Mechanical 
Maintenance 
Depar tment - 
Balance of 
Power 
MMD-BOP
BALANCE OF PLANTS 
 Boi ler 
 Fuel Oi l Pump House 
 CW Pump House 
 Compressed Air System 
 Hydrogen Plant 
 Raw water pump house 
 DG Set 
MMD-BOP 2
BOILER 
74 meters long. 
two passes with platen super heaters. 
The boiler's four corners are designated as 
A,B,C,D for communication purpose
FIRST PASS 
At bottom, leftover ash eliminated from 
chimney and electrostatic precipitator (esp) is 
collected in bottom ash hopper 
collected ash mixed with water is sent to the 
ash water pond.
FIRST PASS 
From 22 metres to 37 meters the furnace is 
situated 
The furnace is divided into17 partitions 
designated as AA, A, AB, B, BC till HH from top 
to bottom. 
Partitions designated with single letters have 
inlets through which raw materials like coal, 
air, water and different oils are sent through. 
Oils are pumped using oil guns.
From 56metres to 74 the final super heaters 
exist along with platen heaters and roof 
heaters. 
There exist water walls all along the boiler. 
There exist soot blowers at particular height to 
blow the ash that is left over after combustion 
process
MMD-BOP 7
SECOND PASS 
 Contains the economiser, low temperature super heater, low 
temperature re-heater, air pre heater, force draf t fan, induced 
draf t fan and scanner fan. 
 The second pass focuses primarily on increasing ef ficiency.
WORKING OF A BOILER 
The boiler is initiated by firing light diesel oil 
(LDO) along with air and coal. 
LDO is pumped through the oil guns that are 
situated at the eight corners in a tangential 
direction. 
 LDO is used until the temperature reaches 400 
degrees Celsius after which high fluid oil (HFO) is 
used. 
The gases that are produced after combustion of 
coal are called flue gas which is used up in 
economizer and Pre-heaters
FIRST PASS 
The dam water enters through the economiser 
through feed pump. 
Gets pre heated in the economizer and enters the 
bottom ring header from where the water enters 
the spiral water walls in the boiler in pass 1. 
 The water walls heat the water and send them 
over to roof heater and then to low temperature 
super heater next to the platen heater and then 
to final super heater where most of it is 
converted to super critical fluid.
SECOND PASS 
This super critical fluid comes back to boiler 
to reheat through re-heater line. 
This liquid passes through the economiser in 
pass 2 then to low temperature re-heater 
Then back to final super heater
The soot blowers blow the ash with help of 
steam to the bottom ash hopper. 
The air preheater heats the secondary air 
along with primary air so that the efficiency is 
increased. Secondary air is used when there is 
excess need of air in the furnace. This 
secondary air is blown through force draft fan. 
The scanner fan present in the boiler is used 
to cool the sensors present in the boiler 
The induced draft fan is used to remove or 
suck the flue gas from the boiler
FUEL OIL SYSTEM 
 Providing Auxiliary Ignition Energy to coal -air mixture 
 Total Ignition Energy = Inherent Ignition Energy + Auxiliary 
Ignition Energy 
 When heat becomes stable, heat avai lable from combustion 
of coal exceeds Total Ignition Energy, no more Auxiliary 
Energy is required 
MMD-BOP 14
FUEL OIL HANDLING SYSTEM 
 Unloading through Unloading pumps. 
 Storing in Storage tanks. 
 Transferring to Day oi l Tanks 
MMD-BOP 15
TYPES OF OIL USED 
MMD-BOP 16
COOLING WATER SYSTEM 
 Circulate CW in condenser and condensing turbine exhaust 
system 
 Discharge valve is hydraulic operated 
 Discharge water used to cool motor windings 
MMD-BOP 17
CW PUMP SPECIFICATION 
 Manufacture KIRLOSKAR BROTHERS LIMITED 
 Pump type BHM135, Single stage, Sel f water lubr icat ing pump 
 Motor Rat ing 3600 KW 
 Speed 330 RPM (NOM) 
 Make WEG 
 Motor Weight 35300 KG 
 Pump Discharge 39825 M^3/HR 
 Total Head 26 M 
 Pump Ef f iciency 92 % 
 Pump Input 3049.73 KW 
 Type Three phase induct ion motor 
 Power 3600 kw 
 Speed 330 rpm 
 Frequency 50Hz 
 Duty S1 
 Vol tage 11kv 
 Cur rent 245.5 amp 
 Insulat ion class F 
 Ef f iciency 96( -2%) 
MMD-BOP 18

Mais conteúdo relacionado

Mais procurados

Mais procurados (20)

Steam Drum, Super Heater, Economizer, Air preheater-done by Samriddha shil
Steam Drum, Super Heater, Economizer, Air preheater-done by Samriddha shilSteam Drum, Super Heater, Economizer, Air preheater-done by Samriddha shil
Steam Drum, Super Heater, Economizer, Air preheater-done by Samriddha shil
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)
 
Power Generation and Steam power plant
Power Generation and Steam power plantPower Generation and Steam power plant
Power Generation and Steam power plant
 
Modern thermal power plant
Modern thermal power plantModern thermal power plant
Modern thermal power plant
 
Thermal Power Plant
Thermal Power PlantThermal Power Plant
Thermal Power Plant
 
Steam Power Plant
Steam Power PlantSteam Power Plant
Steam Power Plant
 
Industrial Traning at SSTPS ppt
Industrial Traning at SSTPS pptIndustrial Traning at SSTPS ppt
Industrial Traning at SSTPS ppt
 
Thermal power point
Thermal power pointThermal power point
Thermal power point
 
Feedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu VaidFeedwater heaters by Himanshu Vaid
Feedwater heaters by Himanshu Vaid
 
Steam Power Plants
Steam Power PlantsSteam Power Plants
Steam Power Plants
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Gas turbine
Gas turbine Gas turbine
Gas turbine
 
Report on Boilers at NTPC Ramagunadam
Report on  Boilers at NTPC RamagunadamReport on  Boilers at NTPC Ramagunadam
Report on Boilers at NTPC Ramagunadam
 
BOILER INSTRUMENTATION
BOILER INSTRUMENTATIONBOILER INSTRUMENTATION
BOILER INSTRUMENTATION
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Heat recovery steam generator
Heat recovery steam generatorHeat recovery steam generator
Heat recovery steam generator
 
Feed Water Heater - SNIST
Feed Water Heater - SNISTFeed Water Heater - SNIST
Feed Water Heater - SNIST
 
Closed feed water heaters :)
Closed feed water heaters :)Closed feed water heaters :)
Closed feed water heaters :)
 
Gas turbine
Gas turbineGas turbine
Gas turbine
 
Renewable energy sources
Renewable energy sources Renewable energy sources
Renewable energy sources
 

Destaque

Prashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs finalPrashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs final
prashant rai
 
Mechanical Maintenance & Operation Engineer
Mechanical Maintenance & Operation EngineerMechanical Maintenance & Operation Engineer
Mechanical Maintenance & Operation Engineer
Mazahar Nawaz Shaliban
 
PM Outsource Vs. Inhouse Final 2.14.11
PM Outsource Vs. Inhouse Final 2.14.11PM Outsource Vs. Inhouse Final 2.14.11
PM Outsource Vs. Inhouse Final 2.14.11
kkosin
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
Rajeev Sharan
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
Rajeev Sharan
 
Facility engineering and Maintenance
Facility engineering and MaintenanceFacility engineering and Maintenance
Facility engineering and Maintenance
Pat Cabangis
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenance
SHIVAJI CHOUDHURY
 
Building maintenance management in malaysia
Building maintenance management in malaysiaBuilding maintenance management in malaysia
Building maintenance management in malaysia
Nur Zakaria
 

Destaque (20)

Laser Preventive Maintenace Training
Laser Preventive Maintenace TrainingLaser Preventive Maintenace Training
Laser Preventive Maintenace Training
 
Prashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs finalPrashant_rai_Mech8 yrs final
Prashant_rai_Mech8 yrs final
 
Sealcare Brochure
Sealcare BrochureSealcare Brochure
Sealcare Brochure
 
Vietnam Laser Alignment
Vietnam Laser Alignment Vietnam Laser Alignment
Vietnam Laser Alignment
 
Mechanical Maintenance & Operation Engineer
Mechanical Maintenance & Operation EngineerMechanical Maintenance & Operation Engineer
Mechanical Maintenance & Operation Engineer
 
PM Outsource Vs. Inhouse Final 2.14.11
PM Outsource Vs. Inhouse Final 2.14.11PM Outsource Vs. Inhouse Final 2.14.11
PM Outsource Vs. Inhouse Final 2.14.11
 
Lapping Machine Process and Application
Lapping Machine Process and ApplicationLapping Machine Process and Application
Lapping Machine Process and Application
 
Comparing In-House vs Outsourced IT Services
Comparing In-House vs Outsourced IT ServicesComparing In-House vs Outsourced IT Services
Comparing In-House vs Outsourced IT Services
 
Bearing 2016
Bearing 2016 Bearing 2016
Bearing 2016
 
Energy saving and pollution control in urea plant though prilling tower and o...
Energy saving and pollution control in urea plant though prilling tower and o...Energy saving and pollution control in urea plant though prilling tower and o...
Energy saving and pollution control in urea plant though prilling tower and o...
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Maintenance management
Maintenance managementMaintenance management
Maintenance management
 
Indian oil corporation limited ppt of mechanical engineering
Indian oil corporation limited ppt of mechanical engineeringIndian oil corporation limited ppt of mechanical engineering
Indian oil corporation limited ppt of mechanical engineering
 
Material technology
Material technologyMaterial technology
Material technology
 
sealing system for rotating shafts ( mechanical seals and packing )
sealing system for rotating shafts ( mechanical seals and packing )sealing system for rotating shafts ( mechanical seals and packing )
sealing system for rotating shafts ( mechanical seals and packing )
 
Iocl barauni presentation ppt.
Iocl barauni presentation ppt.Iocl barauni presentation ppt.
Iocl barauni presentation ppt.
 
Facility engineering and Maintenance
Facility engineering and MaintenanceFacility engineering and Maintenance
Facility engineering and Maintenance
 
Reliability centred maintenance
Reliability centred maintenanceReliability centred maintenance
Reliability centred maintenance
 
Building maintenance management in malaysia
Building maintenance management in malaysiaBuilding maintenance management in malaysia
Building maintenance management in malaysia
 
A powerpoint presentation on Building maintanance
A powerpoint presentation on Building maintananceA powerpoint presentation on Building maintanance
A powerpoint presentation on Building maintanance
 

Semelhante a Mechanical Maintenance Department-Balance of Power, Adani Power

Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
arvind singh rathore
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
Preeti Pradhan
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
arvind singh rathore
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, Haryana
Eesha Gupta
 

Semelhante a Mechanical Maintenance Department-Balance of Power, Adani Power (20)

PANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANTPANIPAT THERMAL POWER PLANT
PANIPAT THERMAL POWER PLANT
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
Power Plant Engg.pdf
Power Plant Engg.pdfPower Plant Engg.pdf
Power Plant Engg.pdf
 
Coal Base Thermal Power Plant
Coal Base Thermal Power PlantCoal Base Thermal Power Plant
Coal Base Thermal Power Plant
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Panipat thermal power station training ppt
Panipat thermal power station training pptPanipat thermal power station training ppt
Panipat thermal power station training ppt
 
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
SUMMER INTERNSHIP(INDUSTRAIL REPORT) ON THERMAL POWER PLANT
 
Kota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUKota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTU
 
Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01Thermalpowerpoint 130818150844-phpapp01
Thermalpowerpoint 130818150844-phpapp01
 
THERMAL
THERMALTHERMAL
THERMAL
 
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
Thermal Power Plant - Full Detail About Plant and Parts (Also Contain Animate...
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
 
Industrial training at NTPC Shaktinagar
Industrial training at NTPC ShaktinagarIndustrial training at NTPC Shaktinagar
Industrial training at NTPC Shaktinagar
 
training report
training reporttraining report
training report
 
Thermal power plant
Thermal power plantThermal power plant
Thermal power plant
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
BOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptxBOILER OPERATION PPT.pptx
BOILER OPERATION PPT.pptx
 
Thermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, HaryanaThermal power plant Khedr, Hisar, Haryana
Thermal power plant Khedr, Hisar, Haryana
 

Mais de Nemish Kanwar

Mais de Nemish Kanwar (12)

Jd harvesting from custom URLs
Jd harvesting from custom URLsJd harvesting from custom URLs
Jd harvesting from custom URLs
 
Face verification and recognition
Face verification and recognitionFace verification and recognition
Face verification and recognition
 
Optimization of Air Preheater for compactness of shell by evaluating performa...
Optimization of Air Preheater for compactness of shell by evaluating performa...Optimization of Air Preheater for compactness of shell by evaluating performa...
Optimization of Air Preheater for compactness of shell by evaluating performa...
 
Mems vibratory gyroscope simulation and sensitivity analysis kanwar 2015
Mems vibratory gyroscope simulation and sensitivity analysis kanwar 2015Mems vibratory gyroscope simulation and sensitivity analysis kanwar 2015
Mems vibratory gyroscope simulation and sensitivity analysis kanwar 2015
 
Study and simulation of gait cycle of a planar five link kanwar et al. 2015
Study and simulation of gait cycle of a planar five link kanwar et al. 2015Study and simulation of gait cycle of a planar five link kanwar et al. 2015
Study and simulation of gait cycle of a planar five link kanwar et al. 2015
 
Adani Power, Tirora- Project Report
Adani Power, Tirora- Project ReportAdani Power, Tirora- Project Report
Adani Power, Tirora- Project Report
 
Adani power Practice School
Adani power Practice SchoolAdani power Practice School
Adani power Practice School
 
MEMS Pressure difference based Gyroscope
MEMS Pressure difference based GyroscopeMEMS Pressure difference based Gyroscope
MEMS Pressure difference based Gyroscope
 
Prodtfinal1
Prodtfinal1Prodtfinal1
Prodtfinal1
 
Haldiram's
Haldiram'sHaldiram's
Haldiram's
 
Haldiram's Operation Research
Haldiram's Operation ResearchHaldiram's Operation Research
Haldiram's Operation Research
 
Mems gyroscope
Mems gyroscopeMems gyroscope
Mems gyroscope
 

Último

FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
MsecMca
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 

Último (20)

University management System project report..pdf
University management System project report..pdfUniversity management System project report..pdf
University management System project report..pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Netaji Nagar, Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Ankleshwar 7001035870 Whatsapp Number, 24/07 Booking
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...Top Rated  Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
Top Rated Pune Call Girls Budhwar Peth ⟟ 6297143586 ⟟ Call Me For Genuine Se...
 
notes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.pptnotes on Evolution Of Analytic Scalability.ppt
notes on Evolution Of Analytic Scalability.ppt
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort ServiceCall Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
Call Girls in Ramesh Nagar Delhi 💯 Call Us 🔝9953056974 🔝 Escort Service
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
Unit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdfUnit 1 - Soil Classification and Compaction.pdf
Unit 1 - Soil Classification and Compaction.pdf
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...Bhosari ( Call Girls ) Pune  6297143586  Hot Model With Sexy Bhabi Ready For ...
Bhosari ( Call Girls ) Pune 6297143586 Hot Model With Sexy Bhabi Ready For ...
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
chapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineeringchapter 5.pptx: drainage and irrigation engineering
chapter 5.pptx: drainage and irrigation engineering
 

Mechanical Maintenance Department-Balance of Power, Adani Power

  • 1. Mechanical Maintenance Depar tment - Balance of Power MMD-BOP
  • 2. BALANCE OF PLANTS  Boi ler  Fuel Oi l Pump House  CW Pump House  Compressed Air System  Hydrogen Plant  Raw water pump house  DG Set MMD-BOP 2
  • 3. BOILER 74 meters long. two passes with platen super heaters. The boiler's four corners are designated as A,B,C,D for communication purpose
  • 4. FIRST PASS At bottom, leftover ash eliminated from chimney and electrostatic precipitator (esp) is collected in bottom ash hopper collected ash mixed with water is sent to the ash water pond.
  • 5. FIRST PASS From 22 metres to 37 meters the furnace is situated The furnace is divided into17 partitions designated as AA, A, AB, B, BC till HH from top to bottom. Partitions designated with single letters have inlets through which raw materials like coal, air, water and different oils are sent through. Oils are pumped using oil guns.
  • 6. From 56metres to 74 the final super heaters exist along with platen heaters and roof heaters. There exist water walls all along the boiler. There exist soot blowers at particular height to blow the ash that is left over after combustion process
  • 8. SECOND PASS  Contains the economiser, low temperature super heater, low temperature re-heater, air pre heater, force draf t fan, induced draf t fan and scanner fan.  The second pass focuses primarily on increasing ef ficiency.
  • 9. WORKING OF A BOILER The boiler is initiated by firing light diesel oil (LDO) along with air and coal. LDO is pumped through the oil guns that are situated at the eight corners in a tangential direction.  LDO is used until the temperature reaches 400 degrees Celsius after which high fluid oil (HFO) is used. The gases that are produced after combustion of coal are called flue gas which is used up in economizer and Pre-heaters
  • 10. FIRST PASS The dam water enters through the economiser through feed pump. Gets pre heated in the economizer and enters the bottom ring header from where the water enters the spiral water walls in the boiler in pass 1.  The water walls heat the water and send them over to roof heater and then to low temperature super heater next to the platen heater and then to final super heater where most of it is converted to super critical fluid.
  • 11. SECOND PASS This super critical fluid comes back to boiler to reheat through re-heater line. This liquid passes through the economiser in pass 2 then to low temperature re-heater Then back to final super heater
  • 12. The soot blowers blow the ash with help of steam to the bottom ash hopper. The air preheater heats the secondary air along with primary air so that the efficiency is increased. Secondary air is used when there is excess need of air in the furnace. This secondary air is blown through force draft fan. The scanner fan present in the boiler is used to cool the sensors present in the boiler The induced draft fan is used to remove or suck the flue gas from the boiler
  • 13.
  • 14. FUEL OIL SYSTEM  Providing Auxiliary Ignition Energy to coal -air mixture  Total Ignition Energy = Inherent Ignition Energy + Auxiliary Ignition Energy  When heat becomes stable, heat avai lable from combustion of coal exceeds Total Ignition Energy, no more Auxiliary Energy is required MMD-BOP 14
  • 15. FUEL OIL HANDLING SYSTEM  Unloading through Unloading pumps.  Storing in Storage tanks.  Transferring to Day oi l Tanks MMD-BOP 15
  • 16. TYPES OF OIL USED MMD-BOP 16
  • 17. COOLING WATER SYSTEM  Circulate CW in condenser and condensing turbine exhaust system  Discharge valve is hydraulic operated  Discharge water used to cool motor windings MMD-BOP 17
  • 18. CW PUMP SPECIFICATION  Manufacture KIRLOSKAR BROTHERS LIMITED  Pump type BHM135, Single stage, Sel f water lubr icat ing pump  Motor Rat ing 3600 KW  Speed 330 RPM (NOM)  Make WEG  Motor Weight 35300 KG  Pump Discharge 39825 M^3/HR  Total Head 26 M  Pump Ef f iciency 92 %  Pump Input 3049.73 KW  Type Three phase induct ion motor  Power 3600 kw  Speed 330 rpm  Frequency 50Hz  Duty S1  Vol tage 11kv  Cur rent 245.5 amp  Insulat ion class F  Ef f iciency 96( -2%) MMD-BOP 18

Notas do Editor

  1. The boiler at Adani power Maharashtra limited is 74 meters long. It has two passes with platen super heaters. The boiler's four corners are designated as A,B,C,D for communication purpose if there is any maintenance to be done at any particular corner.
  2. In pass 1 at the bottom is a bottom ash hopper which collects leftover ash in the boiler after most of it is eliminated from chimney and electrostatic precipitator (esp). The collected ash mixed with water is sent to the ash water pond.
  3. the furnace is situated from 22 metres to 37 meters . The furnace has been divided into17 partitions. These 17 partitions are designated as AA, A, AB, B, BC till HH from top to bottom. The partitions designated with single letters have inlets through which raw materials like coal, air, water and different oils are sent through. Oils are pumped using oil guns.
  4. the final super heaters exist From 56 to 74metres along with platen heaters and roof heaters. In pass 1 there exist water walls all along the boiler. There exist soot blowers at particular height to blow the ash that is left over after combustion process
  5. Pass 2 contains the economiser, low temperature super heater, low temperature re-heater, air pre heater, force draft fan, induced draft fan and scanner fan. The second pass focuses primarily on increasing efficiency.
  6. The boiler is initiated by firing light diesel oil (LDO) along with air and coal. LDO is pumped through the oil guns that are situated at the eight corners in a tangential direction which makes a spherical fire ball at the center of the furnace. LDO is used until the temperature reaches 400 degrees Celsius after which high fluid oil (HFO) is used. HFO has high calorific value which helps the coal burn in the furnace. The gases that are produced after combustion of coal are called flue gas which contains mostly greenhouse gases.
  7. The dam water enters through the economizer through feed pump. The water gets pre heated in the economizer (by the heat of the flue gases) and enters the bottom ring header from where the water enters the spiral water walls in the boiler in pass 1. The water walls heat the water and send them over to roof heater and then to low temperature super heater next to the platen heater and then to final super heater where most of it is converted to super critical fluid.
  8. This super critical fluid after passing through high pressure heater then comes back to boiler to reheat through re-heater line. This liquid passes through the economizer in pass 2 then to low temperature re-heater then back to final super heater then again to turbine.
  9. The soot blowers blow the ash with help of steam to the bottom ash hopper. The air preheater heats the secondary air along with primary air so that the efficiency is increased. Secondary air is used when there is excess need of air in the furnace. This secondary air is blown through force draft fan. The scanner fan present in the boiler is used to cool the sensors present in the boiler The induced draft fan is used to remove or suck the flue gas from the boiler