource levelling
Module :-5 project scheduling and resource levelling
 
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docxMS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
MS Project - Lesson #4 - Working With CalendarsObjectives - MS.docx
 

Último

Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Krashi Coaching
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsanshu789521
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxheathfieldcps1
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxNirmalaLoungPoorunde1
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptxPoojaSen20
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Celine George
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxRoyAbrique
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesFatimaKhan178732
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAssociation for Project Management
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting DataJhengPantaleon
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 

Último (20)

TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Bikash Puri  Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Bikash Puri Delhi reach out to us at 🔝9953056974🔝
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
Kisan Call Centre - To harness potential of ICT in Agriculture by answer farm...
 
Presiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha electionsPresiding Officer Training module 2024 lok sabha elections
Presiding Officer Training module 2024 lok sabha elections
 
The basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptxThe basics of sentences session 2pptx copy.pptx
The basics of sentences session 2pptx copy.pptx
 
Employee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptxEmployee wellbeing at the workplace.pptx
Employee wellbeing at the workplace.pptx
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
PSYCHIATRIC History collection FORMAT.pptx
PSYCHIATRIC   History collection FORMAT.pptxPSYCHIATRIC   History collection FORMAT.pptx
PSYCHIATRIC History collection FORMAT.pptx
 
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
Incoming and Outgoing Shipments in 1 STEP Using Odoo 17
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptxContemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
Contemporary philippine arts from the regions_PPT_Module_12 [Autosaved] (1).pptx
 
Separation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and ActinidesSeparation of Lanthanides/ Lanthanides and Actinides
Separation of Lanthanides/ Lanthanides and Actinides
 
APM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across SectorsAPM Welcome, APM North West Network Conference, Synergies Across Sectors
APM Welcome, APM North West Network Conference, Synergies Across Sectors
 
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data_Math 4-Q4 Week 5.pptx Steps in Collecting Data
_Math 4-Q4 Week 5.pptx Steps in Collecting Data
 
MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 

Network scheduling with limited_resources- revised1

  • 1. Network Scheduling with Limited Resources
  • 2.
  • 3. Schedule Graph , Unlimited Resources Labor available Project completion time 18 10 12 6 6 1
  • 4. Let assume following constraint 10 labor available on any one day Schedule Graph , Resource Limit Of 10 Men Cont.. 10 10 10 10 6 6 1
  • 5.
  • 6.
  • 7.
  • 8. Early start schedule graph Manpower loading chart Maximum slack 7 days so postpone activity 9 Peak requirement 24 Number over activity indicates the activity number as well as resource.
  • 9. Schedule Graph Manpower loading chart . Peak requirement reduce to 15 Cont..
  • 10. Schedule Graph Manpower Loading Chart Activity 8 is delay by full slack of 2 days Peak requirement occur at days 1, 2 Cont..
  • 11. Schedule Graph Manpower Loading Chart. Best result obtain by delaying activity 3 by 2 days Smoothen histogram Cont..
  • 12. Smoothing Peak Resource Requirement
  • 13.
  • 14. Day 1 - only one job 7 is available to start in this period and there are sufficient men to schedule it. Schedule job 7 , 3 men remain available Only 10 men are available for the project on any day. Resource Day
  • 15. Day 2- Job 1,3,4,5 can be started on day 2 , but there are not enough men to schedule them Then second heuristic is applied for scheduling the jobs with least slack first Schedule job 3( slack=0); 7 men remain Schedule job 4( slack=0); 3 men remain Schedule job 1( slack=3); 2 men remain Job 5 must be delayed , as there are just [2=10-(4+3+1)] men unassigned Postponed the job 5 ( slack =4) Cont..
  • 16. Day 3- continue job 3(slack =0); 7 men remain continue job 4(slack =0); 3men remain continue job 1(slack =3); 2men remain Postpone job 5 (slack =3) Cont..
  • 17. Day 4 Continue job 4 (slack =0); 6 men remain Continue job 1 (slack =3); 5 men remain Job 6 has no slack and hence is critical , but only 5 men are still unassigned Then 3 rd heuristic is applied – job 1 could be postponed without delaying the project Reschedule job 1 ; 6 men remain Schedule job 6 (slack =0); 0 men remain Postpone Job 5 (slack =2) Cont..
  • 18. Cont.. Day Manpower/ resource requirement
  • 19. Day 5 Continue job 6 (slack=0); 4 men remain Schedule Job 2 (slack =0); 2 men remain Schedule Job 1 ( slack = 0); 1 men remain Postpone job 5 (slack =1) Day 6 Continue Job 6 (slack =0); 4 Men remain . Continue Job 2 (slack =0); 2 Men remain . Continue Job 1 (slack =0); 1 Men remain . Postpone job 5 (slack =0) Now job 5 is critical but no active job can be postponed without delaying project Cont..
  • 21. Day 7 Continue Job 1 (slack =1); 9 Men remain Schedule Job 5 ( slack =0); 4 Men remain Postpone job 9 ( slack =1) Day 8 Continue Job 5 (slack =0); 5 men remain Postpone job 9 (slack =0); No noncritical job can be rescheduled Postpone Job 8 (Slack =2) Day Manpower
  • 22. Day 9– Schedule job 9 ( slack =0); 1 man remain . Postpone job 8 (slack =2) Day 10 – Schedule job 10 ( slack =0); no man remain. Postpone Job 8 (slack =1) Day 11 – Continue job 10 (slack =0); no men remain . Postpone Job 8 (slack =0)
  • 23. Day 12— Continue job 10 (slack =1); no men remain Postpone Job 8( slack =0) Day 13— Schedule job 8 ( slack =0); 2 men remain Day 14 – Continue job 8 ( slack = 0); 2 men remain Cont.. Manpower Day Final schedule limited resource 1 2 3 4 5 6 7 8 9 10 11 12 13 14 7 7 7 10 9 9 6 6 9 10 10 10 8 8
  • 24.
  • 25.
  • 26.
  • 27. Conceptual Problem of Critical Path Analysis When Resource Are Limited
  • 28. Early start schedule Late Start schedule Cont.. Day Resource Day Resource 1 2 3 4 5 18 10 10 8 7 1 2 3 4 5 4 4 5 18 22
  • 29. If resources are limited up to 10 men then optimal early start schedule and Late start schedule is as follows Early start schedule Day Resource 1 2 3 4 5 6 10 10 10 9 7 7
  • 30. Late Start schedule Day Resource 1 2 3 4 5 6 10 10 8 10 7 8
  • 31.
  • 32.
  • 33.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. 2 . Job will be performed : 3. Capacity of shop will not be exceeded 4.No job will be started before its predecessors are completed d = 1,……,z AND j= 1,….,n except beginning job
  • 39. 5 . No jobs will be split :
  • 40.  
  • 41.  
  • 42.