TALVIVAARA UPDATE
MINING ON TOP: HELSINKI
17 SEPTEMBER 2013
Saila Miettinen-Lähde, Deputy CEO, CFO
DISCLAIMER
The following information contains, or may be deemed to contain, “forward-looking statements” (as defined in the U.S. Private Securities Litigation
Reform Act of 1995). These statements relate to future events that involve known and unknown risks and other uncertainties. By their nature, forward-
looking statements involve risks and uncertainties because they relate to events and depend on circumstances that may or may not occur in the future.
All forward-looking statements made in this presentation based on information presently available and Talvivaara Mining Company Plc. assumes no
obligation to update any forward-looking statements.
Nothing in this presentation constitutes investment advice and this presentation shall not constitute an offer to sell or the solicitation of an offer to buy
any securities or otherwise to engage in any investment activity.
1. Talvivaara in brief
2. Operational review – turning a corner
3. Safety, sustainability and permitting
4. Financial review
5. Outlook
3
TALVIVAARA IN BRIEF
• Significant base metals producer utilising
advanced proven technologies
• One of the largest known sulphide nickel
deposits in Europe with a long mine life
• Bioheapleaching has demonstrated to be a
feasible and cost-effective technology
following ramp-up
Targeted full scale production*
Nickel 50,000 tpa
Zinc 90,000 tpa
Copper 15,000 tpa
Cobalt 1,800 tpa
Uranium 350 tpa
* Subject to receipt of all necessary permits
4
5
Talvivaara mineral
resources 2012
Kuusilampi 1,033Mt
Kolmisoppi 1,020Mt
Total 2,053Mt
Kuusilampi
Kolmisoppi
Open pit
Secondary heap
Primary heap
Metals
recovery
Gypsum
pond
5
LONG-LIFE ASSET OF INTERNATIONAL SIGNIFICANCE
12,4
5.5 5.5
4.7
4.1
3.0 2.6 2.6 2.6 2.5 2.3 2.0 1.9 1.8 1.8 1.7 1.6 1.3 1.2
0,7
Taimyr(Norilsk)
WedaBay
(Eramet)
Chineseasset,est.
Indonesianasset,
est.
Cubanasset,est.
Talvivaara
Philippinoasset,
est.
MurrinMurrin
(Glencore)
CerroMatoso
(BHP)
SLN(Eramet)
Kola(Norilsk)
Soroako(PTInco)
Koniambo(Xstrata)
Goro(Vale)
Tumagain(Hard
Creek)
Ravensthorpe(FQ)
Ambatovy(Sherritt)
OncaPuma(Vale)
Ontario(Vale)
Fenix(Solway)
Estimated measured and indicated nickel contained resources, excluding inferred
(million tonnes)
Source: Public filings and industry estimates; selected mines
6
= Diversifieds
Estimated production capacity by mine (ktpa nickel)
124
113
70 65 60 60 60 60 53 50 50 45 40
28 24
12
Taimyr(Norilsk)
Kola(Norilsk)
Soroako(PTInco)
WedaBay
(Eramet)
SLN(Eramet)
Koniambo
(Xstrata)
Goro(Vale)
Ambatovy
(Sherritt)
OncaPuma(Vale)
Talvivaara
CerroMatoso
(BHP)
Tumagain(Hard
Creek)
MurrinMurrin
(Glencore)
Ravensthorpe
(FQ)
Fenix(Solway)
Ontario(Vale)
INDUSTRY-LEADING CAPITAL EFFICIENCY
Ambatovy
(Sherritt)
Goro (Vale)
Koniambo
(Xstrata)
Barro Alto (Anglo
American)
Talvivaara*
Onca Puma (Vale)
Ravensthorpe
(First Quantum)
Santa Rita
(Mirabela)
Kevitsa (First
Quantum)
0
5
10
15
20
25
30
35
40
45
50
2008 2009 2010 2011 2012 2013 2014
EstimatedCapex($/lbNiatfullcapacity)
Year of first production
Capital efficiency and production start-up of selected nickel projects
Source: Public filings; Bubble size represents estimated ramped-up production
*Talvivaara Capex intensity incorporates all historical Capex, and estimated remaining Capex required to reach capacity
= Laterite
= Sulphide
Size of bubble
represents
estimated full
capacity
7
World-class
deposit
Capex
efficiency
Profitability
and growth
Investment
grade
geography
TALVIVAARA PROCESS FLOWSHEET
8
Key challenges in 2012-13
• Water balance
• Temporary suspension of
mining
• Slowing down of leaching
process
1. Talvivaara in brief
2. Operational review – turning a corner
3. Safety, sustainability and permitting
4. Financial review
5. Outlook
9
OPERATIONAL REVIEW – TURNING A CORNER
• Production impacted by maintenance downtime
and low metal grades in leach solution
- Continued effect of excess water in older
heaps
• Successful re-start of ore production in May
• Promising early leaching results with new ore
• Extensive efficiency and productivity
programme ongoing
• Organisational changes
10
Nickel and zinc production (t)
Q2
2013
Q1
2013
Q2
2012
FY
2012
Nickel 1,776 2,732 3,194 12,916
Zinc 4,465 3,128 6,686 25,867
EFFICIENCY AND PRODUCTIVITY PROGRAMME
• Key elements of the programme
- Operational efficiency and
productivity
- Organisational structure, roles
and responsibilities
- Clear plans and follow-up
• 30 improvement levers identified;
full-scale implementation on-going
• Performance management process
rolled out into entire organisation as
an integral part of the programme
11
KAIVOS Heinäkuu 2013
Kustannusylitykset Juurisyy ja korjaavat toimenpiteet Omistaja Tuotantoa rajoittaneet tekijät Juurisyy ja korjaavat toimenpiteet Omistaja
KUMULATIIVINEN TUOTANTO- JA KUSTANNUSEURANTA
2013-01 2013-02 2013-03 2013-04 2013-05 2013-06 2013-07 2013-08 2013-09 2013-10 2013-11 2013-12
Tuotanto (tonnia)
Kuukausituotanto 100 100 100 100 100 100 100
Kumulatiivinen tuotanto 100 200 300 400 500 600 700
Kumulatiivinen tavoite 120 210 300 400 550 650 700 750 800 870 900 999
Erotus 20 110 200 300 450 550 600
Kustannukset (EUR / tonni, ilman leasingiä)
Kuukausikustannukset 99 76 56 77 88 66 120
Kuukausibudjetti 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Kumulatiivisen kustannukset 99 175 231 308 396 462 582
Kumulatiivinen tavoite 88 176 264 352 437 522 607 690 773 856 939 1022
Erotus -11 12 32 11 -3 19 -35
KUSTANNUSTEN TARKEMPI EROTTELU
Muutos
Erotus
budjettiin
kEUR EUR/tonni EUR/tonni kEUR EUR/tonni EUR/tonni kEUR EUR/tonni
Kaivos yhteensä 999 999 10 999 999 10 999 999
Ilman leasingiä 999 999 10 999 999 -5 999 999
Leasing 999 999 12 999 999 3 999 999
Poraus ja räjäytys 999 999 10 999 999 10 999 999
Palkat 999 999 10 999 999 -5 999 999
Koneet 999 999 12 999 999 3 999 999
Räjäytysaineet 999 999 -10 999 999 10 999 999
Lastaus ja kuljetus 999 999 10 999 999 10 999 999
Palkat 999 999 10 999 999 -5 999 999
Ajoneuvojen huolto 999 999 12 999 999 3 999 999
Polttoaineet 999 999 12 999 999 3 999 999
Renkaat 999 999 -10 999 999 10 999 999
Yleiskustannukset 999 999 10 999 999 10 999 999
Palkat 999 999 10 999 999 -5 999 999
ITja lisenssit 999 999 12 999 999 3 999 999
… 999 999 -10 999 999 10 999 999
OPERATIIVISET MITTARIT
Poraus (metriä)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Nikkelitonnit kasalle (ton Ni)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Polttoainekulutus (litraa / tkm)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Renkaiden kulutus (rengasta / tkm)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Ajotapakoulutus 6kk sisään (%)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Gatekeeper-osuus (%)
Toteuma 99 76 56 77 88 66 120
Tavoite 88 88 88 88 85 85 85 83 83 83 83 83
Erotus -11 12 32 11 -3 19 -35
Toteuma tukokuu 2013 Toteuma kesäkuu 2013 Budjetti kesäkuu 2013 Kommentit per kululaji
0
20
40
60
80
100
120
140
1 2 3 4 5 6 7 8 9 10 11 12
EUR/malmitonni
Kaivoksenyksikkökustannukset(ilmanleasing)
Kuukausikustannukset
0
200
400
600
800
1000
1200
1 2 3 4 5 6 7 8 9 10 11 12
Malmitonnia
Kaivoksenkumulatiivinentuotanto
Kumulatiivinen tuotanto Kumulatiivinen tavoite
• EUR 100m cash impact
expected in the next 12 mo.
• Positive cash flow
• Permanent change
ORGANISATIONAL CHANGES
• Darin Cooper appointed COO from Sep. 2013
- BEng, Metallurgy, MBA
- Successfully implemented several production
and cost efficiency programmes in the mining
and metals industries
- Former employers include Nyrstar, Teck
Metals, Hudson Bay Mining, Britannia Zinc
• Co-operation consultations concluded in August
- Reduction of headcount by 68 through
terminations of employment and retirements
- The employment of 96 employees with
temporary contracts to terminate at the end
of the agreed contract period without renewal
12
Darin Cooper, COO
SUCCESSFUL RE-COMMENCEMENT OF ORE
PRODUCTION
• Mining and materials handling operations resumed in mid-May, seven
weeks ahead of plan
13
0
10 000
20 000
30 000
40 000
50 000
60 000
04/2011 08/2011 12/2011 04/2012 08/2012 12/2012 04/2013
Average daily ore production (t) – rolling 30 days
MINING AND MATERIALS HANDLING PRODUCING AT
RECORD SPEED AND AT IMPROVED UNIT COSTS
0
1
2
3
4
5
6
7
Jan'12
Feb'12
Mar'12
Apr'12
May'12
Jun'12
Jul'12
Aug'12
May'13
Jun'13
Jul'13
14
Materials handling units costs (EUR / t ore)
Jul-2013
level
Ni tonnes to primary heap since re-start
• Approx. 8,000t of nickel stacked between re-start of ore production and end of July
• Record ore production level of 1.6Mt in July
• Improved grade control
• Improved unit costs across ore processes; especially optimised reclaiming process
0
1 000
2 000
3 000
4 000
5 000
May 2013 Jun 2013 Jul 2013
->13rd
May
+25%
+84%
2012 average
per month
RECLAIMING BOTTLE-NECK REMOVED
0
50 000
100 000
150 000
200 000
250 000
300 000
01/2012
02/2012
04/2012
05/2012
07/2012
08/2012
10/2012
11/2012
01/2013
02/2013
04/2013
05/2013
06/2013
Weekly Q1'12 avg Q2'12 avg Q3'12 avg Since re-start avg Jul-13 avg
15
Weekly primary heap reclaiming (t)
• Reclaiming process operating at planned capacity levels aided by process
modifications and the addition of a jaw crusher unit
BIOHEAPLEACHING – LOW NICKEL GRADE IN
SOLUTION, BUT SHOWING SIGNS OF TURNAROUND
16
0
5
10
15
20
25
30
35
40
45
50
04/13 05/13 06/13 07/13 08/13
Heap 1 Heap 2
Heap 3 Heap 4
Heap temperatures (°C)
-
0.2
0.4
0.6
0.8
1.0
1.2
1.4
1.6
1.8
2.0
Q1 2012 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013
Average nickel grade in plant PLS feed (g/l)
ACCELERATED DE-WATERING OF OLD HEAPS
• De-watering of older heaps slower than anticipated through Q2 2013 e.g. due to
available pond volumes
• De-watering now accelerating as a result of focused efforts to improve leaching
performance; pond volumes now sufficient for solution removed from heaps
17
EARLY LEACHING RESULTS DEMONSTRATE VERY
ACTIVE PROCESS START-UP OF NEW HEAP
• Early leaching of fresh ore has been very promising; temperatures of circulating solution
already exceeding 50°C
- Exceeds corresponding performance of any previous heap historically
• First new heap (primary heap no. 4) completed in the beginning of September
• Fresh ore starting to contribute metals as precipitation phase is ending
• Special attention is paid to securing efficient start-up of the new heaps
18
1 800
2 000
2 200
2 400
2 600
2 800
800
850
900
950
1 000
1 050
1 100
2.8. 3.8. 4.8. 5.8. 6.8. 7.8. 8.8. 9.8. 10.8. 11.8. 12.8. 13.8.
Zn(mg/l)
Ni(mg/l)
Ni (mg/l)
Zn (mg/l)
Metals grades in new heap – starting to contribute metals
METALS RECOVERY – RECORD FLOW RATE AND
CONTINUED STABILITY
• Q2 2013 production impacted by
- Scheduled maintenance stoppage of approx. 2.5 weeks in late May and early June
- Capacity restrictions due to planned maintenance of hydrogen sulphide plants
already from mid-April
• Flow rate reached a record level of 1,650 m3/h in June
• Metals plant operation stable throughout H1 2013
- Plant operation not anticipated to restrict production
- Leach solution metal grade improvement to drive production volume increase
19
3 194
4 030
2 317
2 732
1 776
Q2
2012
Q3
2012
Q4
2012
Q1
2013
Q2
2013
Nickel production (t)
6 686
7 184
4 106
3 128
4 465
Q2
2012
Q3
2012
Q4
2012
Q1
2013
Q2
2013
Zinc production (t)
FLOW RATES AT THE METALS PLANT IMPROVING
20
-
300
600
900
1 200
1 500
1 800
01/11
03/11
05/11
07/11
09/11
11/11
01/12
03/12
05/12
07/12
09/12
11/12
01/13
03/13
05/13
07/13
Monthly average 2011 average 2012 average 2013 average
Monthly average flow rate to the plant (m3/h)
Average in June
2013 subsequent to
plant maintenance
06/13
1. Talvivaara in brief
2. Operational review – turning a corner
3. Safety, sustainability and permitting
4. Financial review
5. Outlook
21
SAFETY, SUSTAINABILITY AND PERMITTING
Safety
• Increased focus on further safety training across all
departments
• LTIs at 19.5 / million working hours at the end of Q2
2013
Sustainability
• Focus continues to be on water management
– Treatment and discharge of water has continued
throughout H1 2013
• Gypsum pond leakage in April fully contained within the
safety dams
• Historical issues with odour and dust resolved
Permitting
• New water discharge permit received in May
– Volume quota removed
– Discharge flow rate restricted by Kalliojoki river
flow rate; Talvivaara has submitted an appeal
with respect to this permit condition
• Decision on renewal of overall environmental permit
and on environmental permit for uranium extraction
expected before the end of 2013
22
APPROX. 3 MILLION M3 OF EXCESS WATERS
DISCHARGED IN THE FIRST HALF OF 2013
23
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
01/2013
02/2013
03/2013
04/2013
05/2013
06/2013
07/2013
Cumulative 2013 water discharge (Mm3)• Treatment and discharge of excess waters
from the mine area continued throughout
H1 2013
• Discharge will continue within permitted
limits, but risks already materially reduced
300 000
400 000
500 000
600 000
01/13 02/13 03/13 04/13 05/13 06/13 07/13
Primary heap pond volume
Max. pond volume
Primary heap solution volume (m3)
12-Feb
discharge
permit from
Kainuu ELY
31-May
environmental
permit update
from AVI
SIGNIFICANT REDUCTION IN ENVIRONMENTAL
OBSERVATIONS FROM NEIGHBOURING RESIDENTS
24
0
5
10
15
20
25
30
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Apr
May
Jun
2011 2012 2013
Numberofobservations
Odour
Noise
Vibration
Dust
Water
Other
1. Talvivaara in brief
2. Operational review – turning a corner
3. Safety, sustainability and permitting
4. Financial review
5. Outlook
25
Q2 2013 FINANCIAL RESULTS
• Results reflect production levels and a
depressed nickel price environment
- LME nickel price below USD 14,000/t
at the end of Q2 2013
• Q2 2013 key financials
- Sales: EUR 13.0m
- Operating loss: EUR (23.9)m
- Capex: EUR 15.3m
• Costs impacted by:
- Water management
- Metals plant maintenance
- Re-commencement of ore production
- Chemicals efficiency impact of low
metals grade in solution
26
33.4
44.8
25.7 27.6
13.0
Q2… Q3… Q4… Q1… Q2…
Net sales (EURm)
-10.9
-4.3
-57.0
-20.0
-23.9
Q2
2012
Q3
2012
Q4
2012
Q1
2013
Q2
2013
Operating profit (EURm)
LIQUIDITY POSITION AND BALANCE SHEET
27
-
50
100
150
200
250
300
2013 2014 2015 2016 2017 2018
Other Finance lease liabilities
Corporate revolver Senior unsecured bond
Convertible bonds* WC (Finnvera) loans
* Convertible bond maturity reflects accreted principal
Debt maturity profile (EURm)
Net interest-bearing debt (EURm)
476
515
564 530
410
Q2
2012
Q3
2012
Q4
2012
Q1
2013
Q2
2013
• Financing transactions in H1 2013 significantly
improved balance sheet and liquidity position
- Gearing from 183% at year-end 2012 to
81% at the end of Q2 2013
- Net debt from EUR 564m at year-end to
EUR 410m at the end of Q2
• Remaining EUR 77m convertible bond
maturity repaid in May
• Next material maturity in December 2015
(excluding RCF)
• Cash at EUR 101.1m at the end of Q2
• Several significant initiatives to maintain
liquidity as part of efficiency and productivity
programme
1. Talvivaara in brief
2. Operational review – turning a corner
3. Safety, sustainability and permitting
4. Financial review
5. Outlook
28
NICKEL MARKET – NEAR-TERM OUTLOOK
CHALLENGING
• Nickel price under significant pressure
through H1 2013
- Declined from USD 18,000-19,000/t in
early 2013 to below USD 14,000/t in
the summer
- Macro outlook and weak stainless steel
market
- Build-up of nickel inventories to a
record level of more than 200,000t
• Short-term outlook:
- Near-term outlook remains challenging
- Current price level considered
unsustainable; restrictions of supply
and positive macro developments may
trigger upside movement
29
LME nickel price (USD/t)
10 000
15 000
20 000
25 000
30 000
01/11 05/11 09/11 01/12 05/12 09/12 01/13 05/13
LME nickel price (USD/t) and nickel stocks (kt)
-
50
100
150
200
250
300
-
5 000
10 000
15 000
20 000
25 000
30 000
2008 2009 2010 2011 2012 2013
LME nickel stocks (t) LME nickel price (USD/t)
LONG-TERM TALVIVAARA STORY INTACT
• Extensive sulphide nickel deposit with a long mine life
• Favourable characteristics of the Talvivaara deposits
• Cost-effective and scalable bioheapleaching technology
• Demonstrated feasibility of using bioheapleaching to extract nickel
• Long-term off-take agreements for nickel, cobalt, zinc and uranium
• Attractive long-term supply-demand dynamics of the nickel industry
• Experienced management team
30
• Long-term story intact – world-class ore body and cost efficiency following ramp-up
• Short-term challenges being addressed and showing signs of success
THANK YOU!
Q & A
31

Mais conteúdo relacionado

Semelhante a Talvivaara Update - Saila Miettinen-Lähde, Talvivaara

Teranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold
 
Microsoft power point magref-apres_padrao_4q09eng
Microsoft power point   magref-apres_padrao_4q09engMicrosoft power point   magref-apres_padrao_4q09eng
Microsoft power point magref-apres_padrao_4q09engMagnesita_ri
 
Presentations 4 q09
Presentations 4 q09Presentations 4 q09
Presentations 4 q09MagnesitaRI
 
Current situation in the shipbuilding industry
Current situation in the shipbuilding industry Current situation in the shipbuilding industry
Current situation in the shipbuilding industry innovationoecd
 
Apres padrao mrsa_1_q10_eng
Apres padrao mrsa_1_q10_engApres padrao mrsa_1_q10_eng
Apres padrao mrsa_1_q10_engMagnesita_ri
 
How to unlock productivity savings in mining operations part 1
How to unlock productivity savings in mining operations part 1How to unlock productivity savings in mining operations part 1
How to unlock productivity savings in mining operations part 1David Mallinson MAICD
 
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Symposium
 
final-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxfinal-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxAnithaDas6
 
Investor Presentation November 2014
Investor Presentation November 2014Investor Presentation November 2014
Investor Presentation November 2014Teranga Gold
 
SHANGHAI YAOHUA PILKINGTON GLASS E Catalogue
SHANGHAI YAOHUA PILKINGTON GLASS  E CatalogueSHANGHAI YAOHUA PILKINGTON GLASS  E Catalogue
SHANGHAI YAOHUA PILKINGTON GLASS E CatalogueCarl Lee
 
Nordnet med Hydro investorpresentasjon
Nordnet med Hydro investorpresentasjonNordnet med Hydro investorpresentasjon
Nordnet med Hydro investorpresentasjonNordnet Norge
 
Results presentation 4 q10
Results presentation 4 q10Results presentation 4 q10
Results presentation 4 q10MagnesitaRI
 
Hard Rock Mine Design Project
Hard Rock Mine Design ProjectHard Rock Mine Design Project
Hard Rock Mine Design ProjectAshishKumar3265
 
RandGold Resources Facts & Figures
RandGold Resources Facts & FiguresRandGold Resources Facts & Figures
RandGold Resources Facts & FiguresCompany Spotlight
 

Semelhante a Talvivaara Update - Saila Miettinen-Lähde, Talvivaara (20)

Teranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 PresentationTeranga Gold Third Quarter 2015 Presentation
Teranga Gold Third Quarter 2015 Presentation
 
Microsoft power point magref-apres_padrao_4q09eng
Microsoft power point   magref-apres_padrao_4q09engMicrosoft power point   magref-apres_padrao_4q09eng
Microsoft power point magref-apres_padrao_4q09eng
 
Presentations 4 q09
Presentations 4 q09Presentations 4 q09
Presentations 4 q09
 
Current situation in the shipbuilding industry
Current situation in the shipbuilding industry Current situation in the shipbuilding industry
Current situation in the shipbuilding industry
 
Apres padrao mrsa_1_q10_eng
Apres padrao mrsa_1_q10_engApres padrao mrsa_1_q10_eng
Apres padrao mrsa_1_q10_eng
 
How to unlock productivity savings in mining operations part 1
How to unlock productivity savings in mining operations part 1How to unlock productivity savings in mining operations part 1
How to unlock productivity savings in mining operations part 1
 
NSG FMP energy excellence
NSG FMP energy excellenceNSG FMP energy excellence
NSG FMP energy excellence
 
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
Investor Presentation | Evolution Mining (ASX:EVN) | Gold Investment Symposiu...
 
Proximity detection and anti collision workshop
Proximity detection and anti collision workshopProximity detection and anti collision workshop
Proximity detection and anti collision workshop
 
final-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxfinal-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptx
 
Investor Presentation November 2014
Investor Presentation November 2014Investor Presentation November 2014
Investor Presentation November 2014
 
SHANGHAI YAOHUA PILKINGTON GLASS E Catalogue
SHANGHAI YAOHUA PILKINGTON GLASS  E CatalogueSHANGHAI YAOHUA PILKINGTON GLASS  E Catalogue
SHANGHAI YAOHUA PILKINGTON GLASS E Catalogue
 
Result presentation Q2 2014
Result presentation Q2 2014Result presentation Q2 2014
Result presentation Q2 2014
 
Nordnet med Hydro investorpresentasjon
Nordnet med Hydro investorpresentasjonNordnet med Hydro investorpresentasjon
Nordnet med Hydro investorpresentasjon
 
Results presentation 4 q10
Results presentation 4 q10Results presentation 4 q10
Results presentation 4 q10
 
4 t10 eng
4 t10 eng4 t10 eng
4 t10 eng
 
Hard Rock Mine Design Project
Hard Rock Mine Design ProjectHard Rock Mine Design Project
Hard Rock Mine Design Project
 
20121029 ipt presentation
20121029 ipt presentation20121029 ipt presentation
20121029 ipt presentation
 
presentation
presentationpresentation
presentation
 
RandGold Resources Facts & Figures
RandGold Resources Facts & FiguresRandGold Resources Facts & Figures
RandGold Resources Facts & Figures
 

Mais de Mining On Top

Mining Investment in Uganda
Mining Investment in UgandaMining Investment in Uganda
Mining Investment in UgandaMining On Top
 
Republic of South Sudan: Mining Investment Opportunities in South Sudan
Republic of South Sudan: Mining Investment Opportunities in South SudanRepublic of South Sudan: Mining Investment Opportunities in South Sudan
Republic of South Sudan: Mining Investment Opportunities in South SudanMining On Top
 
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...Mining On Top
 
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...Mining On Top
 
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...Mining On Top
 
The State of African Mining - Chris Hinde, SNL Metals & Mining
The State of African Mining - Chris Hinde, SNL Metals & MiningThe State of African Mining - Chris Hinde, SNL Metals & Mining
The State of African Mining - Chris Hinde, SNL Metals & MiningMining On Top
 
Republic of Ghana Mining Roundtable
Republic of Ghana Mining RoundtableRepublic of Ghana Mining Roundtable
Republic of Ghana Mining RoundtableMining On Top
 
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...Republic of Botswana: State of the Mineral Industry and Investment Opportunit...
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...Mining On Top
 
Republic of Angola: Governmental Strategy for its Mining Sector
Republic of Angola: Governmental Strategy for its Mining SectorRepublic of Angola: Governmental Strategy for its Mining Sector
Republic of Angola: Governmental Strategy for its Mining SectorMining On Top
 
Zambia Mining Roundtable
Zambia Mining RoundtableZambia Mining Roundtable
Zambia Mining RoundtableMining On Top
 
Mining in Ghana: A partnership - Endeavour Mining
Mining in Ghana: A partnership - Endeavour MiningMining in Ghana: A partnership - Endeavour Mining
Mining in Ghana: A partnership - Endeavour MiningMining On Top
 
Investor Presentation - Allana Potash
Investor Presentation - Allana PotashInvestor Presentation - Allana Potash
Investor Presentation - Allana PotashMining On Top
 
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECA
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECAInfrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECA
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECAMining On Top
 
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...Mining On Top
 
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonald
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonaldMozambique’s Moatize Coal Basin - David Hunter, Mott McDonald
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonaldMining On Top
 
Mabey Bridge - Transport considerations - Phil Bailey, Mabey Bridge
Mabey Bridge - Transport considerations - Phil Bailey,  Mabey BridgeMabey Bridge - Transport considerations - Phil Bailey,  Mabey Bridge
Mabey Bridge - Transport considerations - Phil Bailey, Mabey BridgeMining On Top
 
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...Mining On Top
 
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...Mining On Top
 
Investor Presentation - Endeavour Mining
Investor Presentation - Endeavour MiningInvestor Presentation - Endeavour Mining
Investor Presentation - Endeavour MiningMining On Top
 
The multiplier effect of infrastructure - Marcio Senne de Moraes, Vale
The multiplier effect of infrastructure - Marcio Senne de Moraes, ValeThe multiplier effect of infrastructure - Marcio Senne de Moraes, Vale
The multiplier effect of infrastructure - Marcio Senne de Moraes, ValeMining On Top
 

Mais de Mining On Top (20)

Mining Investment in Uganda
Mining Investment in UgandaMining Investment in Uganda
Mining Investment in Uganda
 
Republic of South Sudan: Mining Investment Opportunities in South Sudan
Republic of South Sudan: Mining Investment Opportunities in South SudanRepublic of South Sudan: Mining Investment Opportunities in South Sudan
Republic of South Sudan: Mining Investment Opportunities in South Sudan
 
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...
NW Province Republic of South Africa: A Land of Tourism, Trade and Investment...
 
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...
Republic of Nigeria: Investment Opportunities in Nigeria’s Minerals And Metal...
 
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...
Republic of Namibia: Minerals, Mineral Potential, Exploration & Mining in Nam...
 
The State of African Mining - Chris Hinde, SNL Metals & Mining
The State of African Mining - Chris Hinde, SNL Metals & MiningThe State of African Mining - Chris Hinde, SNL Metals & Mining
The State of African Mining - Chris Hinde, SNL Metals & Mining
 
Republic of Ghana Mining Roundtable
Republic of Ghana Mining RoundtableRepublic of Ghana Mining Roundtable
Republic of Ghana Mining Roundtable
 
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...Republic of Botswana: State of the Mineral Industry and Investment Opportunit...
Republic of Botswana: State of the Mineral Industry and Investment Opportunit...
 
Republic of Angola: Governmental Strategy for its Mining Sector
Republic of Angola: Governmental Strategy for its Mining SectorRepublic of Angola: Governmental Strategy for its Mining Sector
Republic of Angola: Governmental Strategy for its Mining Sector
 
Zambia Mining Roundtable
Zambia Mining RoundtableZambia Mining Roundtable
Zambia Mining Roundtable
 
Mining in Ghana: A partnership - Endeavour Mining
Mining in Ghana: A partnership - Endeavour MiningMining in Ghana: A partnership - Endeavour Mining
Mining in Ghana: A partnership - Endeavour Mining
 
Investor Presentation - Allana Potash
Investor Presentation - Allana PotashInvestor Presentation - Allana Potash
Investor Presentation - Allana Potash
 
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECA
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECAInfrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECA
Infrastructure to Support Industrialisation in Africa - Antonio Pedro, UN ECA
 
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...
Managing Risk and Cost in Mining Infrastructure Development - Sarah Thomas, P...
 
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonald
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonaldMozambique’s Moatize Coal Basin - David Hunter, Mott McDonald
Mozambique’s Moatize Coal Basin - David Hunter, Mott McDonald
 
Mabey Bridge - Transport considerations - Phil Bailey, Mabey Bridge
Mabey Bridge - Transport considerations - Phil Bailey,  Mabey BridgeMabey Bridge - Transport considerations - Phil Bailey,  Mabey Bridge
Mabey Bridge - Transport considerations - Phil Bailey, Mabey Bridge
 
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...
Mining’s legacy: thinking beyond the mine - Ian Satchwell, International Mini...
 
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...
Africa Mining Risks Assessment - James Lewis and Robert Follie, Holman Fenwic...
 
Investor Presentation - Endeavour Mining
Investor Presentation - Endeavour MiningInvestor Presentation - Endeavour Mining
Investor Presentation - Endeavour Mining
 
The multiplier effect of infrastructure - Marcio Senne de Moraes, Vale
The multiplier effect of infrastructure - Marcio Senne de Moraes, ValeThe multiplier effect of infrastructure - Marcio Senne de Moraes, Vale
The multiplier effect of infrastructure - Marcio Senne de Moraes, Vale
 

Último

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Servicecallgirls2057
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaoncallgirls2057
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...lizamodels9
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCRashishs7044
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdfKhaled Al Awadi
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03DallasHaselhorst
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCRashishs7044
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,noida100girls
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis UsageNeil Kimberley
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?Olivia Kresic
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCRashishs7044
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Timedelhimodelshub1
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Kirill Klimov
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfrichard876048
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailAriel592675
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy Verified Accounts
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...lizamodels9
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCRashishs7044
 

Último (20)

Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort ServiceCall US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
Call US-88OO1O2216 Call Girls In Mahipalpur Female Escort Service
 
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City GurgaonCall Us 📲8800102216📞 Call Girls In DLF City Gurgaon
Call Us 📲8800102216📞 Call Girls In DLF City Gurgaon
 
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
Call Girls In Radisson Blu Hotel New Delhi Paschim Vihar ❤️8860477959 Escorts...
 
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR8447779800, Low rate Call girls in Tughlakabad Delhi NCR
8447779800, Low rate Call girls in Tughlakabad Delhi NCR
 
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdfNewBase  19 April  2024  Energy News issue - 1717 by Khaled Al Awadi.pdf
NewBase 19 April 2024 Energy News issue - 1717 by Khaled Al Awadi.pdf
 
Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03Cybersecurity Awareness Training Presentation v2024.03
Cybersecurity Awareness Training Presentation v2024.03
 
8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR8447779800, Low rate Call girls in Saket Delhi NCR
8447779800, Low rate Call girls in Saket Delhi NCR
 
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Old Faridabad ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
BEST Call Girls In Greater Noida ✨ 9773824855 ✨ Escorts Service In Delhi Ncr,
 
2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage2024 Numerator Consumer Study of Cannabis Usage
2024 Numerator Consumer Study of Cannabis Usage
 
MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?MAHA Global and IPR: Do Actions Speak Louder Than Words?
MAHA Global and IPR: Do Actions Speak Louder Than Words?
 
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
8447779800, Low rate Call girls in Shivaji Enclave Delhi NCR
 
Call Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any TimeCall Girls Miyapur 7001305949 all area service COD available Any Time
Call Girls Miyapur 7001305949 all area service COD available Any Time
 
Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024Flow Your Strategy at Flight Levels Day 2024
Flow Your Strategy at Flight Levels Day 2024
 
Innovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdfInnovation Conference 5th March 2024.pdf
Innovation Conference 5th March 2024.pdf
 
Case study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detailCase study on tata clothing brand zudio in detail
Case study on tata clothing brand zudio in detail
 
Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)Japan IT Week 2024 Brochure by 47Billion (English)
Japan IT Week 2024 Brochure by 47Billion (English)
 
Buy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail AccountsBuy gmail accounts.pdf Buy Old Gmail Accounts
Buy gmail accounts.pdf Buy Old Gmail Accounts
 
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
Call Girls In Connaught Place Delhi ❤️88604**77959_Russian 100% Genuine Escor...
 
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
8447779800, Low rate Call girls in New Ashok Nagar Delhi NCR
 

Talvivaara Update - Saila Miettinen-Lähde, Talvivaara

  • 1. TALVIVAARA UPDATE MINING ON TOP: HELSINKI 17 SEPTEMBER 2013 Saila Miettinen-Lähde, Deputy CEO, CFO
  • 2. DISCLAIMER The following information contains, or may be deemed to contain, “forward-looking statements” (as defined in the U.S. Private Securities Litigation Reform Act of 1995). These statements relate to future events that involve known and unknown risks and other uncertainties. By their nature, forward- looking statements involve risks and uncertainties because they relate to events and depend on circumstances that may or may not occur in the future. All forward-looking statements made in this presentation based on information presently available and Talvivaara Mining Company Plc. assumes no obligation to update any forward-looking statements. Nothing in this presentation constitutes investment advice and this presentation shall not constitute an offer to sell or the solicitation of an offer to buy any securities or otherwise to engage in any investment activity.
  • 3. 1. Talvivaara in brief 2. Operational review – turning a corner 3. Safety, sustainability and permitting 4. Financial review 5. Outlook 3
  • 4. TALVIVAARA IN BRIEF • Significant base metals producer utilising advanced proven technologies • One of the largest known sulphide nickel deposits in Europe with a long mine life • Bioheapleaching has demonstrated to be a feasible and cost-effective technology following ramp-up Targeted full scale production* Nickel 50,000 tpa Zinc 90,000 tpa Copper 15,000 tpa Cobalt 1,800 tpa Uranium 350 tpa * Subject to receipt of all necessary permits 4
  • 5. 5 Talvivaara mineral resources 2012 Kuusilampi 1,033Mt Kolmisoppi 1,020Mt Total 2,053Mt Kuusilampi Kolmisoppi Open pit Secondary heap Primary heap Metals recovery Gypsum pond 5
  • 6. LONG-LIFE ASSET OF INTERNATIONAL SIGNIFICANCE 12,4 5.5 5.5 4.7 4.1 3.0 2.6 2.6 2.6 2.5 2.3 2.0 1.9 1.8 1.8 1.7 1.6 1.3 1.2 0,7 Taimyr(Norilsk) WedaBay (Eramet) Chineseasset,est. Indonesianasset, est. Cubanasset,est. Talvivaara Philippinoasset, est. MurrinMurrin (Glencore) CerroMatoso (BHP) SLN(Eramet) Kola(Norilsk) Soroako(PTInco) Koniambo(Xstrata) Goro(Vale) Tumagain(Hard Creek) Ravensthorpe(FQ) Ambatovy(Sherritt) OncaPuma(Vale) Ontario(Vale) Fenix(Solway) Estimated measured and indicated nickel contained resources, excluding inferred (million tonnes) Source: Public filings and industry estimates; selected mines 6 = Diversifieds Estimated production capacity by mine (ktpa nickel) 124 113 70 65 60 60 60 60 53 50 50 45 40 28 24 12 Taimyr(Norilsk) Kola(Norilsk) Soroako(PTInco) WedaBay (Eramet) SLN(Eramet) Koniambo (Xstrata) Goro(Vale) Ambatovy (Sherritt) OncaPuma(Vale) Talvivaara CerroMatoso (BHP) Tumagain(Hard Creek) MurrinMurrin (Glencore) Ravensthorpe (FQ) Fenix(Solway) Ontario(Vale)
  • 7. INDUSTRY-LEADING CAPITAL EFFICIENCY Ambatovy (Sherritt) Goro (Vale) Koniambo (Xstrata) Barro Alto (Anglo American) Talvivaara* Onca Puma (Vale) Ravensthorpe (First Quantum) Santa Rita (Mirabela) Kevitsa (First Quantum) 0 5 10 15 20 25 30 35 40 45 50 2008 2009 2010 2011 2012 2013 2014 EstimatedCapex($/lbNiatfullcapacity) Year of first production Capital efficiency and production start-up of selected nickel projects Source: Public filings; Bubble size represents estimated ramped-up production *Talvivaara Capex intensity incorporates all historical Capex, and estimated remaining Capex required to reach capacity = Laterite = Sulphide Size of bubble represents estimated full capacity 7 World-class deposit Capex efficiency Profitability and growth Investment grade geography
  • 8. TALVIVAARA PROCESS FLOWSHEET 8 Key challenges in 2012-13 • Water balance • Temporary suspension of mining • Slowing down of leaching process
  • 9. 1. Talvivaara in brief 2. Operational review – turning a corner 3. Safety, sustainability and permitting 4. Financial review 5. Outlook 9
  • 10. OPERATIONAL REVIEW – TURNING A CORNER • Production impacted by maintenance downtime and low metal grades in leach solution - Continued effect of excess water in older heaps • Successful re-start of ore production in May • Promising early leaching results with new ore • Extensive efficiency and productivity programme ongoing • Organisational changes 10 Nickel and zinc production (t) Q2 2013 Q1 2013 Q2 2012 FY 2012 Nickel 1,776 2,732 3,194 12,916 Zinc 4,465 3,128 6,686 25,867
  • 11. EFFICIENCY AND PRODUCTIVITY PROGRAMME • Key elements of the programme - Operational efficiency and productivity - Organisational structure, roles and responsibilities - Clear plans and follow-up • 30 improvement levers identified; full-scale implementation on-going • Performance management process rolled out into entire organisation as an integral part of the programme 11 KAIVOS Heinäkuu 2013 Kustannusylitykset Juurisyy ja korjaavat toimenpiteet Omistaja Tuotantoa rajoittaneet tekijät Juurisyy ja korjaavat toimenpiteet Omistaja KUMULATIIVINEN TUOTANTO- JA KUSTANNUSEURANTA 2013-01 2013-02 2013-03 2013-04 2013-05 2013-06 2013-07 2013-08 2013-09 2013-10 2013-11 2013-12 Tuotanto (tonnia) Kuukausituotanto 100 100 100 100 100 100 100 Kumulatiivinen tuotanto 100 200 300 400 500 600 700 Kumulatiivinen tavoite 120 210 300 400 550 650 700 750 800 870 900 999 Erotus 20 110 200 300 450 550 600 Kustannukset (EUR / tonni, ilman leasingiä) Kuukausikustannukset 99 76 56 77 88 66 120 Kuukausibudjetti 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Kumulatiivisen kustannukset 99 175 231 308 396 462 582 Kumulatiivinen tavoite 88 176 264 352 437 522 607 690 773 856 939 1022 Erotus -11 12 32 11 -3 19 -35 KUSTANNUSTEN TARKEMPI EROTTELU Muutos Erotus budjettiin kEUR EUR/tonni EUR/tonni kEUR EUR/tonni EUR/tonni kEUR EUR/tonni Kaivos yhteensä 999 999 10 999 999 10 999 999 Ilman leasingiä 999 999 10 999 999 -5 999 999 Leasing 999 999 12 999 999 3 999 999 Poraus ja räjäytys 999 999 10 999 999 10 999 999 Palkat 999 999 10 999 999 -5 999 999 Koneet 999 999 12 999 999 3 999 999 Räjäytysaineet 999 999 -10 999 999 10 999 999 Lastaus ja kuljetus 999 999 10 999 999 10 999 999 Palkat 999 999 10 999 999 -5 999 999 Ajoneuvojen huolto 999 999 12 999 999 3 999 999 Polttoaineet 999 999 12 999 999 3 999 999 Renkaat 999 999 -10 999 999 10 999 999 Yleiskustannukset 999 999 10 999 999 10 999 999 Palkat 999 999 10 999 999 -5 999 999 ITja lisenssit 999 999 12 999 999 3 999 999 … 999 999 -10 999 999 10 999 999 OPERATIIVISET MITTARIT Poraus (metriä) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Nikkelitonnit kasalle (ton Ni) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Polttoainekulutus (litraa / tkm) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Renkaiden kulutus (rengasta / tkm) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Ajotapakoulutus 6kk sisään (%) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Gatekeeper-osuus (%) Toteuma 99 76 56 77 88 66 120 Tavoite 88 88 88 88 85 85 85 83 83 83 83 83 Erotus -11 12 32 11 -3 19 -35 Toteuma tukokuu 2013 Toteuma kesäkuu 2013 Budjetti kesäkuu 2013 Kommentit per kululaji 0 20 40 60 80 100 120 140 1 2 3 4 5 6 7 8 9 10 11 12 EUR/malmitonni Kaivoksenyksikkökustannukset(ilmanleasing) Kuukausikustannukset 0 200 400 600 800 1000 1200 1 2 3 4 5 6 7 8 9 10 11 12 Malmitonnia Kaivoksenkumulatiivinentuotanto Kumulatiivinen tuotanto Kumulatiivinen tavoite • EUR 100m cash impact expected in the next 12 mo. • Positive cash flow • Permanent change
  • 12. ORGANISATIONAL CHANGES • Darin Cooper appointed COO from Sep. 2013 - BEng, Metallurgy, MBA - Successfully implemented several production and cost efficiency programmes in the mining and metals industries - Former employers include Nyrstar, Teck Metals, Hudson Bay Mining, Britannia Zinc • Co-operation consultations concluded in August - Reduction of headcount by 68 through terminations of employment and retirements - The employment of 96 employees with temporary contracts to terminate at the end of the agreed contract period without renewal 12 Darin Cooper, COO
  • 13. SUCCESSFUL RE-COMMENCEMENT OF ORE PRODUCTION • Mining and materials handling operations resumed in mid-May, seven weeks ahead of plan 13 0 10 000 20 000 30 000 40 000 50 000 60 000 04/2011 08/2011 12/2011 04/2012 08/2012 12/2012 04/2013 Average daily ore production (t) – rolling 30 days
  • 14. MINING AND MATERIALS HANDLING PRODUCING AT RECORD SPEED AND AT IMPROVED UNIT COSTS 0 1 2 3 4 5 6 7 Jan'12 Feb'12 Mar'12 Apr'12 May'12 Jun'12 Jul'12 Aug'12 May'13 Jun'13 Jul'13 14 Materials handling units costs (EUR / t ore) Jul-2013 level Ni tonnes to primary heap since re-start • Approx. 8,000t of nickel stacked between re-start of ore production and end of July • Record ore production level of 1.6Mt in July • Improved grade control • Improved unit costs across ore processes; especially optimised reclaiming process 0 1 000 2 000 3 000 4 000 5 000 May 2013 Jun 2013 Jul 2013 ->13rd May +25% +84% 2012 average per month
  • 15. RECLAIMING BOTTLE-NECK REMOVED 0 50 000 100 000 150 000 200 000 250 000 300 000 01/2012 02/2012 04/2012 05/2012 07/2012 08/2012 10/2012 11/2012 01/2013 02/2013 04/2013 05/2013 06/2013 Weekly Q1'12 avg Q2'12 avg Q3'12 avg Since re-start avg Jul-13 avg 15 Weekly primary heap reclaiming (t) • Reclaiming process operating at planned capacity levels aided by process modifications and the addition of a jaw crusher unit
  • 16. BIOHEAPLEACHING – LOW NICKEL GRADE IN SOLUTION, BUT SHOWING SIGNS OF TURNAROUND 16 0 5 10 15 20 25 30 35 40 45 50 04/13 05/13 06/13 07/13 08/13 Heap 1 Heap 2 Heap 3 Heap 4 Heap temperatures (°C) - 0.2 0.4 0.6 0.8 1.0 1.2 1.4 1.6 1.8 2.0 Q1 2012 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013 Average nickel grade in plant PLS feed (g/l)
  • 17. ACCELERATED DE-WATERING OF OLD HEAPS • De-watering of older heaps slower than anticipated through Q2 2013 e.g. due to available pond volumes • De-watering now accelerating as a result of focused efforts to improve leaching performance; pond volumes now sufficient for solution removed from heaps 17
  • 18. EARLY LEACHING RESULTS DEMONSTRATE VERY ACTIVE PROCESS START-UP OF NEW HEAP • Early leaching of fresh ore has been very promising; temperatures of circulating solution already exceeding 50°C - Exceeds corresponding performance of any previous heap historically • First new heap (primary heap no. 4) completed in the beginning of September • Fresh ore starting to contribute metals as precipitation phase is ending • Special attention is paid to securing efficient start-up of the new heaps 18 1 800 2 000 2 200 2 400 2 600 2 800 800 850 900 950 1 000 1 050 1 100 2.8. 3.8. 4.8. 5.8. 6.8. 7.8. 8.8. 9.8. 10.8. 11.8. 12.8. 13.8. Zn(mg/l) Ni(mg/l) Ni (mg/l) Zn (mg/l) Metals grades in new heap – starting to contribute metals
  • 19. METALS RECOVERY – RECORD FLOW RATE AND CONTINUED STABILITY • Q2 2013 production impacted by - Scheduled maintenance stoppage of approx. 2.5 weeks in late May and early June - Capacity restrictions due to planned maintenance of hydrogen sulphide plants already from mid-April • Flow rate reached a record level of 1,650 m3/h in June • Metals plant operation stable throughout H1 2013 - Plant operation not anticipated to restrict production - Leach solution metal grade improvement to drive production volume increase 19 3 194 4 030 2 317 2 732 1 776 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013 Nickel production (t) 6 686 7 184 4 106 3 128 4 465 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013 Zinc production (t)
  • 20. FLOW RATES AT THE METALS PLANT IMPROVING 20 - 300 600 900 1 200 1 500 1 800 01/11 03/11 05/11 07/11 09/11 11/11 01/12 03/12 05/12 07/12 09/12 11/12 01/13 03/13 05/13 07/13 Monthly average 2011 average 2012 average 2013 average Monthly average flow rate to the plant (m3/h) Average in June 2013 subsequent to plant maintenance 06/13
  • 21. 1. Talvivaara in brief 2. Operational review – turning a corner 3. Safety, sustainability and permitting 4. Financial review 5. Outlook 21
  • 22. SAFETY, SUSTAINABILITY AND PERMITTING Safety • Increased focus on further safety training across all departments • LTIs at 19.5 / million working hours at the end of Q2 2013 Sustainability • Focus continues to be on water management – Treatment and discharge of water has continued throughout H1 2013 • Gypsum pond leakage in April fully contained within the safety dams • Historical issues with odour and dust resolved Permitting • New water discharge permit received in May – Volume quota removed – Discharge flow rate restricted by Kalliojoki river flow rate; Talvivaara has submitted an appeal with respect to this permit condition • Decision on renewal of overall environmental permit and on environmental permit for uranium extraction expected before the end of 2013 22
  • 23. APPROX. 3 MILLION M3 OF EXCESS WATERS DISCHARGED IN THE FIRST HALF OF 2013 23 0.0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 01/2013 02/2013 03/2013 04/2013 05/2013 06/2013 07/2013 Cumulative 2013 water discharge (Mm3)• Treatment and discharge of excess waters from the mine area continued throughout H1 2013 • Discharge will continue within permitted limits, but risks already materially reduced 300 000 400 000 500 000 600 000 01/13 02/13 03/13 04/13 05/13 06/13 07/13 Primary heap pond volume Max. pond volume Primary heap solution volume (m3) 12-Feb discharge permit from Kainuu ELY 31-May environmental permit update from AVI
  • 24. SIGNIFICANT REDUCTION IN ENVIRONMENTAL OBSERVATIONS FROM NEIGHBOURING RESIDENTS 24 0 5 10 15 20 25 30 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun 2011 2012 2013 Numberofobservations Odour Noise Vibration Dust Water Other
  • 25. 1. Talvivaara in brief 2. Operational review – turning a corner 3. Safety, sustainability and permitting 4. Financial review 5. Outlook 25
  • 26. Q2 2013 FINANCIAL RESULTS • Results reflect production levels and a depressed nickel price environment - LME nickel price below USD 14,000/t at the end of Q2 2013 • Q2 2013 key financials - Sales: EUR 13.0m - Operating loss: EUR (23.9)m - Capex: EUR 15.3m • Costs impacted by: - Water management - Metals plant maintenance - Re-commencement of ore production - Chemicals efficiency impact of low metals grade in solution 26 33.4 44.8 25.7 27.6 13.0 Q2… Q3… Q4… Q1… Q2… Net sales (EURm) -10.9 -4.3 -57.0 -20.0 -23.9 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013 Operating profit (EURm)
  • 27. LIQUIDITY POSITION AND BALANCE SHEET 27 - 50 100 150 200 250 300 2013 2014 2015 2016 2017 2018 Other Finance lease liabilities Corporate revolver Senior unsecured bond Convertible bonds* WC (Finnvera) loans * Convertible bond maturity reflects accreted principal Debt maturity profile (EURm) Net interest-bearing debt (EURm) 476 515 564 530 410 Q2 2012 Q3 2012 Q4 2012 Q1 2013 Q2 2013 • Financing transactions in H1 2013 significantly improved balance sheet and liquidity position - Gearing from 183% at year-end 2012 to 81% at the end of Q2 2013 - Net debt from EUR 564m at year-end to EUR 410m at the end of Q2 • Remaining EUR 77m convertible bond maturity repaid in May • Next material maturity in December 2015 (excluding RCF) • Cash at EUR 101.1m at the end of Q2 • Several significant initiatives to maintain liquidity as part of efficiency and productivity programme
  • 28. 1. Talvivaara in brief 2. Operational review – turning a corner 3. Safety, sustainability and permitting 4. Financial review 5. Outlook 28
  • 29. NICKEL MARKET – NEAR-TERM OUTLOOK CHALLENGING • Nickel price under significant pressure through H1 2013 - Declined from USD 18,000-19,000/t in early 2013 to below USD 14,000/t in the summer - Macro outlook and weak stainless steel market - Build-up of nickel inventories to a record level of more than 200,000t • Short-term outlook: - Near-term outlook remains challenging - Current price level considered unsustainable; restrictions of supply and positive macro developments may trigger upside movement 29 LME nickel price (USD/t) 10 000 15 000 20 000 25 000 30 000 01/11 05/11 09/11 01/12 05/12 09/12 01/13 05/13 LME nickel price (USD/t) and nickel stocks (kt) - 50 100 150 200 250 300 - 5 000 10 000 15 000 20 000 25 000 30 000 2008 2009 2010 2011 2012 2013 LME nickel stocks (t) LME nickel price (USD/t)
  • 30. LONG-TERM TALVIVAARA STORY INTACT • Extensive sulphide nickel deposit with a long mine life • Favourable characteristics of the Talvivaara deposits • Cost-effective and scalable bioheapleaching technology • Demonstrated feasibility of using bioheapleaching to extract nickel • Long-term off-take agreements for nickel, cobalt, zinc and uranium • Attractive long-term supply-demand dynamics of the nickel industry • Experienced management team 30 • Long-term story intact – world-class ore body and cost efficiency following ramp-up • Short-term challenges being addressed and showing signs of success