SlideShare a Scribd company logo
1 of 16
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
PROJECT COST MANAGEMENT
 Make sure the project can be completed within the
approved budget.
 There are 4 processes
 Plan Cost Management
 Estimate Cost
 Determine Budget
 Control Cost
 Notes:
 Different stakeholders -> different ways to manage cost
 primarily concerned with the cost of the resources
needed to complete project activities
1
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
7.1 PLAN COST MANAGEMENT
is the process that establishes the policies, procedures,
and documentation for planning, managing, expending,
and controlling project costs.
2
Inputs Tool&Techniques Outputs
.Project management plan
.Project charter
.EEF
.OPA
.Expert Judment
.Analytical techniques
.Meetings
.Cost management plan
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
7.2 ESTIMATE COST
Is the process of developing approximation of the
monetary resources needed to complete project
activities
3
Inputs Tool&Techniques Outputs
.Cost management plan
.Human resource
management plan
.Scope baseline
.Project schedule
.Risk register
.Enterprise environmental
factors
.Organizational process
assets
.Expert judgment
.Analogous estimating
.Parametric estimating
.Bottom-up estimating
.Three-point estimating
.Reserve analysis
.Cost of quality
.Project management
software
.Vendor bid analysis
.Group decision-making
techniques
.Activity cost estimates
.Basis of estimates
.Project documents
updates
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
TYPE OF COSTS
 Variable Costs
 Change with the amount of production/work
 e.g. material, supplies, wages
 Fixed Costs
 Do not change as production change
 e.g. set-up, rental
 Direct Costs
 Directly attributable to the work of project
 e.g. team travel, recognition, team wages
 Indirect Costs
 Not directly indentifiable, related to project product
 e.g. taxes, fringe benefit
 Sunk Costs:
 is the cost that has already been incurred, and there is no way to
recover this cost.
4
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
QUALITY/ACCURACY OF COST ESTIMATION
5
• Most difficult to estimate as very little project info
is available, made during initiating process
Estimate Accuracy
Rough Order
of Magnitude
(ROM)
+/- 50%
Budget
Estimate
-10%
+25%
Definitive
Estimate
-5%
10%
• Used to finalize the Request for Authorization
(RFA), and establish commitment, made during
planning phase
• During the project and refined
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
7.3 DETERMINE BUDGET
is the process of aggregating the estimated costs of
individual activities or work packages to establish an
authorized cost baseline
6
Inputs Tool&Techniques Outputs
.Cost management plan
.Scope baseline
.Activity cost estimates
.Basis of estimates
.Project schedule
.Resource calendars
.Risk register
.Aggreements
.EEF
.OPA
.Cost aggregation
.Reserse Analysis
.Expert Judment
.Historical relationships
.Funding limit reconciliation
.Cost baseline
.Project funding
requirements
.Project documents
updates
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
MANAGEMENT RESERVE, CONTIGENCY RESERVE
 Contingency reserves: the cost impacts of the remaining risk
 Management reserves: extra fund to cover unforeseen risk or
changes to the project
7
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
COST BASELINE
 is the approved version of the time-phased project budget,
excluding any management reserves,
 only be changed through formal change control procedures and
 is used as a basis for comparison to actual results.
8
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
7.4 CONTROL COST
is the process of monitoring the status of the project to
update the project costs and managing changes to the
cost baseline.
9
Inputs Tool&Techniques Outputs
.Project management plan
. Project funding
requirements
.Work performance data
.OPA
.Earned value management
.Forcasting
.To-complete performance
index (TCPI)
.Performance reviews
.Project management
software
.Reserse Analysis
.Work performance
information
.Cost forecast
.Change requests
.Project management plan
updates
.Project documents
updates
.OPA updates
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
EARNED VALUE MANAGEMENT
 Method to measure project performance against scope, schedule
and cost baseline (performance measurement baseline)
 Importance measurement informations:
 Cost Variance (CV)
 Schedule Variance (SV)
 Cost Performance Index (CPI)
 Schedule Performance Index (SPI)
10
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
EARNED VALUE TECHNIQUE
11
Terms and Formulas Definition
Earned Value (EV) As of today, what is the estimated value of the
work actually accomplished?
Actual Cost (AC) As of today, what is the actual cost incurred for
the work accomplished?
Planned Value (PV) As of today, what is the estimated value of work
planned to be done?
Cost Variance (CV)
= EV - AC
Negative is over budget
Positive is under budget
Schedule Variance (SV)
= EV - PV
Negative is behind schedule
Positive is ahead schedule
Cost Performance Index
(CPI) = EV/AC
We are getting $__ worth of work out of every
$1 spent. Are funds being used efficiently?
Schedule Performance
Index (SPI) = EV/PV
We are (only) progressing at __ percent of the
rate originally planed
Example
$100K
$200K
$300K
$100K – $200K
= ($100K)
$100K - $300K
= ($200K)
$100K/$200K
= 0.5 i.e. 50%
$100K/$300K
= 0.33 i.e 33%
Example:
Project Budget: $400K
Project Schedule: 4
months
At the 3 month
checkpoint:
Spent: $200K
Work completed: $100K
Revised Total Duration Baseline Duration/Schedule Performance Index
4/0.33
= 12 months
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
EARNED VALUE TECHNIQUE (CON’T)
12
Terms and Formulas Definition
Budget at completion (BAC) How much did we BUDGET for the TOTAL project effort?
Estimate at Completion (EAC)
= BAC / CPI
What do we currently expect the TOTAL project cost (a
forecast)?
Estimate to Complete (ETC)
= EAC - AC
From this point on, how much MORE do we expect it to cost to
finish the project (a forecast)?
Variance at Completion (VAC)
= BAC – EAC
As of today, how much over or under budget do we expect to
be at the end of the project?
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
EXAMPLE OF EVM
13
TIME
COST
Schedule
Variance
(SV)
Cost
Variance
(CV)
ACTUAL
PLAN
EARN
VALUE
Estimate at
Completion
(EAC)
Budget at
Completion
(BAC)
Projection of
schedule delay
at completion
Projection of
cost variance
at completion
(VAC)
TODAY
(Reporting day)
BAC
EAC
AC
EV
PV
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
EXAMPLE OF EVM
14
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
TO-COMPLETE PERFORMANCE INDEX (TCPI)
 Helps the team determine the efficiency that
must be achieved on the remaining work for a
project to meet a specified endpoint, such as
BAC or the team’s revised EAC
 TCPI
15
AC)-(EACor– AC)(BACRemainingFunds
EV)–(BACRemainingWork
SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013
REVIEW
 Project cost management?
 4 processes of time management?
 Plan Cost Management
 Estimate Cost
 Determine Budget
 Control Cost
 Type of costs?
 Quality/Accuracy of Cost Estimation?
 Management reserve?
 Contigency reserve?
 Cost baseline?
 CV?
 SV?
 CPI?
 SPI?
 BAC?
 EAC?
 ETC?
 VAC?
 TCPI?
16

More Related Content

What's hot

Smsvn pmp training_slides_chapter_2
Smsvn pmp training_slides_chapter_2Smsvn pmp training_slides_chapter_2
Smsvn pmp training_slides_chapter_2Nam Trung
 
Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Nam Trung
 
Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Nam Trung
 
Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...mohamed mostafa
 
Introduction to PMP Brief Presentation
Introduction to PMP Brief PresentationIntroduction to PMP Brief Presentation
Introduction to PMP Brief Presentationjamilireifij
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance StructureSaurabh Sardesai
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Edureka!
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questionszohaibqadir
 
Maintaining PMP Credential
Maintaining PMP CredentialMaintaining PMP Credential
Maintaining PMP Credentialpritamdutt
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...Shamil Habet
 
How do I get a PMP Certification in 2021?
How do I get a PMP Certification in 2021?How do I get a PMP Certification in 2021?
How do I get a PMP Certification in 2021?Sprintzeal
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionMnbianchi
 

What's hot (20)

Smsvn pmp training_slides_chapter_2
Smsvn pmp training_slides_chapter_2Smsvn pmp training_slides_chapter_2
Smsvn pmp training_slides_chapter_2
 
Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3Smsvn pmp training_slides_chapter_3
Smsvn pmp training_slides_chapter_3
 
Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1Smsvn pmp training_slides_chapter_1
Smsvn pmp training_slides_chapter_1
 
Pmp study-notes
Pmp study-notesPmp study-notes
Pmp study-notes
 
Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...Green pmp exam prep questions answers explanations 2013 edition by christophe...
Green pmp exam prep questions answers explanations 2013 edition by christophe...
 
Introduction to PMP Brief Presentation
Introduction to PMP Brief PresentationIntroduction to PMP Brief Presentation
Introduction to PMP Brief Presentation
 
PMP Exam Prep Plus: Why E-Learning?
PMP Exam Prep Plus: Why E-Learning?PMP Exam Prep Plus: Why E-Learning?
PMP Exam Prep Plus: Why E-Learning?
 
Pmi rmp-2020 - v6
Pmi rmp-2020 - v6Pmi rmp-2020 - v6
Pmi rmp-2020 - v6
 
Sample PMP Exam Questions
Sample PMP Exam QuestionsSample PMP Exam Questions
Sample PMP Exam Questions
 
PMP integration review
PMP integration reviewPMP integration review
PMP integration review
 
Program governance Structure
Program governance StructureProgram governance Structure
Program governance Structure
 
PMP Study Guides
PMP Study GuidesPMP Study Guides
PMP Study Guides
 
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
Project Management Tools & Techniques | PMP® Training Videos | Project Manage...
 
PMP Exam Notes
PMP Exam NotesPMP Exam Notes
PMP Exam Notes
 
175 PMP Sample Questions
175 PMP Sample Questions175 PMP Sample Questions
175 PMP Sample Questions
 
Maintaining PMP Credential
Maintaining PMP CredentialMaintaining PMP Credential
Maintaining PMP Credential
 
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...PMP Chapter 2 of 6  Initiating Process Group (2- Processes) (Based on PMBOK 6...
PMP Chapter 2 of 6 Initiating Process Group (2- Processes) (Based on PMBOK 6...
 
How do I get a PMP Certification in 2021?
How do I get a PMP Certification in 2021?How do I get a PMP Certification in 2021?
How do I get a PMP Certification in 2021?
 
Instructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th EditionInstructor Slides - PMP/CAPM PMBOK 6th Edition
Instructor Slides - PMP/CAPM PMBOK 6th Edition
 
PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4PMP Exam Sample Questions Set 4
PMP Exam Sample Questions Set 4
 

Viewers also liked

Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflictsNam Trung
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Highmark Health
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterYudha Pratama, PMP
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Jeremy Jay Lim
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1Craig Brown
 
Integration Management Presentation
Integration Management Presentation Integration Management Presentation
Integration Management Presentation TDAKINS319
 
Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 JMBOKAcademy
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk managementPMC Mentor
 
Smsvn quality attitude
Smsvn quality attitudeSmsvn quality attitude
Smsvn quality attitudeNam Trung
 
Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Imran Jamil
 

Viewers also liked (12)

Smsvn conflicts
Smsvn conflictsSmsvn conflicts
Smsvn conflicts
 
Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3Project Management Class ( based on PMBOK) - Day 3
Project Management Class ( based on PMBOK) - Day 3
 
Pmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charterPmp – pmbok 5th edition develop project charter
Pmp – pmbok 5th edition develop project charter
 
Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)Project Management Concepts (from PMBOK 5th Ed)
Project Management Concepts (from PMBOK 5th Ed)
 
The Project Management Process - Week 1
The Project Management Process -  Week 1The Project Management Process -  Week 1
The Project Management Process - Week 1
 
Project management
Project managementProject management
Project management
 
Integration Management Presentation
Integration Management Presentation Integration Management Presentation
Integration Management Presentation
 
Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1 Project Management: Initiating Process Group - Lesson 1
Project Management: Initiating Process Group - Lesson 1
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Step by step guide on project risk management
Step by step guide on project risk managementStep by step guide on project risk management
Step by step guide on project risk management
 
Smsvn quality attitude
Smsvn quality attitudeSmsvn quality attitude
Smsvn quality attitude
 
Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...Term paper - impact of organizational culture on enterprise risk management (...
Term paper - impact of organizational culture on enterprise risk management (...
 

Similar to PMP Chapter 7 Cost Management

PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync
 
8.project cost management
8.project cost management8.project cost management
8.project cost managementChanwit Julrod
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Glen Alleman
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagementDhamo daran
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...IJERA Editor
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-controleidalin95
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Shuchi Joshi
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1reddvise
 
Sorge.les
Sorge.lesSorge.les
Sorge.lesNASAPMC
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost managementejlp12
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jimNASAPMC
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Glen Alleman
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_managementSayed Ahmed
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfHuyNguyen657394
 

Similar to PMP Chapter 7 Cost Management (20)

Earned Value Management - Foundation
Earned Value Management - FoundationEarned Value Management - Foundation
Earned Value Management - Foundation
 
Performing against the wall - SPI after completion
Performing against the wall - SPI after completionPerforming against the wall - SPI after completion
Performing against the wall - SPI after completion
 
PetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & ControlPetroSync - Successful Project Cost Estimation & Control
PetroSync - Successful Project Cost Estimation & Control
 
8.project cost management
8.project cost management8.project cost management
8.project cost management
 
Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®Connecting PMB® with PMBOK®
Connecting PMB® with PMBOK®
 
07 projectcostmanagement
07 projectcostmanagement07 projectcostmanagement
07 projectcostmanagement
 
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
Polynomial Function and Fuzzy Inference for Evaluating the Project Performanc...
 
07 project cost management
07 project cost management07 project cost management
07 project cost management
 
160155061 project-monitoring-control
160155061 project-monitoring-control160155061 project-monitoring-control
160155061 project-monitoring-control
 
Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...Project Management Project Assignment - Project Schedule & Resource Allocatio...
Project Management Project Assignment - Project Schedule & Resource Allocatio...
 
2.07 cost management 1
2.07 cost management 12.07 cost management 1
2.07 cost management 1
 
Sorge.les
Sorge.lesSorge.les
Sorge.les
 
PMP Training - 07 project cost management
PMP Training - 07 project cost managementPMP Training - 07 project cost management
PMP Training - 07 project cost management
 
COST MANAGEMENT REPORT
COST MANAGEMENT REPORT COST MANAGEMENT REPORT
COST MANAGEMENT REPORT
 
Cassidy.jim
Cassidy.jimCassidy.jim
Cassidy.jim
 
PMP-Cost Management area
PMP-Cost Management areaPMP-Cost Management area
PMP-Cost Management area
 
Chapter 07
Chapter 07Chapter 07
Chapter 07
 
Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)Building a Credible Performance Measurement Baseline (v3)
Building a Credible Performance Measurement Baseline (v3)
 
Lecture 06 project_cost_management
Lecture 06 project_cost_managementLecture 06 project_cost_management
Lecture 06 project_cost_management
 
Topic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdfTopic 12 - Project Cost Management.pdf
Topic 12 - Project Cost Management.pdf
 

Recently uploaded

How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityEric T. Tung
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Serviceritikaroy0888
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...Paul Menig
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear RegressionRavindra Nath Shukla
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxWorkforce Group
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesDipal Arora
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdfRenandantas16
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangaloreamitlee9823
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Centuryrwgiffor
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 

Recently uploaded (20)

How to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League CityHow to Get Started in Social Media for Art League City
How to Get Started in Social Media for Art League City
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
Call Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine ServiceCall Girls In Panjim North Goa 9971646499 Genuine Service
Call Girls In Panjim North Goa 9971646499 Genuine Service
 
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabiunwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
unwanted pregnancy Kit [+918133066128] Abortion Pills IN Dubai UAE Abudhabi
 
7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...7.pdf This presentation captures many uses and the significance of the number...
7.pdf This presentation captures many uses and the significance of the number...
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 
Regression analysis: Simple Linear Regression Multiple Linear Regression
Regression analysis:  Simple Linear Regression Multiple Linear RegressionRegression analysis:  Simple Linear Regression Multiple Linear Regression
Regression analysis: Simple Linear Regression Multiple Linear Regression
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Cracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptxCracking the Cultural Competence Code.pptx
Cracking the Cultural Competence Code.pptx
 
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best ServicesMysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
Mysore Call Girls 8617370543 WhatsApp Number 24x7 Best Services
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf0183760ssssssssssssssssssssssssssss00101011 (27).pdf
0183760ssssssssssssssssssssssssssss00101011 (27).pdf
 
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service BangaloreCall Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
Call Girls Hebbal Just Call 👗 7737669865 👗 Top Class Call Girl Service Bangalore
 
Famous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st CenturyFamous Olympic Siblings from the 21st Century
Famous Olympic Siblings from the 21st Century
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 

PMP Chapter 7 Cost Management

  • 1. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 PROJECT COST MANAGEMENT  Make sure the project can be completed within the approved budget.  There are 4 processes  Plan Cost Management  Estimate Cost  Determine Budget  Control Cost  Notes:  Different stakeholders -> different ways to manage cost  primarily concerned with the cost of the resources needed to complete project activities 1
  • 2. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 7.1 PLAN COST MANAGEMENT is the process that establishes the policies, procedures, and documentation for planning, managing, expending, and controlling project costs. 2 Inputs Tool&Techniques Outputs .Project management plan .Project charter .EEF .OPA .Expert Judment .Analytical techniques .Meetings .Cost management plan
  • 3. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 7.2 ESTIMATE COST Is the process of developing approximation of the monetary resources needed to complete project activities 3 Inputs Tool&Techniques Outputs .Cost management plan .Human resource management plan .Scope baseline .Project schedule .Risk register .Enterprise environmental factors .Organizational process assets .Expert judgment .Analogous estimating .Parametric estimating .Bottom-up estimating .Three-point estimating .Reserve analysis .Cost of quality .Project management software .Vendor bid analysis .Group decision-making techniques .Activity cost estimates .Basis of estimates .Project documents updates
  • 4. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 TYPE OF COSTS  Variable Costs  Change with the amount of production/work  e.g. material, supplies, wages  Fixed Costs  Do not change as production change  e.g. set-up, rental  Direct Costs  Directly attributable to the work of project  e.g. team travel, recognition, team wages  Indirect Costs  Not directly indentifiable, related to project product  e.g. taxes, fringe benefit  Sunk Costs:  is the cost that has already been incurred, and there is no way to recover this cost. 4
  • 5. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 QUALITY/ACCURACY OF COST ESTIMATION 5 • Most difficult to estimate as very little project info is available, made during initiating process Estimate Accuracy Rough Order of Magnitude (ROM) +/- 50% Budget Estimate -10% +25% Definitive Estimate -5% 10% • Used to finalize the Request for Authorization (RFA), and establish commitment, made during planning phase • During the project and refined
  • 6. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 7.3 DETERMINE BUDGET is the process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline 6 Inputs Tool&Techniques Outputs .Cost management plan .Scope baseline .Activity cost estimates .Basis of estimates .Project schedule .Resource calendars .Risk register .Aggreements .EEF .OPA .Cost aggregation .Reserse Analysis .Expert Judment .Historical relationships .Funding limit reconciliation .Cost baseline .Project funding requirements .Project documents updates
  • 7. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 MANAGEMENT RESERVE, CONTIGENCY RESERVE  Contingency reserves: the cost impacts of the remaining risk  Management reserves: extra fund to cover unforeseen risk or changes to the project 7
  • 8. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 COST BASELINE  is the approved version of the time-phased project budget, excluding any management reserves,  only be changed through formal change control procedures and  is used as a basis for comparison to actual results. 8
  • 9. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 7.4 CONTROL COST is the process of monitoring the status of the project to update the project costs and managing changes to the cost baseline. 9 Inputs Tool&Techniques Outputs .Project management plan . Project funding requirements .Work performance data .OPA .Earned value management .Forcasting .To-complete performance index (TCPI) .Performance reviews .Project management software .Reserse Analysis .Work performance information .Cost forecast .Change requests .Project management plan updates .Project documents updates .OPA updates
  • 10. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 EARNED VALUE MANAGEMENT  Method to measure project performance against scope, schedule and cost baseline (performance measurement baseline)  Importance measurement informations:  Cost Variance (CV)  Schedule Variance (SV)  Cost Performance Index (CPI)  Schedule Performance Index (SPI) 10
  • 11. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 EARNED VALUE TECHNIQUE 11 Terms and Formulas Definition Earned Value (EV) As of today, what is the estimated value of the work actually accomplished? Actual Cost (AC) As of today, what is the actual cost incurred for the work accomplished? Planned Value (PV) As of today, what is the estimated value of work planned to be done? Cost Variance (CV) = EV - AC Negative is over budget Positive is under budget Schedule Variance (SV) = EV - PV Negative is behind schedule Positive is ahead schedule Cost Performance Index (CPI) = EV/AC We are getting $__ worth of work out of every $1 spent. Are funds being used efficiently? Schedule Performance Index (SPI) = EV/PV We are (only) progressing at __ percent of the rate originally planed Example $100K $200K $300K $100K – $200K = ($100K) $100K - $300K = ($200K) $100K/$200K = 0.5 i.e. 50% $100K/$300K = 0.33 i.e 33% Example: Project Budget: $400K Project Schedule: 4 months At the 3 month checkpoint: Spent: $200K Work completed: $100K Revised Total Duration Baseline Duration/Schedule Performance Index 4/0.33 = 12 months
  • 12. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 EARNED VALUE TECHNIQUE (CON’T) 12 Terms and Formulas Definition Budget at completion (BAC) How much did we BUDGET for the TOTAL project effort? Estimate at Completion (EAC) = BAC / CPI What do we currently expect the TOTAL project cost (a forecast)? Estimate to Complete (ETC) = EAC - AC From this point on, how much MORE do we expect it to cost to finish the project (a forecast)? Variance at Completion (VAC) = BAC – EAC As of today, how much over or under budget do we expect to be at the end of the project?
  • 13. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 EXAMPLE OF EVM 13 TIME COST Schedule Variance (SV) Cost Variance (CV) ACTUAL PLAN EARN VALUE Estimate at Completion (EAC) Budget at Completion (BAC) Projection of schedule delay at completion Projection of cost variance at completion (VAC) TODAY (Reporting day) BAC EAC AC EV PV
  • 14. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 EXAMPLE OF EVM 14
  • 15. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 TO-COMPLETE PERFORMANCE INDEX (TCPI)  Helps the team determine the efficiency that must be achieved on the remaining work for a project to meet a specified endpoint, such as BAC or the team’s revised EAC  TCPI 15 AC)-(EACor– AC)(BACRemainingFunds EV)–(BACRemainingWork
  • 16. SMSVN – PMP Training Course 2013 – Chapter 7 Prepared by Nam Trung - 26/07/2013 REVIEW  Project cost management?  4 processes of time management?  Plan Cost Management  Estimate Cost  Determine Budget  Control Cost  Type of costs?  Quality/Accuracy of Cost Estimation?  Management reserve?  Contigency reserve?  Cost baseline?  CV?  SV?  CPI?  SPI?  BAC?  EAC?  ETC?  VAC?  TCPI? 16