3. Schedule Graph , Unlimited Resources Labor available Project completion time 18 10 12 6 6 1
4. Let assume following constraint 10 labor available on any one day Schedule Graph , Resource Limit Of 10 Men Cont.. 10 10 10 10 6 6 1
5.
6.
7.
8. Early start schedule graph Manpower loading chart Maximum slack 7 days so postpone activity 9 Peak requirement 24 Number over activity indicates the activity number as well as resource.
14. Day 1 - only one job 7 is available to start in this period and there are sufficient men to schedule it. Schedule job 7 , 3 men remain available Only 10 men are available for the project on any day. Resource Day
15. Day 2- Job 1,3,4,5 can be started on day 2 , but there are not enough men to schedule them Then second heuristic is applied for scheduling the jobs with least slack first Schedule job 3( slack=0); 7 men remain Schedule job 4( slack=0); 3 men remain Schedule job 1( slack=3); 2 men remain Job 5 must be delayed , as there are just [2=10-(4+3+1)] men unassigned Postponed the job 5 ( slack =4) Cont..
17. Day 4 Continue job 4 (slack =0); 6 men remain Continue job 1 (slack =3); 5 men remain Job 6 has no slack and hence is critical , but only 5 men are still unassigned Then 3 rd heuristic is applied – job 1 could be postponed without delaying the project Reschedule job 1 ; 6 men remain Schedule job 6 (slack =0); 0 men remain Postpone Job 5 (slack =2) Cont..
28. Early start schedule Late Start schedule Cont.. Day Resource Day Resource 1 2 3 4 5 18 10 10 8 7 1 2 3 4 5 4 4 5 18 22
29. If resources are limited up to 10 men then optimal early start schedule and Late start schedule is as follows Early start schedule Day Resource 1 2 3 4 5 6 10 10 10 9 7 7
38. 2 . Job will be performed : 3. Capacity of shop will not be exceeded 4.No job will be started before its predecessors are completed d = 1,……,z AND j= 1,….,n except beginning job