SlideShare uma empresa Scribd logo
1 de 15
Baixar para ler offline
1


           “PIT CREWS” USE
CRITICAL CHAIN PROJECT MANAGEMENT
  TO CUT CYCLE TIMES IN HALF GIVING
FMC TECHNOLOGIES “ THE RACER’S EDGE”.

   A competitive advantage that’s hard to beat.
FMC Manufactures Multimillion Dollar Subsea Trees
                              2

 Under-ocean structures that control the flow of oil
 Very large, extremely
  complex devices with
  thousands of parts
 Custom engineered for
  specific customers and
  applications
 Many redundant systems
  required to ensure ongoing
  production & environmental safety
 Manufacturing requires superb coordination and control
FMC got very good results from the project.
                               3

 “Mark Woeppel’s group (Pinnacle Strategies) came
  in , analyzed our problems and within just a few
  days, gave us a recommendation and started the
  process on the very next (subsea) tree (product) in
  our assembly line.
 We cut almost 50% out of the cycle time of that tree
  assembly and we managed to hold onto that gain
  and continue to improve. That was impressive and
  we did it in just a matter of weeks.”
    Robert Houlgrave, Director, FMC Technologies Houston
FMC Reduced Cycle Time by 50%
                                 4

                       Assembly Cycle Times
        25
                                Average Before
        20                     CCPM & Pit Crews


        15                                      Average After
Weeks




                                              CCPM & Pit Crews

        10

         5

        0
             20 21 22 23 24 25 26 27 28 29        30 31 32 33 34
                                Tree Number
Situation at the beginning… (1)
                                     5

 Record sales pushed assembly to its limits
     Demand outpaced capacity
     Critical customer delivery performance jeopardized
 High defect rates
 Variable (unpredictable) completion times
 Late deliveries
 No standard process to build; high variation in output
 Poor workspace organization
 Engineering processes disconnected from build process
Situation at the beginning… (2)
                                  6

 Assembly & Test took far to long
   18 weeks
       Not simply a production coordination problem
       Required a new approach to project management

     Frequent work stoppages
     Workers waiting for decisions, designs & parts
     Excessive product waiting
 Lost productivity
   Assemblers out of area chasing down parts, tools, fixtures,
    materials handling equipment
   Assemblers waiting for approvals
Implementation Strategy –
        Increase capacity by reducing assembly time
                                7
 Reduce / eliminate                 Event-driven vs. date-
 waiting                             driven
    Improve product quality            Network of specific tasks
 Change focus from                      created
  keeping people moving                 Optimum task sequences
  to keeping product                     identified
  moving                                Parallel work paths
                                         created
 Reallocate work
    Segregate support from
     production
    Implement quick response
“Pit Crew” Approach
                                  8

 Identify “laps” of the FMC assembly “race”
 Careful identification and pre-staging of parts and
  equipment needed for each “lap”
 “Pit Crew” analogy helped team understand the shift
  in thinking
    Not keeping people busy
    Keeping the project moving
Strategy - Transform Culture
                                    9

 Create the “race team” organizational structure
 “Pit crews” responsible for proactive and reactive
 functions
    Proactive
      Planning and organization of scheduled work tasks
      Ensure tools, equipment, service providers and procedures
       reviewed, tested and ready for use
    Reactive
      Problem solving using root-cause analysis to get to bottom of
       recurring dilemmas
      Ensure tools, equipment, service providers and procedures
       reviewed, tested and ready for use
Implement Critical Chain Project Management (1)
                                 10

 New scheduling processes
   Planning & Execution Management

 New measurement system implemented
 Create organizational behaviors to support a
  seamless, continuous tree assembly process
 Systematic process improvements put in place
    Creation of a problem database
    Reviewed in terms of impact on reduction of overall lead times
    Providing handling of problems beyond the “pit crews”
Implement Critical Chain Project Management (2)
                                 11

 Manufacturing line reconfigured providing a solid
 benchmark in performance improvement
    Modified assembly bay functions to enable parallel assembly of
     components
 Posting “dashboard” of critical measurements to the
 shop floor
    Information posted based on workers’ needs to know to
     measure their performance
    Forecasted scheduling vs. actual daily attainment posted
Pinnacle Strategies Knowledge Transfer
                                      12

 Series of formal workshops
   Emphasis on behaviors to
    support the system
   Treated as consensus events
   Different topics to suit job
    roles & responsibility
   3 days to 3 hours

 Implementation led by
  informal & formal leaders
     Pinnacle staff behind the scenes
     Supporting leaders
     Providing individual coaching & “barrier busting”
 “Games” to initiate new behaviors
 Extensive documentation of processes & policies
Wow! Production Capacity Doubled
                                    13

 Workers could see what was coming up 3 to 5 days in
  advance
 Preparations were made before the tree entered their
  segment of the assembly process
    Like knowing and preparing for which lap a car is going to
     come into the pit
      Before car gets there, put new tires on rims and make sure they are
       properly inflated
      Ensure quick action on car to get it moving again

 No need to hire more workers or invest in more
 equipment
Improved Production Results
                                    14

 50% reduction in test duration and final assembly time
  within 60 days
 15 to 30% increased labor productivity within 2 months
     No additional capital investment
 $50,000 cost reduction per tree
     Fewer hours charged to each unit
 Workers at the ready with the right parts at the right time
 Use of “pit-stop” analogy reduced downtime associated
  with learning curve
 Problems acted upon immediately
Get Results Like That in Your Business
                              15

 Contact
 Pinnacle Strategies
   972-492-7951

   http://www.pinnacle-strategies.com

Mais conteúdo relacionado

Destaque

Critical Chain Long
Critical Chain LongCritical Chain Long
Critical Chain LongMihai
 
4th Industrial Revolution is Beyond Cyber Physical Systems
4th Industrial Revolution is Beyond Cyber Physical Systems 4th Industrial Revolution is Beyond Cyber Physical Systems
4th Industrial Revolution is Beyond Cyber Physical Systems VSR *
 
Improving Focus and Predictability on Projects with Critical Chain Project Ma...
Improving Focus and Predictability on Projects with Critical Chain Project Ma...Improving Focus and Predictability on Projects with Critical Chain Project Ma...
Improving Focus and Predictability on Projects with Critical Chain Project Ma...Joe Cooper
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementPlaybook
 
Lean Construction, para la gestión de calidad y productividad en proyectos de...
Lean Construction, para la gestión de calidad y productividad en proyectos de...Lean Construction, para la gestión de calidad y productividad en proyectos de...
Lean Construction, para la gestión de calidad y productividad en proyectos de...Estefany Aracena
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project ManagementYossi Bonomo
 
Planeación y Programación de Proyectos.
Planeación y Programación de Proyectos.Planeación y Programación de Proyectos.
Planeación y Programación de Proyectos.Estefany Aracena
 
Planificación y Control de Proyectos de Construcción
Planificación y Control de Proyectos de ConstrucciónPlanificación y Control de Proyectos de Construcción
Planificación y Control de Proyectos de ConstrucciónManuel García Naranjo B.
 

Destaque (9)

Critical Chain Long
Critical Chain LongCritical Chain Long
Critical Chain Long
 
4th Industrial Revolution is Beyond Cyber Physical Systems
4th Industrial Revolution is Beyond Cyber Physical Systems 4th Industrial Revolution is Beyond Cyber Physical Systems
4th Industrial Revolution is Beyond Cyber Physical Systems
 
Improving Focus and Predictability on Projects with Critical Chain Project Ma...
Improving Focus and Predictability on Projects with Critical Chain Project Ma...Improving Focus and Predictability on Projects with Critical Chain Project Ma...
Improving Focus and Predictability on Projects with Critical Chain Project Ma...
 
Lean Project Leadership
Lean Project LeadershipLean Project Leadership
Lean Project Leadership
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Lean Construction, para la gestión de calidad y productividad en proyectos de...
Lean Construction, para la gestión de calidad y productividad en proyectos de...Lean Construction, para la gestión de calidad y productividad en proyectos de...
Lean Construction, para la gestión de calidad y productividad en proyectos de...
 
Critical Chain Project Management
Critical Chain Project ManagementCritical Chain Project Management
Critical Chain Project Management
 
Planeación y Programación de Proyectos.
Planeación y Programación de Proyectos.Planeación y Programación de Proyectos.
Planeación y Programación de Proyectos.
 
Planificación y Control de Proyectos de Construcción
Planificación y Control de Proyectos de ConstrucciónPlanificación y Control de Proyectos de Construcción
Planificación y Control de Proyectos de Construcción
 

Mais de Pinnacle Strategies

Training & PMOs Will not Save our Projects
Training & PMOs Will not Save our ProjectsTraining & PMOs Will not Save our Projects
Training & PMOs Will not Save our ProjectsPinnacle Strategies
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...Pinnacle Strategies
 
ViewPoint - Why Your Projects Are Late
ViewPoint - Why Your Projects Are LateViewPoint - Why Your Projects Are Late
ViewPoint - Why Your Projects Are LatePinnacle Strategies
 
Visual Project Management webinar handout
Visual Project Management webinar handoutVisual Project Management webinar handout
Visual Project Management webinar handoutPinnacle Strategies
 
Projects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on timeProjects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on timePinnacle Strategies
 
Implementing ToC it doesnt have to be hard!
Implementing ToC   it doesnt have to be hard!Implementing ToC   it doesnt have to be hard!
Implementing ToC it doesnt have to be hard!Pinnacle Strategies
 
TLS - Integrating Tools for Big Results
TLS - Integrating Tools for Big ResultsTLS - Integrating Tools for Big Results
TLS - Integrating Tools for Big ResultsPinnacle Strategies
 
Maximum Flow Scheduling System Overview
Maximum Flow Scheduling System OverviewMaximum Flow Scheduling System Overview
Maximum Flow Scheduling System OverviewPinnacle Strategies
 

Mais de Pinnacle Strategies (8)

Training & PMOs Will not Save our Projects
Training & PMOs Will not Save our ProjectsTraining & PMOs Will not Save our Projects
Training & PMOs Will not Save our Projects
 
Why do projects fail - the project execution maturity model - basic collabor...
Why do projects fail  - the project execution maturity model - basic collabor...Why do projects fail  - the project execution maturity model - basic collabor...
Why do projects fail - the project execution maturity model - basic collabor...
 
ViewPoint - Why Your Projects Are Late
ViewPoint - Why Your Projects Are LateViewPoint - Why Your Projects Are Late
ViewPoint - Why Your Projects Are Late
 
Visual Project Management webinar handout
Visual Project Management webinar handoutVisual Project Management webinar handout
Visual Project Management webinar handout
 
Projects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on timeProjects in less time; 3 secrets to reducing project lead time, on time
Projects in less time; 3 secrets to reducing project lead time, on time
 
Implementing ToC it doesnt have to be hard!
Implementing ToC   it doesnt have to be hard!Implementing ToC   it doesnt have to be hard!
Implementing ToC it doesnt have to be hard!
 
TLS - Integrating Tools for Big Results
TLS - Integrating Tools for Big ResultsTLS - Integrating Tools for Big Results
TLS - Integrating Tools for Big Results
 
Maximum Flow Scheduling System Overview
Maximum Flow Scheduling System OverviewMaximum Flow Scheduling System Overview
Maximum Flow Scheduling System Overview
 

Último

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Neil Kimberley
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.Aaiza Hassan
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insightsseri bangash
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxpriyanshujha201
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Roland Driesen
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLSeo
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMRavindra Nath Shukla
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst SummitHolger Mueller
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...lizamodels9
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsMichael W. Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxAndy Lambert
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Lviv Startup Club
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdftbatkhuu1
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Dave Litwiller
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayNZSG
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒anilsa9823
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876dlhescort
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 DelhiCall Girls in Delhi
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableDipal Arora
 

Último (20)

Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023Mondelez State of Snacking and Future Trends 2023
Mondelez State of Snacking and Future Trends 2023
 
M.C Lodges -- Guest House in Jhang.
M.C Lodges --  Guest House in Jhang.M.C Lodges --  Guest House in Jhang.
M.C Lodges -- Guest House in Jhang.
 
Understanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key InsightsUnderstanding the Pakistan Budgeting Process: Basics and Key Insights
Understanding the Pakistan Budgeting Process: Basics and Key Insights
 
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptxB.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
B.COM Unit – 4 ( CORPORATE SOCIAL RESPONSIBILITY ( CSR ).pptx
 
Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...Ensure the security of your HCL environment by applying the Zero Trust princi...
Ensure the security of your HCL environment by applying the Zero Trust princi...
 
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRLMONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
MONA 98765-12871 CALL GIRLS IN LUDHIANA LUDHIANA CALL GIRL
 
Monte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSMMonte Carlo simulation : Simulation using MCSM
Monte Carlo simulation : Simulation using MCSM
 
Progress Report - Oracle Database Analyst Summit
Progress  Report - Oracle Database Analyst SummitProgress  Report - Oracle Database Analyst Summit
Progress Report - Oracle Database Analyst Summit
 
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
Call Girls In DLf Gurgaon ➥99902@11544 ( Best price)100% Genuine Escort In 24...
 
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
VVVIP Call Girls In Greater Kailash ➡️ Delhi ➡️ 9999965857 🚀 No Advance 24HRS...
 
HONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael HawkinsHONOR Veterans Event Keynote by Michael Hawkins
HONOR Veterans Event Keynote by Michael Hawkins
 
Monthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptxMonthly Social Media Update April 2024 pptx.pptx
Monthly Social Media Update April 2024 pptx.pptx
 
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
Yaroslav Rozhankivskyy: Три складові і три передумови максимальної продуктивн...
 
Event mailer assignment progress report .pdf
Event mailer assignment progress report .pdfEvent mailer assignment progress report .pdf
Event mailer assignment progress report .pdf
 
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
Enhancing and Restoring Safety & Quality Cultures - Dave Litwiller - May 2024...
 
It will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 MayIt will be International Nurses' Day on 12 May
It will be International Nurses' Day on 12 May
 
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒VIP Call Girls In Saharaganj ( Lucknow  ) 🔝 8923113531 🔝  Cash Payment (COD) 👒
VIP Call Girls In Saharaganj ( Lucknow ) 🔝 8923113531 🔝 Cash Payment (COD) 👒
 
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
Call Girls in Delhi, Escort Service Available 24x7 in Delhi 959961-/-3876
 
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
9599632723 Top Call Girls in Delhi at your Door Step Available 24x7 Delhi
 
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service AvailableCall Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
Call Girls Pune Just Call 9907093804 Top Class Call Girl Service Available
 

FMC Critical Chain Project Management Implementation

  • 1. 1 “PIT CREWS” USE CRITICAL CHAIN PROJECT MANAGEMENT TO CUT CYCLE TIMES IN HALF GIVING FMC TECHNOLOGIES “ THE RACER’S EDGE”. A competitive advantage that’s hard to beat.
  • 2. FMC Manufactures Multimillion Dollar Subsea Trees 2  Under-ocean structures that control the flow of oil  Very large, extremely complex devices with thousands of parts  Custom engineered for specific customers and applications  Many redundant systems required to ensure ongoing production & environmental safety  Manufacturing requires superb coordination and control
  • 3. FMC got very good results from the project. 3  “Mark Woeppel’s group (Pinnacle Strategies) came in , analyzed our problems and within just a few days, gave us a recommendation and started the process on the very next (subsea) tree (product) in our assembly line.  We cut almost 50% out of the cycle time of that tree assembly and we managed to hold onto that gain and continue to improve. That was impressive and we did it in just a matter of weeks.”  Robert Houlgrave, Director, FMC Technologies Houston
  • 4. FMC Reduced Cycle Time by 50% 4 Assembly Cycle Times 25 Average Before 20 CCPM & Pit Crews 15 Average After Weeks CCPM & Pit Crews 10 5 0 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 Tree Number
  • 5. Situation at the beginning… (1) 5  Record sales pushed assembly to its limits  Demand outpaced capacity  Critical customer delivery performance jeopardized  High defect rates  Variable (unpredictable) completion times  Late deliveries  No standard process to build; high variation in output  Poor workspace organization  Engineering processes disconnected from build process
  • 6. Situation at the beginning… (2) 6  Assembly & Test took far to long  18 weeks  Not simply a production coordination problem  Required a new approach to project management  Frequent work stoppages  Workers waiting for decisions, designs & parts  Excessive product waiting  Lost productivity  Assemblers out of area chasing down parts, tools, fixtures, materials handling equipment  Assemblers waiting for approvals
  • 7. Implementation Strategy – Increase capacity by reducing assembly time 7  Reduce / eliminate  Event-driven vs. date- waiting driven  Improve product quality  Network of specific tasks  Change focus from created keeping people moving  Optimum task sequences to keeping product identified moving  Parallel work paths created  Reallocate work  Segregate support from production  Implement quick response
  • 8. “Pit Crew” Approach 8  Identify “laps” of the FMC assembly “race”  Careful identification and pre-staging of parts and equipment needed for each “lap”  “Pit Crew” analogy helped team understand the shift in thinking  Not keeping people busy  Keeping the project moving
  • 9. Strategy - Transform Culture 9  Create the “race team” organizational structure  “Pit crews” responsible for proactive and reactive functions  Proactive  Planning and organization of scheduled work tasks  Ensure tools, equipment, service providers and procedures reviewed, tested and ready for use  Reactive  Problem solving using root-cause analysis to get to bottom of recurring dilemmas  Ensure tools, equipment, service providers and procedures reviewed, tested and ready for use
  • 10. Implement Critical Chain Project Management (1) 10  New scheduling processes  Planning & Execution Management  New measurement system implemented  Create organizational behaviors to support a seamless, continuous tree assembly process  Systematic process improvements put in place  Creation of a problem database  Reviewed in terms of impact on reduction of overall lead times  Providing handling of problems beyond the “pit crews”
  • 11. Implement Critical Chain Project Management (2) 11  Manufacturing line reconfigured providing a solid benchmark in performance improvement  Modified assembly bay functions to enable parallel assembly of components  Posting “dashboard” of critical measurements to the shop floor  Information posted based on workers’ needs to know to measure their performance  Forecasted scheduling vs. actual daily attainment posted
  • 12. Pinnacle Strategies Knowledge Transfer 12  Series of formal workshops  Emphasis on behaviors to support the system  Treated as consensus events  Different topics to suit job roles & responsibility  3 days to 3 hours  Implementation led by informal & formal leaders  Pinnacle staff behind the scenes  Supporting leaders  Providing individual coaching & “barrier busting”  “Games” to initiate new behaviors  Extensive documentation of processes & policies
  • 13. Wow! Production Capacity Doubled 13  Workers could see what was coming up 3 to 5 days in advance  Preparations were made before the tree entered their segment of the assembly process  Like knowing and preparing for which lap a car is going to come into the pit  Before car gets there, put new tires on rims and make sure they are properly inflated  Ensure quick action on car to get it moving again  No need to hire more workers or invest in more equipment
  • 14. Improved Production Results 14  50% reduction in test duration and final assembly time within 60 days  15 to 30% increased labor productivity within 2 months  No additional capital investment  $50,000 cost reduction per tree  Fewer hours charged to each unit  Workers at the ready with the right parts at the right time  Use of “pit-stop” analogy reduced downtime associated with learning curve  Problems acted upon immediately
  • 15. Get Results Like That in Your Business 15  Contact  Pinnacle Strategies  972-492-7951  http://www.pinnacle-strategies.com